Dha BWP (Eot) Dha BWP (Eot) : Premobilization Premobilization

This document provides a work breakdown structure and schedule for a project taking place from January 2017 to June 2019. It outlines key activities including premobilization, mobilization, survey and design, roadworks on MB-01 and service roads including earthworks, drainage, and utilities installation. Principal collector routes PC-02 and PC-03 are also scheduled from 2017-2019 with activities like earthworks, paving, and utility works. The schedule shows the project is ongoing with remaining works through mid-2019 including surface works, ancillary activities, and sewer installation.

Uploaded by

Yasir Nasim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
107 views3 pages

Dha BWP (Eot) Dha BWP (Eot) : Premobilization Premobilization

This document provides a work breakdown structure and schedule for a project taking place from January 2017 to June 2019. It outlines key activities including premobilization, mobilization, survey and design, roadworks on MB-01 and service roads including earthworks, drainage, and utilities installation. Principal collector routes PC-02 and PC-03 are also scheduled from 2017-2019 with activities like earthworks, paving, and utility works. The schedule shows the project is ongoing with remaining works through mid-2019 including surface works, ancillary activities, and sewer installation.

Uploaded by

Yasir Nasim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00

Activity ID Activity Name Original Start Finish 2017 2018 2019


Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

DHA BWP (EOT) 732 02-Jan-17 30-Jun-19

Premobilization 11 02-Jan-17 14-Jan-17 14-Jan-17, Premobilization


A1000 Project Start/ Notice to Commence 0 02-Jan-17 02-Jan-17 Project Start/ Notice to Commence
A1010 Submission of Work Schedule 10 02-Jan-17 12-Jan-17 Submission of Work Schedule
A1020 Submission of Work Methodology 10 02-Jan-17 12-Jan-17 Submission of Work Methodology
A1030 Effective Access & Site Possesstion 1 14-Jan-17 14-Jan-17 Effective Access & Site Possesstion
Mobilization 20 14-Jan-17 05-Feb-17 05-Feb-17, Mobilization
A1040 Resource Mobilization 5 14-Jan-17 18-Jan-17 Resource Mobilization
A1050 Provision of Employer's and Engineer's Facilities
15 19-Jan-17 05-Feb-17 Provision of Employer's and Engineer's Facilities
Survey and Design 619 19-Jan-17 26-Feb-19 26-Feb-19, Survey and
A1060 Survey of Project Area 255 19-Jan-17 12-Nov-17 Survey of Project Area
A1070 Issuance of Construction Drawings 500 25-Jan-17 11-Oct-18 Issuance of Construction Drawi
A1080 Submission of Shop Drawings 600 06-Feb-17 26-Feb-19 Submission of Shop D
DHA BWP Sector B 717 19-Jan-17 30-Jun-19
Roadworks 717 19-Jan-17 30-Jun-19
MB-01 (ROW 250'-0") 644 19-Jan-17 06-Apr-19 06-Apr-19, MB-01 (R
Earthworks 444 19-Jan-17 12-Jul-18 12-Jul-18, Earthworks
Sub Base and Base 157 04-Jun-18 23-Dec-18 23-Dec-18, Sub Base and
Surface Course and Pavement 30 24-Nov-18 29-Dec-18 29-Dec-18, Surface Course
Protection Works 10 05-Feb-19 17-Feb-19 17-Feb-19, Protection W
Ancilliary Works 105 30-Sep-18 09-Feb-19 09-Feb-19, Ancilliary Wo
Storm Water Drain 399 01-Nov-17 06-Apr-19 06-Apr-19, Storm W
Potable Water Supply 95 21-Nov-18 21-Mar-19 21-Mar-19, Potable W
Sewrage 130 06-Oct-18 16-Mar-19 16-Mar-19, Sewrage
Utility Crossing Structures 140 17-Aug-17 13-Feb-18 13-Feb-18, Utility Crossing Structures
Electrical Works (Embedded Only) 50 21-Jan-18 20-Mar-18 20-Mar-18, Electrical Works (Embedded Onl
MB-01 (Service Roads) 618 12-Feb-17 20-Mar-19 20-Mar-19, MB-01 (S
Earthworks 89 12-Feb-17 25-May-17 25-May-17, Earthworks
Sub Base and Base 72 24-Feb-18 20-May-18 20-May-18, Sub Base and Base
Protection Works 10 02-Jan-19 13-Jan-19 13-Jan-19, Protection Wo
Surface Course and Pavement 65 11-Dec-18 06-Mar-19 06-Mar-19, Surface Co
Ancilliary Works 247 30-Apr-18 12-Mar-19 12-Mar-19, Ancilliary W
Storm Water Drain 389 05-Aug-17 08-Dec-18 08-Dec-18, Storm Water Dr
Potable Water Supply 148 25-Jun-18 29-Dec-18 29-Dec-18, Potable Water

Actual Work Critical Remaining Work Summary Page 1 of 3 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00

Activity ID Activity Name Original Start Finish 2017 2018 2019


Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
Sewrage 120 22-Oct-18 20-Mar-19 20-Mar-19, Sewrage
Utility Crossing Structures 155 18-Jul-17 30-Jan-18 30-Jan-18, Utility Crossing Structures
Principal Collector PC-02 442 10-Sep-17 31-Mar-19 31-Mar-19, Principal
Earthworks 204 10-Sep-17 23-May-18 23-May-18, Earthworks
Sub Base and Base 103 06-Oct-18 12-Feb-19 12-Feb-19, Sub Base an
Electrical Works (Embedded Only) 70 23-May-18 16-Aug-18 16-Aug-18, Electrical Works (Embe
Utility Crossing Structures 86 24-Apr-18 05-Aug-18 05-Aug-18, Utility Crossing Structure
Irrigation Sleeves 120 28-Aug-18 03-Feb-19 03-Feb-19, Irrigation Sle
Surface Course and Pavement 25 06-Feb-19 07-Mar-19 07-Mar-19, Surface Co
Ancilliary Works 113 27-Oct-18 17-Mar-19 17-Mar-19, Ancilliary
Storm Water Drain 302 03-Mar-18 19-Mar-19 19-Mar-19, Storm Wa
Potable Water Supply 148 20-Sep-18 19-Mar-19 19-Mar-19, Potable W
Sewrage 125 21-Oct-18 31-Mar-19 31-Mar-19, Sewrage
Principal Collector PC-03 145 24-Dec-18 30-Jun-19
Earthworks 75 24-Dec-18 09-Apr-19 09-Apr-19, Earthwor
Sub Base and Base 30 13-Mar-19 27-Apr-19 27-Apr-19, Sub Ba
Storm Water Drain 85 12-Feb-19 01-Jun-19 01-Jun-19, Storm
Utility Crossing Structures 40 31-Mar-19 20-May-19 20-May-19, Utility
Ancilliary Works 43 09-Apr-19 29-May-19 29-May-19, Ancil
Surface Course and Pavement 25 24-Apr-19 23-May-19 23-May-19, Surfa
Electrical Works (Embedded Only) 55 09-Apr-19 12-Jun-19
Potable Water Supply 73 19-Mar-19 22-Jun-19
Sewrage 70 09-Apr-19 30-Jun-19
Internal Roads 392 19-Feb-18 30-Jun-19
Earthworks 284 19-Feb-18 14-Feb-19 14-Feb-19, Earthworks
Sub Base and Base 170 20-Sep-18 23-Apr-19 23-Apr-19, Sub Bas
Storm Water Drain 230 11-Aug-18 09-Jun-19
Electrical Works (Embedded Only) 90 27-Nov-18 21-Mar-19 21-Mar-19, Electrical
Utility Crossing Structures 155 17-Oct-18 05-May-19 05-May-19, Utility
Asphalt Works 140 09-Dec-18 09-Jun-19
Ancilliary Works 223 25-Sep-18 30-Jun-19
Sewrage 70 16-Mar-19 15-Jun-19
Potable Water Supply 78 16-Mar-19 24-Jun-19
Tube Well and Rising Main Works 567 13-Jul-17 30-Jun-19
Tubewell Facilities 188 04-Nov-18 30-Jun-19
A3090 Tubewell No 1 120 04-Nov-18 11-Apr-19 Tubewell No 1
A3100 Tubewell No 2 120 13-Jan-19 20-Jun-19

Actual Work Critical Remaining Work Summary Page 2 of 3 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


DHA BWP (EOT) Classic WBS Layout 19-Dec-18 03:00

Activity ID Activity Name Original Start Finish 2017 2018 2019


Duration Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
A3110 Tubewell No 3 100 24-Feb-19 30-Jun-19
Rising Mains 273 12-Jul-18 30-Jun-19
A3120 Excavation & Backfilling of trenches in all kind
150of 12-Jul-18
soil 28-Jan-19 Excavation & Backfilling
A3130 Providing and laying compacted approved graded150 18-Jul-18
sand 03-Feb-19 Providing and laying com
A3140 Providing and laying approved Class U-PVC 130 Pressure
28-Aug-18
Pipe 14-Feb-19 Providing and laying ap
A3150 Providing and Laying approved class of Control100cable
14-Feb-19 20-Jun-19
A3160 Providing, fabricationg and fixing M.S Pipes 120 30-Sep-18 26-Feb-19 Providing, fabricationg
A3170 Providing all materials and Labour T & P to construct
100 15-Nov-18
Valve Chamber
21-Mar-19
, of different sizes Providing all material
A3180 Providing, and fixing different types of valve 80 19-Mar-19 30-Jun-19
Water Tanks 454 13-Jul-17 09-Feb-19 09-Feb-19, Water Tanks
A3190 OHWT -1 400 10-Sep-17 09-Feb-19 OHWT -1
A3200 OHWT-2 380 13-Jul-17 10-Nov-18 OHWT-2

Actual Work Critical Remaining Work Summary Page 3 of 3 TASK filter: All Activities