CHAPTER 5 Project Control and Monitoring
CHAPTER 5 Project Control and Monitoring
CHAPTER 5
PROJECT CONTROL The concept of monitoring
1
Monitoring & Control: A Feedback Process
INTRODUCTION
The purpose of the project control process is to
guarantee that design requirements, budget and schedule
Detect are met by project team.
deviations
Project control begins with a plan composed of design
documents, an estimate, and schedule
PROJECT CONTROL
Project Controls are the data gathering, data management and
analytical processes used to predict, understand and
constructively influence the time and cost outcomes of a
project or programme; through the communication of
information in formats that assist effective management and
decision making.
7 8
2
Project Control Objectives
1. Check progress against acceptable standards at key
dates
standards of quality are defined by the specs.
Standards of quantity are defined by the drawings
standards of budget are defined by the estimate.
Standards of time are defined by the schedule.
11-12
3
Project Control Cycle
The development of a suitable Project Control system is an to conformance as the measure of quality during the construction
important part of the project management effort (Shtub, Bard & process, the specification of quality requirements in the design
Globerson 2005). and contract documentation becomes extremely important.
Safety during the construction project is also influenced in large
It is widely recognised that planning and monitoring plays a major part by decisions made during the planning and design process.
role as the cause of project failures. Some designs or construction plans are inherently difficult and
dangerous to implement, whereas other, comparable plans may
considerably reduce the possibility of accidents.
Despite the continuous evolution in the project management field, For example, clear separation of traffic from construction zones
it appears evident that the traditional approach still shows a lack during roadway rehabilitation can greatly reduce the possibility of
of utilisation of Project Controls and there have been a number of accidental collisions. Beyond these design decisions, safety
articles published to support the importance of control in the largely depends upon education, vigilance and cooperation during
achievement of project objectives.
the construction process.
Workers should be constantly alert to the possibilities of
It has been proved time and again that Project performance can accidents and avoid taken unnecessary risks.
be improved if dedicated Project Controls systems are in place.
15 16
4
An effective Project Controls process can be applied in:
18
Contd.
ACWP
5
Tradeoffs
Acceleration RM Impediments to Project Acceleration
(Overtime, shift work, Need for rework imposes
Rework, higher-end
equipment, better crews etc.)
Slow progress RM
RM high expenses
High quality needs can lead
to costly miscalculations
Human resources
Multiple-shift work
on labor time Environmental/safety issues, High cost, Neighborhood objections
Delayed occupation,
Higher interest on Overtime/extended workdays
Less RM Low progress
const. loan Trying to save $ Fatigue, Lower morale, Rework
Resource reduction
Loss of tenants Can lead to substitution, Increasing # of workers
Selection of poor quality workers
Opportunity cost lower quality Training (takes time of most experienced!), Space constraints, Hiring time
Default of contractor/subs
workmanship
Technology
Time Quality Using more, larger or more efficient equipment
Quality level impacts speed of work, Training/learning curve, Procurement time, Space constraints
Level of rework
Using faster-installing materials
Procurement, Submittals for owner approval
Quality problems result from
overtime, shift work, new hires Alternate construction methods
Skill set, Learning curve, Unknown side-effects
b) observation of activities
23
24
6
Selection of Control Measures Observation of Activities
Personal Protective Equipment (PPE) is the first line of controls used on
construction projects with regards to health & safety. PPE includes hardhats,
protective glasses, steel toed boots, reflective vests, gloves, etc.
Proper storage and disposal of hazardous materials is a major concern, if they are
The procedures are based upon the
present on the job site. The contractor should have all of the MSDS sheets for
every chemical on site, and comply with the suggested storage and disposal
Ordinance, Subdivision Regulations, Site Plan
methods on the MSDS. Regulations and Construction Standards as
Clean-up of the site is a major concern for worker and public safety. The well as all applicable Federal & State
contractor should clean-up construction debris daily from the area where they were
working before they leave for the day. regulations.
Extra clean-up should also be performed before they leave for the weekend.
Placing barricades (rope, fence, jersey barricades, etc.) to prevent traffic from
interfering with the construction work should be maintained. This traffic includes
the public, who may come over to see what is going on, and will not be wearing Visit the site at intervals appropriate to the
PPE.
stage of construction, in order to observe the
Each specific activity on a construction requires it's own control measures, for
example, excavation requires sloping, shoring, or sheeting to protect the workers in progress and quality of the work completed by
the trench from cave-ins. the Contractor.
Entering into confined spaces requires it's own type of controls, such as air testing
for hazardous gasses, supplying a "clean" air flow while workers are present,
harness and retrieval equipment, etc.
25 26
Project Documentation: Prepare daily reports, photography, field measurements, Wetland Delineation Driveways
construction notification memos, bi-monthly summary reports & meeting memos
as necessary. Clearing & Grubbing Traffic Control Devices
Subgrade Construction Street Trees and Landscaping
Control Water System: Control access and use of the water supply system. Only
authorized representatives shall operate water valves and shutoffs. Blasting Monumentation
Utility Construction Miscellaneous Site Features
Monitoring all independent testing with respect to material, compaction and Subgrade Preparation As-Built Plans
utilities to determine compliance with all applicable county and State regulations
including but not limited to the following: materials, drainage, sanitary sewer and Bank Run Gravel Base Final Walkthrough
water
Placement
Crushed Gravel Placement
27
28
7
Collection of Control Data
cross-checks within the data collection process and
data quality being as much an observation-level
issue as it is a complete data set issue
Example of control data:
a) Labour
b) Machinery
c) Financial
d) Utility
e) Time/schedule
f) Testing etc.
29 30
32
31
8
Delivery Methods
33 34
35 36
9
Building Commissioning
is quality assurance process for achieving, verifying, and
Quality Control documenting that the performance of facility systems and
assemblies meet the defined objectives and criteria for the
project. It is a systematic process of ensuring that building
Quality control starts with matching expectations systems perform interactively and effectively according to
the design intent and the owner's operational needs. This is
about quality levels with budget and scope during achieved by documenting the owner's requirements and
planning and design reviews and continues assuring those requirements are met throughout the entire
through construction delivery with a program of delivery process. Commissioning coordinates and integrates
inspections, tests, and certifications. It requires a planning development and design decisions and verifies that
coordinated performance among the entire the delivered facility and its capabilities are efficient and
work correctly.
project team in order for a completed building
program to fully satisfy a client's and the building
users' expectations.
37 38
QUALITY ASSURANCE
Quality Assurance (QA) focuses on the processes utilized in the project
efficiently to generate quality project deliverables. It includes the following
meeting standards, progressive enhancing project work and eliminating
project defects.
This concept emphasizes the continued control of the start of production
until the beginning of the process that produced the final product.
Quality Assurance assures the quality of the product meaning that this
process ensures that the product generated from the process is defect
free and conforms to all stated customer requirements. It is said to be a
process-based approach whose primary objective is to prevent defects in
deliverables at the planning stage to avoid rework, which increases
process costs.
Quality Assurance can also be viewed upon as a proactive process and it
places importance on planning, documentation, and guidelines finalization
that will be needed to assure the quality. This process begins at the very
start of the project to compare the product’s requirements and
expectations. Once all requirements and expectations are recognised, a
plan is developed to meet these requirements and expectations.
39
40
10
QUALITY ASSURANCE VS. QUALITY CONTROL
42
41
43 44
11
The Difference between Quality Assurance and Quality Control:
READING LIST
The Benefits of Quality Assurance and Quality Control
Anderson, E., Grude, K.V. and Haug, T. (1987), Goal Directed Project Management (2nd Edition), London: Kogan Page.
Burke, R. (2003), Project Management Planning and Control Techniques, 4th Edition, Chichester, UK: John Wiley and Sons Ltd.
The following are few benefits of these processes:
Fondahl, John W., “Non-Computer Approach to the Critical Path Method for the Construction Industry”, Report #9, Stanford
University, 1961
• High quality output Fondahl, John W. “The History of Modern Project Management –Precedence Diagramming Methods: Origins and Early
Development”. Project Management Journal. Volume XVIII. No. 2. June 1987.
• Eliminate waste or in the very least minimize waste Gray, C. F. and Larson, E. W. (2006), Project Management: The Managerial Process, 3 rd Edition, NY: McGraw Hill/Irwin.
Hendrickson, Chris & Au, Tung, Project Management for Construction, Prentice Hall, 1989
• Increase the efficiency of operations by a large factor Knatterud.,G.L., Rockhold, F.W., George, S.L., Barton, F.B., Davis, C.E., Fairweather, W.R., Honohan, T., Mowery, R, O’Neill, R.
(1998). Guidelines for quality assurance in multicenter trials: a position paper. Controlled Clinical Trials, 19:477-493.
• Offer customer satisfaction, which positively affects your brand Most, .M.M., Craddick, S., Crawford, S., Redican, S., Rhodes, D., Rukenbrod, F., Laws, R. (2003). Dietary quality assurance
processes of the DASH-Sodium controlled diet study. Journal of the American Dietetic Association, 103(10): 1339-1346.
and helps individuals and organizations grow their business
Murray, M. and Langford, D. (2004), Architect’s Handbook of Construction Project Management, London: RIBA Enterprises.
Reiss, G. (1995), Project Management Demystified: Today’s Tools and Techniques, 2 nd Edition, London: Spon Press.
• Less rework and after-sale support is needed. This will aid one
Stracke, Christian M. (2006): "Process-oriented Quality Management", in: Ehlers, Ulf-Daniel/ Pawlowski, Jan Martin (Eds.):
save a lot of money Handbook on Quality and Standardisation in E-Learning. Berlin: Springer. 79-96.
Weber, Sandra C., Scheduling Construction Projects: Principles and Practices, Prentice Hall, 2005
• Promote high levels of confidence and a motivated team
Whitney, C.W., Lind, B.K., Wahl, P.W. (1998). Quality assurance and quality control in longitudinal studies. Epidemiologic
Reviews, 20(1): 71-80.
48
47
12