Cost and Duration: Plate NO. 4

The document provides a schedule of activities, durations, costs, manpower, and equipment for the proposed construction of a four-storey apartment building with penthouse. It outlines the excavation and concrete pouring for the foundation, installation of rebar and formwork for floors and columns over 15 days. Electrical and plumbing rough-ins are scheduled for 10 days per floor. Concrete pouring will take 1 day per floor level with necessary formwork removal and scaffolding dismantling. The project requires equipment like backhoes, concrete mixers, vibrators, and bar bending machines operated by tradespeople including masons, carpenters, steel fixers, and their assistants.

Uploaded by

Dexter Mecares
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views6 pages

Cost and Duration: Plate NO. 4

The document provides a schedule of activities, durations, costs, manpower, and equipment for the proposed construction of a four-storey apartment building with penthouse. It outlines the excavation and concrete pouring for the foundation, installation of rebar and formwork for floors and columns over 15 days. Electrical and plumbing rough-ins are scheduled for 10 days per floor. Concrete pouring will take 1 day per floor level with necessary formwork removal and scaffolding dismantling. The project requires equipment like backhoes, concrete mixers, vibrators, and bar bending machines operated by tradespeople including masons, carpenters, steel fixers, and their assistants.

Uploaded by

Dexter Mecares
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

Plate NO.

4
Cost and Duration
Project: Proposed Four - Storey Apartment with Pent House

ACTIVITY DURATION COST MANPOWER EQUIPMENTS


Operators, Dumptruck,
Mobilization 2 days 50,000 laborers=2,
carpenter
Clearing and grubbing 4 days 20,160.00 laborers=6
Construction of temporary carpenter= 3
1.5days 19,968.00
perimeter fence helper= 3
Construction of temporary 3 days 50,000 carpenter=2
bunkhouse/facilities helper= 2

survey team=
3men
Lay-out/ stake out 2 days 20,000 carpenters= 4
laborers= 4

Excavation of footing,tie
Backhoe
beam,wall footing and ground 15days 134,639.55 20 men Jackhammer
floor columns

Fabrication of rebars for


footing,tie beam,wall footing 5 days 660,441.77 Steelman= 20 bar bending machine
helper= 20
and ground floor columns

Installation of rebars for Steelman= 20


footing,tie beam,wall footing 5 days 660,441.77 helper= 20 10- Bar Cutter
and ground floor columns

masons = 2
Pouring of concrete for carpenters = 1
footing, wall footing and tie 1 day 217,342.43 laborers = 4 1 concrete mixer, 1
vibrator
beams vibratory operator
=1

Removal of formworks for tie .5 days 568.10 Carpenter=4


beam Helper=4

Installation of formworks and carpenter=10


scaffolds for Ground Floor 1.5 days 22,118.40 helper= 10
Columns

Pouring of concrete for 1 concrete mixer, 1


Ground Floor Columns .5 day 36,445.19 10 men vibrator

Backhoe
Backfill 2.5 day 33,575.97 32 men Jackhammer
Grader
Fabrication of rebars for 2nd steelman=20
floor beams and slab 2 days 235,260.17 helper= 20 10- Bar Cutter

Installation of rebars for 2nd 2 days 235,260.17 steelman=20 10- Bar Cutter
floor beams and slab helper= 20

Installation of formworks for carpenter= 10


2 days 183,696.00
2nd floor beams and slab helper= 10

Installation of rough-ins for 1 plumber 1helper


Second Floor electrical and 10 days 107,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Second floor beam and slab 1 days 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks for Carpenter=4


1 days 7,654.00
Second Floor beam and slab Helper=4

Fabrication of rebars for Steelman= 20


1 days 103,062.20 bar bending machine
Second floor columns helper= 20
Installation of rebars for Steelman= 10
Second floor columns 1 days 103,062.20 helper= 10 5- Bar Cutter

Installation of formworks and


scaffolds for Second floor 1 days 36,249.60 carpenter=20
helper= 20
columns
masons = 2
carpenters = 1
Pouring of concrete of Second 1 concrete mixer, 1
0.5 day 44,254.88 laborers = 4
floor columns vibratory operator vibrator, 1 pump crete
=1
Removal of forms and carpenter=20
scaffolds for Second floor .5 day 1,510.40
columns helper= 20

Fabrication of rebars for Third steelman=20


2days 235,260.17 bar bending machine
floor beams and slab helper= 20
Installation of rebars for Third 2days 235,260.17 steelman=20 10- Bar Cutter
floor beams and slab helper= 20

Installation of formworks for 5days 183,696.00 carpenter=20


Third floor beams and slab helper= 20

Installation of rough-ins for 1 plumber 1helper


Third Floor electrical and 10days 107,200.00 electrician=5
plumbing helper=5

masons = 2
Pouring of concrete for Third carpenters = 1 1 concrete mixer, 1
floor beam and slab 1day 281,209.65 laborers = 4 vibrator, 1 pump crete
vibratory operator
=1
Removal of formworks for Carpenter=4
Third floor beam and slab 1day 7,654.00 Helper=4
Fabrication of rebars for Third steelman=20
1day 103,062.20 bar bending machine
floor columns helper= 20

Installation of rebars for Third steelman=20


1day 103,062.20 10- Bar Cutter
floor columns helper= 20

Installation of formworks and


carpenter=20
scaffols for Third floor 1day 36,249.60
helper= 20
columns

masons = 2
carpenters = 1
Pouring of concrete for Third .5day 44,254.88 laborers = 4 1 concrete mixer, 1
floor columns vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks and


carpenter=20
scaffolds for Third floor .5day 1,510.40 helper= 20
columns

Fabrication of rebars for 2days 235,260.17 steelman=20 bar bending machine


Fourth floor beams and slab helper= 20

Installation of rebars for 2days 235,260.17 steelman=20 10- Bar Cutter


Fourth floor beams and slab helper= 20

Installation of formworks for carpenter=20


Fourth floor beams and slab 5days 183,696.00 helper= 20

Installation of rough-ins for 1 plumber 1helper


Fourth floor electrical and 10days 107,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Pouring of concrete for Fourth 1day 281,209.65 laborers = 4 1 concrete mixer, 1
floor beam and slab vibrator, 1 pump crete
vibratory operator
=1

Removal of formworks for Carpenter=4


Fourth floor beam and slab 1day 7,654.00 Helper=4
Fabrication of rebars for steelman=20
1day 103,062.20
Fourth floor columns helper= 20
Installation of rebars for steelman=20
1day 103,062.20
Fourth floor columns helper= 20
Installation of formworks and carpenter=20
scaffolds for Fourth floor 1day 36,249.60
helper= 20
columns
masons = 2
carpenters = 1
Pouring of concrete for Fourth .5day 44,254.88 laborers = 4 1 concrete mixer, 1
floor columns vibratory operator vibrator, 1 pump crete
=1

Removal of formworks and


carpenter=20
scaffolds for Fourth floor .5day 1,510.40
columns helper= 20

Fabrication of rebars for Rood steelman=20


deck and Penthouse beams 2days 267,820.82 bar bending machine
helper= 20
and slab

Installation of rebars for Roof


deck and Penthouse beams 2days 267,820.82 steelman=20 10- Bar Cutter
helper= 20
and slab

Installation of formworks for


carpenter=20
Roof deck and Penthouse 5.5days 207,421.92
beams and slab helper= 20

Installation of rough-ins for 1plumber 1helper


Roof deck and Penthouse 2days 75,200.00 electrician=5
electrical and plumbing helper=5

masons = 2
Pouring of concrete for Roof carpenters = 1 1 concrete mixer, 1
deck and Penthouse beam 1day 313,478.29 laborers = 4
vibrator, 1 pump crete
and slab vibratory operator
=1

Removal of formworks for


carpenter=20
Roof deck and Penthouse 1.5days 8,642.58 helper= 20
beam and slab
Fabrication of rebars for steelman=20
.5day 25,267.94 bar bending machine
Penthouse columns helper= 20
Installation of rebars for steelman=20
.5day 25,267.94 10- Bar Cutter
Penthouse columns helper= 20
Installation of formworks and
carpenter=20
scaffolds for Penthouse .5day 10,886.40
helper= 20
columns

masons = 2
carpenters = 1
Pouring of concrete for 1 concrete mixer, 1
Penthouse columns .5day 13,178.84 laborers = 4
vibratory operator vibrator, 1 pump crete
=1

Removal of formworks and


carpenter=20
scaffolds for Penthouse .5day 453.60 helper= 20
columns

Fabrication of rebars for 2nd


floor , 3rd floor, 4th floor, and steelman=20
3.5days 466,953.47 bar bending machine
Roof deck and Penthouse helper= 20
staircase
Installation of rebars for 2nd
floor , 3rd floor, 4th floor, and 3.5days 466,953.47 steelman=20 10- Bar Cutter
Roof deck and Penthouse helper= 20
staircase
Fabrication of formworks for
2nd floor , 3rd floor, 4th floor, 1.5days 25,503.36 carpenter=20
and Roof deck and Penthouse helper= 20
staircase

masons = 2
Pouring of concrete for 2nd
carpenters = 1
floor , 3rd floor, 4th floor, and 1 concrete mixer, 1
Roof deck and Penthouse 1.5days 471,021.60 laborers = 4 vibrator, 1 pump crete
staircase vibratory operator
=1

Removal of formworksfor 2nd


floor , 3rd floor, 4th floor, and .5day 1,062.64 carpenter=10
Roof deck and Penthouse helper= 10
staircase

Installation of CHB for walls masons=20


and firewalls 7.5days 677,291.71 helper=20

Installation of rebars for slab steelman=20


1.5days 100,872.02
of grade (SOG) helper= 20

Installation of rough-ins for 1plumber 1helper


Ground floor electrical and 4days 83,200.00 electrician=5
plumbing helper=5

masons = 2
carpenters = 1
Concreting of SOG .5day 151,854.98 laborers = 4 1 concrete mixer, 1
vibratory operator vibrator, 1 pump crete
=1

Fabrication of Penthouse welders=10


.5day 1,638.38 5 welding machine
Trusses helper= 10

Installation of Penthouse .5day 1,638.38 welders=10 5 welding machine


Trusses helper= 10

Installation of purlins, rafter, welders=10


.5day 2,976.12 5 welding machine
and fascia boards helper= 10

insulators=5
Insulation works 2days 120,000.00 helper=5

Roofing and Gutter Installation 2days 41,781.38 carpenter=2


helper= 2

Ceiling Works 1day 16,001.18 carpenter=2


helper= 2
Installation of electrical wires 9days 336,000.00 electrician=5
and fixtures helper=5
Installation of stairs and
balcony railings 1day 5,000.00 steelman=2

Installation of doors and carpenter=10


windows jamb 3days 133,461.50 helper= 10
Installation of doors , windows carpenter=10
3days 370,100.00
and looksets helper= 10
water proofer=10
Waterproofing works 7days 12,061.54
helper=10
masons=40
Plastering of walls 7.5days 568,335.30 helper=40
Installation of fire escape 1day 25,600.00 laborer=5 helper=5
ladder

Installation of water tank .5day 8,519.00 laborer=4 helper=4

Installation of plumbing 3days 60,000.00 plumber=1


fixtures helper=1
mason=20
Tile Works 1.5days 43,200.00 helper=20
Painting Works 5days 46,046.00 crew=10
Construction of septic tank, 5days 30,400.00 mason=3 helper=3 1 backhoe
cistern and catch basins

Installation of downspout 4.5days 13,464.00 labror=2

Construction of gate 2days 70,000.00 masons=10


helper=10
tester=1
Testing and Commissioning 1day 331,358.72
commisioner=1
Drainage, Permanent power,
labror=10
telephone and other services 2days 352,000.00
connection helper=10

Demobilization 2days 50,000.00 labor=2 Dumptruck,


carpenter=2
General Cleaning 1day 3,000.00 labor=6

TOTAL COST PHP 12,243,692.89


TOTAL FLOOR AREA 896.00 sq.m
COST PER AREA PHP 13,664.84 /sq.m.