0% found this document useful (0 votes)
274 views2 pages

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS V QUIWA

The Supreme Court ruled that while the contracts between the Department of Public Works and Highways (DPWH) and various contractors who aided in rehabilitation efforts after the 1991 eruption of Mt. Pinatubo were void due to lack of proper certification and appropriation, the contractors were still entitled to payment for works completed. The Court held that DPWH could not avoid payment for services rendered to the government under a void contract. However, the Court also ruled that the former DPWH Secretaries should not be held personally liable since they were sued in their official capacity only. Finally, the Court denied awarding attorney's fees and costs of suit since these were not part of the appropriation for the rehabilitation project.

Uploaded by

April Joy Omboy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
274 views2 pages

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS V QUIWA

The Supreme Court ruled that while the contracts between the Department of Public Works and Highways (DPWH) and various contractors who aided in rehabilitation efforts after the 1991 eruption of Mt. Pinatubo were void due to lack of proper certification and appropriation, the contractors were still entitled to payment for works completed. The Court held that DPWH could not avoid payment for services rendered to the government under a void contract. However, the Court also ruled that the former DPWH Secretaries should not be held personally liable since they were sued in their official capacity only. Finally, the Court denied awarding attorney's fees and costs of suit since these were not part of the appropriation for the rehabilitation project.

Uploaded by

April Joy Omboy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS v. RONALDO E. QUIWA, et al.

G.R. No. 183444, 12 October 2011, SECOND DIVISION (Sereno, J.)

Facts:

After the eruption of Mt. Pinatubo in 1991, several contractors, including the respondents, were

hired by the Department of Public Works and Highways (DPWH) for the rehabilitation of the areas

affected by the lahar and floodwater. Respondents finished the works on their respective projects.

When Ronaldo Quiwa sought to claim payment for the works done by its company, DPWH

failed to act upon Quiwa’s request despite the report and Certification of Completion provided by the

Assistant Project Manager for Operations. The other respondent contractors joined Quiwa to file an

action against DPWH for sum of money. The Regional Trial Court (RTC) rendered a decision in favor

of respondents stating that the respondents have completed the works assigned to them, as certified by

DPWH itself; that despite the appropriation provided in the Mt. Pinatubo Rehabilitation Program in the

amount of P700 million, DPWH still denied their claims; and finally, that the contract between DPWH

and respondents were valid.

Upon appeal, DPWH argued that there was no valid contract between it and respondents; there

was no certification issued by the DPWH Chief Accountant or by the head of its accounting unit that

funds were indeed available for the project. Also, the requirements provided in Presidential Decree (PD)

1294 and 1445 were not complied with and that the project manager of DPWH was not authorized to

enter into the subject contracts. The Court of Appeals (CA) affirmed the decision of the RTC. Regarding

the liability of DPWH former Secretaries Gregorio T. Vigilar and Jose P. de Jesus, both the RTC and the

CA held them jointly and solidarily liable with DPWH.

DPWH, however, maintains its position that there was no valid contract.

ISSUES:

1. Are the contractors entitled to payment for the accomplishment of their assigned projects,

notwithstanding the absence of the legal requirements under PD 1445?

2. Whether the Secretary and the Undersecretary of DWPH should be held jointly and

solidarily liable to the contractors

3. Should attorney’s fees and cost of suit be awarded to the contractors?

RULING:
1. YES. DPWH primarily argues that the contracts with herein contractors were void for not

complying with Sections 85 and 86 of P.D. 1445, or the Government Auditing Code of the Philippines,

as amended by Executive Order No. 292. These sections require an appropriation for the contracts and a

certification by the chief accountant of the agency or by the head of its accounting unit as to the

availability of funds. It should be noted that there was an appropriation amounting to P400 million,

which was increased to P700 million. The funding was for the rehabilitation of the areas devastated and

affected by Mt. Pinatubo, which included the Sacobia-Bamban-Parua River for which some of the

channeling, desilting and diking works were rendered by herein respondents construction companies.

It was, however, undisputed that there was no certification from the chief accountant of DPWH

regarding the said expenditure. In addition, the project manager has a limited authority to approve

contracts in an amount not exceeding P1 million. Notwithstanding these irregularities, it should be

pointed out that there is no novelty regarding the question of satisfying a claim for construction

201

contracts entered into by the government, where there was no appropriation and where the contracts

were considered void due to technical reasons. It has been settled in several cases that payment for

services done on account of the government, but based on a void contract, cannot be avoided.

The Court first resolved such question in Royal Trust Construction v. Commission on Audit. In that

case, the court issued a Resolution granting the claim of Royal Trust Construction under a void contract.

2. NO. They were sued in their official capacity, and it would be unfair to them to pay the

contractors out of their own pockets. It has been previously declared that Court declared that it was

unjust to hold the public official liable for the payment of a construction that benefited the government.

3. NO. The Constitution provides that no money shall be paid out of the Treasury except in

pursuance of an appropriation made by law. Attorney’s fees and costs of suit were not included in the

appropriation of expenditures for the Sacobia-Bamban-Parua project.

You might also like