Graded Exam: Total Score: 81%
Graded Exam: Total Score: 81%
Graded Exam
Total score: 81%
Initiating process 73%
Planning process 78%
Executing process 78%
Monitoring & Controlling process 86%
Closing process 100%
Question number: 1
Who is responsible for approving the Project Management Plan?
You answered: C.
D Sponsor only
Question number: 2
You are analyzing quality results looking for a relationship between defects and their causes. Which of the following is the appropriate tool you
should use?
You answered: B.
A Tornado diagram
B Ishikawa diagram
C Control chart
D Histogram
Question number: 3
What is the purpose of a RACI matrix?
You answered: A.
Question number: 4
Your change control board (CCB) has just approved a change request. What is the next thing you should do?
You answered: C.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 2 of 52
Question number: 5
Your company has won a contract to oversee the expansion of a major highway in your area. The project had been discussed for several years,
and due to constant changes in the political climate, the controversial project was hard to get off the ground. The project has drawn criticism from
nearby residential landowners, environmental groups, and taxpayers who deem it too expensive. Moreover, some environmental studies suggest
that the subsurface in some areas may be inadequate to sustain the road, which may result in expensive detours being built around those spots.
You are working on your Risk Management Plan. What is the best way to proceed?
You answered: C.
A Set aside reserves to cover the costs of these risks and others that have been identified
B Conduct a feasibility study to determine whether the project should go forward under these circumstances
C Document each category of risk in the Risk Management Plan to help ensure all risks are properly identified
D Ask the Sponsor to assign an independent project team to assess and handle project risk
Question number: 6
Which of the following does not contain any information about the project requirements or the characteristics of the product?
You answered: D.
A Requirements documentation
B Project charter
Question number: 7
Which of the following is not a result of performing stakeholder analysis?
You answered: A.
Question number: 8
A key stakeholder comes to you with what you believe to be a major change to the project. You only have 1-week of buffer in your plan and your
project absolutely cannot be late. What should you do?
You answered: D.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 3 of 52
A Inform the stakeholder that due to the tight schedule you cannot make the change
B Issue a change request immediately and let the change control board decide
C Begin working on the change, because this is a key stakeholder and you should keep her happy
Question number: 9
As time passes in a project, which of the following does not happen?
You answered: B.
B Risk increases
Question number: 10
You are the project manager for a highway construction project. Your sponsor has asked for an updated project forecast. The project has spent
$100,000 of the total budget of $400,000 and has a CPI of .85. How much more money will you spend on your project?
You answered: B.
A $470,588
B $370,588
C $240,000
D $340,0000
Question number: 11
Which of the following best describes the purpose of the WBS?
You answered: C.
Question number: 12
Which of the following BEST defines high quality?
You answered: D.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 4 of 52
Question number: 13
Which of the following would NOT be included in the Communication Management Plan?
You answered: A.
Question number: 14
Which of the following best describes the purpose of integrated change control on a project?
You answered: C.
Question number: 15
In which of the following processes would it be most helpful for you as a project manager to employ information gathering techniques?
You answered: C.
Question number: 16
You are Performing Quality Control on a project. Which of the following would you NOT use in this process?
You answered: A.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 5 of 52
A Quality audits
B Inspection
D Pareto chart
Question number: 17
You are a project manager overseeing the construction of a new shopping mall. Your team had compiled and reviewed zoning and building
regulations to help ensure that your project would not be interrupted by any regulatory bodies, however, the information reviewed was out of date.
As it turns out, you have unknowingly exceeded the new maximum height restrictions for structures in that area. You must now seek a variance
from the local government authorities, and if it is refused, your project could be shut down. Which of the following could have helped avoid this
situation?
You answered: B.
Question number: 18
Two of your team members are arguing over a technical issue on your project. You suggest that they put their differences aside and offer to take
them both to lunch. Which conflict resolution technique did you use?
You answered: D.
A Withdrawal
B Compromise
C Collaborate/Problem Solve
D Smoothing
Question number: 19
You are working as a project manager for an advertising project. Your inputs include deliverables, work performance information, checklists, and
approved change requests. What PMBOK process are you working on?
You answered: A.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 6 of 52
Question number: 20
You just delivered a product to your customer when you receive an email informing you that the end result is unacceptable. The customer says
that a crucial component is missing, but you know that component was not in the original plan. Also, the product passed all quality tests. How
should you respond?
You answered: C.
A Repair the product to include the missing component at no charge to the customer, because the customer is always right.
B Perform the work and bill the customer for the added cost.
C Meet with the customer to document the missing component, and then issue a change request to complete the required
work.
D Inform the customer that since the product passed all quality tests and passed scope verification, it is complete.
Question number: 21
You are managing a project and a team member comes across a major risk. Based on the team member's assessment the risk has a fairly high
probability and impact of occurring. What should you do first?
You answered: D.
Question number: 22
You are working on a project for a non-profit organization and are putting together the schedule. You recall that you worked on a similar project
last year and decide to use the same activity list as a starting point and just make slight changes. What scheduling tool and technique are you
using?
You answered: A.
A Analogous estimating
B Decomposition
C Templates
Question number: 23
Which of the following best describes the primary purpose of the project charter?
You answered: B.
D It describes the business case and reason for doing the project
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 7 of 52
Question number: 24
You are the project manager for an accounting project. You have requested 2 senior-level auditors to assist you on your project, but the
accounting director assigns 2 very junior team members that lack the necessary skills to complete the work. How should you respond?
You answered: D.
A Go to the accounting director's manager and ask for the senior resources you need.
D Call a meeting with the accounting director, so that you can explain more clearly the need for senior resources on your
project.
Question number: 25
You are working on a fixed price contract and have spent $120,000 so far out of a budget of $120,000. You estimate there is still another $20,000
of work to complete the project. Because you are under contract, your company will have to pay all remaining costs to complete the project.
Which of the following best describes this situation?
You answered: B.
Question number: 26
You are submitting a status report to your external customer. Which form of communication should you use?
You answered: B.
A Formal verbal
B Formal written
C Informal verbal
D Informal written
Question number: 27
You are the project manager overseeing the construction of a new aircraft carrier. The construction involves fitting various components together
at the shipyard, and it must be done in a particular order. Unfortunately, certain components have been assembled at the shipyard, but your
project team cannot install them because other necessary tasks have not yet been completed, and because you currently lack the resources
needed to install them. The components cannot be kept at the shipyard, and thus, you will incur substantial costs for moving and storing them
until they can be installed. You want to ensure that this doesn't occur again on this project, so you should carefully review which of the following?
You answered: C.
A Requirements Documentation
B Resource Documentation
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 8 of 52
Question number: 28
You are managing a datacenter infrastructure project. You have spent $250,000 out of a total budget of $600,000. You have completed 30% of
the work thus far, but according to the schedule you should have completed 40% of the work. All work items carry the same value. Which of the
following best describes the situation?
You answered: A.
Question number: 29
You are managing a complex project to overhaul a water treatment plant. You are trying to report key information to the stakeholders, but are
having trouble compiling all of the relevant data. You have multiple budget reports in various formats, some of which are out of date, and they are
housed in various locations. The work performance information is similarly scattered amongst various documents, and is difficult to interpret.
Which of the following would best assist you in communicating the key information to the stakeholders?
You answered: A.
A Performance Reporting
B Communications Technology
D Issue Log
Question number: 30
You are managing a project and one of your vendors submits a deliverable that you feel is incomplete. He disagrees and insists that his work is
done and refuses to do any further work on it. How should you handle this situation?
You answered: D.
C File a lawsuit to force the vendor to complete the work or pay you damages
Question number: 31
Your team is reviewing the entire procurement process to look for successes and failures. What are you doing?
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 9 of 52
You answered: B.
C Inspection
D Decomposition
Question number: 32
Which of the following contracts has the most risk to the Seller?
You answered: A.
Question number: 33
You are managing a project to develop a new mobile phone. Even though it is not in the requirements, you decide to add a feature allowing the
phone to be used in any country without changing the SIM card. What is this feature called?
You answered: B.
A Scope creep
B Gold plating
C Prototypes
D Alternatives identification
Question number: 34
You are in the process of installing a new heating and air system in your office building when you realize that because of the way the exhaust fan
is situated, winds of over 30 MPH will cause the AC unit to not vent or work properly. You decide to not change anything and continue as
planned. What strategy did you choose?
You answered: B.
A Exploit
B Accept
C Transfer
D Mitigate
Question number: 35
You have several very low impact and probability risks on your project. Which term best describes these?
You answered: C.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 10 of 52
A Reserves
B Residual risks
C Threats
D Watchlist
Question number: 36
All of the following are characteristics of the project management plan except which one?
You answered: C.
A Gantt chart
D Progressive elaboration
Question number: 37
Which of the following best describes the Validate Scope process?
You answered: B.
C It involves breaking down the project work into smaller, more manageable components.
Question number: 38
Parametric estimating is best described as which of the following?
You answered: C.
B Using a previous project to calculate the cost or duration, making adjustments for known differences
C Using a statistical relationship to a past project (such as cost per unit) to calculate the cost or duration
D Breaking an activity down into smaller components that are easier to estimate, then aggregating the costs or durations
Question number: 39
You are managing a project that will produce the next new supercomputer. As each new unit is produced your team is taking measurements and
recording them in a control chart. Which of the following results should you be least concerned with?
You answered: D.
B Seven consecutive data points above the mean, but within the control limits
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 11 of 52
D Several data points falling well above and below the mean, but within the control limits
Question number: 40
You are managing the construction of a new underwater pipeline, and you must hire pipe-fitters to perform large pieces of work. You have
received responses from various companies to your procurement documents, which you are analyzing. You are interested in one company in
particular, because it offered a price which was lower than most. You are unfamiliar with this company, so you obtain from it a list of references
and follow up with them. They all have excellent things to say about this company, and so you award it the contract. Which of the following best
describes your contact with the references?
You answered: C.
B Independent Estimates
D Procurement Negotiations
Question number: 41
All of the following are included in the staffing management plan except which one?
You answered: C.
Question number: 42
When should you identify the stakeholders?
You answered: C.
Question number: 43
You are managing a highway construction project and you are trying to determine if the project is ahead of or behind schedule. Which of the
following would be most helpful?
You answered: B.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 12 of 52
D Reserve analysis
Question number: 44
You are managing a database design project and just realized that there is a major flaw in your design. Your team determines that fixing the
design flaw will result in two additional weeks of work, but not fixing it would result in a major security vulnerability that is unacceptable to the
customer. What should you do next?
You answered: C.
Question number: 45
Government regulations that will limit your options as a project team are best described as?
You skipped this question. You marked this question for review.
A Bureaucracies
B Constraints
C Workarounds
D Assumptions
Question number: 46
Your project has the following schedule network paths: A-D-F-H, B-D-F-H, C-E-F-H, and C-E-G-H. Tasks have the following durations: A=10,
B=8, C=6, D=4, E=12, F=6, G=3, H=4. What is the critical path?
You answered: D.
A 22
B 24
C 25
D 28
Question number: 47
In which of the following team-building stages does the team begin to work together and build good working relationships?
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 13 of 52
You answered: D.
A Storming
B Performing
C Forming
D Norming
Question number: 48
You are managing a project which is wrapping up. One of your team members, Michael, comes to you to voice some frustrations about his role in
the project. He feels that his role was never clearly established, and that he was never provided with any concrete goals, expectations or
feedback. If this is true, you may have done a poor job with which of the following?
You answered: B.
C Team-Building Activities
D Communication Methods
Question number: 49
You are managing a large software project for a bank and are about 50% done with the work when a new stakeholder is identified. It turns out the
stakeholder will be highly impacted by the new software project. You have a tight deadline and the requirements are already firmly set. What
should you do?
You answered: C.
Question number: 50
Which of the following is not part of the project closure process?
You answered: B.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 14 of 52
Question number: 51
What is included in the scope baseline?
You answered: C.
C Scope management plan, project scope statement, WBS, and WBS dictionary
Question number: 52
What is the range of a rough order of magnitude (ROM)?
You answered: A.
A +/- 10%
B +/- 25%
C - 25%/+ 75%
D +/- 100%
Question number: 53
Formal approval has been provided for your project, and you are asking around to see who else you might be impacted by your project. What
process group are you performing?
You answered: B.
A Initiating
B Planning
C Executing
Question number: 54
A major problem with this type of organizational structure is that when the project is finished the team is terminated. What type of organization
structure does this refer to?
You answered: C.
A Balanced Matrix
B Projectized
C Functional
D Weak Matrix
Question number: 55
An important aspect of success criteria is that it should be quantifiable. Which of the following is an example of quantifiable success criteria?
You answered: D.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 15 of 52
Question number: 56
Pareto charts help the project manager to
You answered: B.
Question number: 57
Which of the following best defines high quality?
You answered: C.
Question number: 58
You are managing a project to create a nativity scene for a grade school Christmas play. You are told that one of the requirements is that you
must deliver the nativity scene by December 15 – the date the Christmas play will take place. Where would you document the December 15
deadline?
You answered: C.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 16 of 52
Question number: 59
McClelland's Theory of Needs states that people fit into categories and are motivated by three types of needs. Managers should determine which
of the 3 categories an employee fits into and manage them accordingly. Which of the following is not one of McClelland's 3 needs?
You answered: A.
A Money
B Power
C Affiliation
D Achievement
Question number: 60
You are working as a project manager and are currently looking at a chart that shows you the type and number of resources that you need over a
period of time. Your goal is to smooth out your resources so you can avoid the peaks and valleys. What type of chart are you looking at?
You answered: B.
A Run chart
B Resource histogram
C Resource calendar
Question number: 61
You are working on a large construction project as a project manager and have just found an opportunity to save a lot of money on your project.
Which of the following is an example of exploiting the opportunity?
You answered: B.
B By changing your project approach to ensure that you achieve the full benefits of the opportunity
C Hiring workers in another country to work long hours in poor conditions for very low pay
Question number: 62
Who theorized that quality was a management issue 85% of the time and by the time things got down to the line employee it was too late?
You answered: B.
A Kaizen
B Deming
C Pareto
D Crosby
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 17 of 52
Question number: 63
When working as a project manager there are many things around you that can impact the project’s ability to be successful, including the
corporate culture, infrastructure, marketplace conditions, the number and type of resources available, workplace attitudes, etc. These are referred
to as?
You answered: B.
C Lesson learned
D Constraints
Question number: 64
You are a project manager producing several identical components for an aerospace project. You are supposed to be producing 2 units per
month worth $250,000 per unit. After 3 months you have only produced an average of 1.2 units per month. You use a formula to determine what
the difference is. What is the formula you used?
You answered: C.
A SPI
B CV
C SV
D VAC
Question number: 65
Jeff is a senior engineer on your project. During a progress review meeting you come across a potentially disastrous risk to your project. Jeff tells
the team that he has a fix to avoid the risk and ensure everything goes smoothly. Everyone trusts Jeff's advice, because he has a lot of
experience handling these types of technical risks. What kind of power does Jeff have?
You answered: B.
A Formal
B Expert
C Legitimate
D Referent
Question number: 66
Which of the following types of conflict resolution is considered a win-lose?
You answered: C.
A Smoothing
B Punishment
C Forcing
D Collaborate/Problem Solve
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 18 of 52
up later. Punishment is not a conflict resolution technique; it is a form of power. Collaborate is where you problem solve the issue to find a solution that makes both
parties happy and is the best way to handle conflict.
Question number: 67
You are meeting with the quality assurance (QA) manager to discuss the results of the quality audit of your project. The QA manager informs you
that your team has been following quality procedures that are not particularly helpful, and as a result might be increasing the likelihood for
defects. The QA manager recommends revisions to the quality procedures. You feel that the team is following the quality policies that were
originally set forth, and they are doing a good job. How should you handle this situation?
You answered: C.
B Go to the functional managers of your team members and ask them to ensure the team members follow the new procedures
suggested
C You should analyze the suggested procedures, then submit a change request
Question number: 68
Your project team does not understand the fundamentals of project management. You feel this has the potential to harm your project. You decide
to put together a half-day training session to teach PMBOK basics. Which of the following best describes what you have done?
You answered: A.
B Avoid Risk
D Analyze Risk
Question number: 69
Your project was suddenly terminated after a major design flaw was found in one of the component that you delivered to the customer. What
should you do next?
You answered: A.
A Stop work, document the lessons learned, and then release the team
B Offer the customer box seat tickets to a professional sporting event and try to get him to reinstate your contract
C Keep the team working on the project to fix the problems and try to get the project reinstated
Question number: 70
You are looking at data points on a control chart in real time and notice 7 consecutive points above the mean, but within the control limits. What is
this called and what does it mean?
You answered: D.
A This is called assignable cause and it means you have identified a defect
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 19 of 52
C This is called quality assurance and it means you are doing your job
Question number: 71
You have two key stakeholders on your project that are always arguing. If one makes a suggestion, the other disagrees even if it is a good idea.
Which group creativity technique should you use?
You answered: A.
A Delphi technique
B Focus groups
C Brainstorming
Question number: 72
You have just received formal authorization to start your project. What should you do next?
You answered: D.
Question number: 73
You are managing a graphic design and print project. There is a 30% chance that the paper you are using will be too thin and you’ll have to
reprint the presentation, which will cost you an extra $5,000. There is also a 20% chance that the high capacity ink cartridges you are using will
last you longer than you expect, which will save you $1,000. What is your Estimated Monetary Value (EMV)?
You answered: C.
A $4,000
B $200
C - $1,300
D - $1,500
Question number: 74
You are managing a construction project and there is a chance of a strike at one of your subcontractors which would delay your project. Which of
the following is not a correct statement about risk response strategies?
You answered: C.
A You decide not to use that vender and do the work yourself, which would be an example of avoidance.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 20 of 52
B If the strike happens, your team will work overtime once the delivery arrives to make up for the lost time. This is an example of
mitigation.
Question number: 75
What is the main purpose of the WBS dictionary?
You answered: A.
Question number: 76
You are the project manager at a healthcare services company. Two of your team members are having an argument that has escalated into
yelling. How should you handle the conflict?
You answered: A.
A Collaborate/Problem Solve
B Avoiding
C Smoothing
D Forcing
Question number: 77
Grace is a project manager for Cosmic Systems. When Grace is out of the office she doesn't trust her employees to get work done and when she
is in the office, see is always looking over their shoulders. What type of manager is Grace?
You answered: B.
A Psychotic
B Theory X
C Theory Y
D Expectancy theory
Question number: 78
Susan has just been appointed as the project manager for a software project and realizes that no WBS has been created and the project is
entering the construction phase. What should she do?
You answered: C.
A She should report this to senior management and start work on the construction phase
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 21 of 52
B She should get details from WBS Dictionary to create the WBS
C The WBS should be created first and then construction work started
Question number: 79
You are managing a project with the following EVM metrics: AC = $24,000, EV = $30,000 and PV = $28,000. Which of the following statements is
true?
You answered: D.
Question number: 80
You are taking measurements and plotting the results on a control chart. What process are you performing?
You answered: B.
C Plan quality
Question number: 81
You are a project manager and are having a disagreement about an important design issue with another colleague. Before you can seriously
discuss the issue your colleague says: 'Forget about it. You're always right. We'll just do it your away.' What is the best way to describe how the
colleague handled this situation?
You answered: A.
A She gave up
B She deferred
C She withdrew
D She retreated
Question number: 82
Defects found late in the project are
You answered: B.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 22 of 52
A Easy to fix
B Expensive to fix
Question number: 83
You are managing the manufacture of a new line of cars. The cars must be tested in many ways, but one especially important test is the
crashworthiness test. The cars your team put through the tests performed well and met all requirements. Because you had to crash so many
cars, however, your project came in well over budget. Which of the following items did you likely fail to consider fully?
You answered: B.
A Control Charts
B Cost of Quality
C Reserve Analysis
D Quality Metrics
Question number: 84
You are using the risk register and trying to find the risk score for each identified risk. Which of the following is not a tool and technique of this
process?
You answered: B.
C Risk categorization
Question number: 85
You work for a company that develops software using agile methodologies. You decide to provide your team with a training course in agile
project management. What is this an example of?
You answered: A.
C Team-Building Activity
Question number: 86
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 23 of 52
You are managing a project that will move your 200 person office across the country. You are currently sitting in a meeting with several key
stakeholders performing document reviews, assumptions analysis, and information gathering techniques. Which process are you performing?
You answered: A.
A Identify risk
B Collect requirements
Question number: 87
You are working as a project manager on a construction project. You determine that there is a 40% risk of a flood during a critical period in the
project. If the flood occurs it will damage $40,000 worth of equipment. It will also cost an extra $10,000 to drain the water out of the construction
site. You also note that there is a 35% chance that having a small amount of rain will help the landscaping around the construction site, which will
save you $10,000 in irrigation costs. What is the EMV?
You answered: A.
A - $16,500
B - $23,500
C $40,000
D $50,000
Question number: 88
You have just completed the work on your project. All of the following must be completed before the project is closed out except which one?
You answered: B.
B Document revised risk strategies for all remaining risks to the project
Question number: 89
One of your vendors has not completed the work required on the project and you have exhausted all other options to resolve the dispute. Which
of the following is not an appropriate option?
You answered: D.
A Lawsuit
B Arbitration
C Mediation
D Procurement audit
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 24 of 52
Question number: 90
You are trying to determine how best to reward your team for a job well done. Where would you find this information?
You answered: B.
Question number: 91
You are reviewing a control chart for your project. Which of the following best describes out of control?
You answered: B.
D Seven or more data points above or below the mean but within the control limits
Question number: 92
You are working as a project manager on a construction project and you have identified a risk that you will run out of plywood because the
building has odd angles and that will result in 20% more scrap than normal. You decide to go to the supply house and buy 20% more plywood
than originally planned. Which strategy are you using?
You answered: B.
A Avoidance
B Mitigation
C Transference
D Acceptance
Question number: 93
What would a resource histogram show that a RACI matrix would not?
You answered: B.
B Time
C Activity
D Interrelationships
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 25 of 52
Question number: 94
Regarding change, the project manager's attention is best spent doing which of the following?
You answered: D.
Question number: 95
Which of the following does not require formal written communication?
You answered: C.
C Scheduling a meeting
Question number: 96
You are in the process of wrapping your project up. Which of the following should you consult to determine when and how to release the team?
You answered: B.
C RACI matrix
D Activity list
Question number: 97
You are managing a project for a pharmaceutical company to develop a new flu vaccine that could save millions of lives. Which of the following
would you use if you wanted to analyze actual versus planned results?
You answered: B.
A Status report
B Variance report
C Trend report
D Forecast report
Question number: 98
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 26 of 52
You are managing a project to build a bridge across the bay. The previous project had cost overruns because the project team underestimated
the winds and harsh weather conditions on the bay. The lessons learned from the previous project can be found in which of the following places?
You answered: A.
Question number: 99
What form of communication should a customer use to express their acceptance of the project deliverables?
You answered: B.
A Informal verbal
B Formal written
C Formal verbal
D Informal written
A Business case
C Contract
D Scope statement
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 27 of 52
A Risk manger
B Risk controller
C Risk registrar
D Risk owner
A Delegation
B Transference
C Avoidance
D Mitigation
A Because the BAC is less than the EAC, you will complete the project under budget
B Because the EAC is more than the BAC, you will complete the project over budget
A Create a Requirements Traceability Matrix to ensure that all approved business value requirements are delivered at the
end of the project
B Create a product oriented WBS and use product analysis to ensure that all of the high-level descriptions of the new product are
translated into tangible deliverables
C Develop a clearly defined Integrated Change Control process that will efficiently handle any changes if missing requirements are
discovered later on
D Use major deliverables as the first level of decomposition in your WBS and then ensure the associated work packages are clearly
defined.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 28 of 52
typically be used. While Integrated Change Control would help to handle changes found later, your objective is to reduce the chance of them being missed in the first
place. A deliverables-oriented WBS would not be the best way to track requirements.
B WBS
D Scope statement
A Call an intervention so the entire team can tell him how his behavior has impacted the team
D Set up a meeting with Bob and his wife to try to help them resolve their differences
A Complete the project and show the CMO the results when you are finished
D Stop all work on the project until you get approval from the new CMO to continue
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 29 of 52
A Risks are certain events that may be threats or opportunities to the objectives of the project.
B Risks might be opportunities to the project objectives but only risks that are threats to the project objectives need to be considered
C Risks that are perceived more as rewards to the organization than negative consequences should be accepted
A Compromise
B Forcing
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 30 of 52
C Smoothing
D Withdrawal
B WBS
C Activity list
D WBS dictionary
A Lessons learned
D Document repository
A Prevention costs
B Appraisal costs
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 31 of 52
A A-D-F
B B-D-F
C C-E-F
D C-G-F
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 32 of 52
A Mitigating
B Transferring
C Sharing
D Exploiting
A Identify Risk
A Social, Safety
B Social, Esteem
C Esteem, Social
D Esteem, Self-actualization
A Customer
B Sponsor
C Stakeholders
D Project manager
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 33 of 52
A Bidders Conference
B Advertising
C Internet Search
A $1,400
B $1,500
C $1,600
D $2,400
C Identifying risks
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 34 of 52
A The project should come in under budget and you would therefore be reimbursed for all costs, plus receive a percentage
of the cost savings as per the contract.
B The project should come in over budget and you will therefore not be reimbursed for all costs.
C The project should come in on budget and therefore you will only be reimbursed for costs, with no additional commission or penalty.
D The project should come in on budget and you would therefore be reimbursed for all costs, and receive a fixed sum as a reward
A This is part of the Manage Stakeholder Expectations process to ensure that stakeholder needs are being met
B This is part of the Direct and Manage Project Work process to ensure that stakeholder needs are being met
C This is part of the Manage Project Team process to ensure that project goals are met
D This is part of the Perform Quality Assurance process to ensure that any issues that have arisen during Perform Quality Control are
being managed
A 12
B 13
C 66
D 78
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 35 of 52
A Crashing
B Fast-tracking
C Resource leveling
A The frequency with which they are conducted should be specified in the Risk Management Plan.
B They may be conducted during routine project review meetings or via special risk audit meetings.
C The format of the audit and its objectives should be open and flexible, such that they can be adapted as the audit is in
progress.
D They examine and document the effectiveness of risk responses in dealing with identified risks and their root causes.
A Schedule a kick-off meeting to begin brainstorming with your project team to review the schedule and to understand any issues or
concerns that may immediately arise
B Ask for a copy of the Project Charter so you can review who the major stakeholders are, what the high level budget,
schedule, and requirements are and verify your authority as the project manager
C Immediately begin identifying requirements in order to get a jump on the schedule since your primary concern is ensuring that the
expectations of the project and the customer are fully met this time
D Review the Project Scope Statement to ensure you fully understand all of the requirements and criteria for success and then
schedule a meeting to begin identifying stakeholders
A Networking
B Pre-Assignment
C Virtual Teams
D Negotiation
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 36 of 52
A Procurement Documentation
C Change Requests
D Closed Procurements
A Never, since baselines are used to measure progress against the plan
D Has an upper limit and a lower limit and shows process deviations
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 37 of 52
B Verify quality
C Validate scope
A Push
B Pull
C Interactive
D Electronic
A Status report
B Risk register
C Issues log
A Sponsor
B Functional manager
C Project manager
D Customer
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 38 of 52
A Activity
B Deliverable
C Work package
D Node
A Expediter
B Full-time
C Coordinator
D Part-time
A Project manager
B Project team
C Sponsor
D Stakeholder
D The number of standard deviations away from the mean of 20% of the defects
A Ishikawa diagram
B Run chart
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 39 of 52
C Pareto chart
D Tornado diagram
A If the project is being done for an external customer, it is usually written by the customer
B If the project is internal, it is written by the project manager after receiving the Project Scope Statement
A McGregor's Theory-X
C McGregor's Theory-Y
A EVM analysis
C Sensitivity analysis
A Claims administration
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 40 of 52
C Payment systems
A Lose-lose
B Win-lose
C Win-win
D Negotiation
A Left-over
B Contingent
C Secondary
D Residual
A Plan procurements
B Close procurements
C Control procurements
D Conduct procurements
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 41 of 52
A Release Team
B Validation of scope
D Procurement audits
D It results in Organizational Process Asset Updates such as project reports and presentations.
B CV and SV
C PV and AC
A Issues log
B Lessons learned
D Status reports
A Quality
B Continuous improvement
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 42 of 52
C Conformance
D Sigma
A Money spent during the project to avoid failures and divided into two categories: Prevention and Appraisal
B All costs over the life of the project associated with quality and divided into two categories: Conformance and
Nonconformance
C Money spent during and after the project to avoid failures and divided into two categories: Internal and External
D A qualitative measurement that calculates the expected monetary value of quality control measures using the formula COQ =
impact x probability x cash flow
A Expert
B Legitimate
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 43 of 52
C Referent
D Reward
A Lessons learned
A SOW
B WBS
C Scope statement
D Network diagram
C Act of terrorism
C Ground rules
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 44 of 52
D Sensitivity training
A Deliverables
C Change requests
B Free float
C Total float
D Lag
A Hard
B External
C Mandatory
D Arbitrary
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 45 of 52
Fast tracking involves taking activities that were sequential and doing them in parallel. The only activities you can re-arrange are those that have some flexibility. These
are called preferred, arbitrary, or soft logic dependencies.
A Fast tracking allows you to do two project phases in parallel to speed up the project delivery.
B Crashing a non-critical path activity will help to speed up the project delivery.
C Precedence diagramming method (PDM) allows you to have four types of logical relationships, and is more flexible than arrow
diagramming method (ADM).
D Critical chain method is the same as critical path, but it adds resource leveling and schedule buffers.
A Since they are requiring less external supervision they are about to enter the Performing stage
B The addition of a new team member will cause the team to enter the Storming stage
C Because the new team member has been involved as a stakeholder on the project the team will repeat the Norming stage.
D The addition of the new team member will cause the team to enter the Forming stage.
B Identify Risks
A You agree to install the grass since it would be discarded anyway, you are ahead of schedule, and it only takes about an hour to
complete.
B You politely decline the request since he is a friend and it could be construed as a conflict of interest.
C You agree to install the grass after submitting a change request and receiving approval.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 46 of 52
D You politely decline the request since the project is firm fixed price and therefore does not include additional time to complete the
work.
A Get formal acceptance, write lessons learned, release the team, close the contract
B Release the team, get formal acceptance, write lessons learned, close the contract
C Close the contract, write lessons learned, get formal acceptance, release the team
D Close the contract, get formal acceptance, release the team , write lessons learned
A Unlike the Critical Chain Method, the Critical Path Method does not take into account resource constraints and schedule
buffers and therefore does not protect against schedule slippage
B The Critical Path Method uses activity on arrow and therefore provides a more accurate schedule estimate since it doesn't use
dummy activities
C Unlike the Critical Chain Method, the Critical Path Method does take into account resource constraints and schedule buffers and
therefore does protect against schedule slippage
D The Critical Path Method uses activity on node and therefore provides a more accurate schedule since it does use dummy activities
A Your team has the experience to do the specific work but it would be less expensive to use a subcontractor to accomplish the work.
B Your team is the not very experienced with this specific type of work and it would be less expensive to use a
subcontractor to accomplish the work.
C You identify the work package as having a high risk of failure therefore using a subcontractor would transfer the risk.
D You identify the work package as being very costly to complete therefore using a subcontractor would be more economical.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 47 of 52
A Problem solving
B Workaround
C Preventive actions
D Corrective actions
A Gather information such as roles, departments, interests, etc. and identify the potential impact or support each stakeholder could
generate.
B Plan project communications to ensure expectations are properly managed by promptly distributing information designed
to keep all stakeholders properly informed.
C Distribute weekly status reports to each of the stakeholders to ensure they do not miss any important updates to the project status.
Additionally, schedule a weekly conference call with them to discuss their concerns and any issues that may have arisen.
D Analyze stakeholder interests using quantitative and qualitative techniques to ensure stakeholder relationships can be leveraged to
build coalitions and partnerships.
A The original Scope Statement included assumptions which should be always be resolved during project planning
B The changes requested by the customer have mostly involved changes to internal processes which are not covered by the change
control process
C The changes being requested by the customer were requirements mentioned as exclusions in the Project Scope Statement and
therefore should have been denied
D The changes requested by the customer were originally noted as exclusions in the Project Scope Statement, and because
of poor integrated change control, were not handled properly
A A work package that does not meet the requirements, but is later deemed acceptable by the customer
C A system component that was designed to specifications, but the entire system does not work properly
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 48 of 52
A The cost of performing the test is called an appraisal cost, and the additional costs which may be incurred include re-work
or scrap.
D The problem was discovered during Perform Quality Assurance using a Control Chart when the a safety standard variable went out-
of-control.
A Compromise
B Collaborating/Problem Solving
C Forcing
D Withdrawal
A Requirements document
C Project charter
A SV is a positive number which means you have completed more work than you had planned to date.
D ETC is a positive number, which means the project will finish over budget.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 49 of 52
A The Estimate Cost process, which is the process of aggregating the estimated costs of individual activities or work packages
B The Determine Budget process, which is the process of aggregating the estimated costs of individual activates or work
packages
C The Plan Cost process, which is the process of developing an approximation of the monetary resources needed to complete the
project.
D The Estimate Cost process, which is the process of developing an approximation of the monetary resources needed to complete
the project.
A You realize that the previous project team did not finish the WBS since it should have included the required activities.
B This is OK since the lowest level of the WBS should be the work package level.
C You realize that the previous project team did not finish the WBS since it should have included the required resources.
D This is OK since the previous team was using rolling-wave planning therefore the lowest level of the WBS is the work package
level.
A Schedule a regular meeting with the functional supervisors of each team member to ensure they remain authorized to
work on the project until their responsibilities are completed
B Meet with the functional supervisors of each team member to discuss strategies for coordinating performance appraisals and
feedback
C Develop a training plan and schedule to ensure that team members receive the appropriate training needed to enhance their
competencies
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 50 of 52
C Defining activities
A Poor performing team members, bad attitudes and drinking alcohol at the workplace
A Bottom-up estimating is the most labor intensive and not quite as accurate as parametric estimating.
B You have completed the Estimating Costs process and will use the cost performance baseline to begin the Determine Budget
process which will create the budget performance baseline used to measure future project performance.
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 51 of 52
C Bottom-up estimating is the most labor intensive and is more accurate than parametric estimating.
D You have completed the Determine Budget process and will use the cost performance baseline to begin the Establish Budget
process which will create the budget performance baseline used to measure future project performance.
B Training
D Interpersonal Skills
A Risk identification and monitoring are the responsibilities of the entire project team.
B Product samples that are found to violate the Rule of 7 indicate a risk trigger has occurred and should be reviewed as soon as
possible.
C Risk mitigation is a risk response planning technique associated with opportunities that seek to increase the probability
of occurrence or impact of a positive risk.
D Residual risks are risks that remain after risk responses have been implemented.
A Micro management
B Active listening
C Scope verification
D Push Communication
A Use the conflict resolution technique of Smoothing to examine the alternatives and identify a win-win solution
B Explain that any details on whether the requirement is approved or might be completed would be made by the CCB and
assist them in completing a Change Request
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019
Page 52 of 52
C Recognize the stakeholder as a blocker and leave the meeting room to avoid further conflict with a stakeholder
D Agree to personally handle their request to ensure that it is completed as soon as possible to avoid any further conflict
file:///C:/PMP/StratPMP-M1-Oct2015/exam.html 7/21/2019