PFE GEN4 Specification
PFE GEN4 Specification
(PFE)
LIST OF TABLES
Table 1— Reference Documents .................................................................................................................................................. 6
1.2 Subcontractors
All relevant subcontractors shall also be ISO 9001 registered or, if not registered, the material
being used shall undergo appropriate incoming inspection and controls to ensure their
conformance.
1.6 Non-conformances
The supplier shall provide customer with copies of all non-conformances associated with
contractually agreed upon requirements at the earliest point in the manufacturing process.
2 REFERENCE DOCUMENTS
Document No. Title
EN60950 Safety of Information Technology Equipment
Telcordia
NEBS™ Requirements: Physical Protection
GR-63-CORE
Power Beach
Feed Manhole
Equipment Stress Cone
Power Feed Conduit
Closure
Submarine
Cable Duct
Splice
Fiber Distribution Panel Fiber Optic Conduit
Closure
fig 0036
The PFE shall be capable of double end feed (DEF) and single end feed (SEF) powering of the
system. The design shall not prevent the system from DEF powering when there is a short circuit
cable fault at any point along the route provided that the line current remains within the design
limits specified herein.
In a DEF system, the near-end PFE shall be capable of being balanced with the far-end PFE. An
order wire access connection shall be provided on the PFE to facilitate far-end communication.
Test Load
• Capable of dissipating 13.5kW continuously
Power Converter
• hot-swap capability
• four converters required for n+1 redundancy
• operation in either Constant Current or Constant Voltage mode
• ramping the output regardless of the operating mode
• autonomous operation
An open or short circuit condition on the PFE output terminals shall not cause damage to the PFE.
The PFE shall be capable of ramping current into a short circuit, and capable of ramping voltage
into an open circuit.
The system polarity shall be reversible. The polarity reversal mechanism and procedure shall
ensure the safety of operating personnel. The system shall be protected against incompatible
polarity settings. Polarity indication shall be shown on the front panel of the Output Monitor Unit
(OMU)
CV DC DISTRIBUTION
(CV DCD)
LCU
PFE
MONITOR
NETWORK
SWITCH
1A
ASSA
TL DC DISTRIBUTION
BAT A
1 2 3
A
4 5
CONVERTERS (MAIN)
6 1 2 3
B
4 5 6
(PFE DCD)
(PFE DCD) BAT B
BATTERY
VOLTAGE
+ -
2A
A
ASSA
B BATTERY
+ - A CONVERTERS (AUX) B VOLTAGE
+ -
1 2 3 4 5 6 1 2 3 4 5 6 A
B
+ -
(OPU)
NETWORK SWITCH
NSU
1 2 3 4 5 6 7 8 9
SPEED
(NSU)
POWER L/A
ERROR F/H
1 2 3 4 5 6 7 8 9
SPEED
POWER L/A
ERROR F/H
POWER
ERROR
SPEED
L/A
F/H
1 2 3 4 5 6 7 8 9
LCU
(LCU) 1V = 1kV
1V = 1A
EMERGENCY STOP
+
+
-
VOLTAGE
-
CURRENT
ALARM CUTOFF
ACO ACTIVE
HV ACTIVE
MINOR ALARM
MAJOR ALARM
ACTIVE TEST LOAD
(ATL)
IN SERVICE
OUT OF SERVICE
CAUTION
2 PERSON HANDLING
REQUIRED
CAUTION
UNIT WEIGHS
XX kg (XXX lbs) CONVERTER
OUTPUT MONITOR
- + STATION 1V = 1A CURRENT
NORMAL MINOR ALARM
1V = 1A GROUND PFE
CURRENT TEST OUTPUT MAJOR ALARM
- + OCEAN STATUS
1V = 10V GROUND BYPASS IN SERVICE
VOLTAGE
OUT OF SERVICE
CAUTION
2 PERSON HANDLING
REQUIRED
CAUTION
(OMU)
UNIT WEIGHS
XX kg (XXX lbs) CONVERTER
1A
NORMAL
OCEAN
GROUND
STATION
IN PLACE FOR PROPER
CV3
(PTL1)
HV GROUND
CABLE
SHORT
TEST OG
ALARM CUTOFF
JACK EMERGENCY STOP
+ -
TEST 1V = 1kV VOLTAGE ACO ACTIVE
JACK HV ACTIVE
+ -
1V = 1A CURRENT
MINOR ALARM
OMU
MAJOR ALARM
IN SERVICE
OUT OF SERVICE
CAUTION
2 PERSON HANDLING
REQUIRED
CAUTION
UNIT WEIGHS
XX kg (XXX lbs) CONVERTER
tyco submarice systems ltd.
CV4
OMU OUTPUT INTERLOCK:
THIS MODULE MUST BE PULLED OUT 9" MINIMUM TO ENABLE INSERTION OR REMOVAL OF OMU
IN PLACE FOR PROPER
(SD)
+ -
1V = 1kV VOLTAGE ACO ACTIVE
(PTL2)
+ - HV ACTIVE
1V = 1A CURRENT
MINOR ALARM
MAJOR ALARM
IN SERVICE
OUT OF SERVICE
CAUTION
2 PERSON HANDLING
REQUIRED
CAUTION
UNIT WEIGHS
XX kg (XXX lbs) CONVERTER
tyco submarice systems ltd.
Emergency *Dedicated
Stop Input Station Earth
* PWRA
HV Out
* PWRB Power
* PWRAR Feed
Power Feeding Earth
* PWRBR Equipment
100 Base-T Office Alarms
Ethernet
Electroding ACO
Interface
Cable *
Rack Earth
Access (Safety
Port Ground) fig 0038
• The PFE bays shall accommodate dual –48VDC feeds up to 750MCM cable.
• The interface for the high voltage output and power feeding earth interface shall
accommodate 6 AWG, Type MV-105 cable. Conduit fittings and pre-drilled holes shall be
sized to accommodate #6 AWG Type MV-105 cable.
• The interface for the Dedicated Station Earth shall accommodate two (2) independent #6
AWG cables.
• The Ethernet interface shall be 10/100 Base-T Ethernet with an RJ-45 connector.
• The Remote Emergency Shutdown interface shall be via the office alarm connector.
• Test points (banana jacks) shall be provided to monitor the following at the output of the
PFE
o Voltage
o Current
o Dedicated Station Earth Current
o Power Feed Earth Voltage.
• The externally provisioned electroding interface shall be via the Test Jack port.
• The remote Alarm Cutoff (ACO) interface shall be via the office alarm connector.
5.2.1 Interlocks
The PFE shall be interlocked to prevent personnel gaining access to dangerous potentials.
The interlocks shall only allow access to potentially hazardous areas, when the equipment
is de-powered.
The PFE shall include circuits that automatically discharge to a safe level and clamp to
earth potential all high voltage circuits and capacitors when the equipment is switched off
or access obtained to hazardous areas. This shall not require any action by the operator.
The PFE shall include a facility, by which the PFE may be de-energized by any untrained
staff should a safety hazard exist. Each Power Converter shall contain a red Emergency
Stop Button mounted on the faceplate to ensure that the Emergency Shut Down is not
operated inadvertently. The facility shall be distinctively marked. Also, contact points
shall be provided for external Emergency Stop circuits.
The PFE Emergency shut down shall be also operable from a remote extension in the
Cable Station. Operation of the Emergency Shut Down shall not cause any damage to
either the PFE or the submersible plant.
The PFE shall include an adequately insulated device to enable potentially high voltage
points, in particular the power conductor feeding the submarine cable and/or charged
capacitors, to be discharged to Rack Safety Earth before handling. This shall be
permanently connected to the frame Rack Safety Earth such that it cannot be accidentally
disconnected during use. The PFE shall have the capability to allow visual inspection to
verify the integrity of this ground connection prior to its use. It shall be possible to test
the integrity of the earthing device before each use using external testing equipment. It
shall be possible to use the earthing device at all points of the PFE.
This earthing device is not intended to discharge the undersea cable capacitance, only
residual internal PFE charges.
Plug-in units for sub-assemblies taken out of service for maintenance purposes shall be
safe for handling and testing by station staff.
IT SHALL NOT BE POSSIBLE TO CARRY OUT ANY PFE OPERATIONS FROM
ANY REMOTE FACILITY, OR LOCATION NOT VISIBLE FROM THE PFE WHILE
PERSONNEL HAVE ACCESS TO THE PFE.
The PFE design shall ensure that, for every possible PFE configuration and taking into
account earth potential differences, the PFE shall be fully protected in the following
events:
• Cable fault anywhere in the System
• Lightning strike or any other natural phenomena (e.g., magnetic storms) at or close
to any cable station
• Voltage out-of-limits between Power Feeding Earth and Dedicated Station Earth.
This shall remain true even while the PFE is feeding any value up to its maximum
output including earth potential differences of up to 1500V between the terminal
stations.
5.3.2 Surge
The design shall ensure that no current or voltage is applied to the cable system at any
time sufficient to cause damage to the cable, either during normal operating conditions or
under fault conditions arising from faults external or internal to the PFE.
The design shall ensure that the PFE is protected in the event of a lightning strike at or
adjacent to the cable station or any power surge which may result from a cable fault
anywhere on the system when the PFE is feeding its maximum rated output. It should be
noted that current surges on the cable can reach 200A.
The output voltage from the PFE shall be inherently restricted to a maximum value of
12kV. The limiting action shall not rely on alarm devices.
Current control device(s) shall be capable of adjusting the current from zero to +120% of
the nominal line current.
5.3.5 Powering up
The design shall incorporate a closely controlled powering up sequence for energizing the
submersible plant.
POWER-UP SEQUENCE CAN ONLY BE INITIATED LOCALLY. NO PROVISION
FOR REMOTE INITIATION OF THE POWER-UP SEQUENCE MAY BE PROVIDED.
The method employed for de-energizing the PFE shall not cause power surges sufficient
to damage the Cable.
+
TL
V/I
MONITOR
PWB
CONVERTER 2
V/I
MONITOR
PWB
CONVERTER 3
CONVERTER 4
_
TL
PTL1
K1
K2
PTL2
The Power Converter shall incorporate a built-in ramp-to-zero facility. The Power Converter shall
relinquish ramp control to the LCU when the LCU is properly connected and functioning. The
LCU shall be capable of receiving remote ramp-up/ramp-down rates via the 10/100 Base-T
Ethernet interface. Power Converters shall include a recessed ramp-down button. This button will
allow the converter to ramp down to zero output when the converter is operating in autonomous
mode.
The Power Converter polarity shall be displayed on the OMU front panel. The Power Converter
shall have indicators displaying whether its output is connected to the Cable (In Service) or to the
Test Load (Out of Service).
The Power Converter shall NOT be capable of ramping up without an LCU. However, an
operating Power Converter shall continue operating autonomously if the LCU fails.
The Power Converter shall have hot-swap capability and provide audible alarm notification
Office alarms originate from the Power Converters and are not routed through the LCU.
Audible alarms shall be fitted with both remote and local Alarm Cut-Off (ACO) capability. If a
new alarm condition occurs when the ACO is active, the audible alarm shall be re-instated.
The LCU shall include ramp-up/ramp-down capability to control the voltage ramp rate up to a
maximum of 1,000V per minute (note that earth potential can vary by as much as 10V per
second).
In the event of a LCU failure, the Power Converters shall continue to operate autonomously. A
failed LCU shall produce an alarm condition.
ALL PERSONNEL SAFETY PARAMETERS MUST BE MAINTAINED DURING
AUTONOMOUS OPERATION.
NORMAL:
• PFE connected to Cable
• Test Load disconnected
ISOLATED:
• PFE disconnected from Cable
• PFE connected to Test Load
• Cable shorted
OPEN CIRCUIT:
• PFE disconnected from Cable
• PFE connected to Test Load
• Cable open circuit.
It shall be possible to connect some of the Power Converters to the Cable, and the
remaining Power Converter to the Test Load simultaneously.
The supplier shall provide appropriate procedures.
The OMU module shall include the following features:
• monitoring access points
• cable access port.
The OMU shall provide safe access to the physical cable head without the need to
dismantle the equipment. Cable access port connectors which meet the safety
requirements of this specification shall be provided. This is provided by the Test Jack
feature
The maximum current drain at any input voltage (0 to -60VDC) lasting for longer than 1 second
shall not exceed 1.5 times the current drain at nominal working voltage of -48VDC per ETS 300
132-2. For shorter times, larger in-rush currents are allowed. Refer to ETS 300 132-2 for short-
duration in-rush current values.
Forms part of the circuit for powering the submersible plant. The PFE shall be capable of
switching, by means of a manually-controlled, rotating switch, between Power Feeding
Earth and the Dedicated Station Earth detailed below to enable maintenance of the Power
Feeding Earth system. The switching sequence shall ensure that the connection to the
Dedicated Station Earth is made before the connection to the Power Feeding Earth is
broken. The operation of this switch shall not affect the PFE output. The PFE shall be
capable of working with earth potentials of up to 200V with reference to Power Feeding
Earth System. Protection and or switching devices shall be provided to ensure that the
voltage between the Power Feeding Earth System and Dedicated Station Earth does not
rise above 200V.
The Dedicated Station Earth is for safety use, auxiliary supplies and signaling earth. For
redundancy, this shall be provided by two (2) independent cables connected directly to
the station earth system, referred to as BG1 And BG2. The PFE shall provide for the
independent monitoring of these cables.
All racking and external metalwork shall be capable of being connected to the general
station earth. This is provided by a dedicated cable connected directly to the station earth
system.
The PFE shall limit the voltage difference between the Power Feeding Earth (Ocean
Ground) and the station earth and the rack earth to safe levels (less than 200V). An alarm
shall be provided to monitor this voltage difference.
The threshold voltage difference (between Power Feeding Earth and Dedicated Station
Earth) for automatic shunting of Power Feeding Earth to Dedicated Station Earth shall be
200V.
Whenever Power Feeding Earth and Dedicated Station Earth are connected together
(either automatically or manually) latched audible and visual alarms shall be activated.
6.12.1 Requirements
Output current stability under a constant load shall be better than 0.1% over any 24 hour
period in the temperature range of 5 to 40°C and over the range of 40°C to 50°C for not
more than 24 hours.
Output current ripple shall be less than 10mA peak-to-peak at any output current.
Output voltage ripple shall be less than 0.2% peak-to-peak of any output voltage.
6.12.2 Regulation
The PFE shall be designed such that a current surge caused by a short circuit applied to
the output of the PFE while feeding its maximum design voltage is not sufficient to
damage the Cable.
The supplier shall define the response of the PFE to the application of a short circuit
applied to the output while feeding its maximum design voltage. This response shall
include the maximum current, surge duration and shutdown characteristics if applicable.
The output voltage of the PFE shall automatically adjust to maintain the normal line
current in the presence of naturally induced voltages.
The PFE shall not generate or pass on to the Cable any appreciable AC energy other
than the allowable ripple present at the fundamental switching frequency.
The PFE shall be capable of powering into a resistive, capacitive, or inductive load. As
such, it requires a controlled ramp-up/ramp-down capability.
6.13.1 Alarms
Alarms shall be provided in accordance with the requirements below. Alarms shall be
generated to enable fault finding and easy maintenance in the event of a PFE or Cable
fault.
Tripping alarms shall be provided which will shut the PFE down to prevent risk to
personnel and any hazardous conditions being applied to the System. The trip alarm
threshold shall be higher than the audible alarm threshold and shall be realized in
hardware at the appropriate locations in the PFE. The sequencing of trips and alarms shall
be such as to minimize the risk of unnecessary shut down while ensuring full protection
of personnel and equipment.
Alarm limits shall be adjustable around the voltage and current operating setpoints.
Alarm severity shall be configurable via the LCU.
Alarms shall be raised for:
• High Voltage. This is an indication that the output is above that normal operating setting
but below that which would constitute a risk to the system or performance.
• Low Voltage. This is an indication that the output is below that normal operating setting
but above that which would constitute a risk to the system or performance.
• Very High Voltage. This is an indication that the output is above that normal operating
setting and which would constitute a risk to the system. This alarm shall cause an
immediate shut down of the equipment.
• High Current. This is an indication that the output is above that normal operating
setting but that which would constitute a risk to the system or performance.
• Low Current. This is an indication that the output is below that normal operating
setting but above that which would constitute a risk to the system or performance.
• Very High Current. This is an indication that the output is above that normal
operating setting and which would constitute a risk to the system. This alarm shall
cause an immediate shut down of the equipment.
• Battery Voltage Out of Limits. This is an indication that the primary supply voltage
is such that correct operation of the PFE cannot be guaranteed. This alarm shall cause
an immediate shut down of the equipment.
• Very Low Current. This is an indication that the system is open circuit or that the
current has fallen to a level that could damage the system. This alarm shall be
programmable to levels as low as zero amperes (i.e., disabled) and shall initiate a
shutdown of the equipment.
• Power Feeding Earth Fail. This is an indication that the primary return earth system
has failed. Under these conditions power feeding current should automatically be
routed to the Dedicated Station Earth.
• Shut down This is an indication that the PFE has been shutdown either automatically
by generation of another failure, manually or via emergency shutdown
All PFE alarms, performance information and status shall be passed to the Maintenance
Controller via the LCU 10/100 Base-T Ethernet interface. The PFE shall date and time
stamp all alarm and performance reports. The timestamps shall be accurate to 15 seconds
per year and conform to the Coordinated Universal Time (UTC) standard. The accuracy
of the timestamp will be maintained by synchronizing with the network clock via
Maintenance Controller.
Re-setting of Alarms
All major alarms (shutdown) shall remain active until reset by the operating personnel.
PFE shall provide the ability to temporarily disable alarm extensions for testing purposes.
Disabling the alarm extension shall raise an alarm.
The above values shall be reported to the Maintenance Controller via the LCU 10/100
Base-T Ethernet every 5 seconds. Provisions shall be made to accommodate queries from
the maintenance controller for supporting data regarding alarms and status.
Meters
The PFE shall incorporate metering devices to indicate voltages, currents and other
relevant parameters at principal points in the PFE, to include the output of each Power
Data Logging
The PFE shall be able to capture data at a minimum frequency of 10ms or 100 samples
per second. The device shall have the storage capacity to record data for 7 days minimum.
The device shall communicate to both the PFE central maintenance processor and the
EMS via Ethernet connectivity. The device shall use a java type web browser for easy
recording configuration and channel setup and shall be integrated into the central
maintenance processor tasking architecture.
The following data points shall be available for logging:
• PFE Output Voltage
• PFE Output Current
• Station Ground Current
• Ocean Ground Voltage
Equipment Faults
PFE fault location shall result in an unambiguous identification of a single field-
replaceable module. Fault location shall utilize the Alarm indications, monitor points, test
points and displays to identify the unit to be changed.
A fault location tree shall be provided.
The entire PFE, including the Test Load, LCU, Power Converters, Patch Panel, PFE
Monitor, and OMU shall be contained in a single ETSI compliant bay 2200mm H x
600mm W x 600mm D.
The weight of a fully populated PFE shall not exceed 1300kg (~2860 lbs.) consistent with
the distributed floor loading requirements (560 kg/m2) of GR-63-CORE.
The weight of any single PFE element shall adhere to the guidelines below per GR-63-
CORE. If any single element exceeds 25kg labeling indicating safe carrying methods
shall be prominently displayed.
• 10 to 25 kg (22 – 55.1 lb) One person carrying
• 25 to <50 kg (55.1 -110.2 lb) Two Person carrying
• 50 to <100 kg (110.2 – 220.5 lb) Two person carrying w/ Mechanical Assistance.
Mounting means shall include provision for electrical isolation of the bay from the
building and overhead racking. For this purpose the cabinet shall be equipped with 5/8”-
The floor mounting shall be compatible with the Hendry 08022K01 seismic anchor kit
and the Hendry 08021-V66 or 08024-V12 isolation pad or equivalent.
The PFE shall include measurement and maintenance test points to carry out installation
and maintenance tests. The PFE shall be designed with the minimum number of types of
electrical test connectors.
Test points and jacks shall be accessed on the equipment front face where practical. The
connection of any impedance including short circuit to a test or monitor point shall not
affect the PFE performance.
Any plug-in units or sub-assemblies which perform the same functions shall be identical
and interchangeable physically and electrically, excluding any initial configuration
adjustments. The design of the PFE shall be such that modules plugged into an incorrect
location shall not cause electrical or mechanical damage to any part of the equipment and
shall not pose a safety hazard.
The function of each plug-in unit shall be apparent from its designation and from its
relative location. The direction of the power paths between plug-in units and between
shelves shall form a horizontal and vertical progression where practical.
Racks, shelves and cards shall show their relative designations. Adequate designations
shall be printed at each test, alarm and control point, etc. Designations of jacks, meters,
test points, etc. printed on the equipment shall be in English.
The PFE design shall reflect good ergonomic design principles. In particular the function
of controls, supervisory indicators and test points shall be readily apparent from its
location, designation or coloring, or a combination thereof. Controls or connectors, which
represent a safety hazard to personnel or to the System, shall be so identified, and
protected as necessary. The variety of controls and connectors to be used shall be as a
minimum consistent with the above requirements. Regularly used operational controls,
supervisory indicators and test points shall be mounted at convenient working height.
Frequently used controls may be left exposed.
The PFE shall be painted beige in color. The surface finish shall be durable for the life of
the PFE.
Any power converter used within the PFE shall operate at ultrasonic frequencies. No
discomfort shall be caused to station personnel due to acoustic or vibration effects of
noise generated by the equipment. The PFE shall comply with ETSI requirements of ETS
300 753.
Acoustic noise requirements for the Test Load should meet ETS 300 753 on a best effort
basis.
General
The reference ambient temperature shall be measured at a height of 1.5 meters above the
floor and 0.4 meters from the face of the rack.
The maximum long-term aisle operating temperature shall be 40°C. The maximum short-
term aisle operating temperature shall be 50°C for a period of 24 hours per GR-63-CORE.
6.14.9 Cooling
Forced air cooling fans may be used in this PFE. The fans and filters shall be replaceable
without interrupting the PFE output. A single fan failure shall not cause a PFE shutdown,
failure or degradation in PFE output. The fans shall be alarmed such that the failure of a
single fan triggers an alarm.
All forced air cooling shall flow from front to back, and shall cause a positive pressure
within each shelf. Cooling air shall enter the shelf from the front only, and shall exit from
the front, back, or top of the shelf. Ventilation shall not be through the sides of the shelf.
The design of the exhaust shall not constitute a safety hazard to personnel.
If an overheating condition occurs, a two-stage alarm shall first issue a warning alarm
and then, if the overheating condition worsens, shall cause the equipment to
automatically shut down to protect itself from permanent damage. In the event of an
over-temperature shutdown condition, all outputs shall be ramped down to zero volts and
latched OFF until an operator intervenes.
The fans shall operate and meet all requirements when either of the redundant power
inputs has been removed.
All fans shall be powered by -48VDC (nominal) and shall operate over the range of -40.5
to -57.0VDC. No equipment damage shall occur if less than -40.5VDC is applied, or if
greater than -57.0VDC is applied, up to a maximum of 60.0VDC. If necessary, lower
voltage DC fans (12VDC or 24VDC) may be used, provided their power input is properly
regulated. Fans shall operate reliably and be capable of a cold start over the entire voltage
range.
The PFE shall be designed to minimize the effect of dust on its operation. Unless the
ingress of dust can be entirely prevented all high voltage parts shall be suitably protected.
6.14.11 Ionization
The corona test shall be made at a DC voltage of 9.0 kV. The corona test reference shall
be 15 pico-coulombs and 20 discharges or more exceeding this level in 90 seconds in one
successive 90 second interval shall be considered a failure. The relative humidity
requirement for the test is 30% to 40%.
The equipment once installed shall meet the following EMC/ESD standards and
requirements:
The PFE shall withstand perturbation from ESD and provide a connection point for an
ESD wrist strap.
IEC 61000-4-2 (formerly 1000 PT 4-2) Issue 1.2 - 2001 - Electrostatic Discharge:
• Test level 2: Test result 1 (normal performance).
• Test level 3: Test result 2 (reduced performance).
• Test level 4: Test result 3 (loss of functionality, e.g., customer reset).
Radiated Susceptibility
• IEC 61000-4-3 (formerly 1000 PT 4-3) Issue 1.2 - 2001 - Radiated Immunity, level 3
(normal performance)
• The immunity to the radiated electric fields shall comply with carrier frequency at
900MHz, 1300 MHz and 1800 MHz).
Conducted Emissions
• IEC CISPR 22 Issue 3 - 1997 - Class A Radiated & Conducted Emissions from
Information Technology Equipment.
Radiated Emissions
• IEC CISPR 22 issue 3 - 1997 - Class A Radiated & Conducted Emissions from
Information Technology Equipment
Electric Field
The electric field shall be measured in the range of:
• - 1000 MHz according to IEC CISPR 22 Class A, E < 47db (µv/m)
• 1000 - 2000 MHz, < 47db (µv/m) and measuring method as IEC CISPR 22.
Magnetic Field
• The magnetic field shall be measured in the range 10 kHz - 30 MHz, at 1 meter of the
equipment. The requirements are given in Table 4 below for three type of equipment:
• Static power feeding equipment (> 5 kVA)
• Video Display Terminals (with CRT)
• Other equipment.
Particular precautions shall be taken to physically secure all components used in the
equipment to prevent them vibrating free. A fully populated PFE bay shall be capable of
The use of flammable materials shall be minimized. The product design shall be such that
the PFE cabinet meets the requirements of a fire enclosure per EN 60950.
6.15.1 Redundancy
The PFE shall contain redundant voltage sharing Power Converters and be capable of
series operation with a PFE of opposite polarity at the far end of the Cable system. In the
event of a Power Converter failure the redundant converters shall automatically adjust the
output to assume the full station voltage within 50ms, without affecting the total PFE
output. In the event of an entire PFE failure for a DEF configuration, the far end PFE
shall automatically adjust its output to assume the full system voltage.
The design life of this equipment shall be a minimum of 15 years. However, a 25 year
design life is highly desirable and should be the initial design goal unless a significant
cost penalty would result.
The Mean-Time -To-Repair (MTTR) for any PFE repair shall not exceed 4 hours.
The PFE shall have a service-affecting failure rate of <500 FITs. In order to meet this
objective, it is expected that the PFE supplier will have Power Converter redundancy and
will have an LCU whose failure will not disturb the operation or setting of the PFE at the
time the LCU fails.
The supplier shall recommend the required level of sparing based upon the quantity and
reliability of each unit along with the repair times.
All of the less reliable components in the high voltage output power circuit, e.g., meters,
shall be provided with parallel current paths.