100% found this document useful (2 votes)
3K views113 pages

500+ Time and Work Question & Answers Free PDF - Download Now@www - Studywale.co

This document provides an overview of quantitative aptitude concepts related to time and work. It discusses the key factors of time taken to complete a job, unit of work done, and number of persons doing the job. Several examples are provided to demonstrate calculating the number of days taken to complete a job when multiple people work together or separately. The concept of efficiency, defined as the percentage of work one person can do in a day, is also explained through examples. Tricks for solving time and work problems by using denominators of days are discussed.

Uploaded by

akash sonavane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
3K views113 pages

500+ Time and Work Question & Answers Free PDF - Download Now@www - Studywale.co

This document provides an overview of quantitative aptitude concepts related to time and work. It discusses the key factors of time taken to complete a job, unit of work done, and number of persons doing the job. Several examples are provided to demonstrate calculating the number of days taken to complete a job when multiple people work together or separately. The concept of efficiency, defined as the percentage of work one person can do in a day, is also explained through examples. Tricks for solving time and work problems by using denominators of days are discussed.

Uploaded by

akash sonavane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 113

Download From - www.studywale.

co

Quantitative Aptitude Made Easy

Buy this book from BankExamsToday.com Page 1


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Index
Foreword ................................................................................... 1
Preface ....................................................................................... 3
Introduction ............................................................................... 5

Chapter 1 Number System


Chapter 2 Average
Chapter 3 LCM & HCF
Chapter 4 Ratio & Proportion
Chapter 5 Percentage
Chapter 6 Partnership
Chapter 7 Mixtures & Alligations
Chapter 8 Simple Interest & Compound Interest
Chapter 9 Problems Based on Ages
Chapter 10 Profit & Loss
Chapter 11 Sequence & Series
Chapter 12 Time & Work
Chapter 13 Pipes & Cisterns
Chapter 14 Time & Distance
Chapter 15 Boats & Streams
Chapter 16 Calendar
Chapter 17 Clocks
Chapter 18 Permutation & Combination
Chapter 19 Probability
Chapter 20 Trigonometry
Chapter 21 Geometry
Chapter 22 Mensuration
Chapter 23 Data Sufficiency
Chapter 24 Data Interpretation

Buy this book from BankExamsToday.com Page 2


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Chapter - 12

Time and Work


Three main factors of Time and Work

There is a definite relationship between Time and Work. In this concept, there are only three factors:
 Time taken to complete a certain job
 Unit of work done
 Number of persons doing the job

There is a mental relationship between these three, discussed as follows:


Work done (W) = Number of days (Time taken) (T or D) × Number of men (M)
W=D×M

Some basic points


More number of men can do more work i.e. both are directly proportional
More number of men take less time to complete certain job i.e. both are inversely proportional
By summarizing, we get
= ×
Let us start solving some examples:

Example 1: 10 men can cut 8 trees in 16 days. In how many days can 6 men cut 10 trees?
Solution: This is a very simple example. You are given:
W1 = 8
W2 = 10
M1 = 10
M2 = 6
D1 = 16
D2 = ?

Using formula,
= ×
= ×
⇒D2 = 33.3

Concept of efficiency
This means, "How much work one person can do in one day (expressed in percentage)"
For example: A person can do a job in 2 days
⇒ He can do 50% work in one day
Therefore, his efficiency will be 50%
Just a 2-step concept
This concept involves two steps to calculate efficiency:

 Convert into fraction i.e. per day work


 Multiply with 100 i.e. convert into percentage
Buy this book from BankExamsToday.com Page 3
Download From - www.studywale.co

Quantitative Aptitude Made Easy

Try the following example first, then re-read above points

Example 2: If a person can complete his work in 5days. What will be his efficiency?
Solution: Number of days a person take to complete his work = 5
⇒ He is doing 1/5 th work per day (converted into fraction)
Convert it into percentage:
100/5 = 20%
Therefore, his efficiency is 20%.
Summarizing, If a person can do his job in n days, efficiency will be

Efficiency = %
Note: Negative efficiency cancels the positive efficiency
For Example: Positive efficiency = 5%
Negative efficiency = 1.5%
Net efficiency = 5- 1.5 = 3.5%
As we all know, in competitive exams time management is very important. I suggest you to learn the
fractions till 15.

Number of days required to Work/Day Efficiency (%)


complete work
N 1/n 100/n
1 1 100
2 1/2 50
3 1/3 33.33
4 1/4 25
5 1/5 20
6 1/6 16.66
7 1/7 14.28
8 1/8 12.5
9 1/9 11.11
10 1/10 10
11 1/11 9.09
12 1/12 8.25
13 1/13 7.69
14 1/14 7.14
15 1/15 6.66

Example 3: A can do a job in 10 days. B can do a job in 5 days. In how many days they can complete
the job if they work together?

Solution: Consider the above table


A's efficiency = 10%
B's efficiency = 20%
A+ B efficiency = 10 + 20 = 30%
This means, In one day A and B together can do 30% of work.
Therefore, Number of days A and B together take to do 100% of work =
⇒3.33 days

Buy this book from BankExamsToday.com Page 4


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Example 4: A and B together can do a job in 4 days. If A can do job in 12 days if he works alone, then
how many days B alone take to complete the job?

Solution: A+B take = 4 days


⇒ A+B's efficiency = 25% i.e. they together do 25% of work in one day
A takes = 12 days
⇒ A's efficiency = 8.33%
B's efficiency = (A+B) - (A)

⇒ 25% - 8.33% = 16.66%


This means, B can do 16.66% work in one day
Therefore, to complete the job he will take = .
days
⇒ 6days

Example 5: A and B can do job in 8 days. B and C can do same job in 12 days. A, B and C together can
do same job in 6 days. In how many days A and C together can complete the job?

Solution: You are given that:


A+B's efficiency = 12.5%
B+C's efficiency = 8.33%
A+B+C's efficiency = 16.66%
we need to find A+C
Consider, 2(A+B+C) = (A+B) + (B+C) + (C+A)
⇒2(16.66) = 12.5+ 8.33 + (C+A)
⇒ C+A = 12.49 = 12.5%
Therefore, A and C takes= = 8 days
.
Hope you all understand this topic. I will soon update questions for your practice.

Trick
One simple technique is using days in denominator while solving questions. For example, A can do a
job in 3 days and B can do the same job in 6 days. In how much time they can do the job together.

Solution - 1/3 + 1/6 = 1/2, hence 2 days is the answer.


Examiner can set the question in opposite way and can ask you how much time A or B alone will take
to complete the job. It is quite easy to calculate said question by putting values in equation we
arrived in above question.

You need to understand one simple concept - If A can do a job in 10 day then in one day A can do
1/10th of job.

Now let's solve questions with this trick


Question 1 - A take 5 days to complete a job and B takes 10 days to complete the same job. In how
much time they will complete the job together?

Solution - A's efficiency = 20%, B's efficiency = 10%. If they work together they can do 30% of the job
in a day. To complete the job they need 3.33 days.

Buy this book from BankExamsToday.com Page 5


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Question 2 - A is twice as efficient as B and can complete a job 30 days before B. In how much they
can complete the job together?

Solution - Let efficiency percentage as x


A's efficiency = 2x and B's efficiency = x
A is twice efficient and can complete the job 30 days before B. So,
A can complete the job in 30 days and B can complete the job in 60 days

A's efficiency = 1/30 = 3.33%


B's efficiency = 1/60 = 1.66%
Both can do 5% (3.33% + 1.66%) of the job in 1 day.
So the can complete the whole job in 20 days (100/5)

Question 3 - A tank can be filled in 20 minutes. There is a leakage which can empty it in 60 minutes.
In how many minutes tank can be filled?

Solution -
Method 1
⇒ Efficiency of filling pipe = 20 minutes = 1/3 hour = 300%
⇒ Efficiency of leakage = 60 minutes = 100%

We need to deduct efficiency of leakage so final efficiency is 200%. We are taking 100% = 1 Hour as
base so answer is 30 minutes.

Method 2
⇒ Efficiency of filling pipe = 100/20 = 5%
⇒ Efficiency of leakage pipe = 100/60 = 1.66%
⇒ Net filling efficiency = 3.33%
So, tank can be filled in = 100/3.33% = 30 minutes

You can change the base to minutes or even seconds.

Question 4 - 4 men and 6 women working together can complete the work within 10 days. 3 men
and 7 women working together will complete the same work within 8 days. In how many days 10
women will complete this work?

Solution - Let number of men =x, number of women = y


⇒ Efficiency of 4 men and 6 women = 100/10 = 10%
⇒ So, 4x+6y = 10
Above equation means 4 men and 6 women can do 10% of a the job in one day.

⇒ Efficiency of 3 men and 7 women = 100/8 = 12.5%


So, 3x+7y = 12.5

By solving both equations we get, x = -0.5 and y = 2

⇒ Efficiency of 1 woman(y) = 2% per day


⇒ Efficiency of 10 women per day = 20%
So 10 women can complete the job in 100/20 = 5 days

Buy this book from BankExamsToday.com Page 6


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Question 5 - A and B together can complete a task in 20 days. B and C together can complete the
same task in 30 days. A and C together can complete the same task in 30 days. What is the
respective ratio of the number of days taken by A when completing the same task alone to the
number of days taken by C when completing the same task alone?

Solution - ⇒ Efficiency of A and B = 1/20 per day = 5% per day ___________1


⇒ Efficiency of B and C = 1/30 per day = 3.33% per day_________2
⇒ Efficiency of C and A = 1/30 per day = 3.33% per day_________3

Taking equation 2 and 3 together


⇒ B + C = 3.33% and C + A = 3.33%
⇒ C and 3.33% will be removed. Hence A = B
⇒ Efficiency of A = B = 5%/2 = 2.5% = 1/40
⇒ Efficiency of C = 3.33% - 2.5% = 0.833% = 1/120
⇒ A can do the job in 40 days and C can do the job in 120 days he they work alone.
⇒ Ratio of number of days in which A and C can complete the job 1:3.

Exercise - 12

1) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the
fraction of the work that is left is:
a) 1/4 b) 1/10 c) 7/15
d) 8/15 e) None of these

2) A can lay railway track between two given stations in 16 days and B can do the same job in
12 days, with help of C, they did the job in 4 days only. Then, C alone can do the job in:
a) 9 b) 9 c) 9
d) 10 e) None of these

3) A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can
A do the work if he is assisted by B and C on every third day?
a) 12 days b) 15 days c) 16 days
d) 18 days e) None of these

4) A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than
B. Working together, they can do it in:
a) 20 days b) 22 c) 25 days
d) 30 days e) None of these

5) A alone can do a piece of work in 6 days and B alone 8 days. A and B undertook to do it for
Rs.3200. With the help of C, they completed the work in 3 days. How much is to be paid to
C?
a) Rs.375 b) Rs.400 c) Rs.600
d) Rs.800 e) None of these

6) If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the
same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
a) 4 days b) 5 days c) 6 days
d) 7 days e) None of these

Buy this book from BankExamsToday.com Page 7


Download From - www.studywale.co

Quantitative Aptitude Made Easy

7) A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C
together can do it in 2 hours. How long will B alone take to do it?
a) 8 hours b) 10 hours c) 12 hours
d) 24 hours e) None of these

8) A can do a certain work in the same time in which B and C together can do it. If A and B
together could do it in 10 days and C alone in 50 days, then B alone could do it in:
a) 15 days b) 20 days c) 25 days
d) 30 days e) None of these

9) A does 80% of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days. How long B alone would take to do the whole work?
a) 23 days b) 37 days c) 37
d) 40 days e) None of these

10) A machine P can print one lakh books in 8 hours, machine Q can print the same number of
books in 10 hours while machine R can print them in 12 hours. All the machines are started at
9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete
work. Approximately at what time will the work (to print one lakh books) be finished?
a) 11:30 A.M. b) 12 noon c) 12:30 P.M.
d) 1:00 P.M. e) None of these

11) A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days
and left the job. In how many days, A alone can finish the remaining work?
a) 5 b) 5 c) 6
d) 8 e) None of these

12) 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete
it in 10 days. In how many days will 10 women complete it?
a) 35 b) 40 c) 45
d) 50 e) None of these

13) A and B can together finish a work 30 days. They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work. In how many days A alone can
finish the work?
a) 45 b) 50 c) 54
d) 60 e) None of these

14) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8
days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how
many days can they complete the work?
a) 5 b) 5 c) 6
d) 6 e) None of these

15) 10 women can complete a work in 7 days and 10 children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
a) 3 b) 5 c) 7
d) Data inadequate e) None of these

16) X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone
and then after 4 days Y joined him till the completion of the work. How long did the work
last?

Buy this book from BankExamsToday.com Page 8


Download From - www.studywale.co

Quantitative Aptitude Made Easy

a) 6 days b) 10 days c) 15 days


d) 20 days e) None of these

17) A is 30% more efficient than B. How much time will they, working together, take to complete
a job which A alone could have done in 23 days?
a) 11 days b) 13 days c) 20
d) Data inadequate e) None of these

18) Ravi and Kumar are working on an assignment. Ravi takes 6 hours to type 32 pages on a
computer, while Kumar takes 5 hours to type 40 pages. How much time will they take,
working together on two different computers to type an assignment of 110 pages?
a) 7 hours 30 minutes b) 8 hours c) 8 hours 15 minutes
d) 8 hours 25 minutes e) None of these

19) A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together,
they will complete the same work in:
a) day b) day c) 3 ]
d) 4 days e) None of these

20) Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The
number of days taken by Tanya to do the same piece of work is:
a) 15 b) 16 c) 18
d) 25 e) None of these

21) A takes twice as much time as B or thrice as much time as C to finish a piece of work.
Working together, they can finish the work in 2 days. B can do the work alone in:
a) 4 days b) 6 days c) 8 days
d) 12 days e) None of these

22) A and B can complete a work in 15 days and 10 days respectively. They started doing the
work together but after 2 days B had to lea0ve and A alone completed the remaining work.
The whole work was completed in:
a) 8 days b) 10 days c) 12 days
d) 15 days e) None of these

23) A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days
and C and A in 20 days. They all work together for 10 days when B and C leave. How many
days more will A take to finish the work?
a) 18 days b) 24 days c) 30 days
d) 36 days e) None of these

24) A works twice as fast as B. If B can complete a work in 12 days independently, the number of
days in which A and B can together finish the work in:
a) 4 days b) 6 days c) 8 days
d) 18 days e) None of these

25) Twenty women can do a work in sixteen days. Sixteen men can complete the same work in
fifteen days. What is the ration between the capacity of a man and a woman?
a) 3 : 4 b) 4 : 3 c) 5 : 3
d) Date inadequate e) None of these

26) A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C
together can finish it in 6 days. A and C together will do it in:

Buy this book from BankExamsToday.com Page 9


Download From - www.studywale.co

Quantitative Aptitude Made Easy

a) 4 days b) 6 days c) 8 days


d) 12 days e) None of these

27) A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are
forced to leave after 3 days. The remaining work was done by A in:
a) 5 days b) 6 days c) 10 days
d) 10 e) None of these

28) X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?
a) 13 b) 15 days c) 20 days
d) 26 days e) None of these

29) A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be
done by A alone in:
a) 9 b) 11 days c) 12
d) 16 e) None of these

30) P is thrice as efficient as Q and is therefore able to finish a piece of work in 60 days less than
Q. Find the time in which P and Q can complete the work individually.
a) 90 days, 30 days b) 60 days, 20 days c) 65 days, 30 days
d) 85 days, 90 days e) None of these

31) A tub can be filled in 20 minutes but there is a leakage in it which can empty the full tub in 60
minutes. In how many minutes it can be filled?
a) 10 minutes b) 30 minutes c) 40 minutes
d) 25 minutes e) None of these

32) A can do a piece of work in 14 days while B can do it in 21 days. In how many days, working
together they will complete the whole work?
a) 10.5 b) 8 c) 8.4
d) 9 e) None of these

33) A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8
days more than A, what is the number of days taken by A to finish the whole work, alone?
a) 4 b) 2 c) 12
d) 16 e) None of these

34) Aman can do a piece of work in 14 days, while Suneeta can do the same work in 21 days.
They started the work together but 3 days before the completion of the work, Aman left the
work. The total number of days to complete the work is :
a) 7 b) 8.5 c) 5
d) 10 e) None of these

35) Karan can do a work in 10 days while Sohan can do the same work in 20 days. They started
work together. After 3 days Karan left the work and Sohan completed it. For how many days
Sohan worked alone more than the number of days required when both worked together?
a)4 b) 3 c) 2
d) 3 e) None of these

Buy this book from BankExamsToday.com Page 10


Download From - www.studywale.co

Quantitative Aptitude Made Easy

36) A and B undertook a work for Rs.350. A got Rs.150 more than that of B, when they worked
together. B takes 9 days more than A, when they work individually. In how many days A and
B working together can do the whole work:
a) 5 b) 4 c) 4
d) 5 e) None of these

37) When A, B and C are deployed for a task, A and B together do 70% of the work and B and C
together do 50% of the work. Who is most efficient?
a) a b) b c) c
d) Data inadequate e) None of these

38) A contractor undertook a work to complete in 60 days. But just after 20 days he observed that
only th of the project work had been completed. To complete the work in time (i.e., in rest
days) minimum how many workers he had to increase, if there were initially 75 workers were
deployed for the task?
a) 25 b) 50 c) 75
d) Data inadequate e) None of these

39) If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of
work will be done by 1 man, 1 woman and 1 boy in :
a) 48 days b) 36 days c) 45 days
d) Data inadequate e) None of these

40) A contractor undertook to complete the work in 40 days and he deployed 20 men for his
work. 8 days before the scheduled time he realized that 1/3rd of the work was still to be done.
How many more men were required to complete the work in stipulated time?
a) 16 b) 15 c) 20
d) 25 e) None of these

41) B and C are equally efficient, but the efficiency of A is half of each B and C. A and B started
a work and 3 days later C joined them. If A alone can do the work in 14 days, then in how
many more days the work will be completed?
a) 1 b) 2 c) 3
d) 4.5 e) None of these

42) A and B together can complete a piece of work in 4 days. If A alone can complete the same
work in 12 days, in how many days can B alone complete that work?
a) 6 days b) 12 c) 8 days
d) 9 days e) None of these

43) 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 boys can finish the
same work in 5 days. Also 2 men and 3 women can finish the same work in 5 days. In how
many days 1 man, 1 woman and one boy can finish the work, at their double efficiency?
a) 4 b) 4 c) 3
d) Data inadequate e) None of these

44) A and B undertake to do a piece of work for Rs.600. A alone can do it in 6 days while B alone
can do it in 8 days. With the help of C, they finish it in 3 days. Find the share of each.
a) Rs.80 b) Rs.75 c) Rs.90
d) Rs.82 e) None of these

Buy this book from BankExamsToday.com Page 11


Download From - www.studywale.co

Quantitative Aptitude Made Easy

45) Tap A can fill the empty tank in 12 hours, but due to a leak in the bottom it is filled in 15
hours, if the tank is full and then tap A is closed then in how many hours the leak can empty
it?
a) 45 hours b) 48 hours c) 52 hours
d) 60 hours e) None of these

46) A is twice as good a workman as B and together they finish a piece of work in 18 days. In
how many days will A alone finish the work?
a) 72 days b) 30 days c) 27 days
d) 32 days e) None of these

47) Pipe A basically used as inlet pipe and pipe B is used as outlet pipe. Pipes A and B both are
opened simultaneously, all the time. When pipe A fills the tank and B empty the tank, it will
take double the time than when both the pipes fill the tank. When pipe B is used for filling the
tank, its efficiency remains constant. What is the ratio of efficiency of pipe A and pipe B
respectively?
a) 3 : 1 b) 5 : 2 c) 1 : 3
d) 3 : 2 e) None of these

48) 45 men can complete a work in 16 days. Six days after they started working. 30 more men
joined them. How many days will they now take to complete the remaining work?
a) 18 days b) 12 days c) 9 days
d) 6 days e) None of these

49) Two pipes A and B can fill a cistern in 15 hours and 10 hours respectively. A tap C can empty
the full cistern in 30 hours. All the three taps were open for 2 hours, when it was remembered
that the emptying tap had been left open. It was then closed. How many hours more would it
take for the cistern to be filled?
a) 30 min. b) 1.2 hours c) 24 min.
d) 35 min. e) None of these

50) A tyre has two punctures. The first puncture alone would have made the tyre flat in 9 minutes
and the second alone would have done it in 6 minutes. If air leaks out at a constant rate, how
long does it take both the punctures together to make it flat?
a) 1 b) 3 c) 3
d) 4 e) None of these

51) A single reservoir supplies the petrol to the whole city, while the reservoir is fed by a single
pipeline filling the reservoir with the stream of uniform volume. When the reservoir is full
and if 40,000 litres of petrol is used daily, the supply fails in 90 days. If 32,000 litres of petrol
is used daily, it fails in 60 days. How much petrol can be used daily without the supply every
failing?
a) 64000 litres b) 56000 litres c) 78000 litres
d) 60000 litres e) None of these

52) A is 50% more efficient than B. C does half of the work done by A and B together. If C alone
does the work in 40 days, then A, B and C together can do the work in :
a) 13 days b) 15 days c) 20 days
d) 30 days e) None of these

53) The total number of men, women and children working in a factory is 18. They earn Rs.4000
in a day. If the sum of the wages of all men, all women and all children is in the ratio of 18 :

Buy this book from BankExamsToday.com Page 12


Download From - www.studywale.co

Quantitative Aptitude Made Easy

10 : 12 and if the wages of an individual man, woman and child is in the ratio 6 : 5 : 3, then
how much a woman earn in a day?
a) Rs.400 b) Rs.250 c) Rs.150
d) Rs.120 e) None of these

54) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8
days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how
many days can they complete the work?
a) 5 b) 5 c) 6
d) 6 e) None of these

55) Eklavya can do the 6 times the actual work in 36 days while Faizal can do the one-fourth of
the original work in 3 days. In how many days will both working together complete the 3
times of the originalwork?
a) 6 b) 10 c) 12
d) 15 e) None of these

56) A and B can together finish a work in 30 days. They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work. In how many days A alone can
finish the job?
a) 40 b) 50 c) 54
d) 60 e) None of these

57) Aman and Raman are two workers. Working together they can complete the whole work in
10 hours. If the Aman worked for 2.5 hours and Raman worked for 8.5 hours, still there was
half of the work to be done. In how many hours Aman working alone, can complete the whole
work?
a) 24 hours b) 17 hours c) 40 hours
d) Data inadequate e) None of these

58) 5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a man and a boy are in the ratio :
a) 1 : 2 b) 2 : 1 c) 1 : 3
d) 3 : 1 e) None of these

59) A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200. With the help of C, they completed the work in 3 days. How much is to be paid
to C?
a) Rs.375 b) Rs.400 c) Rs.600
d) Rs.800 e) None of these

60) If there is leakage also which is capable of draining out the liquid drom the tank at half of the
rate of outlet pipe, then what is the time taken to fill the empty tank when both the pipes are
opened?
a) 3 hours b) 3 hours c) 4 hours
d) Data inadequate e) None of these

61) A, B and C are employed to do a piece of work for Rs.529. A and B together are supposed to
do of the work and B and C together of the work. What amount should A be paid?
a) Rs.315 b) Rs.345 c) Rs.355
d) Rs.375 e) None of these

Buy this book from BankExamsToday.com Page 13


Download From - www.studywale.co

Quantitative Aptitude Made Easy

62) A and B can do a job together in 7 days. A is 1 times as efficient as B. The same job can be
done by A alone in :
a) 9 days b) 11 days c) 12 days
d) 16 days e) None of these

63) A, B and C can do a piece of work in 36, 54 and 72 days respectively. They started the work
but A left 8 days before the completion of the work while B left 12 days before the
completion. The number of days for which C worked is :
a) 4 b) 8 c) 12
d) 24 e) None of these

64) A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will
complete the work?
a) 10 days b) 11 days c) 15 days
d) 20 days e) None of these

65) 10 women can complete a work in 7 days and 10 children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
a) 3 b) 5 c) 7
d) Data inadequate e) None of these

66) 12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them.
How many days will they take to complete the remaining work?
a) 2 days b) 3 days c) 4 days
d) 5 days e) None of these

67) A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and C
together earn Rs.152. The daily earning of C is :
a) Rs.40 b) Rs.68 c) Rs.112
d) Rs.150 e) None of these

Solutions:

1. Option D

A’s 1 day’s work =


B’s 1 day’s work =

(A + B)’s 1 day’s work = [ + ]=


(A + B)’s 4 day’s work = [ × 4] =

Therefore, Remaining work = [1 ⎯ ] =

2. Option C

(A + B + C)’s 1 day’s work =

Buy this book from BankExamsToday.com Page 14


Download From - www.studywale.co

Quantitative Aptitude Made Easy

A’s 1 day’s work =


B’s 1 day’s work =

C’s 1 day’s work = ⎯ [ + ]=[ ⎯ ]=


So, C alone can do the work in =9

3. Option B
A’s 2 day’s work =[ ×2 = ]
(A + B + C)’s 1 day’s work =[ + + ]= =

Work done in 3 days =[ + ]=


Now, work is done in 3 days.
Whole work will be done in (3 × 5) = 15 days

4. Option B

Ratio of times taken by A and B = 1 : 3


The time difference is (3 ⎯1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes [ ]
× 60 = 90 days
So, A takes 30 days to do the work.
A’s 1 day’s work =
B’s 1 day’s work =

(A + B)’s 1 day’s work = [ + ]= =


A and B together can do the work in = 22 days

5. Option B

C’s 1 day’s work = ⎯ [ + ]= ⎯ =


A’s wages : B’s wages : C’s wages = : : =4:3:1

C’s share (for 3 days) = Rs. 3 ×[ ]


× 3200 = Rs.400

6. Option A

Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work = y


Then, 6x + 8y = and 26x + 48y =
Solving these two equations, we get : x = and y =

(15 men + 20 boy)’s 1 day’s work = [ + ]=


15 men and 20 boys can do the work in 4 days.

7. Option C

Buy this book from BankExamsToday.com Page 15


Download From - www.studywale.co

Quantitative Aptitude Made Easy

A’s 1 hour’s work =


(B + C)’s 1 hour’s work =
(A + C)’s 1 hour’s work =

(A + B + C)’s 1 hour’s work =[ + ]=


B’s 1 hour’s work ⎯=[ ]=
B alone will take 12 hours to do the work.

8. Option C

(A + B)’s 1 day’s work =


C’s 1 day’s work =

(A + B + C)’s 1 day’s work = + [ ]


= = …….. (i)
A’s 1 day’s work = (B + C)’s 1 day’s work …….. (ii)
From (i) and (ii), we get 2 × (A’s 1 day’s work) =
A’s day’s work =

B’s 1 day’s work= [ ⎯ = =]


So, B alone could do the work in 25 days.

9. Option C
Whole work is done by A in 20 × [ ] = 25 days
[ ]
Now, 1 ⎯ i.e., work is done by A and B in 3 days.
Whole work will be done by A and B in (3 × 5) = 15 days.
A’s 1 day’s work = , (A + B)’s 1 day’s work =

B’s 1 day’s work = [ ⎯ ]= =


So, B alone would do the work in =37 days

10. Option D

(P + Q + R)’s 1 hour’s work = [ + + ]=


Work done by P, Q and R in 2 hours =[ × 2] =

Remaining work = [1 ⎯ ] =

(Q + R)’s 1 hour’s work =[ + ]=


Now, work is done by Q and R in 1 hour.

So, work will be done by Q and R in × [= hours ] 2 hours


So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.

11. Option C

Buy this book from BankExamsToday.com Page 16


Download From - www.studywale.co

Quantitative Aptitude Made Easy

B’s 10 day’s work = [ × 10] =


Remaining work = [1 ⎯ ] =
Now, work is done by A in 1 day.

[
work is done by A in 18 × ] = 6 days.
12. Option B

Let 1 man’s 1 day’s work = x and 1 woman’s 1 day’s work = y.


Then, 4x + 6y = and 3x + 7y =
Solving the two equations, we get x = ,y=
1 woman’s 1 day’s work =

10 women’s 1 day’s work = × 10 =[ ]


Hence, 10 women will complete the work in 40 days.

13. Option D
(A + B)’s 20 day’s work = [ × 20] =
Remaining work = [1 ⎯ ] =
Now, work is done by A in 20 days.
Therefore, the whole work will be done by A in (20 × 3) = 60 days.

14. Option A

P can complete the work in (12 × 8) hrs. = 96 hrs.


Q can complete the work in (8 × 10) hrs. = 80 hrs.
P’s 1 hour’s work = and Q’s 1 hour’s work =

[P + Q)’s 1 hour’s work = [ + ]=


[ ] hrs.
So, both P and Q will finish the work in

Number of days of 8 hours each = [ × ]= days =5 days

15. Option C

1 woman’s 1 day’s work =


1 child’s 1 day’s work =

(5 women + 10 children)’s day’s work = + [= + ] [ ]=


5 women and 10 children will complete the work in 7 days.

16. Option B
Work done by X in 4 days = [ ]
×4 =

Buy this book from BankExamsToday.com Page 17


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Remaining work [
= 1⎯ ]=
(X + Y)’s 1 day’s work =[ + ]= =
Now, work is done by X and Y in 1 day.

So, work will be done by X and Y in × [


= 6 days ]
Hence, total time taken = (6 + 4) days = 10 days

17. Option B

Ration of times taken by A and B = 100 : 130 = 10 : 13


Suppose B takes x days to do the work.

Then, 10 : 13:: 23 : x x= [ ×
] x=
A’s 1 day’s work =
B’s 1 day’s work =

(A + B)’s 1 day’s work = + [ = = ]


Therefore, A and B together can complete the work in 13 days.

18. Option C

Number of pages typed by Ravi in 1 hour = =


Number of pages typed by Kumar in 1 hour = =8

Number of pages typed by both in 1 hour = [ + 8] =


Time taken by both to type 110 pages = [110 × ] hours
=8 hours or 8 hours 15 minutes

19. Option C

If A can do a piece of work in n days, then A’s 1 day’s work =

(A + B + C)’s 1 day’s work = [ + + ]=


Formula: If A’s 1 day’s work = , then A can finish the work in n days.

So, all the three together will complete the job in [ ] days = 3
20. Option B

Ration of times taken by Sakshi and Tanya = 125 : 100 = 5 : 4


Suppose Tanya takes x days to do the work.
5 : 4::20 : x x= [ ×
]
x = 16 days
Hence, Tanya takes 16 days to complete the work.

Buy this book from BankExamsToday.com Page 18


Download From - www.studywale.co

Quantitative Aptitude Made Easy

21. Option B

Suppose A, B and C take x, and days respectively to finish the work.

Then, [ + + ]=
=
x = 12
So, B takes (12/2) = 6 days to finish the work.

22. Option C

(A + B)’s 1 day’s work [ + ]= =

Work done by A and B in 2 days = [ × 2] =

Remaining work = [1 ⎯ ] =
Now, work is done by A in 1 day.

work will be done by A in 15 ×[ ] = 10 days


Hence, the total time taken = (10 + 2) = 12 days.

23. Option A
2 (A + B + C)’s 1 day’s work = [ + + ]= =
Therefore, (A + B + C)’s 1 day’s work = =
×
Work done by A, B, C in 10 days = =

Remaining work [
= 1⎯ ]=
A’s 1 day’s work =[ ⎯ ]=
Now, work is done by A in 1 day.

So, [
work will be done by A in 48 × ] = 18 days.
24. Option A

Ratio of rates of working of A and B =2:1


So, ratio of times taken =1:2
B’s 1 day’s work =
A’s 1 day’s work = ; (2 times of B’s work)

(A + B)’s 1 day’s work = [ + ]= =


So, A and B together can finish the work in 4 days.

25. Option B

(20 × 16) women can complete the work in 1 day.


1 woman’s 1 day’s work =
(16 × 15) men can complete the work in 1 day.

Buy this book from BankExamsToday.com Page 19


Download From - www.studywale.co

Quantitative Aptitude Made Easy

1 man’s 1 day’s work =


So, required ratio = :
= :
= 4 : 3 (cross multiplied)

26. Option C

(A + B + C)’s 1 day’s work =


(A + B)’s 1 day’s work =
(B + C)’s 1 day’s work =

(A + C)’s 1 day’s work [


= 2× ] ⎯[ + ]
=[ ⎯ ]
=
=
So, A and C together will do the work in 8 days.

27. Option C

(B + C)’s 1 day’s work [ + ]= =

Work done by B and C in 3 days = [ × 3] =

Remaining work = [1 ⎯ ] =
Now, work is done by A in 1 day.

So, [
work is done by A in 24 × ] = 10 days.
28. Option A
Work done by X in 8 days = [ × 8] =
Remaining work = [1 ⎯ ] =
Now, work is done by Y in 16 days.

[
Whole work will be done by Y in 16 × ] = 20 days.
X’s 1 day’s work = , Y’s 1 day’s work =

(X + Y)’s 1 day’s work = [ + ]=


Hence, X and Y will together complete the work in [ ] = 13 days.

29. Option B

(A’s 1 day’s work) : (B’s 1 day’s work) = : 1 = 7 : 4


Let A’s and B’s 1 day’s work be 7x and 4x respectively.
Then , 7x + 4x = 11x = x=

Buy this book from BankExamsToday.com Page 20


Download From - www.studywale.co

Quantitative Aptitude Made Easy

A’s 1 day’s work = [ ]


×7 =

30. Option A

Efficiency of P : Q = 3 : 1
Required number of days of P : Q = 1 : 3
i.e., if P requires x days then Q requires 3x days
but 3x ⎯x = 60
2x = 60
x = 30 and 3x = 90
Thus P can finish the work in 30 days and Q can finish the work in 90 days.

31. Option B

Filling efficiency = 5% 5=
Emptying efficiency = 1.66% 1.66 =
Net efficiency = 5 ⎯1.66 = 3.33%
Required time to full the tub = . = 30 minutes

32. Option C

Efficiency of A = 7.14%
Efficiency of B = 4.76%
Efficiency of A + B = 11.9%
Number of days required by A and B, working together = .
= 8.4 days
33. Option A

Efficiency of A + B = 33.33% = [ ]
Ratio of efficiency of A and B = 3 : 1
Efficiency of A = × 33.33 = 25%
Number of days taken by A = 4 = =4

34. Option A

3 days before the completion of the work Aman left the work means in last 3 days only
Suneeta has worked alone.
So, in last 3 days worked done by Suneeta = 3 × =

[
So, the rest 1 ⎯ ]= work was done by Aman and Suneeta both.
/
Number of days in which Aman and Suneeta worked together = /
= =7 days

35. Option A

Karan’s efficiency = 10%


Sohan’s efficiency = 5%
Work done by Karan and Sohan together in 3 days = 15 × 3 = 45%
Now, number of days in which B completed rest (55%) work alone = = 11
Buy this book from BankExamsToday.com Page 21
Download From - www.studywale.co

Quantitative Aptitude Made Easy

Total number of days in which B worked = 3 + 11 = 14


Now number of days required by B, when A and B both worked together = =6

[ ]
Required difference in number of days = (11) ⎯ 6
= =4 days

36. Option B

A’s share = Rs.250


B’s share = Rs.100
It means the ratio of efficiency of A : B = 250 : 100 = 5 : 2
Ratio of days taken by A and B = 2x : 5x
Now, 5x ⎯2x = 9 x=3
Number of days taken by A = 6 (efficiency = 16.66%)
Number of days taken by B = 15 (efficiency = 6.66%)
Therefore number of days taken by A and B, working together = .
= =4 days

37. Option A

A + B = 70%
B + C = 50% [A + B + B + C ⎯(A + B + C) = B]
70 + 50 ⎯100 = 20%
B = 20%
A = 50%
C = 30%
Hence, A is most efficient.

38. Option C

Work done =

Remaining work =
4 (20 × 75) = 40 × x
x = 150
Therefore 75 men should be increased.

39. Option E

Work done by 2 men = 3 women = 4 boys


1 man = 2 boys
1 women = boys
Boys × days = 4 × 52 (boys ⎯days)
Again 1 man + 1 woman + 1 boy = 2 + + 1 = boys

40. Option C

Buy this book from BankExamsToday.com Page 22


Download From - www.studywale.co

Quantitative Aptitude Made Easy

Work done =
Remaining work = , which is half of
× (20 × 32) = 8 × x
x = 40 men
Therefore, 20 more men were required.

41. Option A

Number of days taken by A to complete work alone = 14 days


Number of days taken by B to complete work alone = 7 days
Number of days taken by C to complete work alone = 7 days
One day’s work of A and B = + =
And one day’s work of A, B and C = + + =
3 day’s work of A and B = 3 × =

Remaining work = [1 ⎯ ]
/
This remaining work will be done by A, B and C = /
= 1 day

42. Option A

(A + B)’s 1 day’s work = , As 1 day’s work =

B’s 1 day’s work= [ ⎯ = ]


Hence, B alone can complete the work in 6 days.

43. Option E

Efficiency of 4 men and 2 boys = 20%


Efficiency of 3women and 4 boys = 20%
Efficiency of 2 men and 3 women = 20%

So, Efficiency of 6 men, 6 women and 6 boys = 60%


So, efficiency of 1 man, 1 woman and 1 boy = 10%
Now, since they will work at double their efficiency
Efficiency of 1 man, 1 woman and 1 boy = 20%
Required number of days =5

44. Option B

C’s 1 day’s work = ⎯ [ + ]=


A : B : C = Ratio of their 1 day’s work = : : =4:3:1

[
A’s share Rs. 600 × ] = Rs.300, B’s share = Rs.[ 600 × ] = Rs.225
C’s share = Rs.[600 ⎯(300 + 225)] = Rs.75

45. Option D
Buy this book from BankExamsToday.com Page 23
Download From - www.studywale.co

Quantitative Aptitude Made Easy

Efficiency of A = 8.33%
Effective efficiency = 6.66%, when there is leakage
So, efficiency of leakage = 1.66% = (8.33 ⎯6.66)
It means due to leakage a full tank will be empty in 60 hours.

46. Option C

(A’s 1 day’s work) : (B’s 1 day’s work) = 2 : 1


(A + B)’s 1 day’s work =
Divide in the ratio 2 : 1

So, A’s 1 day’s work = × [ = ]


Hence, A alone can finish the work in 27 days.

47. Option A

Efficiency when both pipes used to fill = A + B


And efficiency when pipe A is used to fill and pipe B is used to empty the tank = A ⎯B
So, ⎯ =
=
Thus, the ratio of efficiency of pipe A and B = 3 : 1

48. Option E

(45 × 16) men can complete the work in 1 day.


So, 1 man’s 1day’s work =

45 men’s 6 day’s work = [ ]


×6 = [
Remaining work = 1 ⎯ ]=
49. Option C

Time taken by pipes A and B to fill the whole tank = . = 6 hours


Capacity filled in 2 hours by pipes A, B and C = 2 × 13.33 = 26.66%
Remaining capacity = 73.33%
.
This remaining capacity can be filled by A and B = =4
.
So, the total time required = 2 + 4 = 6 hours 24 minutes
Thus, in this case 24 minutes extra are required.

50. Option C

1 minute’s work of both the punctures = [ + ]=


So, both the punctures will make the tyre flat in =3 min.

51. Option B

Let x litre be the per day filling and v litre be the capacity of the reservoir, then
Buy this book from BankExamsToday.com Page 24
Download From - www.studywale.co

Quantitative Aptitude Made Easy

90x + v = 40000 × 90 …. (1)


60x + v = 32000 × 60 …. (2)
Solving eq. (1) and (2), we get
x = 56000
Hence, 56000 litres per day can be used without the failure of supply.

52. Option A

(A’s 1 day’s work) : (B’s 1 day’s work) = 150 : 100 = 3 : 2


Let A’s and B’s 1 day’s work be 3x and 2x respectively.
Then, C’s 1 day’s work = [ ]=
So, = or x = [ × ]=
A’s 1 day’s work = ; B’s 1 day’s work = ; C’s 1 day’s work =
(A + B + C)’s 1 day’s work = [ + + ]= =
So, A, B and C together can do the work in = 13 days

53. Option B

Ratio of number of men, women and children = : : = 3x : 2x : 4x


So, (3x + 2x + 4x) = 18
So, x = 2
Therefore, number of women = 4
Share of all women = × 4000 = Rs.1000
(18 + 10 + 12 = 40)
So, Share of each woman = = Rs.250

54. Option A

P can complete the work in (12 × 8) hrs. = 96 hrs.


Q can complete the work in (8 × 10) hrs. = 80 hrs.
So, P’s 1 hour’s work = and Q’s 1 hour’s work =

(P + Q)’s 1 hour’s work = [ + ]=


[ ] hrs.
So, both P and Q will finish the work in

So, Number of days of 8 hours each = [ × ]= days = 5 days

55. Option C

Efficiency of Eklavya = 16.66%


Efficiency of Faizal = 8.33%
Total efficiency of Eklavya and Faizal = 25%
So, they can do actual work in 4 days
So, 3 times work requires 12 days.

56. Option D

Buy this book from BankExamsToday.com Page 25


Download From - www.studywale.co

Quantitative Aptitude Made Easy

(A + B)’s 20 day’s work = [ × 20 = ] Remaining work = [1 ⎯ ] =


Now, work is done by A in 20 days.
Whole work will be done by A in (20 × 3) = 60 days

57. Option B

Efficiency of Aman and Raman = 10%


Aman worked for 2.5 hours and Raman worked separately 8.5 hours. Which means it can be
considered that Aman and Raman worked together for 2.5 hours and Raman worked alone
for 6 hours.
Thus, Aman and Raman in 2.5 hours can complete 25% work. It means the remaining (50 ⎯
25) = 25% of the work was done by Raman in 6 hours.
Therefore, Raman can do 100% work in 24 hours. It means the efficiency of Raman = 4.16%
Therefore, efficiency of Aman = (10 ⎯4.16) = 5.83%
Thus, Aman require . = 17 hours to complete the work alone.

58. Option B

Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work = y


Then, 5x + 2y = 4 (x + y) x = 2y =

59. Option B
C’s 1 day’s work = ⎯ [ + ]= ⎯ =
A’s wages : B’s wages : C’s wages = : : =4:3:1

So, C’s share = Rs. [ ]


× 3200 = Rs.400

60. Option C

Rate of leakage = 8.33% per hour


Net efficiency = 50 ⎯(16.66 + 8.33) = 25%
Time required = = 4 hours

61. Option B

Work done by A = 1⎯[ ]=


So, A : (B + C) = : = 15 : 8

So, A’s share = Rs. [ ]


× 529 = Rs.345

62. Option B

(A’s 1 day’s work) : (B’s 1 day’s work) = : 1 = 7 : 4


Let A’s and B’s 1 day’s work be 7x and 4x respectively.
Then, 7x + 4x = 11x = x=

Buy this book from BankExamsToday.com Page 26


Download From - www.studywale.co

Quantitative Aptitude Made Easy

So, A’s 1 day’s work = [ ×7 =]


63. Option D

Suppose the work was finished in x days.


Then, A’s (x ⎯8) day’s work + B’s (x ⎯12) day’s work + C’s x day’s work = 1
⎯ ⎯
+ + =1 6(x ⎯8) + 4 (x ⎯12) + 3x = 216
So, 13x = 312 or x = 24

64. Option C
B’s 1 day’s work = [ ⎯ ]= =
Now, (A + B)’s 1 day’s work =[ + ]== [
B works for half day only ]
So, A and B together will complete the work in 15 days.

65. Option C

1 woman’s 1 day’s work = ; 1 child’s 1 day’s work =

(5 women + 10 children)’s 1 day’s work = + [


= + =] [ ]
So, 5 women and 10 children will complete the work in 7 days.

66. Option A

1 man’s 1 day’s work =

12 men’s 6 day’s work =[ ]


×6 = [
Remaining work = 1 ⎯ ]=
18 men’s 1 day’s work =[ × 18 = ]
work is done by them in 1 day.

So, work is done by them in 6 × [ ] = 2 days


67. Option A

B’s daily earning = Rs. (300 ⎯188) = Rs.112


A’s daily earning = Rs. (300 ⎯152) = Rs.148

C’s daily earning [


= Rs. 300 ⎯(112 + 148) = Rs.40]

Buy this book from BankExamsToday.com Page 27


Download From - www.studywale.co

www.sscexamguide.com

List of 50 Important Aptitude Questions on Time and Work (with solutions below)

1).A is 30% more efficient than B. How much time will they, working together, take to complete

a job which A alone could have done in 23 days?

a) 11 days

b) 13days
3
c) 20 7 days

d) None of these

2).A does half as much work as B in three-fourth of the time. If together they take 18 days to

complete the work, how much time shall B take to do it?

a) 30 days

b) 40 days

c) 15 days

d) None of these

3).A is 50% as efficient as B.C does half of the work done by A and B together. If C alone does

the work in 40 days, then A ,B and C together can do the work in?

1
a) 133 days

b) 20 days

c) 15 days

d) 30 days

4). Two workers A and B working together completed a job in 5 days. If A worked twice as
1
efficiently as he actually did and B worked 3 as efficiently as he actually did, the work would

have been completed in 3 days. A alone could complete the work in?

1
a) 72 days

For More Study Materials Visit: www.sscexamguide.com Page 1


Download From - www.studywale.co

www.sscexamguide.com
1
b) 64 days
1
c) 54 days

d) None of these

5). A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the

fraction of the work that is left is?

1
a) 10
1
b) 4
7
c)
15
8
d) 15

6). A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10

days and left the job. In how many days, A alone can finish the remaining work?

a) 8

b) 5

c) 6
1
d) 52

7). A and B can complete a work in 15 days and 10 days respectively. They started doing the

work together but after 2 days B had to leave and A alone completed the remaining work. The

whole work was completed in?

a) 10 days

b) 15 days

c) 12 days

d) 8 days

8). A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are
forced to leave after 3 days. The remaining work was done by A in?

For More Study Materials Visit: www.sscexamguide.com Page 2


Download From - www.studywale.co

www.sscexamguide.com

a) 6 days

b) 5 days

c) 10 days
1
d) 102 days

9). A machine P can print one lakh books in 8 hours, machine Q can print the same number of

books in 10 hours while machine R can print them in 12 hours. All the machines are started at

9 a.m. While machine P is closed at 11 am and the remaining two machines complete the

work. Approximately at what time will the work be finished?

a) 11:30 am

b) 12:30 pm

c) 12 noon

d) 1 pm

10). A and B can do a piece of work in 30 days, while B and C can do the same work in 24

days and C and A in 20 days. They all work together for 10 days when B and C leave. How

many days more will A take to finish the work?

a) 18 days
b) 36 days

c) 24 days

d) 30 days

Answers: 1). b) 2). a) 3). a) 4). b) 5). d) 6). c) 7). c) 8). c) 9). d) 10). a)

11).X and Y can do a piece of work in 20 days and 12 days respectively. X started the work
alone and then after 4 days .Y joined him till the completion of the work. How long did the work
last?

For More Study Materials Visit: www.sscexamguide.com Page 3


Download From - www.studywale.co

www.sscexamguide.com

a) 6 days

b) 10 days

c) 15 days

d) 20 days

12).A and B can together finish work in 30 days .They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work .In how many days A alone can finish
the job?

a) 40

b) 50

c) 54

d) 60

13).X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?

a) 13 1/3 days

b) 16 days

c) 25days

d) 50 days

14).A, B,C together can complete a piece of work in 10 days. All the three started working at it
together and after 4 days A left. Then B and C together completed the work in 10 more days .A
alone could complete the work in?

a) 15 days

b) 16 days

For More Study Materials Visit: www.sscexamguide.com Page 4


Download From - www.studywale.co

www.sscexamguide.com

c) 25 days

d) 50 days

15).A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days .How long B alone would take to do the whole work?

a) 23 days

b) 37 days

c) 37 ½ days

d) 40 days

16).A and B together can do a piece of work in 30 days. A having worked for16 days. B
finished the remaining work alone in 44 days. In how many days shall B finish the whole work
alone?

a) 30 days

b) 40 days

c) 60 days

d) 70 days

17).A and B together can do a piece of work in 12 days, which B and C together can do in 16
days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In
how many days C alone will do the work?

a) 46

b) 24

c) 16

d) 36

For More Study Materials Visit: www.sscexamguide.com Page 5


Download From - www.studywale.co

www.sscexamguide.com

18).A and B can do a piece of work in 45 days and 40 days respectively. They began to the
work together but A leaves after some days and then B completed the remaining work in 23
days. The number of days which A left the work was?

a) 8

b) 6

c) 9

d) 12

19).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?

a) 6 3/5

b) 8 1/2

c) 10 1/5

d) 13 1/2

20).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?

a) 15 days

b) 25 days

c) 22 days

d) 35 days

Answers: 11). b) 12). d) 13). a) 14). c)15). c)16). c 17).b 18).c 19).c 20).a

For More Study Materials Visit: www.sscexamguide.com Page 6


Download From - www.studywale.co

www.sscexamguide.com

21).A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and
C together earn Rs.152.The daily earning of C is?

a) Rs.40

b) Rs.112

c) Rs.68

d) Rs.150

22).A,B and c are employed to do a piece of work for Rs.529.A and B together are supposed
to do 19/23 of the work and B and C together 8/23 of the work. What amount should A be
paid?

a) Rs.315

b) Rs.345

c) Rs.375

d) Rs.355

23). Kim can do a work in 3 days while David can do the same work in 2 days. Both of them
finish the work together and get Rs.150.What is the share of Kim?

a) Rs.70

b) Rs.60

c) Rs.75

d) Rs.30

24).If A can do ¼ of a work in 3 days and 3 days and B can do 1/6 of the same work in 4 days,
how much will A get if both work together and are paid Rs.180 in all?

a) Rs.60

For More Study Materials Visit: www.sscexamguide.com Page 7


Download From - www.studywale.co

www.sscexamguide.com

b) Rs.36

c) Rs.75

d) Rs.70

25).A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200.With the help of C, they completed the work in 3 days. How much is to be paid to
C?

a) Rs.600

b) Rs.400

c) Rs.375

d) Rs.800

26).A sum of money is sufficient to pay A’s wages for 21 days and B’s wages for 28 days. The
same money is sufficient to pay the wages of both for?

a) 12 days

b) 14 days

c) 121/4 days

d) 24 ½ days

27).A can do a piece of work in 10 days in 15 days. They work for 5 days. The rest of the work
had finished by C in 2 days. If they get Rs.1500 for the whole work, the daily wages of B and C
are?

a) Rs.150

b) Rs.225

c) Rs.250

For More Study Materials Visit: www.sscexamguide.com Page 8


Download From - www.studywale.co

www.sscexamguide.com

d) Rs.300

28).A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will complete
the work?

a) 10 days

b) 20 days

c) 15 days

d) 11 days

29).A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work
on alternate days. The total work will be completed in?

a) 12 days

b) 13 days
5
c) 13 7 days

3
d) 13 4days

30).A, B and C can do a piece of work in 11 days,20 days and 55 days respectively, working
alone. How soon can the work be done if A is assisted by B and C on every third day?

a) 7 days

b) 8 days

c) 9 days

d) 10 days

Answers: 21).a 22).b 23).b 24).d 25).b 26).a 27). b) 28). c) 29). d) 30). b)

For More Study Materials Visit: www.sscexamguide.com Page 9


Download From - www.studywale.co

www.sscexamguide.com

31).A, B and C can separately do a piece of work in 20, 30 and 60 days respectively. In how
many days can A do the work if he is assisted by B and C on alternative days?

a) 12 days

b) 15 days

c) 18 days

d) 16 days

32). A and B can separately do a piece of work in 20 and 15 days respectively. They worked
together for 6 days, after which B was replaced by C. If the work was finished in next 4 days,
then the number of days in which C alone could do the work will be?

a) 30 days

b) 35 days

c) 40 days

d) 60 days

33).A, B and C can do a work in 36, 54 and 72 days respectively. They started the work but A
left 8 days before the completion of the work while B left 12 days before the completion. The
number of days for which C worked is?

a) 4

b) 12

c) 8

d) 24

34).Twenty women can do a work in sixteen days. Sixteen men can completed the same work
in fifteen days. What is the ratio between the capacity of a man and women?

a) 3:4

For More Study Materials Visit: www.sscexamguide.com Page 10


Download From - www.studywale.co

www.sscexamguide.com

b) 4:3

c) 5:3

d) Data inadequate

35).10 men can complete a piece of work in 15 days and 15 women can complete the same
work in 12 days. If all the 10 men and 15 women work together, in how many days will the
work get completed?

a) 6
1
b) 63

2
c) 63

2
d) 73

36).Seven men can complete a work in 12 days. They started the work and after 5 days, two
men left .How many days will they take to complete the remaining work?

a) 2 days

b) 4 days

c) 5 days

d) None of these

37).12 men complete a work in 9 days. After they have worked for 6 days,6 more men join
them. How many days will they take to complete the remaining work?

a) 2 days

b) 4 days

c) 3 days

For More Study Materials Visit: www.sscexamguide.com Page 11


Download From - www.studywale.co

www.sscexamguide.com

d) 5 days

e) None of these

38).Three men, four women and six children can complete a work in seven days. A woman
does double the work a man does half the work a man does. How many women alone can
complete this work in 7 days?

a) 7

b) 8

c) 12

d) Cannot be determined

e) None of these

39).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many
boys must assist 1 man 1 woman to complete the job ¼ of a day?

a) 1

b) 4

c) 19

d) 41

40).10 men and 15 women together can complete a work in 6 days. It takes 100 days for one
man alone to complete the same work. How many days will be required for one woman alone
to complete the same work?

a) 90

b) 145

c) 125

For More Study Materials Visit: www.sscexamguide.com Page 12


Download From - www.studywale.co

www.sscexamguide.com

d) 150

e) None of these

Answers: 31). b) 32). c) 33). d) 34). b) 35).c 36). d). 37).a 38). a) 39). d) 40). e)

41).12 men can complete a piece of work in 4 days, while 15 women can complete the same
work in 4 days.6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on job to complete the remaining work, if it is to be
completed in 3 days?

a) 15

b) 22

c) 18

d) Data inadequate

e) None of these

42).Twelve children take sixteen days to complete a work which can complete by eight adults
in twelve days. Sixteen adults started working and after three days ten adults left and four
children joined them. How many days will they take to complete the remaining work?

a) 3

b) 8

c) 4

d) 6

e) None of these

43).10 women can complete a work in 7 days and children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?

For More Study Materials Visit: www.sscexamguide.com Page 13


Download From - www.studywale.co

www.sscexamguide.com

a) 3

b) 5

c) 7

d) Cannot be determined

e) None of these

44).Sixteen men can complete a work in twelve days. Twenty –four children can complete the
same work in eighteen days. Twelve men and eight children started working and after eight
days three more children joined them. How many days will they now take to complete the
remaining work?

a) 2 days

b) 4 days

c) 6 days

d) 8 days

e) None of these

45).Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days .Sixteen men and sixteen women started working and worked
for twelve days. How many more men are to added to complete the remaining work in 2 days?

a) 16

b) 24

c) 36

d) 48

e) None of these

For More Study Materials Visit: www.sscexamguide.com Page 14


Download From - www.studywale.co

www.sscexamguide.com

46).5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a woman and a boy are in the ratio?

a) 1:2

b) 2:1

c) 1:3

d) 3:1

47).If 12 men and 2 boys working together can do four times as much work as a man and a
boy. Working capacities of a woman and a boy are in the ratio?

a) 2:1

b) 3:1

c) 3:2

d) 5:4

48).4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can
complete it in 10 days. In how many days will 10 women complete it?

a) 35

b) 40

c) 50

d) 45

49).One man,3 women and 4 boys can do a piece of work in 96 hours,2 men and 8 days can
do it in 80 hours,2 men and 3 women can do it in 120 hours.5men and 12 boys can do in:?
1
a) 39 11 hours

For More Study Materials Visit: www.sscexamguide.com Page 15


Download From - www.studywale.co

www.sscexamguide.com
7
b) 42 11 hours

7
c) 43 11 hours

d) 44 hours

50).If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do
the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will
be?

a) 4 days

b) 5 days

c) 6 days

d) 7 days

Answers: 41). a) 42). e) 43). c) 44). b) 45). b) 46). b) 47). a) 48). b) 49). c) 50). a)

For More Study Materials Visit: www.sscexamguide.com Page 16


Download From - www.studywale.co

www.sscexamguide.com

Solutions for the above Time and Work Aptitude Questions:

1).A is 30% more efficient than B. How much time will they, working together, take to complete

a job which A alone could have done in 23 days?

Ratio of times taken by A and B = 100: 130 = 10: 13,

Suppose B takes x days to do the work.


23×13 299
Then, 10: 13:: 23 : x => x =( ) => x =
10 10

1 10
A’s 1 day’s work =23 ; B’s 1 days work =299.

A and B together can complete the job in 13 days.

Answer: b

2).A does half as much work as B in three-fourth of the time. If together they take 18 days to

complete the work, how much time shall B take to do it?

Suppose B takes x days to do the work


3 3x
A takes (2× 4 x) = days to do it.
2

1
(A + B)’S 1 day’s work =18.

1 2 1
+ 3x = 18 or x=30
x

Answer: a

3). A is 50% as efficient as B.C does half of the work done by A and B together. If C alone

does the work in 40 days, then A, B and C together can do the work in?

(A’s 1 day’s work) : (B’s 1 day’s work)=150:100=3:2.

Let A’s and B’s 1 day’s work be 3x and 2x respectively.


3x+2 5x
Then, C’s 1 day’s work = ( )=
2 2

For More Study Materials Visit: www.sscexamguide.com Page 17


Download From - www.studywale.co

www.sscexamguide.com

5x 1 1 2 1
= or x = × =
2 40 40 5 100
3 1 1
A’s 1 day’s work =100 ; B’s 1 day’s work = 50 ; C’s 1 day’s work=40

3 1 1 15 3
(A+B+C)’s 1 day’s work = + 50 + 40 = 20 = 40
100

40 1
So, A, B and C together can do the work in = 13 3 days.
3

Answer: a

4.) Two workers A and B working together completed a job in 5 days. If A worked twice as
1
efficiently as he actually did and B worked 3 as efficiently as he actually did, the work would

have been completed in 3 days. A alone could complete the work in?

Let A’s 1 day’s work=x and B;s 1 day’s work=y


1 1 1
Then, x+y=5 and 2x+3 y = 3

4 1
Solving, we get : x=25 and y=25

4
A’s 1 day’s work=25

25 1
So, A alone could complete the work in = 6 4days
4

Answer: b

5.) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then

the fraction of the work that is left is?

1 1
A’s 1 day’s work =15 ; B′ s1 day ′ s work = 20

1 1 7
(A+B)’s 1 day’s work=(15 + 20 ) = 60

7 7
(A+B)’s 4 day’s work=(60 × 4) = 15

7 8
Remaining work=(1-15 ) = 15

Answer: d

For More Study Materials Visit: www.sscexamguide.com Page 18


Download From - www.studywale.co

www.sscexamguide.com

6). A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10

days and left the job. In how many days, A alone can finish the remaining work?

1 2 2 1
B’s 10 day’s work=(15 × 10) = 3 . Remaining work = 1 − 3 = 3

1
Now,18 work is done by A in 1 day

1 1
work ′ sdone by A in 18 × = 6days
3 3

Answer: c

7). A and B can complete a work in 15 days and 10 days respectively. They started doing the
work together but after 2 days B had to leave and A alone completed the remaining work. The

whole work was completed in?

1 1 1
(A+B)’s 1 day’s work=(15 + 10 ) = 6

1 1 1 2
Work done by A and B in 2 days= × 2 = 3 . Remaining work = 1 − 3 = 3
6

1
Now,15 work will be done by Ain 1 day.

2 2
work will be done by A in 15 × = 10days.
3 3

Hence, total time taken =(10+2)=12days

Answer: c

8). A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are

forced to leave after 3 days. The remaining work was done by A in?

1 1 7
(B+C)’s 1day’s work =( 9 + 12 ) = 36.

7 7
Work done by B and C in 3 days=(36 × 3) = 12

7 7
Remaining work=(1-12 ) = 12

1
Now,24 work is done by A in 1 day

For More Study Materials Visit: www.sscexamguide.com Page 19


Download From - www.studywale.co

www.sscexamguide.com
5 5
So, 12 work is done by A in 24 × 12 = 10days

Answer: c

9). A machine P can print one lakh books in 8 hours, machine Q can print the same number of

books in 10 hours while machine R can print them in 12 hours. All the machines are started at

9 a.m. While machine P is closed at 11 am and the remaining two machines complete the

work. Approximately at what time will the work be finished?

1 1 1 37
(P+Q+R)’s 1 hour’s work=(8 + 10 + 12 ) = 120

37 37
Work done by P,Q and R in 2 hours=(120 × 2) = 60

37 23
Remaining work=(1-60 ) = 60

1 1 11
(Q+R)’s 1 hour’s work=(10 + 12)=60

11
Now,60 work is done by Q and R in 1 hour

23 60 23 23
So, work will be done byQ and R in × = hours = 2 hours.
60 11 60 11

So, the work will be finished approximately 2 hours after 11a.m, i.e., round 1p.m

Answer: d

10). A and B can do a piece of work in 30 days, while B and C can do the same work in 24

days and C and A in 20 days. They all work together for 10 days when B and C leave. How

many days more will A take to finish the work?

1 1 1 15 1
2(A+B+C)’s 1 day’s work = (30 + 24 + 20 ) = 120 = 8

1
=> (A+B+C)’s 1 day’s work=16

10 5 5 3
Work done by A, B and C in 10 days=16 = 8 Remaining work=(1-8) = 8

1 1 1
A’s 1 day’s work =(16 − ) = 48
24

1
Now, 48 work is done by A in 1 day

For More Study Materials Visit: www.sscexamguide.com Page 20


Download From - www.studywale.co

www.sscexamguide.com
3 3
So, 8 work will be done by A in (48× 8) = 18days.

Answer: a

11).X and Y can do a piece of work in 20 days and 12 days respectively. X started the work
alone and then after 4 days .Y joined him till the completion of the work. How long did the work
last?
1 1 1 4
Work done by X in 4 days =(20 × 4) = 5 Remaining work = 1 − 5 = 5

1 1 8 2
(X+Y)’s 1 day’s work= + 12 = 60 = 15
20

2
Now, 15 work is done by X and Y in 1 day

4 15 4
So, 5 work will be done by X and Y in × 5 = 6 days.
2

Hence, total time taken =(6 + 4) days=10days

Answer: b

12).A and B can together finish work in 30 days .They worked together for 20 days and then B
left. After another 20 days, A finished the remaining work .In how many days A alone can finish
the job?
1 2 2 1
(A+B)’s 20 day’s work = (30 × 20) = 3 , Remaining work = 1 − 3 = 3

1
Now, 3 work is done by A in 20 days.

Whole work will be done by A in (20× 3)=60days

Answer: d

13).X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16
days. How long will they together take to complete the work?
1 1 1 4
Work done by X in 8 days = (40 × 8) = 5 Remaining work = 1 − 5 = 5

4
Now, 5 work is done by Y in 16 days.

For More Study Materials Visit: www.sscexamguide.com Page 21


Download From - www.studywale.co

www.sscexamguide.com
5
Whole work will be done by Y in (16× 4) = 20days

1 1
X’s 1 day’s work =40 Y ′ s 1 day ′ swork = 20

1 1 3
(X+Y)’s 1 day’s work =(40 + 20 )=40

40 1
Hence, X and Y will together complete the work in = 13 3 days.
3

Answer: a

14).A, B,C together can complete a piece of work in 10 days. All the three started working at it
together and after 4 days A left. Then B and C together completed the work in 10 more days .A
alone could complete the work in?
1 2 2 3
Work done by A.B and C in 4 days=(10 × 4) = 3 . Remaining work = 1 − 5 = 5

3
Now, 5 work is done by B and C in 10 days.

5 50
Whole work will be done B and C in (10× 3) = days.
3

1 3
(A+B+C)’s 1 day’s work=10, B + C ′ S 1day ′ s work = 50

1 3 2 1
A’s 1 day’s work = − 50 = 50 = 25
10

A alone could complete the work in 25 days.

Answer: c

15).A does 4/5 of a work in 20 days. He then calls in B and they together finish the remaining
work in 3 days .How long B alone would take to do the whole work?
5
Whole work is done by A in (20× 4) = 25days.

4 1
Now, (1-5)i. e. , 5 work is done by A and B in 3 days.

Whole work will be done by A and B in (3× 5) = 15days


1 1
A’s 1 day’s work =25 , A + B ′ s 1 day ′ s work = 15

75 1
So, B alone would do the work in = 372 days.
2

For More Study Materials Visit: www.sscexamguide.com Page 22


Download From - www.studywale.co

www.sscexamguide.com

Answer: c

16).A and B together can do a piece of work in 30 days. A having worked for16 days. B
finished the remaining work alone in 44 days. In how many days shall B finish the whole work
alone?

Let A’s 1 day’s work=x and B’s 1 day’s work = y


1
Then, x+y=30 and 16x + 44y = 1

1 1
Solving these two equations, we get: x =60 and y = 60

1
B’s 1 day’s work = 60

Hence, B alone shall finish the whole work in 60 days.

Answer: c

17).A and B together can do a piece of work in 12 days, which B and C together can do in 16
days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In
how many days C alone will do the work?

A’s 5 day’s work + B’s 7 day’s work +C’s 13 day’s work=1

=> (A+B)’s 5 day’s work + (B+C)’s day’s work+ C’s 11day’s work = 1
5 2
=> 12 + 16 + C′ s11 day ′ swork = 1

5 2 11
=>C’s 11 day’s work=1-(12 + 16 ) = 24

11 1 1
=>C’s 1 day’s work = (24 × 11 ) = 24

C alone can finish the work in 24 days.

Answer: b

18).A and B can do a piece of work in 45 days and 40 days respectively. They began to the
work together but A leaves after some days and then B completed the remaining work in 23
days. The number of days which A left the work was?

For More Study Materials Visit: www.sscexamguide.com Page 23


Download From - www.studywale.co

www.sscexamguide.com
1 1 17
(A+B)’s 1day’s work = (45 + 40 ) = 360

1 23 23 17
Work done by B in 23 days= (40 × 23) = 40 . Remaining work = 1 − 40 = 40

17
Now, 360 work was done by (A+B) in 1 day.

17 360 17
work was done by A + B in 1 × × = 9 days.
40 17 40

A left after 9 days

Answer: c

19).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
1 1 1 6
B’s 3 day’s work = (21 × 3) = 7 . Remaining work = 1 − 7 = 7

1 1 5
(A+B)’s 1 day’s work=(14 + 21 ) = 42

5
Now, work is done by A and B in 1 day
42

6 42 6 36
work is done by A and B in × = days
7 6 7 5
36 1
Hence, total times taken= (3+ 5 )days = 10 5 days

Answer: c

20).A can do a piece of work in 14 days which B can do in 21 days. They begin together but 3
days before the completion of the work, A leave off The total number of days to complete the
work is?
1 1 1 12
(A+B+C)’s 1 day’s work= (24 + 36 + 48 ) = 144

13 13
Work done by (A+B+C) in 4 days= (144 × 4) = 36

1 1 13 1 5
Work done by B in 3 days = (36 × 3) = 12. Remaining work = 1 − + 12 =9
36

1 1 5
(A+B)’s 1 day’s work=(24 + 36 ) = 72

For More Study Materials Visit: www.sscexamguide.com Page 24


Download From - www.studywale.co

www.sscexamguide.com
5 72 5
Now, 72 work is done by A and B in × 9 = 8 days.
5

Hence total time taken=(4+3+8) days =15 days

Answer: a

21).A, B and C together earn Rs.300 per day, while A and C together earn Rs.188 and B and
C together earn Rs.152.The daily earning of C is?

B’s daily earning = Rs. (300 – 188) = Rs. 112

A’s daily earning = Rs. (300 – 152) = Rs. 148.

C’s daily earning = Rs. [30 – (112 + 148)] = Rs 40

Answer: a

22).A,B and c are employed to do a piece of work for Rs.529.A and B together are supposed
to do 19/23 of the work and B and C together 8/23 of the work. What amount should A be
paid?
8 15
Work done by A=(1 − 23 ) = 23

15 8
A : (B+C)=23 : 23 = 15: 8

15
So, A’s share=Rs.(23 × 529) = Rs. 345

Answer: b

23). Kim can do a work in 3 days while David can do the same work in 2 days. Both of them
finish the work together and get Rs.150.What is the share of Kim?

Kim’s wages: David’s wages = Kim’s 1 day’s work: David’s 1 day’s work
1 1
=3 : 2 = 2: 3

2
Kim’s share = Rs. (5 × 150) Rs. 60

Answer: b

For More Study Materials Visit: www.sscexamguide.com Page 25


Download From - www.studywale.co

www.sscexamguide.com

24).If A can do ¼ of a work in 3 days and 3 days and B can do 1/6 of the same work in 4 days,
how much will A get if both work together and are paid Rs.180 in all?

Whole work is done by A in (3× 4) = 12 days.

Whole work is done by B in (4× 6) = 24 days.


1 1
A’s wages: B’s wages = A’s 1 day’s work; B’s 1 day’s work = 12 : 12 = 2: 1

2
A’s share=Rs. (3 × 180) = 𝑅𝑠. 120

Answer: d

25.)A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it
for Rs.3200.With the help of C, they completed the work in 3 days. How much is to be paid to
C?
1 1 1 1 7 1
C’s 1 day’s work=3 − (6 + 8) = 3 − 24 = 24

1 1 1
A’s wages: B’s wages: C’s wages =6 : 8 : 24 = 4:3:1

1
C’s share = Rs (8 ×3200) Rs 400

Answer: b

26).A sum of money is sufficient to pay A’s wages for 21 days and B’s wages for 28 days. The
same money is sufficient to pay the wages of both for?

Let total money be Rs. X


𝑥 𝑥
A’s 1 day’s wages = Rs. 21 , 𝐵 ′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑎𝑔𝑒𝑠 = 𝑅𝑠. 28

𝑥 𝑥 𝑥
(A+B)’s 1 day’s wages = Rs. (21 + 28 ) = 𝑅𝑠. 28

Money is sufficient to pay the wages of both for 12 days

Answer: a

For More Study Materials Visit: www.sscexamguide.com Page 26


Download From - www.studywale.co

www.sscexamguide.com

27).A can do a piece of work in 10 days in 15 days. They work for 5 days. The rest of the work
had finished by C in 2 days. If they get Rs.1500 for the whole work, the daily wages of B and C
are?
1 1
Part of the work done by A= (10 × 5) = 2

1 1
Part of the work done by B= (15 × 5) = 3

1 1 1
Part of the work done by C= 1-(2 + 3) = 6

1 1 1
So, (A’s share): (B’s share): (C’s share) = 2 : 3 : 6 = 3: 2: 1

3 2
A’s share = Rs.(6 × 1500) = 𝑅𝑠. 750, 𝐵 ′ 𝑠𝑠ℎ𝑎𝑟𝑒 = 𝑅𝑠. × 1500 𝑅𝑠. 500,
6

1
C’s share = Rs. (6 × 1500) = 𝑅𝑠. 250

750 500
A’s daily wages = Rs.( ) = 𝑅𝑠. 150; 𝐵 ′ 𝑠 𝑑𝑎𝑖𝑙𝑦 𝑤𝑎𝑔𝑒𝑠 = 𝑅𝑠. ( ) = 𝑅𝑠. 1𝑜𝑜;
5 5

250
C’s daily wages = Rs. ( ) = Rs. 125.
2

Daily wages of B and C = Rs. (100 + 125) =Rs. 225

Answer: b

28).A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B
does the work only for half a day daily, then in how many days A and B together will complete
the work?
1 1 2 1
B’s 1 day’s work = (12 − 20 ) = 60 = 30

1 1 4 1
Now, (A+B)’s 1 day’s work =(20 + 60 ) = 60 = 15 . |B works for half day only|

So, A and B together will complete the work in 15 days

Answer: c

29).A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work
on alternate days. The total work will be completed in?

For More Study Materials Visit: www.sscexamguide.com Page 27


Download From - www.studywale.co

www.sscexamguide.com
1 1 7
A+B)’s 2 day’s work = + 12 = 48
16

7 7 7 1
Work done in 6 pairs of days = (48 × 6) = 8 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 8 = 8

1 1 1 1
Work done by A on 13th day = 16 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = − 16 = 16
8

On 14th day, it is B’s turn.

1 1 1 3
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝐵 𝑖𝑛 1 𝑑𝑎𝑦. 𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝐵 𝑖𝑛 12 × = 𝑑𝑎𝑦
12 16 16 4
3
Total time taken = 134 𝑑𝑎𝑦𝑠

Answer: d

30).A, B and C can do a piece of work in 11 days,20 days and 55 days respectively, working
alone. How soon can the work be done if A is assisted by B and C on every third day?
1 1 31 1 1 6
(A+B)’s 1 day’s work = (11 + 20 ) = 220 . 𝐴 + 𝐶 ′ 𝑠 𝑤𝑜𝑟𝑘 = + 55 = 55
11

31 6 55 1
Work done in 2 days = (220 + 55 ) = 220 = 4

1
Now, 4 work is done by A in 2 days.

Whole work will be done in (2× 4)=8 days.

Answer: b

31).A, B and C can separately do a piece of work in 20, 30 and 60 days respectively. In how
many days can A do the work if he is assisted by B and C on alternative days? A’s 2 day’s
1 1
work = (20 × 2) = 10

1 1 1 6 1
(A+B+C)’s 1 day’s work = (20 + 30 + 60 ) = 60 = 10

1 1 1
Work done in 3 days = (10 + 10 ) = 5

1
Now, 5 work is done in 3 days

Whole work will be done in (3× 5) = 15 𝑑𝑎𝑦𝑠

For More Study Materials Visit: www.sscexamguide.com Page 28


Download From - www.studywale.co

www.sscexamguide.com

Answer: b

32).A and B can separately do a piece of work in 20 and 15 days respectively. They worked
together for 6 days, after which B was replaced by C. If the work was finished in next 4 days,
then the number of days in which C alone could do the work will be?
1 1 7 3
(A+B)’s 6 day’s work = 6(20 + 15 ) = 10 ; 𝐴 + 𝐶 ′ 𝑠4 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 10

3 1
(A+C)’s 1 day’s work = 40 𝐴′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 20

3 1 1
C’s 1 day’s work = ( 40 − 20 ) = 40

Hence, C alone can finish the work in 40 days.

Answer: c

33).A, B and C can do a work in 36, 54 and 72 days respectively. They started the work but A
left 8 days before the completion of the work while B left 12 days before the completion. The
number of days for which C worked is?

Suppose, the work was finished in x days.

Then, A’s (x-8) day’s work + B’s (x-12) day’s work + C’s x day’s work = 1
𝑥−8 𝑥−12 𝑥
 + + 72 = 1 => 6 𝑥 − 8 + 4 𝑥 − 12 + 3𝑥 = 216
36 54

13x = 312 or x=24

Answer: d

34).Twenty women can do a work in sixteen days. Sixteen men can completed the same work
in fifteen days. What is the ratio between the capacity of a man and women?

(20× 16) Women can complete the work in 1 day.


1
1 woman’s 1 day’s work = 320

(16× 15) men can complete the work in 1 day

For More Study Materials Visit: www.sscexamguide.com Page 29


Download From - www.studywale.co

www.sscexamguide.com
1
1 man’s 1 day’s work = 240

1 1
So, required ratio = 240 : 320 =4:3

Answer: b

35).10 men can complete a piece of work in 15 days and 15 women can complete the same
work in 12 days. If all the 10 men and 15 women work together, in how many days will the
1 1
work get completed? 10 men’s 1 day’s work = 15 ; 15 𝑤𝑜𝑚𝑒𝑛′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 12.

1 1 9 3
(10 men + 15 women)’s 1 day’s work = (15 + 12 ) = 60 =20

3 2
10 men and 15 women will complete the work in 20 = 6 3 𝑑𝑎𝑦𝑠.

Answer: c

36).Seven men can complete a work in 12 days. They started the work and after 5 days, two
men left .How many days will they take to complete the remaining work?

(7× 12) 𝑚𝑒𝑛 𝑐𝑎𝑛 𝑐𝑜𝑚𝑝𝑙𝑒𝑡𝑒 𝑡ℎ𝑒 𝑤𝑜𝑟𝑘 𝑖𝑛 1 𝑑𝑎𝑦


1
1 man’s 1 day’s work = 84

1 5 5 7
7 men’s 5 day’s work = (12 × 5) = 12 . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 w𝑜𝑟𝑘 = 1 − 12 = 12

1 5
5 men’s 1 day’s work = × 5 = 84
84

5
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 1 𝑑𝑎𝑦.
84
7 84 7 49 4
Work is done by them in ( 5 × 12 ) = 𝑑𝑎𝑦𝑠 = 9 5 𝑑𝑎𝑦𝑠
12 5

Answer: d

37). 12 men complete a work in 9 days. After they have worked for 6 days,6 more men join
them. How many days will they take to complete the remaining work?
1
1 man’s 1 day’s work = 108

1 2 2 1
12 men’s 6 day’s work = (9 × 6) = . 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 3 = 3
3

For More Study Materials Visit: www.sscexamguide.com Page 30


Download From - www.studywale.co

www.sscexamguide.com
1 1
18 men’s 1 day’s work = (108 × 18) = 6

1
Work is done by them in 1 day.
6

1 1
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 6 × = 2 𝑑𝑎𝑦𝑠
3 3

Answer: a

38).Three men, four women and six children can complete a work in seven days. A woman
does double the work a man does half the work a man does. How many women alone can
complete this work in 7 days?

Let 1 woman’s 1 day’s work = x


𝑥 𝑥
Then, 1 man’s 1 day’s work = 2 𝑎𝑛𝑑 1 𝑐ℎ𝑖𝑙𝑑′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 4

3𝑥 6𝑥 1 1 4 1
So, ( 2 + 4𝑥 + ) = 7 => 𝑥 = × 28 = 49
4 7

1 woman alone can complete the work in 49 days.


49
So, to complete the work in 7 days, number of women required = ( ) = 7
7

Answer: a

39).A man, a woman and a boy can complete a job in 3,4 and 12 days respectively. How many
boys must assist 1 man 1 woman to complete the job ¼ of a day?
1 1 7
(1 man + 1 woman)’s 1 day’s work = (3 + 4) = 12

1 7 1 7
Work done by 1man and 1 woman in 4 𝑑𝑎𝑦 = × 4 = 48
12

7 1
Remaining work = (1-48 ) = 48

1 1 1 1
Work done by 1 boy in 4 𝑑𝑎𝑦 = × 4 = 48
12

41
Number of boys required = (48 × 48) = 41

Answer: d

For More Study Materials Visit: www.sscexamguide.com Page 31


Download From - www.studywale.co

www.sscexamguide.com

40).10 men and 15 women together can complete a work in 6 days. It takes 100 days for one
man alone to complete the same work. How many days will be required for one woman alone
to complete the same work?
1 1
1 man’s 1 day’s work = 100. (10 men + 15 women)’s day work = 6

1 10 1 1 1
15 women’s 1 day’s work = (6 − 100 ) = − 10 = 15
6

1
1 woman’s 1 day’s work = 225

1 woman alone can complete the work in 225 days.

Answer: e

41).12 men can complete a piece of work in 4 days, while 15 women can complete the same
work in 4 days.6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on job to complete the remaining work, if it is to be
completed in 3 days?
1 1
1 man’s 1 day’s work = 48 ; 1 𝑤𝑜𝑚𝑎𝑛′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 60

6 1 1 3
6 men’s 2 day’s work = (48 × 2) = 4. 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 4 = 4

1
Now, 60 work is done in 1 day by 1 woman

3 3 1
So, 4 𝑤𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑖𝑛 3 𝑑𝑎𝑦𝑠 𝑏𝑦 60 × 4 × 3 = 15 𝑤𝑜𝑚𝑒𝑛

Answer: a

42).Twelve children take sixteen days to complete a work which can complete by eight adults
in twelve days. Sixteen adults started working and after three days ten adults left and four
children joined them. How many days will they take to complete the remaining work?
1 1
1 child’s 1 day’s work = 192 : 1 𝑎𝑑𝑢𝑙𝑡 ′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 96

1 1 1 1
Work done in 3 days = (96 × 16 × 3) = 2 𝑅𝑒𝑚𝑎𝑖𝑛𝑖𝑛𝑔 𝑤𝑜𝑟𝑘 = 1 − 2 = 2

6 4 1
(6 adults + 4 children)’s 1 day’s work = (96 + 192 ) = 12

For More Study Materials Visit: www.sscexamguide.com Page 32


Download From - www.studywale.co

www.sscexamguide.com
1
Work is done by them in 1 day
12

1 1
𝑤𝑜𝑟𝑘 𝑖𝑠 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 12 × = 6 𝑑𝑎𝑦𝑠
2 2

Answer: e

43).10 women can complete a work in 7 days and children take 14 days to complete the work.
How many days will 5 women and 10 children take to complete the work?
1 1
1 woman’s 1 day’s work =70 : 1 𝑐ℎ𝑖𝑙𝑑′ 𝑠 1 𝑑𝑎𝑦 ′ 𝑠 𝑤𝑜𝑟𝑘 = 140

5 10 1 1 1
(5 women + 10 children)’s 1 day’s work = (70 + 140 ) = + 14 = 7
14

5 women and 10 children will complete the work in 7 days.

Answer: c

44).Sixteen men can complete a work in twelve days. Twenty –four children can complete the
same work in eighteen days. Twelve men and eight children started working and after eight
days three more children joined them. How many days will they now take to complete the
remaining work?
1 1
1 man’s 1 day’s work = 192 ; 1 𝑐ℎ𝑖𝑙𝑑′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 432

12 8 1 1 35
Work done in 8 days= 8(192 + 432 ) = 8 + 54 = 54
16

35 19
Remaining work = (1-54 ) = 54

12 11 19
(12 men + 11 children)’s 1 day’s work = (192 + 432 ) = 216

19
Now, work is done by them in 1 day
216

19 219 19
𝑤𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑏𝑦 𝑡ℎ𝑒𝑚 𝑖𝑛 × = 4 𝑑𝑎𝑦𝑠.
54 19 54

Answer: b

For More Study Materials Visit: www.sscexamguide.com Page 33


Download From - www.studywale.co

www.sscexamguide.com

45).Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days .Sixteen men and sixteen women started working and worked
for twelve days. How many more men are to added to complete the remaining work in 2 days?
1 1
1 man’s 1 day’s work = 384 ; 1 𝑤𝑜𝑚𝑎n′ 𝑠1 𝑑𝑎𝑦 ′ 𝑠𝑤𝑜𝑟𝑘 = 768

16 16 3 3
Work done in 12 days = 12(384 + 769 ) = 12 × 48 = 4

3 1
Remaining work = (1 - 4) = 4

16 16 1 1
(16 men + 16 women)’s 2 day’s work = 2 (384 + 768 ) = 2 × 16 = 8

1 1 1
Remaining work = (4 - 8) = 8

1
Work is done in 1 day by 1 man
384

1 1 1
𝑊𝑜𝑟𝑘 𝑤𝑖𝑙𝑙 𝑏𝑒 𝑑𝑜𝑛𝑒 𝑖𝑛 2 𝑑𝑎𝑦𝑠 𝑏𝑦 384 × × = 24 𝑚𝑒𝑛.
8 8 2

Answer: b

46).5 men and 2 boys working together can do four times as much work as a man and a boy.
Working capacities of a woman and a boy are in the ratio?

Let 1 man’s 1 day’s work = x and 1 boy’s work = y


𝑥 2
Then, 5 x + 2y = 4 (x + y) => x=2y => 𝑦 = 1

Answer: b

47).If 12 men and 2 boys working together can do four times as much work as a man and a
boy. Working capacities of a woman and a boy are in the ratio?

Let 1 man’s 1 day’s work = x and 1 boy’s work = y


1 1
Then, 12x+16y = 5 and 13x + 24y = 4

1 1
Solving these two equations, we get: x = 100 and y = 200

1 1
Required ratio = x: y = 100 : 200 = 2: 1

For More Study Materials Visit: www.sscexamguide.com Page 34


Download From - www.studywale.co

www.sscexamguide.com

Answer: a

78).4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can
complete it in 10 days. In how many days will 10 women complete it?

Let 1 man’s 1 day’s work = x and 1 woman’s 1 day’s work = y


1 1
Then, 4x + 6y= 8 and 3x + 7y = 10

11 1
Solving these two equations, we get: x=400 , y = 400

1
1 woman’s 1 day’s work = 400

1 1
10 women’s 1 day’s work = (400 × 10) = 40

Hence, 10 women will complete the work in 40 days.

Answer: b

49).One man,3 women and 4 boys can do a piece of work in 96 hours,2 men and 8 days can
do it in 80 hours,2 men and 3 women can do it in 120 hours.5men and 12 boys can do in:?

Let 1 man’s 1 hour’s work = x, 1 woman’s 1 hour’s work = y

and 1 boy’s 1 hour’s work = z. Then,


1 1 1
x+3y+4y=96 … . . i 2x + 8z = 80 … . . ii 2x + 3y = 120 … . . iii

1
Adding (ii) and (iii) and subtracting (i) from it, we get it, we get: 3x+ 4z = 96 …..(iv)

1 1 1
From (ii) and (iv), we get x= 480 Substituting, we get ∶ y = , z = 960
720

5 12 1 1 11
(5 men + 12 boy)’s 1 hour’s work = (480 + 960 ) = + 80 = 480
96

480 7
5 men and 12 boys can do the work in i. e. , 43 11 hours
11

Answer: c

For More Study Materials Visit: www.sscexamguide.com Page 35


Download From - www.studywale.co

www.sscexamguide.com

50).If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do
the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will
be?

Let 1 man’s 1 day’s work = x and 1 boy’s 1 day’s work = y


1 1
Then, 6x+8y= 10 and 26x + 48y = 2

1 1
Solving these tow equations, we get: x = 100 and y = 200

15 20 1
(15 men+20 boy)’s 1 day’s work = (100 + 200 ) = 4

15 men and 20 boys can do the work in 4 days.

Answer: a

To Subscribe Us Via Email: Click Here

To Follow Us on Facebook: Click Here

For More Study Materials Visit: www.sscexamguide.com Page 36


Download From - www.studywale.co

Time and Distance Questions for


SSC CGL
06 April 2018
Download From - www.studywale.co
TAKE CRACKU'S FREE SSC CGL MOCK
Question 1: Raju travels half of the distance to his school on foot at 10 km/hr and remaining half
of the distance by bus at 30 km/hr. If the distance between school and his starting point is 60 km,
find the time taken by Raju to reach his school?

a) 5 hours
b) 4.8 hours
c) 3.6 hours
d) 4 hours

Question 2: Jogging at a speed of 6.5 km/hr a man can cover a distance in 18 hours. Running at
a speed of 12 km/hr the man covers the same distance in

a) 7.85 hours
b) 10.5 hours
c) 8.36 hours
d) 9.75 hours

Question 3: Two trains moving in opposite directions cross each other in 60 seconds. If their
speeds are 30 km/hr and 120 km/hr, find the sum of the lengths of the trains.

a) 3.2 km
b) 2.8 km
c) 2.5 km
d) 3.6 km

Question 4: A group of rowers can row a boat at a speed of 20 m/min. The speed of the water
current is 0.24 km/hr. What is the difference between the time they will take to row 576 m
upstream and downstream?

a) 8 minutes
b) 10 minutes
c) 12 minutes
d) 15 minutes

SSC CGL Syllabus 2018 PDF

SSC CGL Free Previous Papers


Download Our App
Download From - www.studywale.co

   FREE PAST SSC CGL PAPERS


Question 5: A train of length 480 m crosses a pole in 32 seconds. What is the speed of the train?

a) 36 km/hr
b) 45 km/hr
c) 54 km/hr
d) 63 km/hr

Question 6: 10 men can together do a piece of work in 4 days. But from the second day, 1 worker
kept on leaving the group each day. On which day will the assignment get completed?

a) 5th day
b) 6th day
c) 7th day
d) 8th day

Question 7: A person bought an article marked at Rs. 100 and gets successive discounts of 10%
and 20%. Then, he also spends 10% of the cost price as transportation cost. To earn a profit of
5%, at what price should he sell the article?

a) Rs.79.2079.20
b) Rs.80.3580.35
c) Rs.75.4275.42
d) Rs.83.1683.16

Question 8: To catch the train just in time, Uday estimated that he needs to leave his house
before 3 hours of the scheduled departure if he travels at his normal speed. However, he leaves
his house 45 minutes later than he planned. To catch the train just on time, he needs to increase
his speed by

a) 16.66%
b) 20%
c) 33.33%
d) 25%

SSC CGL English Questions PDF

SSC CGL Free Previous Papers


Download Our App
Download From - www.studywale.co

TAKE CRACKU'S FREE SSC CGL MOCK


Question 9: 3 days of Amit’s work is equal to 2 days of Vinod’s work. If Amit can complete a
particular job in 15 days, then how many days will Vinod take to complete the same work?

a) 22.5 days
b) 10 days
c) 20 days
d) 30 days

Question 10: Ram can do a piece of work in 15 days. Shyam can do the same piece of work in
20 days. They work together for 5 days and then Ram leaves. On which day (from the beginning)
will the work be completed?

a) 10th day
b) 12th day
c) 13th day
d) 14th day

Answers & Solutions:

1) Answer (D)

Total time taken to reach Raju’s school = 30 / 10 + 30 / 30 = 3 + 1 = 4hrs.

2) Answer (D)

Distance he covers = 6.5*18 = 117 km


Time taken by the man to cover the distance while running = 117/12 = 9.75 hours

3) Answer (C)

60 seconds = 1/60 hours


Sum of the lengths of the trains = (sum of the speeds of the trains)*time taken = (30+120)*(1/60)
= 2.5 km

Top 10 SSC CGL Maths Tricks and Shortcuts


SSC CGL Free Previous Papers
Download Our App
Download From - www.studywale.co

TAKE CRACKU'S FREE SSC CGL MOCK


4) Answer (C)

The speed in still water is 20 m/min


Speed of the water current is 0.24 km/hr = 4 m/min
=> Speed of the boat upstream = 16 m/min => Time upstream = 576/16 = 36 min
Speed of the boat downstream = 24 m/min => Time downstream = 576/24 = 24 min
=> Difference in time = 36-24 = 12 min

5) Answer (C)

Speed = Distance / Time


Speed of the train = 480/32 = 15 m/s
To convert m/s to km/hr we need to multiply by 18/5
So Speed = 15*18/5 = 54 km/hr

6) Answer (A)

Let us assume that each man does 1 unit of work each day.
So, the total work to be done is 10 X 4 = 40 units
Now, on the first day 10 workers will work, on the second day 9 workers will work, on third 8 and
so forth.
Since each man does 1 unit of work, the work done on each day can be written as-
10(1st day) + 9(2nd day) + 8(3rd day) + 7(4th day) + 6 (5th day) = 40 units
Thus, the assignment will get completed on the 5th day.

7) Answer (D)

Marked Price = Rs. 100


After successive discount of 10% and 20% ,
Therefore, Cost Price becomes => ( 0.90 ) x ( 0.80 ) x 100 = 72
Since, there is a Transportation Cost as well
Total Cost Price => ( 1.10 ) x 72 = Rs. 79.20
To gain 5%, Selling Price of the dealer should be => Rs.( 1.05 ) x ( 79.20 ) = Rs. 83.16

Number System for SSC CGL

SSC CGL Free Previous Papers


Download Our App
Download From - www.studywale.co

TAKE CRACKU'S FREE SSC CGL MOCK


8) Answer (C)

Let his normal speed be ‘s’.


So, the distance will be 180s. (3 hours = 180 minutes)
But he leaves his house 45 minutes late. So, the time left is 135 minutes.
Let the speed in this case be s’.
=> 135s’ = 180s
=> s’/s = 4/3
Thus, he needs to increase his speed by a factor of 1/3 or 33.33%

9) Answer (B)

The amount of work done by Amit in 3 days is equal to the amount of work done by Vinod in 2
days. Hence if Amit does 1 unit of work in 3 days, Vinod can do it in 2 days. In 15 days, Amit
would do 15/3 = 5 units of work.
The time needed by Vinod to complete 5 units of work = 5*2 = 10 days.

10) Answer (D)

Let the total work to be done be 60 units. So Ram does 4 units of work in a day and Shyam does
3 units of work in a day. Hence when they work together, they will be able to do 7 units in 1 day.
Hence in 5 days, they will do 35 units of work. Thus, the remaining 25 units will have to be done
by Shyam. The time taken by Shyam to do the remaining 25 units of work = 25/3 = 8.33 days.
Hence the total time taken = 5 + 8.33 = 13.33 days.
Hence the work will be completed on 14th day.

20 SSC CGL Mocks for Rs. 99

Whatsapp "SSC" to join in SSC


group to this number (7661025557) 

SSC CGL Free Previous Papers


Download Our App
Download From - www.studywale.co

Time and Work Questions for


SBI PO PDF
23 April 2018
Download From - www.studywale.co

TAKE CRACKU'S FREE SBI PO MOCK


Question 1: Three friends J, K and Ljog around a circular stadium and complete one round in 12,
18 and 20 seconds respectively. In how many minutes will all the three meet again at the starting
point

a) 5
b) 8
c) 12
d) 3
e) None of these

Question 2: The speed of a boat when travelling downstream is 32 Kms. / Hr. , whereas when
travelling upstream it is 28 kms/hr. What is the speed of the boat in still water ?

a) 27 Kms./Hr.
b) 29 Kms./ Hr.
c) 31 Kms./ Hr.
d) Cannot be determined
e) None of these

Question 3: If I walk at 4 km/h, I miss the bus by 10 min. If I walk at 5 km/h, I reach 5 min before
the arrival of the bus. How far I walk to reach the bus stand?

a) 5 km
b) 5.5 km
c) 6 km
d) 7.5 km
e) None of these

Question 4: The speed of a boat in still water is 15 km/hr and the rate of current is 3 km/hr. The
distance travelled down steam in 12 minutes is:

a) 3.3 km
b) 2.9 km
c) 2.4 km
d) 3.6 km
e) None of these
English Language Questions for SBI PO

Free GK Tests Download Our App


Download From - www.studywale.co

SOLVE PAST SBI PO PAPERS


Question 5: An express train travelled at an average speed of 75 km/h stopping for 5 min every
125 km. How long did it take to reach its destination 375 km from the starting point?

a) 6 h 30 min
b) 4 h 45 min
c) 3 h 15 min
d) 5 h 10 min
e) None of these

Question 6: A boat’s speed with the current is 15 kmph and the boat’s speed against the current
is 5 kmph. What is the speed of the current?

a) 15 kmph
b) 10 kmph
c) 5 kmph
d) 20 kmph
e) None of the above

Question 7: A 210 m long train takes 6 s to cross a man running at 9 km/h in a direction opposite
to that of the train. What is the speed of the train? (in km/h)

a) 127
b) 121
c) 117
d) 108
e) 111

Question 8: A truck covers a distance of 640 km in 10 h. A car covers the same distance in 8 h.
What is the respective ratio between the speed of the truck and the car?

a) 3: 4
b) 1: 2
c) 5: 6
d) 6: 7
e) None of these

SBI PO English Questions PDF

Free Daily Topic Tests Download Our APP


Download From - www.studywale.co

TAKE CRACKU'S FREE SBI PO MOCK


Question 9: Faisal walks 325 m every day .How many kilometers will he walk in four weeks?

a) 6.2
b) 9.1
c) 8.6
d) 7.8
e) None of these

Question 10: A 280 m long train crosses a platform thrice its length in 6 min 40 s. What is the
speed of the train?

a) 3.2 m/s
b) 1.4 m/s
c) 2.8 m/s
d) Cannot be determined
e) None of these

Answers & Solutions:

1) Answer (D)

All the three friends will meet at the starting point again after X seconds, such that X is the LCM of
the times taken by J, K and L to complete one round.
=> LCM of 12, 18 and 20 = 180 seconds = 3 minutes.
Hence 3 minutes is the answer.

2) Answer (E)

Let the speed of boat in still water be v and the speed of water be x.
Boat speed while going upstream = v-x = 28
Boat speed while going downstream = v+x = 32
=> 2v = 60 => v = 30
Hence, none of these is the correct answer.

SBI PO 2018 Syllabus PDF

Free GK Tests Download Our App


Download From - www.studywale.co

SOLVE PAST SBI PO PAPERS


3) Answer (A)

Suppose the required distance be d km/h


Then, d/4 - d/5 = 15min = 1/4 h ⇒ d 1/20 = 1/4 ⇒ d = 5km

4) Answer (D)

Speed downstream = (15 + 3) kmph = 18 kmph.


Distance traveled =(18×12/60)km = 3.6 km.

5) Answer (D)

Time taken to cover 375 km = (375 / 75)h = 5h


Number of stoppages = 375 / 125 - 1 = 2
Total time to stoppages = (5 × 2 ) min = 10 min
Hence, total time taken = 5 h 10 min

6) Answer (C)

With the current => downstream


Against the current => upstream
Let the speed of the boat be ‘s’ and the speed of the river be ‘r’.
So, s - r = 5 and s + r = 15
=>2s = 20 => s = 10 and r = 5 kmph
Speed of the current = 5 kmph

7) Answer (C)

Speed of train = x
Relative speed = x + 9(5 / 18) = x + 2.5
Speed = 210 / 6 = 35 m/s
x + 2.5 = 35 => x = 32.5 m/s = 32.5 * (18/5) = 6.5 * 18 = 117 kmph

SBI PO Quantitative Aptitude Questions and Answers PD

Free Daily Topic Tests Download Our APP


Download From - www.studywale.co

TAKE CRACKU'S FREE SBI PO MOCK

8) Answer (E)

We know the formula of speed which is Speed = Distance/Time


Speed of a truck = 640/10 = 64
Speed of a car = 640/8 = 80
Ratio of speed of truck and car = 64:80 = 4:5

9) Answer (B)

Number of days in 4 weeks = 4*7 = 28


Since Faisal walks 325 m every day
Distance walked in 28 days = 325*28 = 9100 m
9100 m = 9.1 km

10) Answer (C)

Length of the train = 280 m


Length of the platform = (280*3) m
Since the train passes the platform completely
Total distance traveled by train = 280 + (3*280) = 4*280
Time take = 6 min 40 s = 360 + 40 = 400 s
Speed = 4*280 / 400 = 2.8 m/s.

SBI PO Expected Cut off 2018

Whatsapp ‘Banking’ to join in Banking


Group to this number (7661025557)

Free GK Tests Download Our App


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Downloaded from: www.thegkadda.com


Download From - www.studywale.co

Q1. A and B can do a piece of work in 15 days. B and C can do the same work in 10 days and A and
C can do the same work in 12 days. Time taken by A, B and C together to do the job is?
(a) 4 days (b) 9 days
(c) 8 days (d) 5 days

Q2. A, B and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days
before the work was completed and B left 2 days after A had left. Number of days required to
complete the whole work is?
(a) 8 days (b) 6 days
(c) 7 days (d) 6 days

Q3. A can complete a piece of work in 10 days, B in 15 days and C in 20 days. A and C worked
together for two days and then A was replaced by B. In how many days, altogether, the work was
completed?
(a) 12 days (b) 10 days
(c) 6 days (d) 8 days

Q4. A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start
the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining
work is?
(a) 10 days (b) 12 days
(c) 15 days (d) 16 days

Q5. A can do a piece of work in 20 days and B in 30 days. They work together for 7 days and then
both leave the work. Then C alone finishes the remaining work in 10 days. In how many days will
C finish the full work?
(a) 25 days (b) 30 days
(c) 24 days (d) 20 days

Q6. X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete
work was finished in 16 days, Y can alone finish that work in how
many days?
(a) 18 days (b) 27 days
(c) 36 days (d) 42 days

Q7. If 6 men and 8 boys can do a piece of work in 10 days and, 26


men and 48 boys can do the same in 2 days. Then, the time taken
by 15 men and 20 boys to do the same type of work will be?
(a) 5 days (b) 4 days
(c) 6 days (d) 7 days

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


1
Download From - www.studywale.co

Q8. If 10 men or 20 women or 40 children can do a piece of work in 7 months. Then, 5 men, 5
women and 5 children together can-do half of the work in?
(a) 6 months (b) 4 months
(c) 5 months (d) 8 months

Q9. A company employed 200 workers to complete a certain work in 150 days. If only one-fourth
of the work has been done in 50 days, then in order to complete the whole work in time, the
number of additional workers to be employed was?
(a) 100 (b) 300
(c) 600 (d) 200

Q10. A contractor was engaged to construct a road in 16 days. After working for 12 days with 20
workers it was found that only th of the road had been constructed. To complete the work in
stipulated time the number of extra workers required is?
(a) 18 (b) 10
(c) 12 (d) 16

Q11. Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes
are opened simultaneously, after how much time should B be closed so that the tank is full in 15
minutes?
(a) 12 min (b) 4 min
(c) 6 min (d) 8 min

Q12. If two pipes function simultaneously the reservoir is filled in 12 hours. One pipe fills the
reservoir 10 hours faster than the other. How many hours does the faster pipe take to fill the
reservoir?
(a) 20 hours (b) 30 hours
(c) 35 hours (d) 45 hours

Q13. Three pipes A, B and C can fill a cistern in 6 hrs. After working together for 4 hours, C is
closed, and A and B fill the cistern in 4 hours. Then find the time in which the cistern can be filled
by pipe C?
(a) 6 hours (b) 12 hours
(c) 14 hours (d) 20 hours

Q14. A tank has a leak which would empty it in 8 hours. A tap is turned on which admits 6 litres a
minute into the tank, and it is now emptied in 12 hours. How many litres does the tank hold?
(a) 8260 liters (b) 8450 liters
(c) 8640 liters (d) 8660 liters

Q15. A tank is normally filled in 8 hours but takes 2 hours longer to fill because of a leak in its
bottom. If the cistern is full, in how many hours will the leak in the bottom empty half of the
tank?
(a) 20 hours (b) 45 hours
(c) 50 hours (d) 55 hours
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
2
Download From - www.studywale.co

Q16.A alone can complete a work in 16 days and B alone in 12


days. Starting with A, they work on alternate days. The total work
will be completed in:
(a) 12 days (b) 13 days
(c) 13 days (d) 13 days

Q17. A, B and C can do a piece of work in 20, 30 and 60 days


respectively. In how many days can A do the work if he is assisted
by B and C on every third day?
(a) 12 days (b) 15 days
(c) 16 days (d) 18 days

Q18. Twenty women can do a work in sixteen days. Sixteen men can complete the same work in
fifteen days. What is the ratio between the capacity of a man and a woman?
(a) 3:4 (b) 4:3
(c) 5:3 (d) Data inadequate

Q19. 10 men can complete a piece of work in 15 days and 15 women can complete the same work
in 12 days. If all the 10 men and 15 women work together, in how many days will the work get
completed?
(a) 6 (b) 6
(c) 6 (d) 7

Q20. 12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them.
How many days will they take to complete the remaining work?
(a) 2 days (b) 3 days
(c) 4 days (d) 5 days

Q21. Three men, four women and six children can complete a work in seven days. A woman does
double the work a man does and a child does half the work a man does. How many women alone
can complete this work in 7 days?
(a) 7 (b) 8
(c) 12 (d) Cannot be determined

Q22. A man, a woman and a boy can complete a job in 3, 4 and 12 days respectively. How many
boys must assist 1 man and 1 woman to complete the job in of a day?
(a) 1 (b) 4
(c) 19 (d) 41

Q23. 10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man
alone to complete the same work. How many days will be required for one woman alone to
complete the same work?
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
3
Download From - www.studywale.co

(a) 90 (b) 125


(c) 145 (d) None of These

Q24. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it
in 10 days. In how many days will 10 women complete it?
(a) 35 (b) 40
(c) 45 (d) 50

Q25. Twenty-four men can complete a work in sixteen days. Thirty-two women can complete the
same work in twenty-four days. Sixteen men and sixteen women started working and worked for
twelve days. How many more men are to be added to complete the remaining work in 2 days?
(a) 16 (b) 24
(c) 36 (d) 48

Q26. 12 men can complete a piece of work in 4 days, while 15 women can complete the same work
in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped
working. How many women should be put on the job to complete the remaining work, if it is to
be completed in 3 days?
(a) 15 (b) 18
(c) 22 (d) Data inadequate

Q27. A, B and C are employed to do a piece of work for Rs. 529. A and B together are supposed to
do of the work and B and C together of the work. What amount should A be paid?
(a) Rs. 315 (b) Rs. 345
(c) Rs. 355 (d) Rs. 375

Q28. A and B can do a piece of work in 45 days and 40 days respectively. They began to do the
work together but A leaves after some days and then B completed
the remaining work in 23 days. The number of days after which A
left the work was:
(a) 6 (b) 8
(c) 9 (d) 12

Q29. Kim can do a work in 3 days while David can do the same
work in 2 days. Both of them finish the work together and get Rs.
150. What is the share of Kim?
(a) Rs. 30 (b) Rs. 60
(c) Rs. 70 (d) Rs. 75

Q30.A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for
Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
(a) Rs. 375 (b) Rs. 400
(c) Rs. 600 (d) Rs. 800

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


4
Download From - www.studywale.co

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


5
Download From - www.studywale.co

Solution

S1. Ans.(c)
Sol.
A+B 15 4
B+C 10 60 6
A+C 12 5
2(A + B + C) = 15
A+B+C=
Time (A + B + C) = = 4 × 2 = 8 days
/

S2. Ans.(c)
Sol.
A 10 6
B 12 60 5
C 15 4
4x + 6(x – 5) + 5(x – 3) = 60
4x + 6x – 30 + 5x – 15 = 60
15x = 105
x = 7 days

S3. Ans.(d)
Sol.
A 10 6
B 15 60 4
C 20 3
2 days’ work of (A + C) = 9 × 2 = 18
Remaining work = 60 – 18 = 42
1 day’s efficiency of B + C = 4 + 3 = 7
Time = = 6 days
Work was completed in = 6 + 2 = 8 days

S4. Ans.(c)
Sol.
A 18 10
B 20 180 9
C 30 6
(B + C)’s 1-day work = 15
(B + C)’s 2-day work = 30
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
1
Download From - www.studywale.co

Remaining work = 180 – 30 = 150


Time taken by A to complete remaining work =
= 15 days

S5. Ans.(c)
Sol.
A 20 3
60
B 30 2
(A + B)’s 1-day work = 5
(A + B)’s 7-day work = 7 × 5 = 35
Remaining work = 60 – 35 = 25
Efficiency of C =
C will finish the full work in = × 10
= 24 days

S6. Ans.(c)
Sol. x → 24 days
Let efficiency of x be → 1/day
Work done by x in 4 days = 4
Remaining work = 24 – 4 = 20
20 work done by (x & y) in 12 days
Efficiency of (x + y) =
Efficiency of y = 1
Complete work done by y is =
/
= 36 days

S7. Ans.(b)
Sol. (6M + 8B) × 10 = (26M + 48B) × 2
8M = 16B
1M = 2B
6M + 8B = 20B
15M + 20B = 50B
20B × 10 days = 50B × x days
x days = 4 days

S8. Ans.(b)
Sol. 10M = 20W = 40C
1M = 2W, 1M = 4C, 1W = 2C
5M + 5W + 5C = 10W + 5W + W
35
W
2
20 × 7 = W × days
Full work is completed in = 8 months
Half work is completed in = 8/2 = 4 months
www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com
2
Download From - www.studywale.co

S9. Ans.(a)
Sol.
200 50 200 100
1/4 3/4
300 = 200 + x
x = 100 more workers

S10. Ans.(d)
Sol.
20 12 20 4
5/8 3/8
36 = 20 + x
x = 16

S11. Ans.(a)
Sol. A can fill in → 24 min
B can fill in → 32 min
Let the capacity of the tank = L.C.M (24, 32) = 96 unit.

The pipe A must be opened for 15 minutes.


So, work done by pipe A = 15 × 4
= 60 units
Remaining work = 96 – 60 = 36 unit
This 36 units must have been done by B.
So, time = = 12 min
Thus, after 12 min, B should be closed.

S12. Ans.(a)
Sol. Let’s do it by option.
Suppose the faster pipe A takes = 20 hrs.
So, slower pipe B takes = 30 hrs.

A+B→ = 12 hrs.
Thus, option (a) is correct.

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


3
Download From - www.studywale.co

S13. Ans.(b)
Sol. A + B + C → 6 hrs.
Let the total work be 6 unit.
So, work done by them in 1 hour = = 1 unit.
According to the question,
They worked for 4 hours, work done = 4 unit
Remaining work = 2 unit
This 2 unit is done by (A + B) in 4 hrs.
So, (A + B) one-day work =
The one-day work of (A + B + C) → 1
So, C → 1
1
2
Time by C = = 12 hrs.

S14. Ans.(c)
Sol. In 1 min it admits = 6 liter.
In 60 min it admits → 60 × 6 liter.
According to the question,
Water leaked in 4 hrs. = Water filled in 12 hours
= 12 × 60 × 6
= 4320 liters.
Thus, the tank holds the water which can be emptied in 8 hrs.
= 4320 × 2
= 8640 liters

S15. Ans.(a)
Sol. Filling pipe A takes = 8 hrs.
B is empty pipe.
According to the question,
A→8
A + B → 10

So, B → –1
/
So, leak can empty half of the tank in =
= 20 hrs.

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


4
Download From - www.studywale.co

S16. Ans.(d)
Sol. (A + B)’s 2 days’ work = .

Work done in 6 pairs of days = 6 . Remaining work = 1 .

Work done-by A on 13th day = . Remaining work = .


On 14th day, it is B’s turn.
work is done by B in 1 day. work is done by B in 12 day.
∴Total time taken = 13 days.

S17. Ans.(b)
Sol. A’s 2 days’ work = 2 .

(A + B + C)’s 1 day’s work = .

Work done in 3 days = .


Now, work is done in 3 days.
∴Whole work will be done in (3 × 5) = 15 days.

S18. Ans.(b)
Sol. (20 × 16) women can complete the work in 1 day.
∴1 woman’s 1 day’s work = .
(16 × 15) men can complete the work in 1 day.
∴1 man’s 1 day’s work = .
So, required ratio = = 4 : 3.

S19. Ans.(c)
Sol. 10 men’s 1 day’s work = ; 15 women’s 1 day’s work = .

(10 men + 15 women)’s 1 day’s work = .


∴10 men and 15 women will complete the work in 6 days.

S20. Ans.(a)
Sol. 1 man’s 1 day’s work = .

12 men’s 6 days’ work = 6 . Remaining work = 1 .

18 men’s 1 day’s work = 18 .


work is done by them in 1 day.

∴ work is done by them in 6 = 2 days.

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


5
Download From - www.studywale.co

S21. Ans.(a)
Sol. Let 1 woman’s 1 day’s work = x.
Then, 1 man’s 1 day’s work = and 1 child’s 1 day’s work = .
So, 4 .
∴1 woman alone can complete the work in 49 days.
So, to complete the work in 7 days, number of women required = = 7.

S22. Ans.(d)
Sol. (1 man + 1 woman)’s 1 day’s work = .
Work done by 1 man and 1 woman in day = .
Remaining work = 1 .
Work done by 1 boy in day = .
∴Number of boys required = 48 = 41.

S23. Ans.(d)
Sol. 1 man’s 1 day’s work = . (10 men + 15 women)’s 1 day’s work = .
15 women’s 1 day’s work = .
1 woman’s 1 day’s work = .
∴1 woman alone can complete the work in 225 days.

S24. Ans.(b)
Sol. Let 1 man’s 1 day’s work = x and 1 woman’s 1 day’s work = y.
Then, 4x + 6y = and 3x + 7y = .
Solving these two equations, we get: x = ,y= .
∴1 woman’s 1 day’s work = .
⇒10 women’s 1 day’s work = 10 .
Hence, 10 women will complete the work in 40 days.

S25. Ans.(b)
Sol. 1 man’s 1 day’s work = ; 1 woman’s 1 day’s work = .
Work done in 12 days = 12 12 .
Remaining work = 1 .
(16 men + 16 women)’s 2 days’ work = 2 2 .
Remaining work = .
work is done in 1 day by 1 man.
∴ work will be done in 2 days by 384 = 24 men.

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


6
Download From - www.studywale.co

S26. Ans.(a)
Sol. 1 man’s 1 day’s work = ; 1 woman’s 1 day’s work = .
6 men’s 2 days’ work = 2 . Remaining work = 1 .
Now, work is done in 1 day by 1 woman.
So, work will be done in 3 days by 60 = 15 women.

S27. Ans.(b)
Sol. Work done by A = 1 .
∴A : (B + C) = = 15 : 8.
So, A’s share = Rs. 529 = Rs. 345.

S28. Ans.(c)
Sol. (A + B)’s 1 day’s work = .
Work done by B in 23 days = 23 . Remaining work = 1 .
Now, work was done by (A + B) in 1 day.
work was done by (A + B) in 1 = 9 days.
∴A left after 9 days.

S29. Ans.(b)
Sol. Kim’s wages : David’s wages = Kim’s 1 day’s work : David’s 1 day’s work
= =2:3
∴Kim’s share = Rs. 150 = Rs. 60.

S30. Ans.(b)
Sol. C’s 1 day’s work = .
A’s wages : B’s wages : C’s wages = = 4 : 3 : 1.
∴C’s share = Rs. 3200 = Rs. 400.

www.bankersadda.com | www.sscadda.com | www.careerpower.in | www. adda247.com


7

You might also like