Construction Method Drainage
Construction Method Drainage
pgn
lOR NO· LNGC-TAS-IDR-0140
<<< >> <:> : : <~ ~ ::.:::.::::~ ~ :: ><< < ·>:<•>:::.: •• iNJTiA~ :<< : :SrAru~ >> . bAtE: . >6A:i6> cbMM~Nts .·. . iNil"I~L{. > .
N9·r · • >• • • ·: <>>>: > ••••·•··•·•••:>•••••••••• ·• · < )NF() > P.ci:rJ9N >1N<<<<: : our:< :: YIN < <> si<3f\l1\t0Re: ·
Construction Manager LKS V
2 Dep. Construction Manager ADF V
3 Project Control Manager
4 QA I QC Manager
~ A -
"~ 7fi - lu
0 Issued for Implementation 21/11/2013 BS/AP 7 FAR F~ V(sl ..,. EML JHS
c Re-Issued for Approval 22/1 0/2013 BS/AP FAR ISL EML JHS
1
B Issued for Approval 14/06/2013 BS/AP FAR ISL EML JHS
A Issued for Review 12/02/2013 BS/AP FAR ISL EML JHS
PREP'D CHK'D APP'D
REV DESCRIPTIONS DATE TAS PGN
HOEGH - REKIND
pgn
~ PGAS SOLUTION
HOEGH LNG REI<I>ri\SI
HOEG H LNG- REKIND CONSORTIUM
TECHNICAL ASSISTANT SERVICES CONSOR TI UM OF HOEG H LNG LTD AND PT REKAYASA INOUS TRI
•
Item 3.9 Revise Backfilling and Compaction Work
--·c·-·-··-·-- ·---2
-::-c2::-:-/1·.--o:-,=-=2~
0..,.,
13:c-·--+-=R=-e--,-
-ls-s- ued for Approval
· - - - - - - - - - -· · · · - - - - · - -
PGAS SOLUTION
HOEGH LNG RE KAYM•
TABLE OF CONTENT
1. GENERAL .................................................................................................................................................4
1.1. SCOPE ..............................................................................................................................................4
1.2. DEFINITIONS ..................................................................................................................................... 4
2. REFERENCE SPECIFICATION ................................................................................................................ 4
2.1. STANDARD SPECIFICATION .......................................................................................................... 4
2.2. DOCUMENT DRAWINGS ................................................................................................................. 5
3. SCOPE OF WORK .................................................................................................................................... 5
3.1. PREPARATION ................................................................................................................................ 5
3.2. SETTING OUT .................................................................................................................................. 6
3.3. EXCAVATION AND COMPACTION WORK .................................................................................... 6
3.4. LEVELING CONCRETE ................................................................................................................... 6
3.5. INSTALLATION OF CULVERT ........................................................................................................6
3.6. INSTALLATION OF PIPE CULVERT ............................................................................................... ?
3.7. SEWERAGE INSTALLATION .......................................................................................................... ?
3.8. STONE MASONRY FOR OPEN DRAINAGE STRUCTURE ............................................................ ?
3.9. BACKFILLING & COMPACTION WORK ......................................................................................... 7
APPENDIX ................................................................................................................•..................................... 9
JOB SAFETY ANALYSIS FORM .............................................................................................................. 9
PGAS SOLUTION
HOEGH LNG ' IIAYASA
1. GENERAL
1.1. Scope
This method procedure covers general requirement for sewer and drainage construction and relevant items to
be performed for EPCIC of the Pipeline System for Lampung LNG Floating Storage and Regasification
Facilities Project owned by PT Perusahan Gas Negara (Persero) Tbk., on Labuhan Maringgai, Lampung ,
Indonesia.
1.2. Definitions
The following words shall have the meaning indicated when used herein:
PGN PT Perusahaan Gas Negara (Persero) Tbk
ASSISTANT Technical assistant who is assigned to assist Client (PGN) during this Project to
advice or service provide all or a specified part of the work or material required
PROJECT EPCIC of the Pipeline System for Lampung LNG Floating Storage and
Regasification Facilities
CONTRACTOR PT REKAYASA INDUSTRI
SUB-CONTRACTOR The party(s) that carry(s) out all or part of the procurement, installation and testing
of the system specified by CONTRACTOR
SUPPLIERNENDOR The party which supply materials, equipments, technical documents/drawings and
services to perform the duties specified by PGN
SHALL Indicated a mandatory requirement
SHOULD Indicates a strong recommendation to comply with the requirement of this
document
2. REFERENCE SPECIFICATION
The requirements contained in the latest editions of the following codes and standards shall form an integral
part of this method.
3. SCOPE OF WORK
Scope of work for this work are shown below:
a. Constructed all drainage system of inside plant (open drainage, man hole and culvert) .
b. Relocation of existing irrigation channel and road (see dwg no LNGC-REK-1800-CV-DG-001 for detail
new route) .
3.1. Preparation
In this case, there will be two items must be prepared. They are working drawing and material to be used.
3.1.1. Working drawing
Working drawings shall be submitted to TAS and PGN and shall show at least the following :
a. Section of excavation
b. Detail of demolition of existing obstacles
c. Detail of reinstatement of existing facilities
d. Detail of protection of existing facilities
e. Detail of temporary safety protection for the work
f. Plan drawing for drainage system .
3.1 .2. Materials
a. All materials to be used for this work shall refer to engineering specification and manufacture
standards. Catalogs and/ or samples of the materials shall be submitted to PGN for approval prior
to commencement of the work.
b. Provide mix design concrete and conduct trial mix for all required grades of concrete.
PGAS SOLUTION
HOEGH LNG """'"'
HOEGH LNG- REKIND CONSORTIUM
TECHNICAL ASSISTANT SER VICES CONSORT IUM OF HOEGH LN G LTD AND PT REKAYASA IN DUSTRI
d. Check the invert level of the drain and record it section by section by CONTRACTOR and shall be
approved by TAS/PGN. The tolerance for invert level shall be conformed to engineering specification.
e. All joints between the precast units shall be filled.
f. Joint inspection for drainable slope of drainage partially between CONTRACTORS, TAS/PGN .
3.6. Installation of Pipe Culvert
The following activities shall be performed :
a. All Materials shall be inspected by CONTRACTOR based on engineering spcification and shall be
approved by TAS/PGN.
b. Pipe culvert for road crossing normally installed is of spigot and socket type unless specified otherwise.
c. Make sure that bedding has been accepted including its elevation prior to installation.
d. Pegging area of drainage to guide centerline, elevation, and left-right border as necessary.
e. Provide a recess on the bedding material to accommodate the socket. The width of the recess of the
socket shall conform to manufacture spec.
f. Pipes shall be laid in upstream direction with the socket towards the inlet.
g. Check the alignment of pipe or drainage section by section, partially, by CONTRACTOR and shall be
approved by TAS/ PGN.
h. Prior to jointing, rubber rings and jointing surfaces shall be cleaned of all contaminants.
i. Rubber ring joints shall be installed strictly in accordance with the manufacturer's instruction.
j. The care must be taken to ensure the rubber ring is adequately compressed to seal the joint.
k. After all pipes for certain section of road crossing is completely installed, the survey on the intended invert
level of pipes to be checked and must be within the tolerance given in the specification before backfilling
can be started.
I. All phase of leveling concrete work shall be inspected by CONTRACTOR and shall be approved by
TAS/PGN.
3.7. Sewerage Installation
The installation sewerage system consists of piping and septic tanks which wi ll be described on detailed
engineering drawing.
3.8. Stone Masonry for Open Drainage Structure
The following activities shall be performed:
a. Make sure the alignment and elevation of open drainage refer to engineering drawing .
b. Provide leveling concrete or sand bedding at the bottom level of drainage prior to arrangement of stone
masonry.
c. Use cement mortar at 1:3 mixture for stone masonry work refers to engineering soec (LNGC-REK-1800-
CV-CS-009).
d. Ensure slope of drainage is achieved section by section during construction work.
e. All phase of levelling concrete work shall be insected by CONTRACTOR and shall be approved by
TAS/PGN.
3.9. Backfilling &Compaction Work
The following activities shall be performed:
a. For pre-cast Ditch, the backfilling material is taken from the original suitable materials .
b. Use approved compactor to compact the backfi lling material.
PGAS SOLUTION
HO EGH LNG R .. ,~,
HOEGH LNG- REKINO CONSORTIUM
TECHNICAL ASSISTANT SERVICES CONSORTI UM OF HOEGH LNG LTD AND PT REKAYASA INOUSTRI
c. For pipe culvert on road crossing , sand to be used as backfilling material until 150mm (or as specified on
engineering drawing) above pipe top level, then suitable materials from the original ground to be used to
complete the backfilling.
d. Backfilling material shall be compacted layer by layer not exceeding 300mm in thickness as specified in
the Construction Specification for Earth Work to achieve the specified compaction requirements .
e. The final layer of soil is compacted together with road sub-grade material.
f. Backfilling and compaction work shall be inspected by CONTRACTOR and shall be approved by TAS and
PGN.
PGAS SOLUTION
HOEGH LN G """""
HOEGH LNG- REKIND CONSORTIUM
TECHNICAL ASSISTANT SERVICES CO NSOR TIUM OF HOEG H LNG LTO AND PT REKAYASA INDUSTRI
APPENDIX
3. Mobilisasi alat-alat • Kecelakaan lalu Sakit, cacat I 5 M • Driver harus punya SIM 1 2 L
lint as sampai Kepolisian dan dalam
kema tian. kondisi fit, sehat lahir
batin.
• Pengecekan kondisi
kendaraan sebelum
berkendara.
• Sural KIR kendaraan dari
instansi berwenang masih
berlaku.
4. Memposisikan dump truck dan • Truk saat Tertabrak, 2 5 M • Pasang traffic cone pada 1 2 L
excavator mundur. terbentur depan dan belakang area
• Excavator saat mengakibatkan kerja.
mundur dan sakit, cacat • Penempatan flagman-
swing sampai, man yang mengawasi
kematian pergerakan
excavator/dump truck.
• Retreat horn supa ya
berfungsi.
• Pastikan hanya yang
berkepentingan yang
berada di lokasi sekitar
area kerja excavator.
B . PEKERJAAN PERSIAP AN
1 Penggalian tanah Alat berat Tertabrak, 2 5 M • Ada isyarat suara saat 2 2 L
(excavator) . terbentur unit bergerak/maneuver.
mengakibatkan • Ada personil flagman
sakit, cacat untuk mengawasi
sampai, pergerakan unit.
kematian • Pastikan selama
penggalian tidak ada
orang berlalu lalang
kecuali flagman dan
PROSEDUR OPERAS!/ OPERATING PROCEDURE
pgn ANALISA KESELAMATAN KERJA/ JOB SAFETY ANALYSIS
PT. Perusahaan Gas Negara (Persero) Tbk.
3. Hauling dan unloading tanah • Alat berat (dump Tertabrak, 2 5 M • Gunakan APD standar 2 2 L
truck) . terbentur saat membuka bak dump
• Kecelekaan lalu mengakibatkan truck (helmet, hand glove
lintas sakit, cacat safety shoes, safety
sampai, glasses) selama pekerjaan
kematian. berlangsung.
Kecelakaan • Pastikan ada flagman
lalu lintas untuk mengawasi selama
membuka bak huck.
• Driver hams punya SIM
Kepolisian dan dalam
kondisi fit, sehat lahir
batin.
• Pengecekan kondisi
kendaraan sebelum
berkendara.
• Surat KIR kendaraan dari
instansi berwenang masih
berlaku.
~
~ PROSEDUR OPERAS!/ OPERATING PROCEDURE
PGAS SOLUTION
pgn ,;'.>.: ~:< J ANALISA KESELAMATAN KERJA/ JOB SAFETY ANALYSIS
PT. Perusahaan Gas Negara (Persero) Tbk.
6-12 Medium 4 Probable Will Occur Frequen tly 4 Major Lost Time Accident, permanent/partial disability, non permanent environm ental damage, high financial loss
1- 5 Low 3 Occasional Will Occur Several Tim e 3 Moderate I Serious Medical Treatment req uired/work restriction , high financial loss, on site release contained with outside assistance
2 Unlikely Unlikely. but can reaso nable be expected to occ ur 2 Mino1 First Aid Treatmen t, on site release immediately contained medium financial loss
I Improbable Unlik ely to occu r. but poss ible 1 Neglig ible No affecting work performance. No injury, Low fi nancial loss
-