Method Statement FOR Chiller Replacement

This document provides a method statement for replacing a chiller unit. It outlines the scope of work, responsibilities of roles involved, references, documents needed, sequence of work, resources required, risk rating, and QA/QC requirements. The chiller will be removed by lifting it with a crane and moving it away from its foundation. Ducting and accessories will also be removed. Safety precautions and permits are required.

Uploaded by

Saif ali Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
3K views8 pages

Method Statement FOR Chiller Replacement

This document provides a method statement for replacing a chiller unit. It outlines the scope of work, responsibilities of roles involved, references, documents needed, sequence of work, resources required, risk rating, and QA/QC requirements. The chiller will be removed by lifting it with a crane and moving it away from its foundation. Ducting and accessories will also be removed. Safety precautions and permits are required.

Uploaded by

Saif ali Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 8

METHOD STATEMENT

FOR
CHILLER REPLACEMENT
TABLE OF CONTENTS

1.0 SCOPE OF WORK ……………………………………………………….…...

2.0 RESPONSIBILITIES …………………………………………………………....

3.0 REFERENCES ……………………………………………………………….….

4.0 DOCUMENTS (DRAWINGS, SKETCHES ETC) …….……………….……….

5.0 SEQUENCE OF WORK……………………………………………….……….

6.0 RESOURCES (MANPOWER, MATERIAL,EQUIPMENT)

7.0 RISK RATING

7.1 SUPERVISION

7.2 HSE REQUIREMENT

7.3 RISK ASSESEMENT

8.0 QA/QC REQUIREMENT

9.0 APPROVALS
1.0 SCOPE OF WORK

The scope of method statement is to describe the activities involved in Removal


of Chiller units.

These guidelines shall be mandatory supporting documents for obtaining permit


to work.

2.0 RESPONSIBILITIES

2.1 CONTRACTOR

2.1.1 To monitor and issue the following list of items required for Removal of
Chiller.
2.1.2 Required Permits & Approved Task Risk Assessment
2.1.3 Approved Drawings
2.1.4 To ensure systematic, Quality, Safe work Execution

2.2 Project Manager

2.2.1 Coordination with the consultants, Project Engineer, Safety Engineer and Sub
contractors for the safe and proper execution of the work.
2.2.2 Specific attention is paid to all safety measures and quality control in
coordination with safety officer.

2.3 Project Engineer

2.3.1 Proper execution of work as per approved MARs, Method statement and
approved shop drawings.
2.3.2 Timely provision of relevant full information and COMPANY approved
documents to site execution team.
2.3.3 To distribute responsibilities among site staff.
2.3.4 Adopt all safety measures as required and under supervision of site /
COMPANY safety Personals.
2.3.5 Follow sequence of execution of work and COMPANY instruction and
approvals.

2.4 QA/QC Engineer

2.4.1 To initiate Request for Inspection (RFI) 24 hours prior to inspection for
COMPANY inspection / approvals.
2.4.2 To advise Site Foreman / Supervisor of the specific requirement related to
work quality and requirement of COMPANY inspection and approvals at
different stages of the work progress.
2.4.3 Implement of COMPANY comments through site team and preparing for final
inspection and approval by COMPANY.
2.4.4 To maintain a comprehensive inspection and test record as Quality
Standards and COMPANY approved Quality Plans.

2.5 HSE Officer

2.5.1 The implementation of all safety measures in accordance with the HSE plan
and that the whole work force is aware of its proper implementation.
2.5.2 Inspection of all the site activities and training personnel in accident
prevention and its proper reporting to the construction manager and the
project manager.
2.5.3 The site is maintained in a clean and tidy manner.
2.5.4 Ensure only trained persons shall operate the power tools.
2.5.5 Ensure all concerned personals shall use PPE and all other items as
required.
2.5.6 Ensure high risk elevated areas, service area/inspection area openings are
provided is barricade.
2.5.7 Ensure safe access to site work at all times.
2.6 Job Performer

2.6.1 Ensures that he is aware of Company’s HSE rules and regulations, work
procedures, job locations, equipment to be worked on, tools and
equipment to be used and defining the anticipated start and finish
time/date and no. of days.
2.6.2 Ensure that no other activity/tool is performed/used except as specifically
described on the PTW/Certificate.
2.6.3 Implements the Work Site Precautions to be taken by the Job Performer as
identified by the Area Authority on the PTW/Certificate.
2.6.4 Remains at the worksite during the duration of the work and obtains Area
Authority/Issuing Authority Signature if Job Performer replacement is
required.
2.6.5 Adheres to and maintains the worksite precautions identified by the Area
Authority on the PTW/Certificate throughout the duration of the job.

3. REFERENCES

3.1 HVAC Specifications


3.2 HSE Manual
3.3 HSE Procedures and Guidelines
3.4 Project Quality Plan
3.5 Project HSE Plan
3.6 Engineering Standard Guidelines.

4. DOCUMENTS

4.1 Approved Shop Drawings


5. SEQUENCE OF WORK

1.

5.1 REMOVAL OF CHILLER

5.1.1 Obtain a valid permit before starting the work.


5.1.2 Prepare a mobile scaffolding if required.
5.1.3 Unbolts the vibration isolators from the chiller unit base frame.
5.1.4 Lift the Chiller with suitable crane.
5.1.5 Relocate the chiller away from the chiller unit foundation.

5.2 REMOVAL OF ALLUMINUM CLADDING, DUCTS & ITS ACCESSORIES

5.2.1 Aluminum claddings shall be completely removed.


5.2.2 Unbolts all duct supports.
5.2.3 Remove duct connections from package unit upto riser.
5.2.4 Remove all the duct accessories properly.
5.2.5 Disconnection of electrical power connections from the package unit.

6. RESOURCES

Contractor shall mobilize resources (Manpower/Material/Equipment) to ensure that


the progress is achieved as per targeted schedule. Material, Equipment, Manpower
shall be as per schedule and daily reports will be monitored accordingly.

6.1 Manpower

6.1.1 Job Performer


6.1.2 HSE Officer
6.1.3 Labors

6.2 Material

6.2.1 Warning Tapes


6.2.2 Temporary Signs
6.2.3 Safety Barriers
6.3 Tools

Following tools shall be arranged before starting the job.

6.3.1 Hand Tools


6.3.2 Power Tools
6.3.3 Measuring Instruments

7. RISK RATING

7.1 Risk: Low

7.2 HSE Requirements

Contractor shall comply with all & Local HSE requirements such as:

7.2.1 All PPE such as helmet, safety shoes, harness, gloves and other
appropriate PPE’s shall be used by the personnel, as required.
7.2.2 Check and ensure that all Electrical connections, extension cord free from
damage.
7.2.3 Ensure that all the tools & equipment’s shall be calibrated/third party
certified.
7.2.4 All other precautions shall be followed as per established project HSE plan.
7.2.5 All HSE related policies of and Contractor shall be followed at all times.
7.2.6 Good housekeeping at all time.
7.2.7 Sufficient drinking water shall be made available for the workforce at all
times in shaded area.
7.2.8 Stand by vehicle shall be made available for the workforce at all times.
7.2.9 All personal involved in above activities shall follow HSE manual.
7.2.10 TRA shall be conducted after the approval of method statement.
7.2.11 standard PPE will be worn by all the personnel at site at all times.
7.2.12 All Emergency contact numbers provided by Main Contractor/Client shall
be displayed at working site at all times and same will be inducted to
working personnel.
7.2.13 All the works must be carried out according to Method statements and
Task risk assessments.
7.2.14 The Safety officer should conduct the necessary adequate training prior to
start installation works and ensure that, the workplace is safe and free
from Risk.

7.3 Risk Assessment Attached.

8. QA/QC REQUIREMENTS

8.1 All Quality Assurance and quality Control activities will be in line with Quality
Management System and as required by the specifications.
8.2 Material Inspections are carried out for each Delivery.
8.3 Upon completion of work Request for Inspection (RFI) is raised and shall
submit 24 hours before the inspection from Client.
8.4 Ensure that third party certificates & calibration certificates are available for
required Tools and Equipments.
8.5 Quality records shall be maintained to each stage of the work and
responsible to get the approval for the same from the as defined in the QCP
until the completion of the work.
8.6 Quality Inspections will be as per approved ITP.

9. APPROVALS