Case Analysis Part 1
Case Analysis Part 1
SOUTHWESTERN UNIVERSITY
Submitted by:
CHIONG, Zeimuill Andrau P.
GAMOTIN, Jessa Mae E.
IBALE, Charissa Joyce D.S.
ACA
Submitted to:
MRS. LHEIDA MARIZ L. BARACCAO
BA24 Teacher
Discussion Questions:
1. Develop a network drawing for Hill Construction and determine the critical path. How long is the project
expected to take?
2. What is the probability of finishing in 270 days?
3. If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case,
assume that optimistic time estimates can be used as crash times.
2
II. Analysis
Question No.1
Determine a network drawing for Hill Construction and determine the critical path. How long is the project
expected to take?
Step 1: To compute for “Normal Days” to be used in AoN Network, we will use PERT:
Table 1. Project Scheduling Considering Uncertain Activity Times
Activity Description Optimistic Most likely Pessimistic Expected time Variance
a m b t = (a+4m+b)/6 [(b-a)/6]2
A Bonding, insurance, tax structuring 20 30 40 30 11.11
B Foundation, concrete footings for boxes 20 65 80 60 100
C Upgrading skybox stadium seating 50 60 100 65 69.44
D Upgrading walkways, stairwells, elevators 30 50 100 55 136.11
E Interior wiring, lathes 25 30 35 30 2.78
F Inspection approvals 0.1 0.1 0.1 0.1 0
G Plumbing 25 30 35 30 2.78
H Painting 10 20 30 20 11.11
I Hardware/AC/metal workings 20 25 60 30 44.44
J Tile/carpet/windows 8 10 12 10 0.44
K Inspection 0.1 0.1 0.1 0.1 0
L Final detail work/cleanup 20 25 60 30 44.44
TOTAL 360.2 422.65
Step 3:
Critical Path (CP): A–C–D–G–H–I–L
Projected Finish Time: 30 + 65 + 55 + 30 + 20 +30 +30
= 260 DAYS
Projected Variance of CP: 11.11 + 69.44 + 136.11 + 2.78 + 11.11 + 44.44 + 44.44
= 319.43
Standard Deviation of CP: √Projected Variance of CP or √319.43
= 17.87
3
estimates (optimistic, most likely, and pessimistic) and come up the expected time for each activity using the
formula presented in Table 1. Since there are three given time estimates, we need to know the dispersion or
variation (see Table 1) in the activity time values. The difference between the pessimistic (b) and optimistic (a)
time estimates greatly affects the value of the variance. Large difference between these two values reflect a
high degree of uncertainty in activity times. Moreover, due to this fact, we can conclude that the projected 260
days of completion is not absolute enough because variation in activities can cause variation in the project
completion time. However, the variation on noncritical activities ordinarily has no effect on the projected completion
time because of the slack time associated with these activities. Take note that for planning purposes, the expected
time still provides valuable information for project managers.
PERT calculates a weighted average as the PERT estimate by using the formula: Pert Estimate =
(Optimistic + (4 x Most Likely) + Pessimistic)/6. That means that we are weighting the most likely estimate by a
factor of four (4) and then determining the average of the weighted most likely time, the best-case scenario and
the worst-case scenario. In the case of Activity A (refer to Table 1), that will be (20 +(4 x 30) +40)/6. The PERT
estimate is therefore calculated as 30 days. If we compare the PERT estimate of 30 days with the normal average
of the three estimates of 30 days (20 + 30 + 40 / 3 = 30) we can see that the PERT estimated is weighted towards
the most likely estimate. We use a weighted average calculation because statistically we find that the largest
portion of a randomly occurring population of data will be found close to the mean as can be seen from the following
bell curve, also called a normal distribution curve:
Mean
Percentage of
cases in 8 portions
of the curve .13% 2.14% 13.59% 34.13% 34.13% 13.59% 2.14% .13%
Standard Deviation
One Sigma: 68%
Two Sigma: 95%
Three Sigma: 99.7%
4
distribution. This also gives us a tool with which we can quantify the probability of how the data will be distributed.
Applying this to Activity A:
Mean
Percentage of
cases in 8 portions
of the curve .13% 2.14% 13.59% 34.13% 34.13% 13.59% 2.14% .13%
Standard Deviation
20 23.33 26.67 30 33.33 36.67 40
Solution:
1 Standard Deviation: 30 + 3.33 = 33.33
-1 Standard Deviation: 30 – 33.33 = 26.67 Same formula applies for the rest.
From the bell curve above, we can thus predict that for Activity A, there is a:
68% probability of completing the activity between 26.67 and 33.33 days.
95% probability of completing the activity between 23.33 and 36.67 days.
99.7% probability of completing the activity between 20 and 40 days.
The same formulas can be used to calculate the one, two and three sigma figures for the critical activities.
The project standard deviation can be calculated by determining the square root of the sum of the PERT
variances. As per presented in the Table 1, the PERT variances is 319.43. The square root of 319.43 is 17.87 (see
computations on page 3). Therefore, one standard deviation for the project as a whole is 17.87 days. This value
can now be used to calculate the values for one, two and three sigma for the total project.
Conclusion:
From the fact stated in the paragraph above we can now conclude that there is:
68% probability of completing the project between 242.13 and 277.87 days.
95% probability of completing the project between 224.26 and 295.74 days.
99.7% probability of completing the project between 206.39 and 313.61 days.
In practice these percentages can be used to indicate, due to the uncertainty of the estimates, that there is a:
50% probability that the project will be completed within 260 days.
68% probability that the project will be completed within 278 days.
95% probability that the project will be completed within 296 days.
99.7% probability that the project will be completed within 314 days.
5
Question No. 2:
What is the probability of finishing in 270 days?
Assuming that the distribution of the path completion time follows a normal or bell-shaped distribution, we
can now compute the probability that a path of activities will meet be completed within a specified time. Now,
suppose the project manager wanted to know probability of finishing the project in 270 days, he can go back to the
values computed before— the Expected Time and Standard Deviation, using the formula:
Due Date - Expected Time
z=
Standard Deviation
Computation: Conclusion:
Referring to the Standard Normal Distribution Table, the corresponding value
270 - 260
z= = 0.5595970901 for 0.56 is 0.7123. This means that the probability of finishing the project
17.87 in 270 days is 71.23%
As you have noticed, there is a small difference between the conclusion in Question No.1 (“There is a
68% probability that the project will be completed within 278 days.”) and No. 2. This is because there is really no
absolute prediction. Moreover, there are quite difference in the underlying assumptions in the formula used.
Remember that all these percentages were all based on estimates and estimates have their own basis.
Question 3:
If it is necessary to crash to 250 or 240 days, how would Hill do so, and at what costs? As noted in the case,
assume that optimistic time estimates can be used as crash times.
When crashing an activity, we assume that each unit of time gained by crashing an activity has the same
associated cost. For this requirement, we will select the activity on the critical path with the smallest crash cost per
day— which is Activity A. To know the maximum possible reduction in time for activity due to crashing, we will
deduct the time for activity under maximum crashing (optimistic time) from the expected time. That is 30 days –
20 days = 10 days. Thus, we can reduce the total project completion date by 10 days which means we can now
“probably” finish the project within 250 days. However, reducing A will cost $1,500 per day.
In order to further reduce the number of days to 240 days, we will still need to crash another project. This
reduction can be achieved by crashing H (using the same formula before) for an additional cost of $2,000 per day.
Now, the total cost to crash to 240 days is $35,000.
Conclusion:
Table 4. Summary of Project Crashing
Activity Description Days Reduced Cost per Day Total Cost
A Bonding, insurance, tax structuring 10 days $1,500 $15,000
H Painting 10 days 2,000 20,000
TOTAL 20 days $3,500 $35,000
You can say that we can also crash D instead of H since it has lower cost than H. However, that is not
the only factor to consider. Crashing D will reduce the days from 250 to 225. However, since it has more days than
H and remember that we assume that each unit of time gained by crashing an activity has the same associated
cost therefore it will still incur higher costs of $28,500 (25 days x $1,900) in total.
6
SOUTHWESTERN UNIVERSITY
Case Analysis PART II
I. The Case:
Southwestern University (SWU), a large state college in Stephenville, Texas, enrolls close to 20,000
students. The school is a dominant force in the small city, with more students during fall and spring than permanent
residents.
Always a football powerhouse, SWU is usually in the top 20 in college football rankings. Since the
legendary Phil Flamm was hired as its head coach in 2009 (in hopes of reaching the elusive number 1 ranking),
attendance at the five Saturday home games each year increased. Prior to Flamm’s arrival, attendance generally
averaged 25,000 to 29,000 per game. Season ticket sales bumped up by 10,000 just with the announcement of
the new coach’s arrival. Stephenville and SWU were ready to move to the big time!
The immediate issue facing SWU, however, was not NCAA ranking. It was capacity. The existing SWU
stadium, built in 1953, has seating for 54,000 fans. The following table indicates attendance at each game for the
past 6 years.
One of Flamm’s demands upon joining SWU had been a stadium expansion, or possibly even a new
stadium. With attendance increasing, SWU administrators began to face the issue head-on. Flamm had wanted
dormitories solely for his athletes in the stadium as an additional feature of any expansion.
SWU’s president, Dr. Joel Wisner, decided it was time for his vice president of development to forecast
when the existing stadium would “max out.” The expansion was, in his mind, a given. But Wisner needed to know
how long he could wait. He also sought a revenue projection, assuming an average ticket price of $50 in 2016 and
a 5% increase each year in future prices.
Discussion Questions
1. Develop a forecasting model, justifying its selection over other techniques, and project attendance
through 2017.
2. What revenues are to be expected in 2016 and 2017?
3. Discuss the school’s options.
7
II. Analysis
Question No.1
Develop a forecasting model, justifying its selection over other techniques, and project attendance through
2017.