Method Statement For Grouting Sonic Tubes of Bored Piles
Method Statement For Grouting Sonic Tubes of Bored Piles
SHEIKH JABER AL
AL-AHMAD
AHMAD AL-SABAH
AL SABAH CAUSEWAY
PROJECT (DOHA LINK)
TABLE OF C
CONTENTS
ONTENTS
1. Introduction
2. References
4. Material Plan
5. Construction Procedure
6. Construction Schedule
8. Attachments
DESIGN, BUILD, COMPLETION AND MAINTAIN
SHEIKH JABER AL
AL-AHMAD
AHMAD AL-SABAH
AL SABAH CAUSEWAY
PROJECT (DOHA LINK)
1.2 Purpose
urpose
The purpose of this method statement is to define the procedures to ensure that the proposed
materials, equipment, manpower, and workmanship to be employed by the Contractor for
grouting of sonic tubes of bored
bore piles is complying with the conditions and requirements of
of the
Contract RA/214 – Design, Build, Completion and Maintain of Sheikh Jaber Al-Ahmad
Al Ahmad Al
Al-
Sabah Causeway Project (Doha Link
Link).
1.3 Scope
cope of Works
The scope of this method statement includes the construction activities for grouting of sonic
cross hole logging (SCL) tubes for all bored piles.
piles
2. REFERENCES
In this method statement the following documents, standards, and codes shall be referenced (but
not limited to):
The Contractor will deploy the required manpower and equipment for the grouting activities for all
bored piles.
DESIGN, BUILD, COMPLETION AND MAINTAIN
SHEIKH JABER AL
AL-AHMAD
AHMAD AL-SABAH
AL SABAH CAUSEWAY
PROJECT (DOHA LINK)
3.1 Equipment
The ffollowing
ollowing equipment shall be used
used.
Mixing Plant
Grouting pump
Steel tank for storage of fresh water
Grouting pipe line
3.2 Manpower
4. MATERIAL PLAN
4.1 Cement
The cement to be used shall be in accordance with Clause 8.3.1 (Cement) of the Project’s
Particular Specifications.
Approved nonnon-shrink high strength grout shall be used. Refer to Attachment No. 2 for the
details of the admixture for the production of non-shrink,
non shrink, high strength grout.
4.3 W
Water
5. CONSTRUCTION PROCEDURE
5.1.1 General
- Cleaning
leaning the sonic tubes
- Mixing of grout
- Pumping of grout into sonic tubes
.
A steel or plastic pipe shall be lowered up to the bottom of the sonic tubes and water
will be pumped in order to remove any debris.
5.1.3 Mixing of G
Grout
Density : + 5 g/cm3
Flow Cone Test : 40~60 sec
Bleeding at 2 hours
hou : <4%
UCS @ 28 Days : >40 MPa.
MPa
6. CONSTRUCTION SCHEDULE
Grouting of sonic tubes shall start after carrying out sonic test and approval of test from
Consultant. The time required for
for completion of grouting is dependent on the depth and numbers
of tubes in the bored pile.
All material will comply with the requirements of the Project Specification.
Specification
The ffollowing
ollowing test shall be done to ensure the quality of grout.
Temperature
Flow Cone Test
UCS Strength at 28 Days
In order to perform the quality controls on the drilling fluid, the following instruments will be
used:
The quality tests of the grout shall be done for each batch
batch.
8. ATTACHMENTS
1 General Hazard
Lifting Accident caused Injury of people/worker 3 4 M a. To make sure all lifting devices 2 2 L Active
by falling object in proper condition.
b. To provide signalman.
signalman
c. To barricade the lifting area to
avoid entry of other people.
people
d. To ensure objects to lift are free
from loose materials. PM, CM,
e. To secure all cranes being CE, HSE
1-1
Mgr., HSE
equipped with overloading
Supervisor
alarm system.
f. Flagman (banks
( men)) shall be
used
g. Lifting objects are to be tied
with long rope during lifting
operations to avoid tumbling by
swing.
Movement of Accident caused Injury of people/worker 3 4 M a. Workers are careful to each 2 2 L Active
heavy machinery by turning of heavy other not to enter blind spot of PM, CM,
/ vehicle equipment CE, HSE
1-2 heavy equipment,
equipment, and indicate
Mgr., HSE
working area clearly.
Supervisor
b. Whenever heavy equipment
DESIGN, BUILD, COMPLETION AND MAINTAIN
SHEIKH JABER AL
AL-AHMAD AL-SABAH
SABAH CAUSEWAY
PROJECT (DOHA LINK)
2 Preparation works
DESIGN, BUILD, COMPLETION AND MAINTAIN
SHEIKH JABER AL
AL-AHMAD AL-SABAH
SABAH CAUSEWAY
PROJECT (DOHA LINK)
Likelihood of Occurrence
Potential Consequence
A(1) B(2) C(3) D(4) E(5)
Similar Similar Incident Happens Happens
incident incident has several several
Environ
Rating People Assets Reputation not occurred occurred times per times per
ment
known in in the in our year in year in
Country Country company company Project
No
0 No injury No effect No impact 1(L) 2(L) 3(L) 4(L) 5(L)
damage
Slight Slight Slight Slight
1 2(L) 3(L) 4(L) 5(L) 6(M)
injury effect damage impact
Minor Minor Minor Limited
2 3(L) 4(L) 5(L) 6(M) 7(M)
injury effect damage impact
Major Localise Localised Considera
3 4(L) 5(L) 6(M) 7(M) 8(H)
injury d effect damage ble impact
Single Major Major Major
4 5(L) 6(M) 7(M) 8(H) 9(H)
fatality effect damage national
Major
Multiple Massive Extensive
5 internation 6(M) 7(M) 8(H) 9(H) 10(H)
fatalities effect damage
al
Legend
= Low Risk (1-5) = Medium Risk (6-7)
7) = High Risk (8-10)
PEOPLE
EOPLE
RATING DESCRIPTION
Slight injury or health effects (including first aid case and medical treatment case) – Not affecting
1
work performance or causing disability.
Minor injury or health effects – Affecting work performance, such as restriction to activities
2
(Restricted Work Case). Limited health effects, which are reversible, example: skin irritation.
Major injury or health effects – Affecting work performance, such as Lost Time Injury, or need to
3 take days to recover (Lost Workday Case). Irreversible health damage without loss of life, examples:
examples:
noise induced hearing loss, chronic back injuries.
Single fatality or permanent total disability (including permanent Partial Disability) – From an
4
accident or occupational illness
ENVIRONMENT
NVIRONMENT
RATING DESCRIPTION
Slight effect – Local environmental damage. Within the fence and within systems. Negligible
1
financial consequences.
Minor effect – Contamination. Damage sufficiently large to attack the environment but not
2
irreversible. Single exceed
exceeding of statutory or prescribed criterion. Single complaint.
Local effect – Limited discharge of known toxicity. Repeated exceed
exceeding of statutory
statutory or prescribed
3
limit. Affecting neighbourhood.
Major effect – Severe environmental damage. The company is required to take extensive measures
4 to restore the contaminated environment to its original state. Extended exceeding
exceed of statutory or
prescribed limits.
Passive
assive effect –Persistent
Persistent severe environmental damage or severe nuisance extending over a large
5 area. In terms of commercial or recreational use or nature conservancy, a major economic loss for
the company. Constant, high exceeding
exceed of statutory or prescribed limits.
ASSETS
SSETS
RATING DESCRIPTION
0 Zero damage
3 Local damage – Partial shutdown (can be restarted but costs up to 100,000 US$)
US$
4 Major damage – Partial operation loss (1 week shutdown costs up to 500,000 US$)
US$
5 Extensive damage – Substantial or total loss of operation (costs in excess of 500,000 US$)
REPUTATION
EPUTATION
RATING DESCRIPTION
1 Slight impact – Public awareness may exist but there is no public concern.
Limited impact – Some local public concern. Some political attention with potentially adverse
2
aspects for company operations.
Considerable impact – Local public concern with attention in local media. Extensive political
3
attention. Adverse stance of government and/or action groups.
National impact – National public concern. Extensive adverse attention in the national media.
4 Regional / national policies with potential restrictive measures and / or impact on grant of licences.
Mobilisation of action groups.
San
ndeep W. Cho, Sang Pyo Kim, Dong Wan
Construction Manager HSE Manager Construction Manager
DESIGN, BUILD, COMPLETION AND MAINTAIN
SHEIKH JABER AL
AL-AHMAD
AHMAD AL-SABAH
AL SABAH CAUSEWAY
PROJECT (DOHA LINK)
A powdered admixture for the production of non-shrink, high strength grouts for post-tensioned cables
and fixing anchors or bolts in concrete or rock
Fig. 1
Section of sheath of post-tensioned cables filled with a cement paste showing bleeding water.
Fig. 2
Section of sheath of post-tensioned cables filled with a cement paste containing MasterRoc FLC 100. No bleed water
is observed.
®
MasterRoc FLC 100 (Formerly known as MEYCO Flowcable)
Type of cement Water % by Flow-Cone Test Bleed water Expansio Setting times
weight of EN 445 EN 445 n at 3
cement hours
Initial 30 (by volume) Initial Final
mins
OPC 34.5 15 17 less than 0-2% >3 hours <10
ASTM C-150 2% hours
Type 1
1 day 20-40N/mm²
28 days 50-70N/mm²
PRECAUTIONS NOTE
The temperature of walls and spaces where the Field service, where provided, does not constitute
grout is to be pumped should be between +5 and supervisory responsibility. For additional
+40°C for optimum results. If the temperature is information contact your local BASF
outside this range, consult your BASF-UAE representative.
representative. BASF reserves the right to have the true cause of
any difficulty determined by accepted test
MasterRoc FLC 100 is a chloride free product, methods.
which is specially important in the case of cables.
However, chlorides can be introduced into a mix if QUALITY AND CARE
brackish water or special types of cement are All products originating from BASF’s Dubai, UAE
used. Therefore, the use of drinkable water facility are manufactured under a management
(generally containing less than 40 mg/l of chloride) system independently certified to conform to the
and chloride-free cements (Cl lower than 0.06% by requirements of the quality, environmental and
weight of cement) is recommended. Though all occupational health & safety standards ISO 9001,
Portland, pozzolanic or slag cements may be ISO 14001 and OHSAS 18001.
employed, the use of Portland cement Type I and,
preferably, Type III, is recommended in cold Request and refer to recommended installation
weather.
procedures for MasterFlow grouts prior to use
STORAGE
Store out of direct sunlight, clear of the ground on * Properties listed are based on laboratory controlled tests.
pallets protected from rainfall. Avoid excessive ® = Registered trademark of the BASF-Group in many countries.
compaction. Do not use if the bag is damaged or
has been opened for more than 1 month.
SAFETY PRECAUTIONS
As with all chemical products, care should be
taken during use and storage to avoid contact with
the eyes, mouth, skin and foodstuffs (which can
also be tainted with vapour until product fully cured
or dried). Treat splashes to eyes and skin
immediately. If accidentally ingested, seek
immediate medical attention. Keep away from
children and animals. Reseal containers after use.
BASF_CC-UAE/Roc_FLC100_01_95/v1/12_13
The technical information and application advice given in this BASF publication are based on the present state of
STATEMENT OF our best scientific and practical knowledge. As the information herein is of a general nature, no assumption can be
RESPONSIBILITY made as to a product's suitability for a particular use or application and no warranty as to its accuracy, reliability or
completeness either expressed or implied is given other than those required by law. The user is responsible for
checking the suitability of products for their intended use.
Field service where provided does not constitute supervisory responsibility. Suggestions made by
NOTE BASF either orally or in writing may be followed, modified or rejected by the owner, engineer or contractor since
they, and not BASF, are responsible for carrying out procedures appropriate to a specific application.