500+ Time and Work Question & Answers Free PDF - Download Now@www - Studywale.co
500+ Time and Work Question & Answers Free PDF - Download Now@www - Studywale.co
co
Index
Foreword ................................................................................... 1
Preface ....................................................................................... 3
Introduction ............................................................................... 5
Chapter - 12
There is a definite relationship between Time and Work. In this concept, there are only three factors:
Time taken to complete a certain job
Unit of work done
Number of persons doing the job
Example 1: 10 men can cut 8 trees in 16 days. In how many days can 6 men cut 10 trees?
Solution: This is a very simple example. You are given:
W1 = 8
W2 = 10
M1 = 10
M2 = 6
D1 = 16
D2 = ?
Using formula,
= ×
= ×
⇒D2 = 33.3
Concept of efficiency
This means, "How much work one person can do in one day (expressed in percentage)"
For example: A person can do a job in 2 days
⇒ He can do 50% work in one day
Therefore, his efficiency will be 50%
Just a 2-step concept
This concept involves two steps to calculate efficiency:
Example 2: If a person can complete his work in 5days. What will be his efficiency?
Solution: Number of days a person take to complete his work = 5
⇒ He is doing 1/5 th work per day (converted into fraction)
Convert it into percentage:
100/5 = 20%
Therefore, his efficiency is 20%.
Summarizing, If a person can do his job in n days, efficiency will be
Efficiency = %
Note: Negative efficiency cancels the positive efficiency
For Example: Positive efficiency = 5%
Negative efficiency = 1.5%
Net efficiency = 5- 1.5 = 3.5%
As we all know, in competitive exams time management is very important. I suggest you to learn the
fractions till 15.
Example 3: A can do a job in 10 days. B can do a job in 5 days. In how many days they can complete
the job if they work together?
Example 4: A and B together can do a job in 4 days. If A can do job in 12 days if he works alone, then
how many days B alone take to complete the job?
Example 5: A and B can do job in 8 days. B and C can do same job in 12 days. A, B and C together can
do same job in 6 days. In how many days A and C together can complete the job?
Trick
One simple technique is using days in denominator while solving questions. For example, A can do a
job in 3 days and B can do the same job in 6 days. In how much time they can do the job together.
You need to understand one simple concept - If A can do a job in 10 day then in one day A can do
1/10th of job.
Solution - A's efficiency = 20%, B's efficiency = 10%. If they work together they can do 30% of the job
in a day. To complete the job they need 3.33 days.
Question 2 - A is twice as efficient as B and can complete a job 30 days before B. In how much they
can complete the job together?
Question 3 - A tank can be filled in 20 minutes. There is a leakage which can empty it in 60 minutes.
In how many minutes tank can be filled?
Solution -
Method 1
⇒ Efficiency of filling pipe = 20 minutes = 1/3 hour = 300%
⇒ Efficiency of leakage = 60 minutes = 100%
We need to deduct efficiency of leakage so final efficiency is 200%. We are taking 100% = 1 Hour as
base so answer is 30 minutes.
Method 2
⇒ Efficiency of filling pipe = 100/20 = 5%
⇒ Efficiency of leakage pipe = 100/60 = 1.66%
⇒ Net filling efficiency = 3.33%
So, tank can be filled in = 100/3.33% = 30 minutes
Question 4 - 4 men and 6 women working together can complete the work within 10 days. 3 men
and 7 women working together will complete the same work within 8 days. In how many days 10
women will complete this work?
Question 5 - A and B together can complete a task in 20 days. B and C together can complete the
same task in 30 days. A and C together can complete the same task in 30 days. What is the
respective ratio of the number of days taken by A when completing the same task alone to the
number of days taken by C when completing the same task alone?
Exercise - 12
1) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the
fraction of the work that is left is:
a) 1/4 b) 1/10 c) 7/15
d) 8/15 e) None of these
2) A can lay railway track between two given stations in 16 days and B can do the same job in
12 days, with help of C, they did the job in 4 days only. Then, C alone can do the job in:
a) 9 b) 9 c) 9
d) 10 e) None of these
3) A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can
A do the work if he is assisted by B and C on every third day?
a) 12 days b) 15 days c) 16 days
d) 18 days e) None of these
4) A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than
B. Working together, they can do it in:
a) 20 days b) 22 c) 25 days
d) 30 days e) None of these
5) A alone can do a piece of work in 6 days and B alone 8 days. A and B undertook to do it for
Rs.3200. With the help of C, they completed the work in 3 days. How much is to be paid to
C?
a) Rs.375 b) Rs.400 c) Rs.600
d) Rs.800 e) None of these
6) If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the
same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
a) 4 days b) 5 days c) 6 days
d) 7 days e) None of these
7) A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C
together can do it in 2 hours. How long will B alone take to do it?
a) 8 hours b) 10 hours c) 12 hours
d) 24 hours e) None of these
8) A can do a certain work in the same time in which B and C together can do it. If A and B
together could do it in 10 days and C alone in 50 days, then B alone could do it in:
a) 15 days b) 20 days c) 25 days
d) 30 days e) None of these
9) A does 80% of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days. How long B alone would take to do the whole work?
a) 23 days b) 37 days c) 37
d) 40 days e) None of these
10) A machine P can print one lakh books in 8 hours, machine Q can print the same number of
books in 10 hours while machine R can print them in 12 hours. All the machines are started at
9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete
work. Approximately at what time will the work (to print one lakh books) be finished?
a) 11:30 A.M. b) 12 noon c) 12:30 P.M.
d) 1:00 P.M. e) None of these
11) A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days
and left the job. In how many days, A alone can finish the remaining work?
a) 5 b) 5 c) 6
d) 8 e) None of these
12) 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete
it in 10 days. In how many days will 10 women complete it?
a) 35 b) 40 c) 45
d) 50 e) None of these
13) A and B can together finish a work 30 days. They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work. In how many days A alone can
finish the work?
a) 45 b) 50 c) 54
d) 60 e) None of these
14) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8
days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how
many days can they complete the work?
a) 5 b) 5 c) 6
d) 6 e) None of these
15) 10 women can complete a work in 7 days and 10 children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
a) 3 b) 5 c) 7
d) Data inadequate e) None of these
16) X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone
and then after 4 days Y joined him till the completion of the work. How long did the work
last?
17) A is 30% more efficient than B. How much time will they, working together, take to complete
a job which A alone could have done in 23 days?
a) 11 days b) 13 days c) 20
d) Data inadequate e) None of these
18) Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a
computer, while Kumar takes 5 hours to type 40 pages. How much time will they take,
working together on two different computers to type an assignment of 110 pages?
a) 7 hours 30 minutes b) 8 hours c) 8 hours 15 minutes
d) 8 hours 25 minutes e) None of these
19) A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together,
they will complete the same work in:
a) day b) day c) 3 ]
d) 4 days e) None of these
20) Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The
number of days taken by Tanya to do the same piece of work is:
a) 15 b) 16 c) 18
d) 25 e) None of these
21) A takes twice as much time as B or thrice as much time as C to finish a piece of work.
Working together, they can finish the work in 2 days. B can do the work alone in:
a) 4 days b) 6 days c) 8 days
d) 12 days e) None of these
22) A and B can complete a work in 15 days and 10 days respectively. They started doing the
work together but after 2 days B had to lea0ve and A alone completed the remaining work.
The whole work was completed in:
a) 8 days b) 10 days c) 12 days
d) 15 days e) None of these
23) A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days
and C and A in 20 days. They all work together for 10 days when B and C leave. How many
days more will A take to finish the work?
a) 18 days b) 24 days c) 30 days
d) 36 days e) None of these
24) A works twice as fast as B. If B can complete a work in 12 days independently, the number of
days in which A and B can together finish the work in:
a) 4 days b) 6 days c) 8 days
d) 18 days e) None of these
25) Twenty women can do a work in sixteen days. Sixteen men can complete the same work in
fifteen days. What is the ration between the capacity of a man and a woman?
a) 3 : 4 b) 4 : 3 c) 5 : 3
d) Date inadequate e) None of these
26) A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C
together can finish it in 6 days. A and C together will do it in:
27) A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are
forced to leave after 3 days. The remaining work was done by A in:
a) 5 days b) 6 days c) 10 days
d) 10 e) None of these
28) X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?
a) 13 b) 15 days c) 20 days
d) 26 days e) None of these
29) A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be
done by A alone in:
a) 9 b) 11 days c) 12
d) 16 e) None of these
30) P is thrice as efficient as Q and is therefore able to finish a piece of work in 60 days less than
Q. Find the time in which P and Q can complete the work individually.
a) 90 days, 30 days b) 60 days, 20 days c) 65 days, 30 days
d) 85 days, 90 days e) None of these
31) A tub can be filled in 20 minutes but there is a leakage in it which can empty the full tub in 60
minutes. In how many minutes it can be filled?
a) 10 minutes b) 30 minutes c) 40 minutes
d) 25 minutes e) None of these
32) A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working
together they will complete the whole work?
a) 10.5 b) 8 c) 8.4
d) 9 e) None of these
33) A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8
days more than A, what is the number of days taken by A to finish the whole work, alone?
a) 4 b) 2 c) 12
d) 16 e) None of these
34) Aman can do a piece of work in 14 days, while Suneeta can do the same work in 21 days.
They started the work together but 3 days before the completion of the work, Aman left the
work. The total number of days to complete the work is :
a) 7 b) 8.5 c) 5
d) 10 e) None of these
35) Karan can do a work in 10 days while Sohan can do the same work in 20 days. They started
work together. After 3 days Karan left the work and Sohan completed it. For how many days
Sohan worked alone more than the number of days required when both worked together?
a)4 b) 3 c) 2
d) 3 e) None of these
36) A and B undertook a work for Rs.350. A got Rs.150 more than that of B, when they worked
together. B takes 9 days more than A, when they work individually. In how many days A and
B working together can do the whole work:
a) 5 b) 4 c) 4
d) 5 e) None of these
37) When A, B and C are deployed for a task, A and B together do 70% of the work and B and C
together do 50% of the work. Who is most efficient?
a) a b) b c) c
d) Data inadequate e) None of these
38) A contractor undertook a work to complete in 60 days. But just after 20 days he observed that
only th of the project work had been completed. To complete the work in time (i.e., in rest
days) minimum how many workers he had to increase, if there were initially 75 workers were
deployed for the task?
a) 25 b) 50 c) 75
d) Data inadequate e) None of these
39) If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of
work will be done by 1 man, 1 woman and 1 boy in :
a) 48 days b) 36 days c) 45 days
d) Data inadequate e) None of these
40) A contractor undertook to complete the work in 40 days and he deployed 20 men for his
work. 8 days before the scheduled time he realized that 1/3rd of the work was still to be done.
How many more men were required to complete the work in stipulated time?
a) 16 b) 15 c) 20
d) 25 e) None of these
41) B and C are equally efficient, but the efficiency of A is half of each B and C. A and B started
a work and 3 days later C joined them. If A alone can do the work in 14 days, then in how
many more days the work will be completed?
a) 1 b) 2 c) 3
d) 4.5 e) None of these
42) A and B together can complete a piece of work in 4 days. If A alone can complete the same
work in 12 days, in how many days can B alone complete that work?
a) 6 days b) 12 c) 8 days
d) 9 days e) None of these
43) 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 boys can finish the
same work in 5 days. Also 2 men and 3 women can finish the same work in 5 days. In how
many days 1 man, 1 woman and one boy can finish the work, at their double efficiency?
a) 4 b) 4 c) 3
d) Data inadequate e) None of these
44) A and B undertake to do a piece of work for Rs.600. A alone can do it in 6 days while B alone
can do it in 8 days. With the help of C, they finish it in 3 days. Find the share of each.
a) Rs.80 b) Rs.75 c) Rs.90
d) Rs.82 e) None of these
45) Tap A can fill the empty tank in 12 hours, but due to a leak in the bottom it is filled in 15
hours, if the tank is full and then tap A is closed then in how many hours the leak can empty
it?
a) 45 hours b) 48 hours c) 52 hours
d) 60 hours e) None of these
46) A is twice as good a workman as B and together they finish a piece of work in 18 days. In
how many days will A alone finish the work?
a) 72 days b) 30 days c) 27 days
d) 32 days e) None of these
47) Pipe A basically used as inlet pipe and pipe B is used as outlet pipe. Pipes A and B both are
opened simultaneously, all the time. When pipe A fills the tank and B empty the tank, it will
take double the time than when both the pipes fill the tank. When pipe B is used for filling the
tank, its efficiency remains constant. What is the ratio of efficiency of pipe A and pipe B
respectively?
a) 3 : 1 b) 5 : 2 c) 1 : 3
d) 3 : 2 e) None of these
48) 45 men can complete a work in 16 days. Six days after they started working. 30 more men
joined them. How many days will they now take to complete the remaining work?
a) 18 days b) 12 days c) 9 days
d) 6 days e) None of these
49) Two pipes A and B can fill a cistern in 15 hours and 10 hours respectively. A tap C can empty
the full cistern in 30 hours. All the three taps were open for 2 hours, when it was remembered
that the emptying tap had been left open. It was then closed. How many hours more would it
take for the cistern to be filled?
a) 30 min. b) 1.2 hours c) 24 min.
d) 35 min. e) None of these
50) A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes
and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how
long does it take both the punctures together to make it flat?
a) 1 b) 3 c) 3
d) 4 e) None of these
51) A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single
pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full
and if 40,000 litres of petrol is used daily, the supply fails in 90 days. If 32,000 litres of petrol
is used daily, it fails in 60 days. How much petrol can be used daily without the supply every
failing?
a) 64000 litres b) 56000 litres c) 78000 litres
d) 60000 litres e) None of these
52) A is 50% more efficient than B. C does half of the work done by A and B together. If C alone
does the work in 40 days, then A, B and C together can do the work in :
a) 13 days b) 15 days c) 20 days
d) 30 days e) None of these
53) The total number of men, women and children working in a factory is 18. They earn Rs.4000
in a day. If the sum of the wages of all men, all women and all children is in the ratio of 18 :
10 : 12 and if the wages of an individual man, woman and child is in the ratio 6 : 5 : 3, then
how much a woman earn in a day?
a) Rs.400 b) Rs.250 c) Rs.150
d) Rs.120 e) None of these
54) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8
days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how
many days can they complete the work?
a) 5 b) 5 c) 6
d) 6 e) None of these
55) Eklavya can do the 6 times the actual work in 36 days while Faizal can do the one-fourth of
the original work in 3 days. In how many days will both working together complete the 3
times of the originalwork?
a) 6 b) 10 c) 12
d) 15 e) None of these
56) A and B can together finish a work in 30 days. They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work. In how many days A alone can
finish the job?
a) 40 b) 50 c) 54
d) 60 e) None of these
57) Aman and Raman are two workers. Working together they can complete the whole work in
10 hours. If the Aman worked for 2.5 hours and Raman worked for 8.5 hours, still there was
half of the work to be done. In how many hours Aman working alone, can complete the whole
work?
a) 24 hours b) 17 hours c) 40 hours
d) Data inadequate e) None of these
58) 5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a man and a boy are in the ratio :
a) 1 : 2 b) 2 : 1 c) 1 : 3
d) 3 : 1 e) None of these
59) A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200. With the help of C, they completed the work in 3 days. How much is to be paid
to C?
a) Rs.375 b) Rs.400 c) Rs.600
d) Rs.800 e) None of these
60) If there is leakage also which is capable of draining out the liquid drom the tank at half of the
rate of outlet pipe, then what is the time taken to fill the empty tank when both the pipes are
opened?
a) 3 hours b) 3 hours c) 4 hours
d) Data inadequate e) None of these
61) A, B and C are employed to do a piece of work for Rs.529. A and B together are supposed to
do of the work and B and C together of the work. What amount should A be paid?
a) Rs.315 b) Rs.345 c) Rs.355
d) Rs.375 e) None of these
62) A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be
done by A alone in :
a) 9 days b) 11 days c) 12 days
d) 16 days e) None of these
63) A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work
but A left 8 days before the completion of the work while B left 12 days before the
completion. The number of days for which C worked is :
a) 4 b) 8 c) 12
d) 24 e) None of these
64) A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will
complete the work?
a) 10 days b) 11 days c) 15 days
d) 20 days e) None of these
65) 10 women can complete a work in 7 days and 10 children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
a) 3 b) 5 c) 7
d) Data inadequate e) None of these
66) 12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them.
How many days will they take to complete the remaining work?
a) 2 days b) 3 days c) 4 days
d) 5 days e) None of these
67) A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and C
together earn Rs.152. The daily earning of C is :
a) Rs.40 b) Rs.68 c) Rs.112
d) Rs.150 e) None of these
Solutions:
1. Option D
2. Option C
3. Option B
A’s 2 day’s work =[ ×2 = ]
(A + B + C)’s 1 day’s work =[ + + ]= =
4. Option B
5. Option B
6. Option A
7. Option C
8. Option C
9. Option C
Whole work is done by A in 20 × [ ] = 25 days
[ ]
Now, 1 ⎯ i.e., work is done by A and B in 3 days.
Whole work will be done by A and B in (3 × 5) = 15 days.
A’s 1 day’s work = , (A + B)’s 1 day’s work =
10. Option D
Remaining work = [1 ⎯ ] =
11. Option C
[
work is done by A in 18 × ] = 6 days.
12. Option B
13. Option D
(A + B)’s 20 day’s work = [ × 20] =
Remaining work = [1 ⎯ ] =
Now, work is done by A in 20 days.
Therefore, the whole work will be done by A in (20 × 3) = 60 days.
14. Option A
15. Option C
16. Option B
Work done by X in 4 days = [ ]
×4 =
Remaining work [
= 1⎯ ]=
(X + Y)’s 1 day’s work =[ + ]= =
Now, work is done by X and Y in 1 day.
17. Option B
Then, 10 : 13:: 23 : x x= [ ×
] x=
A’s 1 day’s work =
B’s 1 day’s work =
18. Option C
19. Option C
So, all the three together will complete the job in [ ] days = 3
20. Option B
21. Option B
Then, [ + + ]=
=
x = 12
So, B takes (12/2) = 6 days to finish the work.
22. Option C
Remaining work = [1 ⎯ ] =
Now, work is done by A in 1 day.
23. Option A
2 (A + B + C)’s 1 day’s work = [ + + ]= =
Therefore, (A + B + C)’s 1 day’s work = =
×
Work done by A, B, C in 10 days = =
Remaining work [
= 1⎯ ]=
A’s 1 day’s work =[ ⎯ ]=
Now, work is done by A in 1 day.
So, [
work will be done by A in 48 × ] = 18 days.
24. Option A
25. Option B
26. Option C
27. Option C
Remaining work = [1 ⎯ ] =
Now, work is done by A in 1 day.
So, [
work is done by A in 24 × ] = 10 days.
28. Option A
Work done by X in 8 days = [ × 8] =
Remaining work = [1 ⎯ ] =
Now, work is done by Y in 16 days.
[
Whole work will be done by Y in 16 × ] = 20 days.
X’s 1 day’s work = , Y’s 1 day’s work =
29. Option B
30. Option A
Efficiency of P : Q = 3 : 1
Required number of days of P : Q = 1 : 3
i.e., if P requires x days then Q requires 3x days
but 3x ⎯x = 60
2x = 60
x = 30 and 3x = 90
Thus P can finish the work in 30 days and Q can finish the work in 90 days.
31. Option B
Filling efficiency = 5% 5=
Emptying efficiency = 1.66% 1.66 =
Net efficiency = 5 ⎯1.66 = 3.33%
Required time to full the tub = . = 30 minutes
32. Option C
Efficiency of A = 7.14%
Efficiency of B = 4.76%
Efficiency of A + B = 11.9%
Number of days required by A and B, working together = .
= 8.4 days
33. Option A
Efficiency of A + B = 33.33% = [ ]
Ratio of efficiency of A and B = 3 : 1
Efficiency of A = × 33.33 = 25%
Number of days taken by A = 4 = =4
34. Option A
3 days before the completion of the work Aman left the work means in last 3 days only
Suneeta has worked alone.
So, in last 3 days worked done by Suneeta = 3 × =
[
So, the rest 1 ⎯ ]= work was done by Aman and Suneeta both.
/
Number of days in which Aman and Suneeta worked together = /
= =7 days
35. Option A
[ ]
Required difference in number of days = (11) ⎯ 6
= =4 days
36. Option B
37. Option A
A + B = 70%
B + C = 50% [A + B + B + C ⎯(A + B + C) = B]
70 + 50 ⎯100 = 20%
B = 20%
A = 50%
C = 30%
Hence, A is most efficient.
38. Option C
Work done =
Remaining work =
4 (20 × 75) = 40 × x
x = 150
Therefore 75 men should be increased.
39. Option E
40. Option C
Work done =
Remaining work = , which is half of
× (20 × 32) = 8 × x
x = 40 men
Therefore, 20 more men were required.
41. Option A
Remaining work = [1 ⎯ ]
/
This remaining work will be done by A, B and C = /
= 1 day
42. Option A
43. Option E
44. Option B
[
A’s share Rs. 600 × ] = Rs.300, B’s share = Rs.[ 600 × ] = Rs.225
C’s share = Rs.[600 ⎯(300 + 225)] = Rs.75
45. Option D
Buy this book from BankExamsToday.com Page 23
Download From - www.studywale.co
Efficiency of A = 8.33%
Effective efficiency = 6.66%, when there is leakage
So, efficiency of leakage = 1.66% = (8.33 ⎯6.66)
It means due to leakage a full tank will be empty in 60 hours.
46. Option C
47. Option A
48. Option E
50. Option C
51. Option B
Let x litre be the per day filling and v litre be the capacity of the reservoir, then
Buy this book from BankExamsToday.com Page 24
Download From - www.studywale.co
52. Option A
53. Option B
54. Option A
55. Option C
56. Option D
57. Option B
58. Option B
59. Option B
C’s 1 day’s work = ⎯ [ + ]= ⎯ =
A’s wages : B’s wages : C’s wages = : : =4:3:1
60. Option C
61. Option B
62. Option B
64. Option C
B’s 1 day’s work = [ ⎯ ]= =
Now, (A + B)’s 1 day’s work =[ + ]== [
B works for half day only ]
So, A and B together will complete the work in 15 days.
65. Option C
66. Option A
www.sscexamguide.com
List of 50 Important Aptitude Questions on Time and Work (with solutions below)
1).A is 30% more efficient than B. How much time will they, working together, take to complete
a) 11 days
b) 13days
3
c) 20 7 days
d) None of these
2).A does half as much work as B in three-fourth of the time. If together they take 18 days to
a) 30 days
b) 40 days
c) 15 days
d) None of these
3).A is 50% as efficient as B.C does half of the work done by A and B together. If C alone does
the work in 40 days, then A ,B and C together can do the work in?
1
a) 133 days
b) 20 days
c) 15 days
d) 30 days
4). Two workers A and B working together completed a job in 5 days. If A worked twice as
1
efficiently as he actually did and B worked 3 as efficiently as he actually did, the work would
have been completed in 3 days. A alone could complete the work in?
1
a) 72 days
www.sscexamguide.com
1
b) 64 days
1
c) 54 days
d) None of these
5). A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the
1
a) 10
1
b) 4
7
c)
15
8
d) 15
6). A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10
days and left the job. In how many days, A alone can finish the remaining work?
a) 8
b) 5
c) 6
1
d) 52
7). A and B can complete a work in 15 days and 10 days respectively. They started doing the
work together but after 2 days B had to leave and A alone completed the remaining work. The
a) 10 days
b) 15 days
c) 12 days
d) 8 days
8). A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are
forced to leave after 3 days. The remaining work was done by A in?
www.sscexamguide.com
a) 6 days
b) 5 days
c) 10 days
1
d) 102 days
9). A machine P can print one lakh books in 8 hours, machine Q can print the same number of
books in 10 hours while machine R can print them in 12 hours. All the machines are started at
9 a.m. While machine P is closed at 11 am and the remaining two machines complete the
a) 11:30 am
b) 12:30 pm
c) 12 noon
d) 1 pm
10). A and B can do a piece of work in 30 days, while B and C can do the same work in 24
days and C and A in 20 days. They all work together for 10 days when B and C leave. How
a) 18 days
b) 36 days
c) 24 days
d) 30 days
Answers: 1). b) 2). a) 3). a) 4). b) 5). d) 6). c) 7). c) 8). c) 9). d) 10). a)
11).X and Y can do a piece of work in 20 days and 12 days respectively. X started the work
alone and then after 4 days .Y joined him till the completion of the work. How long did the work
last?
www.sscexamguide.com
a) 6 days
b) 10 days
c) 15 days
d) 20 days
12).A and B can together finish work in 30 days .They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work .In how many days A alone can finish
the job?
a) 40
b) 50
c) 54
d) 60
13).X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?
a) 13 1/3 days
b) 16 days
c) 25days
d) 50 days
14).A, B,C together can complete a piece of work in 10 days. All the three started working at it
together and after 4 days A left. Then B and C together completed the work in 10 more days .A
alone could complete the work in?
a) 15 days
b) 16 days
www.sscexamguide.com
c) 25 days
d) 50 days
15).A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days .How long B alone would take to do the whole work?
a) 23 days
b) 37 days
c) 37 ½ days
d) 40 days
16).A and B together can do a piece of work in 30 days. A having worked for16 days. B
finished the remaining work alone in 44 days. In how many days shall B finish the whole work
alone?
a) 30 days
b) 40 days
c) 60 days
d) 70 days
17).A and B together can do a piece of work in 12 days, which B and C together can do in 16
days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In
how many days C alone will do the work?
a) 46
b) 24
c) 16
d) 36
www.sscexamguide.com
18).A and B can do a piece of work in 45 days and 40 days respectively. They began to the
work together but A leaves after some days and then B completed the remaining work in 23
days. The number of days which A left the work was?
a) 8
b) 6
c) 9
d) 12
19).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
a) 6 3/5
b) 8 1/2
c) 10 1/5
d) 13 1/2
20).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
a) 15 days
b) 25 days
c) 22 days
d) 35 days
Answers: 11). b) 12). d) 13). a) 14). c)15). c)16). c 17).b 18).c 19).c 20).a
www.sscexamguide.com
21).A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and
C together earn Rs.152.The daily earning of C is?
a) Rs.40
b) Rs.112
c) Rs.68
d) Rs.150
22).A,B and c are employed to do a piece of work for Rs.529.A and B together are supposed
to do 19/23 of the work and B and C together 8/23 of the work. What amount should A be
paid?
a) Rs.315
b) Rs.345
c) Rs.375
d) Rs.355
23). Kim can do a work in 3 days while David can do the same work in 2 days. Both of them
finish the work together and get Rs.150.What is the share of Kim?
a) Rs.70
b) Rs.60
c) Rs.75
d) Rs.30
24).If A can do ¼ of a work in 3 days and 3 days and B can do 1/6 of the same work in 4 days,
how much will A get if both work together and are paid Rs.180 in all?
a) Rs.60
www.sscexamguide.com
b) Rs.36
c) Rs.75
d) Rs.70
25).A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200.With the help of C, they completed the work in 3 days. How much is to be paid to
C?
a) Rs.600
b) Rs.400
c) Rs.375
d) Rs.800
26).A sum of money is sufficient to pay A’s wages for 21 days and B’s wages for 28 days. The
same money is sufficient to pay the wages of both for?
a) 12 days
b) 14 days
c) 121/4 days
d) 24 ½ days
27).A can do a piece of work in 10 days in 15 days. They work for 5 days. The rest of the work
had finished by C in 2 days. If they get Rs.1500 for the whole work, the daily wages of B and C
are?
a) Rs.150
b) Rs.225
c) Rs.250
www.sscexamguide.com
d) Rs.300
28).A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will complete
the work?
a) 10 days
b) 20 days
c) 15 days
d) 11 days
29).A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work
on alternate days. The total work will be completed in?
a) 12 days
b) 13 days
5
c) 13 7 days
3
d) 13 4days
30).A, B and C can do a piece of work in 11 days,20 days and 55 days respectively, working
alone. How soon can the work be done if A is assisted by B and C on every third day?
a) 7 days
b) 8 days
c) 9 days
d) 10 days
Answers: 21).a 22).b 23).b 24).d 25).b 26).a 27). b) 28). c) 29). d) 30). b)
www.sscexamguide.com
31).A, B and C can separately do a piece of work in 20, 30 and 60 days respectively. In how
many days can A do the work if he is assisted by B and C on alternative days?
a) 12 days
b) 15 days
c) 18 days
d) 16 days
32). A and B can separately do a piece of work in 20 and 15 days respectively. They worked
together for 6 days, after which B was replaced by C. If the work was finished in next 4 days,
then the number of days in which C alone could do the work will be?
a) 30 days
b) 35 days
c) 40 days
d) 60 days
33).A, B and C can do a work in 36, 54 and 72 days respectively. They started the work but A
left 8 days before the completion of the work while B left 12 days before the completion. The
number of days for which C worked is?
a) 4
b) 12
c) 8
d) 24
34).Twenty women can do a work in sixteen days. Sixteen men can completed the same work
in fifteen days. What is the ratio between the capacity of a man and women?
a) 3:4
www.sscexamguide.com
b) 4:3
c) 5:3
d) Data inadequate
35).10 men can complete a piece of work in 15 days and 15 women can complete the same
work in 12 days. If all the 10 men and 15 women work together, in how many days will the
work get completed?
a) 6
1
b) 63
2
c) 63
2
d) 73
36).Seven men can complete a work in 12 days. They started the work and after 5 days, two
men left .How many days will they take to complete the remaining work?
a) 2 days
b) 4 days
c) 5 days
d) None of these
37).12 men complete a work in 9 days. After they have worked for 6 days,6 more men join
them. How many days will they take to complete the remaining work?
a) 2 days
b) 4 days
c) 3 days
www.sscexamguide.com
d) 5 days
e) None of these
38).Three men, four women and six children can complete a work in seven days. A woman
does double the work a man does half the work a man does. How many women alone can
complete this work in 7 days?
a) 7
b) 8
c) 12
d) Cannot be determined
e) None of these
39).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many
boys must assist 1 man 1 woman to complete the job ¼ of a day?
a) 1
b) 4
c) 19
d) 41
40).10 men and 15 women together can complete a work in 6 days. It takes 100 days for one
man alone to complete the same work. How many days will be required for one woman alone
to complete the same work?
a) 90
b) 145
c) 125
www.sscexamguide.com
d) 150
e) None of these
Answers: 31). b) 32). c) 33). d) 34). b) 35).c 36). d). 37).a 38). a) 39). d) 40). e)
41).12 men can complete a piece of work in 4 days, while 15 women can complete the same
work in 4 days.6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on job to complete the remaining work, if it is to be
completed in 3 days?
a) 15
b) 22
c) 18
d) Data inadequate
e) None of these
42).Twelve children take sixteen days to complete a work which can complete by eight adults
in twelve days. Sixteen adults started working and after three days ten adults left and four
children joined them. How many days will they take to complete the remaining work?
a) 3
b) 8
c) 4
d) 6
e) None of these
43).10 women can complete a work in 7 days and children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
www.sscexamguide.com
a) 3
b) 5
c) 7
d) Cannot be determined
e) None of these
44).Sixteen men can complete a work in twelve days. Twenty –four children can complete the
same work in eighteen days. Twelve men and eight children started working and after eight
days three more children joined them. How many days will they now take to complete the
remaining work?
a) 2 days
b) 4 days
c) 6 days
d) 8 days
e) None of these
45).Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days .Sixteen men and sixteen women started working and worked
for twelve days. How many more men are to added to complete the remaining work in 2 days?
a) 16
b) 24
c) 36
d) 48
e) None of these
www.sscexamguide.com
46).5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a woman and a boy are in the ratio?
a) 1:2
b) 2:1
c) 1:3
d) 3:1
47).If 12 men and 2 boys working together can do four times as much work as a man and a
boy. Working capacities of a woman and a boy are in the ratio?
a) 2:1
b) 3:1
c) 3:2
d) 5:4
48).4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can
complete it in 10 days. In how many days will 10 women complete it?
a) 35
b) 40
c) 50
d) 45
49).One man,3 women and 4 boys can do a piece of work in 96 hours,2 men and 8 days can
do it in 80 hours,2 men and 3 women can do it in 120 hours.5men and 12 boys can do in:?
1
a) 39 11 hours
www.sscexamguide.com
7
b) 42 11 hours
7
c) 43 11 hours
d) 44 hours
50).If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do
the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will
be?
a) 4 days
b) 5 days
c) 6 days
d) 7 days
Answers: 41). a) 42). e) 43). c) 44). b) 45). b) 46). b) 47). a) 48). b) 49). c) 50). a)
www.sscexamguide.com
1).A is 30% more efficient than B. How much time will they, working together, take to complete
1 10
A’s 1 day’s work =23 ; B’s 1 days work =299.
Answer: b
2).A does half as much work as B in three-fourth of the time. If together they take 18 days to
1
(A + B)’S 1 day’s work =18.
1 2 1
+ 3x = 18 or x=30
x
Answer: a
3). A is 50% as efficient as B.C does half of the work done by A and B together. If C alone
does the work in 40 days, then A, B and C together can do the work in?
www.sscexamguide.com
5x 1 1 2 1
= or x = × =
2 40 40 5 100
3 1 1
A’s 1 day’s work =100 ; B’s 1 day’s work = 50 ; C’s 1 day’s work=40
3 1 1 15 3
(A+B+C)’s 1 day’s work = + 50 + 40 = 20 = 40
100
40 1
So, A, B and C together can do the work in = 13 3 days.
3
Answer: a
4.) Two workers A and B working together completed a job in 5 days. If A worked twice as
1
efficiently as he actually did and B worked 3 as efficiently as he actually did, the work would
have been completed in 3 days. A alone could complete the work in?
4 1
Solving, we get : x=25 and y=25
4
A’s 1 day’s work=25
25 1
So, A alone could complete the work in = 6 4days
4
Answer: b
5.) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then
1 1
A’s 1 day’s work =15 ; B′ s1 day ′ s work = 20
1 1 7
(A+B)’s 1 day’s work=(15 + 20 ) = 60
7 7
(A+B)’s 4 day’s work=(60 × 4) = 15
7 8
Remaining work=(1-15 ) = 15
Answer: d
www.sscexamguide.com
6). A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10
days and left the job. In how many days, A alone can finish the remaining work?
1 2 2 1
B’s 10 day’s work=(15 × 10) = 3 . Remaining work = 1 − 3 = 3
1
Now,18 work is done by A in 1 day
1 1
work ′ sdone by A in 18 × = 6days
3 3
Answer: c
7). A and B can complete a work in 15 days and 10 days respectively. They started doing the
work together but after 2 days B had to leave and A alone completed the remaining work. The
1 1 1
(A+B)’s 1 day’s work=(15 + 10 ) = 6
1 1 1 2
Work done by A and B in 2 days= × 2 = 3 . Remaining work = 1 − 3 = 3
6
1
Now,15 work will be done by Ain 1 day.
2 2
work will be done by A in 15 × = 10days.
3 3
Answer: c
8). A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are
forced to leave after 3 days. The remaining work was done by A in?
1 1 7
(B+C)’s 1day’s work =( 9 + 12 ) = 36.
7 7
Work done by B and C in 3 days=(36 × 3) = 12
7 7
Remaining work=(1-12 ) = 12
1
Now,24 work is done by A in 1 day
www.sscexamguide.com
5 5
So, 12 work is done by A in 24 × 12 = 10days
Answer: c
9). A machine P can print one lakh books in 8 hours, machine Q can print the same number of
books in 10 hours while machine R can print them in 12 hours. All the machines are started at
9 a.m. While machine P is closed at 11 am and the remaining two machines complete the
1 1 1 37
(P+Q+R)’s 1 hour’s work=(8 + 10 + 12 ) = 120
37 37
Work done by P,Q and R in 2 hours=(120 × 2) = 60
37 23
Remaining work=(1-60 ) = 60
1 1 11
(Q+R)’s 1 hour’s work=(10 + 12)=60
11
Now,60 work is done by Q and R in 1 hour
23 60 23 23
So, work will be done byQ and R in × = hours = 2 hours.
60 11 60 11
So, the work will be finished approximately 2 hours after 11a.m, i.e., round 1p.m
Answer: d
10). A and B can do a piece of work in 30 days, while B and C can do the same work in 24
days and C and A in 20 days. They all work together for 10 days when B and C leave. How
1 1 1 15 1
2(A+B+C)’s 1 day’s work = (30 + 24 + 20 ) = 120 = 8
1
=> (A+B+C)’s 1 day’s work=16
10 5 5 3
Work done by A, B and C in 10 days=16 = 8 Remaining work=(1-8) = 8
1 1 1
A’s 1 day’s work =(16 − ) = 48
24
1
Now, 48 work is done by A in 1 day
www.sscexamguide.com
3 3
So, 8 work will be done by A in (48× 8) = 18days.
Answer: a
11).X and Y can do a piece of work in 20 days and 12 days respectively. X started the work
alone and then after 4 days .Y joined him till the completion of the work. How long did the work
last?
1 1 1 4
Work done by X in 4 days =(20 × 4) = 5 Remaining work = 1 − 5 = 5
1 1 8 2
(X+Y)’s 1 day’s work= + 12 = 60 = 15
20
2
Now, 15 work is done by X and Y in 1 day
4 15 4
So, 5 work will be done by X and Y in × 5 = 6 days.
2
Answer: b
12).A and B can together finish work in 30 days .They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work .In how many days A alone can finish
the job?
1 2 2 1
(A+B)’s 20 day’s work = (30 × 20) = 3 , Remaining work = 1 − 3 = 3
1
Now, 3 work is done by A in 20 days.
Answer: d
13).X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?
1 1 1 4
Work done by X in 8 days = (40 × 8) = 5 Remaining work = 1 − 5 = 5
4
Now, 5 work is done by Y in 16 days.
www.sscexamguide.com
5
Whole work will be done by Y in (16× 4) = 20days
1 1
X’s 1 day’s work =40 Y ′ s 1 day ′ swork = 20
1 1 3
(X+Y)’s 1 day’s work =(40 + 20 )=40
40 1
Hence, X and Y will together complete the work in = 13 3 days.
3
Answer: a
14).A, B,C together can complete a piece of work in 10 days. All the three started working at it
together and after 4 days A left. Then B and C together completed the work in 10 more days .A
alone could complete the work in?
1 2 2 3
Work done by A.B and C in 4 days=(10 × 4) = 3 . Remaining work = 1 − 5 = 5
3
Now, 5 work is done by B and C in 10 days.
5 50
Whole work will be done B and C in (10× 3) = days.
3
1 3
(A+B+C)’s 1 day’s work=10, B + C ′ S 1day ′ s work = 50
1 3 2 1
A’s 1 day’s work = − 50 = 50 = 25
10
Answer: c
15).A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days .How long B alone would take to do the whole work?
5
Whole work is done by A in (20× 4) = 25days.
4 1
Now, (1-5)i. e. , 5 work is done by A and B in 3 days.
75 1
So, B alone would do the work in = 372 days.
2
www.sscexamguide.com
Answer: c
16).A and B together can do a piece of work in 30 days. A having worked for16 days. B
finished the remaining work alone in 44 days. In how many days shall B finish the whole work
alone?
1 1
Solving these two equations, we get: x =60 and y = 60
1
B’s 1 day’s work = 60
Answer: c
17).A and B together can do a piece of work in 12 days, which B and C together can do in 16
days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In
how many days C alone will do the work?
=> (A+B)’s 5 day’s work + (B+C)’s day’s work+ C’s 11day’s work = 1
5 2
=> 12 + 16 + C′ s11 day ′ swork = 1
5 2 11
=>C’s 11 day’s work=1-(12 + 16 ) = 24
11 1 1
=>C’s 1 day’s work = (24 × 11 ) = 24
Answer: b
18).A and B can do a piece of work in 45 days and 40 days respectively. They began to the
work together but A leaves after some days and then B completed the remaining work in 23
days. The number of days which A left the work was?
www.sscexamguide.com
1 1 17
(A+B)’s 1day’s work = (45 + 40 ) = 360
1 23 23 17
Work done by B in 23 days= (40 × 23) = 40 . Remaining work = 1 − 40 = 40
17
Now, 360 work was done by (A+B) in 1 day.
17 360 17
work was done by A + B in 1 × × = 9 days.
40 17 40
Answer: c
19).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
1 1 1 6
B’s 3 day’s work = (21 × 3) = 7 . Remaining work = 1 − 7 = 7
1 1 5
(A+B)’s 1 day’s work=(14 + 21 ) = 42
5
Now, work is done by A and B in 1 day
42
6 42 6 36
work is done by A and B in × = days
7 6 7 5
36 1
Hence, total times taken= (3+ 5 )days = 10 5 days
Answer: c
20).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
1 1 1 12
(A+B+C)’s 1 day’s work= (24 + 36 + 48 ) = 144
13 13
Work done by (A+B+C) in 4 days= (144 × 4) = 36
1 1 13 1 5
Work done by B in 3 days = (36 × 3) = 12. Remaining work = 1 − + 12 =9
36
1 1 5
(A+B)’s 1 day’s work=(24 + 36 ) = 72
www.sscexamguide.com
5 72 5
Now, 72 work is done by A and B in × 9 = 8 days.
5
Answer: a
21).A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and
C together earn Rs.152.The daily earning of C is?
Answer: a
22).A,B and c are employed to do a piece of work for Rs.529.A and B together are supposed
to do 19/23 of the work and B and C together 8/23 of the work. What amount should A be
paid?
8 15
Work done by A=(1 − 23 ) = 23
15 8
A : (B+C)=23 : 23 = 15: 8
15
So, A’s share=Rs.(23 × 529) = Rs. 345
Answer: b
23). Kim can do a work in 3 days while David can do the same work in 2 days. Both of them
finish the work together and get Rs.150.What is the share of Kim?
Kim’s wages: David’s wages = Kim’s 1 day’s work: David’s 1 day’s work
1 1
=3 : 2 = 2: 3
2
Kim’s share = Rs. (5 × 150) Rs. 60
Answer: b
www.sscexamguide.com
24).If A can do ¼ of a work in 3 days and 3 days and B can do 1/6 of the same work in 4 days,
how much will A get if both work together and are paid Rs.180 in all?
2
A’s share=Rs. (3 × 180) = 𝑅𝑠. 120
Answer: d
25.)A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200.With the help of C, they completed the work in 3 days. How much is to be paid to
C?
1 1 1 1 7 1
C’s 1 day’s work=3 − (6 + 8) = 3 − 24 = 24
1 1 1
A’s wages: B’s wages: C’s wages =6 : 8 : 24 = 4:3:1
1
C’s share = Rs (8 ×3200) Rs 400
Answer: b
26).A sum of money is sufficient to pay A’s wages for 21 days and B’s wages for 28 days. The
same money is sufficient to pay the wages of both for?
𝑥 𝑥 𝑥
(A+B)’s 1 day’s wages = Rs. (21 + 28 ) = 𝑅𝑠. 28
Answer: a
www.sscexamguide.com
27).A can do a piece of work in 10 days in 15 days. They work for 5 days. The rest of the work
had finished by C in 2 days. If they get Rs.1500 for the whole work, the daily wages of B and C
are?
1 1
Part of the work done by A= (10 × 5) = 2
1 1
Part of the work done by B= (15 × 5) = 3
1 1 1
Part of the work done by C= 1-(2 + 3) = 6
1 1 1
So, (A’s share): (B’s share): (C’s share) = 2 : 3 : 6 = 3: 2: 1
3 2
A’s share = Rs.(6 × 1500) = 𝑅𝑠. 750, 𝐵 ′ 𝑠𝑠ℎ𝑎𝑟𝑒 = 𝑅𝑠. × 1500 𝑅𝑠. 500,
6
1
C’s share = Rs. (6 × 1500) = 𝑅𝑠. 250
750 500
A’s daily wages = Rs.( ) = 𝑅𝑠. 150; 𝐵 ′ 𝑠 𝑑𝑎𝑖𝑙𝑦 𝑤𝑎𝑔𝑒𝑠 = 𝑅𝑠. ( ) = 𝑅𝑠. 1𝑜𝑜;
5 5
250
C’s daily wages = Rs. ( ) = Rs. 125.
2
Answer: b
28).A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will complete
the work?
1 1 2 1
B’s 1 day’s work = (12 − 20 ) = 60 = 30
1 1 4 1
Now, (A+B)’s 1 day’s work =(20 + 60 ) = 60 = 15 . |B works for half day only|
Answer: c
29).A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work
on alternate days. The total work will be completed in?
www.sscexamguide.com
1 1 7
A+B)’s 2 day’s work = + 12 = 48
16
7 7 7 1
Work done in 6 pairs of days = (48 × 6) = 8 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 8 = 8
1 1 1 1
Work done by A on 13th day = 16 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = − 16 = 16
8
1 1 1 3
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝐵 𝑖𝑛 1 𝑑𝑎𝑦. 𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝐵 𝑖𝑛 12 × = 𝑑𝑎𝑦
12 16 16 4
3
Total time taken = 134 𝑑𝑎𝑦𝑠
Answer: d
30).A, B and C can do a piece of work in 11 days,20 days and 55 days respectively, working
alone. How soon can the work be done if A is assisted by B and C on every third day?
1 1 31 1 1 6
(A+B)’s 1 day’s work = (11 + 20 ) = 220 . 𝐴 + 𝐶 ′ 𝑠 𝑤𝑜𝑟𝑘 = + 55 = 55
11
31 6 55 1
Work done in 2 days = (220 + 55 ) = 220 = 4
1
Now, 4 work is done by A in 2 days.
Answer: b
31).A, B and C can separately do a piece of work in 20, 30 and 60 days respectively. In how
many days can A do the work if he is assisted by B and C on alternative days? A’s 2 day’s
1 1
work = (20 × 2) = 10
1 1 1 6 1
(A+B+C)’s 1 day’s work = (20 + 30 + 60 ) = 60 = 10
1 1 1
Work done in 3 days = (10 + 10 ) = 5
1
Now, 5 work is done in 3 days
www.sscexamguide.com
Answer: b
32).A and B can separately do a piece of work in 20 and 15 days respectively. They worked
together for 6 days, after which B was replaced by C. If the work was finished in next 4 days,
then the number of days in which C alone could do the work will be?
1 1 7 3
(A+B)’s 6 day’s work = 6(20 + 15 ) = 10 ; 𝐴 + 𝐶 ′ 𝑠4 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 10
3 1
(A+C)’s 1 day’s work = 40 𝐴′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 20
3 1 1
C’s 1 day’s work = ( 40 − 20 ) = 40
Answer: c
33).A, B and C can do a work in 36, 54 and 72 days respectively. They started the work but A
left 8 days before the completion of the work while B left 12 days before the completion. The
number of days for which C worked is?
Then, A’s (x-8) day’s work + B’s (x-12) day’s work + C’s x day’s work = 1
𝑥−8 𝑥−12 𝑥
+ + 72 = 1 => 6 𝑥 − 8 + 4 𝑥 − 12 + 3𝑥 = 216
36 54
Answer: d
34).Twenty women can do a work in sixteen days. Sixteen men can completed the same work
in fifteen days. What is the ratio between the capacity of a man and women?
www.sscexamguide.com
1
1 man’s 1 day’s work = 240
1 1
So, required ratio = 240 : 320 =4:3
Answer: b
35).10 men can complete a piece of work in 15 days and 15 women can complete the same
work in 12 days. If all the 10 men and 15 women work together, in how many days will the
1 1
work get completed? 10 men’s 1 day’s work = 15 ; 15 𝑤𝑜𝑚𝑒𝑛′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 12.
1 1 9 3
(10 men + 15 women)’s 1 day’s work = (15 + 12 ) = 60 =20
3 2
10 men and 15 women will complete the work in 20 = 6 3 𝑑𝑎𝑦𝑠.
Answer: c
36).Seven men can complete a work in 12 days. They started the work and after 5 days, two
men left .How many days will they take to complete the remaining work?
1 5 5 7
7 men’s 5 day’s work = (12 × 5) = 12 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 w𝑜𝑟𝑘 = 1 − 12 = 12
1 5
5 men’s 1 day’s work = × 5 = 84
84
5
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 1 𝑑𝑎𝑦.
84
7 84 7 49 4
Work is done by them in ( 5 × 12 ) = 𝑑𝑎𝑦𝑠 = 9 5 𝑑𝑎𝑦𝑠
12 5
Answer: d
37). 12 men complete a work in 9 days. After they have worked for 6 days,6 more men join
them. How many days will they take to complete the remaining work?
1
1 man’s 1 day’s work = 108
1 2 2 1
12 men’s 6 day’s work = (9 × 6) = . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 3 = 3
3
www.sscexamguide.com
1 1
18 men’s 1 day’s work = (108 × 18) = 6
1
Work is done by them in 1 day.
6
1 1
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 6 × = 2 𝑑𝑎𝑦𝑠
3 3
Answer: a
38).Three men, four women and six children can complete a work in seven days. A woman
does double the work a man does half the work a man does. How many women alone can
complete this work in 7 days?
3𝑥 6𝑥 1 1 4 1
So, ( 2 + 4𝑥 + ) = 7 => 𝑥 = × 28 = 49
4 7
Answer: a
39).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many
boys must assist 1 man 1 woman to complete the job ¼ of a day?
1 1 7
(1 man + 1 woman)’s 1 day’s work = (3 + 4) = 12
1 7 1 7
Work done by 1man and 1 woman in 4 𝑑𝑎𝑦 = × 4 = 48
12
7 1
Remaining work = (1-48 ) = 48
1 1 1 1
Work done by 1 boy in 4 𝑑𝑎𝑦 = × 4 = 48
12
41
Number of boys required = (48 × 48) = 41
Answer: d
www.sscexamguide.com
40).10 men and 15 women together can complete a work in 6 days. It takes 100 days for one
man alone to complete the same work. How many days will be required for one woman alone
to complete the same work?
1 1
1 man’s 1 day’s work = 100. (10 men + 15 women)’s day work = 6
1 10 1 1 1
15 women’s 1 day’s work = (6 − 100 ) = − 10 = 15
6
1
1 woman’s 1 day’s work = 225
Answer: e
41).12 men can complete a piece of work in 4 days, while 15 women can complete the same
work in 4 days.6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on job to complete the remaining work, if it is to be
completed in 3 days?
1 1
1 man’s 1 day’s work = 48 ; 1 𝑤𝑜𝑚𝑎𝑛′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 60
6 1 1 3
6 men’s 2 day’s work = (48 × 2) = 4. 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 4 = 4
1
Now, 60 work is done in 1 day by 1 woman
3 3 1
So, 4 𝑤𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑖𝑛 3 𝑑𝑎𝑦𝑠 𝑏𝑦 60 × 4 × 3 = 15 𝑤𝑜𝑚𝑒𝑛
Answer: a
42).Twelve children take sixteen days to complete a work which can complete by eight adults
in twelve days. Sixteen adults started working and after three days ten adults left and four
children joined them. How many days will they take to complete the remaining work?
1 1
1 child’s 1 day’s work = 192 : 1 𝑎𝑑𝑢𝑙𝑡 ′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 96
1 1 1 1
Work done in 3 days = (96 × 16 × 3) = 2 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 2 = 2
6 4 1
(6 adults + 4 children)’s 1 day’s work = (96 + 192 ) = 12
www.sscexamguide.com
1
Work is done by them in 1 day
12
1 1
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 12 × = 6 𝑑𝑎𝑦𝑠
2 2
Answer: e
43).10 women can complete a work in 7 days and children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
1 1
1 woman’s 1 day’s work =70 : 1 𝑐ℎ𝑖𝑙𝑑′ 𝑠 1 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 140
5 10 1 1 1
(5 women + 10 children)’s 1 day’s work = (70 + 140 ) = + 14 = 7
14
Answer: c
44).Sixteen men can complete a work in twelve days. Twenty –four children can complete the
same work in eighteen days. Twelve men and eight children started working and after eight
days three more children joined them. How many days will they now take to complete the
remaining work?
1 1
1 man’s 1 day’s work = 192 ; 1 𝑐ℎ𝑖𝑙𝑑′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 432
12 8 1 1 35
Work done in 8 days= 8(192 + 432 ) = 8 + 54 = 54
16
35 19
Remaining work = (1-54 ) = 54
12 11 19
(12 men + 11 children)’s 1 day’s work = (192 + 432 ) = 216
19
Now, work is done by them in 1 day
216
19 219 19
𝑤𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 × = 4 𝑑𝑎𝑦𝑠.
54 19 54
Answer: b
www.sscexamguide.com
45).Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days .Sixteen men and sixteen women started working and worked
for twelve days. How many more men are to added to complete the remaining work in 2 days?
1 1
1 man’s 1 day’s work = 384 ; 1 𝑤𝑜𝑚𝑎n′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 768
16 16 3 3
Work done in 12 days = 12(384 + 769 ) = 12 × 48 = 4
3 1
Remaining work = (1 - 4) = 4
16 16 1 1
(16 men + 16 women)’s 2 day’s work = 2 (384 + 768 ) = 2 × 16 = 8
1 1 1
Remaining work = (4 - 8) = 8
1
Work is done in 1 day by 1 man
384
1 1 1
𝑊𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑖𝑛 2 𝑑𝑎𝑦𝑠 𝑏𝑦 384 × × = 24 𝑚𝑒𝑛.
8 8 2
Answer: b
46).5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a woman and a boy are in the ratio?
Answer: b
47).If 12 men and 2 boys working together can do four times as much work as a man and a
boy. Working capacities of a woman and a boy are in the ratio?
1 1
Solving these two equations, we get: x = 100 and y = 200
1 1
Required ratio = x: y = 100 : 200 = 2: 1
www.sscexamguide.com
Answer: a
78).4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can
complete it in 10 days. In how many days will 10 women complete it?
11 1
Solving these two equations, we get: x=400 , y = 400
1
1 woman’s 1 day’s work = 400
1 1
10 women’s 1 day’s work = (400 × 10) = 40
Answer: b
49).One man,3 women and 4 boys can do a piece of work in 96 hours,2 men and 8 days can
do it in 80 hours,2 men and 3 women can do it in 120 hours.5men and 12 boys can do in:?
1
Adding (ii) and (iii) and subtracting (i) from it, we get it, we get: 3x+ 4z = 96 …..(iv)
1 1 1
From (ii) and (iv), we get x= 480 Substituting, we get ∶ y = , z = 960
720
5 12 1 1 11
(5 men + 12 boy)’s 1 hour’s work = (480 + 960 ) = + 80 = 480
96
480 7
5 men and 12 boys can do the work in i. e. , 43 11 hours
11
Answer: c
www.sscexamguide.com
50).If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do
the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will
be?
1 1
Solving these tow equations, we get: x = 100 and y = 200
15 20 1
(15 men+20 boy)’s 1 day’s work = (100 + 200 ) = 4
Answer: a
a) 5 hours
b) 4.8 hours
c) 3.6 hours
d) 4 hours
Question 2: Jogging at a speed of 6.5 km/hr a man can cover a distance in 18 hours. Running at
a speed of 12 km/hr the man covers the same distance in
a) 7.85 hours
b) 10.5 hours
c) 8.36 hours
d) 9.75 hours
Question 3: Two trains moving in opposite directions cross each other in 60 seconds. If their
speeds are 30 km/hr and 120 km/hr, find the sum of the lengths of the trains.
a) 3.2 km
b) 2.8 km
c) 2.5 km
d) 3.6 km
Question 4: A group of rowers can row a boat at a speed of 20 m/min. The speed of the water
current is 0.24 km/hr. What is the difference between the time they will take to row 576 m
upstream and downstream?
a) 8 minutes
b) 10 minutes
c) 12 minutes
d) 15 minutes
a) 36 km/hr
b) 45 km/hr
c) 54 km/hr
d) 63 km/hr
Question 6: 10 men can together do a piece of work in 4 days. But from the second day, 1 worker
kept on leaving the group each day. On which day will the assignment get completed?
a) 5th day
b) 6th day
c) 7th day
d) 8th day
Question 7: A person bought an article marked at Rs. 100 and gets successive discounts of 10%
and 20%. Then, he also spends 10% of the cost price as transportation cost. To earn a profit of
5%, at what price should he sell the article?
a) Rs.79.2079.20
b) Rs.80.3580.35
c) Rs.75.4275.42
d) Rs.83.1683.16
Question 8: To catch the train just in time, Uday estimated that he needs to leave his house
before 3 hours of the scheduled departure if he travels at his normal speed. However, he leaves
his house 45 minutes later than he planned. To catch the train just on time, he needs to increase
his speed by
a) 16.66%
b) 20%
c) 33.33%
d) 25%
a) 22.5 days
b) 10 days
c) 20 days
d) 30 days
Question 10: Ram can do a piece of work in 15 days. Shyam can do the same piece of work in
20 days. They work together for 5 days and then Ram leaves. On which day (from the beginning)
will the work be completed?
a) 10th day
b) 12th day
c) 13th day
d) 14th day
1) Answer (D)
2) Answer (D)
3) Answer (C)
5) Answer (C)
6) Answer (A)
Let us assume that each man does 1 unit of work each day.
So, the total work to be done is 10 X 4 = 40 units
Now, on the first day 10 workers will work, on the second day 9 workers will work, on third 8 and
so forth.
Since each man does 1 unit of work, the work done on each day can be written as-
10(1st day) + 9(2nd day) + 8(3rd day) + 7(4th day) + 6 (5th day) = 40 units
Thus, the assignment will get completed on the 5th day.
7) Answer (D)
9) Answer (B)
The amount of work done by Amit in 3 days is equal to the amount of work done by Vinod in 2
days. Hence if Amit does 1 unit of work in 3 days, Vinod can do it in 2 days. In 15 days, Amit
would do 15/3 = 5 units of work.
The time needed by Vinod to complete 5 units of work = 5*2 = 10 days.
Let the total work to be done be 60 units. So Ram does 4 units of work in a day and Shyam does
3 units of work in a day. Hence when they work together, they will be able to do 7 units in 1 day.
Hence in 5 days, they will do 35 units of work. Thus, the remaining 25 units will have to be done
by Shyam. The time taken by Shyam to do the remaining 25 units of work = 25/3 = 8.33 days.
Hence the total time taken = 5 + 8.33 = 13.33 days.
Hence the work will be completed on 14th day.
a) 5
b) 8
c) 12
d) 3
e) None of these
Question 2: The speed of a boat when travelling downstream is 32 Kms. / Hr. , whereas when
travelling upstream it is 28 kms/hr. What is the speed of the boat in still water ?
a) 27 Kms./Hr.
b) 29 Kms./ Hr.
c) 31 Kms./ Hr.
d) Cannot be determined
e) None of these
Question 3: If I walk at 4 km/h, I miss the bus by 10 min. If I walk at 5 km/h, I reach 5 min before
the arrival of the bus. How far I walk to reach the bus stand?
a) 5 km
b) 5.5 km
c) 6 km
d) 7.5 km
e) None of these
Question 4: The speed of a boat in still water is 15 km/hr and the rate of current is 3 km/hr. The
distance travelled down steam in 12 minutes is:
a) 3.3 km
b) 2.9 km
c) 2.4 km
d) 3.6 km
e) None of these
English Language Questions for SBI PO
a) 6 h 30 min
b) 4 h 45 min
c) 3 h 15 min
d) 5 h 10 min
e) None of these
Question 6: A boat’s speed with the current is 15 kmph and the boat’s speed against the current
is 5 kmph. What is the speed of the current?
a) 15 kmph
b) 10 kmph
c) 5 kmph
d) 20 kmph
e) None of the above
Question 7: A 210 m long train takes 6 s to cross a man running at 9 km/h in a direction opposite
to that of the train. What is the speed of the train? (in km/h)
a) 127
b) 121
c) 117
d) 108
e) 111
Question 8: A truck covers a distance of 640 km in 10 h. A car covers the same distance in 8 h.
What is the respective ratio between the speed of the truck and the car?
a) 3: 4
b) 1: 2
c) 5: 6
d) 6: 7
e) None of these
a) 6.2
b) 9.1
c) 8.6
d) 7.8
e) None of these
Question 10: A 280 m long train crosses a platform thrice its length in 6 min 40 s. What is the
speed of the train?
a) 3.2 m/s
b) 1.4 m/s
c) 2.8 m/s
d) Cannot be determined
e) None of these
1) Answer (D)
All the three friends will meet at the starting point again after X seconds, such that X is the LCM of
the times taken by J, K and L to complete one round.
=> LCM of 12, 18 and 20 = 180 seconds = 3 minutes.
Hence 3 minutes is the answer.
2) Answer (E)
Let the speed of boat in still water be v and the speed of water be x.
Boat speed while going upstream = v-x = 28
Boat speed while going downstream = v+x = 32
=> 2v = 60 => v = 30
Hence, none of these is the correct answer.
4) Answer (D)
5) Answer (D)
6) Answer (C)
7) Answer (C)
Speed of train = x
Relative speed = x + 9(5 / 18) = x + 2.5
Speed = 210 / 6 = 35 m/s
x + 2.5 = 35 => x = 32.5 m/s = 32.5 * (18/5) = 6.5 * 18 = 117 kmph
8) Answer (E)
9) Answer (B)
Q1. A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and
C can do the same work in 12 days. Time taken by A, B and C together to do the job is?
(a) 4 days (b) 9 days
(c) 8 days (d) 5 days
Q2. A, B and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days
before the work was completed and B left 2 days after A had left. Number of days required to
complete the whole work is?
(a) 8 days (b) 6 days
(c) 7 days (d) 6 days
Q3. A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked
together for two days and then A was replaced by B. In how many days, altogether, the work was
completed?
(a) 12 days (b) 10 days
(c) 6 days (d) 8 days
Q4. A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start
the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining
work is?
(a) 10 days (b) 12 days
(c) 15 days (d) 16 days
Q5. A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then
both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will
C finish the full work?
(a) 25 days (b) 30 days
(c) 24 days (d) 20 days
Q6. X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete
work was finished in 16 days, Y can alone finish that work in how
many days?
(a) 18 days (b) 27 days
(c) 36 days (d) 42 days
Q8. If 10 men or 20 women or 40 children can do a piece of work in 7 months. Then, 5 men, 5
women and 5 children together can-do half of the work in?
(a) 6 months (b) 4 months
(c) 5 months (d) 8 months
Q9. A company employed 200 workers to complete a certain work in 150 days. If only one-fourth
of the work has been done in 50 days, then in order to complete the whole work in time, the
number of additional workers to be employed was?
(a) 100 (b) 300
(c) 600 (d) 200
Q10. A contractor was engaged to construct a road in 16 days. After working for 12 days with 20
workers it was found that only th of the road had been constructed. To complete the work in
stipulated time the number of extra workers required is?
(a) 18 (b) 10
(c) 12 (d) 16
Q11. Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes
are opened simultaneously, after how much time should B be closed so that the tank is full in 15
minutes?
(a) 12 min (b) 4 min
(c) 6 min (d) 8 min
Q12. If two pipes function simultaneously the reservoir is filled in 12 hours. One pipe fills the
reservoir 10 hours faster than the other. How many hours does the faster pipe take to fill the
reservoir?
(a) 20 hours (b) 30 hours
(c) 35 hours (d) 45 hours
Q13. Three pipes A, B and C can fill a cistern in 6 hrs. After working together for 4 hours, C is
closed, and A and B fill the cistern in 4 hours. Then find the time in which the cistern can be filled
by pipe C?
(a) 6 hours (b) 12 hours
(c) 14 hours (d) 20 hours
Q14. A tank has a leak which would empty it in 8 hours. A tap is turned on which admits 6 litres a
minute into the tank, and it is now emptied in 12 hours. How many litres does the tank hold?
(a) 8260 liters (b) 8450 liters
(c) 8640 liters (d) 8660 liters
Q15. A tank is normally filled in 8 hours but takes 2 hours longer to fill because of a leak in its
bottom. If the cistern is full, in how many hours will the leak in the bottom empty half of the
tank?
(a) 20 hours (b) 45 hours
(c) 50 hours (d) 55 hours
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
2
Download From - www.studywale.co
Q18. Twenty women can do a work in sixteen days. Sixteen men can complete the same work in
fifteen days. What is the ratio between the capacity of a man and a woman?
(a) 3:4 (b) 4:3
(c) 5:3 (d) Data inadequate
Q19. 10 men can complete a piece of work in 15 days and 15 women can complete the same work
in 12 days. If all the 10 men and 15 women work together, in how many days will the work get
completed?
(a) 6 (b) 6
(c) 6 (d) 7
Q20. 12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them.
How many days will they take to complete the remaining work?
(a) 2 days (b) 3 days
(c) 4 days (d) 5 days
Q21. Three men, four women and six children can complete a work in seven days. A woman does
double the work a man does and a child does half the work a man does. How many women alone
can complete this work in 7 days?
(a) 7 (b) 8
(c) 12 (d) Cannot be determined
Q22. A man, a woman and a boy can complete a job in 3, 4 and 12 days respectively. How many
boys must assist 1 man and 1 woman to complete the job in of a day?
(a) 1 (b) 4
(c) 19 (d) 41
Q23. 10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man
alone to complete the same work. How many days will be required for one woman alone to
complete the same work?
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
3
Download From - www.studywale.co
Q24. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it
in 10 days. In how many days will 10 women complete it?
(a) 35 (b) 40
(c) 45 (d) 50
Q25. Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days. Sixteen men and sixteen women started working and worked for
twelve days. How many more men are to be added to complete the remaining work in 2 days?
(a) 16 (b) 24
(c) 36 (d) 48
Q26. 12 men can complete a piece of work in 4 days, while 15 women can complete the same work
in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on the job to complete the remaining work, if it is to
be completed in 3 days?
(a) 15 (b) 18
(c) 22 (d) Data inadequate
Q27. A, B and C are employed to do a piece of work for Rs. 529. A and B together are supposed to
do of the work and B and C together of the work. What amount should A be paid?
(a) Rs. 315 (b) Rs. 345
(c) Rs. 355 (d) Rs. 375
Q28. A and B can do a piece of work in 45 days and 40 days respectively. They began to do the
work together but A leaves after some days and then B completed
the remaining work in 23 days. The number of days after which A
left the work was:
(a) 6 (b) 8
(c) 9 (d) 12
Q29. Kim can do a work in 3 days while David can do the same
work in 2 days. Both of them finish the work together and get Rs.
150. What is the share of Kim?
(a) Rs. 30 (b) Rs. 60
(c) Rs. 70 (d) Rs. 75
Q30.A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for
Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
(a) Rs. 375 (b) Rs. 400
(c) Rs. 600 (d) Rs. 800
Solution
S1. Ans.(c)
Sol.
A+B 15 4
B+C 10 60 6
A+C 12 5
2(A + B + C) = 15
A+B+C=
Time (A + B + C) = = 4 × 2 = 8 days
/
S2. Ans.(c)
Sol.
A 10 6
B 12 60 5
C 15 4
4x + 6(x – 5) + 5(x – 3) = 60
4x + 6x – 30 + 5x – 15 = 60
15x = 105
x = 7 days
S3. Ans.(d)
Sol.
A 10 6
B 15 60 4
C 20 3
2 days’ work of (A + C) = 9 × 2 = 18
Remaining work = 60 – 18 = 42
1 day’s efficiency of B + C = 4 + 3 = 7
Time = = 6 days
Work was completed in = 6 + 2 = 8 days
S4. Ans.(c)
Sol.
A 18 10
B 20 180 9
C 30 6
(B + C)’s 1-day work = 15
(B + C)’s 2-day work = 30
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
1
Download From - www.studywale.co
S5. Ans.(c)
Sol.
A 20 3
60
B 30 2
(A + B)’s 1-day work = 5
(A + B)’s 7-day work = 7 × 5 = 35
Remaining work = 60 – 35 = 25
Efficiency of C =
C will finish the full work in = × 10
= 24 days
S6. Ans.(c)
Sol. x → 24 days
Let efficiency of x be → 1/day
Work done by x in 4 days = 4
Remaining work = 24 – 4 = 20
20 work done by (x & y) in 12 days
Efficiency of (x + y) =
Efficiency of y = 1
Complete work done by y is =
/
= 36 days
S7. Ans.(b)
Sol. (6M + 8B) × 10 = (26M + 48B) × 2
8M = 16B
1M = 2B
6M + 8B = 20B
15M + 20B = 50B
20B × 10 days = 50B × x days
x days = 4 days
S8. Ans.(b)
Sol. 10M = 20W = 40C
1M = 2W, 1M = 4C, 1W = 2C
5M + 5W + 5C = 10W + 5W + W
35
W
2
20 × 7 = W × days
Full work is completed in = 8 months
Half work is completed in = 8/2 = 4 months
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
2
Download From - www.studywale.co
S9. Ans.(a)
Sol.
200 50 200 100
1/4 3/4
300 = 200 + x
x = 100 more workers
S10. Ans.(d)
Sol.
20 12 20 4
5/8 3/8
36 = 20 + x
x = 16
S11. Ans.(a)
Sol. A can fill in → 24 min
B can fill in → 32 min
Let the capacity of the tank = L.C.M (24, 32) = 96 unit.
S12. Ans.(a)
Sol. Let’s do it by option.
Suppose the faster pipe A takes = 20 hrs.
So, slower pipe B takes = 30 hrs.
A+B→ = 12 hrs.
Thus, option (a) is correct.
S13. Ans.(b)
Sol. A + B + C → 6 hrs.
Let the total work be 6 unit.
So, work done by them in 1 hour = = 1 unit.
According to the question,
They worked for 4 hours, work done = 4 unit
Remaining work = 2 unit
This 2 unit is done by (A + B) in 4 hrs.
So, (A + B) one-day work =
The one-day work of (A + B + C) → 1
So, C → 1
1
2
Time by C = = 12 hrs.
S14. Ans.(c)
Sol. In 1 min it admits = 6 liter.
In 60 min it admits → 60 × 6 liter.
According to the question,
Water leaked in 4 hrs. = Water filled in 12 hours
= 12 × 60 × 6
= 4320 liters.
Thus, the tank holds the water which can be emptied in 8 hrs.
= 4320 × 2
= 8640 liters
S15. Ans.(a)
Sol. Filling pipe A takes = 8 hrs.
B is empty pipe.
According to the question,
A→8
A + B → 10
So, B → –1
/
So, leak can empty half of the tank in =
= 20 hrs.
S16. Ans.(d)
Sol. (A + B)’s 2 days’ work = .
S17. Ans.(b)
Sol. A’s 2 days’ work = 2 .
S18. Ans.(b)
Sol. (20 × 16) women can complete the work in 1 day.
∴1 woman’s 1 day’s work = .
(16 × 15) men can complete the work in 1 day.
∴1 man’s 1 day’s work = .
So, required ratio = = 4 : 3.
S19. Ans.(c)
Sol. 10 men’s 1 day’s work = ; 15 women’s 1 day’s work = .
S20. Ans.(a)
Sol. 1 man’s 1 day’s work = .
S21. Ans.(a)
Sol. Let 1 woman’s 1 day’s work = x.
Then, 1 man’s 1 day’s work = and 1 child’s 1 day’s work = .
So, 4 .
∴1 woman alone can complete the work in 49 days.
So, to complete the work in 7 days, number of women required = = 7.
S22. Ans.(d)
Sol. (1 man + 1 woman)’s 1 day’s work = .
Work done by 1 man and 1 woman in day = .
Remaining work = 1 .
Work done by 1 boy in day = .
∴Number of boys required = 48 = 41.
S23. Ans.(d)
Sol. 1 man’s 1 day’s work = . (10 men + 15 women)’s 1 day’s work = .
15 women’s 1 day’s work = .
1 woman’s 1 day’s work = .
∴1 woman alone can complete the work in 225 days.
S24. Ans.(b)
Sol. Let 1 man’s 1 day’s work = x and 1 woman’s 1 day’s work = y.
Then, 4x + 6y = and 3x + 7y = .
Solving these two equations, we get: x = ,y= .
∴1 woman’s 1 day’s work = .
⇒10 women’s 1 day’s work = 10 .
Hence, 10 women will complete the work in 40 days.
S25. Ans.(b)
Sol. 1 man’s 1 day’s work = ; 1 woman’s 1 day’s work = .
Work done in 12 days = 12 12 .
Remaining work = 1 .
(16 men + 16 women)’s 2 days’ work = 2 2 .
Remaining work = .
work is done in 1 day by 1 man.
∴ work will be done in 2 days by 384 = 24 men.
S26. Ans.(a)
Sol. 1 man’s 1 day’s work = ; 1 woman’s 1 day’s work = .
6 men’s 2 days’ work = 2 . Remaining work = 1 .
Now, work is done in 1 day by 1 woman.
So, work will be done in 3 days by 60 = 15 women.
S27. Ans.(b)
Sol. Work done by A = 1 .
∴A : (B + C) = = 15 : 8.
So, A’s share = Rs. 529 = Rs. 345.
S28. Ans.(c)
Sol. (A + B)’s 1 day’s work = .
Work done by B in 23 days = 23 . Remaining work = 1 .
Now, work was done by (A + B) in 1 day.
work was done by (A + B) in 1 = 9 days.
∴A left after 9 days.
S29. Ans.(b)
Sol. Kim’s wages : David’s wages = Kim’s 1 day’s work : David’s 1 day’s work
= =2:3
∴Kim’s share = Rs. 150 = Rs. 60.
S30. Ans.(b)
Sol. C’s 1 day’s work = .
A’s wages : B’s wages : C’s wages = = 4 : 3 : 1.
∴C’s share = Rs. 3200 = Rs. 400.