Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 28200m
S.No. Description Unit
1 CD No. = 1
2 Chainage = 28200 m
3 Catchment Area (M) = 0.075 sqkm
4 Q from Dicken Formula (C=17) = 2.440 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 121.595 m
7 Bed Level = 119.745 m
8 FRL-BL Diff. = 1.850 m
9 Top of Water Level = 120.745 m
10 Top of Pipe = 120.860 m
11 FRL - Top Diff. = 0.735 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
Project Manager
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 31800m
S.No. Description Unit
1 CD No. = 2
2 Chainage = 31800 m
3 Catchment Area (M) = 0.077 sqkm
4 Q from Dicken Formula (C=17) = 2.480 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 130.370 m
7 Bed Level = 128.420 m
8 FRL-BL Diff. = 1.950 m
9 Top of Water Level = 129.420 m
10 Top of Pipe = 129.535 m
11 FRL - Top Diff. = 0.835 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
Project Manager
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 44400m
S.No. Description Unit
1 CD No. = 3
2 Chainage = 44400 m
3 Catchment Area (M) = 0.740 sqkm
4 Q from Dicken Formula (C=17) = 2.410 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 126.610 m
7 Bed Level = 124.820 m
8 FRL-BL Diff. = 1.790 m
9 Top of Water Level = 125.820 m
10 Top of Pipe = 125.935 m
11 FRL - Top Diff. = 0.675 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
Project Manager
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 56400m
S.No. Description Unit
1 CD No. = 3
2 Chainage = 56400 m
3 Catchment Area (M) = 0.080 sqkm
4 Q from Dicken Formula (C=17) = 2.560 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 121.290 m
7 Bed Level = 119.310 m
8 FRL-BL Diff. = 1.980 m
9 Top of Water Level = 120.310 m
10 Top of Pipe = 120.425 m
11 FRL - Top Diff. = 0.865 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
Project Manager
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 36200m
S.No. Description Unit
1 CD No. = 5
2 Chainage = 36200 m
3 Catchment Area (M) = 0.072 sqkm
4 Q from Dicken Formula (C=17) = 2.360 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 134.490 m
7 Bed Level = 132.610 m
8 FRL-BL Diff. = 1.880 m
9 Top of Water Level = 133.610 m
10 Top of Pipe = 133.725 m
11 FRL - Top Diff. = 0.765 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 46600m
S.No. Description Unit
1 CD No. = 6
2 Chainage = 46600 m
3 Catchment Area (M) = 0.074 sqkm
4 Q from Dicken Formula (C=17) = 2.410 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 123.070 m
7 Bed Level = 121.250 m
8 FRL-BL Diff. = 1.820 m
9 Top of Water Level = 122.250 m
10 Top of Pipe = 122.365 m
11 FRL - Top Diff. = 0.705 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 50600m
S.No. Description Unit
1 CD No. = 7
2 Chainage = 50600 m
3 Catchment Area (M) = 0.078 sqkm
4 Q from Dicken Formula (C=17) = 2.510 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 119.555 m
7 Bed Level = 117.665 m
8 FRL-BL Diff. = 1.890 m
9 Top of Water Level = 118.665 m
10 Top of Pipe = 118.780 m
11 FRL - Top Diff. = 0.775 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
RajaRam Construction
Balaghat
Hydraulic Calculation For Cross drainage Works
Name of road :- Rajegaon-Kirnapur-Lanji-Amgaon Road
Chainage :- 58400m
S.No. Description Unit
1 CD No. = 7
2 Chainage = 58400 m
3 Catchment Area (M) = 0.076 sqkm
4 Q from Dicken Formula (C=17) = 2.460 cumecs
5 Dia of pipe D = 1.000 m
6 Formation Level = 122.760 m
7 Bed Level = 120.880 m
8 FRL-BL Diff. = 1.880 m
9 Top of Water Level = 121.880 m
10 Top of Pipe = 121.995 m
11 FRL - Top Diff. = 0.765 m
12 Length of Culvert = 7.50 m
13 Hydraulic Radius (R=Area/Perimeter) = 0.25 m
Ke = 1.107*R^0.5
14 = 0.5535 m
= 1.107*0.25^0.50
Kf = 0.00394*L/R^0.10
15 = 0.156 m
= 0.00394*7.5/0.25^0.10
16 Head H = 1.00 m
V=Sqrt (2gh)/(1+Ke+Kf)
17 =Sqrt (2x9.81x1)/(1+0.5535+0.156) = 3.39 m
Discharge Though one Pipe at HFL
18 = 2.66 m
condition
19 Type of C.D. Proposed = 1.00 m
20 Allowable Discharge through the culvert = 2.66x1 = 2.66 m
21 Remarks = ok m
Sub Engineer Sub Divisional Officer Executive Engineer
PWD Sub Div. Balaghat PWD Sub Div. Balaghat PWD Div. Balaghat
RajaRam Construction
Balaghat
Design crossing on Rajegaon-Kirnapur-Lanji-Amgaon Road
of Slab Culvert 2.0 x 2.0 m Single Span Slab Culvert
Crossing :- Km 31/400
1 Design Parameters
Chainage = 31400 m
Difference in HFL & Bed Level = 1.460 m
Catchment Area (A) = 0.255 sqkm
(Clause 3.2 SP-13
15.00 m
Coefficient of Run off © = Clause -4.9)
Percentage Coefficient of Run off For The
Catchment Characteristics (P) = 0.600 m Table 2 SP-13
Distance From the Critical Point to The
Culvert in KM (L) = 1.000 Km
Fall in Level From Critical Point to The
Culvert in M (H) = 6.000 m
Time of Concentration (tc)
tc = (0.87 x L^3/H)^0.385 = 0.475 Hr. (Clause 4.7 SP-13)
Rainfall in cm = 15.000 Cm
Time in = 0.500 Hr.
Critical Intensity of rainfall in cm per hr.(Ic) = 30.500 cm/hr (Clause 4.7 SP-13)
Silt Factor(f) = 1.000 Table 4 SP-13
2 Calculation of Run Off
By Dicken's Formula :-
Q = C*( A )3/4 = 5.38 cumecs
By Emprical Formula :-
Q = 0.028*P*A*Ic*100 = 13.066 cumecs
Design Discharge
Conveyance factor (ƛ) for slab Culvert (Clause 7.1 SP-13)
(ƛ) = A/(1+ke+kf)^(1/2)
Chainage = 31400 m
(as per IRC SP-13
Slab Culvert of 2 x 2 m opening = 3.219
article 22)
3 Discharge through slab culvert
(as per IRC SP-13
Qp = ƛ (2gH)^(1/2)
article 22)
where, H = (HFL-Bed Level of nala-free
Board) in meter
Slab Culvert of 2 x 2 m opening = 15.342 Cumecs
No. of opening = 1.000
Discharge through 1 opening = 15.342 Cumecs
Provide Slab Culvert of 2 x 2 m opening
4 Scour depth
D = 0.0473*Q^(1/3)/f^(1/3) = 1.175 m
Scour depth = 1.200 m
Depth of foundation adopted = 2.000 m
therefore depth of information is safe
Design crossing on Rajegaon-Kirnapur-Lanji-Amgaon Road
of Slab Culvert 2.0 x 2.0 m Single Span Slab Culvert
Crossing :- Km 45/400
1 Design Parameters
Chainage = 45400 m
Difference in HFL & Bed Level = 1.470 m
0.247 sqkm
Catchment Area (A) =
(Clause 3.2 SP-13
15.00 m
Coefficient of Run off © = Clause -4.9)
Percentage Coefficient of Run off For The
Catchment Characteristics (P) = 0.600 m Table 2 SP-13
Distance From the Critical Point to The
Culvert in KM (L) = 1.200 Km
Fall in Level From Critical Point to The
Culvert in M (H) = 6.000 m
Time of Concentration (tc)
(Clause 4.7 SP-13)
tc = (0.87 x L^3/H)^0.385 = 0.587 Hr.
Rainfall in cm = 15.000 Cm
Time in = 0.500 Hr.
(Clause 4.7 SP-13)
Critical Intensity of rainfall in cm per hr.(Ic) = 28.400 cm/hr
Silt Factor(f) = 1.000 Table 4 SP-13
2 Calculation of Run Off
By Dicken's Formula :-
Q = C*( A )3/4 = 5.255 cumecs
By Emprical Formula :-
Q = 0.028*P*A*Ic*100
= 11.767 cumecs
Design Discharge
Conveyance factor (ƛ) for slab Culvert (Clause 7.1 SP-13)
(ƛ) = A/(1+ke+kf)^(1/2)
Chainage = 45400 m
(as per IRC SP-13
Slab Culvert of 2 x 2 m opening = 3.219
article 22)
3 Discharge through slab culvert
(as per IRC SP-13
Qp = ƛ (2gH)^(1/2)
where, H = (HFL-Bed Level of nala-free article 22)
Board) in meter
Slab Culvert of 2 x 2 m opening = 15.395 Cumecs
No. of opening = 1.000
Discharge through 1 opening = 15.395 Cumecs
Provide Slab Culvert of 2 x 2 m opening
4 Scour depth
D = 0.0473*Q^(1/3)/f^(1/3) = 1.175 m
Scour depth = 1.200 m
Depth of foundation adopted = 2.000 m
therefore depth of information is safe
Design crossing on Rajegaon-Kirnapur-Lanji-Amgaon Road
of Slab Culvert 2.0 x 2.0 m Single Span Slab Culvert
Crossing :- Km 46/400
1 Design Parameters
Chainage = 46400 m
Difference in HFL & Bed Level = 1.450 m
Catchment Area (A) = 0.258 sqkm
(Clause 3.2 SP-13
Coefficient Coefficient
Percentage of Run off © of Run off For The = 15.00 m
Clause -4.9)
Catchment Characteristics
Distance From the Critical (P)
Point to The = 0.600 m Table 2 SP-13
Culvert in KM
Fall in Level (L) Critical Point to The
From = 1.300 Km
Culvert in M (H) = 6.000 m
Time of Concentration (tc)
tc = (0.87 x L^3/H)^0.385 = 0.644 Hr. (Clause 4.7 SP-13)
Rainfall in cm = 15.000 Cm
Time in = 0.500 Hr.
Critical Intensity of rainfall in cm per hr.(Ic) = 27.400 cm/hr (Clause 4.7 SP-13)
Silt Factor(f) = 1.000 Table 4 SP-13
2 Calculation of Run Off
By Dicken's Formula :-
Q = C*( A )3/4 = 5.43 cumecs
By Emprical Formula :-
Q = 0.028*P*A*Ic*100 = 11.866 cumecs
Design Discharge
Conveyance factor (ƛ) for slab Culvert (Clause 7.1 SP-13)
(ƛ) = A/(1+ke+kf)^(1/2)
Chainage = 46400 m
(as per IRC SP-13
Slab Culvert of 2 x 2 m opening = 3.219
article 22)
3 Discharge through slab culvert
(as per IRC SP-13
Qp = ƛ (2gH)^(1/2)
where, H = (HFL-Bed Level of nala-free article 22)
Board) in meter
Slab Culvert of 2 x 2 m opening = 15.290 Cumecs
No. of opening = 1.000
Discharge through 1 opening = 15.290 Cumecs
Provide Slab Culvert of 2 x 2 m opening
4 Scour depth
D = 0.0473*Q^(1/3)/f^(1/3) = 1.174 m
Scour depth = 1.200 m
Depth of foundation adopted = 2.000 m
therefore depth of information is safe
Design crossing on Rajegaon-Kirnapur-Lanji-Amgaon Road
of Slab Culvert 2.0 x 2.0 m Single Span Slab Culvert
Crossing :- Km 50/800
1 Design Parameters
Chainage = 50800 m
Difference in HFL & Bed Level = 1.480 m
Catchment Area (A) = 0.260 sqkm
(Clause 3.2 SP-13
Coefficient Coefficient
Percentage of Run off © of Run off For The = 15.00 m
Clause -4.9)
Catchment Characteristics
Distance From the Critical (P)
Point to The = 0.600 m Table 2 SP-13
Culvert
Fall in KM
in Level (L) Critical Point to The
From = 1.500 Km
Culvert in M (H) = 6.000 m
Time of Concentration (tc)
tc = (0.87 x L^3/H)^0.385 = 0.759 Hr. (Clause 4.7 SP-13)
Rainfall in cm = 15.000 Cm
Time in = 0.500 Hr.
Critical Intensity of rainfall in cm per hr.(Ic) = 25.600 cm/hr (Clause 4.7 SP-13)
Silt Factor(f) = 1.000 Table 4 SP-13
2 Calculation of Run Off
By Dicken's Formula :-
Q = C*( A )3/4 = 5.462 cumecs
By Emprical Formula :-
Q = 0.028*P*A*Ic*100 = 11.172 cumecs
Design Discharge
Conveyance factor (ƛ) for slab Culvert (Clause 7.1 SP-13)
(ƛ) = A/(1+ke+kf)^(1/2)
Chainage = 50800 m
(as per IRC SP-13
Slab Culvert of 2 x 2 m opening = 3.219
article 22)
3 Discharge through slab culvert
(as per IRC SP-13
Qp = ƛ (2gH)^(1/2)
article 22)
where, H = (HFL-Bed Level of nala-free
Board) in meter
Slab Culvert of 2 x 2 m opening = 15.447 Cumecs
No. of opening = 1.000
Discharge through 1 opening = 15.447 Cumecs
Provide Slab Culvert of 2 x 2 m opening
4 Scour depth
D = 0.0473*Q^(1/3)/f^(1/3) = 1.178 m
Scour depth = 1.200 m
Depth of foundation adopted = 2.000 m
therefore depth of information is safe