b) Draw symbols for lamp exhaust fan, Light socket and bell
Ans: i) Lamp ii) Exhaust Fan iii) Light Socket iv) Bell
OR
e) State general rule for deciding no. of sub circuit for lighting and power circuit.
Ans: General rule for deciding no. of sub circuit for lighting and power circuit:
Lighting Circuit :- (1 Mark)
Each sub circuit should not have more than a total 10 points (including lights, fans
and 5A socket outlet)
Each sub circuit should not exceed 800 watts.
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
2) Lock nut: To hold and seal the conduit with their wires
pole MCB
12) Kit Kat Fuse: It is a safety device available in 6A to 32 A
13) Saddles, screws, rawal plug, etc
14) Switch board, ICDP Main Switch
15) All types of size of VIR & PVC wire
or equivalent figure
or equivalent figure
OR
(Diagram: 2 Mark)
3-ph,4 wire 400v A.C. supply
Energy meter
S Main Fuse
ICTP
Star-delta starter
k) State the material and size of earth wire used for industrial installation
Ans: The material used and size of earth wire used for industrial installation: (2 Mark)
3. If the total connected load more than 20 HP then Copper strips can be used as a earth
wire
floor.
9. Lights and fans may be wired on a common circuit. Each sub-circuit is not to have
more than a total ten points of lights, fans and socket-outlets. The load on each sub-
circuit is to be restricted to 800 watts.
10. No fuse and switch is to be provided in earthed conductor.
11. Every circuit or apparatus is to be provided with a separate means of isolation such
as a switch.
12. All circuit or apparatus requiring attention are to be provided with means of access
to it.
13. In any building, light and fan wiring and power wiring are to be kept separate.
14. In 3-Phase, 4-wire installation the load is to be distributed equally on all phases.
15. No additional load is to be connected to an existing installation unless it has been
ascertained that the installation can safely carry the additional load and that the
earthing arrangements are adequate.
16. Lamp holders used in bath rooms are to be constructed or shrouded in insulating
materials and fitted with protective shield and earth continuity conductor is not to be
size less than 7/0.915 mm.
17. The metal sheaths or conduits for all wiring and metal coverings of all consuming
apparatus or applications is to be properly earthed in order to avoid danger from
electrical shock due to leakage or failure of insulation.
18. Each sub-circuit is to be protected against excessive current (that may occur either
due to over load or due to failure of insulation) by fuse or automatic circuit breaker.
19. All light conductors are to be insulated or otherwise safe guarded to avoid danger.
After completion of work the installations are to be tested (the test are to be
carried out as described) before energisation.
20. Earth Resistance : should be very low for domestic installation it should be equal to
or less than 5 ohm to 8 ohm
21. Insulation Resistance between conductor : should be very high for domestic
installation it should be equal to or more than 1 mega ohm or it should be not be
50 M
less than =
Number of outlet
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
A room is to be fitted with 1 fan, 1 tube and one light socket. Draw single line diagram,
c)
schematic diagram and wiring diagram
Ans: Single line diagram for 1 fan, 1 tube and one light socket : (2 Marks)
Schematic diagram for 1 fan, 1 tube and one light socket : (1 Marks)
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Wiring diagram for 1 fan, 1 tube and one light socket : (1 Marks)
or equivalent figure
Compare underground service connection and overhead service connection on the basis
e)
of safety, Labour cost, location and installation time
Ans: Compare underground service connection and overhead service connection:
( Each Point : 1 Mark)
S.No Basis Underground service Overhead service connection
connection
1 Safety More safety Less safety
A room consists of following load Tube points 4 Nos : 40 watt each, Fan points 3 nos :
100 watt each, Lamp points 2 nos : 60 watt each, 5A socket outlet 4 nos : 100 watt each,
15A socket outlet 2 nos: 1000 watt each,
b) Find i) Total light load and power load
ii) No. of sub circuits required
iii) Rating of main switch
iv) Rating of DB required
Ans: Given Data: (All data is assumed it may vary or it may not be available, there will be
only steps and this steps are expected) (Give stepwise Marks as mention below)
ii) Total connected Power load in a house 2 1000 2000W or 2.0 KW , (1/2 Mark)
980
Total load in 1.225 2 Nos lighting sub circuit (1/2 Mark)
iii) 800
2000
Total load in 1 Nos Power sub circuit (1/2 Mark)
2000
iv) Distribution Board: So, 3 Number of MCB are required -------------------- ( 1/2 Mark)
Current rating Iron clad main switch = 32A ---------------------------- (1/2 Mark)
vi) Value of current rating of iron clad main switch: ------------------------- (1/2 Mark)
So Use: - 250V, 32A, ISI mark Main switch of any company
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
1) Find out the type of load and total electrical load for the given commercial installation.
2) Differentiate this total electrical load in lighting load and power load.
3) Make the no. of lighting sub circuit for lighting load.
Total Electrical lighting load
No. of Lighting Sub circuits
800 W
OR
Total No. of lighting po int
No. of Lighting Sub circuits
10
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
f) A motor is to be operated with star delta starter. Draw wiring diagram showing
connection for motor, starter and motor switch
S Main Fuse
ICTP
Λ / Δ starter
IM 3 Ø Induction motor OR
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Wiring diagram –
1. To provide an alternative path for the leakage current to flow towards earth.
2. To save human life from danger of electrical shock due to leakage current.
3. To protect high rise buildings structure against lightening stroke.
4. To provide safe path to dissipate lightning and short circuit currents.
5. To provide stable platform for operation of sensitive electronic equipments.
Diagram for plate earthing : ( 2 Marks)
or equivalent figure
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
A room 4m x 5m is to be fitted with one tube, one fan and one 5A socket. Draw
b)
installation plan and wiring diagram. Calculate length of conduit and wire required.
Ans: Note: Credits may be given step wise for numerical problems. In some cases, the
assumed constant values may vary and there may be some difference in the
candidate’s answers and model answer.
Given Data: (The Assumed data may be vary (Give stepwise Marks as mention below)
Total load in Hall tubes watt 1 40 40 W
Fans watt 01 60 60 W
= 1.5 + 4+2+1+2.5+10%
= 11+10%
= 12.1 Mtr
= 12 x 3 +20 % extra
= 36+ 20%
or equivalent figure
Describe how rating of main switch, motor switch DB and cable is decided in industrial
c)
installation.
Ans: (Reason of main switch:2 Marks & Reason of main switch B & cable : 2 Mark)
1. Reason of Main Switch or Fuse Rating is decided in industrial installation:
Rating of main switch or fuse is based up the starting current of motor.
For calculating starting current is considered 2 times that of full load current,.
Thus main switch is decided.
If number of motors are there, then main switch is decided from following
formula.
Incoming current = Starting current of highest rated m/c + Full load current remaining all m/c
Thus from incoming current main switch is decided
2. Reason of Cable Rating is decided in industrial installation:
The current rating of cables for supply to motor is based up on the normal full
load current of motor considering the overload capacity 50%
We take 1.5 times the rated current or full load current. & thus cable rating is
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
decided.
3. Reason of DB Rating is decided in industrial installation:
i.e MCB or fuse rating is decided from starting current of motor which explained
above.
d) State any six requirements of valid contract.
Ans: Following requirements of valid contract:
( First Two point: 1 Mark each & other Four Point:1/2 Mark each –Total 4 mark)
1. Contract should be written.
2. Contract should be signed by proper witness
3. Contractor licenses should be valid.
4. Contract should be signed by competent authority.
5. Contract should be signed by proper authorized persons.
6. It should be legally valid.
e) Give complete procedure for submission and opening of tender.
Ans: Procedure of submission Procedure of Tender:- (2 Marks)
The tender is submitted from party No.2 (Bidder) to party No.1 (Owner) in sealed
envelopes within the specification date & time period.
The is submitted in envelops No.2 titled by envelop No.1 & envelop No.2.
The content in every envelop is given an above.
OR
The system of submitting tender documents is also called as two envelope system.
The treasury challan, deposit, call receipt, forwarding letter the copies of
registration certificate, income tax clearance certificate, and list of machinery to be
used to be sealed in one envelope.
The tender set itself with quoted value should be sealed in another envelope: these
two sealed envelopes should again be put in one coverer and sealed. On the top of
this cover, the name of the work, address of the receiving authority should be
written. These envelopes are then handed over in person or send by post to the
address mentioned before the specified time and date
OR
According to old procedure three envelopes are there and in third envelope rate
offered by the tenderer is given and it is mention at “ Envelop No.3”
of every bidder.
Initially envelop No.1 of every party is opened. The all documents which are
given as above are checked if found O.K. then envelope No.2 of those parties is
opened.
If one of the party having the any short coming in envelop No.1 then the envelop
No.2 of that party is not opened.
The all contents in envelop No.1 are checked. It is as above & after opening the
all envelops of all parties the comparative statement is done and for suitable
company the contract is handed over.
If one of the company having quotation of lowest price can be rejected by party
No.1 (Owner) due to poor reputation, large works in hand, unsuitable drawing or
without any reason.
At first envelop No.1 of all parties are opened and comparative statement of all
parties done.
The rejected party of whose envelope No.1 is invalid there envelope No.2 are not
opened it is freezed.
For all reaming parties envelope No.2 opened and detailed comparative
statement is done.
For lowest eligible bidders the contract is handed over.
Total load in One Shop tubes inWatt Fans in Watt Socket in watt Power Sockect
i) Total load in one Shop 120 120 1000 1240 watt ---------------------- (1 Mark)
1240
Total load in one shop Amps 5.391 Amp assu min g p. f . 0.9 - (1/2 Mark)
230
240
ii) Total load in 0.3 1 Nos lighting sub circuit ----------------- (1/2 Mark)
800
1000
Total load in 0.5 1 Nos Power sub circuit ------------------ (1/2 Mark)
iii) 2000
iv) Total load in one floor Total Shop Total load in one shop -------- (1/2 Mark)
12400
Total load in One Floor in Amp
646.902
Total load in One Floor in Amp 19.1682 Amp ------------------------------ (1 Mark)
vi) Total Load in Building = 3 floor x 1 floor total Load
= 3 x 12400
= 37200 watt
= 37.200 KW
37200
vii) Total load in building ----------------------------------- (1/2 Mark)
3 415 0.9
37200
Total load in building
646.902
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
Wiring Diagram for Lighting circuit in one shop:- (Similar to other shop & Building
floor) (1-Marks)
or equivalent figure
or equivalent figure
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
A hall of 10m x 6m is to be fitted with 8 fan and 15 tubes. Pare schedule of material for
b)
complete installation.
Ans: Note: Credits may be given step wise for numerical problems. In some cases, the
assumed constant values may vary and there may be some difference in the
candidate’s answers and model answer.
Given Data: (The Assumed data may be vary (Give stepwise Marks as mention below)
Total load in Hall tubes watt 15 40 600 W
Fans watt 08 60 480 W
1080
ii) No. of Sub circuit 1.35 2 Nos lighting sub circuit ------------ (1 Mark)
800
23
According to po int No. of Sub circuit 2.3 3 Nos lighting sub circuit
10
Conduit required :
= 1+1.5+1.5+5x7+3
= 3+35+3+10%
= 41+4.1
= 45 Mtr
Wire required :
= 135+20%
= 162 Mtr
Note:- Cost of material it not required or may vary so do not stick on final figures
Ans: Note: Credits may be given step wise for numerical problems. In some cases, the
assumed constant values may vary and there may be some difference in the
candidate’s answers and model answer.
Assuming height of Ceiling if 3 m from the floor.
Motor is installed 1 M away from the nearest wall.
Height of Main Switch is 1.2 M from the floor
Step No. 1:- The out power of induction motor = 10 x 735.5 = 7355 W-------- (1/2 Mark)
Step No. 2:- Input power of I. M = output power of I M / efficiency of IM motor.(1/2 Mark)
Assuming efficiency of I.M is 80 %
Input power of induction motor = 7355 / 0.8 = 9193.75 W
Step No. 3:- To determine the rated current for I.M ---------------------------------- (1/2 Mark)
P 3 V L I L Cos V L 415 V
P
IL
3 VLCos
9193.75
IL Cos 0.8 assumption
3 415 0.8
I L 15.98 Amp Rated current 15.98 Amps
Step No. 4:- To determine the size & core of cable:- --------------------------------- (1/2 Mark)
Starting current is assumed two times rated input current for starting surge,
momentary short circuit & overload. Starting current = 2 x 15.98 = 31.96 Amps
So use,
10 Sqmm 3 core cable for the I.M.
Step No. 5:- Determined the size length & dimensions of ICTP earth wire at input cable:-
The rating of main switch is 450 V, 32 Amp ICTP ISI mark
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
or equivalent figure
Step No. 7:- Find out the estimation chart with material cost & labour cost: ----- (4 Mark)
Length of cable - it should be calculated as per their assumed distances
Material Shedule:
Ratings of main switch, DB, Motor switch and Starter are decided by the following
points:-
1 735.5
Rated input current I L
3 415 efficency P. f
= 1.6 Amp
But IFL is given 5A, So use
Main switch : ICTP, 415V, 8A or 5A
DB : 3-Ph, 415V, 10A, Distribution board of two outlet
Motor switch: 415V, 16A industrial plug socket
Starter : 3-Ph, 415 V, 1 HP DOL Starter
ii) Rating for 3 HP, 3-Ph Slip ring IM, IFL = 8A:-
Total power Total H .P 735.5
Total power 3 HP 735.5 735.5 watt
Total power .2206.5 watt
HP 735.5
Rated input current I L
3 V L Cos
MAHARASHTRA STATE BOARAD OF TECHNICAL EDUCATIOD
(Autonomous)
(ISO/IEC-27001-2005 Certified)
3 735.5
Rated input current I L
3 415 efficency P. f
= 4.80 Amp
But IFL is given 8A, So use
Main switch : ICTP, 415V, 16A
DB : 3-Ph, 415V, 16A, Distribution board of two outlet
Motor switch: 415V, 32A industrial plug socket
Starter : 3-Ph, 415 V, 3 HP Rotor resistance Starter
Ans: (Costing of material is not required marks are only allotted for Material list: 12 Point
Expected Each Point: 1 Marks –Total 12 Marks)
Total load in Hall tubes in Watt Fans in Watt Lamps in WC & Bath
ii) Estimate the cost of installation for workshop as shown in figure No. 3
Ans: (Costing of material is not required marks are only allotted for Material list: 12 Point
Expected Each Point: 1 Marks –Total 12 Marks)
HP 735.5
Rated input current I L
3 V L Cos
2206.5
Rated input current I L
3 415 efficency P. f
2206.5
Rated input current I L
3 415 0.85 0.85
1471
Rated input current I L
3 415 efficency P. f
1471
Rated input current I L
3 415 0.85 0.85
------------------------------------------------------END-------------------------------------------------------