This document provides a checklist for inspecting a nitrogen pump unit. The checklist is divided into sections to check the appearance, safety equipment, trailer, engine oil, fuel system, radiator/cooling system, air cleaner, electrical systems, air systems, hydraulic system/hoses, gearbox, PTO/drivelines, and coolant system of the nitrogen pump unit. The inspection includes checking for cleanliness, damage, proper fluid levels, and that all components are in working order. Upon completion of the inspection, the inspector fills out the checklist to document the results.

Uploaded by

Maxim Kanibetov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
887 views4 pages

Nitrogen Pump SM1 Checklist - Controlled Document PDF

This document provides a checklist for inspecting a nitrogen pump unit. The checklist is divided into sections to check the appearance, safety equipment, trailer, engine oil, fuel system, radiator/cooling system, air cleaner, electrical systems, air systems, hydraulic system/hoses, gearbox, PTO/drivelines, and coolant system of the nitrogen pump unit. The inspection includes checking for cleanliness, damage, proper fluid levels, and that all components are in working order. Upon completion of the inspection, the inspector fills out the checklist to document the results.

Uploaded by

Maxim Kanibetov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Operations Integrity Management System

Document Title: Nitrogen Pump SM1 Checklist


Document Code: OS-HQCSC-S001-C031

Revision Date: Page:


Rev. No: V00
18-February-2015 1 of 4

Nitrogen Pump unit - SM1

LOCATION: EQUIPMENT ID: W/O:

UNIT TYPE: LAST SM-2: INSPECTION DATE:

□ DAILY □ PRE JOB


SM INTERVALS: ENGINE HOURS: INSPECTOR NAME:
□ POST JOB

Guidelines on what to check


System / Pre Post
Review manufacturer tech unit / field inspection
Component Job Job
procedure prior to starting.
No No
Appearance & Cleanliness ok
ok
ok
ok

 Unit is CLEAN with correct labeling. Wash with fresh water


 Unit is PAINTED - no corroded or partially painted areas
 Toolboxes/baskets - clean and free of trash
 Walkaround unit - check for leaks/damage: repair/report as required

Safety Equipment
 Fire Extinguisher(s) - present on unit, inspection date okay
 Eye-Wash Bottle, First Aid Kit & Fire Blanket, Warning signs, Tire chains Walkways,
Railings, Ladders & Grating - check for damage, secure & clean Wheel chocks -
check x2 blocks available & in good condition

Trailer
 Trailer Brake Systems - check work okay when hooked up to tractor
 Trailer Lights - confirm all working
 Tires, lugs, clamps - check for flats & damage and loose lugs or clamps Coupling
Devices - check 5th-wheel, pin & latch mechanism okay Air/Electric Hoses -
connected to/from tractor/trailer, secure, no damage Landing Gear & Legs -work okay,
good condition, pins secured with chain Suspension - check for sag/lean, cracked
parts or deflated/ leaking air bags Loads secured, no loose items, blinds & caps
secure

Engine Oil
 Check the oil level (2 times), fill with OEM recommended engine oil.
 Check oil appearance (should not be milky or too dark).
 Check for leaks on all filters, hoses, and connections.
 Ensure that the oil cap and dipstick are in place and secured.
 Check the crankcase vent system for excessive blow by.

Prepared By: Jose Martinez Reviewed By: Martin McCaffrey Approved By: David Maclean
Revision No. : V00 Issued Date: 18-Feb-15 Controlled Copy Online
Operations Integrity Management System
Document Title: Nitrogen Pump SM1 Checklist
Document Code: OS-HQCSC-S001-C031

Revision Date: Page:


Rev. No: V00
18-February-2015 2 of 4

No No
Fuel System ok
ok
ok
ok

 Check for any water contamination in the fuel filters sight bowls and drain/clean
accordingly.
 Drain any water from the diesel tank - close the valve when done.
 Check for leaks on the filters, hoses, and connections.
 Fill up the diesel tank to 90%, and tighten the filler cap back on.
 Check the labelling
Radiator / Cooling System
 Check the coolant fluid level on a cold engine: Must be 2 in below the filler neck.
 Ensure that the top-up coolant drum (2 galUS) is available and part of the equipment
loadout.
 Check the radiator outside cores: Must be clean and free of damage and leaks.
 The coolant system hoses must be checked for leaks/damage.
 Fan belts/hubs: Check the belt for damage and verify the tension (1/2-in to 3/4-in
yield).
Air Cleaner
1. Remove the cover - check the element for soot or water and clean as required. If the
service Indicator is in RED, replace the filter element.

Electrical Systems
 Batteries - electrolyte levels, terminals, tiedowns, and surface are clean.
 Check voltages: Engine off (batteries) and running (alternator).
 Alternator: Check that the belts are OK (1/2-in to 3/4-in yield), and wiring if applicable.
 Starter: Check the wiring and the condition of the starter.
 Lights: No damage, working, and clean.
 Cables and connectors must be clean with no loose or broken wires.
Air Systems
 Check air supply (90-110 psi) - gauges okay & check for audible leaks
 Drain all air reservoirs/tanks until clean, close drain valve
 Air hoses, piping, valves & actuators - no damage/leaks, valves work ok
 PRV/Tank Certifications - check inspection date and tag
Hydraulic System and Hoses
 Hydraulic oil - 2 in to 4 in from the top of the tank when cold and w/o accumulators
dumped.
 Drain any water from the hydraulic oil reservoir.
 Hoses/connections/valves - undamaged, clean, no leaks, cuts, and/or cracks.
 Hoses - all caps, bundle templates, and ID tags correct and in place.
 Check the filter by-pass indicator when fitted. PRV's: Lock nuts are secured.
 Start the nitrogen pump and load the hydraulic pumps - check and report the system
pressures

Prepared By: Jose Martinez Reviewed By: Martin McCaffrey Approved By: David Maclean
Revision No. : V00 Issued Date: 18-Feb-15 Controlled Copy Online
Operations Integrity Management System
Document Title: Nitrogen Pump SM1 Checklist
Document Code: OS-HQCSC-S001-C031

Revision Date: Page:


Rev. No: V00
18-February-2015 3 of 4

No No
Gearbox ok
ok
ok
ok

 Check the oil level with the engine idling, warm, and in neutral.
 Check all hoses, connections, and seals for cleanliness, leaks, and damage.
 Check the condition of the gearbox breather filter.
PTO & Drivelines
 PTO Operation - working, no air leaks & no unusual noises
 Bearings & U-Joints - check grease points,
 check guards secure & in place
Coolant System, N2 Vaporizer and Heat Exchanger (if applicable)
 Coolant level - check the coolant sight glass (fill with the recommended water-glycol
mixture).
 Coolant pump - grease the bearings (Super Lube M EP).
 Coolant loop circuit (pump through heat exchangers to LN2 vaporizer) - check the
piping for leaks and/or damage.
 Coolant loop temp - check the temperature gauge (must stay between 100 - 120
degF).
 Heat exchangers - check for leaks and/or damage.
Centrifugal Charge Pump (Boost Pump)
 C- pump - check operation and inspect for leaks.
 Connections, valves, and braided hoses are in good condition, with no leaks.
 Suction strainer - check for leaks (must clean after 75 hr of operation).
 Check that the LN2 tank pressure is OK (typically 20 psig).
HP N2 Pumps Cold and Warm Ends
 HP N2 drive box: Use a dipstick to check the level.
 HP N2 pump lubrication tank sight glass - check with the engine at idle.
 Cool down - check that the cold ends frost over uniformly when cooling down.
 Leaks - check for leaks during operation.
Control Panel
Engine controls:
 Function-test the engine shutdown and emergency kill.
 Check that all gauges are in good condition and functioning.
 Check all controls for condition and function.
 Temperature and pressure gauges - all are working, undamaged, and tested.
 Power up / voltage check (volt meter = 11.5 V min - 14.5 V max).
Unit controls:
 Displays - check operation for (rate + RPM) and (pressure + OPSD). OPSD - check
operation and reset.
 HP N2 pump - Check the RPM, LN2 and GN2 discharge pressure, and temperature
control gauges.

Prepared By: Jose Martinez Reviewed By: Martin McCaffrey Approved By: David Maclean
Revision No. : V00 Issued Date: 18-Feb-15 Controlled Copy Online
Operations Integrity Management System
Document Title: Nitrogen Pump SM1 Checklist
Document Code: OS-HQCSC-S001-C031

Revision Date: Page:


Rev. No: V00
18-February-2015 4 of 4

 Heat exchanger - check the controls and gauges panel


 Cables & Connectors - clean & undamaged, dust caps in place
 Power Up/Voltage Check (Volt meter = 11.5V min - 14.5V max) Check Normal Kill &
Emergency Kill (with engine stopped) and reset
 OPSD's - check operation and reset
 Convertor Lock-Up - check operation and light working
Electronics Control, Recording, and Monitoring Devices
 Cables/connectors: Check the condition, cleanliness, tightness of connections, and
dust caps.
 Junction box - check that the door and seals are OK, the connector cable is secured
and not binding, and cables enter via the proper glands.
 Sensors LN2 and GN2 - check that all are working, tested, and calibrated OK
Treating Equipment
 Certifications are up to date, with ID bands in place.
 Grease the plug valves and chicksans swivels, and check the seal rings.
 Dart-type check valve is in place on the discharge line, with in-date test.
 Remote actuated valve - check the certifications and function test to ensure it is
working OK.
 Check for no burrs on the wing nut lugs, and ensure that the valve indicators are
painted white.
 Check that the cryogenic braided hoses and unions (M+F) are undamaged and clean
inside
COMMENTS: Describe any additional checks performed or deficiencies found.
Use SM-2 and 3 Repair Report for documenting all repairs carried out and parts used.

THIS EQUIPMENT IS: IF NOT READY - FURTHER ACTION REQUIRED BY:


GREEN TAGGED AND READY TO PERFORM ITS NEXT JOB
MAIINT. OPER.

INSPECTOR - PRINT NAME & SIGNATURE SUPERVISOR - PRINT NAME & SIGNATURE SDM / MSV - PRINT NAME & SIGNATURE

Date: Date:
Date:
Supervisor/SDM/MSV c o n f i r m s that required SM-1 maintenance inspection has been performed, deficiencies corrected, repair report attached and W O closed in EPICOR. SDM/MSV confirms that defects are corrected & documented in EPICOR. Unit is green tagged & ready to go

Controlled document. Do not modify or change without permission. In compliance with OILSERV Quality Plan

Prepared By: Jose Martinez Reviewed By: Martin McCaffrey Approved By: David Maclean
Revision No. : V00 Issued Date: 18-Feb-15 Controlled Copy Online