Ieee Guide For Onsite Acceptance Tests of Electrical Equipment A
Ieee Guide For Onsite Acceptance Tests of Electrical Equipment A
Sponsored by the
Corporate Advisory Group
IEEE Substations Committee
IEEE Switchgear Committee
IEEE Transformers Committee
IEEE
3 Park Avenue IEEE Std 1861™-2014
New York, NY 10016-5997
USA
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861™-2014
Sponsor
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Abstract: On-site acceptance tests of ultra-high-voltage power equipment are subject to this
guide. Criteria and requirements for test items, conditions, methods, and results are established.
The stated specifications and requirements, both technical and for testing, are universally needed
for acceptance tests on-site and commissioning of ultra-high-voltage power equipment, including
power transformers, reactors, capacitive voltage transformers, bushing-type current transformers,
gas-insulated switchgear, air insulated grounding switches, air insulated disconnecting switches,
bushings, metal-oxide surge arresters, suspension insulators, post insulators, and insulating oil,
etc. It will be sufficient for most installations.
IEEE is a registered trademark in the U.S. Patent & Trademark Office, owned by The Institute of Electrical and Electronics
Engineers, Incorporated.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Important Notices and Disclaimers Concerning IEEE Standards Documents
IEEE documents are made available for use subject to important notices and legal disclaimers. These
notices and disclaimers, or a reference to this page, appear in all standards and may be found under the
heading “Important Notice” or “Important Notices and Disclaimers Concerning IEEE Standards
Documents.”
Notice and Disclaimer of Liability Concerning the Use of IEEE Standards
Documents
IEEE Standards documents (standards, recommended practices, and guides), both full-use and trial-use, are
developed within IEEE Societies and the Standards Coordinating Committees of the IEEE Standards
Association (“IEEE-SA”) Standards Board. IEEE (“the Institute”) develops its standards through a
consensus development process, approved by the American National Standards Institute (“ANSI”), which
brings together volunteers representing varied viewpoints and interests to achieve the final product.
Volunteers are not necessarily members of the Institute and participate without compensation from IEEE.
While IEEE administers the process and establishes rules to promote fairness in the consensus development
process, IEEE does not independently evaluate, test, or verify the accuracy of any of the information or the
soundness of any judgments contained in its standards.
IEEE does not warrant or represent the accuracy or content of the material contained in its standards, and
expressly disclaims all warranties (express, implied and statutory) not included in this or any other
document relating to the standard, including, but not limited to, the warranties of: merchantability; fitness
for a particular purpose; non-infringement; and quality, accuracy, effectiveness, currency, or completeness
of material. In addition, IEEE disclaims any and all conditions relating to: results; and workmanlike effort.
IEEE standards documents are supplied “AS IS” and “WITH ALL FAULTS.”
Use of an IEEE standard is wholly voluntary. The existence of an IEEE standard does not imply that there
are no other ways to produce, test, measure, purchase, market, or provide other goods and services related
to the scope of the IEEE standard. Furthermore, the viewpoint expressed at the time a standard is approved
and issued is subject to change brought about through developments in the state of the art and comments
received from users of the standard.
In publishing and making its standards available, IEEE is not suggesting or rendering professional or other
services for, or on behalf of, any person or entity nor is IEEE undertaking to perform any duty owed by any
other person or entity to another. Any person utilizing any IEEE Standards document, should rely upon his
or her own independent judgment in the exercise of reasonable care in any given circumstances or, as
appropriate, seek the advice of a competent professional in determining the appropriateness of a given
IEEE standard.
IN NO EVENT SHALL IEEE BE LIABLE FOR ANY DIRECT, INDIRECT, INCIDENTAL, SPECIAL,
EXEMPLARY, OR CONSEQUENTIAL DAMAGES (INCLUDING, BUT NOT LIMITED TO:
PROCUREMENT OF SUBSTITUTE GOODS OR SERVICES; LOSS OF USE, DATA, OR PROFITS;
OR BUSINESS INTERRUPTION) HOWEVER CAUSED AND ON ANY THEORY OF LIABILITY,
WHETHER IN CONTRACT, STRICT LIABILITY, OR TORT (INCLUDING NEGLIGENCE OR
OTHERWISE) ARISING IN ANY WAY OUT OF THE PUBLICATION, USE OF, OR RELIANCE
UPON ANY STANDARD, EVEN IF ADVISED OF THE POSSIBILITY OF SUCH DAMAGE AND
REGARDLESS OF WHETHER SUCH DAMAGE WAS FORESEEABLE.
Translations
The IEEE consensus development process involves the review of documents in English only. In the event
that an IEEE standard is translated, only the English version published by IEEE should be considered the
approved IEEE standard.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Official statements
A statement, written or oral, that is not processed in accordance with the IEEE-SA Standards Board
Operations Manual shall not be considered or inferred to be the official position of IEEE or any of its
committees and shall not be considered to be, or be relied upon as, a formal position of IEEE. At lectures,
symposia, seminars, or educational courses, an individual presenting information on IEEE standards shall
make it clear that his or her views should be considered the personal views of that individual rather than the
formal position of IEEE.
Comments on standards
Comments for revision of IEEE Standards documents are welcome from any interested party, regardless of
membership affiliation with IEEE. However, IEEE does not provide consulting information or advice
pertaining to IEEE Standards documents. Suggestions for changes in documents should be in the form of a
proposed change of text, together with appropriate supporting comments. Since IEEE standards represent a
consensus of concerned interests, it is important that any responses to comments and questions also receive
the concurrence of a balance of interests. For this reason, IEEE and the members of its societies and
Standards Coordinating Committees are not able to provide an instant response to comments or questions
except in those cases where the matter has previously been addressed. For the same reason, IEEE does not
respond to interpretation requests. Any person who would like to participate in revisions to an IEEE
standard is welcome to join the relevant IEEE working group.
Users of IEEE Standards documents should consult all applicable laws and regulations. Compliance with
the provisions of any IEEE Standards document does not imply compliance to any applicable regulatory
requirements. Implementers of the standard are responsible for observing or referring to the applicable
regulatory requirements. IEEE does not, by the publication of its standards, intend to urge action that is not
in compliance with applicable laws, and these documents may not be construed as doing so.
Copyrights
IEEE draft and approved standards are copyrighted by IEEE under U.S. and international copyright laws.
They are made available by IEEE and are adopted for a wide variety of both public and private uses. These
include both use, by reference, in laws and regulations, and use in private self-regulation, standardization,
and the promotion of engineering practices and methods. By making these documents available for use and
adoption by public authorities and private users, IEEE does not waive any rights in copyright to the
documents.
Photocopies
Subject to payment of the appropriate fee, IEEE will grant users a limited, non-exclusive license to
photocopy portions of any individual standard for company or organizational internal use or individual,
non-commercial use only. To arrange for payment of licensing fees, please contact Copyright Clearance
Center, Customer Service, 222 Rosewood Drive, Danvers, MA 01923 USA; +1 978 750 8400. Permission
to photocopy portions of any individual standard for educational classroom use can also be obtained
through the Copyright Clearance Center.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Updating of IEEE Standards documents
Users of IEEE Standards documents should be aware that these documents may be superseded at any time
by the issuance of new editions or may be amended from time to time through the issuance of amendments,
corrigenda, or errata. An official IEEE document at any point in time consists of the current edition of the
document together with any amendments, corrigenda, or errata then in effect.
Every IEEE standard is subjected to review at least every ten years. When a document is more than ten
years old and has not undergone a revision process, it is reasonable to conclude that its contents, although
still of some value, do not wholly reflect the present state of the art. Users are cautioned to check to
determine that they have the latest edition of any IEEE standard.
In order to determine whether a given document is the current edition and whether it has been amended
through the issuance of amendments, corrigenda, or errata, visit the IEEE-SA Website at
http://ieeexplore.ieee.org/xpl/standards.jsp or contact IEEE at the address listed previously. For more
information about the IEEE SA or IEEE’s standards development process, visit the IEEE-SA Website at
http://standards.ieee.org.
Errata
Errata, if any, for all IEEE standards can be accessed on the IEEE-SA Website at the following URL:
http://standards.ieee.org/findstds/errata/index.html. Users are encouraged to check this URL for errata
periodically.
Patents
Attention is called to the possibility that implementation of this standard may require use of subject matter
covered by patent rights. By publication of this standard, no position is taken by the IEEE with respect to
the existence or validity of any patent rights in connection therewith. If a patent holder or patent applicant
has filed a statement of assurance via an Accepted Letter of Assurance, then the statement is listed on the
IEEE-SA Website at http://standards.ieee.org/about/sasb/patcom/patents.html. Letters of Assurance may
indicate whether the Submitter is willing or unwilling to grant licenses under patent rights without
compensation or under reasonable rates, with reasonable terms and conditions that are demonstrably free of
any unfair discrimination to applicants desiring to obtain such licenses.
Essential Patent Claims may exist for which a Letter of Assurance has not been received. The IEEE is not
responsible for identifying Essential Patent Claims for which a license may be required, for conducting
inquiries into the legal validity or scope of Patents Claims, or determining whether any licensing terms or
conditions provided in connection with submission of a Letter of Assurance, if any, or in any licensing
agreements are reasonable or non-discriminatory. Users of this standard are expressly advised that
determination of the validity of any patent rights, and the risk of infringement of such rights, is entirely
their own responsibility. Further information may be obtained from the IEEE Standards Association.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Participants
At the time this IEEE guide was completed, the P1861 sub-working group of Ultra-High-Voltage AC
Standards Working Group had the following membership:
Bo Li, Chair
Hui Chao, Co-Chair
Jiangbo Chen, Secretary
Ying Li, Secretary
The Working Group gratefully acknowledges the contributions of the following entities and participants.
Without their assistance and dedication, this standard would not have been completed.
The following entities submitted technical contributions or commented of the draft standard at various
stages of the project development.
The following members of the entity balloting committee voted on this guide. Balloters may have voted for
approval, disapproval, or abstention.
vi
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
When the IEEE-SA Standards Board approved this guide on 12 June 2014, it had the following
membership:
*Member Emeritus
Also included are the following nonvoting IEEE-SA Standards Board liaisons:
Patrick Gibbons
IEEE-SA Content Publishing
Soo Kim
IEEE-SA Standards Technical Community
vii
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Introduction
This introduction is not part of IEEE Std 1861™-2014, IEEE Guide for On-Site Acceptance Tests of Electrical
Equipment and System Commissioning of 1000 kV AC and Above.
With the increase in voltage levels, the reliability and safety of high-voltage electric equipment is facing
new challenges. There is a need to have consensus on a series of technical criteria and requirements for on-
site acceptance tests for ultra-high-voltage (UHV) electric equipment to detect the damages or abnormal
conditions that may occur during the transportation and installation processes and to determine whether
equipment can be put into operation reliably and safely for power systems.
AC transmission systems of 1000 kV or greater have been established and operated with full-voltage in
China and are also currently in various stages of development in other countries. However, there is a lack
of suitable UHV transmission system commissioning procedures and technical information. Therefore, it is
necessary to formulate a series of consensus technical requirements and criteria so as to facilitate the
development of UHV systems and help ensure their successful commissioning.
This guide proposes on-site acceptance tests, relevant test items, test methods, and evaluation criteria for
power transformers, reactors, capacitive voltage transformers (CVTs), bushing-type current transformers
(CTs), gas-insulated switchgear, air-insulated grounding switches, air-insulated disconnecting switches,
bushings, metal-oxide surge arresters (MOSAs), suspension insulators, post insulators, and insulating oil.
System commissioning consists of two parts. The first part is the preparation work before commissioning,
including simulation and making commissioning schemes, testing schemes, and implementation schedules.
The second part is the commissioning of projects with detailed explanation of conditions and contents.
viii
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Contents
1. Overview .................................................................................................................................................... 1
1.1 Scope ................................................................................................................................................... 1
1.2 Purpose ................................................................................................................................................ 1
2. Normative references.................................................................................................................................. 2
Annex A (informative) On-site acceptance tests for UHV transformers—Practical examples based on the
experiences in China......................................................................................................................................33
A.1 Applied voltage test ...........................................................................................................................35
A.2 Induced voltage test with partial discharge measurement (IVPD) .....................................................36
Annex B (informative) On-site tests for gas-insulated switchgear—Practical examples based on the
experiences in China......................................................................................................................................39
B.1 Tests for gas-insulated switchgear .....................................................................................................39
B.2 Dielectric test on the main circuit ......................................................................................................39
ix
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Guide for On-Site Acceptance
Tests of Electrical Equipment
and System Commissioning
of 1000 kV AC and Above
IMPORTANT NOTICE: IEEE Standards documents are not intended to ensure safety, security, health,
or environmental protection, or ensure against interference with or from other devices or networks.
Implementers of IEEE Standards documents are responsible for determining and complying with all
appropriate safety, security, environmental, health, and interference protection practices and all
applicable laws and regulations.
This IEEE document is made available for use subject to important notices and legal disclaimers.
These notices and disclaimers appear in all publications containing this document and may
be found under the heading “Important Notice” or “Important Notices and Disclaimers
Concerning IEEE Documents.” They can also be obtained on request from IEEE or viewed at
http://standards.ieee.org/IPR/disclaimers.html.
1. Overview
1.1 Scope
This guide applies to on-site acceptance tests of electrical equipment and system commissioning of
1000-kV ac and above. It identifies criteria and recommendations for test items, conditions, methods, and
results.
The stated recommendations, both technical and for testing, are universally needed for on-site acceptance
tests and commissioning of 1000 kV ac and above ultra-high-voltage (UHV) power equipment, including
power transformers, reactors, capacitive voltage transformers (CVTs), bushing-type current transformers
(CTs), gas-insulated switchgear, air insulated grounding switches, air insulated disconnecting switches,
bushings, metal-oxide surge arresters (MOSAs), suspension insulators, post insulators, and insulating oil.
1.2 Purpose
The intent of this guide is to identify on-site acceptance tests of 1000-kV ac and above electrical equipment.
This guide also promotes the application and development of on-site acceptance test methodology.
1
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
This guide also provides uniform technology specification recommendations for commissioning of
1000-kV ac and above transmission systems. It also provides the recommendations of testing, acceptance
criteria, and safety specifications.
This guide also provides sufficient technical support for widespread and long-distance UHV ac
transmission and promotes system operating safety and reliability.
2. Normative references
The following referenced documents are indispensable for the application of this document (i.e., they must
be understood and used, so each referenced document is cited in text and its relationship to this document is
explained). For dated references, only the edition cited applies. For undated references, the latest edition of
the referenced document (including any amendments or corrigenda) applies.
IEC 60076-3:2000, Power transformers—Part 3: Insulation levels, dielectric tests and external clearances in
air.
IEC 60383-1:1993, Insulators for overhead lines with a nominal voltage above 1000 V—Part 1: Ceramic or
glass insulator units for a.c. systems—Definitions, test methods and acceptance criteria.
IEC 60694:2002, Common specifications for high-voltage switchgear and controlgear standards.
IEEE Std C37.100.1™-2007, IEEE Standard of Common Requirements for High Voltage Power
Switchgear Rated Above 1000 V. 2,3
IEEE Std C37.122™-2010, Standard for High Voltage Gas-Insulated Substations Rated Above 52 kV.
1
IEC publications are available from the Sales Department of the International Electrotechnical Commission, 3 rue de Varembé, PO
Box 131, CH-1211, Geneva 20, Switzerland (http://www.iec.ch/). IEC publications are also available in the United States from the
Sales Department, American National Standards Institute, 25 West 43rd Street, 4th Floor, New York, NY 10036, USA
(http://www.ansi.org).
2
The IEEE standards or products referred to in this clause are trademarks of The Institute of Electrical and Electronics Engineers, Inc.
3
IEEE publications are available from The Institute of Electrical and Electronics Engineers, 445 Hoes Lane, Piscataway, NJ 08854,
USA (http://standards.ieee.org/).
2
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
IEEE Std C57.12.00™-2010, IEEE Standard for General Requirements for Liquid-Immersed Distribution,
Power, and Regulating Transformers.
IEEE Std C57.12.90™-2010, IEEE Standard Test Code for Liquid-Immersed Distribution Power and
Regulating Transformers.
IEEE Std C57.13.1™-2006, IEEE Guide for Field Testing of Relaying Current Transformers.
IEEE Std C57.13.5™-2009, IEEE Standard of Performance and Test Requirements for Instrument
Transformers of a Nominal System voltage of 115 kV and Above.
IEEE Std C57.19.00™-2004, IEEE Standard General Requirements and Test Procedure for Power
Apparatus Bushings.
IEEE Std C57.93™-2007, IEEE Guide for Installation and Maintenance of Liquid-Immersed Power
Transformers.
IEEE Std C62.11™-2005, IEEE Standard for Metal-Oxide Surge Arresters for AC Power Circuits (> 1 kV).
3.1 Definitions
For the purposes of this document, the following terms and definitions apply. The IEEE Standards
Dictionary Online should be consulted for terms not defined in this clause. 4
on-site acceptance tests: Inspections and tests are performed (or checked) on the correct operation and
dielectric integrity of the equipment after shipping and site assembly, verifying the results of the factory
tests. The on-site acceptance test does not include power grid tests.
system commissioning: A series of tests carried out after an on-site acceptance test to confirm the integrity
of the equipment and system in a power grid before putting it into service.
NOTE—Some countries have regulations such as the Electricity Business Act, Technical Regulations on Electrical
Equipment, Standard on Power Plants and Substations (Non-governmental), and Standards on Electrical Equipment
(Non-governmental). 5
ac alternating current
CT current transformer
4
IEEE Standards Dictionary Online subscription is available at:
http://www.ieee.org/portal/innovate/products/standard/standards_dictionary.html.
5
Notes in text, tables, and figures of a standard are given for information only and do not contain requirements needed to implement
this standard.
3
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
dc direct current
VT voltage transformer
4.1 General
On-site acceptance tests for newly installed electrical equipment are an important approach to judge
whether equipment is normal or abnormal after transportation and installation.
On-site acceptance test results must be analyzed and compared carefully with those from the factory test.
The influence of different test conditions, such as humidity and the ambient temperature, should be taken
into consideration when making comparisons.
For the procedure followed for field tests, the test method should refer to the same kind of tests described in
relevant publications for factory tests, such as IEEE Std C57.12.00-2010, IEEE Std C57.12.90-2010,
IEEE Std C57.93-2007, IEC 60599:2007, and the IEC 60076 series. The test methods and their descriptions
listed below are applicable for UHV transformers. 6
UHV transformers should be subjected to on-site acceptance tests as specified below. The details/
procedures of on-site tests for a UHV transformer based on experiences in China are given in Annex A.
Ratio tests
Polarity check
6
Information on references can be found in Clause 2.
4
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Insulation resistance test on each winding to ground and between windings including bushings
Dissipation factor (tanδ) and capacitance measurement on each winding to ground and between
windings
Tests on bushings
Optional tests based on the requirements of the user include the following:
Refer to 11.8 of IEC 60076-1:2011 for leak testing with pressure (tightness test).
a) Measurement should be performed for all windings at all tap positions (if any).
c) Measured values should be compared with the average value of three phase windings.
b) Voltage ratio should correspond to the value on nameplate and the factory test result.
5
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The polarity of single-phase transformers should be checked. The polarity must be the same as that
identified on the nameplate.
4.2.6 Insulation resistance test between each winding to ground and between windings
including bushings
Refer to 10.11 of IEEE Std C57.12.90-2010 for insulation resistance tests between each winding to ground
and between windings including bushings.
4.2.7 Dissipation factor (tanδ) and capacitance measurement on each winding to ground
and between windings
Dissipation factor (tanδ) and capacitance measurement on each winding to ground and between windings
should include the following:
a) Terminals to be tested should be connected to the test instrument and the terminals not being tested
short-circuited and connected to ground.
b) Tanδ should be compared with the factory test result considering the temperature difference, and
the capacitance value should have no obvious difference with factory test result with certain
deviation based on the experience of users.
Refer to 11.2.3 of IEC 60076-1:2011 for the core and frame insulation check.
The DGA test should be carried out after the completion of oil treatment. If a dielectric test is required, the
DGA test should be carried out after the dielectric test.
a) The excitation current should be measured at the same reduced test voltage as the factory test. The
test should be carried out before the winding resistance measurement to avoid the influence of
residual flux in the core.
6
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
b) The value of excitation current at reduced test voltage should be compared with the factory test
results.
a) The short-circuit impedance should be measured at the same reduced current as in the factory test.
b) The value of short-circuit impedance at reduced current should be compared with the factory test
results.
4.2.16 Induced voltage test with partial discharge measurement (IVPD) (optional test)
4.3 Reactors
For the procedure followed for field tests, the test method should refer to the same kind of tests described in
relevant publications for factory tests, such as IEEE Std C57.12.00-2010, IEEE Std C57.12.90-2010,
IEEE Std C57.93-2007, IEC 60599:2007, and the IEC 60076 series. The test methods and their descriptions
listed below are applicable for UHV reactors.
Shunt reactors and neutral-earthing reactors (if any) should be subjected to on-site acceptance tests as
specified below.
d) Dissipation factor (tanδ) and capacitance measurement on each winding to ground and between
windings
f) Tests on bushings
7
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
h) DGA test
Refer to 11.8 of IEC 60076-1:2011 for leak testing with pressure (tightness test).
Refer to 10.11 of IEEE Std C57.12.90-2010 for insulation resistance tests including bushings.
4.3.5 Dissipation factor (tanδ) and capacitances measurement on each winding to ground
and between windings
Refer to 4.2.7 of this guide for dissipation factor (tanδ) and capacitances measurement on each winding to
ground and between windings.
Refer to 11.2.3 of IEC 60076-1:2011 for the core and frame insulation check.
The DGA test should be carried out after the completion of oil treatment. If a dielectric test is required, the
DGA test should be carried out after the dielectric test.
8
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
For the procedure followed for field tests, the test method should refer to same kind of tests described in
relevant publications, such as IEEE Std C57.13.5-2009, IEEE Std C57.13-2008, and IEC 60044-5:2004.
The test methods and their descriptions listed below are applicable for UHV CVTs.
i) Damper check
A low-frequency withstand test on capacitor voltage dividers is optional based on user requirements.
Insulation resistance measurement of capacitor voltage dividers’ low-voltage terminal to earth terminal
should include the following:
4.4.3 Capacitance and dissipation factor (tanδ) measurement of capacitor voltage dividers
Capacitance and dissipation factor (tanδ) measurement of capacitor voltage dividers should include the
following:
a) Measurement of capacitance and tanδ of each capacitor voltage divider unit should be performed at
10 kV. Measurement of capacitance and tanδ of the intermediate voltage capacitor should be
performed at rated voltage. The value of tanδ should not be greater than 0.2%.
b) The deviation of the capacitance of each capacitor unit and intermediate voltage capacitor unit
should be between −5% ~ +10% of rated value.
9
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
c) If the value of tanδ measured at 10 kV doesn’t meet the requirement, it should be measured at rated
voltage instead. When the value of tanδ measured at rated voltage meets the requirement, the
capacitor voltage dividers can be considered to be acceptable.
Tightness of the liquid-filled capacitor voltage dividers should meet the following requirements:
a) No surface defects that could affect the satisfactory performance in serve should be tolerated.
b) The capacitor voltage divider should be replaced if there is any evidence of leakage.
b) For the resistance of intermediate transformers and compensation reactor windings, relevant
deviation should be within ±10% of the factory test value at the same temperature. For dampers,
the relevant deviation should be within ±15% of the factory test value.
Insulation resistance between terminals of intermediate transformer secondary windings and earth,
insulation resistance of intermediate transformer primary windings to earth, insulation resistance of
compensation reactor windings to earth, as well as insulation resistance of damper to earth should be tested
and meet the requirements of manufacturer and user.
NOTE—Different manufacturers and users may give different suggested values of test voltage and insulation resistance.
In the Chinese case, the test voltage is 2500 V, and insulation resistance should not be lower than 1000 MΩ.
Connection between components of electromagnetic units should be checked and should conform to the
nameplate.
No surface defects that could affect the satisfactory performance in service should be tolerated.
10
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
b) Error measurement should not be replaced by voltage ratio measurement methods with a voltage
ratio tester.
c) A polarity check should be performed simultaneously with error measurement, and the labeling of
each connecting terminal should be checked.
d) Both difference methods and voltage coefficient measurement methods can be applied to accuracy
tests.
e) Tests should be performed on each secondary winding separately except for residual windings. The
access load of tested windings should be between 25% ~ 100% of rated load, and for other
windings the load should be between 0% ~ 100% of rated load. The power factor of the secondary
load should be considered as 1 if there is not any other special requirement given by the user.
f) Tests for the metering winding and the measuring winding (0.2 level and 0.5 accuracy level) should
be performed at 80%, 100%, and 120% of rated voltage or as agreed upon between the
manufacturer and user.
g) Error characteristic measurement of protection windings should be performed at 2%, 5%, and
100% of rated voltage.
h) During measurement, the layout of a high-voltage lead should be as close as possible to actual
operation condition.
NOTE—This test was performed at 80%, 100%, and 105% of rated voltage in the Chinese example.
a) Excitation characteristics and test methods of dampers should follow the requirements of the
manufacturers.
b) Check whether the damper has been connected with the specified secondary winding terminal
correctly.
4.4.11 Low-frequency withstand voltage test on capacitor voltage dividers (optional test)
If needed, the low-frequency withstand voltage test on capacitor voltage dividers should include the
following:
a) 80% of the factory test voltage value should be applied on capacitor voltage dividers and
maintained for 1 min.
b) The capacitance and tanδ should be measured before and after the low-frequency withstand voltage
test. There should be no significant changes.
11
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Insulation resistance between each secondary winding and earth and on secondary windings should be
tested and should meet the requirements of the manufacturer and user.
NOTE—Different manufacturers and users give different suggested values of test voltage and insulation resistance. In
the Chinese example, the test voltage is 2500 V and the insulation resistance should not be lower than 1000 MΩ.
Refer to 8.5 of IEEE Std C57.13-2008 for resistance measurements, with the following addition:
a) Compare the dc resistance of secondary winding with the factory test result when converted to the
same temperature. The difference should not exceed 10%.
b) For CTs with the same batch, model, and specification, the difference of their tested value of the
secondary winding dc resistance should not exceed 10%.
Refer to 7.3 of IEEE Std C57.13.5-2009 for applied voltage tests on secondary windings.
a) The CT used for gate measurement should perform the determination of error test.
b) The polarity check should be performed simultaneously with determination of error, or dc method
should be adopted. The terminal markings should be checked.
c) For multi-transformation ratio windings, measure only the full range error of one transformation
ratio and verify the error at 20% Ir point of the other voltage ratios. The transformation ratio of all
windings should conform to the value given on the nameplate.
12
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
d) For determination of error, the direct method (difference value method) should apply. If the applied
current cannot reach the specified value, the indirect method can be adopted with the precondition
that the error at 20% Ir point has been measured by direct method.
Refer to Clause 9 of IEEE Std C57.13.1-2006 for excitation tests, with the following additions:
a) The test should be carried out when the CT excitation characteristic is required by the relay
protection.
b) If the CT is multi-tap type, the measurement can be taken at the tap in use or the tap with the
minimum transformation ratio. The result should meet the requirement specified by manufacturer
and user.
c) If the test voltage applied is greater than the winding allowable value (4.5-kV peak), the frequency
of the test power supply should be reduced.
The following subclauses based on IEEE Std C37.122-2010 establish the requirements for testing the gas-
insulated switchgear after installation, assembly, and wiring in the field and before placing it into
commercial service.
For details, refer to Annex B of CIGRE WG B3.29 technical brochure [B1] as a practical example based on
the experiences in China, and this standard’s bibliography (Annex E) for standards and publications that
may be useful in implementing this IEEE guide.
Refer to 9.1 of IEEE Std C37.122-2010 for mechanical leakage tests, with the addition that the leakage rate
should conform to following value depending on the agreement between manufacturer and user (see IEC
62271-1:2011 and [B28]): leakage rate < 0.5%/year.
Refer to 9.2 of IEEE Std C37.122-2010 for mechanical gas quality (moisture, purity, and density) tests,
with the following additions:
The moisture content should be determined according to IEEE Std C37.122-2010, IEEE Std C37.100.1-
2007, IEC 62271-203: 2003, and IEC 62271-1: 2011.
Users applying equipment 1000 kV and above should refer to CIGRE WG B3.29 [B1]: the following more
strict moisture value criteria is recommended, since the moisture value corresponds to 876 µL/L at 0.5 MPa
and 568 µL/L at 0.7 MPa.
13
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
CIGRE WG B3.29 [B1] indicates the variation of the criteria between 250 µL/L, 300 µL/L, and 500 µL/L
for apparatus without current-interrupting duties [B30]. The value of 500 µL/L is recommended as a
minimum requirement [B28] and as a reliable criterion that has been verified via the field experiences over
30 years in Japan [B30].
The density of the gas should be measured and verified to be in accordance with the manufacturer’s
nominal rated filling requirements.
Refer to 9.3 of IEEE Std C37.122-2010 for electrical continuity, conductivity, and resistivity tests, with the
following addition: for UHV equipment and system, the resistance should be measured by the dc voltage
application and evaluated as follows [B2], [B28]:
b) The measured resistance value should be 1.2 × Ru or lower, where Ru is defined as resistance
measured in the factory test or before the temperature-rise test in the factory.
Refer to 9.4 of IEEE Std C37.122-2010 for electrical low-frequency ac voltage withstand tests, with the
following additions.
The example of voltage levels and durations of conditioning voltage application is introduced in Figure B.1
of Annex B.
The conditioning voltage application and the 1-min low-frequency voltage withstand test should be
performed after the gas-insulated switchgear has been completely installed and the gas compartments have
been filled to the manufacturer’s recommended nominal rated fill density. A conditioning test before “ac
voltage test followed by PD test” is effective to suppress breakdowns due to the presence of metallic
particles, if any.
Any additional tests may be performed subject to the user-manufacturer agreement. For UHV equipment
and systems, the main circuits may be tested as follows (see IEC 62271-1:2011, [B1], [B2], and [B3]:
As an another option, elimination of the on-site voltage test is possible under the agreement between the
manufacturer and user if a special care is taken in the equipment design and in the quality control during
transportation and on-site assembly in order to keep the same dielectric integrity checked by the test in the
factory. In this case, the test voltage and procedure are as follows [B1] and [B3]:
c) AC voltage test (1 pu-1 h) with PD test (1 pu: operating voltage and commissioning test voltage)
14
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Refer to 9.5 of IEEE Std C37.122-2010 electrical low-frequency ac voltage withstand requirements and
condition tests.
4.6.6 Electrical tests: low frequency ac voltage withstand configurations and applications
(Annex B.2)
Refer to 9.6 of IEEE Std C37.122-2010 for electrical low-frequency ac voltage withstand configuration and
application tests.
4.6.7 Electrical tests: assessment of the ac voltage withstand test (Annex B.2)
Refer to 9.8 of IEEE Std C37.122-2010 for assessment of the ac voltage withstand.
Refer to 9.9 of IEEE Std C37.122-2010 for tests on auxiliary circuits, with the following addition: the
circuits should be checked by withstand voltage test or by insulation resistance measurement as follows
(see IEC 62271-1:2011, [B2], and [B29]):
Refer to 9.10 of IEEE Std C37.122-2010 for mechanical and electrical functional checks and verifications.
Refer to 9.11 of IEEE Std C37.122-2010 for mechanical and electrical test documentation.
On-site acceptance tests for air-insulated grounding switches include the following:
a) Appearance check
b) Dielectric tests on control and auxiliary circuits
c) Mechanical test
15
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Refer to 7.2 of IEC 60694: 2002 for dielectric tests on control and auxiliary circuits with the following
additions:
a) Insulation resistance, measured before applying the voltage withstand test, should be greater than
2 MΩ.
b) Control and auxiliary circuits should withstand power frequency voltage at 2 kV for 1 min. The
value of insulation resistance should not significantly drop after the voltage withstand test.
On-site acceptance tests for disconnecting switches should include the following:
Refer to 7.2 of IEC 60694:2002 for dielectric tests on control and auxiliary circuits, with the following
additions:
a) Insulation resistance, measured before applying the voltage withstand test, should be greater than
2 MΩ.
b) Control and auxiliary circuits should withstand power frequency voltage at 2 kV for 1 min. The
value of insulation resistance should not significantly drop after the voltage withstand test.
Refer to 6.4.1 of IEC 60694: 2002 for measurement of the resistance of the main circuit specifications.
16
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Refer to 7.5 of IEC 60694: 2002 for design and visual inspection specifications.
4.9 Bushings
On-site acceptance tests for UHV bushings should include the following:
a) Visual inspection
b) Tanδ and capacitance measurement
c) Tap withstand voltage
Refer to 9.1 of IEC 60137: 2009 for tanδ and capacitance measurement specifications, with the following
additions:
a) After installation of the transformer and reactor bushings, tanδ and capacitance of the insulation
should be measured at 10 kV while voltage tap (if any) should be short-circuited with the test tap.
b) The deviation between measured capacitance value and nameplate value should be lower than ±5%,
and the value of tanδ should have no obvious difference from the factory test results.
Refer to 7.2.4 of IEEE Std C57.19.00-2004 for tap withstand voltage specifications.
NOTE—For voltage tap, different manufacturers may give different suggested values of test voltage. It is advised to
refer to the product specification or consult the manufacturer before testing.
17
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
4.10 MOSAs
For the procedure followed for field tests, the test method should refer to same kind of tests described in
relevant publications, such as IEEE Std C62.11-2005. The test methods and their descriptions listed below
are applicable for MOSAs.
The insulation resistance should be tested at 5000 V and the tested insulation resistance value should not be
lower than 2500 MΩ.
The insulation resistance should be tested at 2500 V and the tested insulation resistance value should not be
lower than 2000 MΩ.
Total leakage current and resistive leakage current should be measured under operation voltage. The
measured values should meet the requirements of the manufacturer and user.
The appearance of MOSA units should show no visible damage. The MOSAs appearance after installation,
such as the piling order of MOSA units and the shield ring, etc., should be according to the drawing and
instruction manual of the manufacturer.
There should be no damage of the appearance or the script clear and the gauge needle should not be
pointing to zero. The initial number of the counter should be recorded. The lowest current of MOSAs under
the operating voltage should be confirmed by the graduation of the current monitoring device.
18
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
For field tests, the test method should refer to same kind of tests described in relevant publications, such as
IEC 60383-1:1993. The test methods and their descriptions listed below are applicable for suspension
insulators and post insulators.
a) The insulation resistance should be tested at 5000 V. The tested value of insulation resistance of
each piece of suspension insulator should not be lower than 5000 MΩ before installation.
b) For the ac voltage withstand test, the test voltage for the suspension insulator is 60 kV. For the test
method, refer to 14.1 of IEC 60383-1:1993.
The insulation resistance measurement should be performed on a transportation unit with 5000 V before
installation. The value of the measured insulation resistance should not be lower than 5000 MΩ.
NOTE—There is no detailed requirement about insulation resistance and ac voltage withstand tests in IEEE or IEC
standards for UHV on-site acceptance tests. The value provided here is based on the experiences in China.
Test requirements of insulating oil filling into electrical equipment should be as per Table 1.
NOTE—The maximum value of dissipation factor is 0.05% (25 ℃) and 0.3% (100 ℃) in IEEE Std C57.106™-2006 [B28]. Because
of the large quantity of oil in UHV transformers and shunt reactors, it may be difficult to conduct on-site treatment. According to the
Chinese experience, dissipation factor values less than 0.5% (at 90 ℃) after filling oil into the equipment should meet the insulation
requirements.
19
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
5. System commissioning
5.1 General
System commissioning is a necessary characteristic inspection of the new system before it is put into
operation. The commissioning test in this clause is based on engineering experience which was performed
to help ensure the stable and safe operation of the newly constructed UHV system.
The system commissioning test specifies the test items, requirements, and evaluation criteria for the
commissioning of UHV ac transmission systems.
To help ensure the safety of the system and equipment during commissioning, simulation and analysis
should be carried out before the actual commissioning test, including power flow and stability calculation
and electromagnetic transient simulation.
The system commissioning scheme formulations should take simulation results into account. It should
include test items, objectives, contents, procedures, the operation mode of the power system, and safety
measures.
The measurement scheme should be formulated based on simulation results and the commissioning scheme.
It should include the objectives, contents, conditions, instruments, methods, and safety measures.
The system commissioning schedule should be formulated by the dispatching department according to the
system commissioning scheme. It should include the operating authorization, incident management
principle, and protection operation including temporary relay settings.
Items of system commissioning are listed in Table 2. Relevant measurement items are conducted during the
process of system commissioning.
20
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The accuracy of UHV transmission line parameters at rated power frequency is very important to the
simulation analysis of the system commissioning. These parameters provide the basis of short-circuit
current and load flow distribution calculations and choice of reasonable operation mode. The measurement
can verify the insulation and the phase of the newly constructed UHV transmission lines before operation.
The measurement results can help analyze the discrepancy between the measurement parameters and
design parameters and help form operational strategies.
The measurement can be carried out after all the work on the UHV transmission lines has been
completed and the circuit breakers at both ends of UHV transmission lines, isolating switches of
the UHV reactors, and grounding switches have all passed the acceptance inspection and are
switched off.
The other transmission lines that are across or parallel with the UHV transmission lines are out of
service.
Measurement of the induced voltage: Measure the amplitude and phase of induced voltage of phase
to phase and phase to ground. The measured results are used to eliminate the error caused by
induced voltage during parameter measurement and calculation.
Measurement of the insulation resistance: Measure the insulation resistance of phase to phase and
phase to ground. Check the isolation of the UHV transmission lines and whether there are defects
such as a short circuit between phase to ground or phase to phase, etc.
Measurement of the positive sequence impedance: Connect the three-phase power supply at the
rated power frequency to the measuring end of the UHV transmission line with the other end of the
21
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
test line putting on a three-phase short circuit. Measure the phase voltage, phase current, and power
of each phase. Calculate the arithmetical average value of the measured voltage and current and
calculate the algebraic sum of the three-phase power, which is displayed on the low power factor
wattmeter. The positive sequence impedance per kilometer per phase is calculated according to the
measurement results. It can be verified in the current raising from a zero test of the UHV ac
transmission line and the manual single phase to ground fault test.
Measurement of the zero-sequence impedance: Connect the single-phase power supply at the
measuring end of the UHV transmission line with three phase circuits connected together and with
the other end of the test line making a three-phase-to-ground short circuit. Measure the voltage,
current and power. The zero sequence impedance per kilometer per phase is calculated using the
measurement results. It can be verified in the manual single-phase-to-ground fault test.
Measurement of the positive sequence admittance: Connect the three-phase power supply at the
measuring end of the UHV transmission line with the other end of the test line open. Measure
three-phase voltage with a voltage transformer (VT) at the each end of the test line. Calculate the
arithmetical average value of the measured phase voltage and current at both ends of the test line
and calculate the algebraic sum of the three phase power, which is displayed on the low power
factor wattmeter. The positive sequence admittance per kilometer per phase is calculated according
to the measurement results. It can be verified in the test of a UHV ac transmission line with voltage
rising from zero, a switching on/off test of the UHV ac no-load transmission line, and the manual
single phase to ground fault test.
Measurement of the zero-sequence admittance: Connect the single-phase power supply at the head
of the UHV transmission line with a three-phase short circuit and make a three-phase open circuit
at the end of the test line. Measure the three-phase current at the head of the test line and the
voltage of the head to the end of the test line. The zero sequence admittance per kilometer per
phase is calculated according to the measurement results. It can be verified in the test of the UHV
ac transmission line with voltage rising from zero, switching on/off test of UHV ac no-load
transmission line, and the manual single phase-to-ground fault test.
Measurement of the phase to phase coupling capacitance: Connect the single-phase power supply
to the test phase at the measuring end of the UHV transmission line with the other end of the test
line making a three-phase open circuit. Measure the voltage and current of the test phase and the
coupling current of the other two phases. The phase-to-phase coupling capacitance is calculated
according to the measurement results. It can be verified in the test of the UHV ac transmission line
with voltage rising from zero, the switching on/off test of the UHV ac no-load transmission line,
and the manual single phase-to-ground fault test.
Measurement of the phase to phase mutual impedance: Add the single-phase power supply to the
test phase at the head of the UHV transmission line and make a three-phase short circuit to ground
at the end of the test line. Measure the voltage and current of the test phase and the induced voltage
of the other two phases. The mutual impedance is calculated according to the measurement results.
It can be verified in the test of the UHV ac transmission line with voltage rising from zero,
switching the on/off test of UHV ac no-load transmission line, and the manual single phase-to-
ground fault test.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
5.2.2 Test of UHV power transformers with current increasing from zero
This is a performance test on the UHV power transformer before it is put into operation. The aim is to
verify the through-current capability of UHV equipment and the polarity and phase of the CT in a UHV
22
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
power transformer. Also, it can be used to verify whether the relevant relay protections work under normal
conditions.
This test should be performed according to the field conditions and the needs of the user.
Select a generator as the test power supply and connect it to the UHV power transformer. Make
sure the selected generator capacity meets the test requirements.
Install the short-circuit line at the side of current increasing from zero (not the side of the power
supply) of the UHV power transformer. Select its current carrying capacity according to the
calculated value, which should be no less than two times of the calculated value.
Adjust the relevant protection settings according to the system commissioning schedule.
The test of current increasing from zero on the primary side (or secondary side) and the tertiary side
of the UHV power transformer should be carried out in the isolated system.
Test of current increasing from zero on the primary side (or secondary side) of the UHV power
transformer.
Measure the short-circuit impedance of the primary to secondary windings of the UHV power
transformer.
Measure the polarity and phase of the secondary circuit of the CT of the UHV power
transformer.
Measure the infrared temperature of the bus, conducted connectors, circuit breakers, isolating
switches, etc.
Measure the vibration and audible noise of the UHV power transformer when the short-circuit
current is close to the rated value.
Test of current increasing from zero on the tertiary side of the UHV power transformer.
Measure the short-circuit impedance of the primary to secondary (or primary to tertiary)
windings of the UHV power transformer.
Measure the polarity and phase of the secondary circuit of the CT of the UHV power
transformer.
Measure the infrared temperature of the bus, conducted connectors, circuit breakers, isolating
switches, etc.
Measure the vibration and audible noise of the UHV power transformer when the short-circuit
current is at the rated value.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
23
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
5.2.3 Test of UHV ac transmission lines with current increasing from zero
This is a performance test on the UHV ac transmission line before it is put into operation. The aim is to
verify the load-carrying capability of UHV equipment and the polarity and phase of the CT in UHV power
transformer and UHV transmission lines. Also, it can be used to verify whether the relevant relay
protections work in normal conditions.
This test should be performed according to the field condition and the needs of the user.
Select a generator as the test power supply and connect it to the UHV transmission lines. Make sure
the selected generator capacity meets the test requirement.
Install the short-circuit line at the remote end of the UHV transmission line. Select its current-
carrying capacity according to the calculated value, which should be no less than two times the
calculated value.
Adjust the relevant protection settings according to the system commissioning schedule.
Measure the polarity and phase of the secondary circuit of the CT of the UHV power transformer.
Measure the infrared temperature of the bus, conducted connectors, circuit breakers, isolating
switches, etc.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
5.2.4 Test of UHV power transformer with voltage rising from zero
This is a performance test on the UHV power transformer before it is put into operation. The aim is to
verify the insulation of the UHV equipment, mainly the UHV transformer, to verify the voltage phase and
phase sequence of the CVT at each side of the UHV power transformer. Also, it can be used to verify the
operating characteristics of the UHV power transformer, such as excitation characteristics, no-load loss,
harmonic vibration, audible noise, temperature rising, insulation oil, etc. Also, it can be used to verify
whether the relevant relay protections work in normal conditions.
This test should be performed according to the field conditions and the needs of user.
Select a generator as the test power supply and connect it to the UHV power transformer. Make
sure the selected generator capacity meets the test requirements.
Adjust the relevant protection settings according to the system commissioning schedule.
24
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Measure the harmonic spectrum of the three-phase voltage and current of the primary and
secondary sides of the UHV power transformer.
Measure the vibration of the UHV power transformer during voltage rising.
Measure the audible noise of the UHV power transformer during voltage rising. Measure the
background noise level before the transformer is energized. Measure the audible noise level of the
equipment after the transformer is energized at rated voltage.
Measure the amplitude, phase angle, and phase sequence of the secondary voltage of the CVT at
each side of UHV power transformer.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
5.2.5 Test of UHV ac transmission line with voltage rising from zero
This is a performance test on the UHV ac transmission line before it is put into operation. The aim is to
verify the insulation of UHV lines and circuit breakers to verify the polarity and phase of the CT of the
UHV shunt reactor, transformer, and its tertiary connected reactor. Also, it can be used to verify the voltage
amplitude, phase angle, and phase sequence of the CVT of UHV lines.
This test should be performed according to the field condition and the needs of the user.
Select a generator as the test power supply and connect it to the UHV transmission lines. Make sure
the selected generator capacity meets the test requirements.
Make sure the selected generator in the isolated system will not induce self-excitation during the
test based on the analysis.
Switch on/off the tertiary connected reactors of the UHV power transformer according to the
calculation result.
Adjust the relevant protection settings according to the system commissioning schedule.
Measure the amplitude, phase angle, and phase sequence of the current of the UHV transmission
lines.
Measure the amplitude, phase angle, and phase sequence of the voltage of the UHV transmission
lines.
25
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Measure the voltage, current, and reactive power of the UHV shunt reactor and the tertiary
connected reactors.
Measure the vibration of the UHV power transformer during voltage rising.
Measure the audible noise of the UHV power transformer during voltage rising. Measure the
background noise level before the transformer is energized. Measure the audible noise level of the
equipment after the transformer is energized.
Measure the volt-ampere characteristics of the UHV shunt reactor. A high-precision CT should be
installed for the measurement.
Measure the charging power during the process of voltage rising from zero in UHV transmission
lines.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
Because of the nonlinear excitation characteristics of the UHV power transformer core and the periodical
changing of the iron core, harmonics may cause high-amplitude resonance overvoltage while switching
on/off no-load transformers, and the inrush current can be harmful to the relevant relay protections during
the switching. This test aims to verify the function of the circuit breaker to switch on/off the UHV
transformer under operating voltage and to measure the overvoltage and inrush current during the switching.
Also, the function of the UHV transformer protection relay can also be verified. It is usually performed for
newly constructed UHV transformers. For UHV projects for which the test of voltage rising from zero
cannot be performed, this switching on/off test can also verify the UHV transformer operating
characteristics and the voltage phase and phase sequence of the CVT at each side of the UHV power
transformer. Also, it can be used to verify the voltage phase and phase sequence of the CVT of UHV lines.
This test should be carried out respectively by the circuit breakers on the primary and secondary sides of
the UHV power transformer.
Adjust the tap position at the secondary side of the UHV power transformer according to the
commissioning schedule.
Switch on/off the tertiary connected reactors of the UHV power transformer based on the analysis.
Block the single-phase automatic reclosing function of the UHV transmission lines.
Adjust the relevant protection settings according to the system commissioning schedule.
The test can be carried out by switching on/off circuit breakers at primary and secondary sides of
the UHV power transformer five times for each side.
b) Measure the inrush current when the UHV no-load transformer is put into operation by switching
on/off the circuit breakers on the primary side or the secondary side.
26
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
This test aims to verify the function of circuit breakers to switch on/off UHV lines, to measure the
overvoltage during no-load line switching, and to measure the impact on the system operating voltage and
reactive power. Also, the function of UHV line relay protection devices can be verified. And for the UHV
projects where the test of voltage rising from zero cannot be performed, this switching on/off test can also
verify the UHV line insulation and the voltage phase and phase sequence of CVT at each side of UHV
power transformer. This test can also verify the effectiveness of the overvoltage suppression measures,
such as the UHV shunt reactor or the closing resistor of the circuit breaker.
This test should be carried out respectively by the circuit breakers at each end of the UHV transmission line.
Adjust the tap position at the secondary side of the UHV power transformer according to the
system commissioning schedule.
Switch on/off the tertiary connected reactors of the UHV power transformer based on the analysis.
Adjust the relevant protection settings according to the system commissioning schedule.
Tests can be carried out by switching on/off the circuit breakers at each end of the no-load UHV
transmission line three times.
Put the single-phase automatic reclosing function of the UHV transmission lines into service.
Switch off the circuit breaker of A, B, or C phase individually to test single-phase reclosing.
a) Measure the transient voltage and current of the surge arrester when switching on/off UHV no-load
transmission lines. Measure the overvoltage of UHV transmission lines and the neutral point of the
UHV shunt reactor to earth.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
d) Perform a DGA test of the UHV power transformer, UHV shunt reactor, and neutral point
connected reactor
27
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The newly constructed UHV power transformer and transmission lines are required to be put into the
operating system by a synchronization device of the circuit breaker. The process of the UHV equipment
being put into or removed from the operating system is called ring closing (interconnection)/ring opening
(splitting). Ring closing (interconnection)/ring opening (splitting) will impact the operating system,
depending on the differences of voltage and phase angle at each side of the operating point, etc. This is a
common operation in the power system and is necessary to verify the impact of ring closing
(interconnection)/ring opening (splitting) on power, frequency, and voltage of the operating system.
This test should be performed when the UHV transmission lines connect two separate grids, and it should
be carried out respectively by the circuit breakers on the primary and secondary sides of the UHV power
transformer and the circuit breakers at each end of the UHV transmission line.
Tests can be carried out by switching the circuit breaker at each end of the UHV transmission lines
or at the secondary side of the UHV power transformer. If the system to be interconnected is weak
with low short-current capacity, it is suggested that closing (interconnection)/opening (splitting)
test be carried at the secondary side of the UHV power transformer.
The tertiary connected reactors of the UHV power transformer should be switched on/off based on
the analysis.
Adjust the relevant protection settings according to the system commissioning schedule.
Before the actual closing of the circuit breaker, a virtual synchronization ring closing
(interconnection) by switching the circuit breakers at each end of UHV transmission lines or at the
secondary side of UHV power transformer should be taken.
Measure the difference of the voltage amplitude, phase angle, and frequency at each side of
splitting point or interconnection point.
NOTE—All the above measurement results should meet the design requirements of the project within the specified
tolerance as determined by the user.
5.2.9 Induced current and induced voltage test of the double-/multi-circuit UHV ac
transmission lines on the same tower
This test is to verify the switching capability of grounding switches and to measure the voltage and current
induced on an out-of-service transmission line by other on-load circuits that share the same transmission
towers. The measurement result can be used to obtain the coupling characteristics among UHV lines.
This test should be performed for each newly constructed double-/multi-circuit UHV ac transmission line
on the same tower.
Put one of the double-/multi-circuits on the same towers into service and others out of service.
28
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Adjust the relevant protection settings according to the system commissioning schedule.
Tests can be carried out by switching on/off the grounding switches, respectively, once at each end
of the UHV transmission lines that are out of service.
Measure the phase-to-earth voltage at each end of transmission lines that are out of service
(grounding switches are off).
Measure the current at each end of transmission lines that are out of service (grounding switches
are on).
NOTE—All the above measurement results should meet the design requirements of the project within the specified
tolerance as determined by the user.
Reactors connected to the tertiary side of the UHV power transformer by circuit breakers are used for
voltage regulation and reactive power compensation. Because of the large capacity of reactors, their
switching can cause high transient overvoltage and large fluctuation on steady-state voltage. This test aims
to verify the capability of circuit breakers to switch on/off reactors under operating voltage, to measure the
overvoltage at the tertiary side of the UHV power transformer, and to measure the impact on the system
operating voltage. The phase and the polarity of voltage and current of relay protection devices for reactors
can be verified as well.
Adjust the relevant protection settings according to the system commissioning schedule.
The test can be carried out by switching on/off the tertiary connected reactor three times.
Measure the voltage and current at each side of the UHV power transformer.
Measure the voltage and current of the tertiary connected reactor and its neutral point.
Measure the switching overvoltage at the tertiary side of the UHV power transformer.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
Capacitors connected to the tertiary side of the UHV power transformer by circuit breakers are used for
voltage regulation and reactive power compensation. Because of the large capacity of the capacitors, their
switching can cause large inrush transient currents that are very important to check the performance of the
capacitor and its circuit breakers. This test aims to verify the capability of circuit breaker to switch on/off
29
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
the capacitor, to measure the inrush transient current when switching on the capacitor, to measure the
impact on the system operating voltage, and to verify the phase and the polarity of the voltage and current
of relay protection devices for capacitors.
Adjust the relevant protection settings according to the system commissioning schedule.
The test can be carried out by switching on/off the tertiary connected capacitor three times.
Measure the voltage and current at each side of the UHV power transformer.
Measure the voltage and current of the tertiary connected capacitor and its neutral point.
Measure the switching overvoltage at the tertiary side of the UHV power transformer.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
The single phase-to-ground fault occurs most frequently among all line faults in power grids. UHV
transmission lines have the single phase automatic reclosing function installed, and the auto reclosing time
setting depends on the secondary arc current and the recovery voltage after the fault. It is set according to
the simulation results and design parameters of the UHV transmission line. This test aims to verify the
relay protection and single-phase reclosing performance of the UHV transmission lines and the effect of a
neutral point connected reactor of a UHV shunt reactor on restraining secondary arc current.
The installation and commissioning of manual grounding devices should be completed during the
maintenance of transmission lines.
System operation mode and safety precautions should meet the requirements of the system
commissioning schedule.
Adjust the relevant protection settings according to the system commissioning schedule.
The test can be carried out by manual single-phase temporary short circuits grounding.
a) Measure the steady-state voltage and current, active power, reactive power, and frequency of the
operating system before and after the test.
b) Measure the short-circuit current at the single phase-to- ground fault point.
d) Measure the recovery voltage of the UHV transmission line during the short-circuit fault.
30
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
f) In order to measure the transient response characteristics of the UHV CVT, measure the secondary
voltage of the CVT on UHV transmission lines and the voltage of the bushing tap of the UHV
shunt reactor. Check the difference between them.
g) Measure the voltage and current of the reactor connected at a neutral point of the UHV shunt
reactor.
h) Measure the transient voltage of the UHV bus, transformer, shunts reactor, and the tertiary
connected capacitor or reactor.
i) Measure the transient voltage and current of the surge arresters of UHV transmission lines.
j) Measure the induced voltage at the insulation end of UHV ac overhead earthing lines.
Measurement should not be taken under rainy conditions.
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
k) Record the atmosphere conditions of the test location such as wind speed, temperature, humidity,
etc.
l) Perform a DGA test of the UHV transformer, UHV shunt reactor, and the neutral point connected
reactor.
During UHV system operation, incidents such as line trip, generator trip, or a fault on transmission lines
may occur and cause disturbance to the power, frequency, and voltage. Before system commissioning,
simulation studies should be carried out under various abnormal conditions to assess the dynamic
characteristic and the capability of the anti-disturbance of the UHV system. Disturbance tests such as
tripping the generator or transmission line should be performed to verify the simulation results according to
the measurement data. This could also provide operating data and experience for the dispatching center and
help to improve the accuracy of the simulation studies.
This test should be performed for the newly constructed UHV projects or UHV lines interconnecting two
grids.
System operation mode and safety precautions should meet the requirements of the system
commissioning schedule.
The test can be carried out by tripping a generator, transmission line, etc.
Measure the voltage and current at each end of the UHV transmission line.
Measure the system frequency, active power, and reactive power of the UHV transmission line and
other relevant lines.
31
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
NOTE—All the above measurement results should meet the design requirements of the project within specified
tolerance as determined by the user.
The UHV project has characteristics of long distance and large power transmission capacity compared with
EHV transmission lines. This test aims to verify the operating characteristics of equipment under normal
operation load. The harmonic level of the UHV power system and the surrounding environment of the
UHV substation and line can be measured, which helps to collect on-site data and make full assessment on
the UHV project. It also can verify control strategies of the UHV project such as power flow control and
voltage control. It can provide operating data and experience for the dispatching center and help to verify
the simulation results according to the measurement data to improve the accuracy of the simulation studies.
The UHV system should be subject to operate continuously under normal opeation load conditions.
a) Measure the voltage, current, harmonics, frequency, power angle, active power, and reactive power
of the UHV transmission lines.
b) Measure the vibration of the UHV power transformers and UHV shunt reactors. Multi-point
vibration measurement should be taken for each transformer and reactor.
c) Select a right location for the measurement of the sag along the UHV transmission line.
d) Measure the infrared temperature of the bus, connectors, circuit breakers, isolating switches, etc.
e) Measurement of the electric and magnetic field inside/outside the substation test should be carried
out when the air humidity is not greater than 80%. For electric-field measurement, the system
voltage should not be lower than the rated voltage, and for that of the magnetic field, the
transmitted power should not be lower than 30% of the rated power.
f) Measure the audible noise inside/outside the substation. Measurement should not be taken under
rainy conditions or conditions when wind speed exceeds 5 m/s. Audible noise measurement inside
and outside the substation should be taken under rated transformer load conditions. Audible noise
measurement of the transmission line should be taken when the line voltage is not lower than the
rated voltage.
g) Measure the radio interference inside/outside the substation. Measurement should not be taken
under rainy conditions. The location for measurement should be far away from transmission line
transposition, intersection, and corner, and should be 10-km away from the ac substation or at least
2 km under special conditions.
h) Measure the induced voltage at the insulation end of UHV ac overhead grounding lines.
Measurement should not be taken under rainy conditions.
NOTE—All of the above measurement results should meet the domestic laws, regulations and standards relevant to
environmental protection and occupational health as well as project design requirements.
i) Perform a DGA test of the UHV power transformer, UHV shunt reactor and neutral connected
reactor.
32
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Annex A
(informative)
The UHV transformer in China has two parts: the main part of the transformer and the regulating part. The
schematic connection diagram of the UHV transformer in China is shown in Figure A.1. The main
transformer can be connected to the voltage regulating and compensating transformer as a complete
transformer and can also be used independently. The primary parameter of the transformer is described as
follows:
Type: single-phase, oil-immersed, auto transformer with no-load (de-energized) tap changer.
Rated power: 1000 MVA/ 1000 MVA/ 334 MVA.
Rated voltage: 1050/ 3 kV/ 525/ 3 kV/ 110 kV.
Tapped winding: 525/ 3 kV (tapping range ±5%).
Connection symbol: Ia0I0.
Rated frequency: 50 Hz.
Tests of the main, voltage regulating, and compensating transformers are carried out individually and then
on complete assembly.
33
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Ratio tests
Polarity check
Insulation resistance test between each winding to earth and between windings including
bushing
Tests on bushing
DGA tests
IVPD
FRA
Voltage regulating transformer and compensating transformer tests include the following:
Ratio tests
Polarity check
Insulation resistance test between each winding to earth and between windings including
bushing
Tests on bushings
34
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
DGA tests
IVPD
FRA
Tests for the main transformer with voltage regulating and compensating transformer together
include the following:
Ratio tests
a) The test voltage was applied to the neutral point and 110-kV winding while the partial discharge
was monitored.
b) The test voltage value was 80% of the factory test value and the time duration was 1 min. The
values are listed in Table A.1.
d) The separate source ac voltage test was made with single-phase alternating voltage as nearly as
possible on a sine-wave form and at a frequency not lower than 80% of the rated frequency. The
peak value of voltage was measured. The peak value divided by 2 was equal to the test value.
35
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
a) During the whole application of the test voltage, partial discharges were monitored.
1) For the partial discharge measurement, the voltage was applied according to the following
procedure:
ii) Raised the voltage to 1.1 Um/ 3 and held there for a duration of 5 min.
iii) Raised the voltage to U2, and held there for duration of 5 min.
iv) Raised the voltage to U1, if the test voltage frequency was equal to or lower than the
doubled rated frequency and the withstand time was 60 s. When the test voltage
frequency was greater than double of the rated frequency, the withstand time was:
rated frequency
120 × ( s ) , but not lower than 15 s.
test frequency
v) Reduced the voltage without interruption to U2 and held there for at least 60 min with
partial discharge measured every 5 min.
vi) Reduced the voltage to 1.1 Um/ 3 and held there for a duration of 5 min.
vii) Reduced the voltage to a value below one-third of U2 before switching off.
2) When performing the PD test of the main transformer, the test voltages to earth were:
i) U1=1.5 Um/ 3 .
3) When performing the PD test of voltage regulating transformer and compensating transformer,
the test voltages to earth were:
i) U1=1.7 Um/ 3 .
4) The partial discharge values were observed and evaluated according to IEC 60076-3: 2000.
i) Measurements were carried out at the line terminals of all windings. For an auto-
connected pair of windings, the higher and lower voltage line terminals were measured
simultaneously.
36
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
ii) The measuring channel from each terminal used was calibrated with repetitive impulse
between the terminal and earth, while this calibration is used for the evaluation of
readings during the test. The apparent charge measured at a specific terminal of the
transformer, with appropriate calibration, referred to the highest steady-state repetitive
impulses. Occasional bursts of high partial discharge level were disregarded. Continuous
discharges for any length of time occurring at irregular intervals can be accepted, as long
as the value is lower than the specified one and there is no steadily increasing tendency.
When there is abnormal discharge pulse, the ultrasonic monitoring was added for
diagnostic purpose and evaluation.
iii) Before and after the application of test voltage, the background noise level was recorded
on all measuring channels.
iv) During increase of the test voltage up to level U2 and reduction from U2 down again,
possible inception and extinction voltages for partial discharge were noted.
Measurement of the apparent charge was taken at 1.1 Um/ 3 .
v) A reading was taken and noted during the first period at voltage U2, No apparent charge
values are specified for this period.
During the entire second period at test voltage U2, the partial discharge level was continuously observed
and readings were recorded every 5 min.
rated frequency
A = 5 min, B = 5 min, C = 120 × (s ) , D = 60 min, E = 5 min.
test frequency
NOTE—The IVPD test of main transformer and voltage regulating transformer and compensating transformer is
carried out separately before connection. Figure A.2 is the voltage energizing sequence of partial discharging test for
the main transformer.
37
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
ii) During the long duration test at U2, the continuous level of partial discharges of the main
transformer met the following requirements:
iii) The continuous level of partial discharges of voltage regulating transformers and
compensating transformers does not exceed 300 pC at low voltage terminal
iii) The partial discharge behavior shows no continuously rising tendency at U2. Occasional
high bursts of non-sustained nature were disregarded.
iv) The continuous level of apparent charges does not exceed 100 pC at 1.1 Um/ 3 .
38
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Annex B
(informative)
a) The field dielectric test of gas-insulated switchgear filled with SF6 gas to the rated pressure was
performed after the installation and all other field commissioning tests had successfully passed.
Some components were be isolated in the test due to a higher charge current or limitations of test
voltage for these components.
b) The inlet and outlet of gas-insulated switchgear were disconnected and maintained sufficient
insulating distance. The connection of a MOSA to main circuits was done separately. For
electromagnetic voltage transformers, consultation with the manufacturer to determine whether to
perform the main circuit dielectric test is advised.
c) During the test, all CTs in gas-insulated switchgear had their secondary winding short-circuited and
grounded.
d) The test was conducted for one unit of gas-insulated switchgear. The unit is a section of the entire
gas-insulated switchgear, which encloses the circuit breaker, disconnecting switches, grounding
switches, CT, bus, etc. The length of the unit for test may be different than that in the factory and
the field, e.g., 20 m and 200 m. For the sections under test, all the disconnecting switches were
closed and all the grounding switches were opened. Grounding switches of other sections not under
test were closed.
39
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
e) The insulation resistance of each phase conductor to earth was measured before performing a low-
frequency withstand test at voltage not lower than 2500 V.
1) The test procedure was determined by consultation between the user and the manufacturer
based on the equipment condition on-site and design conditions of the gas-insulated
switchgear.
2) The low-frequency series resonance devices and variable-frequency series resonance devices
can be used for test power supplies. The test frequencies were from 10 Hz to 300 Hz.
3) The low-frequency withstand voltage Uf was 80% of the factory test voltage for 1 min.
NOTE 1— According to IEEE Std C37.122.1™-1993, a conditioning procedure is often used during which
low-frequency voltage is applied in gradually increasing levels, since the most common defect results from
free-conducting particles, and these are able to move under low frequency excitation. Figure B.1 shows an
example of a test procedure which has been used in gas-insulated switchgear. Conditioning tests (for the time
duration of “A” and “B”) were performed before a low-frequency withstand voltage test (for the time duration
of “C”). It was noted that conditioning is somewhat dependent on the design of gas-insulated switchgear,
especially the nature and location of low-field regions for trapping particles as indicated in
IEEE Std C37.122.1-1993.
NOTE 2— The duration of each step in Figure B.1 is chosen based on factory test experiences. To avoid any
possible degrading of the insulation caused by high test voltage, the duration of Step B is reduced.
40
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
5) Specified test voltage was applied between each phase conductor and enclosure. The test was
conducted on one phase at a time and other phases were connected to the grounding enclosure.
6) Test voltage was applied to each component at least once. While formulating the test program,
attention was paid to reduce the repetition test time of solid insulation.
7) If it was noticed that interrupter units of the circuit breakers and/or disconnecting switches
had been damaged or dismounted during transportation or installation, the low-frequency
withstand voltage test was performed between interrupter units.
8) If each component of the gas-insulated switchgear had withstood the prescriptive voltage of
the test procedure with no disruptive discharge, it was considered that the whole gas-insulated
switchgear had successfully passed the test.
9) If any breakdown happened during the test, a repeat test was carried out. If the equipment can
withstand prescriptive test voltage a second time, the former discharge failure can be
considered a self-restored discharge, and the low-frequency withstand test was considered
passed. If the repeat low-frequency withstand test failed, the damaged compartment was
opened and checked. Before re-performing the low-frequency withstand voltage test,
necessary restoration measures were adopted.
g) PD tests were carried out after the low-frequency withstand tests were completed or at the same
time as the conditioning test. In order to make PD the tests effective, interference caused by the
power source and environment was reduced, and the corona of the high-voltage wire was avoided.
The following methods are recommended for PD tests.
1) Ultra-high frequency (UHF) method. The UHF method enables the detection of internal
defects by analyzing electromagnetic waves generated by partial discharges in gas-insulated
switchgear. The chosen frequency is usually in the range between 300 MHz and 1.5 GHz. The
electromagnetic signal was preferably obtained by sensors for gas-insulated switchgear, e.g.,
internal sensors.
2) Acoustic method. The acoustic method can detect the discharge by receiving the ultrasonic
signal through acoustic sensors placed on the gas-insulated switchgear enclosure. The
measuring frequency is usually in the range between 20 kHz and 150 kHz.
41
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Annex C
(informative)
C.1 Background
The simulation study for system commissioning is the necessary technical basis for ensuring system
commissioning safety. It consists of two parts: the electromagnetic transient analysis and the power flow
and stability analysis. The electromagnetic transient analysis focuses on the overvoltage and over-current
issues for each commissioning item, such as main electrical equipment switching on/off tests, manual
single phase-to-ground tests, etc. Through the simulation, the operation state of the equipment is estimated
and the safety measures for the test items are put forward. The power flow and stability analysis focuses on
system stability characteristics, control strategies on power flow and system voltage, and also safety
measures for system stability. Through the results, the reasonable operation modes of the test power system
for each commissioning item can be selected, and the stability of the operating power system can be
improved.
The contents of the electromagnetic transient analysis on test of voltage rising from zero are as follows:
The contents of the electromagnetic transient analysis on test of current increasing from zero are as follows:
The maximum current of generator, transformer and transmission lines and other equipment
Steady state voltage of the generator, each bus and line side of ac substation
Transient voltage and current under abnormal conditions
Safety precautions recommendation
The contents of the electromagnetic transient analysis on switching on/off test of no-load UHV power
transformers are as follows:
42
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The contents of electromagnetic transient analysis on the switching on/off test of the UHV ac no-load
transmission line are as follows:
Switching overvoltage of neutral point of the ac substation, the transmission lines and the UHV
shunt reactor
The contents of electromagnetic transient analysis on ring closing (interconnection)/ring opening (splitting)
of the UHV system test are as follows:
The contents of electromagnetic transient analysis on the induced current and induced voltage test of the
double-/multi-circuit UHV ac transmission lines on the same tower are as follows:
Induced voltage of outaged transmission lines with a grounding switch on both sides being
switched off
Induced voltage and induced current of outaged transmission lines with a grounding switch on one
side being switched off
Induced current of outaged transmission lines with a grounding switch on both sides of the
transmission line being switched on
The contents of electromagnetic transient analysis on the switching on/off test of tertiary connected
capacitors are as follows:
43
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The contents of electromagnetic transient analysis on the switching on/off test of tertiary connected reactors
are as follows:
The contents of electromagnetic transient analysis on artificial single phase-to-ground fault tests are as
follows:
The contents of electromagnetic transient analysis on system dynamic disturbance and normal operation
test are as follows:
C.3 Power flow and stability analysis contents for commissioning system
The contents of power flow and stability analysis on power grid characteristics of the commissioning
system are as follows:
The contents of power flow and stability analysis on tests of voltage rising from zero and current increasing
from zero are as follows:
Power flow and stability analysis and operational mode arrangement of the main system after the
test system is isolated.
44
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Analysis of terminal voltage of the generator and voltage of the relevant bus of the isolated system
Analysis of reactive power of the generator and transmission lines of the isolated system
The contents of the power flow and stability analysis on the switching on/off test of no-load
transformer/transmission line are as follows:
Analysis of system voltage change before and after switching the on/off no-load transformer/
transmission line
The contents of the power flow and stability analysis on ring closing (interconnection)/ring opening
(splitting) test are as follows:
The contents of the power flow and stability analysis on switching on/off test of tertiary connected
capacitor/reactor are as follows:
Analysis of the system voltage change before and after switching on/off the tertiary connected
capacitor (reactor)
The contents of the power flow and stability analysis on the artificial single phase-to-ground fault test are
as follows:
The contents of the power flow and stability analysis on the system dynamic disturbance test are as follows:
45
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The contents of the power flow and stability analysis on the normal test are as follows:
46
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Annex D
(informative)
Figure D.1 is a simplified diagram of the artificial single phase-to-ground fault test.
Figure D.2 is a measurement diagram of the artificial single-phase to ground fault test.
Table D.1 provides instructions for the measurement wiring depicted in Figure D.2.
Figure D.3 is a diagram of the measurement equipment.
Figure D.4 shows the short-circuit current.
Figure D.5 shows the secondary-arc current.
Figure D.6 shows the line recovery voltage and neutral-connected reactor voltage.
Table D.2 lists the field test results of secondary arc current and recovery voltage during a manual
single-phase grounding test.
Shunt
reactor Grounding
point
110kV Neutral 110kV
reactor
Reactor
47
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
48
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
49
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
50
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Table D.2—Field test results of secondary arc current and recovery voltage
during artificial single phase-to-ground fault test
Primary short
Secondary
circuit current /kA Max recovery Secondary arc
Test line current (peak
Peak Rms voltage (peak extinction time
(single circuit line) value)
value value value) /kV /ms
/A
(kA) (kA)
beating wave
14.5
Changzhi-Nanyang 10.4 4.6 24.5 for trough 118
(after fault 105 ms)
145 for crest
51
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The switching on/off test of on-load UHV transformers is illustrated by the following:
Figure D.7 is a simplified diagram of the switching on/off test of no-load UHV power transformers.
Figure D.7—Simplified diagram of switching on/off test of no-load UHV power transformer
52
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
The switching on/off test of tertiary connected capacitors is illustrated by the following:
Figure D.8 is a simplified diagram of the switching on/off test of tertiary connected reactors.
53
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Figure D.9 provides locations of substation and transmission line audible-noise measurement points.
A
House2 N
W E
3 2
1 S
4 13
12
D
5 Substation 11
B
6
Hospital
10
7 8 9 school
C
House1
54
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
Annex E
(informative)
Bibliography
Bibliographical references are resources that provide additional or helpful material but do not need to be
understood or used to implement this standard. Reference to these resources is made for informational use
only.
[B1] CIGRE WG B3.29, Technical Brochure No. 562, 2013, Field tests for UHV substations. 7
[B2] CIGRE WG B3.22 Technical Brochure No. 400, 2009, Technical requirements for substations
exceeding 800 kV.
[B3] CIGRE WG C4.302, Technical Brochure, No. 360, 2008, Insulation coordination related to internal
insulation of gas-insulated systems with SF6 and N2/SF6 gas mixtures under ac condition.
[B4] IEC 60044-1:2003, Instrument transformers—Part 1: Current transformers. 8
[B5] IEC 60076-6:2007, Power transformers—Part 6: Reactors.
[B6] IEC 60076-10:2002, Power transformers—Part 10: Determination of sound levels.
[B7] IEC 60099-4:2004, Surge arresters—Part 4: Metal-oxide surge arresters without gaps for a.c. systems.
[B8] IEC 60129:2000, Alternating current disconnectors and earthing switches.
[B9] IEC 60156:1995, Insulating liquids—Determination of the breakdown voltage at power frequency—
Test Method.
[B10] IEC 60247:2004, Insulating liquids—Measurement of relative permittivity, dielectric dissipation
factor (tanδ) and d.c. resistivity.
[B11] IEC 60270:2000, High-voltage test techniques—Partial discharge measurements.
[B12] IEC 60296:2003, Fluids for electrotechnical applications—Unused mineral insulation oils for
transformer and switchgear.
[B13] IEC 60376:2005, Specification of technical grade sulfur hexafluoride (SF6) for use in electrical
equipment.
[B14] IEC 60567:2011, Oil-filled electrical equipment—Sampling of gases and of oil for analysis of free
and dissolved gases—Guidance.
[B15] IEC 60815-1:2008, Selection and dimensioning of high-voltage insulators intended for use in
polluted conditions—Part 1: Definitions, information and general principles.
[B16] IEC 60815-2:2008, Selection and dimensioning of high-voltage insulators intended for use in
polluted conditions—Part 2: Ceramic and glass insulators for a.c. systems.
[B17] IEC 60815-3:2008, Selection and dimensioning of high-voltage insulators intended for use in
polluted conditions—Part 3: Polymer insulators for a.c. systems.
[B18] IEC 61462:2007, Composite hollow insulators—Pressurized and unpressurized insulators for use in
electrical equipment with rated voltage greater than 1000 V—Definitions, test methods, acceptance criteria
& design recommendations.
7
CIGRE publications are available at: http://www.e-cigre.org/.
8
IEC publications are available from the Sales Department of the International Electrotechnical Commission, 3 rue de Varembé, PO
Box 131, CH-1211, Geneva 20, Switzerland (http://www.iec.ch/). IEC publications are also available in the United States from the
Sales Department, American National Standards Institute, 25 West 43rd Street, 4th Floor, New York, NY 10036, USA
(http://www.ansi.org).
55
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
IEEE Std 1861-2014
IEEE Guide for On-Site Acceptance Tests of Electrical Equipment and System Commissioning of 1000 kV AC and Above
9
Available at: http://www.cigre.org/content/download/16997/680451/.../B3_213_2012.pdf
56
Copyright © 2014 IEEE. All rights reserved.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.
I
EEE
st
andards
.i
eee.
org
Phone:+17329810060 Fax:+17325621571
©IEEE
Authorized licensed use limited to: IEEE Xplore. Downloaded on December 11,2014 at 18:40:43 UTC from IEEE Xplore. Restrictions apply.