Rate Analysis BLDG Works
Rate Analysis BLDG Works
Say
Notes:-
1 Cement required for cement mortar is 71.25%
2 1 Cum of cement weight is 1.1286 Tonne
3.2 Cement Mortar 1 : 2 (1 cement : 1 fine sand)
108
3.3 Cement Mortar 1 : 3(1 cement : 3 fine sand)
109
3.5 Cement Mortar 1 : 5 (1 cement : 5 fine sand)
Note:-
1 Cement required is 17.80%
110
3.7 Cement Mortar 1 : 2 (1 Cement : 2 Coarse sand)
111
3.9 Cement Mortar 1 : 4 (1 cement : 4 coarse sand)
112
3.11 Cement Mortar 1 : 6 (1 cement : 6 coarse sand)
113
3.13 Cement Mortar 1 : 2(1 cement : 2 marble dust)
Note:-
1 Cement required is 21.40%
114
3.15 White Cement Mortar 1 : 2 (1 White cement : 2 marble dust)
115
3.17 White Cement Mortar 1 : 5 (1 white cement : 5 marble dust)
6,120.00
-
961.88
-
147.00
13.72
26.90
13.52
7,283.02
7,283.00
Amount
4,080.00
-
1,282.50
-
147.00
13.72
26.91
13.52
5,563.65
5,564.00
Amount
3,060
1,444.5
147
13.72
26.91
13.52
4,705.65
4,706
Amount
2,280
1,444.5
147
13.72
26.91
13.52
3,925.65
3,926
Amount
1,860
1,444.5
147
13.72
26.91
13.52
3,505.65
3,506
Amount
1,500
1,444.5
147
13.72
26.91
13.52
3,145.65
3,146
Amount
4,080
2,632.5
147
13.72
26.91
13.52
6,913.65
6,914
Amount
3,060
1,444.5
147
13.72
26.91
13.52
4,705.65
4,706
Rate Amount
6000 2,280
1350 1,444.5
196 147
196 13.72
1 26.91
1 13.52
3,925.65
3,926
Rate Amount
6000 1,860
1350 1,444.5
196 147
196 13.72
1 26.91
1 13.52
3,505.65
3,506
Amount
1,500
1,444.5
147
13.72
26.91
13.52
3,145.65
3,146
Amount
4,080
1,282.5
147
13.72
26.91
13.52
5,563.65
5,564
Amount
4,080
1,282.5
147
13.72
26.91
13.52
5,563.65
5,564
Amount
1,860
1,444.5
147
13.72
26.91
13.52
3,505.65
3,506
Amount
6,596.00
-
760.00
-
147.00
13.72
26.91
13.52
7,557.15
7,557
Amount
4,947.00
-
856.00
-
147.00
13.72
26.91
13.52
6,004.15
6,004
Amount
3,007.00
-
856.00
-
147.00
13.72
26.91
13.52
4,064.15
4,064
RATE ANALYSIS FOR FLY ASH BRICK WALL-9" THICKNESS
Providing and laying fly ash brick work of class designation 75 in superstructure at all floors, levels and heights as per specifications
A
with approved bricks of 1st quantity in cement mortar 1:6 ( 1 cement : 6 coarse sand)
Cement mortar 1:6(1 cement: 6 coarse sand)
Details of cost for 1 cum.
MATERIALS :
Fly Ash Bricks of class designation 75 Nos 494 4.00 1,976.00
Cement mortar 1:6 (Rate as per item no 3.11) Cum 0.25 3,151.00 787.75
Sundries L.S 67.5 1.00 67.50
LABOUR:
Mason 1 st Class Day 0.36 -
Mason Ilnd Class Day 0.36 -
Coolie Day 1.37 -
Bhishti Day 0.2 -
Area of Wall equivelent to 1 Cum=1/.23X10.76=46.78 SqFt
Cost of Labour Charges Sq Ft 46.78 11.00 514.58
TOTAL 3,345.83
Add 3% for water and Power charges 100.37
Say 4,077.00
Say 3,151.00
RATE ANALYSIS FOR FLY ASH BRICK WALL-9" THICKNESS
Providing and laying fly ash brick work of class designation 75 in superstructure at all floors, levels and heights as per specifications
A
with approved bricks of 1st quantity in cement mortar 1:6 ( 1 cement : 6 coarse sand)
Cement mortar 1:6 (1 cement: 6 coarse sand)
Details of cost for 1 cum.
MATERIALS :
Fly Ash Bricks of class designation 75 Nos 494 4.00 1,976.00
Cement mortar 1:6 (Rate as per item no 3.11) Cum 0.25 3,151.00 787.75
Sundries L.S 67.5 1 67.50
LABOUR:
Mason 1 st Class Day 0.47 -
Mason Ilnd Class Day 0.47 -
Coolie Day 1.8 -
Bhishti Day 0.2 -
Area of Wall equivelent to 1 Cum=1/.23X10.76=46.78 SqFt
Cost of Labour Charges Sq Ft 46.78 11.00 514.58
Say 4,348.00
Providing and laying Clay Hollow Brick brick work of class designation 75 in superstructure at all floors, levels and heights as per
A
specifications with approved bricks of 1st quantity in cement mortar 1:4 ( 1 cement : 4 coarse sand)
Cement mortar 1:4 (1 cement: 4 coarse sand)
Details of cost for 1 cum.
MATERIALS :
Clay Hollow Bricks of class designation 75 Nos 494 12 5,928.00
Cement mortar 1:4 Cum 0.25 3,926.00 981.50
Sundries L.S 67.5 1 67.50
LABOUR:
Mason 1 st Class Day 0.47
Mason Ilnd Class Day 0.47
Coolie Day 1.8
Bhishti Day 0.2
Area of Wall equivelent to 1 Cum=1/.23X10.76=46.78 SqFt
Cost of Labour Charges Sq Ft 46.78 36 1,684.08
TOTAL 9,065.06
Add 3% for water and Power charges 271.95
Say 11,572.00
Say 3,926.00
Random rubble masonry with hard stone in foundation and plinth in Cement mortar 1:6(1 cement: 6 coarse
sand)
TOTAL 5,546.06
Total 6,377.97
Add 4% for WCT 255.12
Add @1% for Labour Cess 63.78
TOTAL 6,696.87
Say 6,697.00
Extra for random rubble masonry with hard stone in superstructure above plinth level
and upto floor five leve
Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Scaffolding etc. L.S. 150 1 150.00
Labour:
Extra labour for lifting of materials upto floor
V level-0.75xl.50= 1.13
Coolie Day 1.13 180 203.40
TOTAL 353.40
Add 3% for water charges & electricity Charges 10.60
Add 12.5% for EPF on labour Charges of Rs.204/- 25.50
TOTAL 389.50
Add 15% for contractor’s profit and overheads 58.43
TOTAL 447.93
Add2.8% for WCT 12.54
Add @1% for Labour Cess 4.48
TOTAL 464.95
Say 465.00
G/Total 7,162.00
1 cement: 6 coarse
Remarks
Item Code: 13.15
20 mm CP 1:2 (1 cement : 2 stone dust)
Details of Cost for : 10.00 Sqm
Code Description Unit Quantity Rate
MATERIALS
03.012 Cement Mortar 1:2 (1 cement : 2 stone dust) Cum 0.224 3220.00
(Rate as per item no. 3.12)
LABOUR
0155 Mason Day 0.94 237.00
0115 Coolie Day 1.02 196
0101 Bhisti Day 1.10 196
9999 Scaffolding and sundries L.S. 12.61 1.00
Total:
Add water charges @ 1% on 1372.19
Say
Amount
721.28
222.78
199.92
215.60
12.61
1372.19
13.72
1385.91
207.89
1593.80
Amount Remarks
1,500.00
1,444.50
147.00
13.72
26.91
88.34
3,220.47
3,220.00
Providing & applying 15 mm thick plaster in CM 1:6 (1 cement 3 coarse sand and 3 fine sand)on the inner
surface of brick with two coarse sand and 4 fine sand at all heights and levels including scaffolding curing etc.
complete. ( The job shall include providing & fixing chicken wire mesh on joint between R.C.C. & brickwork
and also making grooves in horizontal & vertical meeting points, wherever desired by the Architect.
TOTAL 1,680.09
Add 3% for water and Power charges 50.40
Add 12.5% for EPF on labour Charges of Rs. 1,113.64 139.21
TOTAL 1,869.70
Add for contractor’s profit and overheads @ 15% 280.45
TOTAL 2,150.15
Add 4% for WCT -
Add @1% for Labour Cess 21.50
Cost for 10 sqm. 2,171.65
Say 217.00
Sl No Description Unit Quantity Rate Amount Remarks
Say 3,220.00
Providing & applying 15 mm thick plaster in CM 1:6 (1 cement 3 coarse sand and 3 fine sand)on the inner surface
of brick with two coarse sand and 4 fine sand at all heights and levels including scaffolding curing etc. complete.
( The job shall include providing & fixing chicken wire mesh on joint between R.C.C. & brickwork and also
making grooves in horizontal & vertical meeting points, wherever desired by the Architect.
Same as above, but plaster to stone masonary from inside with chicken wire mesh on all surface . Thickness of
plaster shall depend on the quality of stone masonary .
Sl No Description Unit Quantity Rate Amount
TOTAL 2,478.98
3 Add 3% for water and Power charges 74.37
Add 12.5% for EPF on labour Charges of Rs. 1,544.04 193.01
TOTAL 2,746.35
Say 319.00
Say 3,214.00
n the inner surface
ng etc. complete.
ork and also
. Thickness of
Remarks
0.00258
274.64
328.38
37 266.68
0.1347
Remarks
BOQ & PRESENT MARKET RATES
Rate as per
S.No. Description Unit Present Rate Direct Cost
BOQ
1.0 Earthwork:
1.1 Excavation on soils
(a)Up to 3m Cum 139 139 116.20
(b)3 to 6m Cum 185 185 154.66
1.2 In SDR
(a)Up to 3m Cum 200 200 167.20
(b)3 to 6m Cum 277 277 231.57
1.3 Hard QROck
(a)Up to 3m Cum 554 554 463.14
(b)3 to 6m Cum 693 693 579.35
1.4 Filling
(a)Available Earth Cum 74 74 61.86
(bMoorum from outside Cum 300 300 250.80
1.5 ATT Sqm. 80 80 66.88
1.6 Disposing 2Km Cum 69 69 57.68
1.7 Soling 230mm with 50 to 90mm Sqm 1150 1150 961.40
1.8 Pumping out water per HP/hour 69 69 57.68
2.0 Concrete:
2.1 M10 Cum 2743 2890 2,416.04
2.2 M20
(a)Foundations Cum 3500 3540 2,959.44
(b)Coloumns Cum 3815 3855 3,222.78
(c)Beams Cum 3700 4118 3,442.65
(d)Slabs Cum 3700 4118 3,442.65
(e)S.Stairs Cum 3900 4318 3,609.85
(f)Walls Cum 3900 4318 3,609.85
(g)Fins Cum 4200 4618 3,860.65
(h)Bands Cum 4200 4618 3,860.65
(i)Archs Cum 5544 5962 4,984.23
2.3 Extra for M25 Over M20 Cum 200 217 181.41
2.4 Extra for M30 Over M20 Cum 450
2.5 Shuttering
(a)Foundations Sqm. 117 117 97.81
(b)Coloumns Sqm. 230 384 321.02
(c)Beams Sqm. 230 384 321.02
(d)Slabs Sqm. 230 384 321.02
(e)S.Stairs Sqm. 255 409 341.92
(f)Walls Sqm. 255 409 341.92
(g)Fins Sqm. 345 509 425.52
(h)Bands Sqm. 345 509 425.52
(i)Archs Sqm. 832 917 766.61
2.6 Additional Height Sqm. 34 51 42.64
2.7 Reinforcement
(a)MS MT 47827 49541 41,416.28
5.4 Grade 5 Ceramic tiles Rs. 35/- Basic Price Sqm 655 829 693.04
5.5 Choclate brown stone sil Sqm 689 -
5.6 (a)Polyshed granite WB Counter top Sqm. 5742
(b)With basic rate Rs.1500/Sqm Sqm 5742
(c)With Cuddapah Slab Sqm 480
5.7 (a)Cuddapah 50mm thk both sides polished Sqm. 579
(b)One side Polished Sqm 520
5.8 (a)25mm thk Cuddapah Clading Sqm 574
(b)Granite Cladding-1500/sqm Sqm 3445
5.9 (a)Granite Flooring Sqm 4000
(b)Flame finish Sqm 200
5.10 52mm CC Flooring Sqm 450
6 FINISHING WORK
6.1 (a)Plaster(1:6) 15mm Chicken mesh Sqm 140 196 163.86
(b)10mm Ceiling Sqm 115 179 149.64
(c)External including water proofing
Sqm 172 209 174.72
compound
(d)Plastering walls including full chicken
Sqm 231 226 188.94
mesh
6.2 (a)OBD Sqm 73 100 83.60
(b)Snowcem trump Sqm 115 142 118.71
7 ALUMINIUM WORKS :
7.1 (a)Fixed window Sqm 3300 3975 3,323.10
(b)Openable Sqm 4000 3975 3,323.10
(C)SS Mesh Sqm. 3300 3394 2,837.38
7.2 Double shutter Sqm 5750
7.3 12mm thk Clear toughened glass Sqm 12000
7.4 Screen wall Rmt 500
8 MISC ITEMS
8.1 Steel Door Frame Rmt 350 389 325.20
8.2 (a)]Commercial doors 35mm Sqm. 2297
(b)Vision Hole Sqm 700
8.3 25mm Cupboard Shutters Sqm. 3445
8.4 MS Door Cupboard Shutters Sqm 3447
8.4 PVC Door Shutter & Frame Sqm 4158
8.5 (a)Hand Railing Rmt. 1200
(b)with SS Extra Rmt 3445 8698 7,271.53
(c) 19mm Square bars(Type-'A") Rmt 4500 4616 3,858.98
(c) (Type-'C") Rmt 9082 7,592.55
(d)63mm SS HR(Type-"B") Rmt 3300 3300 2,758.80
8.6 MS Grills Kg 69
8.7 Mirror Sqm 1148
Boundary Wall
2.2 M20
(a)Foundations Cum 3500 3540
(b)Coloumns Cum 3815 3855
2.5 Shuttering
(a)Foundations Sqm. 117 110
(b)Coloumns Sqm. 230 200
2.7 Reinforcement MT 47827 42000
Remarks
Considering
Rs.2900 as labour
Rs.38000
in DSR skirting in
Sqm, Where as ours
in Rmt
8698
In quation rate
Rmt also
Quoted
RATE ANALYSIS FOR WINDDDOW
315.36
TOTAL
Add for contractor’s profit and overheads @ 15%
TOTAL
Add 2.8% for WCT
Add @1% for Labour Cess
TOTAL
Say
TOTAL
Add for contractor’s profit and overheads @ 15%
TOTAL
Add 2.8% for WCT
Add @1% for Labour Cess
TOTAL
Say
641.70
TOTAL
Add for contractor’s profit and overheads @ 10%
TOTAL
Add 4% for WCT
Add @1% for Labour Cess
TOTAL
Say
5,201,556.03
(630,336.33) 0.30
0.695652
0.695652
TOTAL
Add for contractor’s profit and overheads @ 15%
TOTAL
Add 4% for WCT
Add @1% for Labour Cess
TOTAL
Say
Amount Remarks
239580
971040
315.36 3975 1253556
1210620
3838.85
3,594.00
539.10
4,133.10
115.73
41.33
4,290.16 3300 4000 7300
0.45205479 0.5479452
4,290.16 7950
3593.83562 4356.1644
4,290.00
3594 4356
4,356.00
653.40
5,009.40
140.26
50.09
5,199.76 3300 4000 7300
0.45205479 0.5479452
5,199.76 7950
3593.83562 4356.1644
5,200.00
3594 4356
644490
1785600
315.36 3975 1253556
1473120
3903210
668009.7
4571219.7 7123.609
9,362.31
3300 4400 3700
9,362.00
0.525 1.200 1.20
9,361.87
4,915.05 11,234.40 11,234.40
2,849.30
2738 3320 2738
6,512.70
6,512.70
5,909.20
886.38 5372
6,795.58
271.82
67.96
7,135.36
7,135.36
7,135.00
Date: 16-Jan-11
RATE ANALYSIS FOR WINDDDOW
TOTAL 2,152.50
Add for contractor’s profit and overheads @ 15% 322.88
TOTAL 2,475.38
Add 4% for WCT 99.02
Add @1% for Labour Cess 24.75
TOTAL 2,599.14
Say 2,599.00
Openable
Rate per Sqm (as per quotation) including all taxes 3,169.00
Add 12.5% for EPF on labour Charges of Rs. 633.80 79.23
TOTAL 3,248.23
Add for contractor’s profit and overheads @ 15% 487.23
TOTAL 3,735.46
Add 4% for WCT 149.42
Add @1% for Labour Cess 37.35
TOTAL 3,922.23
Say 3,922.00
Wire Mesh
Rate per Sqm (as per quotation) including all taxes 2,100.00
Add 12.5% for EPF on labour Charges of Rs. 420.00 52.50
TOTAL 2,152.50
Add for contractor’s profit and overheads @ 15% 322.88
TOTAL 2,475.38
Add 4% for WCT 99.02
Add @1% for Labour Cess 24.75
TOTAL 2,599.14
TOTAL 1,508.77
3 Add 3% for water and Power charges 45.26
Add 12.5% for EPF on labour Charges of Rs. 1,113.64 139.21
4 TOTAL 1,693.24
Add for contractor’s profit and overheads @ 15% 253.99
5 Total 1,947.22
Say 197.00
Say 3,220.00
Providing & applying 15 mm thick plaster in CM 1:6 (1 cement 3 coarse sand and 3 fine sand)on the inner
surface of brick with two coarse sand and 4 fine sand at all heights and levels including scaffolding curing etc.
complete. ( The job shall include pro
TOTAL 1,956.86
3 Add 3% for water and Power charges 58.71
Add 12.5% for EPF on labour Charges of Rs. 1,328.84 166.11
4 TOTAL 2,181.67
Add for contractor’s profit and overheads @ 15% 327.25
5 TOTAL 2,508.92
Add @ 4% for WCT on (5) -
Add @ 1% for Labour Cesson (5) 25.09
Say 253.00
Say 253.00
Say 3,220.00
13.21 Extra for providing and mixing water proofing material in cement plaster work in
proportion recommended by the manufacturers.
Code Description Unit Quantity Rate Amount
Detail of cost for 12 mm cement plaster 1:3
(1 Cement: 3 sand) = 10 sqm. or 1.48 bags of
cement used in the mix
Cement required for 10 sqm = 73.89 kg.
Water proofing material required @ 1 kg per
218.17
250.89
0.043 43
RATE ANALYSIS FOR FLY ASH HALF BRICK WALL (41/2" thick)
Providing and laying first class fly ash half brick (41/2" thick) masonry of class designation 75 in superstructure in
A CM 1:4(cement and coarse sand) with 2 Nos 6mm dia MS bars placed at every fourth course for all floors, heights and
levels.
Details of cost for 10 sqm.
Materials :
Brick of class designation 75 Nos 565.00 4.00 2,260.00
Cement mortar 1:4 (Rate as per item No. 3.9) cum 0.28 4,007.00 1,121.96
MS Bars 6 mm Kgs 10.00 26.50 265.00
Sundries & Scaffolding Day 77.40 1.00 77.40
LABOUR:
Mason 1st class Day 0.60 0 -
Mason 2nd class Day 0.60 0 -
Coolie Day 2.00 0 -
Bhishti Day 0.70 0 -
Area of Wall=10X10.76=107.6 SqFt
Cost of Labour Charges Sqft 107.60 8.00 860.80
TOTAL 4,838.00
3 Add 3% for water and Power charges 145.14
Add 12.5% for EPF on labour Charges of Rs. 1,113.64 139.21
TOTAL 5,122.35
Add @ 4% for WCT on (5) -
Add @ 1% for Labour Cesson (5) 51.22
Say 517.00
Say 4,007.00
RATE ANALYSIS FOR BURUNT CLAY HOLLOW BRICK WALL (41/2" thick)
Sl No Description Unit Quantity Rate Amount Remarks
Providing and laying exposed brick work of Burnt Clay hollow bricks of class designation 75 of appd make & quality with
cement mortar of 1:4 (cement and coarse sand). The maximum size of bricks used shall be 9"x4 ½”x3" with 3" plain face on
exposed size. The quoted rate of cum of brick to include solid core brick as specified of shape as required by architectural
A detail and corner of wall , where two or more sides of bricks are exposed. (some percentage of bricks shall be made of
different sizes varying from 2" to 9" on all sides and also solid on all sides. The job shall include rich cement pointing (V
Shape) (1:2 cement and sand) from outer face joint with water proofing compound. Wherever both side of bricks are
exposed, pointing shall be done on both sides.
TOTAL 13,522.82
4 TOTAL 14,242.56
Say 1,654.00
512
11.36 : Providing and fixing 1st quality ceramic glazed wall tiles conforming to IS : 15622
(thickness to be specified by the manufacture of approved make in all colours, shades
except burgundy, bottle green, black of any size as approved by Engineer-in-Charge
in skirting, risers of steps and dados over 15 mm thick bed of cement Mortar 1:4 (1
cement: 4 coarse sand) and jointing with grey cement slurry @ 3.3kg per sqm including
pointing in white cement mixed with pigment of matching shade complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 sqm
Materials-
Ceramic Glazed tiles = 1.00 sqm
Add for wastage & breakage @ 2.5 % = 0.025
sqm = 1.025 sqm
7800 Tiles Sqm. 1.03 376.00 385.40
9999 Carriage of tiles L.S. 6.24 1.00 6.24
15 mm thick cement mortar 1:4 (1 cement: 4 cum 0.02 3,506.00 63.11
coarse sand (Rate as per item No. 3.8)
9999 Mortar for pointing in white cement L.S. 40.43 1.00 40.43
367 Cement for slurry over bed @ 3.3 kg per sqm tonne 0.00 6,000.00 19.80
Labour:
123 Mason 1 st class Day 0.25 -
115 Coolie Day 0.25 -
Cost of Labour Charges Sqft 10.76 12.50 134.50
9999 Sundries including carriage of cement etc L.S. 26.91 1.00 26.91
TOTAL 676.39
Add for water charges @ 1 % 6.76
TOTAL 683.15
Add for contractor’s profit and overheads @ 15% 102.47
Cost for 1 sqm 785.62
Add @ 4% WCT 31.42
Add Labour Cess @1.0% 7.86
G/Total 824.91
Say 825.00
513
11.38 : Providing and laying Ceramic glazed floor tiles 300x300 mm(thickness to be specified by the
manufacturer) of 1st quality conforming to IS : 15622 of approved make in all colours , shades, except
White, Ivory, Grey, Fume Red Brown laid on 20mm thick bed of Cement Mortar 1:4(1 Cement: 4
Coarse sand) including pointing the joints with white cement and matching pigments etc., complete.
4 TOTAL 739.01
Say 858.00
Say 3,506.00
Rate analysis for Mosaic Tiles for Hostel block
1 Materials-
Total 30.90
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.003 3,506.00 10.95
TOTAL 60.33
TOTAL 62.14
7 TOTAL 63.64
9 TOTAL 73.18
12 G/Total 73.92
Say 795.00
Cement Mortar 1 : 4 (1 cement : 4 coarse sand)
Say 3,506.00
Rate analysis for Mosaic Tiles for Hostel block
1 Materials-
Total 15.45
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.003 3,506.00 10.95
TOTAL 46.64
TOTAL 48.04
7 TOTAL 50.04
9 TOTAL 57.54
12 G/Total 58.12
Say 191.00
Cement Mortar 1 : 4 (1 cement : 4 coarse sand)
Say 3,506.00
Providing and fixing in position mirror in toilets and other areas as per detail in drg.
Base Rate() Sqm 1722
TOTAL
Say
Providing and fixing in position Aluminium Curtain Rod with bracket etc complete.
Base Rate() RM 375
TOTAL
Say
detail in drg.
1,722.00
258.30 5372
1,980.30
-
19.80
2,000.10
2,000.10
2,000.00
c complete.
375.00
56.25 5372
431.25
-
4.31
435.56
435.56
436.00
S.No. Description Quantity Unit Rate Amount
- 176 -
S.No. Description Quantity Unit Rate Amount
TOTAL TO SUMMARY -
2 CONCRETE BLOCK
e) Staircase with waist slab landing and steps. Cum 5,857 -
f) Wall (any thickness) Cum 5,857 -
g) Vertical and horizontal fins individually or
Cum 5,857 -
forming box louvers and facias.
h) String courses, bands, copings, bed plates,
anchor blocks, window sills, frame for doors, next to
Cum 6,200 -
stone masonary for fixing steel frame of door and the
like.
i) Arches, arch ribs, domes and vaults. Cum 6,200
- 177 -
S.No. Description Quantity Unit Rate Amount
e) Staircase with waist slab landing and steps Sqm. 390 -
f) Wall (any thickness) Sqm. 390 -
g) Vertical and horizontal fine individually or
Sqm. 390 -
forming box louvers and facias.
h) String courses, bands, copings, bed plates,
anchor blocks, window sills, frame for doors next to
Sqm. 390 -
stone masonary for fixing steel frame of door and the
like.
i) Arches, arch ribs, domes, vaults etc., round
Sqm. 832
column and circular shuttering on plan etc.
- 178 -
S.No. Description Quantity Unit Rate Amount
TOTAL TO SUMMARY -
3 MASONARY WORK
- 179 -
S.No. Description Quantity Unit Rate Amount
TOTAL -
BRICKBAT COBA TREATMENT (FOR
4.1
TERRACES AND SUNKEN AREAS)
- 180 -
S.No. Description Quantity Unit Rate Amount
TOTAL -
5 FLOORING WORK
- 181 -
S.No. Description Quantity Unit Rate Amount
5.1b Same as above, but plain tandoor stone flooring. Sqm 751 -
- 182 -
S.No. Description Quantity Unit Rate Amount
5.6b Same as above, but one side polished shelves. Sqm 750
TOTAL -
6 FINISHING WORK
- 183 -
S.No. Description Quantity Unit Rate Amount
TOTAL -
7 ALUMINIUM WORKS :
TOTAL -
8 MISC ITEMS
- 184 -
S.No. Description Quantity Unit Rate Amount
Same as above 8.3, but m.s doors with all fittings etc.
8.4 Sqm
complete.
- 185 -
S.No. Description Quantity Unit Rate Amount
- 186 -
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 370
P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 2130
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1670
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 940
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 170
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 1090
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 630
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 345
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 520
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 1729
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 120/150 hour 1423
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 690
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1320
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 1090
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 23000
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 19550
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 17250
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 15525
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2070
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 1175 1808.5
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 7070
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 14880
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 290
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 2600
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 920
Paver Finisher Hydrostatic with sensor control 100
P&M-034 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 2530
TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 1090
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 4485
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1035
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 3740
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 750
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 110
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 746.5
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1320
Transportation of soil, GSB, WMM, Hotmix
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km 45
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 4.5
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 629.8
etc.
Page 1 of 171
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 1336.8
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 19
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 550
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km 12
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 45
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 629.8
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 4.5
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 1704.6
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1320
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour input
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 5510
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 3000
P&M-076 Compressor with guniting equipment along with accessories hour input
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour input
P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour input
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 935
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs input
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour input
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour input
Page 2 of 171
(B) Labour
Page 3 of 171
(C) Materials
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 300
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 300
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 300
M-009 Granular Material or hard murrum for GSB works at Site Cum 250
M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 365
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant Cum 250
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) Cum 800
Rate at Plant
Description Unit
(HMP/Batching)
Rate at Site
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 250 500
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 250 500
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 250 500
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 250 500
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 250 500
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 250 500
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm 250 500
M-020 Close graded Granular sub-base Material 2.36 mm cum 250 500
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 230 500
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 250 500
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm 250 500
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 250 500
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 250 500
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 250 500
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 250 500
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 250 500
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 250 500
Page 4 of 171
M-042 Aggregates 13.2 mm to 0.09 mm cum 230 450
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos input
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the
M-066 nos 12000
process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne nos input
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel
M-068 nos 10000
mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all comp
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos input
M-082 Cold twisted bars (HYSD Bars)/ TMT Bars tonne 42000
M-089 Credit for excavated rock found suitable for use cum 55
Page 5 of 171
M-090 Curing compound liter 75
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 488.8
M-092 Earth Cost or compensation for earth taken from private land cum 41
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause
M-093 metre 1.3
915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1000
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 300
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 50
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm input
Lime kg 45
Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
M-127 metre input
comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
M-128 metre input
containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 214
M-136 Pesticide kg 35
Page 6 of 171
M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 86.04
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 6
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg input
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 3951.7
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 5341.41
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 214
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre input
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre input
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre input
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre input
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre input
RMC- M 20 Cum
RMC- M 25 Cum
M-159 Sand bags (Cost of sand and Empty cement bag) nos input
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 4
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 300
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each input
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each input
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos input
M-173 Steel helmet and cushion block on top of pile head during driving. kg input
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm input
Page 7 of 171
M-183 Tie rods 20mm diameter nos 457
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 100
M-189 Water KL 50
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each input
Page 8 of 171
Overheads for Road Works 7.0%
Overheads for Bridge Works 7.0 % for input of Overheads or Contractors profit please type in collum C as like below
Type symble of apostrope(') then input value then one space then symble of
Overheads for Bridge Works (Rehabilitation) 7.0 %
percentage (%) for example '08 %
Page 9 of 171
Description Unit Quantity Rate Rs Cost Rs Remarks
Excavation
Unit = cum
Taking output = 10 cum
Mechanical Means
a) Labour
Mate day 0.20 196.00 39.20
Mazdoor day 5.00 196.00 980.00
b) Machinery
Air Compressor 250 cfm with 2 leads of hour 6.00 370.00 2220.00
pneumatic
Total breaker 3239.20
Add 3% for water and Power charges 97.18
Add 12.5% for EPF on labour Charges of Rs. 1019.20 127.40
Total 3463.78
Add @ 15% Contractor's profit 519.57
Total 3,983.34
Add 4% for WCT 159.33
Add @1% for Labour Cess 39.83
Cost for 10 cum = a+b+c+d 8,165.85
Rate per cum = (a+b+c+d)/10 816.59
say 817.00
1. Cost of dewatering upto10 per cent of (a+b), may
be added, where required Assessment for
dewatering shall be made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug
and hence not included.
Filling the approved good quality earth in plinths,
area development etc. wherever specified in layers
of not exceeding 150 mm thick including breaking
clods, watering, compacting each layer with vibratory
compactor and at un-accessible places with woode
say 142.00
say 520.00
Providing & filling sand for foundation pits and
wherever specified including filling in 150mm layers
and compacting to the required levels,all leads and
lifts, etc.,complete.
Unit = cum
Taking output = 1 cum
a) Labour
Mate day 0.01 196.00 1.96
Mazdoor day 0.30 196.00 58.80
b) Material
Sand (assuming 20 per cent voids) cum 1.20 1,350 1620.00
Total 1680.76
Add 3% for water and Power charges 50.42
Add 12.5% for EPF on labour Charges of Rs. 60.76 7.60
Rate per cum = a+b+c+d 1738.78
Add @ 15% Contractor's profit 260.82
Total 1999.59
Add @ 4% WCT 79.98
Add Labour Cess @1.0% 20.00
Total 2099.57
say 2,100.00
Carting away debris and other like materials and
waste generated from other agencies outside to the
designated areas identified by the local authorities
for dumping of such materials as instructed by the
project incharge.
Unit = cum
Taking output = 6 cum
a) Labour
Mate day 0.12 196.00 23.52
Mazdoor for loading & unloading of debris day 3.00 196.00 588.00
b) Machinery
Tractor-trolley for transportation hour 1.00 345.00 345.00
Total 956.52
say 208.00
PCC 1:5:10 in Foundation
Unit = cum
Taking output = 1cum
a) Labour
Mate day 0.05 196.00 9.80
Mason day 0.13 237.00 30.81
Mazdoor day 1.43 196.00 280.28
b) Material
40 mm Aggregate cum 0.92 800 736.00
coarse Sand cum 0.48 1,350 648.00
cement tonne 0.13 6,000 780.00
Cost of water KL 1.20 50 60.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 0.40 345.00 138.00
Generator 33 KVA hour 0.40 240.00 96.00
Water tanker 6 KL capacity hour 0.13 345.00 44.85
Total 2823.74
Add 3% for water and Power charges 84.71
Add 12.5% for EPF on labour Charges of Rs. 320.89 40.11
Cost for 1 cum = a+b+c+d+e 2948.56
Add @ 15% Contractor's profit 6.02
Total 2954.58
Add @ 4% WCT 118.18
Add Labour Cess @1.0% 29.55
Total 3102.31
say 3932.00
Vibrator is a part of minor T & P which is already
included in overhead charges of the contractor.
PCC 1:3:6 in Foundation
Unit = cum
Taking output = 1cum
a) Labour
Mate day 0.04 196.00 8.43
Mason day 0.07 237.00 15.88
Mazdoor day 1.00 196.00 196.00
b) Material
40 mm Aggregate cum 0.90 800.00 720.00
coarse Sand cum 0.45 1,350.00 607.50
cement tonne 0.23 6,000.00 1380.00
Cost of water KL 1.20 50.00 60.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 0.40 345.00 138.00
Generator 33 KVA hour 0.40 240.00 96.00
Water tanker 6 KL capacity hour 0.13 345.00 44.85
Total 3266.66
Add 3% for water and Power charges 98.00
Add 12.5% for EPF on labour Charges of Rs. 220.31 27.54
Per Cum Basic Cost of Labour, Material &
3393.00
Machinery (a+b+c)
TOTAL 3,392.20
say 4096.00
Vibrator is a part of minor T & P which is already
included in overhead charges of the contractor.
Plain/Reinforced Cement Concrete in Open
Foundation complete as per Drawing and
Technical Specifications.
PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.86 196.00 168.56 L-12
Mason day 1.50 237.00 355.50 L-11
Mazdoor day 20.00 196.00 3920.00 L-13
b) Material
40 mm Aggregate cum 8.10 800.00 6480.00 M-055
20 mm Aggregate cum 4.05 1,084.00 4390.20 M-053
10 mm Aggregate cum 1.35 1,084.00 1463.40 M-051
coarse Sand cum 6.75 1,350.00 9112.50 M-005
cement tonne 3.45 6,000.00 20700.00 M-081
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 345.00 2070.00 P&M-009
Generator 63 KVA hour 6.00 240.00 1440.00 P&M-019
50100.16
Add 3% for water and Power charges 1503.00
Add 12.5% for EPF on labour Charges of Rs. 4444.06 555.51
say 4368.00
say 5168.00
RCC Grade M20
With Batching Plant, Transit Mixer and Concrete
Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 6,000.00 249960.00 M-081
Coarse Sand cum 54.00 1,350.00 72900.00 M-004
20 mm Aggregate cum 64.80 1,084.00 70243.20 M-053
10 mm Aggregate cum 43.20 1,084.00 46828.80 M-051
b) Labour
Mate day 0.84 196.00 164.64 L-12
Mason day 3.00 237.00 711.00 L-11
Mazdoor day 18.00 196.00 3528.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1,670.00 10020.00 P&M-002
Generator 100 KVA hour 6.00 1,090.00 6540.00 P&M-080
Loader 1 cum capacity hour 6.00 1,320.00 7920.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 1,336.80 20052.00 P&M-049
Lead beyond 1 km, L-lead in km tonne.km 300L 19.00 34200.00 P&M-050
Concrete Pump hour 6 Lead= 6 km
3780.00 P&M-007
630.00
RMC cum 120.00 0.00
526847.64
Add 12.5% for EPF on labour Charges of Rs. 4403.64 550.46
Per Cum Basic Cost of Labour, Material &
4395.00
Machinery (a+b+c)
d) Formwork @ 4 per cent on cost of concrete -
i.e. cost of material, labour and machinery
TOTAL 4,395.00
say 5307.00
3 TOTAL 14,797.12
Add 12.5% towards P.F contribution on labour
4 246.00
charges of Rs.1968/- (Rs.984/- per RM)
5 TOTAL (3+4) 15,043.12
7 TOTAL 17,299.59
10 G/Total 18,164.57
Say 9,082.00
3 TOTAL 2,496.00
Add 12.5% towards P.F contribution on labour
4 37.50
charges of Rs.300
5 TOTAL (3+4) 2,533.50
7 TOTAL 2,913.53
10 G/Total 3,059.20
Say 10,034.00
Remarks
176,331.00
328,632.00
504,963.00
16-Jan-11
Rate analysis for Tandoor Flooring
1 Materials-
Total 16.48
VAT @ 4% 0.66
Transportation , Loading & un loading(Rs.3000/- per
2.00
1500 Tiles
2 Labour Charges
For Laying 10.00
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.003 3,725.00 11.18
TOTAL 53.31
7 TOTAL 57.79
9 TOTAL 66.46
10 Add WCT @ 4% on (9) 2.66
11 Add Labour Cess @ 1% on (9) 0.66
12 G/Total 69.78
TOTAL
Add 1% for water charges
TOTAL
Add 15% for contractor’s profit and overheads
Cost for 2.2 sqm.
Cost of 1 sqm.
Add 4% for WCT
Add @1% for Labour Cess
TOTAL
Say
Quantity Rate Amount
48 157 75.36
2 74 148.00
1 175 175.00
1 45 45.00
1 125 125.00
-
2.1 107.6 225.96
5,227.46
52.2746
5279.7346
1055.94692
6335.68152
2879.855236
115.19
28.80
3,023.85
3,024.00
Rate analysis for Tandoor Flooring
1 Materials-
Total 20.60
VAT @ 4% 0.82
Transportation , Loading & un loading(Rs.3000/- per
1500 Tiles
2 Labour Charges
For Laying 10.00
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.002 3,725.00 7.45
TOTAL 48.87
7 TOTAL 52.84
9 TOTAL 60.77
10 Add WCT @ 4% on (9) 2.43
11 Add Labour Cess @ 1% on (9) 0.61
12 G/Total 63.80
1 Materials-
Total 20.60
VAT @ 4% 0.82
Transportation , Loading & un loading(Rs.3000/- per
1500 Tiles
2 Labour Charges
For Laying 18.00
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.002 3,725.00 7.45
TOTAL 56.87
7 TOTAL 62.08
9 TOTAL 71.39
10 Add WCT @ 4% on (9) 2.86
11 Add Labour Cess @ 1% on (9) 0.71
12 G/Total 74.96
Total 17.47
VAT @ 4% 0.70
Transportation , Loading & un loading(Rs.3000/- per
2.00
1500 Tiles
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.0030 3,725.00 11.18
TOTAL 56.34
TOTAL 58.03
7 TOTAL 61.53
9 TOTAL 70.76
12 G/Total 74.30
Say 799.00
Say 3,725.00
TMT Bars
3 Labour Charges
Total
Add 1% for water charges
Cost of one MT
12 G/Total
Cost of MT
Say
TMT Bars
3 Labour Charges
Cutting and Placing of TMT Bars(average Rate
MT 1.00 4,400
incl Lifting Charges)
Total
Add 1% for water charges
Cost of one MT
12 G/Total
Cost of MT
Say
188
5.22 : Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and bi
12 G/Total
Cost of MT
Say
Amount Remarks
44,100.00
480.00
2,800.00
2500
2750
47,380.00 3025
473.80
350.00
48,203.80
7,230.57
55,434.37
2,217.37
554.34 55,988.71
58,206.09
58,206.09
58,206.00
Amount Remarks
44,100.00
480.00
4,400.00
2500
2750
48,980.00 3025
489.80
550.00
50,019.80
7,502.97
57,522.77
2,300.91
575.23 58,098.00
60,398.91
60,398.91
60,399.00
Amount
4,252.50
-
52.00
48.00
258.00
196.00
26.91
4,833.41
48.33
56.75
4,938.49
740.77
5,679.27
227.17
56.79
5,963.23
59,632.32
59,632.00
Steel Door Frame
5 Add for fixing of Door @ Rs.250 per No i.e 5.28 Mtr 47.35
6 Add for PCC in 1:3:6 for Fill up in Frame Cum 0.02 3824 90.86
Add for EPF @12.5% on Labour Charges .Rs. 47.35 5.92
7 G/Total 364.54
8 Add 15%’for contractor’s profit and overheads 54.68
9 TOTAL 419.22
12 G/Total 440.18
Say 440.00
Remarks
Rate Analysis Of Formwork For Normal Slab .
Total= 30
Add for Wastage @ Avg. 8% 2.38
Total No Of Sheets= 32.09
Say 32 1468.00 46,976.00
Considering 6 repeatitions 7,829.33 7,829.33
Cost of Steel Plates 2'x3'x2mm
3.0 Slab (Item I-C) sqm 84.996 925.00 78,621.30
Considering 30 repeatitions 2,620.71 2,620.71
Materials:
I. Calculation Of Plywood For Beams and Steel Plate Shuttering for Slab:
Materials:
I. Calculation Of Plywood For Beams and Steel Plate Shuttering for Slab:
509
11.31 : Extra for pre finished nosing in treads of steps of Kota stone/ sand stone slab.
Code Description Unit
Details of cost for 10m
Labour-
0126 Stone mason (ornamental) Day
TOTAL
Add 1 % for water charges
TOTAL
Add 15% for contractor’s profit and overheads
TOTAL
Cost for 10 sqm.
Cost for lsqm.
Say
11.32 : Extra for Kota stone/ sand stone in treads of steps and risers using single length
upto 1.05 metre .
Code Description Unit
Details of cost for 10sqm.
Labour-
124 Mason 2nd class Day
114 Beldar Day
TOTAL
Add 1 % for water charges
TOTAL.
Add 15% for contractor’s profit and overheads
Cost for 10 sqm.
Cost for 1 sqm.
Say
Quantity Rate Amount
1 20 20.00
4 200 800.00
208.13 1 208.13
1,028.13
10.28
1,038.41
155.76
1,194.17
119.42
119.00
3 141.6 424.80
3 135.25 405.75
1 135.25 135.25
7 138.45 969.15
174.98 1 174.98
5,800.96
58.01
5,858.97
878.85
6,737.82
673.78
674.00
2 Total 691.00
9 G/Total 855.24
Say 855.00
2 Total 988.00
9 G/Total 1,194.12
Say 1,194.00
Remarks
11.38 : Providing and laying of Dado with Ceramic glazed tiles 200x300 mm(thickness to be specified
by the manufacturer) of 1st quality conforming to IS : 15622 of approved make in all colours , shades,
except White, Ivory, Grey, Fume Red Brown laid on 20mm thick bed of Cement Mortar 1:4(1 Cement:
4 Coarse sand) including pointing the joints with white cement and matching pigments etc., complete.
4 TOTAL 708.61
Say 823.00
Say 3,725.00
Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption’s less than
0.08% and conforming to IS : 15622 of approved make, colour and shade, laid on 20mm thick cement mortar 1:4(1 cement: 4 coarse sand)
including grouting the joints with white cement and matching pigments etc., complete.
TOTAL 1,193.82
2 Add for water charges @ 1% 11.94
TOTAL 1,205.76
3 Add for EPF @12.5% on Labour Charges .Rs. 162.12 20.27
4 G/Total 1226.02
9 G/Total 1,480.42
Say 1,480.00
Black Cudapah for Raisers & threads Sqft 1.00 40.00 40.00
Total 41.20
VAT @ 4% 1.65
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.0027 3,725.00 10.06
TOTAL 111.91
TOTAL 115.26
7 TOTAL 122.64
9 TOTAL 141.03
12 G/Total 142.44
Say 1,533.00
Say 3,725.00
Rate analysis for Cladding with Black Kudapah
Total 41.20
VAT @ 4% 1.65
Transportation , Loading & un loading(Rs.3000/- per
2.00
1500 Tiles
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.0027 3,725.00 10.06
TOTAL 67.91
TOTAL 69.94
7 TOTAL 71.57
9 TOTAL 82.30
12 G/Total 83.13
Say 894.00
Say 3,725.00
612
13.26 Providing and applying plaster of paris putty of 2 mm thickness over plastered surface
to prepare the surface even and smooth complete
13.43 Applying one coat of cement primer of approved brand and manufacture on wall
surface
13.43.1 Cement primer Unit Quantity Rate
Code Description
13.42 Distempering with 1st quality acrylic washable distemper (ready made) of approved
manufacturer and of required shade and colour complete, as per manufacturer’s
specification..
13.42.1 Two or more coats on new work.
G/Total
9 G/Total
Say
13.26 Providing and applying plaster of paris putty of 2 mm thickness over plastered surface
to prepare the surface even and smooth complete
13.43 Applying one coat of cement primer of approved brand and manufacture on wall
surface
13.43.1 Cement primer Unit Quantity Rate
Code Description
13.44 Finishing walls with water proofing cement paint of required shade
13.44.1 New work (Two or more coats applied @ 3.84 kg/10 sqm).
Code Description Unit Quantity Rate
Detail of cost for 10 sqm
MATERIALS
851 Water proofing cement paint kilogram 3.84 45.00
9999 Carriage of material L.S 1.56 1.00
LABOUR
131 Painter Day 0.46 300.00
115 Coolie Day 0.23 180.00
101 Bhisti Day 0.10 180.00
9999 Brushes, sand paper etc L.S 7.15 1.00
9999 Sundries L.S 8.06 1.00
TOTAL
Add 1 % for water charges
TOTAL
Add 15% for contractor’s profit and overheads
Cost of 10.00 sqm
Cost of 1.00 sqm
Say
G/Total
7 Add WCT@4% on (6)
8 Add Labour Cess @1% on (6)
9 G/Total
Say
13.46 Finishing walls with Acrylic Smooth exterior paint of required shade : —
13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including base
coat of water proofing cement paint applied @ 2.20 kg/ 10 sqm).
Code Description Unit Quantity Rate
9 G/Total
Say
Say
TOTAL
Add 1 % for water charges
TOTAL
Add 15% for contractor’s profit and overheads
Cost of 10.00 sqm
Cost of 1.00 sqm
9 G/Total
Say
Say
over plastered surface
Amount
66.70
0.00
227.50
163.80
83.98
541.98
5.42
547.40
82.11
629.51
62.95
63.00
nufacture on wall
Amount
84.00
0.00
100.00
36.00
8.06
228.06
2.28
230.34
34.55
264.89
26.49
26.00
y made) of approved
per manufacturer’s
Amount
60.00
0.00
11.57
100.00
82.80
8.06
262.43
2.62
265.05
39.76
304.81
30.48
30.00
119.00
4.76
1.19
124.95
125.00
Amount
69.00
3.90
273.00
163.80
83.98
593.68
5.94
599.62
89.94
689.56
68.96
69.00
nufacture on wall
Amount
87.50
7.15
100.00
36.00
8.06
238.71
2.39
241.10
36.16
277.26
27.73
28.00
Amount
172.80
1.56
138.00
41.40
18.00
7.15
8.06
386.97
3.87
390.84
58.63
449.47
44.95
45.00
142.00
5.68
1.42
149.10
149.00
Amount
1291.20 1291.2
12.91
1304.11
195.62
1499.73
149.97
0.00
1.50
151.47
151.00
151.00
1076.00 1076
10.76
1086.76
163.01
1249.77
124.98
0.00
1.25
126.23
126.00
126.00
Fabrication and fixing of MS Grill
Sl no Item Unit Qty
Fabrication
and fixing of
1 Kg 1.00
MS Grill (as
per PO)
2 Total
9 G/Total
9.48 Providing and fixing M.S. grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. all complete.
9.48.1 Fixed to steel windows by welding.
Code Description
Details of cost for a grill 90x120cm =
1.08sqm.
Material-
M.S. bar 16mm diameter- 11x86cm = 9.46m.
@ 1.58kg/m= 14.95kg+
Add wastage @ 10% = 1.50kg.
= 16.45kg. Say 0.165 quintal
1003 M.S.bar
M.S. flat 25x3.15mm
2xl20cm = 2.40m+
2x90cm= 1.80m+
lxl20cm= 1.20m+
2x15cm = 0.30m
=5.70m
5.70m @ 0.63kg/m = 3.59kg+
Add wastage @ 10% = 0.36kg.
= 3.95kg. Say 4 kg. or 0.04 quintal
1008 M.S. flat
2205 Carriage of steel 0.165 + 0.04 = 0.205 q =
0.0205 t Say 0.02 tonne
9999 Sundries
9999 Welding charges
Labour-
102 Blacksmith 1st class
114 Beldar
TOTAL
Add for water charge @ 1 %
TOTAL
Add for contractor’s profit and overheads @
1,500%
Cost for 18.54 kg.
Cost for 1 kg.
Say
9.48 Providing and fixing M.S. grills of required pattern in frames of windows etc. with
M.S. flats, square or round bars etc. all complete.
9.48.2 Fixed to openings /wooden frames with rawl plugs screws etc.
Code Description
Details of cost for a grill 90x120cm =
1.08sqm.
Material-
M.S. bar 16mm dia. 11x86cm = 9.46m.
@ 1.58kg/m= 14.95kg+
Add wastage @ 10% = 1.50kg.
= 16.45kg. Say 0.165quintal
1003 M.S. bar
M.S. flat 25x3.15mm
2xl20cm = 2.40m+
2x90cm= 1.80m+
lxl20cm= 1.20m+
2xl5cm = 0.30m
=5.70m
5.70m @ 0.63kg/m = 3.59kg+
Add wastage @ 10% = 0.36kg.
= 3.95kg. Say 4 kg. or 0.04 quintal
1008 M.S. flat
2205 Carriage of steel 0.165 + 0.04 = 0.205 q =
0.0205 tonne. Say 0.02 tonne
9999 Sundries
9999 Welding charges
Labour-
102 Blacksmith 1st class
114 Beldar
7048 Rawl plug 50 mm (designation 10 no)
9999 Fixing of rawl plugs
TOTAL
Add for water charge @ 1 %
TOTAL
Add for contractor’s profit and overheads @
15
Cost for 18.54 kg.
Cost for 1 kg.
Say
S Grill
Rate Amount Remarks
75.00 75.00
75.00
1.88
76.88
11.53
88.41
-
0.88
89.29
Say 89.00
350
n frames of windows etc. with
1 193.95
64.4
64.4
06/17/2020
8 TOTAL 604.31
9 Add @ 4% for WCT on (8) -
10 Add @ 1% for Labour Cess on (8) 6.04
11 Total 610.36
Say 610.00
181
5.16 : Providing Cast-in situ reinforced cement concrete, cost of required centring, shuttering and finishing with neat
cement punning on exposed surfaces but excluding the cost of reinforcement with 1:2:4 (1 ce
LABOUR -
Extra labour for laying cement concrete in -
RCC work due to delay etc. -
114 (B) Beldar Day .016 180 2.88
101 (B) Bhishti Day .0032 180 0.58
123 (B) Mason 1st class Day .0006 300 0.18
124 (B) Mason 2nd class Day .0006 250 0.15
128 (B) Mate Day .0006 190 0.11
TOTAL 457.05
(C) Add for water charges @ 1 % 4.57
915.74
Cost for 0.0162 cum 544.00
Cost for 1 cum. 33,580.33
Say 33,580.00
Cost of Reinforcement
0.1 51500 5150
Cost of Wire Mesh 0.6
38,730.00
4.1 Providing and laying in position cement concrete of specified grade excluding the
cost of centring and shuttering -
-All work upto plinth level:
4.1.3 1:2:4 ( 1 Cement: 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)
1 Materials-
Total 100.00
VAT @ 4% 4.00
TOTAL 104.00
TOTAL 104.00
10 G/Total 124.38
Say 124.00
Cement Mortar 1 : 4 (1 cement : 4 coarse sand)
Say 3,412.00
4/14/2011
1 Materials-
Wastage @ 5% 2.00
Total 42.00
VAT @ 4% 1.68
2 Labour Charges
TOTAL 64.86
9 TOTAL 74.58
10 Add WCT @ 4% on (9) -
11 Add Labour Cess @ 1% on (9) 0.75
12 G/Total 75.33
Say 811.00
Rate analysis for Black Kudapah Strips
Total 148.65
VAT @ 4% 5.95
2 Labour Charges
Cement mortar 1:4( Rate as per item No. 3.9) cum 0.0027 3,725.00 10.06
TOTAL 197.45
7 TOTAL 207.48
9 TOTAL 238.60
12 G/Total 250.53
Say 3,725.00
06/17/2020
EXTRA ITEM
Water Proofing of Sunken Slabs including Surface preparation with wire brush and applying of acrylic polimer modified
cementation watter proofing compound Brush bond RFX (elstro meric) laid over wall and including overlapping in raft slab in
two coats (
2 Labour Charges
a) For wire brushing & Applying Water proofing compond Sqft 6.00
6 Total 35.70
8 TOTAL 41.05
Say 446.00
Providing & applying 12mm thick plaster in CM 1:3 (1 cement 3 coarse sand )
TOTAL 1,774.97
Add 3% for water and Power charges 53.25
Add 12.5% for EPF on labour Charges of Rs. 1,113.64 139.21
TOTAL 1,967.42
Add for contractor’s profit and overheads @ 15% 295.11
TOTAL 2,262.54
Add 4% for WCT -
Add @1% for Labour Cess 22.63
Cost for 10 sqm. 2,285.16
Say 229.00
Sl No Description Unit Quantity Rate Amount Remarks
Say 4,505.00
Providing & applying 10 mm thick plaster in CM 1:3 on Sunken Slabs
Sl No Description Unit Quantity Rate Amount Remarks
TOTAL 1,661.42
3 Add 3% for water and Power charges 49.84
Add 12.5% for EPF on labour Charges of Rs. 1,113.64 139.21
4 TOTAL 1,850.47
Add for contractor’s profit and overheads @ 15% 277.57
5 Total 2,128.04
Say 215.00
Say 4,505.00
0.00258
0.1146667
185.05
Expansion joint
Base Rate RM 990
TOTAL
incl 1% power
Say
990.00
9.90
999.90
149.99 5372
1,149.89
-
11.50
1,161.38
1,161.38
1,161.00
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 250.00 20.00 L-12
Mazdoor day 2.000 180.00 360.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 290.00 812.00 P&M-031
Air compressor 250 cfm hour 2.800 370.00 1036.00 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.000 940.00 1880.00 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 345.00 345.00 P&M-060
c) Material
Bitumen emulsion @ 0.6 kg per sqm tonne 2.100 46962.00 98620.20 M-077
Cost of water KL 6.000 50.00 300.00 M-189
d) Overhead charges @ 8 % on (a+b+c) 8269.86
e) Contractor's profit @ 10 % on (a+b+c+d) 11164.31
Cost for 3500 sqm = a+b+c+d+e 122807.36
Rate per sqm = (a+b+c+d+e)/3500 35.09
say 35.00
Bitumen primer has been provided @ 0.60 kg per sqm as
per clause 502.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
5.2 Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.50 kg per
sqm on the prepared bituminous/granular surface cleaned
with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 250.00 20.00 L-12
Mazdoor day 2.000 180.00 360.00 L-13
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 290.00 812.00 P&M-031
Air compressor 250 cfm hour 2.800 370.00 1036.00 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 940.00 1880.00 P&M-004
c) Material
Bitumen emulsion @ 0.5 kg per sqm tonne 1.750 31463.00 55060.25 M-077
d) Overhead charges @ 8 % on (a+b+c) 4733.46
e) Contractor's profit @ 10 % on (a+b+c+d) 6390.17
Cost for 3500 sqm = a+b+c+d+e 70291.88
Rate per sqm = (a+b+c+d+e)/3500 20.08
say 20.00
1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.
Page 1 of 171
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 250.00 210.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 180.00 2880.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 19550.00 117300.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2530.00 15180.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 450.00 2700.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1320.00 7920.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.50 12150.00 Lead =6
km & P&M-
058
Add 10 per cent of cost of carriage to cover cost of loading 1215.00
and unloading
smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 746.50 2911.35 P&M-044
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 1704.00 6645.60 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1320.00 5148.00 P&M-045
roller.
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 36400.00 696332.00 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.190 560.00 35386.40 M-049
25 - 10 mm 13 per cent cum 37.340 1025.00 38273.50 M-046
10 -4.75 mm 19 per cent cum 54.580 750.00 40935.00 M-040
4.75 mm and below 44 per cent cum 126.390 623.00 78740.97 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3800.00 32756.00 M-188
or
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 86.160 1025.00 88314.00 M-046
10 - 5 mm 28 per cent cum 80.430 750.00 60322.50 M-040
5 mm and below 40 per cent cum 114.900 623.00 71582.70 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 3800.00 32756.00 M-188
* Any one of the alternative may be adopted as per
approved design
For Grading I ( 40 mm nominal size )
d) Overhead charges @ 5 % on (a+b+c) 54896.69
e) Contractor's profit @ 10 % on (a+b+c+d) 115283.05
Page 2 of 171
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 250.00 210.00 L-12
Mazdoor working with HMP, mechanical broom, paver, day 16.000 180.00 2880.00 L-13
roller, asphalt cutter and assistance for setting out
lines, levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 250.00 1250.00 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 19550.00 117300.00 P&M-022
Paver finisher hydrostatic with sensor control @ 75 hour 6.000 2530.00 15180.00 P&M-034
cum per hour
Generator 250 KVA hour 6.000 450.00 2700.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 1320.00 7920.00 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 4.50 12150.00 Lead =6
km & P&M-
058
Page 3 of 171
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Page 4 of 171
Remarks/
Sr No Description Unit Quantity Rate Rs Cost Rs
Input ref.
Page 5 of 171