DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00
Activity ID Activity Name Original Start Finish 2017 2018 2019
Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
DHA BWP (EOT) 732 02-Jan-17 30-Jun-19
Premobilization 11 02-Jan-17 14-Jan-17 14-Jan-17, Premobilization
A1000 Project Start/ Notice to Commence 0 02-Jan-17 02-Jan-17 Project Start/ Notice to Commence
A1010 Submission of Work Schedule 10 02-Jan-17 12-Jan-17 Submission of Work Schedule
A1020 Submission of Work Methodology 10 02-Jan-17 12-Jan-17 Submission of Work Methodology
A1030 Effective Access & Site Possesstion 1 14-Jan-17 14-Jan-17 Effective Access & Site Possesstion
Mobilization 20 14-Jan-17 05-Feb-17 05-Feb-17, Mobilization
A1040 Resource Mobilization 5 14-Jan-17 18-Jan-17 Resource Mobilization
A1050 Provision of Employer's and Engineer's Facilities
15 19-Jan-17 05-Feb-17 Provision of Employer's and Engineer's Facilities
Survey and Design 619 19-Jan-17 26-Feb-19 26-Feb-19, Survey and
A1060 Survey of Project Area 255 19-Jan-17 12-Nov-17 Survey of Project Area
A1070 Issuance of Construction Drawings 500 25-Jan-17 11-Oct-18 Issuance of Construction Drawi
A1080 Submission of Shop Drawings 600 06-Feb-17 26-Feb-19 Submission of Shop D
DHA BWP Sector B 717 19-Jan-17 30-Jun-19
Roadworks 717 19-Jan-17 30-Jun-19
MB-01 (ROW 250'-0") 644 19-Jan-17 06-Apr-19 06-Apr-19, MB-01 (R
Earthworks 444 19-Jan-17 12-Jul-18 12-Jul-18, Earthworks
Sub Base and Base 157 04-Jun-18 23-Dec-18 23-Dec-18, Sub Base and
Surface Course and Pavement 30 24-Nov-18 29-Dec-18 29-Dec-18, Surface Course
Protection Works 10 05-Feb-19 17-Feb-19 17-Feb-19, Protection W
Ancilliary Works 105 30-Sep-18 09-Feb-19 09-Feb-19, Ancilliary Wo
Storm Water Drain 399 01-Nov-17 06-Apr-19 06-Apr-19, Storm W
Potable Water Supply 95 21-Nov-18 21-Mar-19 21-Mar-19, Potable W
Sewrage 130 06-Oct-18 16-Mar-19 16-Mar-19, Sewrage
Utility Crossing Structures 140 17-Aug-17 13-Feb-18 13-Feb-18, Utility Crossing Structures
Electrical Works (Embedded Only) 50 21-Jan-18 20-Mar-18 20-Mar-18, Electrical Works (Embedded Onl
MB-01 (Service Roads) 618 12-Feb-17 20-Mar-19 20-Mar-19, MB-01 (S
Earthworks 89 12-Feb-17 25-May-17 25-May-17, Earthworks
Sub Base and Base 72 24-Feb-18 20-May-18 20-May-18, Sub Base and Base
Protection Works 10 02-Jan-19 13-Jan-19 13-Jan-19, Protection Wo
Surface Course and Pavement 65 11-Dec-18 06-Mar-19 06-Mar-19, Surface Co
Ancilliary Works 247 30-Apr-18 12-Mar-19 12-Mar-19, Ancilliary W
Storm Water Drain 389 05-Aug-17 08-Dec-18 08-Dec-18, Storm Water Dr
Potable Water Supply 148 25-Jun-18 29-Dec-18 29-Dec-18, Potable Water
Actual Work Critical Remaining Work Summary Page 1 of 3 TASK filter: All Activities
Remaining Work Milestone © Primavera Systems, Inc.
DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00
Activity ID Activity Name Original Start Finish 2017 2018 2019
Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Sewrage 120 22-Oct-18 20-Mar-19 20-Mar-19, Sewrage
Utility Crossing Structures 155 18-Jul-17 30-Jan-18 30-Jan-18, Utility Crossing Structures
Principal Collector PC-02 442 10-Sep-17 31-Mar-19 31-Mar-19, Principal
Earthworks 204 10-Sep-17 23-May-18 23-May-18, Earthworks
Sub Base and Base 103 06-Oct-18 12-Feb-19 12-Feb-19, Sub Base an
Electrical Works (Embedded Only) 70 23-May-18 16-Aug-18 16-Aug-18, Electrical Works (Embe
Utility Crossing Structures 86 24-Apr-18 05-Aug-18 05-Aug-18, Utility Crossing Structure
Irrigation Sleeves 120 28-Aug-18 03-Feb-19 03-Feb-19, Irrigation Sle
Surface Course and Pavement 25 06-Feb-19 07-Mar-19 07-Mar-19, Surface Co
Ancilliary Works 113 27-Oct-18 17-Mar-19 17-Mar-19, Ancilliary
Storm Water Drain 302 03-Mar-18 19-Mar-19 19-Mar-19, Storm Wa
Potable Water Supply 148 20-Sep-18 19-Mar-19 19-Mar-19, Potable W
Sewrage 125 21-Oct-18 31-Mar-19 31-Mar-19, Sewrage
Principal Collector PC-03 145 24-Dec-18 30-Jun-19
Earthworks 75 24-Dec-18 09-Apr-19 09-Apr-19, Earthwor
Sub Base and Base 30 13-Mar-19 27-Apr-19 27-Apr-19, Sub Ba
Storm Water Drain 85 12-Feb-19 01-Jun-19 01-Jun-19, Storm
Utility Crossing Structures 40 31-Mar-19 20-May-19 20-May-19, Utility
Ancilliary Works 43 09-Apr-19 29-May-19 29-May-19, Ancil
Surface Course and Pavement 25 24-Apr-19 23-May-19 23-May-19, Surfa
Electrical Works (Embedded Only) 55 09-Apr-19 12-Jun-19
Potable Water Supply 73 19-Mar-19 22-Jun-19
Sewrage 70 09-Apr-19 30-Jun-19
Internal Roads 392 19-Feb-18 30-Jun-19
Earthworks 284 19-Feb-18 14-Feb-19 14-Feb-19, Earthworks
Sub Base and Base 170 20-Sep-18 23-Apr-19 23-Apr-19, Sub Bas
Storm Water Drain 230 11-Aug-18 09-Jun-19
Electrical Works (Embedded Only) 90 27-Nov-18 21-Mar-19 21-Mar-19, Electrical
Utility Crossing Structures 155 17-Oct-18 05-May-19 05-May-19, Utility
Asphalt Works 140 09-Dec-18 09-Jun-19
Ancilliary Works 223 25-Sep-18 30-Jun-19
Sewrage 70 16-Mar-19 15-Jun-19
Potable Water Supply 78 16-Mar-19 24-Jun-19
Tube Well and Rising Main Works 567 13-Jul-17 30-Jun-19
Tubewell Facilities 188 04-Nov-18 30-Jun-19
A3090 Tubewell No 1 120 04-Nov-18 11-Apr-19 Tubewell No 1
A3100 Tubewell No 2 120 13-Jan-19 20-Jun-19
Actual Work Critical Remaining Work Summary Page 2 of 3 TASK filter: All Activities
Remaining Work Milestone © Primavera Systems, Inc.
DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00
Activity ID Activity Name Original Start Finish 2017 2018 2019
Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
A3110 Tubewell No 3 100 24-Feb-19 30-Jun-19
Rising Mains 273 12-Jul-18 30-Jun-19
A3120 Excavation & Backfilling of trenches in all kind
150of 12-Jul-18
soil 28-Jan-19 Excavation & Backfilling
A3130 Providing and laying compacted approved graded150 18-Jul-18
sand 03-Feb-19 Providing and laying com
A3140 Providing and laying approved Class U-PVC 130 Pressure
28-Aug-18
Pipe 14-Feb-19 Providing and laying ap
A3150 Providing and Laying approved class of Control100cable
14-Feb-19 20-Jun-19
A3160 Providing, fabricationg and fixing M.S Pipes 120 30-Sep-18 26-Feb-19 Providing, fabricationg
A3170 Providing all materials and Labour T & P to construct
100 15-Nov-18
Valve Chamber
21-Mar-19
, of different sizes Providing all material
A3180 Providing, and fixing different types of valve 80 19-Mar-19 30-Jun-19
Water Tanks 454 13-Jul-17 09-Feb-19 09-Feb-19, Water Tanks
A3190 OHWT -1 400 10-Sep-17 09-Feb-19 OHWT -1
A3200 OHWT-2 380 13-Jul-17 10-Nov-18 OHWT-2
Actual Work Critical Remaining Work Summary Page 3 of 3 TASK filter: All Activities
Remaining Work Milestone © Primavera Systems, Inc.