The above screen shows the mandatory field required to create material which is
shown in Arrow Marks.
Basic Data 2 screen
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
MRP 1/2/3 views as shown in below screen shot. The arrow marks shows the
mandatory fields. If materials is under planning these MRP views are mandatory
for creating Material in SAP MM.
MRP View 1
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
MRP View 2
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
MRP View 3
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
SAP System will ask for saving the date for creating Material Finished Product
say ‘YES’
And save the document
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
Vendor is mandatory for creating Purchase order in SAP MM. One who supplies
the materials/goods to the company is called vendor. The below screen shots
flow shows how to create vendor.
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
Select the required order of currency for India it is INR in the mark as shown in
screen shot.
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
After this screen entry you can able to create vendor with some number range
Create Info Record – T-Code ME11 with the combination vendor and
Material
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
In this post, I will explain about the basic of the purchasing/procurement process,
which usually known as Procurement Cycle as the following steps.
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
1. Determination of Requirements
In this step, there is a requirement of material or service, which must be
procured externally, from the user. The requirement must be recorded as
Purchase Requisition (PR) document in SAPMM.
Purchase Requisition (PR) is an internal purchasing document in
SAP ERP that is used to give notification to responsible department about
the requirement of material/service and to keep track of such requirement.
PR must contain clear information about the description and quantity of
the material/service, the required date, and other information.
PR can be created directly in SAP MM module with ME51N t-code, or
indirectly by another SAP component, such as: materials planning,
maintenance order of PM module, production order of PP module, network
activity of PS module, etc. We have explained this in the previous article
about MM integration with other modules.
2. We can set in SAP that the PR must be approved or released before it can
be passed to the next step of purchasing processes. We have explained
about the PR Release Strategy in the previous article.
3. Determination of the source of supply
After the PR has been created (and released if needed) in the previous
step, the responsible department (usually purchasing/procurement
department of the company) must process it. The buyer of the
procurement department must determine the possible sources of supply of
the material/service specified in the PR.
With ME57 t-code, the buyer can check in the SAP whether the
material/service needed can be obtained from the existing outline
agreement (contract or scheduling agreement) documents or not. If there
is no existing outline agreement, the buyer can also check whether there
is an existing info record documents (which contain information about the
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
If in the previous step, there are some outline agreements or info record
documents that can be used as references to create a PO, the buyer can
select or choose which vendor that will be appointed to provide the
material/service at this time.
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
SAP ERP can also create rejection letters to the vendors that are not
selected as the supplier of the material/service.
5. PO Processing
In the previous step, the buyer has selected the vendor which will provide
the material/service needed in PR. In this step, the buyer creates a
Purchase Order (PO) based on the PR and the reference document
(that can be an outline agreement, an info record, or a quotation).
Purchase Order (PO) is a legally binding document that issued by a
company to a vendor which contains information about description,
quantity, delivery date, agreed prices, terms of delivery, and terms of
payment for material or service the vendor will provide to the company.
6. POMonitoring
After the PO has been sent to the vendor, the buyer has the responsibility
to monitor whether the vendor delivers the material/service at the right
time on the right place. The buyer can monitor whether the
material/service has been received by the person responsible (such as the
warehouse man) online with PO history function in the PO document. If
the warehouse man or anyone else has received the material/service and
posted the Goods Receipt/Service acceptance document, the PO history
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore
7. GoodsReceipt
When the vendor delivers the material or perform the service, the
responsible person of the company must perform the goods receipt
(GR) or service acceptance (SA) transaction. The GR/SA will update
the PO history. If the PO item is an inventory material, the GR will
increase the stock level of the material.
When we perform the GR for the PO item for the first time, SAP will
propose the quantity to be GR as the PO order quantity. Depends on the
delivery terms agreed with the vendor, the vendor might deliver the
material partially. We can post the GR partially too, so when the next
material delivery is received, SAP will propose the quantity to be GR as
the remaining quantity that has not been GR yet.
8. InvoiceVerification
After the vendor delivered the material/service; it will send the invoice to
the person responsible in the company.
Invoice is a formal document issued by a vendor to the company to
request the payment for the material or service that the vendor has
already provide to the company according to the terms of payment agreed
in the PO. An invoice is usually attached with the delivery note (goods
receipt) document.
The person responsible, usually an accounting staff, will perform the three
way matches. He will check whether the invoice information (such as
price, terms of payment, etc) is the same with the PO, and whether the PO
item has been received (GR/SA). If yes, then he will post the Invoice
By SAP MM Consultant
GANESH, Collabera Software Pvt Ltd, Bangalore