LG 35 40
LG 35 40
Learning Guide-35
Unit of Competence: Produce Bricks and Blocks
Module Title: Producing Bricks and Blocks
LG Code: EIS MAS2 M08 LO 01-LG-35
TTLM Code: EIS MAS2 M08 TTLM 0919v1
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to:
Information Sheet-1
Obtaining, confirming and applying work instructions
I.INTRODUCTION
A work instruction describes how a task will performed within a process (Process – any
activity or set of activities that uses resources to transform inputs into outputs). Work
instructions includes Plan/ Drawing, specification and quality.
1.1Following procedures:
Procedures are a form of communication set out by a company to inform its employees of a
Particular way the organization wants a task or tasks to be performed.
Procedures may include:
Safety procedures
Environmental procedures
Quality procedures
Maintenance procedures
An example why following procedure is advantageous.
A company has a procedure in place to inspect and lubricate a concrete mixer daily when in
use following the manufactures recommendations.
They are procedure is followed and regular inspections are made and the mixer is lubricated
to prevent parts ceasing up and wearing.
If this procedure is not followed the parts in the mixer can wear or cease and the equipment
could break down in the middle of a project, when it is required to be used impacting on time
to complete a job.
Using the term "specification" without a clear indication of what kind is confusing and
considered bad practice.
A design or product specification describes the features of the solutions for the
Requirement Specification, referring to either a designed solution or final produced solution.
It is often used to guide fabrication/production. Sometimes the term specification is here used
in connection with a data sheet (or spec sheet), which may be confusing. A data sheet
describes the technical characteristics of an item or product, often published by a
manufacturer to help people choose or use the products. A data sheet is not a technical
specification in the sense of informing how to produce.
Now days, hollow concrete blocks and bricks are becoming very popular. These blocks are
being widely used in construction of residential buildings, factories and multi-storied
buildings. These hollow blocks are commonly used in compound walls due to its low cost.
These hollow blocks are more useful due to its lightweight and ease of ventilation. Concrete
Page 5 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
blocks are wall constructing material made up of sand, cement, gravel, pumice and water
with different kinds and types of mix ratio. Depending upon the required strength and
purposes of the block, these ingredients may vary with mix ratio. It is sometimes called a
concrete masonry unit (CMU). Most concrete blocks have one or more hollow cavities, and
their sides may be cast smooth or with a design. In use, concrete blocks are stacked one at a
time and held together with fresh concrete mortar to form the desired length and height of the
wall.
Solid concrete block: Solid concrete blocks are heavier than hollow concrete blocks. Mostly
manufactured solid block size is 400mmx200mmx150 mm size. These blocks are mostly
used for load bearing wall construction.
I. 10 cm x 20 cm x 40 cm
II. 15 cm x 20 cm x 40cm
III. 20 cm x 20 cm x 40 cm
Class A and B are load bearing HCB units and suitable for
External walls pointed, rendered and plastered
The inner leaf of cavity walls or stone masonry
Internal walls or partitions
Panels in steel framed and reinforced steel framed buildings
Class C and D are non- load bearing HCB units and suitable for
Non- load bearing internal panels in steel framed and
reinforced concrete buildings
A brick is building material used to make walls, pavements and other elements in masonry
construction. Traditionally, the term brick referred to a unit composed of clay, but it is now
used to denote rectangular units made of clay-bearing soil, sand, and lime, or concrete
materials. Bricks can be joined together using mortar, adhesives or by interlocking them.
Bricks are produced in numerous classes, types, materials, and sizes which vary with region
and time period, and are produced in bulk quantities. Two basic categories of bricks are fired
and non-fired bricks.
Block is a similar term referring to a rectangular building unit composed of similar materials,
but is usually larger than a brick. Lightweight bricks (also called lightweight blocks) are made
from expanded clay aggregate.
Fired bricks are one of the longest-lasting and strongest building materials, sometimes
referred to as artificial stone, and have been used since circa 4000 BC. Air-dried bricks, also
known as mud bricks, have a history older than fired bricks, and have an additional
ingredient of a mechanical binder such as straw.
Bricks are laid in courses and numerous patterns known as bonds, collectively known as
brickwork, and may be laid in various kinds of mortar to hold the bricks together to make a
durable structure.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
1. ______often refers to a set of documented requirements to be satisfied by a material,
design, product, or service. (3 points)
A Plan B Specification C Schedule D all
2. Hollow concrete blocks are classified into the following classes(3points)
A Class 1,2,3 &4 B Type I,II,II C Class A,B,C&D D A&C
You can ask you teacher for the copy of the correct answers.
2.1 INTRODUCTION
Safety is the first essential requirement and every personnel must learn the safety measures
even before he/she starts working on a machine or on equipments. Safety is an attitude, a
form of mind of worker. If the attitude of worker towards safety is good and he/she is safety
conscious, then he/she him/her self will develop the safe working habits. Before you can use
equipment and tools or attempt practical work in a workshop you must understand basic
safety rules. These rules will help keep you and others safe in the workshop.
Classification of safety
1. Personal safety(PPE & HSE)
2. Safety hand tools & equipments
3. Safety working area
4. Safety rules & regulation of in the construction site.
5. First aid.(plaster, destinficant, bandage , ointment ).
Stay alert:- Watch what you are doing, and use common sense when operating a
power tool. Do not use a power tool while tired or under the influence of drugs,
Use safety equipment:- Always wear eye protection. Dust mask, non-skid safety
shoes, hard hat, or hearing protection must be used for appropriate conditions.
Always dress properly:- Dress properly for your work. While you must wear your
aprons are provided so that you can work on the machines. Remove any jeweler,
neckties, chains, bracelets, and rings. Roll up your sleeves and tie any hair back in a
ponytail before beginning any work
Keep the shop clean: - Put your tools back where they belong when you finished.
Page 11 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Keep the floor clear of debris and sawdust:- the floor should be clear of scrap
blocks, excessive material, and sawdust. Keep projects, sawhorses, and other
equipment and materials you are using out of travel lanes. Wipe up any spilled liquids
immediately.
Learn to use the tools correctly
Understanding using of hand tools in proper ways.
Avoid house play
Directions: Answer all the questions listed below. Use the Answer sheet provided in the next
page.
1. It will help keep you and others safe in the workshop
A Personal safety (PPE & HSE)
B Safety hand tools & equipments
C Safety working area
D Safety rules & regulation of in the construction site
E All the above
2. The term hazard may be defined by the following; except
A An energy source over which control has been lost
B The potential for harm
C A source of potential damaging
D The potential for the realization of unwanted negative consequences of an event
You can ask you teacher for the copy of the correct answers.
Safety signs
Safety Signs are generally either screen-printed or poly vinyl applied to aluminum, PVC or
Corflute. Some are reflective or glow in the dark.
Must do Signs
Are WHITE with a BLUE circle Restriction Signs
Are RED circle with BLACK writing
What is important is that you appreciate and know how to respond to signs. It is just as
important that you follow the meaning of the signs. People who do not respond to signs are
a risk to themselves and others
Signs should be placed where they will be effective and at a height that is readily visible.
This usually means that they need to be close, but before, to where the danger is and it
Page 15 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
should be fixed to a stable object. Consider the effectiveness of placing a number of signs at
the entrance of a large commercial job. This means that everyone has the opportunity to
read the signs before entering the site, but what happens an hour later when they actually
come across the danger? Will they remember the details of the sign or will it be too late.
Signs are best located near to the danger but not that close that it is too late. The following
sign is typical of a cluster of signs that may be found on large commercial building sites.
Above is a typical safety sign seen at QLD residential construction sites that advise people of
certain conditions and restrictions onsite and who to contact for entry.
Barricading can also be on construction sites to restrict the entry of the general public. Note
the signage at the site entry to give safety and entry conditions for the site.
Emergency Signs
Wherever „lifesaving‟ equipment exists, it is critical to ensure that it is ready to perform in the
event of an emergency.
For those responsible for workplaces, there are strict requirements for the maintenance of
essential services such as fire safety equipment. Responsibilities can include maintaining
equipment to specific standards, keeping maintenance records and completing necessary
compliance reports. One of the very important signs for every one is the emergency
assembly area on the next page.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
1._________ are universal in language
2. ________Signs are triangular YELLOW with BLACK writing
You can ask you teacher for the copy of the correct answers.
1. ______________________________________________________________________________
2._______________________________________________________________________________
________________________________________________________________________________
In small-scale backyard block making no special equipment is generally needed for making
concrete blocks, if the concrete is mixed by hand and simple wooded or steel moulds are
used. But with certain equipment the production process can be facilitated and the quality of
blocks improved considerably.
Mixers
The quality of concrete blocks depends largely on the type of mixer and period of mixing. The
free fall, revolving drum type mixers are not suitable, because of the semi-dry nature of the
mix. Pan mixers have a quick moving action and are thus recommended. Trough mixers are
also suitable.
Several types of machines are available, ranging from simple hand-operated ones to
complex stationary or mobile plants. The simpler machines are generally mechanically
operated using electric, petrol or diesel power, while the larger machines are usually
electrically operated. In most of the block making machines, the concrete is compacted by
vibration.
These are relatively inexpensive, simple and robust devices, which are especially suited for
on-site production of concrete blocks. Output rates for 40 x 20 x 20 cm blocks can range
from 10 to 80 blocks per hour, depending on the efficiency of the machine, rate of supply of
concrete and number of workers involved. There are basically three types:
Steel moulds that can be carried around by one person and used on a raised
working surface (eg table) or on the ground; the mix is tamped with the help of
special tampers that fit on the mould, but is more usually compacted by means of a
vibrator fixed to the mould or to the working surface (vibrating table).
concrete
fig.4.2.spade
Bucket
Brush
to clean hand tools before and after use and to clean dust on surfaces of tools and
equipments.
fig.4.4.brush
fig.4.8
mixer
fig.4.9 meter
Sprit level- used to check whether the surfaces are
level (horizontal) or plumb (vertical).
fig.4.11 trower
Page 22 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
2. "Egg-laying" mobile machines
These are machines designed for medium-scale production, either on-site or in a factory.
The name was given to these machines, because they leave the blocks to dry where they
are produced on a flat production surface and move a short distance away to produce the
next batch of blocks, and so on. The machines, which can be manually operated or fully
automatic, have output rates for 40 x 20 x 20 cm blocks ranging from 60 to 400 blocks per
hour, depending on the size of machine, the degree of automation, availability of continuous
supplies of concrete and production site organization.
These are automatic and very versatile machines used for the medium- and large-scale
production of superior quality concrete components. They can be of various sizes, but are
generally far more expensive than egg-laying machines of comparable sizes. The filling of
the moulds, the compaction (vibration) and ejection of the blocks is done automatically, and
Page 23 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
output rates for 40 x 20 x 20 cm blocks can range from 200 to 800 blocks per hour. These
high output rates are only possible with sophisticated ancillary equipment for transportation,
handling, stacking, etc, a well-trained staff, efficient management and sound financial base.
Space is saved by stacking the green blocks in shelves, where they are usually steam cured
for better product quality and quicker turnover.
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers.
1. list down the necessary tools required for HCB productions?(5 pts)
2. Mention all the equipments required for HCB productions? (5 pts)
You can ask you teacher for the copy of the correct answers.
5.1. Introduction
Measurements are the size of something to be measured or simply pertaining to its size,
quantity, length, or rate of something that has been measured. It is very important to know
how to measure and calculate the particular object, with a particular measuring instruments
needed in the job requirements.
The most common measurement of block production is measure by volume unless other
ways area & length.
Before anything else, you should learn what are the four fundamental basic mathematical
operations; addition, subtraction, multiplication and division.
Addition(+) is the process of calculating the sum of two or more numbers or amounts.
Example: a. 10+15= 25
b. 15 Birr + 5 Birr= 20 Birr
Subtraction(-) is the process or act of deducting one number or quantity of another and
withdrawal from a larger whole..
Example: a. 6*3 = 18
b. 5 Birr x 4 Birr = 20 Birr
Division(/,÷) is one of the mathematical operation also that an act of separating or splitting
something into parts or an any instances, or an operation used to calculate the number of
times one number is contained in another (dividing one number by another).
Example: a. 30 /6 = 5
b. 10÷5 = 2
c. 10Birr ÷2 Birr = 5 Birr
AREA Area is a quantity that expresses the extent of a two dimensional surface or shape in
the plane and can be understood as the amount of material with a given thickness
Formula
Shape Formula Variables
circle Where is pi, r is the radius.
triangle
Volume is the quantity of three-dimensional space enclosed by some closed boundary, for
example, the space that a substance (solid, liquid, gas) or shape occupies or contains. Any
unit of length gives a corresponding unit of volume namely the volume of a cube whose side
has the given length.
Let us assume that you have decided to mould your own blocks, and you have been faced
with the challenge of estimating the quantity of cement and sand to sale that will satisfy the
construction requirement. Here will give you a guide on how to make such estimate. This is
steps, so that you will be able to make calculations just in case you are using standard size
of blocks.
Example-1
Assume Number of blocks required = 3000pieces
To produce class B ratio (1:4)
200mm.
Fig.5.4. sectional view shows sizes of HCB thickness, width, length and Height
Now, we can estimate the number of wheel barrow trips of sand that the molder should
provide in order to make 17 blocks from one bag of cement.
Total volume of 17 blocks required = 0.1445 m3
Let the number of wheel barrow trips of sand be x
Hence, (volume of 1 bag of cement) + (Total volume of sand) = Volume of 17 blocks
Hence, 0.03472 + x(0.065) = 0.1445m3
On solving, x = 1.6889 un heaped wheelbarrow trips of sand
The volume of sand required to make 17blocks = 1.6889 × 0.065 = 0.10978 m3
Therefore summarily, we need 176.47 bags of cement and 11 trips of sand to mould
about 3000 pieces of (20*20*40)cm blocks with holes (for 1 bag = 17 blocks) B-Class
blocks.
You can ask you teacher for the copy of the correct answers.
A. Cement
The following cements are commonly used in concrete block making:
Ordinary Portland cement (OPC). Cheapest and most common type used.
Rapid hardening Portland cement (RHPC): more finely ground cement,
which hardens much faster than OPC. It is especially useful:
where storage space is limited,
when rapid production is important, and
To produce good strength blocks despite poor gradation of aggregate.
Block mix cement: marketed especially for block making, but can vary from
one manufacturer to another. It has the high early strength qualities of RHPC,
but is lower in price.
Special cements: such as Portland blast furnace cement, sulphate-resisting
Portland cement and others, used where special properties are of importance.
The partial replacement of cement by a pozzolana, eg rice husk ash, fly ash,
may be acceptable in certain cases, but should not be implemented without
prior laboratory testing.
B. Aggregates
The maximum particle size of coarser aggregates is 13 mm (or 10 mm for hollow blocks).
Rounded stones produce a concrete that flows more easily than angular (broken) particles,
but the latter give higher 'green strength' to the newly demoulded block, because the
particles interlock. This is very important for concrete block production.
Suitable aggregates are usually obtained from natural sources (eg river beds, gravel pits,
stone quarries, volcanic deposits) or from industrial by-processes (eg expanded clay, air
cooled, granulated or foamed blast furnace slag, sintered fly ash, etc). All aggregates,
whether fine or coarse, must be free from silt, clay, dust, organic matter, salts or other
chemical impurities, that could interfere with the bond between cement and aggregate or
cause deleterious chemical reactions.
Materials shall be stored and placed so as not to endanger the public, the workers or the
adjoining property. Materials shall be stacked on well‐drained, flat and unyielding surface.
Material stacks shall not impose any undue stresses on walls or other structures.
Materials shall be separated according to kind, size and length and placed in neat, orderly
piles. High piles shall be staggered back at suitable intervals in height. Piles of materials
shall be arranged so as to allow a minimum 800 mm wide passageway in between for
inspection and removal. All passageways shall be kept clear of dry vegetation, greasy
substance and debris.
For any site, there should be proper planning of the layout for stacking and storage of
different materials, components and equipments with proper access and proper
maneuverability of the vehicles carrying the material. While planning the layout, the
requirements of various materials, components and equipments at different stages of
construction shall be considered.
Stairways, passageways and gangways shall not become obstructed by storage of building
materials, tools or accumulated rubbish. Materials stored at site, depending upon the
individual characteristics, shall be protected from atmospheric actions, such as rain, sun,
winds and moisture, to avoid deterioration. Special and specified care should be taken for
inflammable and destructive chemicals and explosive during storage.
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers. Write your answers in the sheet provided in
the next page.
1. Stored materials shall be separately stored under following classifications; except? (10
points)
A. Climatically Sensitive Materials
B. Durable Materials
C. Materials Vulnerable to Rough Handling
D. Hazardous Materials
E. All are correct answer
You can ask you teacher for the copy of the correct answers.
1.______________________________________________________________________
Environmental protection
Due to the pressures of overconsumption, population growth and technology, the biophysical
environment is being degraded, sometimes permanently. This has been recognized, and
governments have begun placing restraints on activities that cause environmental
degradation. Since the 1960s, environmental movements have created more awareness of
the various environmental problems. There is disagreement on the extent of the
environmental impact of human activity and even scientific dishonesty occurs, so protection
measures are occasionally debated.
The construction and operation of a block making plant is associated with several
environmental issues, namely:-
Site selection
Dust and air emissions
Noise
Wastewater and storm water run-off
Solid wastes
Waste Oil, hydrocarbon and oil spills from vehicles and equipment
Energy and water consumption
Objectives of the guideline
This guideline is meant to ensure that prospective developers:-
adopt appropriate mitigating measures to safeguard the environment.
comply with provisions of relevant laws/ regulations/standards.
adopt eco-friendly practices to optimize use of resources.
Applicable Legislation
A block making plant manufacturing up to 10,000 blocks per day does not warrant a
Preliminary Environmental Report (PER) Approval or an Environmental Impact Assessment
(EIA) Licence. It requires a Building and Land Use Permit under the Local Government Act
2011. The construction and operation of a block making plant has to be carried out in
accordance with the provisions under the Planning Policy Guidance and Outline Planning
Scheme.
Location and Siting
i. The site should be located in industrial areas or at a suitable site outside the defined
settlement boundary/residential areas or within the buffer of bad neighbourhood
activities/ development.
ii. The existing development context of the site should be compatible with the activity.
iii. At the design stage of new block making plants, consideration should be given to the
site lay-out, with a view to avoiding disturbances to the surrounding environment. In
particular, attention should be paid to the location of entrances, exits, car parks,
access roads and amenities.
iv. The site should not be located within any Environmentally Sensitive Area (ESA) and
its prescribed buffer zone as per ESA Study 2009 such as wetland, steep slope and in
Industrial wastewater comprises effluents from cleaning of equipment and sprinkling of water
for dust abatement
Mitigating measures include:
Provision of appropriate domestic wastewater treatment and disposal facility to the
satisfaction of the Wastewater Management Authority.
Installation of grease traps or oil water separators for removal of floatable solids from
water.
Note:- Maintenance of the grease trap or oil water separator is to be carried out by the
owner / promoter.
Wash water should be channeled into a sedimentation tank. The effluent from the
sedimentation tank should be treated and reused for dust abatement and the settled
solids be reused.
Solid wastes
Solid wastes are mainly domestic wastes generated by the staff as well as cracked/ broken
blocks.
Mitigating measures include:-
Domestic solid wastes to be regularly collected in bins or waste handling receptacles
and disposed of to the satisfaction of the Local Authority.
No waste of any type to be disposed of in any watercourse including drains, canals
and the surrounding environment.
The cracked/ broken blocks to be reused for backfilling purposes.
Waste Oil, hydrocarbon and oil spills from vehicles and equipment
Where fuelling is proposed on site, a dedicated platform/ bay must be provided. Necessary
measures need to be taken to prevent any hydrocarbon and oil spill at the fuelling bay or
from storage tanks.
Where servicing is proposed on site, a dedicated workshop must be provided for such
activity.
Mitigating measures include:-
Waste oil shall be collected and disposed of as per the provisions of the Environment
Protection (Collection, Storage, Treatment, Use and Disposal of Waste Oil)
Regulations 2006.
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers.
1. The construction and operation of a block making plant is associated with several
environmental issues, namely:-
A. Dust and air emissions
B. Noise
C. Solid wastes
D. Waste Oil, hydrocarbon and oil spills from vehicles and equipment
E. A &C
F. All the above
You can ask you teacher for the copy of the correct answers.
4. Obtain the volume of the block to be moulded (the solid part by reducing the holes)
5. Know the standard quantities of block can be produced for class A- B- C ratio .
4. Formoso, C.T., Isatto, E.L., and Hirota, E.H. ( 1999). Method for waste Control in
theBuilding Industry, IGLC-7 proceedings, University of California, Berkeley, CA,
USA276.
Learning Guide-36
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
Determining Quantities of
cement, aggregate and water
Information Sheet-1
Inspecting and selecting aggregates
DEFINITIONS
An aggregate is a produced product having specific physical and gradational properties and
is created by manipulation of material through a processing operation. The material may be
from natural sand and/or gravel deposits, quarried bedrock, slag from steel mills or copper
refineries, debris from mining operations, or crushed Portland cement concrete.
Acceptance Tests – Tests conducted on produced material for acceptance or rejection.
These tests may be conducted any time including incorporation into the finished work. These
tests include MDOT‟s quality assurance testing.
Aggregates (Crushed Stone) – These aggregates are derived from the crushing of quarried
bedrock.
Aggregates (Natural Gravel) – These aggregates occur in natural, unconsolidated deposits
of granular material which are derived from rock fragments such as boulders, cobbles,
pebbles and granules and may be rounded, crushed or a combination of both. These
deposits may be found either above or below the water table. Natural gravel aggregates
consist predominantly of particles larger than the No. 4 sieve (4.75 mm).
*Natural Gravel Aggregates and Crushed Stone Aggregates are both included in the
Standard Specifications for Construction under the definition of Natural Aggregates.
Assuming that the ingredients and workmanship are of average quality, the main
characteristics of the most common types of concrete are:
the need for a relatively large amount of clean water for mixing and curing,
which can be a serious problem in dry regions;
The need for special knowledge and experience in the production process;
The risk of deterioration through sulphates in the soil or water to which the
concrete is exposed.
Entrepreneurs(short term trainees) wishing to start the production of concrete blocks will not
only have to consider all these technical and economic aspects, but also a number of
environmental, social and administrative factors, in comparison to other alternative building
materials, before undertaking further steps towards the establishment of a manufacturing
plant
1.One is not true of the main characteristics of the most common types of concrete? (6
points)
You can ask you teacher for the copy of the correct answers.
Batching
Aggregates can be batched by volume or by weight, but the latter is more accurate. For this
reason, cement should only be batched by weight, or preferably by using only whole bags of
50 kg. In backyard block production, with less stringent quality standards, batching by
volume using buckets, tins, wooden boxes or wheelbarrows is quite acceptable, if done with
care to ensure uniform proportions of mix.
Aggregate-Cement Ratio
After determining the correct blend of aggregates, the proportion of aggregate to cement
must be found by trials with different ratios, eg 6:1, 8:1,10:1, up to 16:1 by weight, end testing
the qualities of blocks produced.
The proportion of fine aggregate to cement is of special importance: if the ratio is too high,
the mortar will lack the cohesiveness needed for green strength and will be too weak to
impart enough strength to the matured blocks; if the proportion is too low, the mortar will be
very cohesive and the mix may not flow easily in handling and filling the mould.
Water-Cement Ratio
Only water that is fit for drinking should be used to mix the concrete. The correct amount of
water to be added to the mix depends on the types and mix proportions of aggregates and
cement, the required strength of the block, and the production method and equipment used.
The concrete must contain just enough water to facilitate production without any slumping of
blocks occurring after de-moulding. If the aggregates are dry, they may absorb some of the
water (lightweight aggregates may absorb up to 20 % by weight), but if the aggregates are
wet, the blocks will take longer to dry out
The following mixing proportions for the production of hollow concrete blocks are used in
accordance to ESC D3.301:
Table 1
Proportions by volume of
Class
Sand Gravel 00 Gravel 01 Red ash or Cement
Page 51 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
pumice
A 2 1 1 1
2 1 1 1
B 2 1 2 1
2 1 2 1
C 3 1 2 1
3 1 2 1
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
1. mixing proportions for the production of hollow concrete blocks Class A?(6 points)
A Sand (2) Gravel 00(1) Gravel 01(1) Red ash or pumice(0) Cement(1)
B Sand (3) Gravel 00(1) Gravel 01(2) Red ash or pumice (0) Cement(1)
C Sand (4) Gravel 00 (3) Gravel 01 (2) Red ash or pumice(1) Cement(1)
You can ask you teacher for the copy of the correct answers.
Equipment
Mixing Equipments of the materials has to be set up operated as close as mixing place.
Fig.3.1mixing equipment
1.Mixing Equipments of the materials has to be set up operated as close as mixing place?(4
points)
You can ask you teacher for the copy of the correct answers.
INTRODDUCTION
The production of concrete blocks consists of four basic processes: mixing, molding, curing, and
cubing. Some manufacturing plants produce only concrete blocks, while others may produce a wide
variety of precast concrete products including blocks, flat paver stones, and decorative landscaping
pieces such as lawn edging. Some plants are capable of producing 2,000 or more blocks per hour.
Mixing
In case of hand-molded block where compaction is done manually, concrete mix should be
sufficiently consistent to enable remolding immediately after casting. The consistency of the
mix should be such that it may cohere when compressed in the hand without free water
being visible. Too little water causes the mix to be friable, while too much water causes
difficulty in the immediate withdrawal of the mould. It shall be carried out on a water-tight
platform and care shall be taken to ensure that mixing is continued until the mass is uniform
in colour and consistency. Ten percent extra cement may be added if hand-mixing is an
alternative according to Indian standard.
In case of machine-molded blocks, the web markings on the units as they come from the
machine give a good indication as to whether the proper consistency of concrete has been
used. In addition to the grading of the aggregate and the quantity of cement, the amount of
water required for mix will depend to an extent on the type of machine on which blocks are
produced. It is possible to judge the proper consistency by squeezing a handful of concrete
mixture.
Mixing
The sand and gravel are stored outside in piles and are transferred into storage bins
in the plant by a conveyor belt as they are needed. The Portland cement is stored
outside in large vertical silos to protect it from moisture.
Production:
You can ask you teacher for the copy of the correct answers.
Water Content:
Water content is critical. The mixture must be wet enough to bind together when
Compacted, but should not be so wet that the blocks slump or sag when the mould is
removed. A common mistake is the use of mixes that are too dry, resulting in incomplete
compaction. Moisture content is approximately right when ripple marks form on a steel
rod or the back of a shovel when it is rubbed against some of the mixture. The water
content is just optimum when ripple marks start appearing on blocks when they are
removed from the mould.
As a simple test for cohesiveness, no excess water should be visible when a slump of
concrete is squeezed in the hand, but if the sample is rubbed quickly on a smooth round
metal bar or tube (2 to 4 cm in diameter) a slight film or paste should be brought to the
surface.
1. In hot climates, the fresh mix must be shaded from the sun to avoid premature setting
(2 points)
You can ask you teacher for the copy of the correct answers.
You can ask you teacher for the copy of the correct answers.
Instructions: Given necessary templates, tools and materials you are required to perform
the following tasks within a hours.
Learning Guide-37
Unit of Competence: Produce Bricks and Blocks
Module Title: Producing Bricks and Blocks
LG Code: EIS MAS2 M08 LO 03-LG-37
TTLM Code: EIS MAS2 M08 TTLM 0919v1
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
completing De-molding or
removing of molds
Learning Instructions:
12. Read the specific objectives of this Learning Guide.
13. Follow the instructions described below 3 to 6.
14. Read the information written in the information “Sheet 1, Sheet 2, Sheet 3 and Sheet 4”.
Information Sheet-1
Selecting and inspecting block making machine
Brick/block making machine is selected, inspected for damage or wear and operated
according to manufacturers‟ instructions.
You can ask you teacher for the copy of the correct answers.
Definition
Pouring is a manufacturing process by which a liquid material is usually Casted into a mold,
which contains a hollow cavity of the desired shape, and then allowed to solidify. the
solidified part is also known as a casting, which is ejected or broken out of the mold to
complete the process.
Tools and Materials needed for Pouring
Mold
Cement
Aggregate
Water
Concrete mixer or wheelbarrow and shovel
Float
Trowel
Planks
Broom
The general procedure for mixing and pouring is as follows;
1 x 50kg Cement
3 x batching box of Sand
3 x batching box of fine aggregates
Add enough water to make mix. This is only dependent on your grade of sand
According to Indian standard IS: manual compaction, the mixture shall be placed into the
mould in layers of about 50 to 75 mm and each layer thoroughly tamped with suitable
tampers until the whole mould is filled up and struck off level with a trowel.
In the case of mechanical compaction, the mould shall be filled up to overflow, vibrated or
Mechanically tamped and struck off level. After remolding the blocks shall be protected
against sun and wind by placing on the shade until they are sufficiently hardened to permit
Page 71 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
handling without damage. On the other hand, GTZ low cost housing manual Volume I specify
to vibrate the mixture for 60 second before extruded as hollow concrete block and
transported and remains for 24 hours on wooden pallet then it is be cured covered by plastic
sheet to enhance the curing process and preventing the water from evaporation.
Adequate care must be taken when compacting the concrete in the moulds of the block
making machine. Too little or poor compaction will result in greatly reduced strengths.
points
You can ask you teacher for the copy of the correct answers.
Fig.3.1 De-molding
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
1.
You can ask you teacher for the copy of the correct answers.
Inspection is the first step towards any maintenance program. The purpose of structural
inspection can be classified as under:
i. To provide assurance that the concrete structure is structurally safe and fit for
it‟s designed use.
ii. To identify actual and potential sources of trouble at the earliest possible stage.
iii. To record systematically and periodically the state of the structure. This enables
one to know the time when defects occurred and to identify any significant
structural changes like deformation, loss of camber, et c.
iv. To provide necessary information on which decision will be made for carrying
repairs, strengthening, replacement in the concrete structure.
There should be three types i.e. Routine inspection, detailed inspection and Special
inspection
2. Detailed Inspection: This is a more intensive and thorough inspection than the
routine inspection. All parts are closely examined, and if necessary, special equipments
are used for this inspection. Specially trained engineers conduct detailed inspection.
3. Special Inspection: Special inspections of concrete structures are done in the event of
unusual occurrences such as:
Visual inspection
A visual inspection is an examination of concrete to identify and define many of the various
conditions concrete may exhibit during its service life. The visual inspection is typically
limited to the surfaces of the concrete structure that are visually accessible.
You can ask you teacher for the copy of the correct answers.
You can ask you teacher for the copy of the correct answers.
The following procedures should be taken into account to Pour and compact of
Concrete materials:
Instructions: Given necessary templates, tools and materials you are required to perform
the following tasks within 4 hours.
Task 3. Perform Sieving (sand), in order to separate bigger rocks. The sand must be clean
from dirt, garbage, and mud.
Task 6.Dry mix cement, sand, and aggregate, (mixing by hand, or using a mixing machine)
till the ingredient come uniform color.
Task 8.mix cement, sand, aggregate, and water (mixing by hand, or Using a mixing
machine) till the ingredient come uniform color.
Task 10.put mixed ingredient into the prepared mould (metal moulds) and
Task 11. Make sure that the mix is measured spread and leveled then compact.
Task 12.Take the poured products out of the mould and placing it in the temporary storage.
Task 13.Cleaning the materials, tools, equipments and workplace used at the end of the
workday
Learning Guide-38
Unit of Competence: Produce Bricks and Blocks
Module Title: Producing Bricks and Blocks
LG Code: EIS MAS2 M08 LO 04-LG-38
TTLM Code: EIS MAS2 M08 TTLM 0919v1
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
Removing, Stacking and waiting Bricks/blocks in preparation for curing
Stacking bricks/blocks
Covering bricks/blocks
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to:
Remove, Stack and wait bricks/blocks in preparation for curing
Stack bricks/blocks
Cover bricks/blocks
Learning Instructions:
18. Read the specific objectives of this Learning Guide.
19. Follow the instructions described below 3 to 6.
20. Read the information written in the information “Sheet 1, Sheet 2, Sheet 3 and Sheet 4”.
21. Accomplish the “Self-check 1, Self-check t 2, Self-check 3 and Self-check 4” in page -6,
9, 12 and 14 respectively.
22. If you earned a satisfactory evaluation from the “Self-check” proceed to “Operation Sheet
1, Operation Sheet 2 and Operation Sheet 3 ” in page -15.
23. Do the “LAP test” in page – 16 (if you are ready).
Purpose
The blocks are demoulded immediately after compaction, so that they have to maintain their
shape even before the concrete hardens and Transported to stacking area to cure.
Curing
Curing of concrete is defined as the process of maintaining the moisture and temperature
conditions of concrete for hydration reaction to normally so that concrete develops hardened
properties over time.
Types of curing
There are generally 3 main type of curing used in the construction sector, namely:
Water curing
Vapor curing
Steam curing
a) Water curing
Water curing is the most commonly used practice. It is the system that is most appropriate for house
construction and does not require any special infrastructure or skill. However, water curing requires a
lot of water, which is not always easy at hand and might be even expensive.
In order to economize on water it is important that all measures are taken to prevent water
evaporation of cement products. E.g. concrete must be protected from direct sunshine and
winds to prevent rapid water evaporation. Methods such as covering the concrete with wet,
earth, sand, sawdust, grass and leaves are inexpensive, still quite effective. Further, plastic,
jute bags, hessian clothes too are common used material to prevent rapid water evaporation
It is of paramount importance that the entire cement product (concrete blocks, pavement
tiles, stone masonry, brick masonry, plaster work, cement flooring work etc.) is kept wet and
that it does never fully dry out, otherwise the final strength of the cement product will suffer. If
the hydration process has prematurely ended due to overheating (no curing), sprinkling water
onto the fully dried out cement product will not reactivate the hydration process, the loss in
strength will be permanent. In water curing, the cement product must be kept fully wet (e.g.
by covering the products with plastic canvas) for at least 7 days.
b) Vapor curing
Vapor curing is done where water is scare and cement based prefabricated elements such
as toilet slabs, tiles, stairs, beams etc are mass-produced. Vapor curing reduces the curing
time compared with simple water curing of about 50 to 60%. The principle of vapor curing is
to keep the cement product in a humid and hot environment that allows the cement to gain
strength in a much quicker way then with simple water curing. To create this humid and hot
environment a simple chamber with water retaining walls and floor needs to be constructed
which is covered with plastic to allow the sunshine to heat the chamber up and prevents the
water from evaporating. A floor water level of about 5 to 7 cm is to be maintained all the
times to keep the vapor system principle working.
c) Steam curing
Steam curing is normally used in only very sophisticated industrial plants that produce mass
cement based produces. A steam curing system is expensive and requires a lot of energy to
generate the required heat required for the steam. However, steam cured products can be
used after approx. 24 to 36 hrs. after production, providing a distinctive advantage over all
other curing systems.
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers. Write your answers in the sheet provided in
the next page.
You can ask you teacher for the copy of the correct answers.
You can ask you teacher for the copy of the correct answers.
2.1. Definition
A very basic form of storage, in which objects are placed on a surface (usually a flat floor)
and stacked on top of one another in blocks, is known as block stacking.
Fig.2.1.stacking systems
2.2. Purpose
Once the block is removed from production area, it must stack well at prepared
stacking site to provide required quality and Strength.
To assess Easley and manage.
To make environment clear and conducive.
You can ask you teacher for the copy of the correct answers.
Covering
Fresh blocks should be protected from the rain and from the drying effects of the sun and
wind during the first day with plastic sheets or any suitable covering.
In some cases, it may be necessary to protect blocks from frost damage. Covering with
plastic sheeting with the edges held down is normally sufficient.
To minimize breakages in cold weather, increase the cement content of the mix or the
curing period before moving blocks.
Directions: Answer all the questions listed below. Use the Answer sheet provided in the
next page:
You can ask you teacher for the copy of the correct answers.
The most effective technique for curing HCB production by watering are:
1. Observe the existing water
2. Identify equipments for curing
3. spray on surface uniformly
4. cover by jute bag, grass/plastic,etc
Instructions: Given necessary templates, tools and materials you are required to perform
the following tasks within 30 minutes per day for 7 days.
1. Environment Protection Guidelines for Construction and Land Development in the ACT
retrieved from https://ginninderry.com/wp-content/uploads/2017/03/EPA-Guidelines-for-
Construction-and-Land-Development-ACCESS.pdf. Accessed on Oct 30/2017.
2. Project profile on cement concrete hollow block-dc msme from
3. www.dcmsme.gov.in/reports/glass/hollowconcreteblocks.pdf
4. Storing, stacking and handling practice from
5. https://law.resource.org/pub/bd/bnbc.2012/gov.bd.bnbc.2012.07.02.pdf
Learning Guide-39
Unit of Competence: Produce Bricks and Blocks
Module Title: Producing Bricks and Blocks
LG Code: EIS MAS2 M08 LO 05-LG-39
TTLM Code: EIS MAS2 M08 TTLM 0919v1
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
Inspecting bricks/blocks for strength, dimension and shrinkage
This guide will also assist you to attain the learning outcome stated in the cover page.
Specifically, upon completion of this Learning Guide, you will be able to:
Inspect bricks/blocks for strength, dimension and shrinkage
Learning Instructions:
24. Read the specific objectives of this Learning Guide.
25. Follow the instructions described below 3 to 6.
26. Read the information written in the information “Sheet 1, Sheet 2, Sheet 3 and Sheet 4”.
27. Accomplish the “Self-check 1, Self-check t 2, Self-check 3 and Self-check 4” in page -6,
9, 12 and 14 respectively.
28. If you earned a satisfactory evaluation from the “Self-check” proceed to “Operation Sheet
1, Operation Sheet 2 and Operation Sheet 3 ” in page -15.
29. Do the “LAP test” in page – 16 (if you are ready).
Quality Control
The manufacture of concrete blocks requires constant monitoring to produce blocks that
have the required properties. The raw materials are weighed electronically before they are
placed in the mixer. The trapped water content in the sand and gravel may be measured with
ultrasonic sensors, and the amount of water to be added to the mix is automatically adjusted
to compensate. In areas with harsh temperature extremes, the water may pass through a
chiller or heater before it is used.
As the blocks emerge from the block machine, their height may be checked with laser beam
sensors. In the curing kiln, the temperatures, pressures, and cycle times are all controlled
and recorded automatically to ensure that the blocks are cured properly, in order to achieve
their required strength.
Strength:
The quality of blocks should be controlled so that the strengths are adequate to avoid
breakages or rejection by customers and the mixes are as economical as possible.
Ideally, blocks should be regularly tested for strength and mixes, and production
processes modified if necessary. If testing is not practical or unaffordable, block strength
should be continually assessed by looking to see if the corners and edges, or even the
whole bricks, tend to break in handling. Knocking two bricks together can also be used
to assess strength.
Dimensions:
The length and width of the units are determined by the mould and will not vary
greatly. However, the height can vary and should be monitored using a simple gauge.
Units of inconsistent height will lead to difficulties during building and possibly cause
rain penetration.
Page 100 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
fig 5.1 standard dimension of hollow concrete block
Shrinkage:
Concrete masonry units shrink slightly after manufacture. In order to avoid this from
happening in the wall, cured blocks should be allowed to dry out for at least seven days
before being used for construction.
Compressive Strength
According to Ethiopian standards hollow concrete block shall conform four classes
depends on their strength, as Class A, B, C and D and their requirements are defined below
and their minimum comprehensive strength listed in Table 5.1. On the other hand Indian
standard recommended classes of hollow concrete blocks as A, B, and C but class D
manufactured as solid block used for the purpose of load bearing wall having a minimum
density of 1800 kg/m3.
Class A used for load bearing wall construction above or below ground level in damp
proof course, in exterior walls that may or may not be treated with weather- protective
coating and for interior walls and density of Class A blocks must conform between the
range of 900 – 1200 kg/m3 on the other hand Indian standard recommended
minimum density 1500 kg/m3.
Class B and C are used for load bearing wall construction above ground level in
damp proof course in exterior walls that are treated with suitable weather- protective
coating and their density should be between 900 – 1200 kg/m3 on the other hand
Indian standard recommended minimum density within the range of 1000-1500 kg/m3
but class C is recommended for non load bearing wall.
Class D are used for non load bearing interior walls and exterior panels walls in steel
or reinforced concrete framed construction when protected from weather by rendering
or by some other efficient treatment and their density should be between 600 - 900
kg/m3.
Page 101 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Table 5.1. Comprehensive strength of hollow concrete blocks at 28 days ES.
Type of hollow Class Minimum comprehensive strength (N/mm2)
concrete block Average of 6 units Individual units
Load bearing A 5.5 5.0
B 4.5 4.0
C 3.5 3..0
Non load bearing D 20 1.8
Block Density
For hollow concrete, low density is probably the most characteristic feature. This is due to the
holes. In addition, it depend primary on the aggregate density and the proportions of
aggregate because the particle density of individual grading fraction can differ considerably
and thus will affect the density of concrete. This property also influenced by the cement,
water and air contents.
The density of a block can only be obtained after the casting process by taking three blocks
taken randomly from the selected samples and then dried to constant mass in a suitable
oven heated to approximately 105°C. After cooling the blocks to room temperature, the
dimensions of each block shall be measured in centimeters (to the nearest millimeter) and
the overall volume computed in cubic centimeters. According to Ethiopian standard and
Indian standard three blocks shall be taken for average density and it should conform to the
requirements specified in Table 5.2 below. The blocks shall then be weighed in kilograms (to
the nearest 10 g) and the density of each block calculated as follows:
Note- According to Ethiopian standard Class A, B, C are load bearing units but class D is non
Page 102 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
load bearing unit but in case of Indian standard class A and B are load bearing units but
Class C is for non load bearing units
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers.
1. What is the quality that has to be monitored to control for HCB production? (6 points)
points
Name: _________________________ Date: _______________
You can ask you teacher for the copy of the correct answers.
Page 103 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
List of Reference Materials
Page 104 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Masonry level II
Learning Guide-40
Unit of Competence: Produce Bricks and Blocks
Module Title: Producing Bricks and Blocks
LG Code: EIS MAS2 M08 LO 06-LG-40
TTLM Code: EIS MAS2 M08 TTLM 0919v1
LO-6: Clean up
Page 105 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Page 106 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Instruction Sheet Learning Guide #40
This learning guide is developed to provide you the necessary information regarding the
following content coverage and topics:
Learning Instructions:
30. Read the specific objectives of this Learning Guide.
31. Follow the instructions described below 3 to 6.
32. Read the information written in the information “Sheet 1, Sheet 2, Sheet 3 and Sheet 4”.
33. Accomplish the “Self-check 1, Self-check t 2, Self-check 3 and Self-check 4” in page -6,
9, 12 and 14 respectively.
34. If you earned a satisfactory evaluation from the “Self-check” proceed to “Operation Sheet
1, Operation Sheet 2 and Operation Sheet 3 ” in page -15.
35. Do the “LAP test” in page – 16 (if you are ready).
Page 107 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Information Sheet-1
Clearing Work area
The Producer (she/he) shall, during the production period maintain and clean up both
permanent and temporary facilities. He/she shall provide temporary site drainage to leave the
facilities free of standing water, accumulation of scrap, debris, waste material, and maintain
good standards of hygiene.
Inspection shall be carried out daily to ensure that sufficient workmen/women, tools and
facilities are provided to maintain the standard of hygiene.
Final cleaning of the site and removal of all temporary facilities shall be carried out to
approval at completion of works.
Page 108 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Self-Check 1 Written Test
1. Final cleaning of the site and removal of all temporary facilities shall be carried out to
approval at completion of works? 4 points
points
Name: _________________________ Date: _______________
You can ask you teacher for the copy of the correct answers.
Page 109 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Information Sheet- 2 Reusing, recycling and disposing waste materials
2.1 Definition
Disposing Removing and destroying or storing damaged, used or other unwanted domestic,
agricultural or industrial products and substances
Recycling means turning an item into raw materials which can be used again, usually for a
completely new product. This is an energy consuming procedure.
Reusing refers to using an object as it is without treatment. This reduces pollution and
waste, thus making it a more sustainable process.
Purpose
Reusing (R), and recycling (R) can help you, your community, and the environment by saving
money, energy, and natural resources.
Recycling is the process of collecting and processing materials that would otherwise be
thrown away as trash and turning them into new products. Recycling can benefit your
community and the environment.
Recycling reduces waste disposal by transforming useful materials such as plastic, glass and
paper into new products
The reusing process is not just about re-purposing materials, but the object as it is. This
includes buying and selling used goods and repairing items rather than discarding them.
Reusing is better than recycling because it saves the energy that comes with having to
dismantle and re-manufacture products. It also significantly reduces waste and pollution
because it reduces the need for raw materials, saving both forests and water supplies.
Waste that cannot be reused or recycled in some form eventually finds its way to disposal.
This disposal includes landfills, but an increasing number of municipalities have elected to
Page 110 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
divert waste into resource recovery. These recovery methods use the waste to generate
electricity or produce raw materials for industry.
Instructions: Answer all the questions listed below. Illustrations may be necessary to aid
some explanations/answers. Write your answers in the sheet provided in
the next page.
1. What is the 3R Define? 6 points
You can ask you teacher for the copy of the correct answers.
Page 111 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Information Sheet-3
Maintaining plant, tools and equipment
3.1 Maintenance
Maintenance on plant and equipment is carried out to prevent problems arising, to put faults
right, and to ensure equipment is working effectively.
Maintenance may be part of a planned programme or may have to be carried out at short
notice after a breakdown.
An effective maintenance programme will make plant and equipment more reliable. Fewer
breakdowns will mean less dangerous contact with machinery is required, as well as having
the cost benefits of better productivity and efficiency.
Additional hazards can occur when machinery becomes unreliable and develops faults.
Maintenance allows these faults to be diagnosed early to manage any risks. However,
maintenance needs to be correctly planned and carried out. Unsafe maintenance has caused
many fatalities and serious injuries either during themaintenance or to those using the badly
maintained or wrongly maintained/repaired equipment.
If you are an employer and you provide equipment for use, from hand tools and ladders to
electrical power tools and larger plant, you need to demonstrate that you have arrangements
in place to make sure they are maintained in a safe condition.
Page 112 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Establishing a planned maintenance programme may be a useful step towards reducing risk,
as well as having a reporting procedure for workers who may notice problems while working
on machinery.
Some items of plant and equipment may have safety-critical features where deterioration
would cause a risk. You must have arrangements in place to make sure the necessary
inspections take place.
Release any stored energy, such as compressed air or hydraulic pressure that could
cause the machine to move or cycle
Support parts of plant that could fall, eg support the blades of down-stroking bale
cutters and guillotines with blocks
Allow components that operate at high temperatures time to cool
Place mobile plant in neutral gear, apply the brake and chock the wheels
Safely clean out vessels containing flammable solids, liquids, gases or dusts, and
check them before hot work is carried out to prevent explosions. You may need
specialist help and advice to do this safely
Avoid entering tanks and vessels where possible. This can be very high-risk work. If
required, get specialist help to ensure adequate precautions are taken
Clean and check vessels containing toxic materials before work starts
Do…
Ensure maintenance is carried out by a competent person (someone who has the
necessary skills, knowledge and experience to carry out the work safely)
Maintain plant and equipment regularly – use the manufacturer‟s maintenance
instructions as a guide, particularly if there are safety-critical features
Have a procedure that allows workers to report damaged or faulty equipment
Provide the proper tools for the maintenance person
Schedule maintenance to minimise the risk to other workers and the maintenance
person wherever possible
make sure maintenance is done safely, that machines and moving parts are isolated
or locked and that flammable/explosive/toxic materials are dealt with properly
Page 113 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Don’t…
Ignore maintenance
Ignore reports of damaged or unsafe equipment
Use faulty or damaged equipment
3.6 Dos and don’ts of machinery safety for workers
Do…
Check the machine is well maintained and fit to be used, ie appropriate for the job and
working properly and that all the safety measures are in place – guards, isolators,
locking mechanisms, emergency off switches etc
Use the machine properly and in accordance with the manufacturer‟s instructions
Make sure you are wearing the appropriate protective clothing and equipment
required for that machine, such as safety glasses, hearing protection and safety shoes
Don’t…
Use a machine or appliance that has a danger sign or tag attached to it. Danger signs
should only be removed by an authorized person who is satisfied that the machine or
process is now safe
Wear dangling chains, loose clothing, rings or have loose, long hair that could get
caught up in moving parts
Distract people who are using machines
Remove any safeguards, even if their presence seems to make the job more difficult
Page 114 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
Self-Check -3 Written Test
points
You can ask you teacher for the copy of the correct answers.
Name: _________________________ Date: _______________
Page 115 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
List of Reference Materials
Page 116 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019
This learning guide prepared by :
No Name of trainer Qualification Region E-mail
1 Dereje Teshome Construction technology & Diredewa [email protected]
managment(MS)
7 Zelallem taye gedifew M.A IN LEADER SHIP (MA) Amhara Tayezelalem22@gmail .com
Page 117 of 117 Federal TVET Agency TVET program title: Version -1
Author/Copyright Masonry Level II September 2019