Satellite Power Systems Requirements
Satellite Power Systems Requirements
R=19800022395 2019-09-15T17:30:33+00:00Z
G. M. Hanley
CONTRACT NASs-32475
SEPTEMBER 1980
NASA
TECH LIBRARY KAFB, NM
G. M. Hanley
Rockwell In term tiona 2
Downey, California
Prepared for
Marshall Space Flight Center
under Contract NASS-32475
NationalAeronautics
and SpaceAdministration
Scientific and Technical
Information Branch
1980
-. m-m.., I .m--1 m---..n -..I. -. m-
FOREWORD
The SPS final report will provide the NASA with additional
information on the selection of a viable SPS concept and will
furnish a basis for subsequent technology advancement and veri-
fication activities. Other volumes of the final report are
listed as follows:
Volume Title
I Executive Summary
II Systems Engineering
IV Transportation Analyses
iii
__.__...
--...-. -. ..
CONTENTS
Section Page
V
.-.
-
ILLUSTRATIONS
Figure Page
Vii
. . , @.-... ..--..---...--.... . . ...-.-. ._. .._ .. ... _. ..._. .__....,
,._.... ..,,... ..-.._,..-.. ._ ._. . ,, _._._.__.__
_ -.-_
Figure Page
Table Page
IX
Table Page
X
1.0 SCOPE/GENERAL REQUIREMENTS
1 .O SCOPE/GENERAL REQUIREMENTS
1.1 INTRODUCTION
Figure 1.1-l establishes the relationship of the satellite system with the
other elements of the SPS program.
. HLLV
l SlS
l CON
.POTV
l-1
Figure 1.1-2 identifies the various satellite subsystems and the functions
as they apply on the satellite. Equivalent functions are applicable to the
ground receiving station (rectenna) system and will not be expanded here. A
limited discussion of ground receiving station subsystem functions will be
found in the section dedicated to ground receiving station requirements.
r ----
SATELLITE 1 GROUND 7
SYSTEM 1 SYSTEM I
L J
-2--
---a-)
I !
l SOLAR CELLS *DC-RF CONV l FWR OISTRIB *CENTRAL l AlTlTUOE .POWER *PROCESSOR *RF-OC
aSOLAR BLANKET *ANTENNA *REGULATION
GIRDER
4ECONOARY
OETERMIN CONVERSION/
l
PHOTOVOLTAIC ;EM;ONTROL
CONVERSION
-POWER
*REFLECTOR *ANTENNA *ENERGY *HEAT OlSTRlBUTlONl
GIMBAL STORAGE .REEFLECTOR REJECTION *DATA BUS CONTROL’
*HEAT CONTROL’
REJECTION’ *POWER *ANTENNA l MW ANTEN- *REMOTE 4NFORYATION
*SECONDARY CONOITIONING NA FIG. *ANTENNA
SYSTEMS ACOUISITION MANAGEMENT’
l SECONDARY STRUCTURE .ROTARY CONTROL &CONTROL
STRUCTURE* *ROTARY JOINT JOINT
CONCEN- *ROTARY JOINTS *SUBMULTI- .
l %ELL
*CONTROL *SOLAR ARRAY PLEXOR
EToR *SECONDARY
.SECONOARY STRUCTURES* .MICRO- l STRUCTURE’
*MECHANISMS CONTROL
STRUCTURE* PROCESSOR
l REACTION
CONTROL *CONTROL*
*UTILITY GRNO
*SECONDARY INTERFACE’
STRUCTURE*
. SECONOARY
STRUCT*
*MAJOR INTERFACES PROCESSING’
Many candidate system concepts have been considered since the inception
of this study program. Six satellite concepts were identified for considera-
tion at a briefing in November 1977. These concepts are shown in Figure 1.2-1.
A single rectenna farm concept was assumed, applicable to all satellite concepts,
l-2
Figure 1.2-l. SPS Conceptual Configuration (Nov. 1977)
l-3
Solar Photovoltaic (CR-2). Figure 1.2-3 illustrates the solar photovoltaic
(CR-2) satellite power system concept. The CR-2 system used reflector membranes
to concentrate solar energy on the cells. The satellite had two "Vee" troughs
per wing. The overall planfonn dimensions were 2.75x27.16 km, and the depth
was 1.2 km. This system required 23.76 km2 of deployed solar cell area and had
a total mass of 33.7~10~ kg, including a 30-percent growth factor. The major
advantages of the CR-2 configuration were the reduced requirement for solar
cells and low weight which reduced overall cost. The disadvantages were the
planform of the satellite was higher than for CR-1 and the system was sensitive
to misorientation. A +l degree misorientation of the solar array required an
additional 7.9 percent of reflector surface area. The reflective membranes
for the GE0 environment was not available, and reflectivities of 90 percent
at the beginning of life and 72 percent at the end of life were used in the
design.
l-4
Figure 1.2-4. Solar Photovoltaic Satellite (CR-51 (Nov. 1977)
Solar Thermal - Brayton. Figure 1.2-5 shows one Boeing concept for a
lo-GW solar thermal SPS. It used four concentrator modules, each composed of
thousands of planar facets which reflect sunlight into a cavity absorber.
Ceramic tubing in the absorber heated pressurized helium to 1379'C (2514'F)
which was supplied to a Bray:on cycle power module comprised of a turbine,
regenerator, cooler, compressor, and electrical generator. Heat rejected
from the cycle was dissipated by means of a NaK loop to a heat pipe/fin
radiator. Microwave power was transmitted from a single antenna at the end
of the satellite.
l-5
- 8 tN KWKW,
PIESClYY/w4 ,, .;g, I
I,, - 818 l 3M UWaPOWERSAT YOOULE
f I ow IIJ&md
IIIGH PRESSURE
DESIGN
shadow shield, fuel reprocessing assembly, and two closed Brayton cycle power
conversion units. The power module could be removed from the radiator for
replacement by remotely operated equipment.
Satellite Mass Properties. Tables 1.2-l through 1.2-3 present the summary
weights for the six initial candidate satellite concepts. The solar thermal
weight summary illustrates the known weight elements for both potassium-(K) and
cesium-(Ce) based Rankine thermal cycles.
l-7
Table 1.2-l. Solar Phqtovoltaic Weight Summary
(GaAlAs Solar Cells) (Nov. 1977)
COMPARABLE SILICON CR - i
WEIGHT - 43.589 X l@ KG
1-i
Table 1.2-J. Nuclear Reactor Concept Weight Summary
(Nov. 1977)
The two concepts selected for further evaluation and definition at the
end of the initial study in April 1978 were a photovoltaic (CR-2) approach
and a variation of the proposed Rockwell Solar Thermal satellite. A summary
description of the two selected point designs are given in the following two
paragraphs. Both these concepts are described in greater detail in Volume II
,of the Final Report (SD 79-AR-0023, dated April 1978).
l-9
Solar Photovoltaic (CR-2). The GaAlAs photovoltaic point design satel-
lite power system concept is shown in Figure 1.2-8. The system utilizes
aluminized reflector membranes to concentrate the solar energy on the cells.
The satellite solar reflectors produce a concentration ratio of CR-2. The
satellite employes the "Vee trough" configuration has three troughs per wing.
The system has an overall efficiency of 6.08% and delivers 5 GW of electrical
energy to the utility company on the ground. The overall planform dimensions
are 3.85x21.3 km, and the depth is 1.69 km. The satellite has a mass of
36.56~10~ kg which includes a 30% growth factor for the mass. The system
requires 30.6~10~ m2 of solar cells and 61.2~10~ m2 of reflector surface.
The solar cells for the point design are GaAlAs cells rated at 20% efficiency
at AM0 and 28'C. The solar array blanket mass is 0.2525 kg/m'.
Solar Thermal - Rankine. Figure 1.2-9 shows the Rockwell point design
concept of a 5-GW solar thermal SPS using a cesium/steam Rankine cycle. The
two concentrators are of an inflatable design, using aluminized plastic film
with a transparent canopy. Sunlight is concentrated on an open-disc absorber
(cesium boiler) which provides cesium vapor at 1260°C (2300'F) to cesium
turbines. Exhaust from the cesium turbines is condensed at 593°C (llOO°F)
on the outside of steam boiler tubes which produce steam at 538'C (1000'F)
and 16.6 kN/m' (2400 psia) to a bottoming steam turbine. Exhaust from the
steam turbines is condensed at 204°C (400'F) in a tube/heat pipe/fin radiator.
l-10
. INFUTAILE *&sonBcR b 159
INDEPENDEI -
l x)0 PSI REFLECTOR FILM STRESS
POWER MOL”...
l 5 KM DIA
RECTENNA MODVLE
l-11
/sw’rcn IARD
N0.’
/CONVERTER L RELAY 1DG
-MAINTENANCE AtEA
CONQETE RANT3
’ KtIMElEt fENCE
. RECIENNA IANCL
tiEA ,I0 KY X I3 KM,
Mass Properties. Table 1.2-4 and 1.2-5 present a summary of the estimated
weight for the two point design concepts.
Keight
Subsystem (Yfllion kg)
collector array
Structure and orchanisms 3.777
Power source 8.831
Power distribution and control 1.166
Attitude control 0.095
Infcrmacion nanagment and control 0.050
Total array (dry) (13.919)
Anrenna section
Structure and mechanisms 1.685
Thenal control l.LO8
Yicrowave power 7.012
Povrr distribution and control 3.:69
Informtion management and control 0.630
Total antenna section (dry) (11..?OL)
l-12
Table 1.2-5. Solar Thermal Satellite Mass Statement
- Point Design (Apr. 1978)
WEIGHT
SUBSISTER (MILLION KG)
tOLLECTOR ARRAY
STRUCTURE AND HECHANISMS I.661
POWER SOURCE 3.120
POWER DlSTRl8UTlON AND CONTROL 4.304
ATTITUDE CONTROL 0.095
THERMAL CONTROL 0.706
INFORIlAT10N MANAGEMENT AND CONTROL 0.050
TOTAL ARRAY (DRY) (18.016)
ANTENNA SECTION
STRUCTURE AND HECHANISHS
THERMAL CONTROL :%
HICROUAVE POWER 7:012
POWER DISTRIBUTION AND CONTROL 3.469
INFOIWATION MANAGEHENT AND CONTROL 0.630
TOTAL ANTENNA SECTION (14.204)
The Silicon cell based concept consisted of 8 cell troughs each containing
16 bays. The GaAlAs concept consisted of 5 troughs by 20 bays. Both concepts
utilized an end mounted, 1 km (nominal) microwave antenna. Both concepts were
normally 5.3x10.4 km, with the Silicon concept containing a greater mass.
(51~10~ kg) compared with GaAlAs (34 10 kg). Figure 1.2-12 illustrates the
GaAlAs version of the reference satellite. Overall system efficiency for the
Silicon based concept is estimated to be 7.06%, while for GaAlAs the efficiency
is estimated to be 6.97%. Power output for these concepts (at utility inter-
face) is estimated at 5.0 GW.
Mass Properties. Table 1.2-6 presents a summary of the estimated mass for
the two reference concepts.
l-13
i ,050 m
1-14
:h \
Cb)
The solar array panel is 600 m wide X 750 m long. Two of these panels
make up a voltage string (45.7 kV). The 600 m width consists of 24 rolls each
25 meters wide. Sizing of the array is based on a solar constant at summer
solstice (1319.5 W/m2), an end of life concentration ratio of 1.83, an operat-
ing temperature of 113°C and the design factors listed in the figure. A
design margin factor of 0.975 is used to match the available area of 27~10~ m2.
Total power at the array output is 9.52 GW. Total transmitted power is 6.79 GW.
System efficiency factors for the satellite as indicated in Figure 1.2-14.
Mass Properties. Table 1.2-7 presents a summary of the mass for the two
alternate concepts.
The rectenna panels are located in the center of the receiving station
and covers a ground area of approximately 80 km2 (approximately 25,000 acres).
An additional 32 km2 (approximately 10,000 acres) is required for the distribu-
tion and conversion stations plus a security perimeter. Received power is
approximately 5.53 GW (at 2.45 GHz). Power available at the utility interface
is approximately 4.6 GW ac.
1-15
(9.52 GW r ,
SLIP
SWITCH
RING/ -
GEAR
RRUSH (~(8.92 Gw)
I- 0.9381- I
POWER DIST
l- 0.7608
MW ANT
4
\‘.-, ‘.,
I I
GROUND
SUBSYSTEM END-MOUNTED
l-17
1.3 TRANSPORTATION SYSTEM
l-18
I -
Table 1.4-l shows the program ground rules that affected the development
of requirements. Table 1.4-2 shows the general requirements describing the
overall SPS program.
Progr-tic Technology
-
CONSTRUCTION-Structural material to be
graphite composite.
STARruP/.SHClTDCi#N-!fSD
--
1-19
II
2.1 SATELLITE
2.1.1 INTRODUCTION
The IMCS also provides subsystem processing support for all but the very
special functions. The only specific case of a special function identified
at the present time is the beam programmer element in the microwave antenna
subsystem. The man-machine interface has also been established to be at
computer-generated display/control terminals. The display/control terminals
have not, as yet, been defined -- nor will they be during this contract.
2-l
DISRIDUlION
Power Generation
Figure 2.1-2 presents the basic power generation concepts for the photo-
voltaic concept with a concentration ratio of 2 (CR-2). Switchgear for inter-
segment connections are considered part of the power generation group.
;: SUMMING&
I
BUS
43.1 I(”
21120 8.96 GW
022
Jv=emv
2-2
Power Distribution
Figure 2.1-3 presents the functional block diagrams for the satellite
power distribution subsystem. The supplementary power source is required
during eclipse periods to power critical support systems and to sustain
temperature-sensitive subsystem elements such as the MW antenna klystrons.
Figures 2.1-4 through 2.1-6 present the subsidiary systems that make up
the attitude control and stationkeeping subsystem for the photovoltaic SPS
satellite concepts. These three systems are the attitude reference (platform)
system, the microwave antenna pointing system (ring drive and gimbal drives),
and the tank and engine systems,
2-3
---a
1 AH CON? 1
pENG & 1Ky
*RINGS L
I I
GIW
kINFIG 1
r “1 r
I MGMT I
I -1
L-- J L-Ja-
?? P
ff r--1
r--1 r Iwo 1
I**-1 1 YGNT 1 I
WUIO S-’
IcoFllux I 1-I I I
L w-d LW-.l-- L-w J
I- - - -1
lA~CONlROLt
1 (*nm \
I --,-I
c
7-7
INK)
I MGMT I
1
r --1 r-- 1
2-4
.
Structure
r
1
13
INFO ‘I
MGNT 1
I MO i
LWNTROLJ
--
--
LUUCIW~
I I
L--J
r-- 1
‘-
I
I I
L--d
Thermal
Microwave Antenna
Figure 2.1-9 presents the beam generation and control portion of the micro-
wave antenna subsystem. Most of the paths shown operate at frequencies of
approximately 2.45 GHz and are, therefore, either coaxial cable, strip lines,
or waveguides. The beam programmer is a special-purpose dedicated processor
design to accomplish high-speed RF pointing control via the digital diode phase
shifter. External processing is limited to much slower, large element antenna .'
pointing and performance monitoring and control.
2-5
-
- ‘I
PHOTOVO'LTAIC, GaAlAs, CR = 2
*SOLAR ARRAY
I TBLANKET = ll3"Cl
*POWER DISTRIBUTION
*ROTARY JOINT
*INFORMATION MGMT
T = 60"~
MAX
T = 60°C
MIN
El
*ANTENNA
CAVITY RADIATOR
T = 200°C
COLLECTOR RADIATOR
T = 700°C
2-6
--
I I- 1
I ro*n I
, wanrtu,
I L- J
I T 30wntnnw
RoJ
I
N
I
W
I-1
P _ rr
I 7s
2.2.1 INTRODUCTION
The functional flow diagrams for the Ground Receiving Station (GRS) are
in many respects similar to those established for the SPS satellite. This
becomes apparent when considering the relationship of the various subsystems
and interfaces as shown in Figure 2.2-l. As on the satellite the Information
Management and Control Subsystem (IMCS) provides primary control and system
monitoring with the man-machine interface primarily used for judgement and
system reconfiguration.
I ,
INFORhWION MANAGEMENT AND CONTROL
Power Reception
2-10
‘0.3lM WIDE FOOTING. 0.194 Ay3vL GUDL,
0.43 Y YLCW GRMIE (2 FUCES,
INTERCONNECT SCHEME
2 LINKS 2 XgLONG
4 LINES 7/2 k ALL OTHERS A g LONG
4 LINES 7/2 fiA
Figure 2.2-4 presents the functional block diagram for the GRS. Power to
supply the various operating systems during periods when the satellite source
is not transmitting power, or during startup periods, is provided by cross-
feeds to other auxiliary power sources not shown in this diagram.
2-11
96 DOUBLE BOXES
EA SECTOR
1M . CUBES
\ 40,000 VDC BUSSES ISOLATION
SWITCHES\
(CONVERTER
I 400 MW
I STATION I 500 KVAC
(lYPlCAL
OF 12
SITES)
2 \
-g-c
Eli
IL \
\
108s ROWS
----- w------------------
FEEDERPOWER (INPUT TO
40,000 VDC BUSSES)
I RANGE 12.1 - 16 MW AT
‘- (300 - 400A) ’
14.8 MW AS MANY FEEDERS
AS REQUIRED TO
APPROACH 16 MW
Figure 2.2-4. Ground Receiving Station Schematic
Block Diagram - Preliminary
lr
Included in the power distribution networks are the voltage feeders run
behind each rectenna panel, the 40 kV dc and 500 kV ac buses as well as the
voltage string isolating motor switches and system protecting switchgear.
4g
4 4
I I
I
- I
- CONTROL _ _ - - - - - - - -I
Structure
Thermal
The specifics of thermal control and/or shielding have not, as yet, been
determined. Details will be established by future studies (TBD).
2-13
Figure 2.2-6. Panel Installation Operations
This subsystem provides for overall ground site control as well as all
on site system status monitoring. With the addition of appropriate connnunica-
tion channels the on site IMCS can also provide for off-site safety and
security.
The basic architecture of the individual subsystems have not been defined
because of the limited details available.
2-14
I
Group A l Group C Group B
Equipment , Equipment Equipment
PERIMETER
HONITOR
NO. 1
I
I
I
COMPUTER I
I I
I
POWER DISTRIB POWER OISTRIB. POWER DISTRIB. POWER DISTRIB.
I
4 I
THERML THERHAL
GROUP A GROUP C I
CDHPUTER l
BCU
3.1 SATELLITE
l Power Conversion
l Microwave Transmission
l Power Distribution and Control
9 Structure
l Attitude Control and Stationkeeping
l Thermal Control
l Information and Management Control
Major Assemblies
The major assemblies and components that are required for the photovoltaic
subsystem are shown in Figure 3.1-3.
3-l
Table 3.1-l. Solar Array Functional Requirements
--- PROGRAMMA'TIC
ENEIGY SOURCE - Solar
CtlPACI'I'y - 9.5 GW (nominal) delivered to power distribution networks
LIFETIME - 30 years with minimum planned maintenance (should be capable of extended life beyond 30
years with replacement)
K-K' DA7'E - 2000
OPERd'TIONS - Geosynchronous orbit; O-degree inclination, circular (35,786 km altitude)
RESOURCES- Minimum use of critical resources
COPlEfERRCIAIJZdTION- Compatible with United States utility networks
DEVEU3PEfENT- Evolutionary, with provi:;ions for incorporatinq later technoloqv
r
-.. _-.- . __
OUTPUT POWER - Power level is defined
MASS GROWTH- 25 percent
as constant
TECHNOLOGY
power level (except during solar eclipse)
J
SOLAR ENERGY
1
F
O.l*FOR
1
CC
~RCIJI, DISPLAYS
1
1 Ifi
3-3
SOLAR PHOTOVOLTAIC
’ POWER CONVERSION
I I
3-4
-
.46
50 loo WI MO 25Q
SOUR CELL lEMFE9AlLRE f-0
TODAYS XIMTCELLS
(HUGHER S9S DESIGN S.O.L.
l2=20.4 (Z.W.J.59 04
CR-I; 12x 8X-1.72; I2SC
.W3.1% (Aho 47.6%
V~9-0.69 VOLlS/CELL
V~-x69V/(ILLm.m2v/ch4l
I,&23 M*JCM WIDTHI (10.5.’ MAfCUl
ly+27MA-U.5WCMWlDTM
( b-f01
3-s
rnlGH1 fMGm.4
7.w
INlERCONNfC75 a.4
&TO, GRID C.ONlACTS
0.03
1.66
4.0
1.7
II I27nsU II
---.-..
.._.
-,
SOLAR ARRAY DESIGN FAClORS
3-6
Concentrators. Thin reflector membranes are used on the SPS to reflect
the sun onto the solar cell surfaces and obtain a nominal concentration ratio
of 2. The reflector is made of 12.5 pm (0.5 mil) aluminized Kapton. Reflec-
tivity of the reflector was taken at 0.9 BOL and 0.72 EOL. The reflector
membrane has a mass of 0.018 kg/m'. The reflective membranes are mounted on
the structure using attachments and tensioning devices. Tensioning based on
structural limit of the existing beam design (with safety factor of 1.5)
indicates that tensioning of up to 75 psi can be used.
ITEM CHARACTERISTIC
3-7
Table 3.1-3. SPS Reflector Preliminary
Specification (CR-L?)
ILeE
The subsystem interfaces are shown in Table 3.1-4 for the photovoltaic
conversion subsystem. The major interfaces include the array orientation,
attitude control, IMS and control, energy storage, power distribution,
structure, thermal control, and support operations.
The array is phased by means of a pilot beam formed at the rectenna which
is received by the array and used to form the power converter drive signals.
3-8
Table 3.1-4. Solar Array Interfaces
Subsystem Interface Interface Requirement I Value or Comment
r Voltage 45.i kL’
Power distribution
I Power (E.OL) 9.52 Cli
+-- --
-l-kermal
Array Temperature 113°C
I Reflector Temoerature 46°C to -73’C
DNA
an
I t
WCWNICY
UmAlloN counu
3-9
Table 3.1-5. Microwave Antenna - Operating Modes
asing tests
Rectenna tests
a MECHANICAL
Major Assemblies
i-10
. KLYSTRON (I) . WAVEGUIDES
( 1) ~-~?-~~<-~~~~ft~~ ~yij~&y--- ---;
--w---w
l ELECTRONIC
(4) ~~~~TR-O-~-----
-,,,-,,,-,J BEAM STEERING
l SENSORS l REFERENCE
SIGNAL
FEED
(2) L-
r~-k7~Xi7
-- X5 ?%7 7
---,,,,A
l PHASE CONTROL
l WAVE GUIDE PANELS
(3)~~r&Kc7o~Xoi~
-------a
l RiFiRENCE SIGNAL (1) SEE POWER DISTR. d CONTROL
GENERATION (2) SEE THERMAL CONTROL
l SENSORS (3) SEE ATT. CONTROL
(4) z --------,..a
??%Tk’o’iS- - - - y (4) SEE Ih’CS
(5) SEE SXUCTURES
, HEAT PIPES
MICROWAVE
SLOTS IN RCR
ELECTRONICS
MOUNTING IS0
KLYSTRON COLLEClOR
The transmitted signal is formed from the pilot beam by means of the
retroelectronics shown previously in Figure 2.1-9; there is one of these
circuits per subarray. Figure 3.1-13 shows a servo system for transferring
the required reference phase from a central point to a mechanical module,
where it is distributed to the nine subarrays.
f 4
RWRENCE SIGNAL
06lRINllON
TRANMSSICW LINE
RUSE
stwrR
-3
M
DaJuR
3-12
Figure 3.1-14 illustrates the power supply system required for each 50-kW
klystron. Note that the "mod anode" is a low-current electrode. It
would be
supplied by a separate circuit capable of varying its potential to control
klystron power.
PtJ0.5w PO 50 KW
/COLLECTOR
P =3.2 KW 1.4-
MOD-ANODE ELECTRON BEAM 0.7’
POWER SUPPLY POWER SUPPLY + 0.47
0.08 A
(REGULATED) ‘(REGULATED)
I COLLECTOR 1
I POWER SUPPLY
(NON-REGULATED) PT = 59 YW
OVERALL EFFICIENCY ? = 84.596
The functional requirements for the MPTS system are shown in Table 3.1-6
through 3.1-11. Table 3.1-6 summarizes the system functional requirements;
Table 3.1-7 shows the prime power requirements for the array; Table 3.1-8
shows a phase error budget for the retroelectronics; Table 3.1-9 shows the
array characteristics; Table 3.1-10 shows the characteristics of the klystron
power module; and Table 3.1-11 shows the characteristics of the alternate
transistor power module.
3-13
TO SECOND DC CONNECTOR
COMBINER OR
ANTENNA
FIVE TO TEN _
HOUSING WITH
SAPPHIRE POWER
DIVIDER/COMBINERS POWER MODULE
CTD, ,rm IBC
AT BOTTOM.
3-14
DIPOLE
ED THRU)
STRIP
LINE
SLOTS
I , 1 IDIPOLE
NOTE: DIVISION INTO
CELLS NOT SHOWN
Figure 3.1-17. Transistor Chip Layout
1 3-15
Table 3.1-7. Design and Performance Characteristics
Voltage Regulation
Device Frea. W) Current A Power (kTJ) (73
3-16
Table 3.1-10. Klystron Power Module
The power distribution and control subsystem (PDS) receives power from
the power generation subsystem, and provides the regulation and switching re-
quired to deliver regulated power from distribution to the antenna system
(Klystrons) and the various subsystems (Attitude Control, IMCS, etc.). During
the ecliptic periods, batteries will be utilized to supply the minimum requir-
ed power to the various subsystems. The feeders, and power cabling of all SPS
subsys terns, are included in the PDS. The grounding, electromagnetic interfer-
ence control, and shielding requirements of the SPS are also included as part
of the PDS. The life expectancy of the PDS is 30 years with the exception of
the energy storage (batteries), which has a life expectancy of 10 years.
Resupply of the PDS will be as needed.
3-17
Table 3.1-12. Power Distribution and Control-subsystem
- Operating Modes
Operaticn
EdiF=
lied to subsvstems
Transition (from con-
L-Z strwtion_______
trms3ort.l
-- --
Failurcy - ---
ndstenancti
Cixtckouc
Major Assemblies
Figure 3.1-19 illustrates the major assemblies comprising the power dis-
tribution and control subsystem (PDS).
3-18
I SUBSYSTEM LOAD IUS
I-
SLIP RING “*”
TYPICAL
.Q DRLISHES
1
SOLENOID 2GV DL ID6
COMPUTEn 1oV 01 10x
RETROELECT 2OV 01 IOI
TOTAL 60 8
DlSTRlSUTlON
3-20
Rotary Joint. The rotary joint is utilized to transfer energy through
slip rings and brushes from the SPS fixed member to the SPS rotating member
upon which the microwave antenna is located. The power transferred includes
both that required to operate antenna-mounted equipment, as well as that to be
transmitted to the ground.
Design -~-~.
_--- and.-~~
Performance Characteristics
The design and performance characteristics for the power distribution sub-
system are listed in-Table 3.1-13.
Table 3.1-13. Design and Performance Characteristics
GENERAL
Mass Configuration dependent
MTBF Subsystem dependent
Life 30 years
Efficizzy 88-98% (config. dependent)
Resuppl:- and maintenance As needed
POWERDI~?.IBUTIO?I (PD) Mostly flat conductor Further study is
Mass Configuration dependent required to deter-
Materihl Aluminum 6001-T6 mine feasibility L>f
Insuls:ion l-mm Kapton superconductivity
Efficiczzy 88-98% (config. dependent) for reduction of
Subsyszzx cabling Location and power dependent mass.
ResuppI:- and maintenance As required
Life 30 years or greater
POWERCO!.-:sITER .UTl COXDITIONING
Dens icT 0.197 kg/kW Further analysis is
Voltape Subsystem dependent required to specify
Currecz Subsystem dependent design requirements
Efficii-xy 96-98% and type.
Life 30 years
Resup?::: and nainienance As required
SWITCH GE1-Z
Densic:; Approx. 0.00086 kg/kW Study is required ti
5w Penning discharge tube specify design
Power raring Configuration dependent requiraments.
Voltaj Config. and location dependent
Efficiazcy 99-99.9%
Life 30 years
Resup;::; and maintenance As required
ENERGYSI:~GE (BATTERY)
Densic~ Approx. 200 Wh/kg Further study to
Type Sodium chloride define chargefdis-
Temperature 2oo"c charge cycle, size,
Efficiency 80-95% (turnaround) volume, and instal-
Life lo-20 years lation is required.
Resupllr and maintenance As required
3-21
Table 3.1-13. Design and Perfdmance Characteristics (Cont.)
SECOKDARYSTRUCTLXE
Mass 1OZ of PDS veig:lt was considered
equired for maunting and
cross-section
Shoe size
Dimension/shoe
Contact surface area/shoe
Weight/shoe
Shoe travel velocity
Wear rate per year
Current density
Operating teoperature
Subsystem interfaces are shown in Figure 2.1-2 for the photovoltaic con-
cept. The power required from the photovoltaic power source is 9.55 GW.
The primary SPS structure assemblies are made up, basically, of tribeam
girders, tension cables, and joints. The fabrication and assembly of these
structures are accomplished on orbit by beam machines and supporting auxiliary
equipment. These structural elements must individually withstand the forces,
torques, and dynamics imposed by the construction process. Once built up to
an assembly level (e.g., solar array wing, rotary joint, etc.), the structure
3-22
must have sufficient strength and stiffness to withstand forces, torques, and
dynamics generated by the environment (gravity-gradient torques), the attitude
control system (forces and frequencies) and the operational equipment (rotary
joint torques, microwave induced thermal environment, etc.). The level of
strength and stiffness are dictated by other subsystem requirements such as
pointing accuracies and ACS bandwidth frequencies.
Major Assemblies
Figure 3.1-20 depicts the major structural subsystem assemblies and tabu-
lates the elements that make up each of these major assemblies. An example of
this element breakdown in shown in Figure 3.1-21.
3-23
Figure 3.1-20. Assembly Tree - Structures Subsystem
3-24
-DesiEand Performance Characteristics
Subsystem interfaces are shown in Figure 2.1-7. The only active inter-
face identified to date is the laser transit network, established to determine
the satellite figure for the CR-2 photovoltaic satellite. It is expected that
this network would be applicable to any photovoltaic concept.
3-25
c
Table 3.1-15. Design and Performance Characteristics
CONSTRUCTION
TRANSITION FROfl
I VEHICLE STABILIZATION
DOCK1 NC
STATIONKEEPING
i ANTENNA POINTING
FIGURE CONTROL
STATIONKEEPING
f
FAIL-OPERATIONAL REDUNDANCY ON
FAILURE MAINTENANCE ALL ATTITUDE CONTROL FUNCTIONS
MAINTENANCE INTERVAL. -> I YEAR
LEAK CHECKS
1
SOLAR POINTING AND FIGURE CONTROL
CHECKOUT
STATIONKEEPING
DYNAMIC RESPONSE
BODY ATTITUDE
I
I
I
SENSORS
4
* BODY l
DYNAMICS SOLAR COLLECTOR
4 A POINTING
DISTURBANCE _,
ENVIRONMENT
GIMBAL
+ 1 MW ANTENNA b I
FIGURE SENSORS
3-27
Table 3.1-17. Attitude Control Requirements
PHOTO-
VOLTAIC
PARAMETER CR = 2
Y-POP
x-top
3-28
-- __..._..... _-..------ .._..-..,.,..
---~
3-29
Table 3.1-19. Stationkeeping RCS Requirements
Reaction Control System. The reaction control system (RCS) provides the
necessary forces and torques for attitude control and stationkeeping. For
the photovoltaic concept the RCS consists of four ion bombardment thruster
modules with 16 thrusters at each corner of the vehicle. The argon propellant
is stored cryogenically. A refrigeration system is ncess'ary to maintain the
cryogenic temperatures. The thruster characteristics are given in Table 3.1.20.
Major Assemblies
Figure 3.1-24 illustrates the major assemblies comprising the ACSS. The
description of each assembly, as applicable to the photovoltaic option, is
given in the preceding section.
Subsystem Interfaces
The primary interfaces are the IMCS, the power distribution and control
subsystem, and the structure. The IMCS, which functions as an integral part
of the ACSS, also provides the interface for the ground support system to the
ACSS. Figures 2.1-4 through 2.1-6 show the primary interfaces for the atti-
tube reference system, the MW antenna pointing system, and the tank and engine
system, respectively.
3-30
I 1
I
ATTITUDE CONTROL
6 STATION KEEPING
SUBSYSTEM
I
II
1
I I I I
ATTITUDE M. W. ANT.
FIG. REACTION PROPELLANT
DETERMINATION CONTROL SUPPLY
CONTROL : I
*FIG. SENSORS *THRUSTERS . TANKS
. FIG. ACTUATORS . DRIVE l LINES
1
C6LilMATORS *VALVES
. ELECTRONICS
I
(1)
r- -1 r--
i SECONDARY’
CRUCTUREA
--- -a-
. INSTALLATION l Al-T.
. TORQUERS DETERMINATION
*ANGLE SENSORS l FIG. CONTROL
3-31
Ta Le 3.141. Thermal Control Subsystem - Operating Modes
Xode I Assemblv I Cunccions ^" --I
I I .
'la-ntain ailcwable tempeiatl~re irveis
and gradients tc restrict structural
:onsfruccion 1 Subsystem 1
deformations/stresses and protect
assemblies. I
Gineain allowable temperature levels
:nter-Orbit Transfer Subsystem and gradients; power required opera-
tion phases. 1
Support steady-state operation for
)peracions Subsystam 1
all assemblies.
TEMP LEVELS
ANTENNA
d TEMP LEVELS
OPERATION
t
NORMAL
OPERATION ECLIPSE
PERTURgATIONT
ACTIVE WASTE
SHOV8RUSH HEAT REJECTION
TEMP LEMLS SYSTEM
STRucTUP.AL
THERMAL DIST
L TEMP LEVELS
CONVERSION PERTURBATIONS
CONDUCTOR
TEMP NORMAL OPERATIONS
3-32
KLSTRON COllECTOk
Major Assemblies
Design and performance data for the klystron radiators are presented in
Table 3.1-22.
3-33
THERMAL
SUBSYSTEM
------e--m--- 7
1
I I 1 ----A -w-m ‘I
r
POWER CONVERSION ANTENNA ROTARY I I
I RECTENNA
(PHoToVOLTAIC) SYSTEMS JOINT
IN-.----.- - - - 1
‘COATINGS l COATINGS . COATINGS l COATINGS
l SENSORS . INSULATION l SENSORS
. KLYSTRON HEAT PIPES
.FINNED CONTAINERS
FOR ELECTRONICS
. SENSORS
l HEATERS
(1)
------- 1
r
I SECONDARY 1
STRUCTURE -1
L ----m-e
. COATINGS
(I) MAJOR INTERFACE
!
Table 3.1-22. Klystron Cavity Radiators
(Slaximum Intensity Region)
Major Assemblies
Figure 3.1-31 identifies the major assemblies that form the IMCS. six
major assemblies have been identified at this time: (1) processors, (2) bus
control units (BCU), (3) data bus, (4) remote acquisition and control units
(RAC), (5) submultiplexers (SM), and (6) microprocessors (up).
3-35
Table 3.1-23. IMCS - Operating Modes
Assembiv runct1on \
Xode
Temperature monitor
Conrtluction Subsyse‘em Attitude monitor and control
Safety monitor
Power conversion and distrib.xtion
Nonitor and control
Navigation
Inter-Orbit Transportation Subsysteu Attitude monitor and control
Subsystem monitor
Configuration control
MW pointing, gimbal pointing
control
operations Subsystem Steady-state monitor and control
Eclipse monitor
Shutdown/startup monitor and
Eclipse Subsystem control
Subsystem standby monitor and
control
Orjentacion monitor
Transition Sobsys tern Subsystem monitor and control
Failure detection/isolation
Redundancy management
FaLlurelHaintenance Auto shutdown/restart
Override control
Kaintenance logging
Bus Control Unit. The bus control unit (BCU) provides the control neces-
sary for data/command transfer over the subsystem data bus network. The BCU
accepts instructions and data (or commands) from its associated processor and
translates these data from a processor-compatible format to one compatible with
the data network. It also accepts bus-compatible data and converts these data
to processor formats. In addition, the BCU monitors the data traffic--performing
bit and word checks as well as health/status checks.
Data Bus. The data bus network accommodates multiplexed, digital data
transmitted between the BCU and all other remotely located data acquisition and
contra1 devices associated with a specific processor/BCU combination. The bus
link may utilize conventional wire techniques for short runs in low EM1 areas
or fiber-optic technology for long paths or through high EM1 areas. Basic bit
rate within the bus assembly is assumed to be 1.0 Nbps. Included in the data
bus assembly are the data bus coupling devices used to connect the various
3-36
MASTER
CONIXOL
COMFulfR
Ku
10 OTHR
, slJrERvIsow
CoMNTfIS
c
MlaowLvl
*NltNN*
suffRvIsonY
COM;WCR
KU
I
c
huaow*vT
ANTINNA
COMnmR
Ku
I
MIaOWAVf
*NltNN*
COmFlJltR
x5J
!
3
l&P _ P
I 75
Ku 1 Ku
i
i
i
i
:I:
WTEl
DISPIA~
:
CmJnoL .- * AND
COMnllR
KU
CONlIOL Ii
cwm SfclIoN
I
LlGwmG- I
HXIIP*YNT ------ J
I r- ToorHm
II I stlmvlsoIY I
I I I CoMNlES
E
fOHR DlSl’RlblJlIoN ’ POWS DISRIUJllON
sUMMsoIY SUNRVISOW
I f
COYnJlR
KU
cohvu1n
‘Ku
r:
4
I
I I
i!
I I
i
I
I I . I I
KNEI c4SnlmJTloN fOWER DISlRIllJlION
CINtR RIGHT WING RICH1 WlNG i
CDHPulR COMRLIU‘2
KU \ KU I
i
i
I
BUS RLWJIE
PRuCESSOR CONTROL ACQUISITION
L CONTROL
11.x2
l H*IIDWARE -DATA WS *HARDWARE
- CPU COUPLER - CPU
- MEMORY l IRIDGE - MfMOKY
3740
remote units (one required per remote) as well as the bridge coupler required
to transfer data across the microwave antenna rotary joints; the latter
element is presently TBD.
Remote Acquisition and Control. The remote acquisition and control (UC)
assembly is the basic interface between the IMCS and the various operating sub-
systems. The RAC provides for data format conversion from the preconditioned
analog, digital or event voltage/impedance levels, and converts these data in-
to 8-big digital, serial, equivalents. The RAC also accepts digital data words
and outputs commands in a format compatible with the receiving subsystems.
The subsystem interfaces for the three major subsystems are indicated in
Figure 2.1-2 through 2.1-11. Table 3.1-26 summarizes the number of IMCS ele-
ments required for a typical photovoltaic configuration. Table 3.1-27 summa-
rizes the physical (weight, power, volume) requirements for this system.
3-41
Table 3.1-26. Hardware Summary
fUUCTlON -
‘ROTE
MASTER DISPLAY SUPER- IUS muIs.
HARDWARECONTROL AN0 VlSORY REnOTE HICRO- CONTROL AND
ELEMENT COMPUTER COnTROL SUJ-MUX.
SATELLITE 2 I m w - 2 - -
CONTROL
THERMAL - - m
CONTROL 2 5 7 a5 1.352
STRUCT. - I . - - -
ALIGN. 3 3
ATTITUDE I1 2a 148
CONTROL 1 10
POWill . I -
OISTRI6. 2 5 7 as
HI CROYAVE
ANTENNA c 1 14 777 792 787 29,500
CONTROL
_I ]
DISPLAY 6 CONTROL SET 1 200 206 0.9 0.) 0.72
SUPERVISORY COHPUTER 9 14 70 0.07 0.35 0.01
REMOTE COVPUTER 23 14 322 0.07 I 1.61 0.01
YlCROOROCESSOR 5 0.02 0.003
IUS CONTROL UNIT 1 5 150 0.02 0.6 0.005
RCM~~EACO~JISIT~ON~ CONTROL 1 ,l9l9 : 1 990 0.02 3 96 0.005 0.99
SUE ~ULTIPLEXOR L SO0 001 15.0 0 003 45
SUETJlAl 1 1.232 26.42 , 7.44
IOTATI!dG - --~
UAf7ER CONTROL COUPUTER I 2 0.4
DlSPLAY 6 CONTROL SET 09 0%
SUPERVISORY CO*.IPUTER I 1 0 07
REMOTE COVPUTER 1 14 0 07
MICRO PROCESSOR 111 0.02
BUS COSTAOL UYIT 792 0.02
REMOTE ACOUISITION 6 CONTROL 767 0.02
SUE VULTIPLEXOR
CABLE
YON~ROlATING-WIRE 122GAI 1.200 KM 12 O/KM 14.000
FIBER OPTICS ?9 KY 0.141KM 12
ROTAllnC-WIRE 23.000 KM 279,000
Fl6ER OPTICS 350 KM 50
to,., / 191000
3-42
3.2 GROUND RECEIVING STATION
STORAGE 6 MAINT.
ERTZ)
A --
KMX 13
A separate study activity, under task 2 of the primary SPS study, was
made to evaluate the system control requirements. The results of this latter
study is documented in Section 8.0, Volume V of the final report.
3.2.1 RECTEXNA
3-43
GROUND
RECEIVING
STATION
I I I I I
1
POWER
POWER THERMAL
RECTENNA DISTRIBUTION
CONVERSION CONTROL
AND CONTROL
DATA SAFETY
STRUCTURES COMMUNICATION MANAGEMENT AND
AND CONTROL SECURITY
I
I
r I I 1
ANTENNA RECTIFIERS REGULATORS SWITCHING
Major Assemblies
The major assemblies and components that are required for the rectenna
subsystem are shown in Figure 3.2-5.
3-44
Table 3.2-l. Rectenna Functional Requirements
'ROGRAMMATIC
ENERGY SOURCE - HICRO!4AVE AT 2.45 GHz
CAPACITY - 5 GW (NOIIIIIAL) DELIVERED TO ~tiz DISTRIBUTION NETWORK
LIFETIdE - 3G YEAAS WITH MlN;tll;M PLAHIIEC t’4 I’4TEN;rNCE
, (S:-IO!JLD CE CAPASLE CF EXTEE!DED LIFE BFYOND
30 YEARS WITH REPLACEMENT)
IOC DATE - 2000
OPERATIONS - ANYWHERE WITHIN OR IMHEDIATE~Y ADJACENT TO CONTINENTAL U.S.A.
RESOURCES - tllNlHUH USE OF CRITICAL RESC,?.,ES
COMt4ERClALlZATlON - COHPATl8LE WITH UNIT:: STATES UTILITY NETWORKS
DEVELOPHENT - EVOLUTIOZARY, WITH PROVISlC’.S FOR INCORPORATING LATER TECHNOLOGY
TECHNOLOGY
OUTPUT POWER-POWER LEVEL IS DEFINED AS C:‘;STANT POWER LEVEL (5 GU, MAX), EXCEPT DURING SOLAR
ECLIPSE
ENERGY STORAGE-NONE
FAILURE CRITERIA-NO SINGLE-POINT FAILURE “:Y CAUSE TOTAL LOSS OF SPS FUNCTION
ENERGY PAYBACK-LESS THAN THREE YEARS
COST-COMPETITIVE WITH HYDROCARBON OR HY::::LECTRIC POWER GENERATION CONCEPTS WITHIN LIFETIME
OF SPS PROJECT
9PERATION
MODE ASSEMBL'! FUNCTION
CONSTRUCTION SUBSYSTE” NONE
OPERATIONS SUBSYSTE’ STEADY-STATE OPERATION
OPEN ISOLATION SWITCHES
ECLIPSE SUBSYSTE”
CLOSE ISOLATION SWITCHES
FAI LURE,“fiH~TENANCE SUBSYSTE’ VOLTAGE CHECKS: SWITCH STATUS
CHECKOUT SUBSYSTE” FAIL-SAFE CHECKS; CONTROL RESPONSE
Regulators. The regulation assembly accepts the voltage from the series
.. . .. ._
connected rectenna diodes and adjusts the voltage output to the power distribu-
tion feeders to a value consistant with positive current flow.
3-45
Cu Clad
Mylar
Dielectric
The subsystem interfaces are shown in Figure 3.2-3. Details of the inter-
face are TBD.
The power distribution and control subsystem receives power from the
rectenna subsystem and provides the switching required to deliver the power
to the power conversion stations, and then delivers the power station outputs
3-46
Table 3.2-2. Rectenna Preliminary Specifications
I TER CHARACTERISTIC
Major Assemblies
Figure 3.2-7 illustrates the major assemblies comprising the power dis-
tribution and control subsystem.
3-47
L
96 DOUBLE BOXES
EA SECTOR
1M . CUBES
40,000 VDC BUSSES ISOLATION
\
3 EMSECTOR
\ ’
1088 ROWS
_------------------
FEEDER POWER (INPUT TO
40,ow VDC SUSSES) -
RANGE 12.1 - 16 MW AT
’ ‘W (300 - 400A) AS MANY FEEDERS
14.8 MW
AS REQUIRED TO
MASS IN QUADRANT (FEEDERSONLY) SO,ooO KG (200,~ KG FOR ENTIRE FARM) APPROACH 16 Mw
POWER
DISTRIBUTION
AND CONTROL
I I
I-
I
POWER SWITCHING I
DISTRIB, I
l- - ----
3-48
the rectenna array and continuing to the perimeter. The feeders are grouped
in each quadrant of the array to permit systematic maintenance and to avoid
catastropic system failures. The main feeders utilize TBD cm round aluminum
cables, uninsulated, mounted on insulated standoffs or in insulated raceways.
Other feeders, tie lines, buses, etc., are sized to handle maximum estimated
loads, at specified voltages. All cables are passively cooled by radiation
to local environment.
3-49
Design and Performance Characteristics
SECONDARY STRUCTURE
Mass TBD% of PDS weight was considered
to be required for mounting and
installat ion.
CONTROL
Temperature sensors No. of sensors config. dependent
Current sensors No. of sensors config. dependent
Voltage sensor‘5 No. of sensors config. dependent
Switch gear cor.trol conflguratfon dependent
Overcurrent
Overvoltage
Undercurrent
Undervol tage
Subsystem interfaces are shown in Figure 3.2-6 for the power distribution
subsystem approach selected for ground receiving station. Power handling cap-
acity is estimated to range up to 5.0 Gtl.
3.2.3 STRUCTURES
The GPS structure assemblies considered in this report are primarily those
associated with the support of the rectenna panels, plus the secondary elements
already discussed in Section 3.2.2. Included in this subsystem are concrete
footing, steel primary and secondary support structure, bracing and the various
3-50
connection fittings. A more detailed description of the installation activ-
ities and procedures is presented in Volume V of this report.
3-51
Major Assemblies
STRUCTURES
PANEL SECONDARY
FACILITIES
SUPPORT STRUCTURE
Design Characteristics
The initial design for the panel structural and base support elements
are illustrated in Figure 3.2-10.
’ NOT TO SCALE
3-52
3.2.4 CONVERTER STATIONS
-w
4 4
I I
I
- I
- CONTROL - - - - - _ - _ - -I
Specific design details of this subsystem was not derived during the
preceeding study and must await clarification in a future study effort.
The data management and control hierarchy for the ground complex is out-
lined in Figure 3.2-12. The primary approach, pyramidal, is similar to that
selected for the satellite. Similar, but not necessarily space qualified,
devices would be used to implement the ground data system. A description of
the various devices is given in Section 3.1.7.
3-53
I
Group A I Group C
Equipment Equipment
I
T
SUPERVISORY SUPERVISORY I SUPERVISORY
I
------l’ L
I I I I1
I
I
I I
BEAM
I
i UTILITY
INTERFACE I
BEAM
MONI TOR MONI TOR
I CONTROL
COtiPUTER COIIPUTER
COHPUTER I
A I I
I I
PERIHETER E INTRUSION PERI METER
MONITOR
I
HONITOR I MONITOR
NO. I COMPUTER NO. 2
COMPUTER BCU I COHPUTER
I
I I
L
1 1 I I r I 1 1
1
I I I 1 I I 1 -I 1
THERMAL THERMAL THERMAL THERMAL THERMAL
GROUP A GROUP A I GROUP C I GROUP B GROUP B
COMPUTER I COMPUTER 2 COMPUTER COMPUTER 2 COtiPUTER I
BCU I BCU
KU BCU BCU
I I
Figure 3.2-12. IMCS Hierarchy - Ground Receiving Station
-
The PLV is used to transfer the SPS construction crew from earth to LEO.
This vehicle is a growth Shuttle version in which the solid rocket booster
(SRB) is replaced with a reusable liquid rocket booster (LRB). The PM is
designed to fit within the existing orbiter cargo bay.
The EOTV is employed for cargo transfer from LEO to GEO, and utilizes the
same power sources and construction techniques as the SPS. The configuration,
payload capability, and trip time are established on the basis of overall SPS
program compatibility.
4-l
The POTV is the propulsive element required to transfer the PM and its
crew/passengers from LEO to GEO. The POTV is a single, chemical rocket stage
and is sized to fit within the cargo bay and payload capability of the PLV.
4-2
Transportation system GE0 operations are depicted in Figure 4.3-2. Upon
arrival at GEO, the SPS construction cargo is transferred from the EOTV to the
SPS construction base by IOTV. The POTV with crew module docks to the con-
struction base to effect crew transfer and POTV refueling for return flight to
LEO. Crew consumables and resupply propellants are also transported to GE0
by the EOTV.
4-3
Table 4.3-l. TFU Transportation Requirements
SATELLITECONST.MAINl. 8
PACKAGING 37,12 37012 45 163.5 45 6.5 164 164
CREWCONSUMABLES
8 PKG, 0,98 0.94 4.3 0,2 4 4
POTVPROPELLANTS
8 PKG, 2.91 1.46 12,8 0,3 13 6
EOTVCONST,, MAINT, 8 PKG, 7020 - 15 31.7 32
EOTVPROPELLANTS
8 PKG. 4.79 - 21.1 21
IOTV PROPELLANTS
8 PKG. 0.13 0,06 046 1
-- - ,- 235
TOiAL 53813 39,58 60 234-O
VEHICLEREQUIREMENTS
TFU FLEET 2 15 14 6 4
CARGO CARRIER/ENGINE
GROWTH
SHUTTLEVEHICLES- PERSONNEL (PLV) MODULE AND LAUNCH VEH
PRECURSO:
REQUIREMENTS:
*LEO BASE
*SPACE CONSTR, BASE 72 FLIGHTS 129 FLIGHTS
l EOTV TEST VEHICLE
1 VEHICLE ~. ~. 2 VEHICLESm.-.-
4-4
Table 4.3-3. Totdl Transportation Requirements, 60-Year Prog.ram
I i,
MASS x IO6 KG I VEHICLE FLIGHTS r ll
POTV EOTV IOTV
LEO 1 GE0
SATELLITE
CONSTRUCTION 1220 425.1 9682 9682
OPERATIONS& YAINTENANCE 3660 348.7 7943 7943
CREWCONSUMABLES
CONSTRUCTION 139 c 5.6 139 126
OPERATIONS& YAINTENANCE 86.8 86.0 - / 382 - 16.6 382 379
POTV PROPELLANTS I
CONS'lWJCTION 82.7 41.4 - 364 - 8.0 364 182
OPERATIONS& MAINTENANCE 267.6 133.8 - 1180 - 25.9 1180 589
EOTV CONSTRUCTION
CONSTRUCTION 28.2 24.2 - 124. - 4.7 124 107
OPERATIONS& MAINTENANCE 22.2 19.0 - 98; - 3.7 98 84
EOTV PROPELLANTS
CONSTRUCTION 340.3 2.0 - 1499 - 0.4 1499
OPERATIONS& MAINTENANCE 304.0 - - 1339 - 1339 -g
IOTV PROPELLANTS
CONS'I'RlJCTION 7.2 3.3 - 32 - 0.6 32 15
OPERATIONSLlrMAINTENANCE 6.6 3.0 - 29 - 0.6 29 13
SUMMARY
CONSTRUCTION 2687.7 2297.4 1340 11,640 1220 444 11,840 lQ121
OPERATIONS& MAINTENANCE
-P-.--L. 2490 4 20.14.tj 3694 10971 3660 396 10,971 9,008
TOTAl. 5178.1 4342. 2 5034 22p1 1 4H80 840 22,811 19,129
VEllIC1.E FIJXT
C0NSTItUCFION 14 39 12 22 110
--A-- Ol'l~llA'I'IONS k LIAINTF:NANCI:
-_ __-_-___. - 37 37 :17 2n IOn
TWAI, !i I 7(i *I!) 42 2I0
4.3.2 HEAVY-LIFT LAUNCH VEHICLE (HLLV)
The HLLV utilizes a parallel burn mode with propellant cross-feed from
the first-stage tanks to the second-stage engines. The first stage employs
high chamber pressure gas generator cycle LOX/HP fueled engines with LHz
cooling and the second stage employs a staged combustion engine similar to
the Space Shuttle main engine (SSME) which is LOXjLHz fueled.
4-7
.
*CROSS FEED, DUAL DELTA
DRY WING, L/D -7.5
RP.1 TANK
ROCKET ENGINES. 7 REQ’D
TOTAL THRUST. 71.441.9~33 N(S.L,
AIR BREATHER
FLYBACK
ENGINES - 8 fwaa
4-8
Table 4.3-7. HLLV Propellant Weight Summary
(X106)
-I- ~~FIRS STAGE SECOH STAGE
A KG LB KG
12.900 DIA
4-9
The cargo bay is located in the mid-fuselage and has a length of approxi-
mately 90 feet. The detailed weight statement and a propellent summary for the
orbiter are included in Tables 4.3-6 and 4.3-7, respectively.
The EOTV depicted in Figure 4.3-6 is based upon a rigid design which can
accommodate two "standard" solar blanket areas of 600.m by 750 m from the
MSFC/Rockwell baseline satellite concept. The commonality of the structural
configuration and construction processes with the satellite design is noted.
Since the thrust levels will be very low (as compared to chemical stages), the
engines and power processing units are mounted in four arrays at the lower
corners of the structure/solar array. Each array contains 36 thrusters; however,
only 64 thrusters are required to fire simultaneously. The additional thrusters
provide redundancy when one or more arrays cannot be operated due to plume
impingement on the solar array. Up to 16 thrusters, utilizing stored electrical
power, are used for attitude hold only during periods of occultation. The atti-
tude determination system is the same as the SPS, mounted at the extremities of
the six vertical beams. Payload attach platforms are located so that loading/
unloading operations can be conducted from "outside" the lightweight structure.
4-10
Primary EOTV requirements are summarized in Table 4.3-8. The orbital
parameters are consistent with SPS requirements and the delta-V requirement
is taken from previous SEP and EOTV trajectory calculations. A 0.75% delta-V
margin is included in the figure given.
Table 4.3-8. EOTV Sizing Requirements
The solar array has a total power output of 33.5 megawatts. Line losses
of 6% and an end-of-life cell degradation of 15% yield a net power to the
thruster arrays of 268.1 megawatts. The power storage system is sized on the
same basis as the SPS, 200 kilowatt-hours per kilogram weight.
The PLV and STS-derived HLLV are growth versions of the Shuttle transporta-
tion system (STS). The growth version of the PLV, Figure 4.3-7, is achieved by
replacing the existing recoverable solid rocket boosters (SRB) with a pair of
recoverable liquid rocket boosters (LRB). The existing orbiter and external
tank are used in their current configuration. The added performance afforded
by the LRB increases the orbiter payload capability to the reference STS orbit
by approximately 54%, or a total capability of 45,350 kg (100,000 lb).
The LRB has a gross weight of 395,000 kg, made up of 324,000 kg of propel-
lant (278,000 kg of LO2 and 46,000 kg of LHz), and 71,000 kg of inert weight.
The overall length of the LRB is 47.55 meters with a nominal diameter of
6.1 meters.
4-12
8oosTm (EACH):
Glass UT n 87lU LI
PROP. UT - 7lSK 18
IHERl YT = 1561: LB
LAlJttCHCONFlGURATlON
PAVLOAO l IOOK LB tLOY‘= 3.6761 LO
I56 FT.
-1
t0.U Fl WA
1
\LANOIffi ROCKETS
\ KS
LIFTOFF WEIGHTS
(lo3 kg)
PAYLOAD 100.0
EXTENALTANK 738.3
LRB (2) 790.0
REUSABLEPOD 13.7
TOTAL 1642.0
The POTV is the propulsive element used to transfer the personnel module
(PM) from LEO to GE0 and return. The POTV concept uses a single stage to trans-
port the PM and its crew and passengers to GEO. After initial delivery of the
POTV to LEO by the STS or SPS-HLLV, the propulsive stage is subsequently refueled
in LEO (at the LEO station) with sufficient propellants to execute the transfer
of the PM to GEO. At GEO, the stage is refueled for a return trip of crew and
passengers to LEO. The HLLV delivers crew consumables and POTV propellants to
LEO and the EOTV delivers the same items required in GEO. The PM with crew/
personnel is delivered to LEO by the PLV.
The POTV utilizes two advanced space engines whose characteristics are
given in Figure 4.3-11 and Table 4.3-12.
4-15
2ASE
ENGINES
a-
4-16
THRUST (LB) 20,000
LENGTH (IN.)
4-17
4.3.6 PERSONNEL MODULE (PM)
4-18
4.4 LEO OPERATIONAL BASE
(TBD)
(TBD)
(TBD)
4-19
1. Report No. 2. Government Accuion No. 3. Recipient’8 Catalog No.
NASA CR-3324
4. Title and Subwle 5. Repon Date
September 1980
SATELLITE POWER SYSTEMS (SPS) CONCEPT DEFINITION STUDY
6. Performing Organization Code
VOLUME VII - SYSTm/SUBSYSTEM REQUIREMENTS DATA BOOK