1. The document is a certification from the Municipality of Lal-lo attesting to compliance requirements for the release of funds from the FY 2020 Local Government Support Fund - Provision of Potable Water Supply Program. 2. It certifies that the municipality has completed all required documents for project implementation including an engineering design, permits, and land rights. 3. It commits the municipality to comply with implementation and monitoring guidelines, make funds available for project maintenance, and establish a functional website.

Uploaded by

michael ricafort
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
260 views3 pages

Certification SalinTUBIG CY 2020

1. The document is a certification from the Municipality of Lal-lo attesting to compliance requirements for the release of funds from the FY 2020 Local Government Support Fund - Provision of Potable Water Supply Program. 2. It certifies that the municipality has completed all required documents for project implementation including an engineering design, permits, and land rights. 3. It commits the municipality to comply with implementation and monitoring guidelines, make funds available for project maintenance, and establish a functional website.

Uploaded by

michael ricafort
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Annex B.

4 - Notarized MLGU Certification of Compliance for Fund Release


(Potable for Drinking _ not in Hazard Area _ no Website)
FY 2020 LGSF-SALINTUBIG

Republic of the Philippines


Province of Cagayan
MUNICIPALITY OF LAL-LO

Office of the
Mayor
CERTIFICATION

In the implementation of amounting to


PhP_______________ in the Municipality of Lal-lo under the FY 2020 Local Government
Support Fund-Provision of Potable Water Supply (LGSF-SALINTUBIG) Program, we hereby
attest that:

1. Detailed Engineering Design (DED) has been prepared in accordance with Annex “A” of
2016 Revised IRR of R.A. 9184 (Detailed Engineering for the Procurement of Infrastructure
Project), National Government standards, and relevant provisions of the General
Appropriations Act (GAA) and other applicable laws and issuances;

2. The water source has been validated by the Municipal Engineer and has found to be feasible
in supplying water to the intended beneficiaries and potable for drinking.

3. Our Municipal Local Government Unit (MLGU) has an established PIT, PMC, and
Inspectorate Team based on the attached Executive Orders issued by the undersigned.

4. Certified True Copies of the following documents are hereby attached:

4.1. Approved Detailed Engineering Design (DED);

4.2. Proof of application and/or payment of the following permits:

a. Environmental Compliance Certificate (ECC) or Certificate of Non-


Coverage (CNC) from the Department of Environment and Natural Resources–
Environmental Management Bureau (DENR-EMB), whichever is applicable.

b. Certificate of Non-Overlap (CNO) or Free, Prior and Informed Consent


(FPIC) from National Commission on the Indigenous People (NCIP), whichever is
applicable.

c. Water Permit from the National Water Resources Board (NWRB);

d. Other permits as may be required by laws, rules, or other concerned agencies for
the implementation of the project.

4.3. Deed of Donation or Deed of Absolute Sale or Usufruct or any other legal
documents proving that the site of the project has no land ownership or Right-of-Way
(ROW) issues;

4.4. Water Source Validation Report (WSVR)

4.5. MGB Certification that the project is not located in the “no-build” zone and
hazard-prone area;

4.6. Executive Orders creating or activating the PIT, PMC and Inspectorate Team.
Annex B.4 - Notarized MLGU Certification of Compliance for Fund Release
(Potable for Drinking _ not in Hazard Area _ no Website)
FY 2020 LGSF-SALINTUBIG

5. The project is included in the updated and duly adopted Local Development Investment
Program (LDIP) of the Municipality and must not be funded from other sources.

6. The proposed SALINTUBIG Project/s is/are included in the approved Annual Procurement
Plan of the Municipality.

7. The bidding documents have been prepared, and to ensure that the bidding can commence
on (identify date), these documents shall be made available to DILG during field
monitoring visits and/or as may be requested.

8. Funds downloaded to our MLGU from the national subsidy of DILG-OPDS Administered
Programs from previous funding years (2012-2018) will be fully liquidated by 31 December
2020

9. Undisbursed funds from the national subsidy of DILG-OPDS Administered Programs from
previous funding years (2012-2018) have been reverted to the source agency (DILG or
Bureau of Treasury) and the Notarized Affidavit of Undertaking, when applicable, were
submitted to the DILG, pursuant to applicable provisions of the General Appropriations Act
(GAA) and all the DILG Memoranda issued for the purpose;

10. Our Municipality commits and binds itself/ourselves to comply with all the provisions of the
Project Implementation and Monitoring Guidelines issued by the DILG.

11. Funds shall be made available for the maintenance once the project is completed.

12. Our MLGU commits to established a functional and operational website within the year.

We agree that our Municipality may be ineligible to receive a subsidy from the SALINTUBIG
Program in the next Fiscal Year (FY) if any of the above attestations/declarations to be
misrepresented or false.

We agree that our Municipality is primarily and solely accountable and responsible as to the
truthfulness of these attestations, and at the same time, further attests to the accuracy and
completeness of the submitted technical documents, as well as its consistencies and conformity
to national standards.

We further agree that our Municipality will be subjected to penalties and sanctions in case of
non-compliance to Project Implementation and Monitoring Guidelines issued by the DILG.

This Certification is being issued in compliance with the DILG Memorandum Circular
No._____, Series of 2020.

ENGR. JOLSON A. MAAGAD


Municipal Planning and Development Coordinator Date

ENGR. RONALD E. MATAS


Municipal Engineer Date
Annex B.4 - Notarized MLGU Certification of Compliance for Fund Release
(Potable for Drinking _ not in Hazard Area _ no Website)
FY 2020 LGSF-SALINTUBIG

FLORENCE OLIVER B. PASCUAL


Municipal Mayor Date

ACKNOWLEDGEMENT
REPUBLIC OF THE PHILIPPINES
(Municipality/City of ________________) S.S.

Subscribed and sworn to before me on this date, a Notary Public for and in __________,
Philippines.

NOTARY PUBLIC

Doc. No. __________


Book No. __________
Page No. __________