60-0000-L-SPE-0001 Rev 2 - Spec For Plant and Piping Layout PDF
60-0000-L-SPE-0001 Rev 2 - Spec For Plant and Piping Layout PDF
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 2 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
TABLE OF CONTENTS
1. SCOPE ..........................................................................................................................5
2. CODES, STANDARDS AND SPECIFICATIONS ...........................................................5
2.1 KAZAKH CODES AND STANDARDS ........................................................................5
2.2 INTERNATIONAL CODES AND STANDARDS ..........................................................6
2.3 PROJECT SPECIFICATIONS ....................................................................................6
2.4 GENERAL REQUIREMENTS .....................................................................................7
3. ABBREVIATIONS AND DEFINITIONS..........................................................................7
4. INTRODUCTION............................................................................................................8
4.1 BASIS OF DESIGN ....................................................................................................8
5. EQUIPMENT PLANT LAYOUT.......................................................................................10
5.1 PUMPS.....................................................................................................................10
5.2 COMPRESSORS .....................................................................................................10
5.3 VESSELS .................................................................................................................11
5.4 EXCHANGERS ........................................................................................................11
5.5 AIR COOLERS .........................................................................................................12
5.6 FIRED HEATERS AND BOILERS ............................................................................12
5.7 PIPEWAYS...............................................................................................................13
5.8 STORAGE TANKS ...................................................................................................13
5.9 BUILDING SITING IN PROCESS PLANTS ..............................................................15
5.10 EQUIPMENT LOCATION......................................................................................16
5.11 CLEARANCE AND ACCESSIBILITY.....................................................................17
5.12 PLATFORMS,STAIRS & LADDERS- ACCESS & LAYOUT REQUIREMENTS .....19
5.13 PIPE SUPPORTS, ANCHORS AND GUIDES.......................................................21
5.14 UNDERGROUND PIPING.....................................................................................22
6. EQUIPMENT PIPING LAYOUT ...................................................................................23
6.1 GENERAL REQUIREMENTS ...................................................................................23
6.2 PUMP AND TURBINE PIPING .................................................................................23
6.3 COMPRESSOR PIPING...........................................................................................25
6.4 VESSEL AND COLUMN PIPING..............................................................................26
6.5 EXCHANGER PIPING..............................................................................................26
6.6 AIR COOLED EXCHANGER PIPING .......................................................................27
6.7 HEATER AND BOILER PIPING................................................................................28
6.8 PIPEWAY PIPING ....................................................................................................28
6.9 STORAGE TANK PIPING.........................................................................................30
7. VALVING AND PIPING ITEMS....................................................................................30
7.1 PROCESS REQUIREMENTS...................................................................................30
7.2 OPERATIONAL REQUIREMENTS...........................................................................30
7.3 MAINTENANCE REQUIREMENTS ..........................................................................31
7.4 VALVE ACCESS (for valves not accessible from grade)...........................................32
7.5 LINE VENTS AND DRAINS......................................................................................32
7.6 SAMPLE CONNECTIONS........................................................................................33
7.7 LINE BLINDS............................................................................................................33
7.8 FLANGES & BOLTING.............................................................................................35
8. SERVICE PIPING ........................................................................................................36
8.1 STEAM PIPING ........................................................................................................36
8.2 HEAT TRACING AND WINTERISING ......................................................................36
8.3 UTILITY STATIONS .................................................................................................37
8.4 EMERGENCY SAFETY SHOWERS ........................................................................37
Page 3 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 4 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
1. SCOPE
This document defines the requirements for the above ground spacial arrangement
of equipment, piping and associated facilities within the property limits of the plant.
The layout shall be developed in line with acceptable standards of - safety,
constructability, operability and maintenance for the Asset Development Projects,
which are to be undertaken at Tengizchevroil’s facility at Tengiz in the Republic of
Kazakhstan.
The Power & Steam Utilities Area and parts of the Sulphur recovery units are
arranged as a single combined unit, taking into account dictates of, Process and
Vendor requirements and are a standard industry design and therefore are not
restricted by the requirements of the spacing chart in appendix ‘A’.
Layout & Piping discipline shall take overall responsibility for the space management
of all above ground facilities and plot plan layouts.
Page 5 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 6 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Separate specifications cover the special requirements for surface water and,
sewer drainage systems and electrical installations. Other conditioning
requirements shall apply to fire protection systems, heating, ventilating, air
conditioning and water systems serving buildings.
Standard vent, drains, and instrument connection details are contained in the
"Specification for Piping Material Classes".
Reference shall be made to the project line Designation Tables for indication
of the design and operating pressures and temperatures.
Page 7 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
4. INTRODUCTION
SID induction courses shall be held for all new starters. SID
checklists shall be applied in all Design Review sessions. The site
will be divided into separate areas with fire and maintenance
access roads between and around the perimeter. New flares will be
grouped within the existing flare area. No process equipment shall
be located under the piperacks. All high fire / explosion risk
equipment shall be identified and provisions made for fireproofing
and fire monitor / deluge protection systems.
The plant layout shall utilise the input and experience of the
Operations of the Maintenance departments. Clear operator access
and egress, double width platforms and high-level, and link
platforms and stairways shall be provided. The modern control
technology shall reduce the number of site operator requirements.
Page 8 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
4.1.5 Constructability
The plant layout shall utilise the input and experience of the
Construction department. All heavy lifts shall be carried out from
one side of the central piperack to minimise crane movements.
Provision shall be made for construction lay down areas close to
the unit. The layout is primarily of stick built design. The
engineering design shall be aligned with the Construction Work
Package philosophy.
Page 9 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Spacing Tables
The spacing tables in Appendix ‘A’, B and ‘C’ give minimum spacing guidelines for
the following:
• Plant to plant
• Plant to property line
• Plant to equipment
• Equipment to equipment
5.1 PUMPS
Consider locating LPG and hot pumps on the outside edge of plants to
improve access, drainage and fire water coverage.
Clear access, both vertically and horizontally shall be provided for trucks or
mobile equipment to service pumps.
5.2 COMPRESSORS
Unobstructed access for a mobile crane or a bridge / gantry crane for larger
equipment, shall be provided to allow easy removal / installation of
compressor machinery components such as rotors.
Page 10 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
5.3 VESSELS
Adequate room shall be allowed for erection, access to drop out areas, and
maintenance. Maintenance of vessel shall be by mobile crane. The use of
davits on the top platform used for lifting items from grade shall be avoided.
Drop out area for vertical vessels shall generally be located on the opposite
side to the rack, close to access ways or roads.
Adequate space shall be provided for the handling and storage of catalyst.
5.4 EXCHANGERS
Shell and tube exchangers shall be located to minimise piping runs and,
wherever practicable be grouped together perpendicular to the pipeway with
the channel end positioned away from the rack pipeways to facilitate tube
bundle removal. Generally exchangers will be located with their support
location closest to the rack aligned. Exchangers of a similar size in the same
process circuit in series may be located with their channel nozzles aligned.
Horizontal shell and tube exchangers, in similar services, may be placed one
above the other. The top exchangers centre line shall not exceed 5.5 metres
from grade unless mounted in a structure. The static head difference between
exchangers and the effect on flow splitting shall be considered.
For exchangers under drums or structures, the channel head shall be at least
1 metre beyond any obstruction for bundle pulling.
Page 11 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Air-cooled heat exchangers shall be located over areas where risks of serious
fires are minimal, and shall not be located over pumps or other mechanical
equipment.
Air coolers shall be located where possible above piperacks with adequate
permanent access for tube cleaning & replacement of tubes in situ. Air
coolers may be located in safe area at grade on freestanding structures.
There will be no provision for routine maintenance or removal of cooler tube
bundles by mobile cranes. Permanent access for fan/motor maintenance will
be provided including unrestricted header box access. Air cooler motor shall
extend below head height providing they do not protude into walkways.
Air coolers in dirty service (Crude, Heavy Oils, Amine etc.) or air coolers that
require regular maintenance shall be provided with an extra width header box
platform, on one side only.
Page 12 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
5.7 PIPEWAYS
Bund wall height shall be 1 metre minimum for tanks with a nominal capacity
up to 10,000 cubic metres and 1.5 metres minimum for tanks with a nominal
capacity of 10,000 cubic metres or over, including 200mm free board. The
overall bund area to be calculated on tank capacity.
Size, height and access into bunds shall conform to the Institute of Petroleum
Model Code of Safe Practice part 3 or part 9 and it is preferred that tanks
have at least one side adjacent to an access road. Bunded tanks shall have
vehicle accessways for maintenance if the capacity of the tank is over 5000m³
then two vehicle access ways shall be provided.
In bunded enclosures, the walls of the bund are to be of earth, steel, concrete
or solid masonry and be liquid tight to withstand a full hydrostatic head.
Every bunded or remote impounded area must have a 3 metre clear area
around the outside of the bund or remote impounded area and a 1.5 metre
clear area inside of any bund for fire-fighting access.
Page 13 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
500 to 2000 3 3
7570 to 15 15
113570
113570 to 23 23
264990
264990 to 30 30
340700
340700 to 37.5 30
454265
Over 454265 60 30
API 2510 does not apply to tanks smaller than 7570 Litres.
Page 14 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 15 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Notes
1. Prior to receipt of equipment outline drawing co-ordinate longitudinal
centreline and reference face of foundation. Delete after fixing discharge
nozzle.
2. Prior to receipt of equipment outline drawing co-ordinate longitudinal
centreline and a reference line, usually aisle side head. Delete after fixing
centreline of support for anchored end.
3. Underside of equipment base plate is generally 200mm above HPP,
unless design conditions govern otherwise.
Page 16 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
6.0
Over major plant roads for heavy equipment and fire
trucks
Over secondary on plot roads 5.3
Page 17 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 18 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Platforms, ladders and stairways shall be the minimum consistent with the
specified access and safety requirements. Where feasible common
supporting structures, stairs, ladders, walkways and foundations, shall be
utilised.
5.12.1 Platforms with Stair Access to main operating & service levels in
structures.
Page 19 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
5.12.3 Platforms are not required for manways, when manway centreline
elevation from grade is :
Page 20 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Stress Group will review all piping and identify requirements for
springs, anchors and loops.
For details on pipe supports in hot, cold and acoustic service and
heights of pipe shoes etc. refer to pipe support standards.
Page 21 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 22 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Refer to the Specification for Piping Standard Details for typical pump
arrangements.
The first support local to the pump where possible shall be located
on the foundation of the pump. This support shall be adjustable to
allow for alignment and any settlement that may occur.
Page 23 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 24 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 25 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 26 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 27 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 28 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
In general the lower levels shall contain the process pipework and
the upper levels utility pipework where practicable.
The relief valve header pipework shall generally be located on the
top level.
The minimum header line size within the pipeway shall be 2".
Pipework that runs vertically off the side of the pipeway shall be
grouped together with a common back of pipe to allow the ease of
supporting, taking into account insulation and any pipe shoe
requirements.
Page 29 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Piping in bunds shall be routed neatly in banks at grade, allowing for vehicle
and personnel access into the bunded area. Provide stiles over pipe banks
where necessary.
Valves in liquid sulphur and tail gas services shall not be installed in a vertical
line.
Valve installations shall comply with any specific instructions supplied by the
Valve Manufacturers.
Valve stem positions shall be installed above the horizontal centreline, except
in flare lines where they shall be installed below the horizontal centreline.
Page 30 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Locate heavy valves close as possible to support points and allow at least
300mm from the flange to the support.
Valves in lines off vessels shall be located as close as practical to the vessel
in order to minimise lengths of pipe subjected to steamout during
maintenance.
Branch line block valves from pipe rack headers shall be accessible from rack
platforms or appropriate locations at the edge of pipe rack.
Careful consideration shall be given to the location of valves that have Ring
Type Joints (RTJ's). The valve shall be located close to a change in direction
with a flanged elbow in order to ease the removal of the valves.
Valves in Butt Weld services unless identified on the P&ID's will not be
provided with break out flanges/ removable spools all maintenance activities
will be performed in situ.
Page 31 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Where positive shut off is required, either for process or maintenance needs,
"double block and bleed" valves are to be used. Small bore branch
connections with Double Block and bleed arrangements shall be adequately
supported.
NOTES:
1. Operating valves are valves which are essential for plant operation.
2. Non-operating valves are valves which are not essential for plant operation.
3. Small valves are defined as valves which can be easily operated with one
hand and are normally 1½” and smaller.
4. The use of chain operators for valves shall be avoided. If no other means of
access exist, prior approval is required to use chain operators in compliance
with the following:
Line vents and drains fall into two categories, process and pressure testing.
Page 32 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Process vents and drains for equipment and piping shall be valved
and shall be shown on the P&ID's.
c) All other services shall have vent and drain connections provided at
the high and low points of the piping system to facilitate
maintenance and hydrostatic testing. (The vents and drains shall
not be shown on P&ID's.)
Page 33 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
One flange shall be drilled and tapped, with two jackscrews. Note
that valve and nozzle flanges shall not be tapped.
Page 34 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Page 35 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
8. SERVICE PIPING
Where temporary type connections are used, the hose length for
servicing connection shall not exceed 15 metres.
Steam traps shall be provided at low points and drip legs of steam
lines.
Page 36 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Utility stations, which may be a combination of air, steam, nitrogen and water
as identified on P&ID's in compliance with the ‘Specification for Standard
Details’. Utility stations shall be located throughout the operating area of each
process unit, so that a 15 metre length of hose can service any point in the
area.
Page 37 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
9. INSTRUMENT PIPING
Page 38 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Relief valve inlet and outlet piping shall be arranged such that the
relief valve can be anchored with sufficient flexibility in the up and
down stream piping.
Gate valves used in relief and flare systems shall have spindles in
the horizontal or below position, so that valve spindle fracture will
result in a valve set open.
9.3.1 Location
9.3.2 Standpipes
Page 39 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Access to Standpipe block valves 2’’ and above shall be from fixed
platforms.
Horizontal meter runs for up/ down stream pipe lengths shall be in
accordance with Control System Design requirements. Provide sufficient
clearance at orifice flanges for installation of instrument piping and seal pots
where required. When reducers are used in metre runs they shall be
concentric, wherever practical. Meter runs in horizontal exceptions are steam.
Instrument group to ensure correct orientation.
Page 40 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
ACCESS REQUIREMENT
TYPE OF INSTRUMENT
FOR FROM FROM FROM
OPERATION PORTABLE FIXED FIXED
LADDER (for LADDER PLATFORM
maintenance)
Thermocouples & Resistance NO YES YES YES
Bulbs
Test Thermowells YES NO YES YES
Page 41 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
10. MATERIALS
The Specification for ‘Piping and Material Classes’ includes individual Service
Material Classes. It also indicates in detail, pipe, valve, flange, fittings, bolting,
gasket, branch connection and other specific material requirements for
various classes of fluid, temperature and pressure services.
Page 42 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
Pipe sizes 1¼”, 2½”, 5”, 7” and 9” shall not be used except where
equipment connections are these sizes. In such cases, transitions
to other commercial pipe sizes shall be made as close as possible
to the equipment connection.
Page 43 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
NOTES FOR APPENDIX “A”, “B” AND “C” (Spacing Charts derived from Chevron standards and incorporating Design Institute Comments)
1. The plant outlines are the equipment lines (frequently called equipment setback or line-up lines) and should be clearly identified on all plot plans. Equipment lines are used to establish plant spacing.
2. The so-called plot limit lines (which usually delineate the near edge of adjacent roads) are not used to establish plant spacing.
3. The spacing between the near edge of a road bordering high or low-pressure plants and equipment set-back lines may be reduced to 1.5 metres. All roads closer than 7.5 metres to high or low pressure plants are
considered restricted roads.
4. Provide a 6 metre minimum vertical space between overhead air coolers and the top of pumps handling flammable or combustible liquids. Pumps shall not be located directly under air coolers.
5. The minimum distance from flares is determined by the radiation zone footprint requirements at grade. However, the minimum distance to equipment handling flammable fluids should not be less than 60 metres
(except equipment directly related to the system and normally located near base of stack).
6. Plot limit valves should be accessible from grade or from a raised platform. Platform should be accessible by stairway and not located over pipeway drainage channel.
7. Primary fire water pumps and spares should be 60 metres from process equipment when spaced together. Individual pumps 60 metres apart may be within 30 metres of the process units. The loss of any fire
pump should not reduce the capacity of the fire water system more than 50%.
8. If pipe trenches are used, spacings shown are to be trebled.
9. Note Deleted
10. Truck traffic to Tank Truck Loading Rack (TTLR) should not interfere with process plant traffic.
11. 90 metre spacing – Process to office is based on potential for explosions to shatter glass and wood and other construction materials susceptible to explosion and fire damage. Single offices for field supervisors
can be located in workshops or control buildings.
12. Pumps should be outside tank bundwalls and impounding basins.
13. Pumps operating over 316ºC shall be located at least 15m from Fired Heaters and furnaces, place pumps 1.5m apart and should be 3m from equipment handling other flammables so that a packing gland fire will
not expose adjacent equipment.
14. High flash product tanks may be closer to facilities and equipment. Crude oil stored in cone roof tanks require special consideration. See NFPA 30.Tanks containing non-flammable liquids shall be located to suit
their service requirements.
15. Spacing from property lines that can be built on:
• Residential Commercial = distance as shown
• Industrial Zone or Undeveloped Properties = ½ distance as shown
16. See Plant Spacing note 5.9 for information on control house spacing.
17. Incineration type vapour recovery units should meet the furnace spacing.
18. Electrical Substations shall be located 15 meters minimum from any source of hazardous release. (Kazakh Code requirement) When transformers and MCCs are located indoors.
19. Plant to Equipment or Equipment to Equipment spacing. (Refer to Appendix ‘A’, ‘B’ and ‘C’).
Choose type of equipment on the diagonal and go down or across to the other type of equipment, Example: Spacing of Motor Control Center to Air Cooler.
Locate Motor Center on the Vertical ( Column 24)
Drop down column 24 to the row corresponding to Air Coolers (Row 29)
Where they intersect is the minimum spacing – in this case 15 metres.
MOTOR
CONTROL
CENTERS
23 P-M
24 15 P-M FIN
25 7.5 15 7.5 AIR
26 15 15 15 4.5 COOLERS
27 15 15 15 12 3
28 7.5 15 15 12 7.5 1
29 7.5 15 7.5 12 3 3 P-M
30 7.5 15 7.5 7.5 P-M P-M P-M P-M
31 7.5 15 7.5 7.5 3 3 P-M P-M
32 7.5 15 15 7.5 3 3 P-M P-M
33 7.5 15 23 7.5 3 3 P-M P-M
34 LPG 15 15 60 15 15 15 15
23 24 25 26 27 28 29 30
Page 44 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
(SEE NOTE 1)
NOTE 5)
(SEE NOTE 1)
A P-M = PERSONNEL ACCESS – MAINTENANCE ACCESS
B A 1.0 I METRE MINIMUM FOR PERSONNEL – 1.2 METRE FOR MAINTENANCE
C B-C = FOLLOW SNIP BUILDING CODES
D LPG = SEE API 2510 FOR SPACING TO PROPERTY LINE.
- = NO SPACING REQUIREMENTS.
(SEE
E
COOLING TOWERS
6 30 30 30 1.5 1.5 - -
OFFSITES
PIPERACK (SEE NOTE 8 )
(SEE NOTE 8)
7 30 15 15 60 60 15 7.5 15
ELECTRIC SUBSTATIONS
NOTE 18)
8 P-M 7.5 7.5 7.5 7.5 7.5 7.5 7.5 -
MULTI-PLANT INSTRUMENT
AIR COMPRESSORS & DRYERS
10 30 45 60 30 30 60 30 15 7.5 - P-M
PLANT ROADS
(SEE NOTE 3)
13 4.5 15 15 23 23 30 15 15 7.5 - 15 15 30 B-C
WAREHOUSES – PETROLEUM
PRODUCTS
15 60 30 45 T T 15 30 60 15 15 60 60 30 B-C - -
21 - 15 23 7.5 7.5 7.5 7.5 23 1.5 - - 7.5 7.5 P-M P-M P-M P-M P-M P-M 15 15 -
FLARE LINE K.O. DRUMS
23 3 P-M P-M 7.5 7.5 15 1.5 15 3 15 15 7.5 7.5 15 7.5 60 30 60 30 30 30 7.5 N P-M
PLOT LIMIT MANIFOLDS
(SEE NOTE 6)
24 7.5 15 15 15 15 15 P-M 15 7.5 P-M P-M P-M 15 P-M P-M 7.5 P-M P-M P-M 15 15 - N 15 P-M
FURNACES
30 3 - - 15 15 15 15 - 7.5 15 23 15 - 15 7.5 60 30 60 23 15 P-M 7.5 N 7.5 15 7.5 15 P-M P-M P-M P-M
COLUMNS
Page 45 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
LEGEND:
N = REQUIRED FLARE RADIATION ZONE DISTANCE BUT A MINIMUM SPACING 60 METRES. (SEE
NOTE 5 APPENDIX ‘A’)
B-C = FOLLOW SNIP BUILDING CODES ( Ref: SPECIFICATION 60-0000-R-SPE-0001 – APPENDIX ‘A’ )
WAREHOUSES – PETROLEUM
PRODUCTS
OFFICE BUILDINGS,
FIELD ENGINEERS OFFICES
PRIMARY FIRE WATER PUMPS
TANK TRUCK LOADING RACKS
PIERS AND WHARVES
FLARES - PROCESS
FLARE LINE K.O. DRUMS
MOTOR CONTROL CENTERS
PLOT LIMIT MANIFOLDS
AUXILIARY – BUILDINGS,
WORKSHOPS, ETC.
FIRE HOUSE (MOBILE FIRE
FIGHTING EQUIPMENT)
25 60 15 15 23 23 30 15 15 7.5 15 15 15 15 - - B-C 30 15 30 60 60 N 15 - 30 -
WAREHOUSE – NON PETROLEUM
PRODUCTS
26 15 90 90 60 60 60 30 60 15 30 30 30 30 - - - 30 - - 30 30 90 60 - 45 15 -
PARKING LOTS (ON PLOT)
Page 46 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
FLARE
E22
RACK TO FLARE AREA
A15 or B15
60m (min)
OFFSITE INTERCONNECTING PIPERACK
4.5m
A8 or B8
1 2
A9 or
B9 R
R R
SS
PROPERTY LINE
LEGEND
R RESRICTED ROADS
R ACCESSWAY
U UNRESTRICTED ROADS
5m (min.) TO ROAD
FROM EDGE OF
EQUIPMENT (TYP.)
PIPEWAYS
PLANT OUTLINES –
EQUIPMENT LINES
NOTE NUMBERS
2
(SEE PAGE 42)
UNIT PIPERACK
AREAS CONTAINING
PRESSURED EQUIPMENT OF
1000 PSIG OR GREATER
PROPERTY LINES OF
R ACCESSWAY OTHERS THAT CAN BE
BUILT UPON
WIDE
CONTROLLED ACCESS
BOUNDARY OF ONSITE
4.5m
RESTRICTED
ROADS
FACILITY.
U
Page 47 of 48
TENGIZCHEVROIL ASSET DEVELOPMENT PROJECTS PFD
PROJECT №. 571500
SPECIFICATION FOR PLANT DOCUMENT №. : 60-0000-L-SPE-0001
AND PIPING LAYOUT Rev. 2
NOTES
CRANE ACCESS
OVERHEAD INLET 3. EIGHT METRES COLUMN SPACING BETWEEN
HEADER AND SUPPORT PIPERACK SECTIONS.
AS REQUIRED
HEADER BOX PLATFORM TO
BE DOUBLE WIDTH ON 4. ELEVATION SUBJECT TO FLARE SIZING.
COOLERS IN DIRTY SERVICE
(ONE SIDE ONLY) 5. PUMPS NOT LOCATED IN PUMP HOUSE OR
SHELTERS TO BE 3 METERS MINIMUM FROM
AIR FIN COOLERS PIPERACK COLUMN CENTRE LINES.
CRANE ACCESS
TOWER
2100
TOWER
HEADROOM
MOTOR ACCESS
AS REQUIRED
TOWER
DROPOUT ZONE
TOWER
RECIRCULATION
BY AIR - FIN CABIN
COOLER VENDOR
BY PFD RELIEF/CONTROL
2500 CABLE TRAYS CABLE TRAYS
J J J J J J J 2500 VALVES
J
RELIEF/CONTROL J J J J J J J J
VALVES P P P P P P P P
P P P P P P P P
P P P P P P P P LINK PLATFORM
AS REQUIRED
TOWER
DROPOUT ZONE
SLOPING RELIEF
HEADER
DRUM
DRUM DRUM
PUMP’s NOT
LOCATED INSIDE
CABLE TRAYS INTERMEDIATE SUPORT PUMP HOUSES
AS REQUIRED (see note 5)
EXCHANGERS
BUNDLE REMOVAL
OF PIPEWAY
VEHICLE
Page 48 of 48