2020-03a - Kiln Shut Down PDF

1. This document outlines the major activities to be completed during a kiln shutdown from March 1-28, 2020 at a cement plant. 2. The activities are divided into multiple systems and include maintenance tasks like installing new equipment, cleaning, inspections, and addressing outstanding issues from punch lists. 3. Over 40 individual tasks are scheduled with assigned teams and durations specified to ensure all work is completed during the allotted shutdown window.

Uploaded by

hiddenhidden16
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
99 views1 page

2020-03a - Kiln Shut Down PDF

1. This document outlines the major activities to be completed during a kiln shutdown from March 1-28, 2020 at a cement plant. 2. The activities are divided into multiple systems and include maintenance tasks like installing new equipment, cleaning, inspections, and addressing outstanding issues from punch lists. 3. Over 40 individual tasks are scheduled with assigned teams and durations specified to ensure all work is completed during the allotted shutdown window.

Uploaded by

hiddenhidden16
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Kiln Shut Down-Major Activities Date: 01.03.

20
23075340-91/92 YSCC - New Plant, 2 x 10.000 tpd Cement Plant
D000661 & D000662 YamamaCement Line 1 + Line 2
ID Activity Start End Resp. Supv WorkersDuration

March 2020
02 Mar '20 09 Mar '20 16 Mar '20 23 Mar '20
S M T W T F S S M T W T F S S M T W T F S S M T W T F
1 KILN SHUT DOWN-Major Activities to Execute Sun 01-03-20 Sat 28-03-20 28 d?
2 SYSTEM 2 Mon 02-03-20 Sun 22-03-20 21 d
3 Crushing limestone for cement production Mon 02-03-20 Thu 05-03-20 TK/YCC Ralph 4d
4 2D1 Installation of dummies Mon 09-03-20 Wed 11-03-20 TK P.Bosse 3d
5 Installation of cylinder for lifting belt 2D1.BC02 Fri 06-03-20 Sat 07-03-20 MCC5 Ali 3 2d
6 Installation of new double lip sealing for 2E1.BC05 Fri 13-03-20 Sun 15-03-20 MCC5 Ali 3 3d
7 Installation of impact table for 2E1.BC05 (Design+fabrication+installation) Fri 20-03-20 Fri 20-03-20 TK Ali 0d 20-03
8 Installation of new drive for the stacker belt in 2G1 Mon 16-03-20 Tue 17-03-20 MCC5 Ali 3 2d
9 Installation of pulley main drive in 2D2 Wed 11-03-20 Sun 15-03-20 MCC5 P.Bosse 3d
10 Installation of panel for air compressor in 2D2 Wed 04-03-20 Thu 05-03-20 TK Manju 2d
11 Installation of holders for the apron conveyor 2D2.AY01 Mon 09-03-20 Sun 15-03-20 MCC5 P.Bosse 7d
12 Checking of the reclaimer in 2L1 Wed 04-03-20 Tue 10-03-20 TK Ali 7d
13 Closing of punch list points Mon 02-03-20 Sun 22-03-20 TK/MCC5Dieter 21 d
14 SYSTEM 3 Mon 02-03-20 Sun 22-03-20 21 d
15 3F1/3F2 cleaning the system and retightening of the bolts Mon 02-03-20 Thu 05-03-20 YCC Ali 4d
16 Installation of new double lip sealings in 3C1.BC01 and 3C1.AY01 Mon 09-03-20 Tue 10-03-20 MCC5 Ali 3 2d
17 Installation of additional roller station for 3C1.BC01 Wed 11-03-20 Thu 12-03-20 MCC5 Ali 3 2d
18 Inspection of 3F1/3F2 Mon 02-03-20 Wed 04-03-20 YCC Ralph 3d
19 Checking of the equipments of magnetic separator Mon 02-03-20 Thu 05-03-20 TK Khalid 4d
20 Closing of punch list points Mon 02-03-20 Sun 22-03-20 TK/MCC5Dieter 21 d
21 SYSTEM 4 Mon 02-03-20 Sat 28-03-20 27 d?
22 Cleaning and sealing repair the kiln inlet Wed 04-03-20 Fri 13-03-20 TK S.Tosta 10 d
23 Checking the tertiary air duct Auma drive Wed 04-03-20 Fri 13-03-20 TK/MCC5KK/S.Tosta 10 d
24 Blower of kiln camera - Over heating Thu 05-03-20 Sun 08-03-20 TK KK 4d
25 Vibrations of the calciner fan - 3rd party balancing Sun 08-03-20 Sat 28-03-20 TK Uwe 3w
26 Kiln Roller Stn - Water pipes leakage Wed 04-03-20 Fri 06-03-20 TK Derry 3d
27 Kiln feed PFISTER calibration Wed 04-03-20 Fri 06-03-20 TK Erick/Tamas 3d
28 Checking the tension of the chain in 4S1 Sun 08-03-20 Wed 11-03-20 YCC S.Tosta 4d
29 Checking the sealing of all inspection doors in the preheater Wed 04-03-20 Tue 17-03-20 TK Erick/Tamas 14 d
30 Preheater & Cooler Inspection Wed 04-03-20 Sat 07-03-20 TK Erick/Tamas 4 d?
31 Sealing of the Cooler aerated chambers Sat 14-03-20 Sun 15-03-20 TK Dieter 2d
32 Bolt Tightening of the belt of the bucket elevators 4C1.BE01 & BE02 Wed 04-03-20 Tue 10-03-20 YCC S.Tosta 7d
33 Change the girth grease in the kiln Wed 04-03-20 Tue 10-03-20 YCC S.Tosta 7d
34 Checking the temperature of the motor in 4S1.FN01 Tue 03-03-20 Thu 05-03-20 TK Erick/Tamas 3d
35 Kiln Outlet Ventilation Duct touching Kiln Shell Wed 04-03-20 Fri 13-03-20 MCC5 S.Tosta 3 10 d
36 Closing of punch list points Mon 02-03-20 Sun 22-03-20 TK/MCC5Dieter 21 d
37 SYSTEM U Sun 01-03-20 Sat 28-03-20 28 d
38 RO System PVC T-Joint Sun 01-03-20 Mon 02-03-20 TK Afifi 2d
39 Flow Meter installation Mech/Elec Wed 04-03-20 Wed 04-03-20 TK Derry/Manju 2 1d
40 Biocide Inhibitor relocation Mech/Elec Tue 03-03-20 Fri 06-03-20 TK/MCC5Derry/Manju EL-2 (1d) 4d
41 UW4.RU01.PMP02 - Reinstall Damaged Pump Tue 10-03-20 Tue 10-03-20 TK Derry 1d
42 Gravel Filter - New filtration media & nozzles Wed 04-03-20 Sun 15-03-20 TK Derry/Afifi 12 d
43 NALCO - Flushing Pipeline Mon 09-03-20 Sat 28-03-20 TK Afifi 20 d
44 Cooling Tower Access Platform for Impeller Motor Mon 09-03-20 Sat 28-03-20 TK Afifi 20 d