Volume 2 Drainage Design Manual PDF
Volume 2 Drainage Design Manual PDF
January 2010
Drainage Design Manual
PREAMBLE
This Road Design Manual Volume II: Drainage Design is one of a series of Engineering Specifications,
Standards, Manuals and Guidelines issued by Ministry of Works and Transport. The Manual is part of
the revised Road Design Manual, November 1994.
The Parts of the Road Design Manual include:
i
Ministry of Works and Transport
Drainage Design Manual
TABLE OF CONTENTS
INTRODUCTION
ii
Ministry of Works and Transport
Drainage Design Manual
iii
Ministry of Works and Transport
Drainage Design Manual
iv
Ministry of Works and Transport
Drainage Design Manual
v
Ministry of Works and Transport
Drainage Design Manual
APPENDIX
List of Appendices (Section 4)
vi
Ministry of Works and Transport
Drainage Design Manual
vii
Ministry of Works and Transport
Drainage Design Manual
viii
Ministry of Works and Transport
Drainage Design Manual Section 1
SECTION 1
1
Ministry of Works and Transport
Drainage Design Manual Section 1
more detailed attention is also being given to the planning and design of the supplementary
aspects of the overall “major system” which carry the excess flow over and above the hydraulic
capacity of the various components of the minor system.
The increased use of storage to balance out handling or treatment of peak flows; use of land
treatment systems for handling and “disposal” of stormwater; and perhaps most important,
a recognition of detention at various points in a system, are potential design solutions rather
than problems in many situations.
Another basic reality is that every site or situation presents a unique array of physical resources,
land use conditions and environmental values. Variations of such factors generally require
variation in planning of approaches and standards for optimal achievement of stormwater
management objectives.
Since many communities and urban areas use less than a 10 years frequency value for their
storm drainage facilities, coordination of the highway drainage with that of the local urban area
is a primary factor requiring very careful consideration. Location studies of a highway through
a built up area require close attention to how the proposed highway’s drainage requirements
can be satisfactorily coordinated with those of the community. Necessarily, both horizontal and
vertical location of the proposed highway improvements are of great significance since most
major city streets are likely to have existing storm sewers and underground utilities.
1.3 Economics of Storm Drainage
Various types of drainage facility area employed to protect the road against damage by surface
and subsurface water. Drainage facilities must be designed as simply as possible to convey
the storm water along or away from the road in the most economic, efficient and practical
manner with out damaging the road or adjacent properties.
The economics of storm drainage is concerned principally with the costs associated with proper
handling of runoffs of various frequencies versus the associated inconveniences or damages.
The higher the design return period, the larger are the design capacities of the storm drainage
facilities which lead to larger first cost.
It has generally been impractical to develop a realistic evaluation of damages associated
with each of several alternative stormwater systems and its cost. This is because stormwater
damages related to rainfall events of known frequency of recurrence are difficult to measure
and evaluate; and the collection of suitable data is costly. Usually such studies are not made
for all types of storm drainage projects. Judgment based upon performance experience in
similar developed areas is generally the basis for selecting a design frequency.
The relative hazards to persons, property and traffic associated with each of the runoffs
related to rainfalls of several selected frequencies should be used in storm drainage design.
Mitigation of drainage-related damages or losses is theoretically balanced as a benefit against
the associated drainage costs. In practice, judgment has largely been relied upon to choose
the design rainfall frequency.
Recent storm drainage cost studies (taking principally the construction cost) show that
irrespective of the degree of development (per cent of imperviousness), there was a rapid
increase in the cost per hectare of storm drainage facilities for the 10 years average recurrence
interval as compared to a slow increase in unit cost between the 10 to 100 years average
recurrence intervals.
1.3.1 Cost Considerations
The design cost objectives are to minimize the total annual cost of the stormwater drainage
facilities (capital costs, maintenance and operating costs, etc.). An associated objective is
the reduction in average annual costs of damages by overflow or other aspects associated
with lack of capacity in the system. Where overflows are evidences of incapacity of the storm
system, investment to reduce the frequency of such overflows is more likely to be justified.
2
Ministry of Works and Transport
Drainage Design Manual Section 1
The basic factors making up the total costs of a drainage system are:
i. Capital costs;
ii. Right-of-way or land acquisition costs;
iii. Construction costs;
iv. Traffic delays;
v. Maintenance;
vi. Operation and administration;
Existing serviceable facilities including natural drainage swales, ditches, creeks, detention
areas, etc. should be used wherever possible to reduce initial costs. For highways in urban
areas, keeping the drainage facilities underground is of great help in minimizing the cost of
land.
An overall consideration of optimum design of stormwater collection, storage and treatment
facilities indicates that at least a balance should be struck among the capital costs, operation
and maintenance costs, public convenience, environmental enhancement and other design
objectives. Such an optimum balance is dynamic, changing over time with changing physical
conditions and value perceptions.
3
Ministry of Works and Transport
Drainage Design Manual Section 2
SECTION 2
2.0 STORM WATER SYSTEM DESIGN
2.1 Steps in Planning of Storm Water Management Studies
2.1.1 General
A storm water management plan is prepared to consider what storm water management
practices and measures are to be provided for large public works project, an urban estate
and other developments. These plans will have a local focus responsive to specific functions
(drainage provision, open space provision, etc.). They prescribe individual area management
techniques and practices. If a storm water strategy plan is available for a catchment, each
local area storm water management plan will be required to accommodate the principles and
directions identified in the broader strategic plan.
Ideally, a storm water management plan should be prepared for a local area prior to implementing
structural and non-structural management measures identified in the strategy plan for the
catchment. That is, detailed planning should precede the design, construction, and operation
phases of a development project.
2.1.2 Preparing Concept Plans
The following tasks should be carried out for the preparation of a storm water management
plan.
Step 1: Establishing Objectives and Standards - Objectives and standards should be established
to guide the planning process. These may be obtained from the strategy plan for the
catchment (if available). The objectives and standards should provide the basis for and
give direction to the planning process and should be used to determine the expected
outputs of the recommended plan.
Step 2: Data Collection - Data collected for the planning process provides the factual basis
for the plan and allows an appreciation of past and an understanding of present
conditions within the catchment. The extent of data collection would be the reflection
of the objective/s and standard/s set. The data collected for the development of the
strategy plan for the catchment should be used if available. This data may need to be
supplemented with additional data necessary to further define the characteristics of the
area under investigation.
2.1: Base Map - The base map should identify the watershed areas and sub areas, land
use and cover types, soil types, existing drainage patterns, and other topographic
features. This base information is then supplemented with underground utility
locations (and elevations if available), a preliminary roadway plan and profile,
and locations of existing and proposed structures.
2.2: Hydro meteorological Data - Hydro meteorological data gives information mainly on
the rainfall, and for gauged areas, the runoff.
Step 3: Analysing Existing Conditions - The main purposes of this phase is to use the data and
information collected under the data collection phase to understand the present state of
storm water management related conditions in the catchment.
The water quantity and/or quality characteristics for the existing catchment conditions
must be determined.
For existing developments, models are required to:
• determine the capacity of existing major and minor conveyance systems;
• determine the location and extent of any flooding under major and minor system;
• determine the pollutant loads for existing land uses within the catchment; and,
• determine the performance of any existing water quality control structures.
4
Ministry of Works and Transport
Drainage Design Manual Section 2
5
Ministry of Works and Transport
Drainage Design Manual Section 2
6
Ministry of Works and Transport
Drainage Design Manual Section 2
7
Ministry of Works and Transport
Drainage Design Manual Section 2
Special opportunities that could have a bearing on the implementation of a plan, such
as possible sources of financing, should be identified. Other aspects of implementation
programme include clear identification of desired endorsements, agreements, and
required approvals and permits
ii. Plan Implementation - Of all the steps in the planning process, plan implementation is the
most unpredictable. The extent to which a comprehensive storm water management
plan is accepted and the enthusiasm with which the public and private sectors will push
for its implementation will depend, among others, on the following factors:
• the credibility of the plan as determined by the quality of the technical work and
the thoroughness of the community involvement carried out during the planning
process; and,
• the frequency and severity of storm water-related problems and the level of
concern that past problems will occur again.
The ultimate test of a storm water management plan is the degree to which
storm water problems have been mitigated and the degree to which potential
storm water problems have been prevented from occurring.
2.1.8 Plan Components
Storm water management plans should consist of two major components: a technical report,
and supporting plans.
i. Technical Report - This report should provide a comprehensive analysis of existing and
proposed storm water quantity and quality conditions for the catchment. The report
should provide narrative descriptions of existing conditions and how the proposed
system will meet objectives of the plan, and contain all necessary technical data for
both existing and proposed conditions.
ii. Supporting Plans - A conceptual or preliminary plan of the proposed storm water
conveyance, runoff quantity control, and water quality control systems, based upon
accurate field topographic mapping should be provided along with sufficient details to
identify systems elements. Plans should be of adequate scale and detail for accurate
definition and location of all system elements.
8
Ministry of Works and Transport
Drainage Design Manual Section 3
SECTION 3
3.0 DESIGN FLOW CONSIDERATIONS
3.1 Introduction
Design of a drainage system involves determination of flow magnitudes which every line in
the system is to be designed for. Hydrologic considerations determine the flow magnitudes or
flow hydrographs, as the case may be, at each point in the drainage system. The resulting flow
hydrographs are then routed downstream according to hydraulic principles.
Design flow is determined based on the statistical (frequency) analysis on historic records of
flow for gauged sites or rainfall and the associated hydrologic parameters for un-gauged sites.
Generally, the longer the length of data, the more reliable the estimation of design flow will
be.
3.1.1 Average Recurrence Interval (ARI)
As all magnitudes of flow have some chance of occurrence, the design flow is decided by
attaching an average recurrence interval. Average recurrence interval is defined as the average
interval in years between the occurrence of a flow of specified magnitude or larger flow. It is the
long term average of the intervals between successive exceedences of a flow magnitude.
The word “average” is the important part of the definition of recurrence interval. As hydrological
events are generally random in their occurrences, it can not be inferred that a flow of particular
average recurrence interval is equaled or exceeded at regular interval. This important point is
also to be explained to decision makers and to the public at large who are affected by them.
3.1.2 Exceedence Probability
Exceedence probability is the probability that an event of a given average recurrence interval
will be equaled or exceeded during a given period of time. Consideration of the probability of
exceedence during a given span of time, particularly the design life of a structure can be used
as an aid in the selection of the level of serviceability to be provided.
Equation 3.1 is used to compute the probability that at least one event which equals or exceeds
the -yr event will occur in any series of years
Equation 3.1 is used to compute the probability J that at least one event which equals
or exceeds the t p -yr event will occur in any series of N years
J 1 (1 P ) N Eqn. 3.1
Where: 1
P
tp
The probability that an event of a given recurrence interval will be equaled or exceeded
during periods of various lengths is depicted in Table 3.1
9
Ministry of Works and Transport
Drainage
Drainage Design
Design Manual
Manual Section
Section 3 3
Table 3.1 : Probability That An Event of a Given Recurrence Interval will be Equaled or
Exceeded during Periods of Various Lengths (Computed Employing Eqn. 3.1)
*In this case the probability can never be 1, but for practical purposes its value may be
taken as unity
3.2
3.2 Design
DesignFlows
Flows
3.2.1 General
3.2.1 General
Design flow is defined as discharge that may be expected from the sever combination
of meteorological and hydrologic conditions that are reasonably considered to reflect
Design flow is defined as discharge that may be expected from the sever combination
characteristics of the area involved, excluding extremely rare combinations.
of meteorological and hydrologic conditions that are reasonably considered to reflect
Adequate stormofwater
characteristics drainage
the area system
involved, or adequate
excluding extremelywaterway is a system or a waterway
rare combinations.
which has the hydraulic characteristics to accommodate the maximum expected flow (design
Adequate
flow) of stormstorm
waterwater
for a drainage systemorora portion/s
given watershed adequatethereof.
waterway is a system
Adequate system/s:or a
waterway which has the hydraulic characteristics to accommodate the maximum
1) should
expected flowbe designed
(design flow)toof
account for both
storm water foroff-site
a givenand on-site storm
watershed water, including
or a portion/s thereof.storm
water coming
Adequate system/s: into a given tract of land from upstream;
2) should discharge the flow in to natural drainage line or other appropriate outlets; and
1) should be designed to account for both off-site and on-site storm water, including
3) should carry water to a point where it should flow downstream into a stream channel or
storm water coming into a given tract of land from upstream;
water way.
2) should discharge the flow in to natural drainage line or other appropriate outlets;
Designandflood standards are influenced by many factors including:
3) should
• safety;carry water to a point where it should flow downstream into a stream
channel or water way.
• the level of hydraulic performance required;
Design• flood
environmental impact;
standards are influenced by many factors including:
• construction and operation costs;
safety;
• maintenance requirements;
the level of hydraulic performance required;
• serviceability; and,
environmental impact;
construction
• Legal andandstatutory requirements.
operation costs;
The
maintenance requirements; average recurrence intervals adopted. These measures
standards are expressed by
determine the magnitude
serviceability; and, of a design rainfall or runoff event with which the system can cope.
Past practice has often been based on one level of operation. But it is usually appropriate to
Legal
design and statutory
for several requirements.
performance levels which include:
• A maintenance
The standards requirement
are expressed by (frequent
average event), related
recurrence to a short
intervals design
adopted. average
These
recurrence interval;
measures determine the magnitude of a design rainfall or runoff event with which the
systemAcan
• cope. Past
convenience orpractice
nuisancehas often been
reduction based on (infrequent
requirement one level ofevent),
operation.
one But it isyears
to five
usuallyofappropriate to design for several
average recurrence interval; performance levels which include:
• A flood damage prevention requirement (sever or rare event), 50 to 100 years of average
recurrence interval; and,
• A disaster management requirement (extreme event), related to extreme events such
as probable maximum floods.
The first two are relevant to minor drains, and all but the second to major drains discussed
under 3.3.2.
Assigning an average recurrence interval takes into account the level of safety (standard)
required. The required level of safety in turn depends upon potential losses to occur following
the probable failure (both structural and serviceability) of an element of a drainage system or
a combination thereof. Generally, the longer the average recurrence interval, the higher the
magnitude of flow will be and the safer the level of protection.
3.2.2 Minor and Major Drainage Systems
a. Minor Drainage System (span < 6.0 meters)
The minor system, sometimes referred to as the “Convenience” system, consists of the
components that have been historically considered as part of the “storm drainage system”.
These components include curbs, gutters, ditches, inlets, access holes, pipes and other
conduits, open channels, pumps, detention basins, water quality control facilities, etc.
The minor drainage systems are part of the total drainage system which are intended to collect
the maximum run off from the initial storm and convey runoff from frequent storm events such
that nuisance is minimised, while the major systems are intended to safely convey runoff not
collected by the minor drainage system to receiving waters.
b. Major Drainage System (span > 6.0 meters)
The major system provides overland relief for storm water flows exceeding the capacity of the
minor system. This usually occurs during more infrequent storm events. The major system is
composed of pathways that are provided for the runoff to flow to natural or manmade receiving
channels such as streams, creeks, or rivers.
The major system typically consists of a network of overland flow paths including roads, natural
channels and streams, engineered waterways, culverts, and detention basins which ultimately
discharge into receiving waters.
3.2.3 Selection of Design Average Recurrence Interval
The selection of design average recurrence interval values must be made by the designer
in relation to the cost of a facility, amount of traffic and expected level of service; potential
flood hazard to property; the magnitude and risk associated with damages from larger flood
events; and conditions for practical detour during probable failure. In selecting a design
frequency, all potential upstream land use for the anticipated life of the drainage facility must
be considered.
Review of existing drainage system should be carried out using the same general sequence
as planning and design of new drainage projects. The first step will take into account the
existing (constructed) drainage system. It is often found that older existing systems are lacking
considerations of the major system flows. Minor system is normally designed to carry runoff
from up to 10 year frequency storm events. Major systems are designed for floods of average
recurrence intervals 25, 50, and 100-year.
The design frequency value depends on particular site and catchment conditions. This being
the case, the values rendered in Table 3.2 which is based on geometric design criteria could
be used for initial planning, design and analysis.
11
Ministry of Works and Transport
Drainage Design Manual Section 3
Table 3.2: Design Average Recurrence Intervals for Flood/Storm (Yrs) by Geometric Design
Criteria (Source: ERA Drainage Design Manual, 2002)
Note 1: Span in the above table is the total clear-opening length of a structure. For
example, the span for a double 1.2-meter diameter pipe is 2.4 meters, and
the design storm frequency is therefore “culvert, 2m < span < 6m.” Similarly
a double box culvert having two 4.5-meter barrels should use the applicable
design storm frequency for a short span bridge and a bridge having two 10-
meter spans is a medium span bridge.
All bridges and major culverts shall be checked for performance under a storm event less
frequent than the design storm event shown in the table as the Check/Review Flood. All other
drainage structures shall be checked for the storm having the next lower frequency than the
design storm event. For example, minor culverts designed for a 10-year storm shall be checked
for adequate performance with a 25-year interval storm event.
3.2.4 Environmental Impact
a. Physical
There is no published information available on the average recurrence interval of the flow
that should be used for assessing and minimizing possible environmental damage. Each site
should be investigated for possible environmental impact that might occur with a range of flow
events, with emphasis on the more frequent ones. The following factors need be considered
when assessing any potential environmental damage.
• Selection of suitable site;
• Provision of adequate opening to limit backwater effects and excessive localized bed
scour;
• Protection of banks from erosion that comes as a result of redirection of flow, turbulence
or excessive increase in velocity;
• Protection of natural vegetation, especially where it protects or stabilizes; and,
• Control of road side drainage where it enters streams, to limit bank erosion.
12
Ministry of Works and Transport
Drainage Design Manual Section 3
b. Water Quality
When runoff flows, it collects pollutant loads. The variation of pollutants with time results in
pollutant-load graphs. The pollutant-load graphs are then routed downstream according to
hydraulic principles. Water quality may then be improved by natural process or introduction
of treatment devices. Because of the interaction between hydrology, hydraulics, and water
quality, all aspects need to be considered in an integrated manner.
13
Ministry of Works and Transport
Drainage Design Manual Section 4
SECTION 4
4.0 ESTIMATION OF DESIGN FLOW FOR UNGAGED CATCHMENTS
4.1 General
A major objective in storm water management is to see that excess water flow is controlled so
as to minimize nuisance and hardship to traffic, residents and damage to properties and the
environment. This could be achieved by:
• minimizing the overflowing of drainage lines;
• containing the rivers in their channels for their possible exploitation;
• introducing methods to reduce the amount of surface runoff in general the peak discharge
in particular; and,
• providing proper drainage system and outfalls.
The degree of protection is highly dependant on the magnitude of the design flow. The method
to be used to estimate the design flood depends upon the type and quality of data. For gauged
sites, flood frequency analysis may be employed to determine the design flow. For this a
reasonably long record of annual maximum flows may suffice. If the coverage of flow data
is short, it may be complemented with results of regional flood frequency analysis. Design
discharges for un-gauged sites could either be estimated by transforming, discharges from
gauge sites or by using models that synthesize storm data in to discharge magnitude.
4.2 Design Flow
The process of design flow estimation for a watershed from rainfall data generally involves the
following main steps.
1. Determination of time of concentration
2. Design rainfall estimation
3. Estimation of rainfall excess
4. Estimation of runoff
4.2.1 Time of Concentration
For any particular locality and return period there is statistical relationship between storm
duration and intensity. Analysis of storms through the world indicates that the storm intensity
could be predicted with reasonable accuracy with an equation of the form:
a
i Eqn. 4.1
(b t d ) c
t d is duration of storm.
For a given return period and locality, the intensity solely depends on the rainfall duration, td ,
as the rest of the parameters are constants. Maximum peak runoff for any return period occurs
if the storm last as long as it takes to reach equilibrium condition. A longer duration storm will be
of lesser intensity and shorter duration storm will not reach equilibrium. The duration of rainfall
that gives maximum peak runoff for a given watershed is termed as time of concentration.
It is defined as the time required by a drop of water to travel from the hydraulically remotest
point to the point of interest. A drop of rain within a catchment joins different modes of flow
with different travel speeds and hence with different travel times. The significant ones are
discussed here under.
14
Ministry of Works and Transport
Drainage Design Manual Section 4
15
Ministry of Works and Transport
Drainage Design Manual Section 4
16
Ministry of Works and Transport
Drainage Design Manual Section 4
Table 4-2: Intercept Coefficients for Velocity vs. Slope Relationship of (Source: HDS 2)
0.076 Forest with heavy ground litter; hay meadow (overland flow)
0.152 Trash fallow or minimum tillage cultivation; contour or strip cropped; woodland
(overland flow)
Table 4-3: Manning's Roughness Coefficient (n) for Overland Sheet Flow
(Source HEC 22)
Surface Description n
Smooth asphalt 0.011
Smooth concrete 0.012
Ordinary concrete lining 0.013
Good wood 0.014
Brick with cement mortar 0.014
Vitrified clay 0.015
Cast iron 0.015
Corrugated metal pipe 0.024
Cement rubble surface 0.024
Fallow (no residue) 0.05
Cultivated soils
Surface Description n
Woods*
* When selecting n, consider cover to a height of about 30 mm. This is only part of
the plant cover that will obstruct sheet flow.
18
Ministry of Works and Transport
Drainage Design Manual Section 4
Segment
Flow Segment Length (m) Slope (m/m)
Description
Find: Using a rainfall intensity, i , = 60 mm/hr, the time of concentration, t c , for the
area.
Solution:
Tti = (6.943/ i 0.4 ) ( nL S 0.5 )0.6 = [6.943/(60)0.4] [(0.15)(25)/(0.005)0.5] 0.6 = 14.6 min.
19
Ministry of Works and Transport
Drainage Design Manual Section 4
Segment 2
Obtain intercept coefficient, k , from Table 4.2:
k = 0.213
Determine the concentrated flow velocity from Equation HDS2 (Table 4.1):
0.5
V kS P = (0.213)(0.5)0.5= 0.15 m/s
Determine the travel time from Equation HDS2 (Table 4.1):
20
Ministry of Works and Transport
Drainage Design Manual Section 4
21
Ministry of Works and Transport
Drainage Design Manual Section 4
22
Ministry of Works and Transport
Drainage Design Manual Section 4
In practice the daily rainfall for appropriate recurrence interval is determined using Appendices
4.3, 4.4, and 4.5 and Eqn. 4.5. The required design rainfall is then obtained by employing the
relevant intensity - duration - frequency model. The form of the above model are, therefore,
adjusted as follows to simplify this operation.
23
Ministry of Works and Transport
Drainage Design Manual Section 4
a
i
(b t d ) c
aT
Rainfall in time T RT
(b T ) c
24a
The daily total R D
(b 24) c
c
T 24 b
Eliminating 'a' RT * RD Eqn.4.4
24 b T
With b = 0.33, a unique set of curves can be developed for converting daily rainfall to rainfall
of any given duration.
Example 4-2 (Adopted from TRRL Laboratory Report 623)
Calculate the design storm of 25 years average recurrence interval on a 20 square kilometer
catchment of grid reference 32o E 1o N.
Solution:
Locate the catchment on Appendix 4.3
The 2 year 24hr rainfall = 70 mm
Locate catchment on Appendix 4.4
10 year: 2 year ratio (Group 6 Inland) = 1.49
From Appendix 4.5 for a 10 year: 2 year ratio of 1.49 and average recurrence interval of 25
years, the flood factor is 1.74
The 25 year 24 hour point rainfall = 1.74 x 70 mm = 121.8 (say 122)
From Eqn 4.5 calculate the area reduction factor for a 20 square kilometer = 0.9
The aerial rainfall for the catchment is 122 x 0.9 = 109.8 (say 110)
From Tables 4.5 or 4.6 select a suitable ‘c’ value = 0.96
Using ‘n’ = 0.96, select rainfall ratios for 15 minutes, 30 minutes, 1 hour, 2 hours, 4 hours and
multiply by 110 mm to obtain RT for each period. These are then plotted as a symmetrical
histogram RT being shown in units of (mm of rain in 15 minutes)
15 min. 0.36 x 110 RT = 39.6 RT = 39.6
30 min. 0.51 x 110 RT = 56.1 RT = 56.1 - 39.6 = 16.5
1 hr. 0.655 x 110 RT = 72.05 RT = (72.1- 56.1)/2 = 8.0
2 hr. 0.825 x 110 RT = 90.75 RT = (90.8 - 72.1)/4 = 4.7
4 hr. 0.855 x 110 RT = 94.05 RT = (94.1 - 90.8)/8 = 0.4
24
Ministry of Works and Transport
Drainage Design Manual Section 4
Time (h)
25
Ministry of Works and Transport
Drainage Design Manual Section 4
Even after rainfall commences, some amount infiltrates at a rate that again depends on surface
and soil characteristics. The infiltration rate is nil for impervious surfaces. A rainfall, therefore,
whose magnitude does not exceed the volume of initial abstraction and depression storage
and whose intensity does not override the infiltration rate of the watershed will not produce
runoff. From the above statements, it is seen that the actual rainfall duration needs to be
longer than the computed time of concentration by the time require to fill the initial abstraction
and depression storage.
There are three models used to determine the pattern of loss.
a. Constant loss rate:- In this model, the rainfall excess is the residual left after a selected
constant rate of infiltration.
b. Initial loss and continuing loss:- This model is similar to (a) except that no runoff is
assumed to occur until a given initial loss capacity has been satisfied, regardless of the
intensity of rainfall. The continuing loss is at a constant rate. A variation of this model is
to have an initial loss followed a loss consisting of a constant fraction of the rainfall in
the remaining time.
c. Infiltration Curve:- In this model, the basic assumption is the reduction of infiltration with
time.
Loss values are derived by analyzing observed rainfall and runoff data. For design an average
value is usually needed and since there is no reason for expecting loss rate values for a
catchment to conform to a particular distribution, the median of the derived values is probably
the most appropriate for design.
4.3.3 Runoff Coefficient Rational Method
The estimation of rainfall excess depends on the method used to estimate the discharge.
In Rational Method, the amount of excess rainfall is determined through an appropriate
determination of the Rational Coefficient. Representative values of rational coefficients for
urban and rural areas are depicted in Table 4.7 (a) and (b).
The runoff coefficient (rational coefficient) is difficult to determine precisely and can be
interpreted in different ways. Engineering judgment is necessary in selecting the appropriate
procedure. Selection of coefficients should be based on ultimate catchment development and
weighted average (calculated through equation 4.6) need be computed where more than one
land use is encountered in a catchment.
26
Ministry of Works and Transport
Drainage Design Manual Section 4
Example 4.2
Given: The following existing and proposed land uses with unimproved existing conditions:
Table Example 4.2.1: Existing Conditions (unimproved):
Weighted C = 0.235
Weighted
C (2.22)(0.90) (0.66)(0.15) (7.52)(0.25) (7.17)(0.22) /(17.55)
Weighted C = 0.315
27
Ministry of Works and Transport
Drainage Design Manual Section 4
Table 4.7- (a): Typical Values of Rational Coefficients for Urban Areas
Table 4.7 - (b): Typical Values of Rational Coefficients for Rural Areas
MAP (mm)
Factor Component
<300 300- 600 >600
3.5% flat 0.01 0.02 0.03
average slope of
3.5%-11% soft to moderate 0.04 0.06 0.08
Cs hillsides in
11%-35% steep 0.09 0.12 0.16
catchment
>35% very steep 0.18 0.22 0.26
very permeable 0.02 0.03 0.04
permeable 0.04 0.06 0.08
Ck Permeability of soil semi-permeable 0.08 0.12 0.16
impermeable 0.15 0.21 0.26
28
Ministry of Works and Transport
Drainage Design Manual Section 4
stoppage of rainfall. For the maximum prolongation Tc + Td = 1.67t (refer Fig. 4.2) the peak flow
by Basic Rational Method is reduced by 25 per cent.
2t c
Cs Eqn. 4.7
2t c t d
where: C s = a reduction factor of the discharge estimated by the Rational
Method
t c = time of concentration
The time area method of obtaining runoff or discharge from rainfall can be considered
as an extension and improvement of the rational method. It is usually used for sensitive
quantification works as it is rather rigorous. The peak discharge is the sum of flow
contributed from sub divisions of the catchment defined by time contours (called
isochrones) which are lines of equal flow time to the point where the discharge is
required. In this method flow from each contributing area bounded by two isochrones
(T T , T ) is obtained from the product of the mean intensity of effective rainfall, i,
from time T T to time T and the area A . For instance the flow at time at X at time
4h is given by:
29
Ministry of Works and Transport
Drainage Design
Drainage Design Manual
Manual Section 4 4
Section
T
i.e: Q p i
k 1
( n k ) A( k ) Eqn. 4.8
As before, the whole catchment is taken to be contributing to the flow after time equals
Tc.
Using the above nomenclature, it is seen that the peak flow at X when the whole
catchment is contributing to the flow, a period Tc after commencement of rainfall, is:
n
Q p i( n k ) A( k ) Eqn. 4.9
k 1
Isochrones
A4
Tc
T
T Rainfall intensity
T
A5
A3
A2 io
i1
i3
5 A1 X
i2 i4
T 1 T 2 T 3 T 4 T 5 T
4 T
T Time, T
3 T 2 T
Figure 4.3: Rainfall Bar Graph and Catchment Showing Isochrones of Travel Time
(Adopted from Shaw, 1981)
The crude assumption made in the Rational method of uniform rainfall intensity over the
whole catchment and during the whole Tc is avoided in the time - area method, where
the catchment contributions are subdivided in time. The varying intensities within a
storm are averaged over discrete period according to the isochrone time interval
selected. Hence in deriving flood peaks for design purposes, a design storm with critical
sequence of intensities can be used for the maximum intensities applied to the
contributing areas of the catchment that have most rapid runoff.
30
Ministry of Works and Transport
4.17
Ministry of Works and Transport
Drainage Design Manual Section 4
31
Ministry of Works and Transport
Drainage Design Manual Section 4
Storage tends to dampen the response of a watershed to very short events and to accentuate
the response to very long events. This alters the relationship between frequency of precipitation
and the frequency of the resultant runoff.
e) Drainage Density
Drainage density can be defined as the ratio between the number of well defined drainage
channels and the total drainage area in a given watershed. Drainage density is usually
assumed to equal the total length of continuously flowing streams (km) divided by the drainage
area (km2).
Drainage density has a strong influence on both the spatial and temporal response of a watershed
to a given precipitation event. If a watershed is well covered by a pattern of interconnected
drainage channels, and the overland flow time is relatively short, the watershed will respond
more rapidly than if it were sparsely drained and overland flow time was relatively long.
Drainage density has impact on the total volume of runoff since some of the abstraction
processes are directly related to how long the rainfall excess exists as overland flow.
Therefore, the lower the density of drainage, the lower will be the volume of runoff from a
given precipitation event.
f) Channel Length
Channel length is an important watershed characteristic. The longer the channel, the more
time it takes for water to be conveyed from the headwaters of the watershed to the outlet.
Consequently, if all other factors are the same, a watershed with a longer channel length will
usually have a slower response to a given precipitation input than a watershed with a shorter
channel length. As the hydrograph travels along a channel, it is attenuated and extended in
time due to the effects of channel storage and hydraulic roughness.
g) Antecedent Moisture Conditions
Antecedent moisture conditions, which are the soil moisture conditions of the watershed at the
beginning of a storm, affect the volume of runoff generated by a particular storm event. Runoff
volumes are related directly to antecedent moisture levels. The smaller the moisture in the
ground at the beginning of precipitation, the lower will be the runoff. Conversely, the larger the
moisture content of the soil, the higher the runoff attributable to a particular storm.
h) Other Factors
There can be other factors within the watershed that determine the characteristics of runoff,
including the extent and type of vegetation, the presence of channel modifications, and flood
control structures. These factors modify the runoff by either augmenting or negating some of
the basin characteristics described above.
4.4 Estimation of Runoff
4.4.1 General
Design methods determine the arrangement of a drainage system and the characteristics and
sizes of its components. They can involve full analysis or simplified procedures. Generally,
the larger, more complex and expensive the project, the more elaborate the method to be
used. Consequences of failure which involve an assessment of the resulting risk should also
influence the choice of the method.
There are two basic approaches to estimate discharges from rainfall. The first approach relates
peak runoff to rainfall intensity through a proportionality factor. The second approach starts
with a rainfall intensity hyetograph, accounts the losses and temporary storage effects and
yields a discharge hydrograph. Strictly speaking, the approach adopted by the first method
could also be interpreted in such a way that it results in a simplified hydrograph. Classified
under the first approach are Rational and Modified Rational Models. Numerous methods are
available under the second approach
32
Ministry of Works and Transport
Drainage Design Manual Section 4
For larger developments and for schemes which can have implication for the drainage system
into which the outfall discharges or the receiving water, time-varying design precipitation and
computer-based flow simulation models are recommended. For any application, it is necessary
to select a method where the appropriate balance between cost, complexity and required
accuracy is achieved.
Many methods, that are based on mathematical models of the physical process involved, are
available. These are expressed as a set of computations performed by hand, programmable
calculator or computer program. They include:
• hydrological models which calculate peak flow rates, storage volumes or flow hydrographs
for system components; and,
• other models and computations concerning water quality, maintenance requirements
and economics.
4.4.2 Rational Method
Rainfall, which can be either an observed storm or a synthesized one, is entered in the form
of an intensity hyetograph. The volume of runoff is determined by assuming an appropriate
rational coefficient that represents the ratio of peak discharge to the rate of rainfall given a
hydraulic balance of the watershed. The Rational Method has been the most frequently used
model. The primary attraction of the Rational Model is its simplicity and its relative tolerance
for data scarcity. Rational Method can provide satisfactory estimates of peak discharge for
small catchments. For larger catchments, storage and timing effects can become significant
and, therefore, a hydrograph method is required. Some methods have been devised to form
hydrographs based on the Rational Formula. Their applicability is, however, to be limited to the
preliminary design of on-site detention and retention facilities.
Rational method of determining peak runoff is mainly based on the following assumptions.
1. The peak flow occurs when the entire area contributes to the flow.
2. The rainfall intensity is uniform over the entire area.
3. The rainfall intensity is uniform over the duration of the rainfall.
4. The return period of the runoff is assumed to match with the return period of the
rainfall.
The model is expressed by the mathematical relationship of the following form
CiA
Q Eqn. 4.10
360
Where:
3
Q is the discharge magnitude for an adopted return period ( m )
s
C is the (dimensionless)rational coefficient
i is the design rainfall intensity ( mm )
hr
A is the area to be drained (ha)
In Rational Method, the parameter C is a dimension less fraction. It shows the proportion of
precipitation rate that contributes to the peak discharge. Although it may appear that C is the
ratio of volume of runoff to volume of precipitation, the rational equation is not intended so. The
ratio of the total loss to total depth of precipitation is not necessarily
1- . Strictly speaking C is the ratio of peak discharge to the rate of rainfall given a hydraulic
balance of the watershed. It accounts for the aggregate effects of the interception, infiltration,
depression storage, etc.. When estimating a value for the Rational Coefficient, the effects of
such hydrologic variables should be taken in to account.
33
Ministry of Works and Transport
Drainage Design Manual Section 4
Similar to the time of concentration, the rational coefficient C also depends, on catchment
characteristics and intensity of rainfall. Among the catchment characteristics, surface cover
and slope are the important ones. Tables 4.7 (a) and (b) provides typical values of rational
coefficient for some land uses.
As the rate of precipitation increases, the proportion of run-off and velocity of overland flow
generally tend to increase. Both the increase in the proportion of runoff and velocity of overland
flow have impacts on the peak discharge. The effects of the aforementioned variables are
usually taken care of by frequency factors. Some of these factors are depicted on Table 4.8.
Table 4.8: Multipliers for Higher Recurrence Interval (Source: UNCHS,1991)
Weighted C
C A i i
13.95
0.32
A 43.7
34
Ministry of Works and Transport
Drainage Design Manual Section 4
The intensity is obtained from the IDF curve for the locality using a duration equal to
the time of concentration:
i = 85 mm/hr
1 (0.32)(85)(43.7)
Q CIA
360 360
= 3.3 m3/sec
4.4.34.4.3
Modified Rational
Modified Method
Rational Method
Modified Rational Method, as the name implies, is a modified version of the Rational
Method. To take care of the rise in significance of the routing effect of catchments, the
Rational Formula is multiplied by a factor the magnitude of which is determined based
on the discussions made under sub Section 4.3.5.
CiA
Q Cs Eqn. 4.11
360
Where:
3
Q is the discharge magnitude for an adopted return period ( m )
s
C s is peak reduction factor
C is the rational coefficient (dimensionless)
i is the design rainfall intensity ( mm ) 35
hr
MinistryAof is
Works and Transport
the area to be drained (ha)
Where:
3
Q is the discharge magnitude for an adopted return period ( m )
s
C s is peak reduction factor
C is the rational coefficient (dimensionless)
i is the design rainfall intensity ( mm )
hr
A is the area to be drained (ha)
Modified Rational Method is recommended when the catchment area exceeds 80
hectares. It could safely be applied up to 120 hectares. For areas that exceed 120
hectares, it should be employed with caution.
4.4.4 4.4.4
SCS Rainfall Runoff Relation
SCS Rainfall Runoff Relation
The Design
Drainage of runoff ( Q ) depends on the volume of precipitation ( P ) and the
volume Manual volume
Section 4
of runoff that is available for retention. The actual retention ( P ) is the difference
between the volume of precipitation and runoff. Further more, a certain volume of
precipitation at the beginning of the storm which is called the initial abstraction ( I a ), will
not appear as runoff. The SCS assumes the following rainfall runoff relations.
4.23
F Works Q and Transport
Ministry of Eqn. 4.12
S P Ia
F (P I a ) Q
Eqn. 4.13
(P Ia ) Q Q
Eqn. 4.14
S P Ia
Rearranging yields
(P I a )2
Q
(P I a ) S Eqn. 4.15
The initial abstraction is a function of land use, treatment and condition; interception;
infiltration; depression storage; and antecedent soil moisture. Initial abstraction could
best be estimated by the following relationship.
The initial abstraction is a function of land use, treatment and condition; interception;
Drainage Design Manual
infiltration; Section
depression storage; and antecedent soil moisture. Initial abstraction 4
could
best be estimated by the following relationship.
( P 0.2 S ) 2
Q
P 0.8S Eqn. 4.17
The volume and rate of runoff depends on both meteorology and watershed
characteristics, and the estimation of runoff requires an index to represent these two
factors. The precipitation volume is probably the single most important meteorological
characteristic in estimating the volume of runoff. The soil type, land use and the
hydrologic conditions of the cover are the watershed factors that will have the most
significant impact in estimating the volume of runoff. The antecedent soil moisture will
also be an important determinant of runoff volume.
The SCS developed an index, which was called the runoff curve number (CN), to represent
the combined hydrologic effect of soil, land use, agricultural land treatment class, hydrologic
4.24
condition, and antecedent soil moisture. Curve Numbers for different soil groups are depicted
Ministry of Works
in Table 4.9. and Transport
b) Soil Group Classification
SCS developed a soil classification system that consists of four groups, which are identified
by the letters A, B, C, and D. Soil characteristics that are associated with each group are as
follows.
Group A: Deep sand, deep loess, aggregated silts
Group B: Shallow loess, sandy loam
Group C: Clay loams, shallow sand loam, soils low in organic content, and soils usually high
in clay
Group D: Soils that swell significantly when wet, heavy plastic clays, and certain saline
soils
37
Ministry of Works and Transport
Drainage Design Manual Section 4
Table. 4.9: Runoff Curve Numbers for Hydrologic Soil Cover Complexes (Antecedent
Moisture Condition II, and Ia = 0.2S (Source: HEC 22)
Land Use Description /Treatment/
Hydrologic Soil Group
Hydrologic Condition
Residential I
Average lot Average A B C D
size Impervious (%)
1/8acre or less 65 77 85 90 92
1/4acre or less 38 61 75 83 87
1/3acre or less 30 57 72 81 86
1/2acre or less 25 54 70 80 85
1acre or less 20 51 68 79 84
Paved Parking Lots, roofs, drive
98 98 98 98
ways, etc.
Streets and roads
Paved with curbs and storm sewers 98 98 98 98
Gravel 76 85 89 91
Dirt 72 82 87 89
Commercial and business areas (85
89 92 94 95
%) impervious
Industrial districts (72 %
81 88 91 93
impervious)
Open spaces, lawns, parks, cemeteries, etc..
good condition: grass cover on 75
39 61 74 80
% or more of the area
fair condition: grass cover on 50 %
49 69 79 84
to 75 % of the area
38
Ministry of Works and Transport
Drainage Design Manual Section 4
39
Ministry of Works and Transport
Drainage Design Manual Section 4
4.4.4.1 Limitations of the SCS Runoff Curve Number Method (SCS, 1986)
SCS could be used for larger catchments with due consideration for the following
limitations it has:
• Curve numbers describe average conditions that are useful for design purposes. If
the rainfall event used is a historical storm, the modeling accuracy decreases.
• Use the runoff curve number equation with caution when recreating specific
features of an actual storm. The equation does not contain an expression for
time and, therefore, does not account for rainfall duration or intensity.
• The user should understand the assumption reflected in the initial abstraction
term ( ) and should ascertain that the assumption that applies to the situation.
, which consists of interception, initial infiltration, depression storage,
evapotranspiration, and other factors, was generalized as 0.2S based on data
from agricultural watersheds (S is the potential maximum retention after runoff
begins). This approximation can be especially important in urban areas because
the combination of impervious areas with pervious areas can imply a significant
initial loss that may not take place. The opposite effect, a greater initial loss, can
occur if impervious areas have surface depressions that store some runoff.
• The CN procedure is less accurate when runoff is less than 12 mm. As a check,
use another procedure to determine runoff.
• When the weighted CN is less than 40, use another procedure to determine
runoff.
4.4.5 Design of Drainage Network in Built up Areas
The design of a drainage line in built up areas could be effected employing the design methods
discussed in the different sections of this manual. The design of a network of drainage lines
which is usually encountered in built up portions of urban areas requires systematic handling
of the design procedure. This could be facilitated using Design Formats. The design format
adopted for the Manual is given in Appendix 4.2.
40
Ministry of Works and Transport
Drainage Design Manual Section 4
41
Ministry of Works and Transport
Drainage Design Manual Section 5
SECTION 5
5.0 UNIT HYDROGRAPH METHOD
5.1 General
A hydrograph is a graph of discharge rate, which passes a particular point, verses time.
It reflects both precipitation and watershed characteristics. The slope of the rising limb
is specially sensitive to rainfall characteristic while the shape of the recession limb is
more sensitive to characteristics of the watershed. The crest segment is sensitive to both
rainfall and watershed characteristic.
A unit hydrograph is a special case of flood hydrograph. Specifically a unit hydrograph is
the hydrograph that results from 1 millimeter of excess rainfall generated uniformly over
the watershed at a uniform rate during a specified period of time. While discussing unit
hydrographs, the following five points warrant emphasis.
1) The rainfall occurs from excess rainfall.
2) The volume of runoff is 1 millimeter.
3) The excess rainfall is applied at a uniform rate.
4) The excess is applied with uniform spatial distribution.
5) The intensity of rainfall excess is constant over a specified period of time, which is
termed as the duration of the rainfall.
There are several types of unit hydrographs. The ones of interest herein are the
dimensionless and D-hour unit hydrograph in which case the duration of excess rainfall
is D-hours. A dimensionless unit hydrograph is a hydrograph the ordinates of which are
given as a ratio of the time to peak discharge ( q p ) and the time axis of which is
q
measured as a ratio of the time to peak ( t p ); that is, it is a graph of qp versus t
tp ,
where q is the discharge at any time t .
Two steps are employed to calculate the hydrograph, the runoff Curve Number method
and the Tabular Hydrograph Method. The Runoff Curve Number method is used to
determine the runoff and the Tabular Hydrograph method is used to calculate the
composite hydrograph at the watershed outlet.
To calculate a hydrograph the simplified method known as TR-55 methodology begins with
imposing a specific time distribution of rainfall uniformly in space over the watershed.
The rainfall is converted to runoff with the Runoff Curve Number method. A unit hydrograph
is obtained based on sub-area and event specific variables. The unit hydrograph is then
scaled by the rainfall to obtain the hydrograph using the Tabular Hydrograph method.
5.2.1 SCS Dimensionless Unit Hydrograph
The SCS methods use dimensionless unit hydrographs that are based on an extensive
analysis of measured data. Unit hydrographs were evaluated for a large number of actual
watersheds and then made dimensionless. An average of these dimensionless unit
hydrographs was developed. The time base of unit hydrograph was approximately five
times the time-to-peak and approximately 3/8 of the total volume accrued before the time-
to-peak. The inflection point on the recession limb occurs at approximately 1.7 times the
time-to-peak and the unit hydrograph has a curvilinear shape. The average dimensionless
unit hydrograph is shown in Fig. 5.1 and the discharge ratios for selected values of the
time ratio are given in Table 5.1.
42
Ministry of Works and Transport
Drainage Design Manual Section 5
The curvilinear hydrograph can be approximated by a triangular unit hydrograph that has more
or less similar characteristics. Fig 5.2 shows the comparison of the two unit hydrographs. While
the time base of the triangular unit hydrograph is only 8/3 of the time-to-peak (compared to 5
for the curvilinear unit hydrograph, the area under the rising limbs of the two unit hydrographs
are the same (~37.5 per cent)
5.2.2 Peak Discharge of the Unit Hydrograph
The area under the unit hydrograph equals the volume of direct runoff, which was estimated
by Eqn 5.1.
1
Q q p (t p t r ) Eqn. 5.1
2
Where:
t p is time-to-peak
t r is the recession time
t p is the peak discharge.
Q 2
qp Eqn. 5.2
t p tr
1 t
p
Letting K replace the contents within the bracket yields:
KQ
qp Eqn. 5.3
tp
Considering area to be measured in km2, t p to be measured in hours, and the
discharge to be obtained in m3/s, the formula could be rearranged as:
0.208 AQ
qp Eqn. 5.4
tp
ForFor
mountainous
mountainouswatershed, thethe
watershed, constant may
constant go go
may as as
high as as
high 0.258 andand
0.258 for for
flat flat
swampy areas
swampy
it may come down as low as 0.129.
areas it may come down as low as 0.129.
The time-to-peak in the peak discharge equation may be expressed in terms of the duration
of unit precipitation excess and the time of concentration. Fig. 5.2 provides the following
relationships
D
tp 0.6t c Eqn. 5.6
2
Solving for D (rainfall duration) yields
( t ) q ) Qa
tp qp Ratios ( )
Q
0 .000 .000
.1 .030 .001
.2 .100 .006
.3 .190 .012
.4 .310 .035
.5 .470 .065
.6 .660 .107
.7 .820 .163
.8 .930 .228
.9 .990 .300
1.0 1.000 .375
1.1 .990 .450
1.2 .930 .522
1.3 .860 .589
1.4 .780 .650
1.5 .680 .700
1.6 .560 .751
1.7 .460 .790
1.8 .390 .822
1.9 .330 .849
2.0 .280 .871
2.2 .207 .908
2.4 .147 .934
2.6 .107 .953
2.8 .077 .961
3.0 .055 .977
3.2 .040 .984
3.4 .029 .989
3.6 .021 .993
3.8 .015 .995
4.0 .011 .997
4.5 .005 .999
5.0 .000 1.000
44
Ministry of Works and Transport
Drainage Design Manual Section 5
1.2
1
Discharge Ratio (q/qp)
0.8
0.6
0.4
0.2
0
0 1 2 3 4 5 6
Fig. 5.1: Dimensionless Unit Hydrograph and Mass Curve (Computed from Table 5.1)
5.2.3 Convolution
Fig: 5.2: Dimensionless Curvilinear Unit Hydrograph and Equivalent Triangular Hydrograph
(Source: Adopted from H.McLVEN, 1982)
Fig: 5.2: Dimensionless Curvilinear Unit Hydrograph and Equivalent Triangular Hydrograph
5.6
Ministry of Works and Transport
45
Ministry of Works and Transport
Drainage Design
Drainage Manual
Design Manual Section
Section 5 5
3.125 Ak QD 3.125(1.2)(1) 3
qp 2.8 m
tc 1.34 s
2 2
tp t c (1.34) 0.893hr
3 3
46
Ministry of Works and Transport
5.7
Ministry of Works and Transport
Drainage Design Manual Section 5
Example 5.2
Given:
Excess rainfall data given in Table Example 5.2.1
Time, t (hr) Unit Direct Runoff Direct Runoff Direct Runoff Total Direct
Hydrograph for first hour for second for third hour Runoff
Discharge, Q (m3/s) hour (m3/s) Outflow
(m3/s)
(m3/s) Hydrograph
(m3/s)
(1) (2) (3) (4) (5) (6) (7)
0 0 (0.5)(0) = 0 - - 0=0
1 30 (0.5)(30)=15 (1.0)(0)=0 - 15+0=15
2 10 (0.5)(10)=5 (1.0)(30)=30 (1.5)(0)=0 5+30+0=35
3 0 (0.5)(0)=0 (1.0)(10)=10 (1.5)(30)=45 0+10+45=55
4 (1.0)(0)=0 (1.5)(10)=15 0+15=15
5 (1.5)(0)=0 0=0
The final total direct outflow hydrograph is shown in Figure Table: Example 5.2-2 (b)
47
Ministry of Works and Transport
Drainage Design Manual Section 5
Drainage Design Manual Section 5
48 5.9
Ministry of Works and Transport
Ministry of Works and Transport
DrainageDesign
Drainage DesignManual
Manual Section 5
Section 5
5.3
5.3 TRRLEast
TRRL East African
African Flood
Flood ModelModel
5.3.1of Form
5.3.1 Form Model of Model
The most widely used dimensionless unit hydrograph is that of the US Soil
Conservation Service. The similar results for the ratio of time to peak to base time for
other catchments is not satisfactorily applicable in East African catchments studied by
TRRL. In the TRRL East African Flood Model the base time is assumed to be the time
from 1 per cent of peak flow on the rising limb to 10 per cent of peak flow on the falling
limb of the hydrograph. Defined this way, the ratio of base time to time to peak is
approximately 3.0 for US hydrographs. For East African catchments it varied between
2.7 and 11.0. The use of a single hydrograph base on time to peak was therefore not
appropriate.
A much more stable ratio was found to be the peak flow (Q) divided by the average
flow measured over the base time (Q ) (Peak Flow Factor)
Q
F Eqn. 5.8
Q
The peak flow can therefore be simply estimated if the average flow during the base
time of the hydrograph can be calculated.
RO ( P Y )C A * A * 10 3 ( m 3 ) Eqn. 5.9
Where: P = rainfall (mm) during time period equal to the base time
Y = initial retention
CA = contributing are coefficient
A = catchment area (km2)
If the hydrograph base time is measured to a point on the recession curve at which the
flow is one tenth of the peak flow, then the volume under the hydrograph is
approximately 7 per cent less than the total run off given by eqn. 5.9
0.93 * RO
Q Eqn. 5.10
3600 * TB
Where:
TB = hydrograph base time (hrs.)
Estimates of Y and CA are required to calculate RO and lag time K to calculate TB.
In arid and semi arid zones an initial retention of 5 mm could be considered. Elsewhere 49
zero initial retention could be assumed.
Ministry of Works and Transport
5.10
Ministry of Works and Transport
Where:
TB = hydrograph base time (hrs.)
Drainage
In Design
arid
5.3.3 Manual
and semi
ContributingaridArea
zones an initial retention
Coefficient (CA) Section 5
of 5 mm could be considered. Elsewhere
5.3.3 Contributing Area Coefficient
zero initial retention could be assumed. (CA)
Contributing area coefficient is a coefficient that reflects the effects of the catchment
Contributing
5.3.3
5.3.2 Contributing
wetness area
Contributing
andArea coefficient
Area
the land is a ) coefficient
use.Coefficient
Coefficient
A (C
grassed (CA)
catchmentthatatreflects the effects
field capacity of the
is taken as acatchment
standard
A 5.10
wetness
value and the land
of contributing use. A grassed catchment at field capacity is taken
area coefficient. The design value of the contributing as a standard
area
Ministry of Works and Transport
value of contributing
Contributing
coefficient area coefficient.
areabecoefficient
could estimated isfrom Thethat
a coefficient
the followingdesign value
reflects
equation. the of the contributing
effects area
of the catchment
coefficient could be estimated from the following equation.
wetness and the land use. A grassed catchment at field capacity is taken as a standard
value of contributing area coefficient. The design value of the contributing area
C A C S *could
coefficient C * C Lestimated from the following equation. Eqn. 5.11
C C * CW *be
A S W C L Eqn. 5.11
A CS *
CWhere: CC *C Eqn. 5.11
S W= theL standard value of contributing area coefficient for a grassed
Where: CS = the standard value of contributing area coefficient for a grassed
catchment at field capacity
catchment at field capacity
Where: CCWS ==the catchment
the standardwetness factor
value of contributing area coefficient for a grassed
CW = the catchment wetness factor
CL =catchment
the land useat factor
field capacity
CL = the land use factor
CW = the catchment wetness factor
The threeCfactors
L = the are given
land usein Tables 5.2, 5.3, and 5.4
factor
The three factors are given in Tables 5.2, 5.3, and 5.4
Table 5.2: Standard Contributing Area Coefficient (wet zone catchment, short grass
TableThe three
5.2: factors Contributing
Standard are given in Tables 5.2, 5.3, and(wet
Area Coefficient 5.4 zone catchment, short grass
cover)
Source: TRRL Laboratory Report 706 cover)
Table
Table Source:
5.2:5.2:
Standard
StandardTRRL Laboratory
Contributing
ContributingArea Report
Area 706 (wet(wet
Coefficient
Coefficient zone catchment,
zone short
catchment, grass
short cover)
grass
cover)
Source: TRRL Laboratory Report 706 Soil Type
Soil Type
Catchment Slope Slightly Impeded
Catchment Slope Well Drained Slightly Impeded Impeded Drainage
Well Drained Drainage
Soil Type Impeded Drainage
Drainage
Very Flat
Catchment < 1.0 %
Slope 0.15
Slightly Impeded 0.30
Very Flat < 1.0 % Well Drained 0.15 Impeded0.30
Drainage
Moderate 1-4 % 0.09 0.38
Drainage 0.40
Moderate 1-4 % 0.09 0.38 0.40
Rolling
Very Flat <4-10
1.0 % 0.10 0.45
0.15 0.50
0.30
Rolling 4-10 % 0.10 0.45 0.50
Hilly
Moderate 10-20
1-4 %% 0.11
0.09 0.50
0.38 0.40
Hilly 10-20 % 0.11 0.50
Mountainous 4-10
Rolling >20 % % 0.12
0.10 0.45 0.50
Mountainous >20 % 0.12
Note:
Hilly The soil types
10-20 % are based on
0.11 the soil map contained
0.50 in the Hand Book of Natural
Note: The soil types are based on the soil map contained in the Hand Book of Natural
Resources
Mountainous >20 % of East Africa0.12
Resources of East Africa
Note: The soil types are based on the soil map contained in the Hand Book of Natural
Table
Resources
Table of East Table
5.3: Catchment
5.3: Catchment Africa 5.3: Catchment
Wetness Wetness
Factor (Source: Factor
TRRL Laboratory Report 706)
Wetness Factor (Source: TRRL Laboratory Report 706)
Catchment Wetness Factor
Table 5.3: Catchment
Rainfall Zone Wetness Factor (Source: TRRL Laboratory
Catchment Report 706)
Wetness Factor
Rainfall Zone Perennial Streams Ephemera Streams
Perennial Streams Ephemera Streams
Wet Zone 1.0
Catchment Wetness Factor1.0
Wet Zone Rainfall Zone 1.0 1.0
Semi Arid Zone Perennial1.0Streams Ephemera1.0Streams
Semi Arid Zone 1.0 1.0
Dry Zones
Wet Zone (except West. Uganda) 0.75
1.0 0.50
1.0
Dry Zones (except West. Uganda) 0.75 0.50
West Arid
Semi Uganda
Zone 0.60
1.0 0.30
1.0
West Uganda 0.60 0.30
Dry Zones (except West. Uganda) 0.75 0.50
West Uganda 0.60 0.30
50
Ministry of Works and Transport
5.11
5.11
Drainage Design Manual Section 5
Drainage Design Manual Section 5
Drainage Design Manual Section 5
Table 5.4: Land Use Factor (Base assumes short grass cover)
Table 5.4: Land Use Factor (Base assumes short grass cover)
Source: TRRLTable
Laboratory Report
5.4: Land Use 706
Factor (Base assumes short grass cover)
Source: TRRL Laboratory Report 706
51
5.12
Ministry of Works and Transport 5.12
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Section 5
Drainage
DrainageDesign
DesignManual
Manual Section
Section 5 5
Table 5.6: Rainfall Time (TP) for East African 10 year Storm
(Source:
Table 5.6: Rainfall TRRL
Time (TP) forLaboratory Report
East African 706)
10 year Storm
(Source: TRRL Laboratory Report 706)
Zone Index 'c' Rainfall time (T P) (hr)
Inland zone Zone Index
0.96'c' Rainfall time
0.75 (T P) (hr)
Inland
Coastalzone
zone 0.96
0.76 0.75
4.0
Coastal zone
Kenya Aberdare Uluguru Zone 0.76
0.85 4.0
2.0
Kenya Aberdare Uluguru Zone 0.85 2.0
The flood wave attenuation (TA) could be estimated from equation 5.13
The flood wave attenuation (TA) could be estimated from equation 5.13
0.028L
TA 1 1 Eqn. 5.13
0.028L
T A Q 14 S 12 Eqn. 5.13
Q 4S 2
Where:
Where: L = length of main stream (km)
LQ==length of main
average streambase
flow during (km)time (m3/s)
Q== average
S averageslope
flow during base time
along main (m3/s)
stream
The base S
time is, therefore,
= average slope estimated
along mainfrom equation 5.14:
stream
The base time is, therefore, estimated from equation 5.14:
TB TP 2.3K T A Eqn. 5.14
T TP 2.3K T A Eqn. 5.14
It Bis noted that Q appears in eqn. 5.13. So an iterative or trial end error solution is
It is notedIf that Q Tappears in eqn. 5.13. So an iterative or trial end error solution is
required. initially A is assumed zero, two iterations could be adequate. Knowing Q
and F, theIfpeak
required. flowTAisiscalculated
initially assumedusing zero, eqn. 5.8
two iterations could be adequate. Knowing Q
and F, the peak flow is calculated using eqn. 5.8
Example 5.3 (Adopted from TRRL Laboratory Report 706)
Example 5.3 (Adopted from TRRL Laboratory Report 706)
A 10 year average recurrence interval design flood is required for a catchment that has
the10following
A details.recurrence interval design flood is required for a catchment that has
year average
the following details.
a) Area: 10 square kilometer
a)
b) Area: 10 square
Land slope: 6 % kilometer
C) Land
b) Channel slope:
slope: 6 %3%
d) Channel
C) Channel length:
slope: 3%4 km
o
d) Channel length: 4Skm
e) Grid reference: 5 35o E
o o
f)
e)Catchment
Grid reference: type:5Poor
S 35pasture
E
f) Catchment type: Poor pasture
From Table 5.5, lag time (K) = 0.5 h
From Table
Appendix5.5,5.1
lag and
timeTable
(K) = 5.2,
0.5 hstandard contributing area coefficient CS = 0.45
From Table
Appendix5.3,5.1
catchment
and Table wetness factor CW
5.2, standard = 0.5
contributing area coefficient CS = 0.45
From Table 5.4, 5.3, land use factor
catchment CL =factor
wetness 1.0 CW = 0.5
Therefore,
From Tablethe 5.4,design value
land use for CCAL == 0.23
factor 1.0
Initial retention
Therefore, Y = 0 value for CA = 0.23
the design
From
Initial Table 5.6,YT=P 0
retention = 0.75 hrs.
From Table 5.6, TP = 0.75 hrs.
Using Eqn. 5.14with TA = 0
Ts = 0.75
Using + 0.23
Eqn. (0.5)T=A =1.9hrs.
5.14with 0
Ts = 0.75 + 0.23 (0.5) = 1.9hrs.
52
Ministry of Works and Transport 5.13
Ministry of Works and Transport 5.13
Ministry of Works and Transport
Drainage Design Manual Section 5
53
Ministry of Works and Transport 5.14
Ministry of Works and Transport
Drainage Design Manual Section 6
SECTION 6
6.0 FREQUENCY ANALYSIS OF GAUGED DATA
6.1 General
Analysis of gauged data permits an estimate of the peak discharge in terms of its probability
or frequency of exceedance at a given site. This is done by statistical methods provided
sufficient data are available at the site to permit a meaningful statistical analysis to be made.
It is suggested that at least 10 years of record are necessary to warrant a statistical analysis
by method presented therein.
At some sites, historical data may exist on large floods prior to or after the period over which
stream flow data were collected. Whenever possible, these data should be compiled and
documented to improve frequency estimates.
6.2 Analysis of Annual and Partial-Duration Series
Before analyzing data, it is necessary to arrange it in a systematic manner. Data can be arranged
in a number of ways depending on the specific characteristics that are to be examined. An
arrangement of data by a specific characteristic is called a distribution or a series.
The most common arrangement of hydrologic data is by magnitude of the annual peak
discharge. This arrangement is called an annual series. Another method used in flood data
arrangement is the partial-duration series. This procedure uses all peak flows (for instance all
flows above the discharge of approximately bank-full stage) above some base value.
Partial-duration series are used primarily in defining annual flood damages when more than
one event that causes flood damages can occur in any year. The partial-duration series avoids
a problem with the annual-maximum series. Annual maximum series analyses ignore floods
that are not the highest flood of that year even though they are larger than the highest floods of
other years. While partial-duration series produce larger sample sizes than annual maximum
series, they require a criterion that defines independence of the discharges to be considered
for the frequency analysis.
The difference between the results of the two methods is large at the lower flows and becomes
very small at the higher peak discharges. If the recurrence interval of these peak flows is
computed as the order divided by the number of events (not years), the recurrence interval of
the partial-duration series can be computed in terms of the annual series by the equation:
1
TB Eqn (6.1)
ln T A ln(T A 1)
where:
TB and TA are the recurrence intervals of the partial-duration series and annual series,
respectively.
Comparison between analyses results of the two methods shows that the maximum deviation
between the two series occurs for flows with recurrence intervals less than 10 years. At this
interval the deviation is about 5 percent and for the 5-year discharge, the deviation is about 10
percent. For the less frequent floods, the two series approach one another.
When using the partial-duration series, one must be especially careful that the selected flood
peaks are independent events. This is a tough practical problem since secondary flood peaks
may occur during the same flood as a result of high antecedent moisture conditions. In this
case, the secondary flood is not an independent event. One should also be cautious with the
choice of the lower limit or base flood since it directly affects the computation of the properties
of the distribution (i.e., the mean, the variance and standard deviation, and the coefficient of
skew) all of which may change the peak flow determinations.
54
Ministry of Works and Transport
Drainage Design Manual Section 6
For this reason, it is probably best to utilize the annual series and convert the results to a
partial-duration series through use of Equation 6.1. For the less frequent events (greater than
5 to 10 years), the annual series is entirely appropriate and no other analysis is required.
6.3 Frequency Analysis Concepts
Future floods cannot be predicted with certainty. Therefore, their magnitude and frequency are
treated using probability concepts. To do this, a sample of flood magnitudes are obtained and
analyzed for the purpose of estimating a population that can be used to represent flooding at
that location. The assumed population is then used in making projections of the magnitude
and frequency of floods. It is important to recognize that the population is estimated from
sample information and that the assumed population, not the sample, is then used for making
statements about the likelihood of future flooding. The purpose of this section is to introduce
concepts that are important in analyzing sample flood data in order to identify a probability
distribution that can represent the occurrence of flooding.
6.3.1 Plotting Position Formulas
When making a flood frequency analysis, it is common to plot both the assumed population
and the peak discharges of the sample. To plot the sample values on frequency paper, it is
necessary to assign an exceedence probability to each magnitude. A plotting position formula
is used for this purpose. A number of different formulas have been proposed for computing
plotting position probabilities, with no unanimity on the preferred method. A general formula for
computing plotting positions is:
ia
P Eqn. 6.2
n a b 1
where:
i = the rank of the ordered flood magnitudes, with the largest flood having a rank of 1
n = the record length
a and b = constants for a particular plotting position formula
55
Ministry of Works and Transport
Drainage Design Manual Section 6
Several cumulative frequency distributions are commonly used in the analysis of hydrologic
data, and as a result they have been studied extensively and are now standardized. The
frequency distributions that have been found most useful in hydrologic data analysis are the
normal distribution, the log-normal distribution, the Gumbel extreme value distribution, and the
log-Pearson Type III distribution.
Log-Pearson Type III Distribution has found wide application in hydrologic analysis. It is a
three-parameter gamma distribution with a logarithmic transform of the variable. It is widely
used for flood analyses because the data quite frequently fit the assumed population.
The log-Pearson Type III distribution differs from most of other distributions in that three
parameters (mean, standard deviation, and coefficient of skew) are necessary to describe the
distribution. By judicious selection of these three parameters, it is possible to fit just about any
shape of distribution.
An abbreviated table of the log-Pearson III distribution function is given in 6.1. Using the mean,
standard deviation, and skew coefficient for any set of log-transformed annual peak flow data,
in conjunction with 6.1, the flood with any exceedence frequency can be computed from the
equation:
A) Procedure
The specific steps for making a basic log-Pearson type III LP3 analysis without any of
the optional adjustments are as follows:
Q i
Q i 1 Eqn. 6.5
n
0 .5
n 2
0.5
Qi
n
2
(Qi Q) ( Q 1)
= Q Eqn 6.6
i 1
S i 1
n 1 n 1
n Q n
n(Qi Q) n( i 1)3
3
i1 Q
G i1 Eqn. 6.7
56
(n 1)(n 2)V (n 1)(n 2)V3
3
S
Ministry of where: V Transport
Works and
X
n
Q i
Q i 1 Eqn. 6.5
n
0 .5
n 2
0.5
Qi
n
2
(Qi Q) ( Q 1)
Drainage Design
S Manual
i 1 = Q i 1
Eqn 6.6 Section 6
n 1 n 1
n n
Q
n(Qi Q)3 n( i 1)3
i1 Q
G i1 Eqn. 6.7
(n 1)(n 2)V (n 1)(n 2)V3
3
S
where: V
X
3. Since the LP3 curve with a nonzero skew does not plot as a straight line, it is necessary
to use more than two points to draw the curve. The curvature of the line will increase as
the absolute value of the skew increases, so more points will be needed for larger skew
magnitudes.
4. Compute the logarithmic value for each exceedence frequency using Equation 6.4.
5. Transform the computed values of step 4 to discharges using
Xˆ 10Y
Eqn 6.8
in which
Xˆ is 10 Y
the computed discharge for the assumed LP3 population.
6. Plot the points of step 5 on logarithmic probability paper and draw a smooth curve
through the points. The sample data can be plotted on the paper using a plotting position
formula to obtain the exceedence probability. The computed curve can then be verified,
and, if acceptable, it can be used to make estimates of either a flood probability or flood
magnitude.
Log-Pearson III distributions are usually plotted on log-normal probability graph paper
even though the plotted frequency distribution may not be a straight line. It is a straight
line only when the skew of the logarithms is zero.
Example 6.1 (Adopted from HDS 2, 1996)
The Log-Pearson Type III distribution will be illustrated using an exemplary river flood data
(Table Example 6-1-1) for the case of station skew. Appendix 6-1 and Equation 6.4 are used
to compute values of the log-Pearson III distribution for the 2- to 100- years flood using the
parameters, Y , S y , and G for the flood data with the following steps.
Step 1: Transform all the flow into their logarithmic values
This is done by taking the logarithm (to the base 10) of the discharge data. In the
example, it is included in the third column of Table Example 6.1 – 1.
Step 2: Computation of the mean ( Q ) , standard deviation (S), and station skew (G) of the
logarithms using Equation 6.5, Equation 6.6, and Equation 6.7, respectively for both
the flow data and the log-transformed data sets. The means for the flow data and the
log transformed version are figured out to be 186.96 and 2.0912 respectively and
standard deviations are computed to be 200.33 and 0.3941 respectively. To facilitate
the computation of the generalized skew, the term n
∑(
i =1
Qi
Q
− 1) 3
is rendered in the fifth column of Table Example 6.1–1. The Station Skew is then
computed to be 0.236 employing Eqn. 6.7. The value 0.236 is rounded to the nearest
tenth (i.e. to 0.2).
57
Ministry of Works and Transport
Drainage Design Manual Section 6
Step 3: For the Frequency value for which the discharge is to be estimated, compute the
exceedence probability. For Frequency of 10 years, for instance, the exceedence
probability is
0.1 = 1/10
With the G value computed in step 2 and the exceedence probability for the
frequency value under consideration, find the K value from Appendix 6.1.
For the rounded of G value of 0.2 and exceedence probability of 0.1, for
instance, the corresponding K value is read to be 1.30105 and the Y value is
2.6039 = 2.0912 + 1.30105(0.3941).
Step 4: Transform the computed values of step 3 to discharges using Eqn. 6.8. The discharge
for the return period of 10 years, thus, become
401.7 m 3 / s 10 2.6039
Similarly the discharges for the different frequency values could be computed. The
results for the frequency values of two to hundred years are rendered in Table Example
6.1- 2.
58
Ministry of Works and Transport
Drainage Design Manual Section 6
Drainage Design Manual Section 6
Weibull Plotting
Flood X, (m3/s) Rank Y = Log (x) Position (Y Y 1)3
903.30 1 2.96 0.023 0.071
900.50 2 2.95 0.045 0.070
495.50 3 2.70 0.068 0.024
492.70 4 2.69 0.091 0.024
410.60 5 2.61 0.114 0.016
370.90 6 2.57 0.136 0.012
342.60 7 2.53 0.159 0.010
274.10 8 2.44 0.182 0.005
267.30 9 2.43 0.205 0.004
261.10 10 2.42 0.227 0.004
231.10 11 2.36 0.250 0.002
212.70 12 2.33 0.273 0.001
195.10 13 2.29 0.295 0.001
180.10 14 2.26 0.318 0.000
160.30 15 2.20 0.341 0.000
155.20 16 2.19 0.364 0.000
153.80 17 2.19 0.386 0.000
146.70 18 2.17 0.409 0.000
140.60 19 2.15 0.432 0.000
134.50 20 2.13 0.455 0.000
130.80 21 2.12 0.477 0.000
116.90 22 2.07 0.500 0.000
112.10 23 2.05 0.523 0.000
100.20 24 2.00 0.545 0.000
95.10 25 1.98 0.568 0.000
94.90 26 1.98 0.591 0.000
90.60 27 1.96 0.614 0.000
86.40 28 1.94 0.636 0.000
83.50 29 1.92 0.659 -0.001
77.30 30 1.89 0.682 -0.001
71.90 31 1.86 0.705 -0.001
61.20 32 1.79 0.727 -0.003
60.90 33 1.78 0.750 -0.003
60.60 34 1.78 0.773 -0.003
58.00 35 1.76 0.795 -0.004
56.60 36 1.75 0.818 -0.004
56.10 37 1.75 0.841 -0.004
49.50 38 1.69 0.864 -0.007
41.60 39 1.62 0.886 -0.012
34.00 40 1.53 0.909 -0.019
25.20 41 1.40 0.932 -0.036
24.50 42 1.39 0.955 -0.038
22.70 43 1.36 0.977 -0.043
59
Ministry of Works and Transport
6.6
Ministry of Works and Transport
Drainage Design Manual Section 6
Table Example 6.1- 2. Calculation of Log Pearson Type III Discharges for the
Exemplary River Using Station Skew
(1)
(2) 5
Return (3) (4)
Exceedence X
Period K Y 3
Probability (m /s)
(Yrs)
2 0.50 -0.03325 2.0781 119.7
5 0.20 0.83044 2.4185 262.1
10 0.10 1.30105 2.6039 401.7
25 0.04 1.81756 2.8075 641.9
50 0.02 2.15935 2.9422 875.3
100 0.01 2.47226 3.0655 1162.8
Compute the plotting position values for the discharge data set given for example
6.1using Weibull Plotting Position Formula.
Step 1: The discharge data is arranged in rank. This is done in column 4 of Table
Example 6.1-1
Step 2: Compute the plotting position value employing Weibull’s formula. For the data
ranked first, the plotting position value is (for i = 1 and n=43)
1
0.023
43 1
Using similar procedure, the plotting position values could be calculated for the whole
data set.
6.3.3 Outliers
6.3.3 Outliers
Outliers, which may be found at either or both ends of a frequency distribution, are
measured values that occur, but appear to be from a longer sample or different
population. This is reflected when one or more data points do not follow the trend of the
remaining data. If the station skew is greater than 0.4, tests are applied for high outliers
first; and if less than -0.4, low outliers are considered first. If the station skew is
between ± 0.4, both high and low outliers are tested before any data are eliminated.
The detection of high and low outliers is obtained with the following equations,
respectively:
YL Y K N S Y Eqn. 6.9
and
YL Y K N S Y Eqn. 6.10
where:
YL is the log of the high or low outlier limit
Y is the deviation of the sample
K N is the critical deviate taken from Appendix 6.2
If the sample is found to contain high outliers, the peak flows should be checked
against historical data and data from nearby stations. It is recommended that high
outliers be adjusted for historical information or retained in the sample as a systematic
peak. The high outlier should not be discarded unless the peak flow is shown to be
seriously in error. If a high outlier is adjusted based on historical data, the mean and
60
Ministry of Works and Transport
Drainage Design Manual Section 6
seriously in error. If a high outlier is adjusted based on historical data, the mean and standard
deviation of the log distribution should be recomputed for the adjusted data before testing
for low outliers.
To test for low outliers, the low outlier threshold YL of Equation 6.10 is computed. The
corresponding discharge X L = 10 YL is then computed. If any discharges in the flood
series are less than X L , then they are considered to be low outliers and should be
deleted from the sample.
To illustrate the criteria for outlier detection, Equation (6.9) and Equation (6.10) are
applied to the 43-year record for the exemplary River data (Table Example 6.1-1),
which has a log mean of 2.0912 and a log standard deviation of 0.3941. From Appendix
6.2 , KN = 2.710. Testing first for high outliers
and
X L 10 3.1592 1443 m
3
s
No flows in the sample exceed this amount, so there are no high outliers. Now testing
for low outliers, Equation 6.10 gives
and
X L 101.0232 11 m
3
s
There are no flows in the Medina River sample that are less than this critical value. Therefore,
the entire sample should be used in the log-Pearson III analysis. If any discharges in the flood
series are less than XL, then they are considered to be low outliers and should be deleted from
the sample. The moments should be recomputed with the data set that does not bear the low
outlier.
6.3.4 6.3.4 Incomplete
Incomplete Records
Records andFlows
and Zero Zero Flows
Stream flow records are often interrupted for a variety of reasons. Gages may be removed
for some period of time, there may be periods of zero flow and there may be periods when a
gage is inoperative either because the flow is too low to record or it is too large and causes
a gage malfunction. If the break in the record is not flood related, such as the removal of a
gage, no special adjustments are needed and the segments of the interrupted record can be
combined together to produce a record equal to the sum of the length of the segments. When
a gage malfunctions during a flood, it is usually possible to estimate the peak discharge from
high water marks or slope-area calculations. The estimate is made a part of the record, and a
frequency analysis performed without further adjustment.
Zero flows or flows that are too low to be recorded present more of a problem since in the
log transform, these flows produce undefined values. In this case, an adjustment based on
conditional probability that is applicable if not more than 25 percent of the sample is eliminated.
The adjustment for zero flows also is applied only after all other data adjustments have been
made. The adjustment is made by first calculating the relative frequency, , that the annual peak
will exceed the level below which flows are zero, or not considered (the truncation level):
61
Ministry of Works and Transport
Drainage Design Manual Section 6
M
Pa Eqn. 6.11
n
where:
P Pa * Pd Eqn. 6.12
where:
Since the frequency curve adjusted by Equation 6.12 has unknown statistics, its
properties, synthetic values, are computed by the equations:
log(Q0.01 / Q0.50 )
SS Eqn. 6.14
K 0.01 K 0.50
and
log(Q0.01 / Q0.10
G S 2.50 3.12 Eqn. 6.15
log(Q0.10 / Q0.50 )
where:
Q S , Ss , and Gs are the mean, standard deviation, and skew of the synthetic
frequency curve, Q0.01 , Q0.10 and Q0.50 are discharges with exceedence probabilities
of 0.01, 0.10 and 0.50, respectively, K 0.01 and K 0.50 are the log-Pearson III deviates for
exceedence probabilities of 0.01 and 0.50, respectively.
The values of Q0.01 , Q0.10 and Q0.50 must usually be interpolated since probabilities
computed with Equation 6.11 are not normally those needed to compute the properties
of the synthetic or truncated distribution.
The
The log-Pearson
log-Pearson III
III distribution
distribution can
can thenthen be
be computed
computed in in the
theconventional
conventionalmanner
mannerusing
using the
synthetic statistical
the synthetic properties.
statistical It is Itrecommended
properties. is recommended that that
the distribution be compared
the distribution with the
be compared
observed flows since
with the observed datasince
flows adjusted
data for conditional
adjusted probabilityprobability
for conditional may not follow
may a log-Pearson
not follow a III
distribution.
log-Pearson III distribution.
The procedures for the aforementioned discussions could be summarized as follows:
The procedures for the aforementioned discussions could be summarized as follows:
1. Obtain site information, the systematic station data, and historic information. This data
should
1. Obtain beinformation,
site examined forthe changes in watershed
systematic conditions,
station data, gage datum,
and historic flow regulation,
information. This
etc. It is in this initial step that missing data should be estimated if
data should be examined for changes in watershed conditions, gage datum, flow indicated by the
project.
regulation, etc. It is in this initial step that missing data should be estimated if
indicated by the project.
2. Order the flood data, determine the plotting position, and plot the data on selected
probability graph paper (usually log-probability). Examine the data trend to select the
standard distribution that best describes the population from which the sample is taken.
62
Ministry of Works and Transport
Drainage Design Manual Section 6
Use a mixed-population analysis if indicated by the data trend and the watershed
information.
3. Compute the sample statistics and the frequency curve for the selected distribution.
Plot the frequency curve with the station data to determine how well the flood data are
distributed according to the selected distribution.
4. Check for high and low outliers. Adjust for historic data, retain or eliminate outliers, and
recompute the frequency curve.
5. Adjust data for missing low flows and zero flows and recompute the frequency curve.
6. Check the resulting frequency curve for reliability.
63
Ministry of Works and Transport
Drainage Design Manual Section 7
SECTION 7
7.0 DESIGN AND USE OF DETENTION BASIN
7.1 General
The temporary storage or detention of excess storm water runoff as a means of controlling
the quantity and quality of storm water is a fundamental principle in storm water management
and a necessary element of a growing number of highway storm drainage systems. Previous
concepts that called for the rapid removal of storm water runoff from developed areas, usually
by channelization, are now being combined with methods for storing storm water runoff to
prevent overloading of existing downstream drainage systems and to control their quality.
The storage of storm water can reduce the frequency and extent of downstream flooding, soil
erosion, sedimentation, and water pollution. Detention facilities have also been used to reduce
the costs of large storm drainage systems by reducing the required size for downstream storm
drain conveyance systems.
Storm water quantity control facilities can be classified by function as either detention or retention
facilities. The primary function of detention is to store and gradually release or attenuate storm
water runoff by way of a control structure or other release mechanism. True retention facilities
provide for storage of storm water runoff, and release via evaporation and infiltration only.
Retention facilities which provide for slow release of storm water over an extended period of
several days or more are referred to as extended detention facilities. Typical detention and
retention hydrographs are shown in Fig. 7.1.
64
Ministry of Works and Transport
Drainage Design Manual Section 7
where they are shown to be beneficial by hydrologic, hydraulic, health, and cost analysis.
7.4 Storage Location and Size
7.4.1 Location
Storage can be classified by location as on-site, off-site, upstream, downstream, channel (or on-
stream) and off-stream. Based on function, storage facilities may be for single or multipurpose
use and temporary (detention) or permanent (retention). Site selection involves (in addition
to hydrologic, hydraulic, health and cost analysis) a number of selection points of which the
following are the important ones:
• The size, shape, and depth of a detention facility must provide sufficient volume to
satisfy the projects’ storage requirements. This is best determined by routing the inflow
hydrograph through the facility;
• The site must be accessible both for construction and maintenance; and,
• The geology should be suitable for weir construction and other elements thereof.
7.4.2 Size
Estimating the required volume of storage to accomplish the necessary peak reduction is an
important task since an accurate first estimate will reduce the number of trials involved in the
routing procedure. The following sections present methods for determining an initial estimate
of the storage required to provide a specific reduction in peak discharge. All of the methods
presented provide preliminary estimates only. It is recommended that the designer apply
several of the methods and a degree of judgment to determine the initial storage estimate.
7.5 Triangular Hydrograph Method
A preliminary estimate of the storage volume required for peak flow attenuation may be obtained
from a simplified design procedure that replaces the actual inflow and outflow hydrographs with
standard triangular shapes. This method should not be applied if the hydrographs can not be
approximated by a triangular shape. This would introduce additional errors of the preliminary
estimate of the required storage. The procedure is illustrated by Fig. 7-2. The required storage
volume may be estimated from the area above the outflow hydrograph and inside the inflow
hydrograph as defined by Equation 7-1.
where:
Vs = storage volume estimate, m3
Qi = peak inflow rate into the basin, m3 /s
Qo = peak outflow rate out of the basin, m3 /s
t i = duration of basin inflow, s
The duration of basin inflow should be derived from the estimated inflow hydrograph.
Maximum allowable discharge may be determined by the modified rational method for tributary
areas of less than 500 acres.
65
Ministry of Works and Transport
Drainage Design Manual Section 7
Example 7.1
Given: The post-developed hydrograph of Fig. Example 7.1 and a limiting outflow rate, from the
proposed detention facility, of 0.55 m3/s.
Solution
Solution:
From Example Fig. 7.1, the duration of basin inflow ( t i ) is read to be 1.43 hours (5148
3
seconds) and the inflow rate into the detention basin ( Qi ) is also read to be 0.88 m /s.
Due to a local ordinance, the peak flow rate out of the basin ( Qo ) is set to be = 0.55
m3/s. Using Equation 8-1, the initial storage volume is computed as:
Vs = 0.5 t i ( Qi - Qo )
66
Ministry of Works and Transport
Drainage Design Manual Section 7
Both the inflow I and outflow O are time varying functions, with I being the inflow
hydrograph and O being the outflow hydrograph. While the inflow hydrograph is
known, the objective of the reservoir routing is to compute the outflow hydrograph. The
storage equation can be rewritten as:
If the subscripts 1 and 2 are used to indicate time t and t t , respectively, the
average inflow and average outflow can be used to expand Eq. 7.3:
1 1
( I 1 I 2 ) t (O1 O2 ) t S 2 S1 Eqn. 7.4
2 2
Eqn. 7.4 can be rearranged such that the known are placed on one side and the
unknowns on the other side:
1 1
( I1 I 2 ) t ( S1 O1 t ) S 2 12 O2 t Eqn. 7.5
2 2
In order to find the outflow hydrograph, it is only necessary to compute the outflow-
storage relationship, which is easily obtained for site data.
A solution for Eqn. 7.5 can be obtained by deriving the storage-indication curve, which
1
is the relationship between O and ( S Ot ) . Given the storage discharge curve,
2
O vs. S , the following four-step procedure can be used to develop the storage-
indication curve:
1. Select a value of O ;
2. Determine the corresponding value of S from the storage-discharge curve;
1
3. Use the values of S and O to compute ( S Ot ) ; and
2
1
4. Plot O vs. ( S Ot ) .
2
67
Ministry of Works and Transport
Drainage Design Manual Section 7
These four steps are repeated for a sufficient number of values of O to define the storage-
indication curve.
The objective of the storage-indication method is to derive the outflow hydrograph. There are
five data requirement:
1. The storage-discharge relationship;
2. The storage-indication curve;
3. The inflow-hydrograph;
4. Initial values of the storage and outflow rate; and
5. The routing increment.
The following five-step procedure can be used to derive the outflow hydrograph, with the
storage-time relationship as a by-product:
1
Step 1. Determine the average inflow: ( I 1 I 2 )t ;
2
1
Step 2. Determine ( S1 O1 t ) ;
2
1
Step 3. Using Eqn. 7.5 and the values from steps 1 and 2, compute ( S 2 O2 t ) ;
2
Step 4. Using the value computed in step 3, as input, find O2 from the storage-
indication curve; and
These five steps are repeated for the next time increment using I 2 , O2 , and S 2 as the
new values of I 1 , O1 , S1 , respectively. The process is solved iteratively until the
outflow hydrograph is computed.
O2 C o I 2 C1 I1 C 2 O1 Eqn. 7.6
I C D
Co Eqn. 7.7
I DC
I C D
C1 Eqn. 7.8
I DC
I C D
C2 Eqn. 7.9
I DC
68
and
Ministry of Works and Transport
t
C c Eqn. 7.10
x
and
I C D
Co Eqn. 7.7
I DC
I C D
C1 Eqn. 7.8
I DC
I CManual
Drainage Design D Section 7
C2 Eqn. 7.9
I DC
and
t
C c Eqn. 7.10
x
and
qo
D Eqn. 7.11
S o cx
where:
t = time (s),
x = distance along the channel (m),
c = celerity (m/s),
qo = is discharge per unit channel width (m2/s), and
S o = slope
Celerityc is obtained from a rating curve as V with velocity V based on the peak
discharge. The unit discharge, q o , is based on a reference discharge, typically the
peak flow. In this method, C o C1 C 2 = 1. The following guidelines produce the
best results when using the Muskingum-Cunge method.
The Muskingum-Cunge method is appropriate for use on most stream channels. It accounts
for diffusion of the flood wave. However, if there are significant backwater effects caused by
upstream or downstream controls, then this method should not be used (actually, only the
full dynamic equation can account for backwater effects). The main advantage of using the
Muskingum-Cunge over the Muskingum routing method is that the Muskingum-Cunge method
is physically based and requires minimal streamflow data. The parameters are based on the
rating curve and slope. Therefore, this method is ideal for use in un-gauged streams.
Example 7-2
Consider a river shown in Example Figure 7.2. It has a 4.8 km reach between A and B with
an inflow hydrograph (peak discharge of 84 m3/s) given in Example Table 7-2. The average
discharge for this hydrograph is 34 m3/s. Using the trapezoidal cross section given in Example
Figure 7.2 and a flow depth of 2 m, the average velocity is computed from the continuity
equation and travel time = length/velocity. The cross-sectional area corresponding to Q =
34 m3/s is 24 m2, which yields a velocity of 1.4 m/s (= 34 m3/s/24 m2). The travel time at this
velocity is 4800 m/[1.4 m/s (3600 s/h)] = 0.95 hours.
69
Ministry of Works and Transport
Drainage Design Manual Section 7
Assuming = 5/3 and t = 1,800 s, the inflow hydrograph can be routed using the
Equation 7.7 through Equation 7.11, and using the following x and t values. D and
the C values shall then be:
D = 0.718
C= 0.875
Co = 0.2287
C1 = 0.4462
C2 = 0.3251
The outflow hydrograph is computed from Equation 7-6 and is given in Example Table
3
7.2-1. The peak flow attenuates to 79 m /s, and translates to hour 4.5.
70
Ministry of Works and Transport
Drainage
DrainageDesign
DesignManual
Manual Section
Section 7 7
Example Table 7.2-1: Inflow and Outflow Hydrograph for Muskingum-Cunge Routing
Method
71
Ministry of Works and Transport
7.8
Ministry of Works and Transport
Drainage Design Manual Section 8
SECTION 8
8.0 PAVEMENT DRAINAGE
8.1 General
Effective drainage of highway pavements is essential to maintain the levels of service and
to traffic safety of roads. Water on the pavement can interrupt traffic, reduce skid resistance,
increase potential for hydroplaning, limit visibility due to splash and spray, and cause difficulty
in steering a vehicle when the front wheels encounter puddles. The substructures of a roadway
are also highly influenced by intrusion of water.
Pavement drainage requires consideration of surface drainage, gutter flow, and inlet capacity.
The design of these elements is dependent on storm frequency and the allowable spread of
storm water on the pavement surface. This chapter presents design guidance for the design
of these elements.
8.2 Design Frequency and Spread
Two of the more significant variables considered in the design of highway pavement drainage
are the frequency of the design runoff event and the allowable spread of water on the
pavement. A related consideration is the use of an event of lesser frequency to check the
drainage design.
Spread and design frequency are not independent. The implications of the use of a criteria for
spread of one-half of a traffic lane is considerably different for one design frequency than for a
lesser frequency. It also has different implications for a low-traffic, low-speed highway than for
a higher classification highway. These subjects are central to the issue of highway pavement
drainage and important to highway safety.
8.2.1 Selection of Design Frequency and Design Spread
The objective of highway storm drainage design is to provide for safe passage of vehicles
during the design storm event. The design of a drainage system for a kerbed highway pavement
section is to collect runoff in the gutter and convey it to pavement inlets in a manner that
provides reasonable safety for traffic and pedestrians at a reasonable cost. As spread from the
kerb increases, the risks of traffic accidents and delays, and the nuisance and possible hazard
to pedestrian traffic increase.
The process of selecting the recurrence interval and spread for design involves decisions
regarding acceptable risks of accidents and traffic delays and acceptable costs for the drainage
system. Risks associated with water on traffic lanes are greater with high traffic volumes, high
speeds, and higher highway classifications than with lower volumes, speeds, and highway
classifications. A summary of the major considerations that enter into the selection of design
frequency and design spread follows.
1. The classification of the highway is a good starting point in the selection process since it
defines the public’s expectations regarding water on the pavement surface. Ponding on
traffic lanes of high- speed, high-volume highways is contrary to the public’s expectations
and thus the risks of accidents and the costs of traffic delays are high.
2. Design speed is important to the selection of design criteria. At speeds greater than 70
km/hr, it has been shown that water on the pavement can cause hydroplaning.
3. Projected traffic volumes are an indicator of the economic importance of keeping the
highway open to traffic. The costs of traffic delays and accidents increase with increasing
traffic volumes.
4. The intensity of rainfall events may significantly affect the selection of design frequency
and spread. Risks associated with the spread of water on pavements may be less in
arid areas subject to high intensity thunderstorm events than in areas accustomed to
frequent but less intense events.
5. Capital costs are neither the least nor last consideration. Cost considerations make it
72
Ministry of Works and Transport
Drainage Design Manual Section 8
DESIGN DESIGN
ROAD CLASSIFICATION
FREQUENCY SPREAD*
High Volume or < 70 km/hr 10-yrs Shoulder + 1 m
Divided or Bi- > 70 km/hr 10-yrs Shoulder
Directional Sag Point 50-yrs Shoulder + 1 m
Collector < 70 km/hr 10-yrs 1/2 Driving Lane
> 70 km/hr 10-yrs Shoulder
Sag Point 10-yrs 1/2 Driving Lane
Local Streets Low ADT** 5-yrs 1/2 Driving Lane
High ADT 10-yrs 1/2 Driving Lane
Sag Point 10-yrs 1/2 Driving Lane
*A gutter flowing at capacity should not flood more than 1.5 meters into carriageway
73
Ministry of Works and Transport
Drainage Design Manual Section 8
1. A minimum longitudinal gradient is more important for a kerbed pavement than for an
un-kerbed pavement since the water is constrained by the kerb. However, flat gradients
on un-kerbed pavements can lead to a spread problem if vegetation is allowed to build
up along the pavement edge.
2. Desirable gutter grades should not be less than 0.5 percent for kerbed pavements with
74
Ministry of Works and Transport
Drainage Design Manual Section 8
an absolute minimum of 0.3 percent. Minimum grades can be maintained in very flat
terrain by use of a rolling profile, or by warping the cross slope to achieve rolling gutter
profiles.
3. To provide adequate drainage in sag vertical curves, a minimum slope of 0.3 percent
should be maintained within 15 meters of the low point of the curve. This is accomplished
where the length of the curve in meters divided by the algebraic difference in grades in
percent ( ) is less than or equal to 50. This is represented as:
L
K Eqn. 8.1
G2 G1
where:
75
Ministry of Works and Transport
Drainage Design Manual Section 8
Gutters formed in combination with kerbs are available in 0.3 through 1.0 meter widths. Gutter
cross slopes may be the same as that of the pavement or may be designed with a steeper
cross slope, usually 80 mm per meter steeper than the shoulder or parking lane (if used).
AASHTO geometric guidelines state that an 8 percent slope is a common maximum cross
slope.
A kerb and gutter combination forms a triangular channel that can convey runoff equal to or
less than the design flow without interruption of the traffic. When a design flow occurs, there is
a spread or widening of the conveyed water surface. The water spreads to include not only the
gutter width, but also parking lanes or shoulders, and portions of the traveled surface. Spread
is what concerns the hydraulic engineer in kerb and gutter flow. The distance of the spread, T,
is measured perpendicular to the kerb face to the extent of the water on the roadway and is
shown in Figure 8-1. Limiting this width becomes a very important design criterion.
Where practical, runoff from cut slopes and other areas draining toward the roadway should
be intercepted before it reaches the highway. By doing so, the deposition of sediment and
other debris on the roadway as well as the amount of water which must be carried in the
gutter section will be minimized. Where kerbs are not needed for traffic control, shallow ditch
sections at the edge of the roadway pavement or shoulder offer advantages over kerbed
76
Ministry of Works and Transport
Drainage Design Manual Section 8
sections by providing less of a hazard to traffic than a near-vertical kerb and by providing
hydraulic capacity that is not dependent on spread on the pavement. These ditch sections are
particularly appropriate where kerbs have historically been used to prevent water from eroding
fill slopes.
Kerb Flow Time - The velocity of water flowing in kerb gutter depends on: the roughness of the
kerb gutter and road surface; cross-fall of the road; the longitudinal profile of the gutter; the
magnitude of flow in the gutter.
Flow along the gutter varies with the length of the kerb as more flow joins the gutter and this
makes estimation of the flow time difficult. The flow time, however, could be approximated by
equation 8.2.
L
tg Eqn. 8.2
40 S
where:
t g kerb gutter flow time (minute)
L = length of kerb gutter (meters)
S= longitudinal grade of the kerb gutter (percent)
Equation 8.3 neglects the resistance of the kerb face since this resistance is negligible.
77
Ministry of Works and Transport
Drainage Design Manual Section 8
Table 8-3. Manning's Roughness (n) for Street and Pavement Gutters
(Source: USDOT, FHWA, HDS-3)
Spread on the pavement and flow depth at the kerb are often used as criteria for spacing
pavement drainage inlets. Design Chart 1 (Appendix 8.1) is a nomogram for solving Equation
8.3. The chart can be used for either criterion with the relationship:
d TS x Eqn. 8.4
where:
d = depth of flow , m
others as defined earlier
Chart 1 (Appendix 8.1) can be used for direct solution of gutter flow where the Manning
n value is 0.018. For other values of n, divide the value of Qn by n . Instructions for
use and an example problem solution are provided on the chart.
S L 0.010 m/m
S x 0.020 m/m
n = 0.017
Find: (1) Spread at a flow of 0.05 m3/s
(2) Gutter flow at a spread of 2.5 m
Solution (1):
T Qn / K m S x
1.67
SL
0.5
0.375
T = [(0.0008)/{(0.377)(0.020)1.77(0.010)0.5}]0.375
T = 2.7 m
Solution (2):
Step 1. Using Equation 8.3 or Chart 1 with T = 2.5 m and the information given above,
78 determine Qn .
Ministry of Works
Q and
KTransport
S
1.67
S
0.5
T 2.67
n m x L
T = [(0.0008)/{(0.377)(0.020)1.77(0.010)0.5}]0.375
T = 2.7 m
Drainage Design Manual Section 8
Solution (2):
Step 1. Using Equation 8.3 or Chart 1 with T = 2.5 m and the information given above,
determine Qn .
1.67 0.5
Qn K m S x S L T 2.67
Qn = (0.377) (0.020)1.77 (0.010)0.5 (2.5)2.77
Qn = 0.00074 m3/s
To examine the effects of cross slope on gutter capacity, Equation 8.3 can be
transformed as follows into a relationship between S x and Q as follows:
Let
n
K1 0.5
Eqn. 8.5
K m S L T 2.67
then
1.67
Sx K1Q and
1.67
S x1 K 1Q1 Q1
Eqn. 8.6
S x2 K 1Q1 Q2
79
Ministry of Works and Transport
Drainage Design Manual Section 8
Little latitude is generally available to vary longitudinal slope in order to increase gutter capacity,
but slope changes which change gutter capacity are frequent. Figure 8.2 shows that a change
from = 0.04 to 0.02 will reduce gutter capacity to 71 percent of the capacity at = 0.04.
8.4.3 Bridge Decks
Bridge deck drainage is similar to that of kerbed roadway sections. Effective bridge deck
drainage is important for the following reasons:
Deck structural and reinforcing steel is susceptible to corrosion from deicing salts;
Hydroplaning often occurs at shallower depths on bridges due to the reduced surface texture
of concrete bridge decks.
Bridge deck drainage is often less efficient than roadway sections because cross slopes are
flatter, parapets collect large amounts of debris, and drainage inlets or typical bridge scuppers
are less
Hydraulically efficient and more easily clogged by debris. Because of the difficulties in
providing for and maintaining adequate deck drainage systems, gutter flow from roadways
should be intercepted before it reaches a bridge. For similar reasons, zero gradients and sag
vertical curves should be avoided on bridges. Additionally, runoff from bridge decks should be
collected immediately after it flows onto the subsequent roadway section where larger grates
and inlet structures can be used.
Figure 8.2. Relative Effects of Spread, Cross Slope, and Longitudinal Slope on Gutter
Capacity
8.5 Inlets
Storm drain inlets are used to collect runoff and discharge it to an underground storm drainage
system. Inlets are typically located in gutter sections, paved medians, and roadside and median
ditches. Inlets used for the drainage of highway surfaces can be divided into the following four
classes:
• grate inlets;
80
Ministry of Works and Transport
Drainage Design Manual Section 8
• slotted inlets;
• kerb-opening inlets; and,
• combination inlets.
8.5.1 Grate inlets
As a class, Grate inlets perform satisfactorily over a wide range of gutter grades. Grate inlets
generally lose capacity with increase in grade, but to a lesser degree than kerb opening inlets.
The principal advantage of grate inlets is that they are installed along the roadway where the
water is flowing. Their principal disadvantage is that they may be clogged by floating trash
or debris. For safety reasons, reference should be given to grate inlets where out-of-control
vehicles might be involved. Additionally, where bicycle traffic occurs, grates should be bicycle
safe.
8.5.2 Slotted Inlets
Slotted inlets can be used in areas where it is desirable to intercept sheet flow before it crosses
onto a section of roadway. Their principal advantage is their ability to intercept flow over a wide
section. However, slotted inlets are very susceptible to clogging from sediments and debris,
and are not recommended for use in environments where significant sediment or debris loads
may be present. Slotted inlets on a longitudinal grade do have the same hydraulic capacity as
kerb openings when debris is not a factor.
8.5.3 Kerb-opening
Kerb opening inlets are most effective on flatter slopes, in sags, and with flows which typically
carry significant amounts of floating debris. The interception capacity of kerb-opening inlets
decreases as the gutter grade steepens. Consequently, the use of kerb-opening inlets is
recommended in sags and on grades less than 3 percent. Of course, they are bicycle safe as
well.
8.5.4 Combination Inlets
Combination inlets provide the advantages of both kerb opening and grate inlets. This
combination results in a high capacity inlet which offers the advantages of both grate and
kerb-opening inlets. When the kerb opening precedes the grate in a “Sweeper” configuration,
the kerb-opening inlet acts as a trash interceptor during the initial phases of a storm. Used in a
sag configuration, the sweeper inlet can have a kerb opening on both sides of the grate.
8.6 Drainage Inlet Design
The hydraulic capacity of a storm drain inlet depends upon its geometry as well as the
characteristics of the gutter flow. Inlet capacity governs both the rate of water removal from
the gutter and the amount of water that can enter the storm drainage system. Inadequate inlet
capacity or poor inlet location may cause flooding on the roadway resulting in a hazard to the
traveling public. As they are highly efficient and their interference with carriageways is rather
limited, the design of kerb opening inlets is further discussed
8.6.1 Kerb-Opening Inlets
Kerb-opening inlets are effective in the drainage of highway pavements were flow depth at
the kerb is sufficient for the inlet to perform efficiently. Kerb openings are less susceptible to
clogging and offer little interference to traffic operation. They are viable alternative to grates
on flatter grades where grates would be in traffic lanes or would be hazardous for pedestrians
or bicyclists. Kerb opening heights vary in dimension. However, a typical maximum height
is approximately 100 to 150 mm. The length of the kerb-opening inlet required for total
interception of gutter flow on a pavement section with a uniform cross slope is expressed by
Equation 8.9:
The efficiency of kerb-opening inlets shorter than the length required for total interception is
expressed by Equation 8.10
81
Ministry of Works and Transport
Drainage Design Manual Section 8
The efficiency of kerb-opening inlets shorter than the length required for total
interception is expressed by Equation 8.10
1.8
L
E 1 1 Eqn. 8.10
LT
where:
L = kerb-opening length, m
Chart 2 (Appendix 8.2) is a nomogram for the solution of Equation 8.9, and Chart 3
(Appendix 8.3) provides a solution of Equation 8.10.
The length of inlet required for total interception by depressed kerb-opening inlets or
kerb-openings in depressed gutter sections can be found by the use of an equivalent
cross slope, S e , in Equation 8.9 in place of S x . S e can be computed using Equation
8.11.
where:
SW' = cross slope of the gutter measured from the cross slope of the pavement, S x ,
m/m
S 'W a /1000W
S x = cross slope, m/m
a = gutter depression, mm
82
Ministry of Works and Transport
Drainage Design Manual Section 8
Without depression of the gutter section, the weir coefficient, CW , becomes 1.70 (3.0,
English system). The depth limitation for operation as a weir becomes d h.
Kerb-opening inlets operate as orifices at depths greater than approximately 1.4 times
the opening height. The interception capacity can be computed by Equation 8.14 and
Equation 8.15. These equations are applicable to depressed and undepressed kerb-
opening inlets. The depth at the inlet includes any gutter depression.
Qi Co hL 2 gd o
0.5
Eqn. 8.14
0.5
h
Qi C o Ag 2 g d i Eqn. 8.15
2
where:
C o = orifice coefficient (0.77)
d o = effective head on the center of the orifice throat, m
L = length of orifice opening, m
Ag
= clear area of opening, m 2
d i = depth at lip of kerb opening, m
h = height of kerb-opening orifice, m
h = TS x a1000
The height of the orifice in both Equation 8.14 and Equation 8.15 assumes a vertical orifice
opening.
The location and spacing of kerb inlets depend on the following factors:
• amount of runoff
• grade profile
• geometry of intersection
• width of flow limitation
• inlet capacity.
83
Ministry of Works and Transport
Drainage Design Manual Section 8
84
Ministry of Works and Transport
Drainage Design Manual Section 8
The start and out let of pipe subsurface drains should be indicated on the surface by means of
markers. These are necessary for the maintenance personnel.
Design of subsurface drains is associated with soil type and seepage flow rate. The
interrelationship, between the permeable filler material, the filter fabric and the subsurface
drain pipe selected is important in the design of an effective subsurface drain. Cost could
have a major bearing on the type of subsurface drain used. All possibilities should therefore
be investigated.
8.7.5 Materials
a) Filter Materials:- permeable filter materials for subsurface drains should consist of sand
and /or crushed stone plus gravel of suitable grading. Grading specifications may have
to be varied to suit availability of material.
b) Filter fabric:- Synthetic fiber filter fabrics should also be considered where there is a
definite engineering and cost advantage, but preference should be given to the use of
local natural materials.
c) Subsurface pipes:- Cost, ease of handling and ease of laying should be the main
considerations when specifying subsurface pipes, which may consist of perforated,
slotted or open jointed concrete, clay, pitch fiber or plastic pipes.
85
Ministry of Works and Transport
Drainage Design Manual Section 9
SECTION 9
9.0 DESIGN OF HYDRAULIC CULVERTS
9.1 General
This section considers the hydraulics of conventional culverts and the requirements for selecting
a culvert size for a given set of conditions. Guidelines are provided to enable the designer
to make use of standard design charts adopted from AASHTO-Model Drainage Manual, as
well as other relevant documents. However, the designer retains the right to deviate from the
standard on the basis of well-proven and applicable state-of-the-art knowledge on the subject
and with the approval of the concerned authority (MoWT).
9.1.1 Rural Road Drainage
A road is considered as a dyke which divides the countryside in two parts, and therefore
disturbs the water flow characteristics of the area, whether it be sheet overland flow or channel
flow in defined water courses. The importance of continuity in surface drainage is illustrated by
the fact that most road embankment failures are caused by water problems. Drainage design
will influence the road geometry on the higher standard road to a large extent. An efficient
drainage system is an essential contribution to the overall design of the road. A vital factor in
rural areas is to ensure continuity of flow from one side of the road to the other, whatever class
of road is involved.
The road, which functions as a barrier, will cause storm runoff to flow parallel to the road
embankment until a discharge point is reached, whether it be a relieving culvert or a culvert
at a low point.
Between two watersheds there is generally one low point in the road. The distance from a
watershed to this low point can be several kilometres, dependent on the nature of the terrain.
Provision should be made to discharge the runoff across the road at regular intervals to avoid
such a concentration of runoff at the low point and to maintain a balance of runoff. These
intervals depend upon the locality and type of road and could be in excess of 500m in flat semi
arid terrain.
There the situation arises that a road is aligned parallel to and close upstream or downstream
of an existing railway line, the siting and sizing of the road drainage structures may need
artificial adjustment to match that of the railway structures. The designer is encouraged to
liaise closely with the relevant authorities in all such cases.
To prevent the collection of water and ponding on the road surface, roads should be cambered
as follows:
86
Ministry of Works and Transport
Drainage Design Manual Section 9
drainage system must not, however, be incorporated at the expense of a satisfactory surface
drainage layout.
9.2 Culvert Type and Class
Hydraulic performance is one of several factors which influence the selection of type of culvert
for a particular location. However, the shape and type of culvert to be used should not be
determined by hydraulic performance alone. The economics and availability of different culvert
types in the various regions should also be considered. The guidelines in this manual indicate
the common types of culverts in use. Whenever the designer feels that other appropriate
culvert types are applicable to specific local conditions, he can use his professional experience
to select the appropriate type after getting the permission of the concerned authority.
9.2.1 Culvert Types
Different shapes of culverts and a description of their applicability is given in the form of a table
in appendix 9.1. Land use requirements can dictate a larger or different barrel geometry than
required for hydraulic consideration. Arch or oval shapes are used only if required by hydraulic
limitations, site characteristics, structural criteria, or environmental criteria.
Transport and purchase costs play a major role in selecting the culvert type for a particular
region. In evaluating the suitability of alternate materials, the selection process shall be based
on a comparison of the total cost of alternate materials over the design life of the structure that
is dependent upon the following:
• durability (service life);
• cost;
• availability;
• construction and maintenance ease;
• structural strength;
• traffic delays;
• abrasion and corrosion resistance; and,
• water tightness requirements;
Concrete is the preferred material for construction of culverts, if aggregate materials are available
locally. However, other materials may be more suitable for a particular location, hydraulic
roughness, bedding condition, etc. A pipe material other than concrete may be accepted as
an alternate if the substitution is supported by evidence that the hydraulic capacity, strength,
durability, abrasion, and corrosion resistance of the concrete pipe specified is equalled or
exceeded. In addition, any substitution must be analyzed in terms of cost and availability.
The advantages of corrugated metal pipe sections should be considered for small to medium
sized culverts and the corrugated metal multi-plated arch for larger culverts. Such culverts
usually require protection from corrosion. They shall be protected at the ends by headwalls. Use
of corrugated metal pipes with projecting ends is not permitted under any circumstances.
Prefabricated concrete pipe and portal units are encouraged, wherever they can be economically
and practically justified.
A newly developed plastic pipe with radial ribs may also be considered for the smaller range
of culvert sizes.
9.2.2 Culvert Loading
Culvert of whatever type will be subjected to loads. The primary loads which should be
considered are as follows: self mass, water mass, mass of backfill, traffic loads, temporary
handling and construction. These factors, individually or collectively, influence the class of
culvert to be installed.
9.3 Headwater– Depth Relationship
All culverts should be designed to carry the design frequency flood with a headwater depth that
does not materially increase the size of the flooded upstream area.
87
Ministry of Works and Transport
Drainage Design Manual Section 9
88
Ministry of Works and Transport
A weir is a flow control section where the upstream water surface elevation can be
predicted for a given flow rate. The relationship between flow and water surface
elevation can be determined by model tests of the weir geometry or by measuring
prototype discharges.
Drainage Design Manual Section 9
300 mm
c) Transition Zone
The transition zone is located between the unsubmerged and the submerged flow
conditions where theFigure flow is9.2 Submerged
poorly Flowzone
defined. This InletisControl
approximated by plotting the
unsubmerged
c) and submerged
Transition Zone flow equations and connecting them with a line
tangential to both curves. Appendix 9.2 shows this type of curve.
The transition zone is located Figure 9.2 Submerged
between Flow Inlet
the unsubmerged and Control
the submerged flow conditions
where
d) the flow is poorly
Nomographs defined.
applicable forThis
Inletzone is approximated by plotting the unsubmerged
Control
and submerged flow equations and connecting them with a line tangential to both curves.
The inlet control
Appendix 9.2 showsflowthis
versus
type headwater
of curve. curves, which are established using the above
c) Transition
procedure, are theZonebasis for constructing the inlet control design nomographs. Note that
d)
in the inletNomographs applicable
control nomographs, HwforisInlet Controlto the total upstream energy grade line
measured
The
The transition
including
inlet the zone
approach
control is located head. Inletthe
between
velocityheadwater
flow versus unsubmerged
control
curves, are and
nomographs
which thegiven
are submerged
established flow
in appendix
using the above
conditions where the flow is poorly defined. This
culverts, zone is approximated
corrugated by plotting the
9.3 to appendix
procedure, are the9.5,
basisforforconcrete pipe the
constructing inlet control designmetal culverts,Note
nomographs. andthatbox in the
unsubmerged
culverts, and submerged flow equations and connecting them with a line
respectively.
inlet control nomographs, Hw is measured to the total upstream energy grade line including
tangential to both curves. Appendix 9.2 shows this type of curve. 9.4
the approach velocity head. Inlet control nomographs are given in appendix 9.3 to appendix
Ministry 9.4.2
of Works Outlet
and Transport
Control
9.5,
d) forNomographs
concrete pipe culverts, corrugated
applicable metal culverts, and box culverts, respectively.
for Inlet Control
9.4.2 Outlet
Outlet Control
control has depths and velocity that are subcritical. The control of the flow is at
The downstream
the inlet control flow
end versus
of the headwater
culvert curves,
(thethat
outlet). which are established
The tailwater isusing the above
Outlet
procedure, control
are has
the depths
basis forand velocity
constructing theare
inletsubcritical.
control Thedepth
design control assumed flowtothat
of the Note
nomographs. isbeat the
critical
downstream depth near the culvert
end ofnomographs, outlet
the culvert (the or in the downstream channel, whichever is higher.
in
In the
a the inlet control
given culvert, theortype Hwoutlet).
of downstream
flow
The tailwater
isismeasured
dependent to on depth
the all
total is assumed
of upstream
the is
barrel
to be
energy
factors
critical depth
grade
suchlineas
near
including culvert outlet
the approach in the
velocity head.length, channel,
Inlet control whichever
nomographs higher.
are OutletIn
given ina given
appendix culvert,
barrel
the type roughness,
of flow is barrel
dependentarea, barrel barrel slope and so on. control flow
9.3 to appendix
is illustrated for concrete pipe culverts, corrugated metal culverts, and boxarea,
9.5, 9.3.
in Figure
on all of the barrel factors such as barrel roughness, barrel
barrel
culverts, length, barrel slope and so on. Outlet control flow is illustrated in Figure 9.3.
respectively.
Outlet control has depths and velocity that are subcritical. The control of the flow is at
the downstream end of the culvert (the outlet). The tailwater depth is assumed to be
critical depth near the culvert outlet or in the downstream channel, whichever is higher.
In a given culvert, the type of flow is dependent on all of the barrel factors such as
barrel roughness, barrel area, barrel length, barrel slope and so on. Outlet control flow
is illustrated in Figure 9.3.
9.5
Drainage Design Manual Section 9
Outlet controlled culvert flows are calculated with an energy (total head) equation. Occasionally
a backwater calculation through the culvert is required. The energy equations are expressed
below based on schematic diagram of Figure 9.3.
Ignoring the outlet velocity head, the energy equation between u/s and d/s ends of the
culvert:
Hw + SoL = Tw + H (9.1)
where: Hw : depth from the inlet invert to the energy grade line, m
So : slope of channel
L : length of channel
Tw : tailwater depth
H : head losses
where:
g = acceleration due to gravity, 9.8 m/s2
entrance loss
HE = KE (V2/2g) (9.5a)
where:
KE = entrance loss coefficient, see appendix 9.6.
90
Ministry of Works and Transport
Drainage Design Manual Section 9
friction Loss
HF = [(19.63n2L)/R1.33] [V2/2g) (9.5b)
where:
n = Manning’s roughness coefficient (see appendix 9.7)
L = length of the culvert barrel, m
R = hydraulic radius of the full culvert barrel = A/P, m
P = wetted perimeter of the barrel, m exit Loss
Ho = 1.0 [(V2/2g) - (Vd2/2g)] (9.5c)
where:
Vd = channel velocity downstream of the culvert, m/s (usually
neglected, resulting in equation (9.5d)).
Ho = HV = V2/2g (9.5d)
Barrel Losses
H = HE + Ho+HF
H = [1 + Ke + (19.63n2L/R1.33)] [V2/2g] (9.6)
The energy grade line represents the total energy at any point along the culvert barrel. Equating
the total energy at sections 1 and 2, upstream and downstream of the culvert barrel in Figure
9.3, the following relationship results:
HWo + ( Vu2/2g) = TW + (Vd2/2g) + HL (9.7)
where:
HWo = headwater depth above the outlet invert, m
Vu = approach velocity, m/s
TW = tailwater depth above the outlet invert, m
Vd = downstream velocity, m/s
HL = sum of all losses (equation 9.2)
The hydraulic grade line is the depth to which water would rise in vertical tubes connected to
the sides of the culvert barrel. In full flow, the energy grade line and the hydraulic grade line are
parallel lines separated by the velocity head except at the inlet and the outlet.
a) Nomographs applicable to outlet control
Nomographs (full flow) - The nomographs were developed assuming that the culvert barrel is
flowing full and:
• TW > D, Outlet Control (see figure 9.3) or;
• dc > D, Inlet Control (see figure 9.4);
• Vu is small and its velocity head can be considered a part of the available headwater
(HW) used to convey the flow through the culvert;
• Vd is small and its velocity head can be neglected; and,
• Equation 9.7 will appear in same form as equation 9.1. With rearrangement it
becomes:
91
Ministry of Works and Transport
Drainage Design Manual Section 9
92
Ministry of Works and Transport
backwater calculations are required. (See Figure 9.6 if TW < dc and Figure 9.7 if TW >
dc)
Minimum data are cross section of channel and the rating curve for channel.
Step 4 Summarize Data on Design Form (see appendix 9.9). Use data from Steps 1-3
Step 5 Select Design Alternative
Choose culvert material, shape, size, and entrance type
Step 6 Select Design Discharge Qd
a. Determine flood frequency from data
b. Determine Q from discharge-frequency plot (Step 2)
c. Divide Q by the number of barrels
Step 7 Determine Inlet Control Headwater Depth (HWi)
Use the inlet control nomograph (Charts in appendix 9.3 to appendix 9.5)
Locate the size or height on the scale
a. Locate the discharge
• for a circular shape use discharge; and,
• for a box shape use Q per metre of width.
b. Locate HW/D ratio using a straightedge
• extend a straight line from the culvert size through the flow rate;
• mark the first HW/D scale. Extend a horizontal line to the desired scale, read
HW/D, and note on Charts;
c. Calculate headwater depth (HW)
• multiply HW/D by D to obtain HW to energy gradeline;
• neglecting the approach velocity HWi = HW; and,
• including the approach velocity HWi = HW - approach velocity head.
Step 8 Determine Outlet Control Headwater Depth at Inlet (HWoi)
a. Calculate the tailwater depth (TW) using the design flow rate and normal depth
(single section) or using a water surface profile
b. Calculate critical depth (dc) using appropriate chart (appendix 9.10 to appendix
9.11)
• locate flow rate and read dc; and,
• dc cannot exceed D.
c. Calculate (dc + D)/2
d. Determine (ho)
• ho = the larger of TW or (dc + D/2).
e. Determine entrance loss coefficient (Ke) from appendix 9.6
f. Determine losses through the culvert barrel (H) using charts given in appendix
9.12 to 9.14
• use nomograph charts or equation 9.6 if outside range;
• locate appropriate KE scale; and,
• locate culvert length (L) or (L1);
- use (L) if Manning’s n matches the n value of the culvert and
- use (L1) to adjust for a different culvert n value
L1 = L(n1/n)2 ( 9.10)
94
Ministry of Works and Transport
Drainage Design Manual Section 9
where:
L 1 = adjusted culvert length, m
L = actual culvert length, m
n 1 = desired Manning n value
n = Manning n value on chart
• mark point on turning line
- use a straightedge and
- connect size with the length
• read (H)
- use a straightedge
- connect Q and turning point and
- read (H) on Head Loss scale
g. Calculate outlet control headwater (HW)
• use equation 9.11, if Vu and Vd are neglected;
HWoi = H + ho - SoL ( 9.11)
• use equation 9.2, 9.5c, 9.6 to include Vu and Vd;
• if HWoi is less than 1.2D and control is outlet control;
- the barrel may flow partly full
- the FHWA approximate method of using the greater tailwater or (dc+ D)/2 may not be
applicable
- backwater calculations should be used to check the result and
- if the headwater depth falls below 0.75D, the approximate method shall not be
used
Step 9 Determine Controlling Headwater (HWc)
• compare HWi and HWoi, use the higher;
• HWc = HWi, if HWi > HWoi;
- the culvert is in inlet control
• HWc = HWoi, if HWoi > HWi;
- the culvert is in outlet control.
Step 10 Compute Discharge over the Roadway (Qr)
a. Calculate depth above the roadway (HWr)
HWr = HWc - HWov
HWov = height of road above inlet invert
b. If HWr < 0, Qr = 0
If HWr > 0, determine Qr
Step 11 Compute Total Discharge (Qt)
Qt = Qd + Qr (9.12)
Step 12 Calculate Outlet Velocity (Vo) and Depth (dn)
If inlet control is the controlling headwater
a. Calculate flow depth at culvert exit
• use normal depth (dn)
• use water surface profile
b. Calculate flow area (A)
95
Ministry of Works and Transport
Drainage Design Manual Section 9
96
Ministry of Works and Transport
Drainage Design Manual Section 9
The rating curve for the channel calculated by normal depth yields:
3
Q (m /s) TW (m) V (m/s)
2.83 0.43 3.39
5.66 0.63 4.18
8.50 0.76 4.87
11.33 0.85 5.34
14.16 0.93 5.73
a. D = 1.83 m
b. Q/B = 11.33/2.13 = 5.32
c. HW/D = 1.27 for 45o bevel
d. HW i = (HW/D)D = (1.27)1.83 = 2.32 m (Neglect the approach
velocity)
3
a. TW = 0.85 m for Q50 = 11.33 m /s
b. dc = 1.43 m from charts in appendix 9.11
c. (dc + D)/2 = (1.43 + 1.83)/2 = 1.63 m
d. ho = the larger of TW or (dc + D/2)
ho = (dc + D)/2 = 1.63 m
e. KE = 0.2 from tables in appendix 9.6
f. Determine (H) - use chart in appendix 9.14
KE scale = 0.2;
culvert length (L) = 90 m;
n = 0.012 same as on chart;
2
area = 3.90 m ;
H = 0.85 m;
g. HW oi = H + ho - SoL = 0.85 + 1.63 - (0.05)90 = - 2.02 m
HW oi is less than 1.2D, but control is inlet control, outlet control
computations are for comparison only
Step 12 Calculate Outlet Velocity (Vo) and Depth (dn) Inlet Control
Step 12 Calculate Outlet Velocity (Vo) and Depth (dn) Inlet Control
Use Q100 for the upper limit, Steps 6 through 12 should be repeated
for each discharge used to plot the performance curve, figure 9.10.
Step 16 Documentation
99
Ministry of Works and Transport
Drainage Design Manual Section 9
100
9.18
Ministry
MinistryofofWorks
Worksand Transport
and Transport
Drainage Design Manual Section 9
101
Ministry of Works and Transport
Drainage Design Manual Section 9
102
Ministry of Works and Transport
Drainage Design Manual Section 9
103
Ministry of Works and Transport
Drainage Design Manual Section 9
Culverts should be laid to grades that produce a non-silting or a non-erosive velocity, ideally
between 1 and 3.5m/s. This is particularly important in the sandy, semi-arid regions which
experience sporadic high intensity cloudbursts.
Maximum permissible velocities in erodible ditches and corresponding roughness coefficients
are given in Table 9.1.
9.8 Culvert Alignment
Generally, a culvert should be aligned along the natural watercourse. However, the culvert
itself should be straight between the inlet and outlet. This may require some modification of
the natural conditions.
Where natural conditions call for skewed alignments, a reduced degree of skew angle should
be investigated in order to shorten the culvert, and reduce costs. The culvert skew shall not
exceed 45o as measured from a line perpendicular to the roadway centreline without the
approval of the concerned Authority. Sound judgement should be used in any associated
channel relocations as these could adversely influence the hydraulic performance of the
culvert. Unless downstream scour would present serious problems, the inlet of the culvert
should be placed in the natural watercourse.
104
Ministry of Works and Transport
Drainage Design Manual Section 9
105
Ministry of Works and Transport
Drainage Design Manual Section 9
Wingwalls are used to retain the roadway embankment to avoid a projecting culvert barrel.
They are also used where the side slopes of the channel are unstable, and where the culvert
is skewed to the normal channel flow.
Aprons are used to reduce scour from high headwater depths or from approach velocity in the
channel. They should extend at least 1.5 pipe diameters upstream, and should not protrude
above the normal streambed elevation. The apron slab may be omitted where the culvert is
founded on rock embankment.
b) Endwall structure
This is headwall without the wingwalls, and similar construction to the headwall/wingwall
structure should be considered.
c) Mitred structure
This is the endwall structure, but mitred to match the slope of the embankment. If this structure
is used it is normally constructed in cement-mortared stonework or gabion mattresses. Mitring
improves the hydraulics of flow at the entrance and is therefore preferred to the endwall
structure. Mitred ends are recommended on shallow fill slopes. The ends should be fixed at
least 3m from the shoulder break point, wherever the fill slope falls within the recovery area.
d) Projecting end
These are box or pipe culvert extensions beyond the embankment of the roadway. They have
low construction cost, eliminating headwalls and wingwalls. However, they are susceptible to
damage during roadway maintenance. Hydraulically it is the most unsound and some form
of scour protection may therefore be required at the outlet. They have poor inlet hydraulic
efficiency, and they may require anchoring of the inlet to strengthen the weak leading edge.
They are suggested for only low standard roads. Cutoff walls are recommended in all cases
where the culvert is not founded on rock.
9.13 Flare Angle of Wingwalls
Inlet and outlet wingwalls should be flared at an angle of 45 degrees to the culverts center
line on all pipe culverts and minor box culverts up to 1.2 m span. The wingwalls on major
structures should preferably be flared at an angle of 30 degrees as any increase in this flare
angle will only aggravate the potential scour at the outlet particularly for large culvert.
9.14 Effects of Scour
9.14.1 Effects on Culverts
Unchecked erosion is a prime cause of culvert failure. The greatest scour potential is at the
culvert outlet where high velocities may necessitate scour protection or energy dissipation.
Road embankments that are designed to be overtopped in a flood should also be protected
against scour, if this is deemed desirable.
9.14.2 Effects at Bridge Sites
The need for scour protection can be minimized by locating bridges on stable tangential
reaches of rivers and by placing foundations on non-erodible materials. However, such a
solution is not always practicable, economic or desirable from the road alignment standpoint.
In such cases the designer is reminded to check for local scour at bridge sites, which is caused
by macro-turbulence resulting from the concentration of energy. Potential scour around piers
and abutments should also be checked and allowed for if necessary. Where scour around the
abutments of major bridges is likely to be a serious problem, particularly where the bridge is
sited in a wide flood plain, consideration should be given to the allowance of guide banks or
spur dykes. The issue of scour at bridge sites and recommended measures of river training is
discussed in section 10 which treats the topic of hydraulic design of bridges.
Before finally fixing the level of the pier and abutment foundation footings, consideration should
be given to the possible shifting of the river channel during a flood.
106
Ministry of Works and Transport
Drainage Design Manual Section 9
107
Ministry of Works and Transport
Drainage Design Manual Section 10
SECTION 10
10.0 HYDRAULIC DESIGN ASPECTS OF BRIDGES
10.1 Introduction
Bridges are defined as:
• structures that transport traffic over waterways or other obstructions; and,
• part of a stream crossing system that includes the approach roadway over the flood plain,
relief openings, and the bridge structure;
The purpose of this section is to provide guidance on the hydraulic design of a stream crossing
system through appropriate policy, design, and technical criteria. In addition, this section
will provide non-hydraulic factors that influence design, including environmental concerns,
emergency access, and traffic service.
Proper hydraulic analysis and design is as vital as the structural design. Stream crossing
systems shall be designed for minimum cost, to the desired level of hydraulic performance up
to an acceptable risk level, and to mitigate impacts on stream environment.
10.2 Design Principles
Standards are a set of goals that establish a definite course of action or method of action
and that are selected to guide and determine present and future decisions. Principles that
are unique to bridge crossings are presented in this section. The hydraulic analysis should
consider various stream-crossing system designs to determine the most cost-effective proposal
consistent with design constraints.
These policies identify specific areas for which quantifiable criteria can be developed:
• The final design selection should consider the maximum backwater allowed (0.5m)
unless exceeding of this limit can be justified by special hydraulic conditions;
• The final design should not significantly alter the flow distribution in the flood plain;
• The “crest-vertical curve profile” shall be considered as the preferred highway crossing
profile when allowing for embankment overtopping;
• A specified clearance shall be established to allow for passage of debris; a vertical
clearance shall be established based on normally expected flows and to allow for the
passage of small boats where necessary;
• Degradation or aggradation of the river as well as contraction and local scour shall be
estimated as part of the final design; the design should either eliminate scour or provide
scour protection; and,
• Foundation level shall be positioned below the total scour depth whenever practical.
10.3 Design Criteria
There are a number of hydraulic as well as non-hydraulic factors affecting the design of bridges.
Hereunder, the different criteria are discussed for clarity of design procedure.
10.3.1 General Criteria
Design criteria are the tangible means for placing accepted policies into action and become
the basis for the selection of the final design configuration of the stream-crossing system. The
following are the general criteria related to the hydraulic analyses for the location and design
of bridges:
• Backwater will not significantly increase flood damage to property upstream of the
crossing;
• Velocities through the structure(s) will not either damage the highway facility or increase
damages to adjacent property;
• Maintain the existing flow distribution to the extent practicable;
108
Ministry of Works and Transport
Drainage Design Manual Section 10
• Pier spacing, orientation, and abutment are to be designed to minimize flow disruption
and potential scour; spill-through type abutments using side slopes are preferred over
deep abutments to minimize scour and backwater, see appendix 10.5;
• Select foundation design and/or scour countermeasures to avoid failure by scour;
• Freeboard at structure(s) designed to pass anticipated debris;
• Acceptable risks of damage or viable measures to counter the unpredictability of alluvial
streams;
• Minimal disruption of ecosystems and values unique to the flood plain and stream;
• Provide a level of traffic service compatible with that commonly expected for the
class of highway and compatible with projected traffic volumes; and,
• Design choices should support costs for construction, maintenance, and operation,
including probable repair and reconstruction and potential liability.
10.3.2 Specific Criteria
These criteria augment the general criteria. They provide specific, quantifiable values that
relate to local site conditions. Evaluation of various alternatives according to these criteria can
be accomplished by using the water surface profile computation.
a) Location of a Stream Crossing
Although many factors, including non-technical ones, are used to determine the final location
of a stream-crossing system, the hydraulics of the proposed location must have a high priority.
Hydraulic considerations in selecting the location include flood plain width and roughness,
flow distribution and direction, stream type (braided, straight, or meandering), stream regime
(aggrading, degrading, or equilibrium), and stream controls. The hydraulics of a proposed
location also affect environmental considerations such as aquatic life, wetlands, sedimentation,
and stream stability. Finally, the hydraulics of a particular site determine whether or not
certain national objectives such as wise use of flood plains, reduction of flooding losses, and
preservative of wetlands can be met.
b) Inundation
Inundation of the carriageway dictates the level of traffic services provided by the facility. The
carriageway overtopping flood level identifies the limit of serviceability.
c) Risk Evaluation
The selection of hydraulic design criteria for determining the waterway opening, road grade,
scour potential, riprap, and other features should consider the potential impacts to interruptions
to traffic, adjacent property, the environment, and the infrastructure of the highway.
The evaluation of the consequence of risk associated with the probability of flooding attributed
to a stream-crossing system is a tool by which site specific design criteria can be developed.
This evaluation considers capital cost, traffic service, environmental and property impacts, and
hazards to human life.
The evaluation of risk is a two-stage process. The initial step, identified as risk assessment, is
more qualitative than a risk analysis and serves to identify threshold values that must be met
by the hydraulic design.
In many cases where the risks are low and/or threshold design values can be met, it is
unnecessary to pursue a detailed economic analysis. In those cases where the risks are high
and/or threshold values cannot be met, a Least Total Expected Cost (LTEC) analysis shall be
considered.
The results of a least-cost analysis can be presented in a graph of total cost as a function of
the overtopping discharge. The total cost consists of a combination of capital costs and flood
damages (or risk costs). Risk costs decrease with increases in the overtopping discharge
while capital costs simultaneously increase. The overtopping discharge for each alternative
is determined from a hydraulic analysis of a specific combination of embankment height and
bridge-opening length. The resulting least-cost alternative provides a tradeoff comparison.
109
Ministry of Works and Transport
Drainage Design Manual Section 10
The alternatives considered in the least-cost analysis do not require the specification of a
particular design flood. This information is part of the output of the least-cost analysis. In other
words, the least-cost alternative has a specific risk of overtopping that is unknown before the
least-cost alternative has been determined. Therefore, design flood frequencies are used only
to establish the initial alternative.
Thereafter, specific flood-frequency criteria shall be considered only as constraints on the final
design selection. Deviation from the least-cost alternative may be necessary to satisfy these
constraints and the trade-off cost for doing so can be obtained from the least-cost analysis.
Risk based analysis does not recognize some of the intangible factors that influence a design.
The minimum design that results from this type of analysis may be too low to satisfy the site
condition.
d) Design Floods
Design floods for such purposes as the evaluation of backwater, clearance, and overtopping
shall be established predicated on risk based assessment of local site conditions. They should
reflect consideration of traffic service, environmental impact, property damage, hazard to
human life, and flood plain management criteria.
e) Backwater
Backwater and/or increases over existing condition up to 0.5 m during the passage of the 100-
year flood, if practicable.
The expression for backwater is formulated by applying the principle of conservation of energy
between the point of maximum backwater upstream from the bridge, and a point downstream
from the bridge at which normal stage has been reestablished. The expression is reasonably
valid if the channel in the vicinity of the bridge is essentially straight, the cross sectional area
of the stream is fairly uniform, the gradient of the bottom is approximately constant between
the upstream and downstream section, the flow is free to contract and expand, there is no
appreciable scour of the bed in the constriction and the flow is in the subcritical range.
f) Clearance
A minimum clearance conforming to the requirements of the Bridge Design manual (usually
1.5 meters) shall be provided between the design approach water surface elevation and the
low chord of the bridge for the final design alternative to allow for passage of debris.
g) Scour
Design for bridge foundation scour should be made considering the magnitude of flood,
through the 1% event (100 years return period), which generates the maximum scour depth.
The designer should use a safety factor of three. The resulting design should then be checked
using a superflood that is 1.7 times the magnitude of the 1% event.
The extreme hazard posed by bridges subject to bridge scour failures dictates a different
philosophy in selecting suitable flood magnitudes to use in the scour analysis.
With bridge flood hazards other than scour, such as those caused by roadway overtopping
or property damage from inundation, a prudent and reasonable practice is to select first a
design flood to determine a trial bridge opening geometry. This geometry is selected either
subjectively or objectively based on the initial cost of the bridge along with the potential future
costs for flood hazards. Following the selection of this trial bridge geometry, the base flood
(100 years return period) is used to evaluate the selected opening. This two step evaluation
process is used to ensure the selected bridge opening based on the design flood implies no
unexpected increase in any existing flood hazards other than those from scour or aggradation.
Not only is it necessary to consider bridge scour or aggradation from the base flood, but also
from an even larger flood termed herein as the “superflood”.
Scour prediction technology is steadily developing, but lacks at this time, the reliability
associated with other facets of hydraulic engineering. Several formulae for predicting scour
110
Ministry of Works and Transport
Drainage Design Manual Section 10
depths are currently available and others will certainly be developed in the future. The designer
should strive to be acquainted with the “state of practice’ at the time of a given analysis and is
encouraged to be conservative in the resulting scour predictions.
With potential bridge scour hazards, a different flood selection and analysis philosophy is
considered reasonable and prudent. The foregoing trial bridge opening which was selected
by considering initial costs and future flood hazard costs shall be evaluated for two possible
scour conditions with the worse case dictating the foundation design and possibly a change in
the selected trial bridge opening.
First, evaluate the proposed bridge and road geometry for scour using the base flood, incipient
overtopping flood, overtopping flood corresponding to the base flood, or the relief opening
flood whichever provides the greatest flood discharge through the bridge opening. Once the
expected scour geometry has been assessed, the geotechnical engineer would design the
foundation.
The foundation design would use the conventional foundation safety factors and eliminate
consideration of any stream bed and bank material displaced by scour for foundation
support.
Second, impose a “superflood” on the proposed bridge and road geometry. This event must
be greater than the base flood and shall be used to evaluate the proposed bridge opening to
ensure that the resulting potential scour will produce no unexpected scour hazards.
The “superflood” is defined as the 500-year flood or a designated ratio (e.g. 1.7) times the
100-year flood. Similar to the base flood to evaluate the selected bridge opening, use either
the “superflood’, or the relief opening flood, whichever imposes the greatest flood discharge
on the selected bridge opening. The foundation design based on the base flood would then
be reviewed by the geotechnical engineer using an appropriate safety factor and again, taking
into account any stream bed and bank material displaced by scour from the “superflood”.
h) Preventive /Protection Measures Against Scour
Based on an assessment of potential scour provided by the Hydraulic Engineer, the structural
designers can incorporate design features that will prevent or mitigate scour damage at piers.
In general, circular piers or elongated piers with circular noses and an alignment parallel to
the flow direction are a possible alternative. Spread footings shall be used only where the
stream bed is extremely stable below the footing and where the spread footing is founded at
a depth that is below the maximum scour computed in the scour subsection. Drilled shafts or
drilled piers may be possible where pilings cannot be driven. Drop structures or grade-control
structures can provide protection against general streambed degradation in or downstream of
the bridge opening.
Rock riprap is often used, where stone of sufficient size is available, to armor abutment fill
slopes and the area around the base of piers.
Whenever possible, clearing of vegetation upstream and downstream of the toe of the
embankment slope shall be avoided. Embankment overtopping may be incorporated into the
design but shall be located well away from the bridge abutments and superstructure. Spur
dikes are recommended to align the approach flow with the bridge opening and to prevent
scour around the abutments. They are usually elliptical shaped with a major to minor axis ratio
of 2.5 to 1. This issue is discussed in detail under river training and stabilization in subsection
10.10.
i) Deck Drainage
Improperly drained bridge decks can cause numerous problems including hydroplaning. Bridge
decks should drain over the side. Where curb and gutter is used deck drainage is carried to
the ends, the bridge decks shall be watertight, and drains at the end of the bridge should have
sufficient inlet capacity to carry all bridge drainage.
111
Ministry of Works and Transport
Drainage Design Manual Section 10
j) Environmental Consideration
Environmental criteria must be met in the design of stream-crossing systems. Such
considerations might require the expertise of an environmentalist on the design team. Water
quality considerations should also be included in the design process insofar as the stream-
crossing system affects the water quality relative to beneficial uses. As a practical matter
with bridges, the hydraulic design criteria related to scour, degradation, aggradation, flow
velocities, and lateral distribution of flow, for example, are important criteria for evaluation of
environmental impacts as well as the safety of the stream-crossing structures.
All borrow areas existing within the flood plain shall be chosen so as to minimize the potential
for scour and adverse environmental effects within the limits of the bridge and its approaches
on the flood plain.
k) Construction Maintenance Aspects
Construction plans shall be reviewed jointly by the Contractor and the Hydraulic Engineer to
note any changes in the stream from the conditions used in the design. Temporary structures
and crossings used during construction shall be designed for a specified risk of failure due to
flooding during the construction period. The impacts on normal water levels, fish passage, and
normal flow distribution must be considered.
The stream-crossing design should incorporate measures which reduce maintenance costs
whenever possible. These measures include spur dikes, retards, guide dikes, jetties, riprap
protection of abutments and embankments, embankment overflow at lower elevations than
the bridge deck, and alignment of piers with the flow.
10.4 Investigation and Design Procedure
The investigation of bridge sites and hydraulic design of bridges involve a number of steps
which must be properly formulated to develop a systematic procedure. The following sections
discuss the relevant aspects and steps that are necessary in the data collection and hydraulic
design of bridges .
10.4.1 Physical Survey
The purpose of surveys is to gather all necessary site information. This should include such
information as topography and other physical features, land use and culture, flood data, basin
characteristics, precipitation data, historical high-water marks, existing structures, channel
characteristics, and environmental data. A site plan shall be developed on which much of the
survey data can be shown.
The designer of a stream crossing system requires a comprehensive engineering approach
that includes formulation of alternatives, data collection, selection of the most cost effective
alternative according to established criteria, and documentation of the final design. Water
surface profiles are computed for a variety of technical uses including:
• flood hazard mitigation investigations;
• drainage crossing analysis; and,
• longitudinal encroachments.
The completed profile can affect the highway bridge design and is the mechanism for
determining the effect of a bridge opening on upstream water levels.
10.4.2 Design Procedure Outline
The following design procedure outline shall be used. Although the scope of the project and
individual site characteristics make each design a unique one, the following procedure shall
be applied.
112
Ministry of Works and Transport
Drainage Design Manual Section 10
I. Data Collection
A. Survey
1. Topography
2. Geology
3. High-water marks
4. History of debris accumulation and scour
5. Review of hydraulic performance of existing structures
6. Maps, aerial photographs
7. Rainfall and stream gage records
8. Field reconnaissance
B. Other Relevant Information
1. From Concerned Ministries
2. River basin studies
3. Hydraulic performance of existing bridges
C. Influences on Hydraulic Performance of Site
1. Other streams, reservoirs, water intakes
2. Structures upstream or downstream
3. Natural features of stream and flood plain
4. Channel modifications upstream or downstream
5. Flood plain encroachments
6. Sediment types and bed forms
D. Environmental Impact
1. Existing bed or bank instability
2. Flood plain land use and flow distribution
3. Environmentally sensitive areas (fisheries, wetlands, etc.)
E. Site-specific Design Criteria
1. Preliminary risk assessment
2. Application of agency criteria
II. Hydrologic Analysis
A. Catchments area morphology
1. Drainage area (attach map)
2. Catchment area and stream slope
3. Channel geometry
B. Hydrologic computations
1. Discharge for historical flood that complements the high water marks used for
calibration
2. Discharges for specified frequencies
III. Hydraulic Analysis
A. Computer model calibration and verification
B. Hydraulic performance for existing conditions
C. Hydraulic performance of proposed designs
IV. Selection of Final Design
113
Ministry of Works and Transport
Drainage Design Manual Section 10
114
Ministry of Works and Transport
Drainage Design Manual Section 10
channel hydraulic conditions (up to and including, for example, water surface profile analysis)
and basic sediment transport analyses such as evaluation of catchment area sediment yield,
incipient motion analysis and scour calculations. This analysis can be considered adequate
for many locations if the problems are resolved and the relationships between different factors
affecting stability are adequately explained. If not, a more complex quantitative analysis based
on detailed mathematical modeling and/or physical hydraulic models shall be considered. This
multilevel approach is presented in HEC-20.
Less hazardous perhaps are problems associated with aggradation. Where freeboard is
limited, problems associated with increased flood hazards to upstream property or to the
traveling public due to more frequent overtopping may occur. Where aggradation is expected,
it may be necessary to evaluate these consequences. In addition, aggradation in a stream
reach may serve to moderate potential scour depths. Aggradation is sometimes referred to as
negative scour.
10.5.1 Scour Types
Present technology dictates that bridge scour be evaluated as interrelated components:
• long term profile changes (aggradation/degradation);
• plan form change (lateral channel movement);
• contraction scour/deposition; and,
• local scour.
Long-term profile changes can result from streambed profile changes that occur from
aggradation and/or degradation.
• Aggradation is the deposition of bedload due to a decrease in the energy gradient; and,
• Degradation is the scouring of bed material due to increased stream sediment transport
capacity that results from an increase in the energy gradient.
Forms of degradation and aggradation shall be considered as imposing a permanent future
change for the streambed elevation at a bridge site whenever they can be identified.
10.5.2 Plan Form Changes
The form and shape of the stream path created by its erosion and deposition characteristics
comprise its morphology. A stream can be braided, straight, or meandering, or it can be in the
process of changing from one form to another because of natural or manmade influences. A
historical study of the stream morphology at a proposed stream-crossing site is mandatory.
This study should also include an assessment of any long-term trends in aggradation or
degradation. Braided streams and alluvial fans should especially be avoided for stream-
crossing sites whenever possible.
Plan form changes are morphological changes such as meander migration or bank widening.
The lateral movement of meanders can threaten bridge approaches as well as increase scour
by changing flow patterns approaching a bridge opening. Bank widening can cause significant
changes in the flow distribution and thus the bridge’s flow contraction ratio.
It is difficult to anticipate when a change in plan form may occur. It may be gradual or the result
of a single major flood event. Also, the direction and magnitude of the movement of the stream
are not easily predicted. It is difficult to evaluate properly the vulnerability of a bridge due to
changes in plan form; however, it is important to incorporate potential plan form changes into
the design of new bridges and design of countermeasures for existing bridges.
Assessing the significance of plan form changes, such as the shifting location of meanders,
the formation of islands, and the overall pattern of streams, usually cannot be accomplished
without field observations. Records and photographs taken by bridge inspectors and
maintenance personnel may provide some insight into the nature of the stream for the initial
assessments. Historical aerial photographs of the stream can be extremely valuable in this
analysis. Ultimately, an engineering judgement must be made as to whether possible future
or existing plan form changes represent a hazard to the bridge, and the extent of field work
required to evaluate this condition.
116
Ministry of Works and Transport
Drainage Design Manual Section 10
10.5.3 Contraction
A constriction of the channel, which may be caused, in part, by bridge piers in the waterway,
can result in channel contraction scour. Deposition results from an expansion of the channel
or the bridge site being positioned immediately downstream of a steeper reach of stream.
Highways, bridges, and natural channel contractions are the most commonly encountered
cause of constriction scour.
10.5.4 Local Scour
The potential scour hazard at a bridge site is exacerbated by abutments or piers located within
the flood flow prism. The amount of potential scour caused by these features is termed local
scour. Local scour is a function of the geometry of these features as they relate to the flow
geometry. However, the importance of these geometric variables will vary. As an example,
increasing the pier or cofferdam width either through design or debris accumulation will
increase the amount of local scour, but only up to a point in subcritical flow streams. After
reaching this point, pier scour should not be expected to increase measurably with increased
stream velocity or depth. This threshold has not been defined in the more rare, supercritical
flowing streams.
10.6 Natural Armoring
Armoring occurs because a stream or river is unable, during a particular flood, to move the
more coarse material comprising either the bed or, if some bed scour occurs, its underlying
material. Scour may occur initially but later become arrested by armoring before the full scour
potential is reached again for a given flood magnitude.
When armoring does occur, the coarser bed material will tend to remain in place or quickly
redeposit so as to form a layer of riprap like armor on the stream bed or in the scour holes
and thus limit further scour for a particular discharge. When a larger flood occurs than used
to define the probable scour hole depths, scour will probably penetrate deeper until armoring
again occurs at some lower threshold.
Armoring may also cause bank widening. Bank widening encourages rivers or streams to seek
a more unstable, braided regime. Such instabilities may pose serious problems for bridges
as they encourage further plan form changes that are difficult to assess. Bank widening also
spreads the approach flow distribution, which in turn results in a more severe bridge opening
contraction.
10.7 Naturally Occurring Scour Resistant Materials
Caution is necessary in determining the scour resistance of bed materials and the underlying
strata. With smaller size material, the passage of a single flood may result in the predicted
scour depths. Conversely, in scour resistant material the maximum predicted depth of scour
may not be realized during the passage of a particular flood; however, some scour resistant
material may be lost. Commonly, this material is replaced with more easily scoured material.
Thus, a later flood may reach the predicted scour depth. Serious scour has been observed to
occur in materials commonly perceived to be scour resistant, such as consolidated soils, so-
called bed rock streams, and streams with gravel and boulder beds.
10.8 Methods of Computation of Extent of Scour
Determination of maximum scour depth that can occur at a crossing site is necessary in the
design of abutment and pier foundation. Actual extent of scouring at a particular crossing site
depends on various factors such as velocity of water, change in the channel geometry and
hydraulics resulting from the introduction of the crossing structure, nature of river bank and
river bed materials, shape and size of Abutment/pier structure, etc.
A number of empirical formulas for computing depth of scour have been developed over
the years based on results of numerous experiments. The method recommended by US
Department of Transportation, Office of Research and Development is re-commended.
117
Ministry of Works and Transport
Drainage Design Manual Section 10
According to this method, contraction scour and local scour are considered. Constriction scour
occurs when the waterway opening size provided by the bridge is less than regime width.
Otherwise no contraction scour occurs.
There are two cases of contraction scour to be considered; Live bed scour and Clear water
scour. For any case or condition, it is only necessary to determine if the flow in the main
channel or over-bank area upstream of the bridge, or approaching relief bridge, is transporting
bed material (live-bed), and then apply the appropriate equation with the variable defined
according to the location of contraction scour (channel or over bank). The calculation procedure
explained in this sub-section is demonstrated by means of a worked example in appendix
10.4.
To determine if the flow upstream of the bridge is transporting bed material, calculate the
critical velocity for beginning of motion Vc and compare it with the mean velocity V of the flow
in the main channel or over-bank area upstream of the bridge opening. If the critical velocity of
the bed material is higher than the mean velocity (Vc > V), then clear water contraction scour
will exist. On the other hand if the critical velocity of the bed, which is sufficient enough to
transport the D50 size of the bed material, is less than the mean velocity (Vc < V), then live-
bed contraction scour will exist.
The critical velocity is calculated by Laursen’s equation: -
Vc=10.95*Y1 (1/6)*D50(1/3)
Where: Vc = Critical velocity(ft/s)
Drainage Design Manual
Y1 = Mean depth of flow(ft)
D50 = Diameter at which 50% of the river bed material passes(ft)
10.8.1 Live-Bed
10.8.1 Contraction
Live-Bed Scour
Contraction Scour
10.8.2 10.8.2
Clear Water Contraction
Clear Scour
Water Contraction Scour
where:
7/6
Q
ys y1 0.13 1 10.4
Dm Y1 W
1/3 7/6
ys = scour depth (ft)
y1 = mean depth of flow prior to scour [ft]
Q = Discharge through the bridge, [cfs]
Dm = Effective mean diameter of the bed material (1.25*D50), [ft]
W = Bottom width of the bridge less pier width, [ft]
10.8.3 10.8.3
Local scour at Pier
Local scour at Pier
Drainage Design Manual
The local scour at pier is a function of bed material size, flow characteristics, fluid
properties and the geometry of the pier.
where;
10.13
MinistryYsof Works and
= scour Transport
depth
Y1 = flow depth directly upstream of the pier, [ft]
K1 = Correction factor for pier nose shape
K2 = Correction factor for angle of attack of flow
K3 = Correction factor for bed condition
a = Pier width, [ft]
V1 = mean velocity of flow directly upstream of the pier, [ft/sec]
1/2
Fr1 = Froude number = V1/(gy1)
TableTable
10.2:10.2: Correction
Correction Factor
Factor for Table 10.3: Correction Factor
Table Factor k2
k2for
forangle attack
pier nose
for pier nose
shape angle attack of flowof flow
120
Ministry of Works and Transport
Drainage Design Manual Section 10
X2 Y2
2
1 (10.6)
Ls ( 0. 4 L s ) 2
Height - is based on the anticipated high water level. The guide bank should have sufficient
height and free board to avoid overtopping and be protected from wave action.
Length - is estimated using the method recommended in “Hydraulics of bridge waterways”
(Bradley, 1978) in which the length of guide bank, Ls, is determined from the discharge ratio
Qf/Q30, relating the flow over the left or right flood plain to a specific portion of the flow under
the bridge, a representative velocity adjacent to the abutment of the bridge, and the length of
the guide bank needed. The length Ls is determined from nomograph in appendix 10.7.
Definitions of the symbol used in the Figure are:
Q = total stream discharge (m3/s)
Qf = lateral of flood plain flow (one side) (m3/s)
Q30 = Q/bx30 = discharge (m3/s) in 30 m of stream adjacent to abutment
b = length (m) of bridge opening
An2 = Water area (m2) under bridge referred to normal stage
Vn2 = average velocity (m/s) through bridge opening
Qf/Q30 = guide bank discharge ratio
Ls = top length (m) of guide bank (as shown on appendix 10.7)
It can be observed that the length of guide bank should be increased with an increase in
floodplain discharge, with an increase in velocity under the bridge, or both. The chart is read
by entering the ordinate with the proper value of Qf/Q30, moving horizontally to the curve
corresponding with the computed value of Vn2 and then downward to obtain from the abscissa
the length of guide bank required.
As a general rule, if the length read from the abscissa is less than 10m, a guide bank is not
required. For chart lengths from 10 to 30 m, it is recommended that a guide bank not less than
30 m long constructed. This length is needed to direct the curvilinear flow around the end of
the guide bank so that it will merge with the main channel flow and establish a straight course
down river before reaching the bridge abutment.
Curvilinear flow can have several times the capacity to scour than that of parallel flow, depending
on the radius of curvature, velocity, depth of flow and other factors. Holding the depth flow and
other factors constant, the depth of scour will increased with decrease in radius of curvature.
For this reason the deepest scour produced by a guide bank occurs near the nose where the
radius of curvature is least.
121
Ministry of Works and Transport
Drainage Design Manual Section 10
Appendix 10.6 shows the guide bank details including the provision of rock protection, which
should be extended out from the toe of the guide bank on the river bed, so that as the scour
hole forms, the rock will fall into place on the side of the scour hole to prevent undermining of
the guide bank.
10.13.2 Spurs
Spurs, retards or groynes are structures or embankments projecting into a stream from the
bank at some angle to deflect flowing water away from critical zones, to prevent erosion of the
bank, and establish a more desirable channel alignment or width. By deflecting the current
from the bank, a spur or a series of spurs may protect the stream bank more effectively and at
less cost than rock protecting the bank.
Also, by moving the location of any scour away from the bank, failure of the rock protection
on the spur can often be repaired before damage is done to structures along and across the
river. Spurs are also used to protect road embankments that form the approaches to a bridge
crossing. Often these embankments cut off the over bank flood flows causing these flows to
run parallel to embankment enroute to the bridge opening. Spurs constructed perpendicular
to the embankment keep the potentially erosive current away from the embankment, thus
protecting it. In this context guide banks also act as spurs. The noses of spurs are generally
rock protected.
The length of bank or road embankment protected by each spur is about three times its
projected length perpendicular to the direction of flow, as shown of appendix 10.9. Therefore,
spurs of equal length need not be spaced closer than three times their projected length. For a
group of four or more, the spacing may be up to four times their projected length.
10.13.3 Rock Protection
For abutments and piers where scour is expected, properly designed rock riprap will afford
protection against progressive erosion. This type of protection has generally been found to
be the most practical and economic solution for the protection of spill through abutments and
guide banks.
a) Selection of size and thickness of rock - The basic assumptions in determining the
rock size and thickness are as follows:
The stones are graded uniformly between specified minima for class of rock protection with
two thirds heavier than minimum required on face.
Minimum mass of stone (kg),
11x10 3 V 6 S gr
W (10.7)
(S gr 1) 3 sin 3 ( )
where,
V = Velocity (m/s)
S gr = Specific gravity of rock
= 70o for randomly placed rock rubble
= Face slope (degrees)
1/3
Thickness (m) of rock protection, T=0.3sin x W c
where, Wc = Class of rock protection (see appendix 10.8) expressed in kg.
(ie Wc = 1/4 tonne = 250 kg)
o 6
Assuming, S gr = 2.65 and = 1.5: 1(33.69 ), then W= 0.032 V and the size
and thickness of rock can be determined from appendix 10.8.
122
Ministry of Works and Transport
Drainage Design Manual Section 10
Note that the mass by which the class of rock protection, Wc is designated does not correspond
to the mass W. The class of rock protection, Wc should be graded so that at least 2/3 of all
rocks in the class have a greater mass than W.
b) Grading of rock - the grading of rock riprap affects its resistance to erosion. The
stone should be reasonably well graded throughout the riprap layer thickness. The grading of
the various standard classes of rock protection should be in accordance with appendix 10.8.
Each load of riprap should be reasonably well graded from the smallest to the maximum
specified. Stones smaller than the specified 10 percent size should not be permitted in an
amount exceeding 20 percent by weight of each load.
c) Quality of rock - the riprap should be hard, dense and durable. In addition, it should
be resistant to weathering, free from overburden, spoil, shale and organic matter. Rock that
is laminated, fractured, porous, or otherwise physically weak is unacceptable as rock slope
protection.
Stone shape is another important factor in the selection of an appropriate riprap material. In
general, riprap constructed with angular material has the best performance. Round material
can be used as riprap provided it is not placed on slopes greater than 3:1. Flat slab-like stones
should be avoided since they are easily dislodged by flow. An approximate guide to stone
shape is that the breadth or thickness of a single stone should be not less than one-third its
length.
d) Method of placement of rock protection - the thickness of the rock protection has
been determined assuming the following method of placement.
A footing trench should be excavated, along the toe of the slope. Rock should be placed so as
to provide a minimum of voids. The larger rocks should be placed in the foundation course and
on the outside surface of the slope protection. The rock may be placed by dumping and may
be spread in layers by bulldozers or other similar equipment.
Where filter fabrics are not used, best results are obtained when the embankment and rock
protection are raised in progressive horizontal layers. At each level the large rocks are placed
at the face by bulldozer, and where required a graded sand/gravel filter material is pushed
tightly in behind the rock protection, before raising the general level of the embankment to the
next level. Local surface irregularities of the slope protection should not vary from the planned
slope by more than 300 mm measured at right angles to the slope.
e) Filter material - where necessary a filter should be placed between the embankment
fill and the rock slope protection to prevent fine embankment material from being washed out
through the voids of the face stones. The filter may be a graded sand/gravel filter.
123
Ministry of Works and Transport
Drainage Design Manual Section 10
APPENDICES
124
Ministry of Works and Transport
Drainage Design Manual Appendices
Appendix 4.1: Example on Development of IDF Equations/Curves for a "Demonstration Rainfall Station"
Maximum Annual Intensity Data for 10, 20, 30, and 60 minutes Durations
125
Ministry of Works and Transport
1) 10 minutes duration
a) 2 yr. Return period
mean = 13.37 S.D = 5.12
X = 12.62
b) 5 yr. Return period
mean = 13.37 S.D = 5.12
X= 18.07
c) 10 yr. Return period
mean = 13.37 S.D = 5.12
X= 21.69
d) 25 yr. Return period
mean = 13.37 S.D = 5.12
X= 26.25
e) 50 yr. Return period
mean = 13.37 S.D = 5.12
X= 29.64
f) 100 yr. Return period
mean = 13.37 S.D = 5.12
X= 33.00
2) 20 minutes duration
a) 2 yr. Return period
mean = 20.76 S.D = 7.05
X= 19.72
b) 5 yr. Return period
mean = 20.76 S.D = 7.05
X= 27.23
c) 10 yr. Return period
mean = 20.76 S.D = 7.05
X= 32.21
d) 25 yr. Return period
mean = 20.76 S.D = 7.05
X= 38.49
e) 50 yr. Return period
mean = 20.76 S.D = 7.05
X= 43.16
f) 100 yr. Return period
mean = 20.76 S.D = 7.05
X= 47.79
126
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendices
3) 30 minutes duration
a) 2 yr. Return period
mean = 26.82 S.D = 9.99
X= 25.34
b) 5 yr. Return period
mean = 26.82 S.D = 9.99
X= 35.99
c) 10 yr. Return period
mean = 26.82 S.D = 9.99
X= 43.05
d) 25 yr. Return period
mean = 26.82 S.D = 9.99
X= 51.96
e) 50 yr. Return period
mean = 26.82 S.D = 9.99
X= 58.57
f) 100 yr. Return period
mean = 26.82 S.D = 9.99
X= 65.14
4) 60 minutes duration
a) 2 yr. Return period
mean = 32.30 S.D = 13.29
X= 30.34
b) 5 yr. Return period
mean = 32.30 S.D = 13.29
X= 44.51
c) 10 yr. Return period
mean = 32.30 S.D = 13.29
X= 53.90
d) 25 yr. Return period
mean = 32.30 S.D = 13.29
X= 65.75
e) 50 yr. Return period
mean = 32.30 S.D = 13.29
X= 74.55
X= 83.28
127
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 4
t(min) X X2 Y Y2 XY
10 -0.33 0.11 1.88 3.53 -0.62
20 -0.20 0.04 1.77 3.14 -0.35
30 -0.10 0.01 1.70 2.91 -0.17
60 0.11 0.01 1.48 2.20 0.17
Sum -0.51 0.17 6.84 11.77 -0.97
Avg. -0.13 0.04 1.71 2.94 -0.24
C = -0.89 0.89
k = 1.60
a = 39.40
r = -0.995
t(min) X X2 Y Y2 XY
10 -0.33 0.11 2.04 4.14 -0.67
20 -0.20 0.04 1.91 3.66 -0.38
30 -0.10 0.01 1.86 3.45 -0.18
60 0.11 0.01 1.65 2.72 0.19
-0.51 0.17 7.45 13.97 -1.05
-0.13 0.04 1.86 3.49 -0.26
C = -0.86 0.86
k = 1.75
a = 56.70
r = -0.996
128
Ministry
Ministry of Works of
andWorks and
Transport Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 4
Appendix 4.1 continued
t(min) X X2 Y Y2 XY
10 -0.33 0.11 2.11 4.47 -0.70
20 -0.20 0.04 1.99 3.94 -0.39
30 -0.10 0.01 1.93 3.74 -0.19
60 0.11 0.01 1.73 3.00 0.20
-0.51 0.17 7.77 15.15 -1.08
-0.13 0.04 1.94 3.79 -0.27
C= -0.84 0.84
k= 1.83
a= 68.14
r= -0.996
t(min) X X2 Y Y2 XY
10 -0.33 0.11 2.20 4.83 -0.73
20 -0.20 0.04 2.06 4.25 -0.41
30 -0.10 0.01 2.02 4.07 -0.20
60 0.11 0.01 1.82 3.30 0.21
-0.51 0.17 8.09 16.45 -1.12
-0.13 0.04 2.02 4.11 -0.28
C= -0.83 0.83
k= 1.92
a= 82.60
r= -0.995
129
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 4
t(min) X X2 Y Y2 XY
10 -0.33 0.11 2.25 5.06 -0.74
20 -0.20 0.04 2.11 4.46 -0.42
30 -0.10 0.01 2.07 4.28 -0.20
60 0.11 0.01 1.87 3.51 0.21
-0.51 0.17 8.30 17.31 -1.15
-0.13 0.04 2.08 4.33 -0.29
C= -0.83 0.83
k= 1.97
a= 93.32
r= -0.994
t(min) X X2 Y Y2 XY
10 -0.33 0.11 2.30 5.27 -0.76
20 -0.20 0.04 2.16 4.65 -0.43
30 -0.10 0.01 2.11 4.47 -0.20
60 0.11 0.01 1.92 3.69 0.22
-0.51 0.17 8.49 18.09 -1.17
-0.13 0.04 2.12 4.52 -0.29
C= -0.82 0.82
k= 2.02
a= 103.96
r= -0.993
130
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 4
39 .4 56 .7 68 .14
i2 i5 i10
(0 .3 t d ) 0.89 ( 0 .3 t d ) 0 .86 ( 0 .3 t d ) 0.84
82 .6 93 .32 103.96
i 25 i50 i100
( 0 .3 t d ) 0.83 ( 0 .3 t d ) 0.83 ( 0.3 t d ) 0.82
131
Ministry of Works and Transport
Ministry of Works and Transport
MoWHC Drainage Design Manual Appendix for Section 4
132
250
Drainage Design Manual
200
Intensity (mm/h)
100
ARI = 50yrs.
50
0
0.0 0.5 1.0 Time (h) 1.5 2.0 2.5
SABA/FINNROAD
Drainage Design Manual Appendices
Appendix
Appendix 4.3:
4.3: Two
Two Years
Years 24
24 hours
hours Rainfall
Rainfall (Source:
(Source: TRRL
TRRL Laboratory
Laboratory Report
Report 623)
623)
133
Ministry of Works and Transport
Drainage Design Manual Appendices
134
Ministry of Works and Transport
Drainage Design Manual Appendices
135
Ministry of Works and Transport
Drainage Design Manual Appendices
Appendix 5.1: Rainfall Time (TP) Zones (Source: TRRL Laboratory Report 706)
Appendix 5.1: Rainfall Time (TP) Zones (Source: TRRL Laboratory Report 706)
136
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 6
Prob. Skew
-2.0 -1.9 -1.8 -1.7 -1.6 -1.5 -1.4
0.9999 -8.21034 -7.98888 -7.76632 -7.54272 -7.31818 -7.09277 -6.86661
0.9995 -6.60090 -6.44251 -6.28285 -6.12196 -5.95990 -5.79673 -5.63252
0.9990 -5.90776 -5.77549 -5.64190 -5.50701 -537087 -5.23353 -5.09505
0.9980 -5.21461 -5.10768 -4.99937 -4.88971 -4.77875 -4.66651 -4.55304
0.9950 -4.29832 -4.22336 -4.14700 -4.06926 -3.99016 -3.90973 -3.82798
0.9900 -3.60517 -3.55295 -3.49935 -3.44438 -3.38804 -3.33035 -3.27134
0.9800 -2.91202 -2.88091 -2.84848 -2.81472 -2.77964 -2.74325 -2.70556
0.9750 -2.68888 -2.66413 -2.63810 -2.61076 -2.58214 -2.55222 -2.52102
0.9600 -2.21888 -2.20670 -2.19332 -2.17873 -2.16293 -2.14591 -2.12768
0.9500 -1.99573 -1.98906 -1.98124 -1.97227 -1.96213 -1.95083 -1.93836
0.9000 -1.30259 -1.31054 -1.31760 -1.32376 -1.32900 -1.33330 -1.33665
0.8000 -0.60944 -0.62662 -0.64335 -0.65959 -0.67532 -0.69050 -0.70512
0.7000 -0.20397 -0.22250 -0.24094 -0.25925 -0.27740 -0.29535 -0.31307
0.6000 0.08371 0.06718 0.05040 0.03344 0.01631 -0.00092 -0.01824
0.5704 0.15516 0.13964 0.12381 0.10769 0.09132 0.07476 0.05803
0.5000 0.30685 0.29443 0.28150 0.26808 0.25422 0.23996 0.22535
0.4296 0.43854 0.43008 0.42095 0.41116 0.40075 0.38977 0.37824
0.4000 0.48917 0.48265 0.47538 0.46739 0.45873 0.44942 0.43949
0.3000 0.64333 0.64453 0.64488 0.64436 0.64300 0.64080 0.63779
0.2000 0.77686 0.78816 0.79868 0.80837 0.81720 0.82516 0.83223
0.1000 0.89464 0.91988 0.94496 0.96977 0.99418 1.01810 1.04144
0.0500 0.94871 0.98381 1.01973 1.05631 1.09338 1.13075 1.16827
0.0400 0.95918 0.99672 1.03543 1.07513 1.11566 1.15682 1.19842
0.0250 0.97468 1.01640 1.06001 1.10537 1.15229 1.20059 1.25004
0.0200 0.97980 1.02311 1.06864 1.11628 1.16584 1.21716 1.26999
0.0100 0.98995 1.03695 1.08711 1.14042 1.19680 1.25611 1.31815
0.0050 0.99499 1.04427 1.09749 1.15477 1.21618 1.28167 1.35114
0.0020 0.99800 1.04898 1.10465 1.16534 1.23132 1.30279 1.37981
0.0010 0.99900 1.05068 1.10743 1.16974 1.23805 1.31275 1.39408
0.0005 0.99950 1.05159 1.10901 1.17240 1.24235 1.31944 1.40413
0.0001 0.99990 1.05239 1.11054 1.17520 1.24728 1.32774 1.41753
Prob. Skew
-1.3 -1.2 -1.1 -1.0 -0.9 -0.8 -0.7
0.9999 -6.63980 -6.41249 -6.18480 -5.95691 -5.72899 -5.50124 -5.27389
0.9995 -5.46735 -5.30130 -5.13449 -4.96701 -4.79899 -4.63057 -4.46189
0.9990 -4.95549 -4.81492 -4.67344 -4.53112 -4.38807 -4.24439 -4.10022
0.9980 -4.43839 -4.32263 -4.20582 -4.08802 -3.96932 -3.84981 -3.72957
0.9950 -3.74497 -3.66073 -3.57530 -3.48874 -3.40109 -3.31243 -3.22281
0.9900 -3.21103 -3.14944 -3.08660 -3.02256 -2.95735 -2.89101 -2.82359
0.9800 -2.66657 -2.62631 -2.58480 -2.54206 -2.49811 -2.45298 -2.40670
0.9750 -2.48855 -2.45482 -2.41984 -2.38364 -2.34623 -2.30764 -2.26790
0.9600 -2.10823 -2.08758 -2.06573 -2.04269 -2.01848 -1.99311 -1.96660
0.9500 -1.92472 -1.90992 -1.89395 -1.87683 -1.85856 -1.83916 -1.81864
0.9000 -1.33904 -1.34047 -1.34092 -1.34039 -1.33889 -1.33640 -1.33294
0.8000 -0.71915 -0.73257 -0.74537 -0.75752 -0.76902 -0.77986 -0.79002
0.7000 -0.33054 -0.34772 -0.36458 -0.38111 -0.39729 -0.41309 -0.42851
0.6000 -0.03560 -0.05297 -0.07032 -0.08763 -0.10486 -0.12199 -0.13901
0.5704 0.04116 0.02421 0.00719 -0.00987 -0.02693 -0.04397 -0.06097
0.5000 0.21040 0.19517 0.17968 0.16397 0.14807 0.13199 0.11578
0.4296 0.36620 0.35370 0.34075 0.32740 0.31368 0.29961 0.28516
0.4000 0.42899 0.41794 0.40638 0.39434 0.38186 0.36889 0.35565
0.3000 0.63400 0.62944 0.62415 0.61815 0.61146 0.60412 0.59615
0.2000 0.83841 0.84369 0.84809 0.85161 0.85426 0.85607 0.85703
0.1000 1.06413 1.08608 1.10726 1.12762 1.14712 1.16574 1.18347
0.0500 1.20578 1.24313 1.28019 1.31684 1.35299 1.38855 1.42345
0.0400 1.24028 1.28225 1.32414 1.36584 1.40720 1.44813 1.48852
0.0250 1.30042 1.35153 1.40314 1.45507 1.50712 1.55914 1.61099
0.0200 1.32412 1.37929 1.43529 1.49188 1.54886 1.60604 1.66325
0.0100 1.38267 1.44942 1.51808 1.58838 1.66001 1.73271 1.80621
0.0050 1.42439 1.50114 1.58110 1.66390 1.74919 1.83660 1.92580
0.0020 1.46232 1.55016 1.64305 1.74062 1.84244 1.94806 2.05701
0.0010 1.48216 1.57695 1.67825 1.78572 1.89894 2.01739 2.14053
0.0005 1.49673 1.59738 1.70603 1.82241 1.94611 2.07661 2.21328
0.0001 1.51752 1.62838 1.75053 1.88410 2.02891 2.18448 2.35015
Prob. Skew
-0.6 -0.5 -0.4 -0.3 -0.2 -0.1 0.0
0.9999 -5.04718 -4.82141 -4.59687 -4.37394 -4.15301 -3.93453 -3.71902
0.9995 -4.29311 -4.12443 -3.95605 -3.78820 -3.62113 -3.45513 -3.29053
0.9990 -3.95567 -3.81090 -3.66608 -3.52139 -3.37703 -3.23322 -3.09023
0.9980 -3.60872 -3.48737 -3.36566 -3.24371 -3.12169 -2.99978 -2.87816
0.9950 -3.13232 -3.04102 -2.94900 -2.85636 -2.76321 -2.66965 -2.57583
0.9900 -2.75514 -2.68572 -2.61539 -2.54421 -2.47226 -2.39961 -2.32635
0.9800 -2.35931 -2.31084 -2.26133 -2.21081 -2.15935 -2.10697 -2.05375
0.9750 -2.22702 -2.18505 -2.14202 -2.09795 -2.05290 -2.00688 -1.95996
0.9600 -1.93896 -1.91022 -1.88039 -1.84949 -1.81756 -1.78462 -1.75069
0.9500 -1.79701 -1.77428 -1.75048 -1.72562 -1.69971 -1.67279 -1.64485
0.9000 -1.32850 -1.32309 -1.31671 -1.30936 -1.30105 -1.29178 -1.28155
0.8000 -0.79950 -0.80829 -0.81638 -0.82377 -0.83044 -0.83639 -0.84162
0.7000 -0.44352 -0.45812 -0.47228 -0.48600 -0.49927 -0.51207 -0.52440
0.6000 -0.15589 -0.17261 -0.18916 -0.20552 -0.22168 -0.23763 -0.25335
0.5704 -0.07791 -0.09178 -0.11154 -0.12820 -0.14472 -0.16111 -0.17733
0.5000 0.09945 0.08302 0.06651 0.04993 0.03325 0.01662 0.00000
0.4296 0.27047 0.25558 0.24037 0.22492 0.20925 0.19339 0.17733
0.4000 0.34198 0.32796 0.31362 0.29897 0.28403 0.26882 0.25335
0.3000 0.58757 0.57840 0.56867 0.55839 0.54757 0.53624 0.52440
0.2000 0.85718 0.85653 0.85508 0.85285 0.84986 0.84611 0.84162
0.1000 1.20028 1.21618 1.23114 1.24516 1.25824 1.27037 1.28155
0.0500 1.45762 1.49101 1.52357 1.55527 1.58607 1.61594 1.64485
0.0400 1.52830 1.56740 1.60574 1.64329 1.67999 1.71580 1.75069
0.0250 1.66253 1.71366 1.76427 1.81427 1.86360 1.91219 1.95996
0.0200 1.72033 1.77716 1.83361 1.88959 1.94499 1.99973 2.05375
0.0100 1.88029 1.95472 2.02933 2.10394 2.17840 2.25258 2.32635
0.0050 2.01644 2.10825 2.20092 2.29423 2.38795 2.48187 2.57583
0.0020 2.16884 2.28311 2.39942 2.51741 2.63672 2.75706 2.87816
0.0010 2.26780 2.39867 2.53261 2.66915 2.80786 2.94834 3.09023
0.0005 2.35549 2.50257 2.65390 2.80889 2.96698 3.12767 3.29053
0.0001 2.52507 2.70836 2.89907 3.09631 3.29921 3.50703 3.71902
Prob. Skew
0.1 0.2 0.3 0.4 0.5 0.6 0.7
0.9999 -3.50703 -3.29921 -3.09631 -2.89907 -2.70836 -2.52507 -2.35015
0.9995 -3.12767 -2.96698 -2.80889 -2.65390 -2.50257 -2.35549 -2.21328
0.9990 -2.94834 -2.80786 -2.66915 -2.53261 -2.39867 -2.26780 -2.14053
0.9980 -2.75706 -2.63672 -2.51741 -2.39942 -2.28311 -2.16884 -2.05701
0.9950 -2.48187 -2.38795 -2.29423 -2.20092 -2.10825 -2.01644 -1.92580
0.9900 -2.25258 -2.17840 -2.10394 -2.02933 -1.95472 -1.88029 -1.80621
0.9800 -1.99973 -1.94499 -1.88959 -1.83361 -1.77716 -1.72037 -1.66325
0.9750 -1.91219 -1.86360 -1.81427 -1.76427 -1.71366 -1.66253 -1.61099
0.9600 -1.71580 -1.67999 -1.64329 -1.60574 -1.56740 -1.52830 -1.48852
0.9500 -1.61594 -1.58607 -1.55527 -1.52357 -1.49101 -1.45762 -1.42345
0.9000 -1.27037 -1.25824 -1.24516 -1.23114 -1.21618 -1.20028 -1.18347
0.8000 -0.84611 -0.84986 -0.85285 -0.85508 -0.85653 -0.85718 -0.85703
0.7000 -0.53624 -0.54757 -0.55839 -0.56867 -0.57840 -0.58757 -0.59615
0.6000 -0.26882 -0.28403 -0.29897 -0.31362 -0.32796 -0.34198 -0.35565
0.5704 -0.19339 -0.20925 -0.22492 -0.24037 -0.25558 -0.27047 -0.28516
0.5000 -0.01662 -0.03325 -0.04993 -0.06651 -0.08302 -0.09945 -0.11578
0.4296 0.16111 0.14472 0.12820 0.11154 0.09478 0.07791 0.06097
0.4000 0.23763 0.22168 0.20552 0.18916 0.17261 0.15589 0.13901
0.3000 0.51207 0.49927 0.48600 0.47228 0.45812 0.44352 0.42851
0.2000 0.83639 0.83044 0.82377 0.81638 0.80829 0.79950 0.79002
0.1000 1.29178 1.30105 1.30936 1.31671 1.32309 1.32850 1.33294
0.0500 1.67279 1.69971 1.72562 1.75048 1.77428 1.79701 1.81864
0.0400 1.78462 1.81756 1.84949 1.88039 1.91022 1.93896 1.96660
0.0250 2.00688 2.05290 2.09795 2.14202 2.18505 2.22702 2.26790
0.0200 2.10697 2.15935 2.21081 2.26133 2.31084 2.35931 2.40670
0.0100 2.39961 2.47226 2.54421 2.61539 2.68572 2.75514 2.82359
0.0050 2.66965 2.76321 2.85636 2.94900 3.04102 3.13232 3.22281
0.0020 2.99978 3.12169 3.24371 3.36566 3.48737 3.60872 3.72957
0.0010 3.23322 3.37703 3.52139 3.66608 3.81090 3.95567 4.10022
0.0005 3.45513 3.62113 3.78820 3.95605 4.12443 4.29311 4.46189
0.0001 3.93453 4.15301 4.37394 4.59687 4.82141 5.04718 5.27389
140
Ministry of Works and Transport
Drainage Design
Drainage DesignManual
Manual Appendix for Appendices
Section 6
Prob. Skew
0.8 0.9 1.0 1.1 1.2 1.3 1.4
0.9999 2.18448 -2.02891 -1.88410 -1.75053 -1.62838 -1.51752 -1.41753
0.9995 -2.07661 -1.94611 -1.82241 -1.70603 -1.59738 -1.49673 -1.40413
0.9990 -2.01739 -1.89894 -1.78572 -1.67825 -1.57695 -1.48216 -1.39408
0.9980 -1.94806 -1.84244 -1.74062 -1.64305 -1.55016 -1.46232 -1.37981
0.9950 -1.83660 -1.74919 -1.66390 -1.58110 -1.50114 -1.42439 -1.35114
0.9900 -1.73271 -1.66001 -1.58838 -1.51808 -1.44942 -1.38267 -1.31815
0.9800 -1.60604 -1.54886 -1.49188 -1.43529 -1.37929 -1.32412 -1.26999
0.9750 -1.55914 -1.50712 -1.45507 -1.40314 -1.35153 -1.30042 -1.25004
0.9600 -1.44813 -1.40720 -1.36584 -1.32414 -1.28225 -1.24028 -1.19842
0.9500 -1.38855 -1.35299 -1.31684 -1.28019 -1.24313 -1.20578 -1.16827
0.9000 -1.16574 -1.14712 -1.12762 -1.10726 -1.08608 -1.06413 -1.04144
0.8000 -0.85607 -0.85426 -0.85161 -0.84809 -0.84369 -0.83841 -0.83223
0.7000 -0.60412 -0.61146 -0.61815 -0.62415 -0.62944 -0.63400 -0.63779
0.6000 -0.36889 -0.38186 -0.39434 -0.40638 -0.41794 -0.42899 -0.43949
0.5704 -0.29961 -0.31368 -0.32740 -0.34075 -0.35370 -0.36620 -0.37824
0.5000 -0.13199 -0.14807 -0.16397 -0.17968 -0.19517 -0.21040 -0.22535
0.4296 0.04397 0.02693 0.00987 -0.00719 -0.02421 -0.04116 -0.05803
0.4000 0.12199 0.10486 0.08763 0.07032 0.05297 0.03560 0.01824
0.3000 0.41309 0.39729 0.38111 0.36458 0.34772 0.33054 0.31307
0.2000 0.77986 0.76902 0.75752 0.74537 0.73257 0.71915 0.70512
0.1000 1.33640 1.33889 1.34039 1.34092 1.34047 1.33904 1.33665
0.0500 1.83916 1.85856 1.87683 1.89395 1.90992 1.92472 1.93836
0.0400 1.99311 2.01848 2.04269 2.06573 2.08758 2.10823 2.12768
0.0250 2.30764 2.34623 2.38364 2.41984 2.45482 2.48855 2.52102
0.0200 2.45298 2.49811 2.54206 2.58480 2.62631 2.66657 2.70556
0.0100 2.89101 2.95735 3.02256 3.08660 3.14944 3.21103 3.27134
0.0050 3.31243 3.40109 3.48874 3.57530 3.66073 3.74497 3.82798
0.0020 3.84981 3.96932 4.08802 4.20582 4.32263 4.43839 4.55304
0.0010 4.24439 4.38807 4.53112 4.67344 4.81492 4.95549 5.09505
0.0005 4.63057 4.79899 4.96701 5.13449 5.30130 5.46735 5.63252
0.0001 5.50124 5.72899 5.95691 6.18480 6.41249 6.63980 6.86661
141
Ministry of Works and Transport
Drainage Design
Drainage DesignManual
Manual Appendix for Appendices
Section 6
Prob. Skew
1.5 1.6 1.7 1.8 1.9 2.0
.9999 -1.32774 -1.24728 -1.17520 -1.11054 -1.05239 -.99990
.9995 -1.31944 -1.24235 -1.17240 -1.10901 -1.05159 -.99950
.9990 -1.31275 -1.23805 -1.16974 -1.10743 -1.50568 -.99900
.9980 -1.30279 -1.23132 -1.16534 -1.10465 -1.04898 -.99800
.9950 -1.28167 -1.21618 -1.15477 -1.09749 -1.04427 -.99499
.9900 -1.25611 -1.19680 -1.14042 -1.08711 -1.03695 -.98995
.9800 -1.21716 -1.16584 -1.11628 -1.06864 -1.02311 -.97980
.9750 -1.20059 -1.15229 -1.10537 -1.06001 -1.01640 -.97468
.9600 -1.15682 -1.11566 -1.07513 -1.03543 -.99672 -.95918
.9500 -1.13075 -1.09338 -1.05631 -1.01973 -.98381 -.94871
.9000 -1.01810 -.99418 -.96977 -.94496 -.91988 -.89464
.8000 -.82516 -.81720 -.80837 -.79868 -.78816 -.77686
.7000 -.64080 -.64300 -.64436 -.64488 -.64453 -.64333
.6000 -.44942 -.45873 -.46739 -.47538 -.48265 -.48917
.5704 -.38977 -.40075 -.41116 -.42095 -.43008 -.43854
.5000 -.23996 -.25422 -.26808 -.28150 -.29443 -.30685
.4296 -.07476 -.09132 -.10769 -.12381 -.13964 -.15516
.4000 .00092 -.01631 -.03344 -.05040 -.06718 -.08371
.3000 .29535 .27740 .25925 .24094 .22250 .20397
.2000 .69050 .67532 .65959 .64335 .62662 .60944
.1000 1.33330 1.32900 1.32376 1.31760 1.31054 1.30259
.0500 1.95083 1.96213 1.97227 1.98124 1.98906 1.99573
.0400 2.14591 2.16293 2.17873 2.19332 2.20670 2.21888
.0250 2.55222 2.58214 2.61076 2.63810 2.66413 2.68888
.0200 2.74325 2.77964 2.81472 2.84848 2.88091 2.91202
.0100 3.33035 3.38804 3.44438 3.49935 3.55295 3.60517
.0050 3.90973 3.99016 4.06926 4.14700 4.22336 4.29832
.0020 4.66651 4.77875 4.88971 4.99937 5.10768 5.21461
.0010 5.23353 5.37087 5.50701 5.64190 5.77549 5.90776
.0005 5.79673 5.95990 6.12196 6.28285 6.44251 6.60090
.0001 7.09277 7.31818 7.54272 7.76632 7.98888 8.21034
-
142
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 6
Source: FHWA
144
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design
Drainage Design Manual
Manual Appendix for SectionAppendices
9
146
Ministry
Ministry ofof Works
Works andand Transport
Transport
Drainage Design
Drainage Design Manual
Manual Appendices
Appendix for Section 9
147
Ministry of Works and Transport
148
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendix for Section 9
2
He = Ke (V /2g)
149
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design
Drainage Design Manual
Manual Appendices
Appendix for Section 9
150
Ministry of Works and Transport
Is
The approach Yes
Consider design option
velocity V
depending on the results.
negligible ?
No
Yes Hwi = HW
Hwi = HW-V²/2g
Do you
have enough values to Yes
plot performance
curve ? Compute the Tailwater depth
TW
No Yes
Are results in
Calculate critical depth (dc)
agreement with cons-
traints and assump- using in Appendix 9.11 -9.12
tions ?
Yes
No
HWc= HWi Yes HWi> Hwoi ?
HWc-HWov>0 ? Inlet control
( HWov=height of road
above inlet invert) No
Yes
HWc= Hwoi HWoi>1.2D ?
Outlet control
No
Approximation has to
Source : ERA be checked (see Step 8)
151
Ministry of Works and Transport
Drainage Design Manual Appendix for Section 9
152
Ministry of Works and Transport
Drainage Design
Drainage Design Manual
Manual Appendices
Appendix for Section 9
153
Ministry of Works and Transport
1,6
1,4
1,2
Critical Depth-dc (Meters)
0,8
0,4
0,2
0
0 1 2 3 4 5 6
Q/B
4,5
4
Critical Depth-dc (Meters)
3,5
1,5
1
5 10 15 20 25 30 35
Q/B
154
Ministry of Works and Transport
155
Ministry of Works and Transport
156
Ministry of Works and Transport
157
Ministry of Works and Transport
158
Ministry of Works and Transport
162
Appendix 9.19 Capacity of Concrete Pipe Culverts
3
Capacity of pipes at different slopes (m /s) n=0.015
Diameter (inches)
Single Double Triple Single Double Triple Single Double Triple Single Double Triple
)
(%
m
n( Height(m)
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
163
Ministry of Works and Transport
Ministry of Works and Transport 1
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
164
Ministry of Works and Transport
Ministry of Works and Transport 2
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
165
Ministry of Works and Transport
Ministry of Works and Transport 3
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
166
Ministry of Works and Transport
Ministry of Works and Transport 4
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
167
Ministry of Works and Transport
Ministry of Works and Transport 5
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
168
Ministry of Works and Transport
Ministry of Works and Transport 6
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
169
Ministry of Works and Transport
Ministry of Works and Transport 7
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
170
Ministry of Works and Transport
Ministry of Works and Transport 8
Drainage Design Manual Appendices
n = 0.017
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
171
Ministry of Works and Transport
Ministry of Works and Transport 9
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
172
Ministry of Works and Transport
Ministry of Works and Transport 10
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
173
Ministry of Works and Transport
Ministry of Works and Transport 11
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
174
Ministry of Works and Transport
Ministry of Works and Transport 12
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
175
Ministry of Works and Transport
Ministry of Works and Transport 13
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
176
Ministry of Works and Transport
Ministry of Works and Transport 14
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
177
Ministry of Works and Transport
Ministry of Works and Transport 15
Drainage Design Manual Appendices
) n = 0.017
)
(%
m
Height(m)
n(
pe
Sp
Sl
178
Ministry of Works and Transport
Ministry of Works and Transport 16
Drainage Design Manual Appendices
n = 0.017
)
)
(%
m
Height(m)
n(
pe
a
1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5
o
Sp
Sl
179
Ministry of Works and Transport
Ministry of Works and Transport 17
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 10
Source: HDS-1
180
Ministry of Works and Transport
182
Ministry of Works and Transport
Method 1 Method 2
Yes Is armouring or an No
expanding reach of
concern ?
Select a trial bridge opening and compute Estimate contraction scour using
the bridge hydraulics empirical contraction formula (8.1)
Yes
Does the revision lead
to a variation of more
than 5% in velocity,
elevation or flow depth?
No
Plot the scour and aggradation depths on a cross section
Yes
Ye s
Appendix 10.4 Calculation Procedure For Stage Discharge Relationship at a Bridge Site
Design Parameters:
Col. 1 Col. 2 Col. 3 Col. 4 Col. 5 Col. 6 Col. 7 Col. 8 Col. 9 Col. 10 Col.11
Stage DH Aw (m2) Circumf.(m) Lw (m) P (m) R (m) Q (m3/s) H (m) V (m/s) Fr
774.571 0.500 3.692 25.552 12.712 12.840 0.2875 3.636 0.5000 0.985 0.44
775.071 0.500 10.522 29.593 14.609 14.985 0.7022 18.793 1.0000 1.786 0.57
775.571 0.500 18.301 33.635 16.506 17.129 1.0684 43.239 1.5000 2.363 0.62
776.071 0.500 27.028 37.676 18.402 19.274 1.4023 76.552 2.0000 2.832 0.64
776.571 0.500 36.575 40.606 19.640 20.965 1.7446 119.831 2.5000 3.276 0.66
777.071 0.500 46.617 42.900 20.512 22.388 2.0823 171.852 3.0000 3.686 0.68
777.571 0.500 57.070 45.176 21.370 23.807 2.3972 231.102 3.5000 4.049 0.69
778.071 0.500 69.506 55.398 26.345 29.053 2.3924 281.086 4.0000 4.044 0.65
STAGE DISCHARGE
STAGE CURVE
DISCHARGE CURVE
778.50
778.00
777.50
777.00
Stage (m)
776.50
776.00
775.50
775.00
774.50
774.00
0 50 100 150 200 250 300
DISCHARGE Q [ m3/s]
3
50 years design discharge, Q50 = 246 m /s Corresponding V = 4.05 m/s
From graph above;
Stage corresponding to Q50 = 777.600 m
Area of water, Aw = 60.7 m2
184
Ministry of Works and Transport
Recommended opening
Since the actual clear span provided is less than the limiting span for constriction,
a scour computation is necessary to place the abutments below the scour depth.
Hence, a constriction scour based on Laursen is adopted as shown below:
Yu Yc
Wu [ft] Wc [ ft] Q1 [cfs] Qc [cfs] K1 Ys [m]
[ft] [ft]
11.58 14.73582 70.5381 65.616798 6949.889 8687.361 0.69 0.96
Where:
Y1 = depth of upstream flow (ft)
D50 = diameter at which 50% of the river bed material passes (ft)
Vc = critical velocity (ft/s)
V = mean velocity (ft/s)
Yu = average depth in the upstream main channel (ft)
Yc = average depth in the contracted section (ft)
= Yu*(Qc/Q1)6/7*(W u/127.9528)k1
W u = bottom width of the upstream main channel (ft)
W c = bottom width of the contracted section (ft)
Q1 = flow in the upstream channel transporting sediments (cfs)
Qc = flow in the contracted channel (cfs)
K1 = exponent based on mode of bed material transport.
Ys = Yc - Yu
185
Ministry of Works and Transport
Ministry of Works and Transport
Drainage Design Manual Appendices
Drainage Design Manual Appendix for Section 10
Take, ys = 1.50 m
Appendix 10.4 Calculation Procedure for stage-discharge at a bridge site
Backwater Computation
By Molesworth's Formula:
Therefore, ha = 0.23 m
With the grade level 780.10 m ,since the afflux h1* is less than 2.50 m, the grade is in
a safe level and there is no risk of overtopping. Therefore, a bridge 1X20 m span is sufficient
for this crossing.
186
Ministry of Works and Transport
Appendix 10.4 Calculation Procedure for Stage Discharge Relationship at a Bridge Site
The following are surveyed values for the determination of the curve:
Surveyors Flood Mark, River Bed Level , Slope of River Bed at the Site Hydraulic Roughness
Coefficient
A worked example is given in the next page. To facilitate discussion of calculation procedure,
the table is divided into 11 columns. The column labels will be used to write
necessary equations.
Col. 1 Stages starting from river bed to a height above the surveyors flood mark is given in
column 1. The range is subdivided in 0.5 m intervals.
Col. 2 Differences between consecutive stages in column 1 are entered in this column.
Col. 3 Area upto the given stage is measured and registered in this column. The surveyed
cross-section of the river is used for the purpose.
Col. 5 Length of water surface from bank to bank is measured and registered in this column.
Col. 6 Wetted perimeter is calculated as the difference between circumference and length of
a given stage.
Col. 9 Water Depth is calculated as the difference between given stage and river bed Level
187
Ministry of Works and Transport
Appendix 10.4 Calculation Procedure for Stage Discharge Relationship at a Bridge Site
V Col .10
F
gy 9.81xCol.9
After Completing the above calculation, stage-discharge curve is constructed by plotting Col.
8 versus Col.1.
188
Ministry of Works and Transport
189
Ministry of Works and Transport
190
Ministry of Works and Transport
191
Ministry of Works and Transport
Minimum
Rock Mass Percentage of
Rock Class Rock Size* (m)
(kg) Rock Larger
Than
Facing 0.40 100.00 0
0.30 35.00 50
0.15 2.50 90
Light 0.55 250.00 0
0.40 100.00 50
0.20 10.00 90
1/4 tonne 0.75 500.00 0
0.55 250.00 50
0.30 35.00 90
1/2 tonne 0.90 1000.00 0
0.70 450.00 50
0.40 100.00 90
1 tonne 1.15 2000.00 0
0.90 1000.00 50
0.55 250.00 90
2 tonne 1.45 4000.00 0
1.15 2000.00 50
0.75 500.00 90
4 tonne 1.80 8000.00 0
1.45 4000.00 50
0.90 1000.00 90
192
Ministry of Works and Transport
193
Ministry of Works and Transport
194
Ministry of Works and Transport