Procedure For Desilting The Basin

The document provides a plan for desilting a basin that is 6 meters deep. It involves closing and opening gates to flush sand from both the western and eastern sections of the basin until the sand level is reduced by 0.5 meters. Safety measures are in place and the work is done in phases by an operator and team monitoring water levels and adjusting inlet gates. Tools, equipment, and risk mitigations are identified.

Uploaded by

Ddumba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
216 views2 pages

Procedure For Desilting The Basin

The document provides a plan for desilting a basin that is 6 meters deep. It involves closing and opening gates to flush sand from both the western and eastern sections of the basin until the sand level is reduced by 0.5 meters. Safety measures are in place and the work is done in phases by an operator and team monitoring water levels and adjusting inlet gates. Tools, equipment, and risk mitigations are identified.

Uploaded by

Ddumba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

WESTERN BASIN

EASTERN BASIN

SLIDING GATES
DIRECION OF WATER

The above is a sketch of our desilting basin which is 6.0m deep. We measure sand level from
the middle of the basin and we desilt at sand level of 0.5m.
The down gates are the flushing gates.

Equipment:
COMPANY LOGO
EXECUTION JOB BUG.000.001
PLAN 001 Total duration :

Equipment Name: Desilting Basin


Location: Intake.
Job plan description: Ensure all the safety measures are in place, Desilt the Basin

Operational phases

Run
Duration
Op # Description or
hrs
Stop
A Preparatory work Run
B Operation of western Desilting basin Run
C Operating the Eastern Desilting basin Run
D Normalization Run

Work procedure
Op # Steps Description of work Responsible
A1 Prepare the Work permit and JSA.
A A2 Tools and PPE
A3 Safety Manager introduces the task to his team.
B B1 Manually Close the basin inlet gate to 20Cm.
B2 Close the western Desilting Basin out let gate fully
B3 Open the flushing gates for western Desilting Basin Fully
B4 Monitor the volume of water in the western basin
B5 Manually adjust western Desilting basin inlet gate for faster
flushing of sand (silt) until the basin is empty of sand.
B6 Close the flushing gates for western Desilting Basin Fully
B7 Open the western desilting basin inlet gate fully
B8 Open the western Desilting Basin out let gate fully
C1 Manually Close the basin inlet gate to 20Cm.
C2 Close the eastern Desilting Basin out let gate fully
C3 Open the flushing gates for eastern Desilting Basin Fully
C4 Monitor the volume of water in the eastern basin
C Manually adjust eastern Desilting basin inlet gate for faster
C5
flushing of sand (silt) until the basin is empty of sand.
C6 Close the flushing gates for eastern Desilting Basin Fully
C7 Open the eastern desilting basin inlet gate fully
C8 Open the eastern Desilting Basin out let gate fully
D1 Insure that every body is out of Desilting basin area
D D2 Close and lock all desilting basin access dores
D3 Report the entire work done in the MTCP system.

Manpower required
Op # Quantity Designation
A Operator and 3 casuals
B Operator and 3 casuals
C Operator and 3 casuals
D Operator

Materials/Spares required
Op # Code Quantity Unit Description
E1 PPE
E2 1 pc WORK PERMIT
A
E3 1 pc Risk analysis
E4 8 pcs procedure

Tools required
Op # Code Quantity Unit Description
B 2 pcs Big and small size opening handles.
C 2 pcs Big and small size opening handles.

Safety analysis (Risk assessment)


Op # Hazard Risk Mitigation
Water way tasks Drowning Put on safety jacket
B &C Sharp Objects Cuts Use cotton gloves
Work at a height Falling Use harness
A Driving to site Accident Drive carefully

Participant Names Signature Date


Team leader
1
2
3
4
5