PLANTA KM: 7+000 - 8+000: Cuadro de Elementos de Curva
PLANTA KM: 7+000 - 8+000: Cuadro de Elementos de Curva
TMC D=36"
Km. 7+910, L=6.57
9 294 900 N
9 294 800 N
P3
8 KM
PI-87
CUADRO DE ELEMENTOS DE CURVA
7+800
N° CURVA PI PC PT RADIO CUERDA LONG.CURVA TANGENTE EXTERNA < DEFLEXION S/A
PI-89
PI-86
PI-75 7+012.837 6+970.07 7+051.63 109.67 79.690 81.556 42.77 8.04 42°36'23" 0.50
7+
7+950
85
8+00
0
75
7+900
PI-76 7+145.977 7+128.56 7+163.33 240.00 34.742 34.772 17.42 0.63 8°18'04" 0.40 7+
8+05
0
PI-77 7+206.677 7+183.56 7+229.71 300.00 46.107 46.152 23.12 0.89 8°48'52" 0.40
PI-88
DME 05
0
PI-78 7+284.660 7+251.09 7+314.22 75.00 61.285 63.132 33.57 7.17 48°13'47" 0.70
0
70
PI-79 7+362.405 7+349.59 7+370.40 14.12 18.977 20.809 12.81 4.94 84°25'16" 2.40 -85
PI
9 295 000 N
7+
PI-80 7+381.997 7+370.40 7+390.14 15.00 18.346 19.740 11.59 3.96 75°24'07" 2.40
PI-83
P4
PI-81 7+471.735 7+449.26 7+487.11 27.92 35.019 37.851 22.48 7.92 77°39'40" 1.60
0
65
0
7+
7+60
PI-82 7+511.313 7+487.11 7+533.12 60.00 44.894 46.013 24.20 4.70 43°56'21" 0.70
550
PI-83 7+570.990 7+548.29 7+589.59 40.00 39.490 41.300 22.70 5.99 59°09'30" 1.20
7+
PI-84
PI-75
PI-84 7+628.584 7+603.74 7+649.85 50.00 44.496 46.113 24.84 5.83 52°50'31" 1.20
81
7+50
7+050
PI-
PI-85 7+710.456 7+692.84 7+727.82 120.00 34.850 34.974 17.61 1.29 16°41'55" 0.50
7+00
7+100
2
P5
PI-77
PI-8
PI-86 7+772.169 7+757.09 7+782.93 20.00 24.079 25.839 15.08 5.05 74°01'29" 20.00
7+150
7+200
7+450
6+950
PI-87 7+802.982 7+782.93 7+813.21 18.10 26.871 30.281 20.05 8.91 95°51'15" 1.80
7+250
78
PI-
ALCANT. ALIVIAD. TMC D=36"
PI-76
PI-74
7+
NORTE
7 KM
7+400
7+
0
3
PI-8
50
9 294 900 N
9 294 800 N
9 294 700 N
9 294 600 N
9
PI-7
2940.00
2937.50
PLANTA KM: 7+000 - 8+000
Esc. 1/2,000
2935.00
LEYENDA
2932.50 EJE PROYECTADO
VIVIENDA
2930.00 -9
.5
7% CARRETERA EXISTENTE
2927.50 RIO
CANTERA
2925.00
D.M.E.
ALC. EXISTENTE
2922.50
ALC. PROYECTADA
2920.00
PLAZOLETA
BENCHMARK BM(s)
2917.50
BUZONES
2910.00 2910.00
2907.50 2907.50
LCV=60.00
PROGRESIVA PVI=7+404.05
2905.00 COTA PVI=2895.460 2905.00
PROGRESIVA=7+374.05
COTA=2898.330
2902.50 2902.50
2900.00 2900.00
PROGRESIVA=7+434.05
COTA=2893.627
2897.50 2897.50
2895.00 2895.00
2892.50 2892.50
2890.00 2890.00
2887.50 2887.50
-6.
2885.00 11 2885.00
%
LCV=60.00
2882.50 PROGRESIVA PVI=7+762.79 2882.50
COTA PVI=2873.546
PROGRESIVA=7+732.79
COTA=2875.378
2880.00 2880.00
2877.50 2877.50
PROGRESIVA=7+792.79
COTA=2870.828
2875.00 2875.00
2872.50 2872.50
2870.00 2870.00
2867.50 2867.50
2865.00 2865.00
2862.50 2862.50
2860.00 2860.00
2857.50 2857.50
2855.00 2855.00
2852.50 2852.50
2850.00 2850.00
794.56 358.74 659.06
PENDIENTE -9.57% -6.11% -9.06%
7+000
7+020
7+040
7+060
7+080
7+100
7+120
7+140
7+160
7+180
7+200
7+220
7+240
7+260
7+280
7+300
7+320
7+340
7+360
7+380
7+400
7+420
7+440
7+460
7+480
7+500
7+520
7+540
7+560
7+580
7+600
7+620
7+640
7+660
7+680
7+700
7+720
7+740
7+760
7+780
7+800
7+820
7+840
7+860
7+880
7+900
7+920
7+940
7+960
7+980
8+000
PROGRESIVA
2927.61
2925.21
2906.81
2891.11
2879.91
2868.51
2861.41
2934.14
2918.63
2918.33
2916.42
2914.53
2911.57
2910.04
2907.93
2907.46
2900.63
2897.82
2900.74
2897.12
2890.47
2891.07
2886.33
2884.74
2882.70
2880.62
2878.86
2881.50
2877.36
2873.32
2865.16
2861.16
2859.30
2939.88
2932.89
2932.28
2930.05
2923.29
2920.45
2906.38
2895.38
2894.75
2890.68
2887.69
2877.09
2879.15
2869.15
2865.35
2862.18
2860.55
2857.68
COTA DE
TERRENO
2918.81
2884.71
2934.12
2932.20
2930.29
2928.38
2926.46
2924.55
2922.64
2920.72
2916.90
2914.98
2913.07
2911.16
2909.24
2907.33
2905.42
2903.50
2901.59
2899.67
2897.77
2896.04
2894.54
2893.26
2892.04
2890.82
2889.60
2888.38
2887.16
2885.93
2883.49
2882.27
2881.05
2879.83
2878.60
2877.38
2876.16
2874.93
2873.53
2871.95
2870.18
2868.36
2866.55
2864.74
2862.93
2861.12
2859.30
2857.49
2855.68
2853.87
2852.06
COTA DE
SUBRASANTE
2.71
3.31
5.41
1.31
4.22
4.87
2.57
2.57
2.32
2.52
6.70
2.86
2.30
2.98
2.84
2.47
2.60
0.42
2.42
2.88
5.62
5.76
0.68
5.76
3.59
3.06
3.35
3.35
3.38
5.87
0.84
7.47
5.08
3.93
0.87
3.95
5.14
0.79
0.93
7.96
3.15
0.14
0.29
3.67
5.43
1.99
1.64
1.73
1.78
1.65
1.48
ALT.DE CORTE
ALT.RELLENO
L=76.93 L=20.22 LC=46.15 L=21.38 L=35.37 L=59.11 L=15.16 L=14.16 L=42.99 L=29.27 L=30.28 L=20.61 L=40.22 L=152.79
L=19.74 L=46.01
R=300.00
ALINEAMIENTO LC=81.56 LC=63.13
LC=20.81
LC=46.11
LC=34.97
LC=25.84
LC=45.74
R=109.67 R=75.00 LC=37.85 LC=41.30 R=120.00 LC=68.52 R=110.00
R=50.00 R=20.00
R=14.12 R=27.92 R=40.00 R=70.00
LC=34.77
R=240.00
MUNICIPALIDAD DISTRITAL
DE SAN ISIDRO DE MAINO
PROYECTO:
UBICACION Y CLIMA:
CEJA DE SIERRA TRAMO III
LEV. Y CAD:
VDT
PP-08
CONTRATISTA SUPERVISION ESCALA: FECHA: