NGT Final Order 30mar2012
NGT Final Order 30mar2012
Quorum:
B E T W E E N:
1. PRAFULLA SAMANTRAY
Lohiya Academy, A/3, Unit – 9
Bhubaneshwar, Orissa – 751022
2. BIRANCHI SAMANTRAY
Village Dhinkia, Kujang
Jagatsingpur, Orissa – 754141 ….Appellants
AND
1. UNION OF INDIA
Through the Secretary
Ministry of Environment & Forests
Paryavaran Bhawan
CGO Complex, New Delhi – 110 003
Page 1 of 32
2. ORISSA STATE POLLUTION CONTROL BOARD
Through the Member Secretary
Paribesh Bhawan, A/118, Nilakantha Nagar
Unit-VIII, Bhubaneshwar – 751012, Orissa
(Advocates appeared: Mr. Raj Panjwani, Senior Counsel with Mr. Ritwick
Dutta and Ms Srilekha Sridhar for Appellant, Ms Neelam Rathore for
Respondent No. 1, Mr. Ashok Kumar Panda with Snehasish Mukherjee for
Respondent No. 2, Mr. Sanjit Mohanty, Senior Counsel with Mr. Satyajit
Mohanty for Respondent No. 3).
JUDGMENT
1. This appeal is filed against the final order dated 31.1.2011 of the Ministry
of Environment & Forests, imposing additional conditions to the
Environmental Clearances (for short ECs) in respect of (i) steel cum
captive power plant project and (ii) captive minor port project of M/s
POSCO India (for short POSCO), the Respondent No. 1, during the year
2007.
1.1 Originally, the EC to these two projects were granted vide order No.
10 – 9/2006-IA-III dated 15.5.2007 and No. J-11011/285/2007-IA II (I)
dated 19.7.2007. Subsequently, after review the final order was issued on
31.01.2011.
Page 2 of 32
1.2 The Forest Clearance granted for the project by the MOEF appears to
be under challenge in a WP(C) No. 14885 of 2011 before the Hon’ble High
Court of Orissa, Cuttack and the same is pending. However, we are not
aware of the scope of the said writ petition challenging the forest
clearance. We have not dealt with issues regarding the allotment of vast
forest land for the purpose of the project, etc. except examining the
allotment of land disproportionate to that of project proposed to be
taken up in the first phase.
Page 3 of 32
1.5 According to the Appellants, the main components of the project, for
which a Memorandum of Understanding (for short MOU) for setting up an
integrated steel plant with captive port with the total capacity of 12
million tons per annum at Paradip in Jagatsinhpur district of Orissa
wherein an estimated investment of Rs. 51,000/-crore (approximately 12
million US Dollars), are as under:
(i) The integrated steel plant with captive power plant project at
Kujang, near Paradip in Jagatsinhpur district of Orissa
(ii) Captive Port at Jatadhar in Jagatsinhpur district of Orissa
(iii) Mining project
(iv) Integrated township and water supply infrastructure.
1.6 As per the MOU, the Government of Orissa agreed to facilitate and
use its best efforts to enable the Project Proponent (POSCO) to obtain a
‘No Objection’ through the State Pollution Control Board in the minimum
time possible. It is also mentioned that the Project Proponent will
conduct a rapid Environment Impact Assessment (for short EIA) and
prepare a detailed EIA report and an environment management plan for
the project. Further, it is stated that the Government of Orissa agreed to
use its best efforts to procure the grant of all environmental approvals
and forest clearance from the Central Government within the minimum
possible time.
1.7 It is the case of the Appellant that the manner in which the entire
appraisal starting from preparation of EIA report to conduct of PH to
examination by the respective Expert Appraisal Committee (for short
EAC) of Ministry of Environment and Forests (for short MOEF) for
Industries and Infrastructure respectively was done, including the
Page 4 of 32
reappraisal in the year 2010 based on the findings of Review Committee
constituted for the purpose and subsequently the issuance of final order
regarding ECs shows that the provisions of EIA Notification 2006 were not
followed in letter and spirit. The MOEF and particularly the respective
EACs failed to consider the environmental and social implications of such
a large project and relied mainly on the assurances given by the project
proponent. Clarifications were though sought by EACs, but there was
limited follow up action and consideration to the points raised during PH.
The manner in which the rapid EIA Report and subsequent detailed EIA
report were prepared for a project of such dimensions and grant of
approvals in the background of the objections raised right from the very
initial stages, casts severe doubts in the manner in which the EACs and
the MOEF acted upon.
Page 5 of 32
(e) Detailed Scrutiny of the EIA report and the proceedings of
the Public Consultation by the MOEF and specifically the EAC
(Appraisal); and
(f) Grant of approval or rejection of application by the MOEF.
Page 6 of 32
consideration and a summary of the PH was made available to the people
at the end of the process of PH. The rapid EIA report was prepared as per
the guidelines and the EACs examined the same meticulously and
recommended for grant of ECs. The Committee constituted for the
purpose of review, does not vitiate since Ms. Meena Gupta was a party to
it. The majority report of the Committee has exceeded its brief; therefore,
the report of Ms. Meena Gupta was rightly relied upon by the MOEF. The
objections filed by the Appellant as well as others at various stages did
not reflect any issue worth the name for consideration. The ECs granted
by the MOEF or the final order, does not suffer from any legal infirmities
requiring interference of this Tribunal.
3. Counsel on either side argued the matter at length. We have given our
earnest consideration to the respective submissions made by Learned
Senior Counsel on either sides and the following issues arise for
consideration in this appeal:
i) Whether the Appeal has been filed within the period of limitation
in so far as challenging the ECs granted in May/June, 2007 and
whether appeal can be entertained to that extent?
iii) Whether the MOEF was right in accepting the review report
submitted by Ms. Meena Gupta who participated in the issue of
grant of original ECs since she was the Secretary to the
Government of India, MOEF and whether the Government was
Page 7 of 32
right in rejecting the majority report of the review committee. And
whether the apprehensions/issues raised by the Review Committee
are properly addressed while issuance of the final order under
challenge?
4.1 It is the case of the respondents that the appeal is not filed within the
period of limitations as required under the NGT Act. The original ECs for the
projects were granted on 15/05/2007 in respect of steel-cum-captive power
plant and on 19/07/2007 in respect of captive minor port. Based on the
complaints and various representations against the project, the Respondent
No. 1 constituted a four member review committee under the Chairmanship
of Ms. Meena Gupta on 8/7/2010 and subsequently modified its TOR on
27/8/2010.The members of the Committee could not reach a consensus. In
the result, two separate reports, one by Ms. Meena Gupta and the other by
three members Committee were submitted to the MOEF on 18.10.2010. The
final order was issued only on 31/01/2011. However, the appellant had not
chosen to challenge the original ECs granted on 15/05/2007 in respect of
steel-cum-captive power plant and on 19/07/2007 in respect of captive
minor port. Now, after issuance of the final order of 31/01/2011, it is not
permissible under the law to challenge the original ECs issued in 2007.
4.2 Whereas it is the contention of the Learned Senior Counsel Shri Raj
Panjwani, for the appellant, that the original ECs granted on 15/05/2007 in
respect of steel-cum-captive power plant and on 19/07/2007 in respect of
Page 8 of 32
captive minor port were never given effect to, since other clearances were
pending and upon receipt of number of objections/complaints after the
original ECs by the authorities, a four member committee was constituted
and ultimately, while accepting the minority report of Ms. Meena Gupta, the
final order was granted on 31/1/2011. Therefore, it cannot be said that the
appeal is time barred or is not maintainable. Once, the original ECs granted
on 15/05/2007 in respect of steel-cum-captive power plant and on
19/07/2007 in respect of captive minor port were under review and finally
the order was issued on 31/1/2011, it must be deemed that the original ECs
culminated in the issuance of the final order on 31/1/2011. Review order of
any order passed earlier would merge in the final one. The existence of the
original order looses its identity and merges in the review order and
therefore as per settled principle of law, the limitation period for filing an
appeal would start from the date of review and not from the date of original
order. Therefore, appeal is also maintainable against original ECs granted in
May/July, 2007.
Page 9 of 32
precautionary measures. The review, etc. was not of immediate one to the
grant of original ECs. The Review Committee itself was constituted after
three years of the original ECs, which resulted in adding further conditions.
Therefore, it may not be proper on the part of the appellant to say that he is
entitled even to challenge the original ECs and the conditions attached
thereto. There was no merger of the original ECs in the so called final order.
Though, the appellant appears to have filed certain objections even prior to
the PH and at other subsequent stages of the proceedings, no reason is
forthcoming as to why the original ECs could not be challenged for more than
three years and what made them to wait till the final order was issued on
31.1.2011.The final order is nothing but inclusion of some more conditions
by way of precautionary measures. Therefore, we are of the opinion that the
original ECs granted in July 2007 does not merge in the final order issued on
31.01.2011.They are independent of each other. It is also the submission of
the Respondent No. 3 that the very application under section 14 (1) of NGT
Act is not maintainable since section 14 does not contemplate filing an
appeal against orders granting EC. The NGT Act 2010 came into force with
affect from 18.10.2010 and an EC granted on 15.05.2007 for the port and
19.07.2007 for the steel plant, were granted prior to the commencement of
NGT Act 2010. The legality or otherwise of such an order dated 15.05.2007
cannot be challenged by way of an appeal under section 16(h) of the NGT Act
2010. Further no substantial question relating to environment as defined
under Section 2(m) had arisen, for invoking Section 14. Thus, on either
counts, the appeal is not maintainable. The order dated 31.01.2011 cannot
be treated as grant/ reissue of the order dated 15.05.2007 (port) and
19.07.2007 (steel plant and CPP). Granting of original ECs to the project
cannot be challenged in the guise of challenging the order dated 31.01.2011
which is only an order imposing additional conditions. It is true that Section
14 of NGT Act, 2010 has no application to the facts of the present case, since
Page 10 of 32
no substantial environmental issue had arisen after the issuance of the
original ECs nor it is the case of the appellant. Further, under Section 16 of
the NGT Act, 2010, the ECs issued in May/July, 2007, cannot be challenged as
the Section 16 contemplates challenging of the order passed on or after the
commencement of the Act i.e., 18th October, 2010. Broadly, we are in
agreement with the submission made by the learned Senior Counsel Shri
Sanjit Mohanty for respondent No. 3.
4.5 Therefore, we are of the considered opinion that what can be challenged
by the appellant is only the final order issued on 31.01.2011 if there is any
threat to the environment and ecology in spite of the additional conditions
imposed, and not otherwise.
Page 11 of 32
This appeal is maintainable only in respect of the final order dated
31.01.2011 and the conditions attached thereto.
5.1 Here, at the outset, it may be noticed that we have already concluded in
the Issue No. (i) to say that this appeal to the extent of challenging ECs
granted in May/July, 2007 is not maintainable. However, since both the
parties have advanced arguments elaborately, the issue is being answered
accordingly.
5.2 According to the Appellant, the PH for both the components of the
project took place when respondent No. 1 was yet to examine the rapid EIA
Report for the project for accuracy and completeness as on 16.4.2007 while
the PH took place on 15.4.2007. The EAC waived of the need to conduct site
visit before the PH, despite the scope and magnitude of the project without
giving any reasons. The PH dated 15.4.2007 conducted by the OSPCB was
held far away from the site which resulted in low public participation. This
issue was raised in the PH meeting and recorded in the Minutes of the
meeting but no credence was given by the EACs. Public raised issues with
respect to likely adverse impact due to the proposed project, impact on their
livelihood and the fact that rapid EIA is deficient and not available to the
people in advance. Though there were two projects i.e. the steel plant of 4
MTPA and captive minor port with two separate EC applications and EACs,
only one PH was held by combining the projects. The 17th meeting of EAC
(Industry) held during 13th and 14th of December 2010 wrongly concluded
Page 12 of 32
that multiple hearing at different locations is not in consonance with the
statute.
5.3 None of these issues raised in the public consultation were given due
consideration or deliberation despite the requirement under EIA Notification
2006. In the EACs meetings held on 5.6.2007, 19 to 21.5.2007, 19.4.2007,
21.4.2007, no detailed scrutiny was undertaken. The conclusions drawn by
the District Magistrate in the PH, which was contrary to the views expressed
by the public, were also not taken into consideration by the EACs. The
majority report of the review committee had, in fact, recommended for a
fresh PH. This was also ignored.
5.4 Whereas, it is the case of the respondent No. 1 that the allegation that
the PH was conducted without a letter from the MOEF to OSPCB, is incorrect.
The EIA Notification, 1994 was superseded by the EIA Notification 2006.
Pursuant to EIA Notification 2006, the MOEF issued interim operational
guidelines vide circular dated 13.10.2006 in respect of applications made
under EIA Notification 1994 till September 13, 2007. On new applications for
EIA appraisal received on or after 14.9.2006, and upto 30.6.2007, it was
clarified vide para 2.2.1 (i) (a) of the circular which reads as under:
Page 14 of 32
meetings dated 16.11.2006 and 19th - 20th April, 2007 reveals that after
deliberations, the proposal was recommended for EC subject to stipulation of
environmental safeguards.
5.7 A perusal of the submissions would indicate that there was no flaw in the
PH. The PH started under the Notification of 1994 and the entire procedure
as required therein was followed. The contention of the appellant that the
MOEF was not consulted before taking up the PH process by the OSPCB was
not contemplated in the EIA Notification 1994. In the transit of the period
between EIA Notification of 1994 and EIA Notification of 2006, all the PH
conducted was governed by the Circular issued by the Government of India
as noticed above. Even though, the majority Members of the Review
Committee had recommended for fresh public hearing but they have not
taken the fact as to saving of all the PH conducted under EIA Notifications,
1994 between the relevant dates PH for the project was also held on
15.4.2007. After submission of PH report, the proposal was placed before the
EAC (Industry) in its 67th Meeting held on 5th June 2007. Pursuant to the EIA
Notification, 2006, the MOEF issued interim operational guidelines vide
circular dated 13.10.2006 in respect of applications made under EIA
Notification 1994 till September 13, 2007. It is stated that on new
applications for EIA appraisal received on or after 14.9.2006, and upto
30.6.2007, it was clarified vide para 2.2.1 (i) (a) of the circular as noted
above.
Page 15 of 32
of the PH proceedings and made it known to the public. Thus, it is clear that
procedural wise, there is no substantial error committed by the authority in
conducting the PH. Therefore, the allegation of the Appellant that the PH was
not conducted in accordance with the law cannot be countenanced, though;
it does not fall within the ambit of challenge of this appeal, as discussed at
Issue No. (i) above.
Page 16 of 32
Meena Gupta which was accepted by the MOEF is hit by official / personal /
departmental bias. The fact that Ms. Meena Gupta was party to the earlier
proceedings and she herself expressed reservation to participate in the
review proceedings, is clear from the letter dated 18.10.2010 addressed to
the MOEF at the time of submission of her report.
6.2 The TOR entrusted to the committee initially on 28th July, 2010 was as
under:
6.3 Thereafter, by the order dated 28th July, 2010, the same was amended for
investigation into the proposal submitted by POSCO India Private Limited for
establishment of integrated Steel Plant and Captive Port in Jagatsinghpur
District, in partial modification of Clause 9, and the TOR for the committee
were set as follows:
Page 17 of 32
(iii) Review compliances with Environmental (EIA), Coastal
Regulation Zone (CRZ) & other Clearances / approvals granted
by the Ministry of Environment and Forests and other Central,
State and local authorities;
(iv) Review compliance with statutory provisions, approvals
clearances and permissions under various statutes, rules,
notifications, etc.
(v) Review compliance with pari-passu conditionalities
imposed in item in item (iii) and (iv) above;
(vi) Any other matter with pari-passu furtherance of the above
objectives.”
6.4 The date for submission of report by the committee was revised from
28th August 2010 to 30th September, 2010.
6.6 In the executive summary of the report, Ms. Meena Gupta stated that
Page 19 of 32
agreement in the Committee that the procedure to recognize
forest rights should be re-done in the project villages.
The other members of the Committee did not agree with this.
Their view was that the EC granted for the steel plant and EC and
CRZ clearance granted to the captive port should be cancelled
forthwith, because of flaws in the studies, and shortcomings in
the clearances granted.”
6.7 Whereas the majority report says that the PH was not conducted
properly and there were many other short comings in compliance of the
provisions of EIA report, therefore the EC granted should be annulled and
fresh proceedings to be initiated. The reasons furnished in respect of PH
are as under:
Page 20 of 32
in the Public Hearing. The committee was informed that there was
presence of a strong police force at the venue of the public hearing
a day prior to the hearing itself. This served as a deterrent to free
participation by local villagers, who were opposing the project.
Other project affected people like traditional fishing community
and farmers were not covered by the public hearing. The social
impact of the project was also not discussed. Project proponent has
failed to answer all the objections raised during the public hearing.
The EAC has failed to apply its mind to the objections raised by
various authorities and the public and have also failed to consider
the available material on record. The EAC has also failed to record
any reasons in respect of accepting or rejecting the objections
raised but instead gave clearance. Such mechanical clearance
makes a mockery of rule of law and procedural safeguards.”
6.9 Though the report of Ms. Meena Gupta appears to be balanced one,
even this was not taken into consideration in totality by the EACs. Further,
Page 21 of 32
it is also seen that she was the Secretary, MOEF at the time of issuance of
clearances earlier which are sought to be reviewed through the TOR. Here,
there is a clear bias to defend her previous acts as Secretary, MOEF. Apart
from this, there is a major shift in the approach made by her in defending
the ECs. It is her argument that since the ECs have already been granted,
there is no necessity of going into all the details except suggesting
additional precautionary measures. Whether the act of Ms. Meena Gupta is
fair or not, they are definitely hit by personal / official / departmental bias,
in other words, she supported the decision made by her earlier. This is in
gross violation of principles of natural justice. Therefore, the entire process
of review is vitiated under the law.
However, we have kept in mind the need for industrial development,
employment opportunities created by such projects that involve huge
foreign investment, but at the same time we are conscious that any
development should be within the parameters of environmental and
ecological concerns and satisfying the principles of sustainable
development and precautionary measures.
A close scrutiny of the entire scheme of the process of issuing final order in
the light of the facts placed before us and material placed on record together
with the observations made by the review committee though in two separate
volumes; reveals that a project of this magnitude particularly in partnership
with a foreign country has been dealt with casually, without there being any
comprehensive scientific data regarding the possible environmental impacts.
No meticulous scientific study was made on each and every aspect of the
matter leaving lingering and threatening environmental and ecological
doubts un-answered. We have dealt with some of these issues on the basis
Page 22 of 32
of records placed before us by the MOEF and argued by the Appellant –
however for the purpose of cancellation of original ECs granted in 2007. We
are extremely conscious that we are dealing with only the review and post
review proceedings in granting final order of 31.01.2011.
7.1 Need for Comprehensive and integrated EIA report of various project
components
The majority members of the Review Committee have pointed out that for a
project of this magnitude, a Comprehensive and integrated EIA report was
required based on atleast one full year base line data at the time of conduct
of PH and subsequent appraisal by the EACs and the same argument has
been put forward by the appellant. Whereas, the Respondents have
submitted that at relevant point of time and as per the procedure,
Comprehensive and integrated EIA report was not mandatory, it was only
that as a part of own responsibility that Respondent No. 3 prepared a
Comprehensive and integrated EIA report engaging agencies of repute at a
later date. The issue of integrated EIA report for various components of the
project raised by the Review Committee and the appellants needs a
consideration. Of course, as per the provisions, the proponent was required
to approach different EACs for steel plant and captive minor port and
accordingly, separate rapid EIAs were furnished. The available records also
indicate that respective EACs were well aware of the other component. We
have gone through the various provisions in the EIA requirement procedure
and the material placed on record, undoubtedly, at the time of PH and
subsequent appraisal by the EACs, Comprehensive and integrated EIA report
was not warranted, however, it would have been prudent to have this report
at the very beginning stage itself to avoid all the confusion and delays
especially considering the magnitude of the project and its likely impact on
various environmental attributes in the ecologically sensitive area. In this
Page 23 of 32
direction, it would be prudent to note that a similar observation has also
been made by Ms. Meena Gupta in her review report. Similar apprehensions
have also been raised by the majority members of the Review Committee
that considering the nature and extent of project, it was necessary to have a
comprehensive and integrated EIA rather than rapid fragmented EIA. In this
context, we find it necessary that MOEF establishes clear
guidelines/directives that project developers need to apply for a single EC
alone if it involves components that are essential part to the main industry
such as the present case where main industry is the Steel plant, but it
involves major components of port, captive power plant, residential
complex, water supply, etc.
7.2 Grant EC for 4 MTPA capacity steel plant when all the other
components i.e. captive port, captive power plant and other
infrastructural needs including land requirement are for the 12 MTPA
steel plant with proposed expansion every few years is justifiable
As per the MOU, the production capacity of the steel plant is envisaged
to be 12 MTPA whereas the EC for the steel plant in the instant case has
been sought for 4MTPA and it is stated that subsequent capacity
augmentation shall be taken up in phases. The issue is critical when it is
seen that entire infrastructural needs i.e. township, port, captive power
plant, etc. have been planned for 12 MTPA only including the land
requirement for the components. The majority members of the Review
Committee had also considered the issue and observed that the project
would be financially viable at 12 MTPA only. Even according to the
submissions of the Respondent No.3, the project is viable at 12 MTPA.
The respondents have submitted that they have never given an
impression that the project is going to be 4 MTPA and not 12 MTPA, this
fact has been known from the very beginning and they shall approach the
Page 24 of 32
EC granting authority as and when such capacity upgradation is proposed
to be taken up. According to Respondent No. 3, since they are constantly
trying to develop new clean technologies and their product mix would be
dependent on market potential and therefore, the product mix as well as
technological configuration cannot be decided at this stage. Henceforth,
they have carried out EIA study for 4 MTPA only and as and when
subsequent upgradation is planned, they shall undertake fresh EIA study
and obtain fresh EC. As far as other infrastructural needs of port, captive
power plant, residential area together with land requirement is
concerned; the entire project has been planned for ultimate capacity of
12 MTPA considering the logistic requirements. Apparently, the argument
has its own merits, however, a large uncertainty remains over the entire
proposal – as to what would be the scenario if EC is not granted to
propose future expansion for certain reasons – how the additional
infrastructure created is proposed to be utilized. It is also not clear
whether these aspects have been considered in the MOU or while
granting the ECs. In this context, the Respondent No. 3 was asked to
furnish phase wise land requirement and from the proposal it is noted
that out of total land requirement of 4004 acres (3566 acres government
land and 438 acres private land), for the initial phase, the land
requirement for steel plant is 3097 acres of forest land at once as forest
diversion in piece meal is not desirable though the requirement is for
2500 acres.
In this context, Ms. Meena Gupta in her conclusions of the review report
points out that:
Given the facts, we are also of the considered opinion that MOEF
should immediately take a policy decision accordingly apart from
giving a due thought to the question of optimizing the land
requirement in the instant case where the land requirement for
residential complex, steel plant and other infrastructural needs would
be less, when the initial phase is contemplated to be 4 MTPA only.
The project envisages other components in addition to steel plant and port
such as railways, road transport, township, mining, water transport pipeline,
etc. apart from its being located in ecologically sensitive area where already
development is undergoing. Accordingly, in the absence of comprehensive
and integrated EIA, the combined impact of proposed development including
its infrastructural needs in ecologically sensitive area would cause additional
impacts. The issue has also been apprehended by the majority members of
the review committee. From the records, it is seen that the only clarification
offered is limited to non-applicability of the Comprehensive Environmental
Pollution Index at the relevant point of time. In this context, we are not in full
agreement with the justification offered because environmental issues
cannot and should not be ignored taking such stance and it would have been
fair to examine the issue more elaborately duly applying principle of
sustainable development and precautionary principles. In this regard, the
review committee also noted number of factors, such as siting of the project,
present pollution levels, proximity to CRZ and other ecologically sensitive
Page 26 of 32
habitat, sourcing of water from a distance of 87 km or so that too under
competing uses, etc. From the material on record, it is also evident that at
the time of appraisal by EAC in the light of the Committee’s Report, extensive
discussion focused on the matter and necessary stipulations have been made
in the ECs through additional conditions. It is, however, felt that, since
considerable time has elapsed ever since the grant of original ECs and even
after the stipulations of additional conditions to the ECs, wherein, the project
proponent was asked to furnish additional reports/ documents/ plans, etc.
by the MOEF; however, the response from the proponent during proceedings
of the matter regarding progress on these matters was surprising that since
they are not able to go to project area, no significant progress could be
made, is little surprising and raises doubt about implementation/ compliance
of various stipulations to the conditions imposed in ECs. We are therefore of
the opinion that MOEF should consider defining timelines for compliance of
the conditions in the ECs and considering the nature and extent of the
project, MOEF should establish a special committee to monitor the progress
and compliance on regular basis.
Apart from the foregone issues, in so far as this issue is concerned we may
have to consider only the EIA reports and their evaluation by EACs after
submission of the report by Ms. Meena Gupta on one hand and the majority
members on the other hand. This appears to have been done to some extent
as evidenced from the records placed before us, though not put forward
explicitly by the Respondents especially the Project Proponent and MOEF. It
Page 27 of 32
would not be out of place to mention that this Tribunal being specialized one
comprising of Expert Member as well and having option for inviting
additional technical opinion, the Tribunal could have appreciated more the
technical issues being raised in a very effective and fruitful manner as
required under the law. The matter being pursued otherwise, from the
material placed on record, we can only infer that a holistic appreciation of
the objections/ views raised and its due consideration in the EACs was only
reasonable. On receipt of the fractured report from the Review Committee, it
simply asked the Project Proponent to furnish written replies and make
presentation before the EACs. To illustrate the point, it may be seen that in
the majority members report of the Review Committee, several
environmental issues that were even raised at the time of PH, have been
enumerated on page 185 to 193. Similarly, Ms. Meena Gupta made certain
observations on page 26-29 of her report. In this context, the proponent
furnished Comprehensive EIA report that partially incorporated certain
additional TOR awarded and objections raised earlier by engaging expert
institutions such as NIO, DHI, etc. However, the completeness and veracity of
the responses was ascertained in what manner in view of non-availability of
certain reports, as earlier sought by EACs and again pointed out by the
members of the Review Committee, leaves certain issues unanswered. In
totality, it appears that MOEF has mostly accepted the minority report of Ms.
Gupta that too in pieces and proceeded with the matter for issuance of final
order imposing additional conditions to the original ECs in view of some of
the objections/issues raised. There was lot of scope for making scientific
study in the matter which is briefly indicated here under:
Page 28 of 32
source to Cuttack town is facing a great deal of opposition and finally it is
mentioned that the issue needs to be looked into by the EAC with a view to
suggest altered or additional conditions relating to water supply. Despite it
being so, the final order only incorporates a condition stating that “Source
suitability study of water requirement shall be carried out by an institute of
repute”. The study was to be completed within six months. It is in this
background, need for Compliance Monitoring Team is essential.
We are all aware that in the country, the drinking water is becoming
scarce commodity and at every level precaution needs to be taken for
protecting the drinking water supply to human habitation and
preventing from utilizing such water for industrial use. It is always
better to insist upon the project proponent /industry to create its own
source of water supply particularly, when it can afford to do so. It
appears, the alternative water source for the present project, like
creating/ constructing a small barrage or augmenting any other
existing source at the cost of project proponent to avoid the utilizing
the water meant for Cuttack city, particularly in the nature and
magnitude of the proposed project conceived could be examined.
Evaluation of proposed zero discharge proposal: According to project
proponent, the project is a zero discharge proposal, however, a closer look
into the proposal, reveals that something like 47 cubic meter per hour of
wastewater is to be discharged into the sea. Of course, as compared to the
total quantum of water required, this figure is only 3 percent. It is not that,
these figures are not mentioned; but what is striking is the fact that these
figures have been well accepted from environment and ecological impacts
that may be associated to its discharge. More so over, although in the EIA
report it is mentioned that a Common Effluent Treatment Plant (CETP)
complying to Central Pollution Control Board specifications shall be designed
at the time of Detailed Engineering Report; however, at the time of appraisal
Page 29 of 32
by the EAC after submission of Review Committee Reports, the project
proponent submitted that since the plant is based on zero discharge
proposal, they do require to install a CETP; however, they would seek
relevant CRZ approval at a later stage on completion of Detailed Engineering
Report. Being a serious environmental concern, how such issue can be left to
be decided in future, puts a serious question mark from all angles especially
when almost all the clearances are in place and project is ready for
implementation. This should have been, in fact, incorporated at the time of
EIA report itself – otherwise it is in all probability likely to cause great
environmental threat.
Impact on surrounding wetlands and mangroves and their biodiversity, etc.
and Risk Assessment with respect to the proposed Port Project: Subsequent
to submission of Review Committee report and appraisal by the EACs,
additional conditions to the ECs have been imposed on these aspects based
on reply furnished by the project proponent. It is, however, noted that the
conditions mostly seek formulation of appropriate management plan/s
without specific timelines and modus operandi for evaluation,
implementation and monitoring of such proposals.
In this context, it may be appropriate to highlight that the Review
Committee also pointed out these aspects and suggested that considering
the large number of port projects coming up in the area, it would be
appropriate to conduct Strategic Environmental Assessment with regards
to location of projects taking into consideration the future requirement,
proneness of the area to cyclones/ flood and erosion, etc.
Page 30 of 32
8. For all the above discussion and deliberation on the issues and the study of
records made by us and keeping in view the need for industrial development,
employment opportunities, etc. but not compromising with the environmental and
ecological concerns, we propose to dispose of this Appeal with the following
directions:
8.1 The MOEF shall make a fresh review of the Project with specific reference to
the observations/ apprehensions raised by the Review Committee in both
the reports i.e. the one given by Ms. Meena Gupta and the other by the
Majority Members apart from consideration to the views of the EACs and
also with reference to the observations made in this Judgment by issuing
fresh TOR accordingly.
8.2 However, the final order dated 31.01.2011 made by the MOEF shall stand
suspended till such fresh review, appraisal by the EACs and final decision by
MOEF is completed, since some study might have already been initiated in
view of the final order dated 31.1.2011.
8.3 The MOEF shall constitute the said fresh review committee by engaging
subject matter specialists for better appreciation of environmental issues.
The project proponent shall be asked to furnish relevant details required for
the said review by the newly constituted committee to recommend specific
conditions to be attached/ revised in the ECs granted by MOEF.
8.4 The MOEF shall define timelines for compliance of the conditions in the ECs
and considering the nature and extent of the project, MOEF should establish
a special committee to monitor the progress and compliance on regular
basis.
8.5 The MOEF shall consider optimizing the total land requirement for 4 MTPA
Steel plant proportionately instead of allotting entire land required for 12
MTPA steel plant which is an uncertain contingency.
Page 31 of 32
8.6 The MOEF shall consider feasibility of insisting upon every major industry
that requires large quantity of water to have creation of its own water
resource facility rather than using/ diverting the water that is being meant
for drinking/ irrigation purposes.
8.7 It is desirable that the MOEF shall establish clear guidelines/directives for
project developers that they need to apply for a single EC alone if it involves
components that are essential part to the main industry such as the present
case where main industry is the Steel plant, but it involves major components
of port, captive power plant, residential complex, water supply, etc.
8.8 It is desirable that MOEF shall undertake a study on Strategic Environmental
Assessment for establishment of number of ports all along the coastline of
Orissa with due consideration to the issues related to biodiversity, risks
associated, etc.
8.9 It is also desirable that MOEF shall take a policy decision that in large
projects like POSCO where MOUs are signed for large capacities and up-
scaling is to be done within a few years, the EIA right from the beginning,
should be assessed for the full capacity and EC granted on this basis.
Page 32 of 32