Central Sector Damodar Valley Corporation (DVC)

The report provides a status update on the construction of various substations in India with voltage levels of 220kV and above. It includes information on the name and location of each substation, its voltage/capacity details, date of land acquisition, and percentage progress on civil works, material/equipment received and erected, and capacity tested/commissioned. The substations belong to various public and private sector transmission companies across different states in India. The report indicates the current status of each major ongoing substation construction project.

Uploaded by

Data Centrum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
260 views24 pages

Central Sector Damodar Valley Corporation (DVC)

The report provides a status update on the construction of various substations in India with voltage levels of 220kV and above. It includes information on the name and location of each substation, its voltage/capacity details, date of land acquisition, and percentage progress on civil works, material/equipment received and erected, and capacity tested/commissioned. The substations belong to various public and private sector transmission companies across different states in India. The report indicates the current status of each major ongoing substation construction project.

Uploaded by

Data Centrum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 24

REPORT INDICATING STATUS OF CONSTRUCTION OF SUB STATIONS (220 kV & ABOV

2020-21

Cummulative progress till date


Voltage Capacity
Sl Name of Date of Land Civil Materials / Materials / Capacity
Ratio (No.xMV Acquire Tested/
No Sub Stations Award d
works Equipments Equipments
(kV/kV) A) completed Received erected
Commissio
ned
(%) (%) (%) (MVA)
(%)

1. 2. 3. 4. 5. 6. 7. 8. 9. 10.
CENTRAL SECTOR
DAMODAR VALLEY CORPORATION ( DVC )
1 Burdwan GIS along with associated line 220/132 2x160 100 20 30 0
bays at Parulia S/s

2 Dhanbad (2 Auto-Xmer) 220/132 2x160 100 80 40 40

3 DSTPS ICT-II S/s 400/220 1x315 100 100 90 60

POWER GRID CORPORATION OF INDIA LIMITED ( P


1 Bhadla S/S 400/220 1000 100 15 0 0

Report generated through NPP 09/07/2020 16.33.14


2 Bhuj S/S 765/400 1x1500 100 60 50 35

3 Bhuj Substaion 400/220 1x1500 100 60 50 35

4 Dwarka -I (GIS) S/S 400/220 2000 100 99 98 95

5 Extn at Jeypore s/s 400/220 2x315 100 80 80 50

6 Extn at Meerut substation 765/400 1x1500 100 100 100 100


Report generated through NPP 09/07/2020 16.33.14
7 Extn at New Siliguri s/s (3rd ICT) 400/220 1x315 100 97 100 90
8 Fatehpur S/S 400/220 500 100 20 5 0

9 Jauljivi (GIS) s/s 400/220 2x315 100 85 80 60

10 Jeerat (New) S/s (PM-JTL -TBCB) 765/400 1x1500 100 60 90 18

11 Maithon S/S 400/220 500 100 99 99 99

Report generated through NPP 09/07/2020 16.33.14


12 Medinipur S/s (PM-JTL -TBCB) 765/400 2x1500 100 86 90 70

13 New Mariani S/S 400/220 2x500 100 68 48 35


14 North Trichur Substation 400/220 2x315 100 77 85 71

15 Raigarh and Pugalur HVDC Station 800 6000 100 96 89 83

16 Repl of 400/220kV Malda S/s (3x315- 400/220 370 100 80 90 55


2x500)

17 Saharanpur S/S 400/220 500 100 8 0 0

Report generated through NPP 09/07/2020 16.33.14


STATE SECTOR
BIHAR STATE POWER TRANSMISSION COMPANY LIMITE
1 Dumraon (GIS) s/s 220/132 480 0 0 0 0
2 Mokama S/S 220/132 420 0 0 0 0
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD
1 Kurud (Dhamtari) S/S 400/220 2x315 100 89 100 100

DELHI TRANSCO LIMITED ( DTL )


1 Patparganj (Addl.) 220/33 1x100 0 0 0 0
2 Sanjay Gandhi Transport Nagar (SGTN) 220/66 2x160 100 90 90 90
GIS
ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR ( ED,
1 Thoubal S/S 400/132 1x315 0 0 0 0

GUJARAT ENERGY TRANSMISSION CORP. LIMITED ( G


1 Babara (Dist. Amreli) S/S 220/66 320 100 0 0 0

2 Bhachunda GIS (Dist. Kutch) 400/220 500 100 0 0 0


3 Kalawad 220/66 1x160 100 0 0 0
HARYANA VIDYUT PRASARAN NIGAM LIMITED ( HV
1 Bakana S/s 220/66 2x160 100 82 72 65

2 Faridabad Sector-58 GIS 220/66 2x160 100 66 13 11

3 Faridabad Sector-78 GIS 220/33 2x100 100 60 20 10

4 Gurgaon Sector-69 GIS 220/33 2x100 100 62 95 13

5 Gurgoan Sector-107 GIS 220/33 2x100 100 31 2 2

Report generated through NPP 09/07/2020 16.33.14


6 Rajokheri S/s 220/66 2x160 100 82 100 80

7 Roj-Ka-Meo 220/66 2x160 100 31 22 11

8 Roj-Ka-Meo 220/33 1x100 100 49 46 10

HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD


1 Charor GIS (GEC-I) 220/33 1x100 0 0 0 0

2 Dehan s/s (GEC-I) 220/132 2x100 100 0 0


3 Sunda (Addl. T/F) (GEC-I) 220/66 1x100 0 0 0 0
4 Sunda S/S 220/132 2x100 0 0 0 0

JHARKHAND URJA SANCHAR NIGAM LTD. ( JUSN


1 Jainamore (Bokaro) S/S 220/132 4x100 100 90 100 90
2 Latehar GSS (PGCIL) 400/220/1 6x105+3 100 95 60 44
32 x100

Report generated through NPP 09/07/2020 16.33.14


3 Lohardaga GSS (PGCIL) 220/132 2x150 100 95 85 70

4 Patratu GSS (PGCIL) 400/220 2x315 100 75 80 60

J&K POWER DEVELOPMENT DEPARTMENT ( JKP


1 Delina (Augmentation ) 220/132 1x160
2 Kathua-II (Ghatti) 220/66 1x160
3 Lassipora (GIS) 220/33 1x160 0 0 0 0

KARNATAKA POWER TRANSMISSION CORP. LIMITED


Report generated through NPP 09/07/2020 16.33.14
1 Channagiri (Nallur/Benkikere) 220/66 2x100 100 60 90 90

2 Heggunje (Mandarthi) S/S 220/110 2x100 100 20 0 0

3 Hosdurga (Madure) 220/66 2x100


4 Mughalkod S/S (GEC-I) 220/110 2x100 100 0 0 0

5 Mylasandra GIS (Near Electronic city) 400/220 1x1500 100 35 10 0

6 Sira s/s 220/66 2x100


Report generated through NPP 09/07/2020 16.33.14
7 T. Gollahalli (Thimmansandra) S/S 220/66 2x100 100 80 95 93

KERALA STATE ELECTRICITY BOARD ( KSEB


1 Aluva 220/110 4x100 100 78 50 0

2 Chalakudy S/S 220/110 2x100 100 55 40 12

3 Chithirapuram S/S 220/66 2x100 100 0 0 0

4 Kunnamangalam S/S 220/110 2x100 100 30 2 0

MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LT


1 Amrapur (Pathardi) S/S 220/132 2x100 100 100 100 96

2 GIS Ulwe Node 220/22 1x100 100 0 0 0

3 Naghbid S/S 220/33 125 100 83 96 91

4 Narangwadi s/s 220/132 250 100 100 100 100

Report generated through NPP 09/07/2020 16.33.14


5 Uppalwadi Sub-Station 220/33 250 100 100 98 96

M.P. POWER TRANSMISSION CORPORATION LIMITED (


1 Barwaha S/S 220/132 1x160 100 81 16 16
2 Gorabazar S/S 220/132 1x160 100 100 70 70

3 Katni 400 kV S/S ( Addl. X-mer) 220/132 1x160


4 Kukshi S/S 220/132 1x160 100 100 78 60
5 Mandsaur (Sitamau) (GEC-I) 400/220 2x315 100 99 54 54
6 Nalkheda (Susner) (GEC) 220/132 2x160 100 71 27 27
7 Pithampur 400kV S/S (Addl. X-mer) 400/220 1x315 100 96 37 37
8 Sukha (Jabalpur) (Addl. T/F) 220/33 1x100 100 70 39 39
9 Udaipura S/S (Upgradation) 220/132 1x160 100 94 49 49
10 Ujjain (GEC-I) 400/220 2x315 100 100 66 66
11 Vidisha (Addl. X-mer) 220/132 1x160
ORISSA POWER TRANSMISSION CORPORATION LTD. (
1 Deogarh 220/33 1x40 100 90 90 80
2 Duburi (ICT-III) 400/220 1x315 100 75 90 65
3 Goda S/S 220/132/3 2x160 100 100 100 100
3
4 Gunupur 220/132 1x160 0 40 40 25
5 Joda S/S 220/132/3 1x160 100 100 100 100
3
6 Laphripara 220/33 2x20 100 85 90 80
7 Meramundali B 400/220 500 100 80 85 70

POWER TRANSMISSION CORP. OF UTTARAKHAND LTD


1 Baram (GIS) s/s 220/33 2x25 100 75 73 25
PUNJAB STATE TRANSMISSION CORPORATION LIMITED
1 Baja Khanna (Aug. of 100 MVA T/F 220/66 60 100 100 100 100
with 160 MVA T/F)
2 Banga (Upgradation of 132 KV S/Stn. to 220/132 1x100
220 KV S/Stn. )
Report generated through NPP 09/07/2020 16.33.14
3 Makhu (Addl. T/F) 400/220 500
4 Maur (Addl. T/F) 220/66 1x100 100 100 100 100
5 Tibber (Addl. T/F) 220/66 1x100
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED ( R
1 Aklera (Dist. Jhalawar) 220/132 1x160 100 95 99 85

2 Chhatargarh GSS (Upgradation) (GEC-I) 220/132 1x160 100 85 97 97

3 NPH Jodhpur S/S 220/132/3 2x160 100 100 100 100


3

TAMILNADU TRANSMISSION CORPORATION LTD. ( TANT


1 Ariyalur S/S 765/400 2x1500 100 65 55 55
2 North Chennai PS (GIS) 765/400 2x1500 100 85 50 30
3 Samayanallur S/S 230/110 2x100 100 100 100 95

4 TNEB HQ (GIS) (JICA) S/S 230/33 2x100 100 100 100 60

TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITE


1 Aug. at Hindupur 400/220 1x315 100 100 90 90

2 Aug.at Kalpaka -4th (500MVA) 400/220 500 100 20 0 0

3 Aug. at Manubolu (Nellore) 400/220 500 100 20 0 0

4 Betamcherla (GEC-I) 220/132/3 2x160 100 85 80 80


3
Report generated through NPP 09/07/2020 16.33.14
5 Mylavaram (GEC-II) 400/220 3x315 100 0 0 0

6 Pydibhimavaram S/S 220/132 3x100 100 85 90 90


Transmission Corporation of Telangana Limited ( TSTRAN
1 Banswada 220 2x100 0 0 0 0 0
2 Bowrampet S/S 220/132 2x160 0 0 0 0 0
3 Indravelly (Utnoor) S/S with Automation 220/132 2x100
System
4 Rayadurg (GIS) 400/220/1 1000 100 90 80 5
32
U.P. POWER TRANSMISSION CORPORATION LTD. ( UP
1 Azizpur S/s Shahjahanpur 220/132 2x160 100 32 24 14
2 Babina S/s (Jhansi) 220/132 2x160 100 56 63 16
3 Badaikala S/s Muzaffarnagar 220/132 2x160 100 55 62 45
4 Basti GIS 400/220 2x500+2 100 76 35 21
x200
5 Integrated Township Noida S/s 220/33 240 100 47 20 0
6 Jehta (Hardoi Road) S/s Lucknow 400/220 2x500 100 52 80 54
7 Jehta (Hardoi Road) S/s (Lucknow) 220/132 4x100 100 52 86 54
8 Nirpura S/s Baghpat 220/132 2x160 100 47 40 24
9 Phoolbagh S/s Kanpur 220/33 60 100 95 95 90

10 Sangipur S/s (Pratapgarh) 220/132 2x160 100 72 74 70


11 Vrindawan S/s 220/132 2x160
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMI
1 Baruipur GIS 220/132 2x160 100 22 10 0
2 Belmuri GIS 220/132 2x160
3 KLC (Augmentation) 220/132 1x80
PRIVATE SECTOR
ADANI POWER LTD. ( APL )
1 Badaun GIS (OBTL) 400/220/1 2X315+ 100 22 7 4
32 2X160
Report generated through NPP 09/07/2020 16.33.14
2 Dhanbad s/s (NKTL-TBCB) 400/220 2x500 0 0 0 0

STERLITE GRID LTD. ( SGL )


1 P.K. Bari S/S (NER-II TL- TBCB) 400/132 2x315 95 75 100 53
2 Surajmaninagar (NER-II TL -TBCB) 400/132 2x315 95 70 100 40

Report generated through NPP 09/07/2020 16.33.14


VE) IN RFD PROGRAMME DURING
As on 30-JUN-2020

Commissioning

Revised/ Tag Type Remarks


Original
Anticipated

11. 12. 13. 14.

)
AUG-20 AUG-20 RFD Order for execution placed on
06.11.18. Supply of materials,
Engineering activities & civil
work under process.However
order for supply of
Transformer placed on
04.06.19 and expected to be
commissioned by Aug'20

AUG-20 MAR-21 RFD The Transformer has been


successfully commissioned on
19.12.2019 and put on load on
21.12.2019. For 2nd Auto
transformer order placed on
04.06.19 and expected to be
commissioned by March,21.

APR-20 JUL-20 RFD 400KV infrastructure is ready


and its 220KV infrastructure is
under construction. ICT
charged from 400KV side on
23.05.18. Order for balance
work placed on 13.02.19 and
expected to be completed by
31st July,2020.

PGCIL )
JAN-21 DEC-20 RFD Award placed in Oct'19. Work
completely was at standstill
due to lockdown of the entire
country due to Corona
Pandemic. Civil work started.

Page 1 of 13
OCT-20 DEC-20 RFD Commissioning of 1st bank of
765 kV ICT in Aug'20 with
contingency plan and balance
assets by Dec'20 progressively.
Work was on hold due to
country wide lockdown
because of COVID-19
Pandemic. Now, work has
been resumed after Lockdown
3.0 with limited manpower.

MAR-21 DEC-20 RFD 2 nos. 400/220 KV 500 MVA


ICT commissioned in Oct'19.
Commissioning of 3rd 400 kV
ICT in Jul'20 and balance
assets by Dec'20 progressively.
Work was on hold due to
country wide lockdown
because of COVID-19
Pandemic. Now, work has
been resumed after Lockdown
3.0 with limited manpower.

JUN-20 DEC-20 RFD 220 KV GIS Charged in


March'20. 400 kV GIS
matching with line. Work
completely at standstill due to
lockdown of the entire country
due to Corona Pandemic.

JUN-20 SEP-20 RFD Award placed in Mar'17. Work


completely at standstill due to
lockdown of the entire country
due to Corona Pandemic. The
Ministry of Home Affairs on
24.03.20 invoked the National
Disaster Management act and
declared lockdown of the
entire country.

MAY-20 JUN-20 RFD Commissioned 07/20.


Page 2 of 13
MAY-20 NOV-20 RFD Award placed in Jun'17. Work
completely at standstill due to
lockdown of the entire country
due to Corona Pandemic. The
Ministry of Home Affairs on
24.03.20 invoked the National
Disaster Management act and
declared lockdown of the
entire country.
JAN-21 DEC-20 RFD Award placed in Aug'19.
Construction activities were
kept in abeyance due to
country wide lockdown for
prevention of COVID-19
spread. Works restarted as per
MHA guidelines.
JUL-20 DEC-20 RFD Due to poor road conditions,
supply of Transformer &
Reactor affected. Critical.
Construction activities were
kept in abeyance due to
country wide lockdown for
prevention of COVID-19
spread.Works restarted as per
MHA Guidelines.

FEB-21 OCT-20 RFD Award placed in Sep'17. Work


completely stopped w.e.f.
23.03.2020 due to lock down
for COVID-19 pandemic. In
line with MHA
order/guidelines, permission
for work sought from District/
State Admin. Clearance
received on 28.04.20. Work
restarted with limited
manpower. Work affected due
to cyclone AMPHAN on
20.05.20.

MAY-20 JUL-20 RFD Award placed in Dec'17. Work


was completely at standstill
due to lockdown of the entire
country due to Corona
Pandemic. Bay work is
completed, testing work under
progress.
Page 3 of 13
JUL-20 OCT-20 RFD Work was stopped from
Nov'19 - Dec'19 due to
agitation by local tribals.
Restarted slowly from
10.12.19. Work completely
stopped w.e.f. 23.03.2020 due
to lock down for COVID-19
pandemic. In line with MHA
order/guidelines, permission
for work sought from District/
State Admin. Clearance
obtained on 24.04.20. Work
restarted with limited
manpower. Work affected due
to cyclone AMPHAN on
20.05.20.

MAR-21 OCT-20 RFD Work progress affected due to


lockdown of the entire country
due to Corona Pandemic.
SEP-20 DEC-20 RFD Work was completely at
standstill due to lockdown of
the entire country due to
Corona Pandemic. Work
resumed as per MHA
guidelines.
AUG-20 SEP-20 RFD Work was completely at
standstill due to lockdown of
the entire country due to
Corona Pandemic. Work
resumed from last week of
Apr'20/ May'20.
JUN-20 AUG-20 RFD Award placed in Mar'17.
Shutdown awaited. Work
completely at standstill due to
lockdown of the entire country
due to Corona Pandemic. The
Ministry of Home Affairs on
24.03.20 invoked the National
Disaster Management act and
declared lockdown of the
entire country.

JAN-21 DEC-20 RFD Award placed in Oct'19. Work


was completely at standstill
due to lockdown of the entire
country due to Corona
Pandemic. Civil work started.

Page 4 of 13

ED ( BSPTCL )
AUG-20 RFD M/s BGCL
AUG-20 RFD M/s BGCL
D. ( CSPTCL )
MAY-20 JUL-20 RFD Work completed .S/s & 1 No.
315 MVA ICT charged on dtd.
31.01.2020

JUL-20 JUL-20 RFD


JUL-20 JUL-20 RFD

D, Manipur )
MAY-20 RFD Completed and equipment
testing in progress
( GETCO )
JUL-20 JUL-20 RFD NIT done on 23.10.17; Price
Bid Opened; Under approval

JUL-20 JUL-20 RFD Initial Stage.


JUL-20 JUL-20 RFD WIP
HVPNL )
MAY-20 JUN-20 RFD Work awarded to M/s HPL JV
Salasar. Work under Process.

MAY-20 OCT-20 RFD Work Awarded to M/s TBEA


Energy India Limited.
Contouring is in progress.
JUN-20 NOV-20 RFD work awarded to M/s TBEA
Energy India Limited, NH-8,
Village MiyagamKarjan,
Vadodara, Gujrat
MAY-20 MAR-21 RFD Contract has been awarded to
M/s Skippers Seil Ltd.

NOV-20 DEC-20 RFD Work awarded to M/S


Kalpataru.
Page 5 of 13
APR-20 JUL-20 RFD The work has been awarded to
M/s IKE Electric Pvt. Ltd.
Maharashtra JV M/s Deesan
Agro-Tech Pvt. Ltd, Mumbai
on dt-17.07.18. Site handed
over to the firm on 14.09.2018
and the civil work is in
progress

OCT-20 MAR-21 RFD Contract Awarded on


20.02.2019 to IKE Electric
Pvt. Ltd. Maharashtra.
OCT-20 MAR-21 RFD Contract Awarded on
20.02.2019 to IKE Electric
Pvt. Ltd. Maharashtra.
TD. ( HPPTCL )
DEC-20 OCT-20 RFD Design and Drawings approval
are under process.

DEC-20 OCT-20 RFD


DEC-20 DEC-20 RFD
DEC-20 DEC-20 RFD Substation is being constructed
with funds sourced from ADB.

SNL )
JUN-20 JUN-20 RFD All supply & erection work
completed. Cable laying work ,
Earthmat & Stringing work
under progress and expected to
be completed 31.03.2020.
JUN-20 JUN-20 RFD Civil and Erection works are in
progress(400 KV,200KV &
132 KV). Civil: - 400KV,200
KV & 132 kV Tower
foundation completed, 220 KV
Equipment foundations, 220
KV & 132 KV Switch Yard
Panel Room and 150 MVA &
315 MVA Transformer Plinth
with Rail Fixing completed.
Major Civil works are
completed.132 KV and 220
KV equipment Structures of
CB, CT, CVT, Isolator SA,
BPI, 220KV Tower & Beam
has been erected.

Page 6 of 13
APR-20 JUN-20 RFD Civil- Major Foudation works
completed. Boundary Wall Pre
cast, RCC Framed Masonry
Boundary Wall, Road works,
Switchyard Brick work drain
are in under progress. Erection
- 220 KV Tower Erection and
Beam completed, and other
equipment work are in
progress.

APR-20 JUN-20 RFD Earth work in cutting & filling


within S/S, RCC Framed
Masonry Boundary
Wall(barbed wire and
plantation pending), Control
Room Building, 400 KV &
220 KV Equipment, 315 MVA
ICT, FFPH Building, Fire
Wall, 400 KV Switch Yard
Panel Room & side cable
trench and Roadwork are in
Progress. Equipment Earthing,
Lattice Structure for 220 KV &
400 KV Tower Erection and
Standard Pipe Structure (400
KV side) are in Progress. 220
KV Bus stringing work
completed.

PDD )
DEC-20 RFD
DEC-20 RFD
DEC-20 RFD Work included in the draft
Transmission Plan. funding
agency to be identified.
D ( KPTCL )
Page 7 of 13
SEP-20 SEP-20 RFD CRB roof slab, Retaining wall,
cable duct and other finishing
work yet to be taken up.
Control room painting work
under progress. All major
equipments erected. Rigid
busbar and busbar
interconnection works under
progress. Equipment and
structure earthing work under
progress. Cable laying,
termination and testing to be
taken up yard lighting. CI pipe
earthing works under progress.

SEP-20 SEP-20 RFD Oil Sump plastering, Control


room building pedestal
concrete and plinth beam
completed. 10MVA
Transformer foundation
excavation & PCC work
completed. Welding & back
filling work, 11kV SWG shed
work, retaining wall SSM
work, control room building
wall construction, and cable
duct inside control room are
under progress.

SEP-20 RFD
DEC-20 AUG-20 RFD LOI issued on 03-Aug-19.
Land is handed over to the
agency on 14.08.2019. Activity
chart approved on 30-Aug-
2019.
OCT-20 OCT-20 RFD 400kV control room plinth
beam and 400kV GIS hall
plinth beam completed. 220kV
GIS hall basement-RCC wall
completed, shattering for
basement roof slab is under
progress. Earthmat formation,
Station tower foundation,
Transformer & Reactor
foundation, Excavation for
mounting structures works
under progress.

DEC-20
Page 8 of 13
SEP-20 SEP-20 RFD Major equipment erection
completed on 220 kV & 66kV
side. Cable laying completed at
220kV side. Earthing of
Equipments under progress.
Civil works, control room
finishing work & electrical
fittings under progress.

B)
APR-20 JUL-20 RFD Work awarded to M/s.
GET&D India Ltd. and work is
in progress.
APR-20 JUL-20 RFD Work awarded to M/s.
Seimens India Ltd and work is
in progress .
SEP-20 JUL-20 RFD Site levelling completing;
work awarded to M/s. Seimens
India Ltd.
MAY-20 JUL-20 RFD Work awarded to M/s.
GET&D India Ltd. and work is
in progress.
LTD. ( MSETCL )
JUN-20 JUL-20 RFD i) 04x132kV line bays,
01x132kV bus sectionaliser
bay, 132kV Main bus test
charged on dt 25.10.2019. ii)
cable laying of 220kV Side
completed, termination is in
progress.
DEC-20 RFD LOA issued recently. Soil
investigation is completed.
DEC-20 SEP-20 RFD All 132kV Bays and 220kV
Bays ( ICT, T/F, & BC) are
ready for charging. - 132kV
Busbar panel testing balance
due to faulty busbar auxiliary
relay, same is informed to GE.
GE engineer left site on dt.
15.05.2020. - Cable laying and
termination work is held up
due to termination gang left
site on dt. 22.05.2020.

DEC-20 NOV-19 RFD 100 MVA 220/33 kV ICT-I


back charged on 29.03.19.
ICT-II and 25 MVA,220/33 kV
T/F-I&II back charged on
30.07.19 .
Page 9 of 13
DEC-20 SEP-19 RFD ICT-I and ICT-II along with
220kV bus & PT backcharged
on 18-03-2019 & 220KV bays
(6 Nos) charged on
dt.28.03.2019.The 220/33 kv
50 MVA T/F is successfully
test charged on dtd.15.05.2019.
T/F-II back charged on
06/12/19.

( MPPTCL )
JUN-20 RFD Additional X-mer work
APR-20 RFD 63 MVA, 132/33 kV X-mer
charged on 21.03.2020
APR-20 RFD
DEC-20 RFD Work under progress.
DEC-20 DEC-20 RFD
DEC-20 RFD
OCT-20 RFD
SEP-20 RFD Additional X-mer
SEP-20 RFD
OCT-20 OCT-20 RFD
APR-20 RFD
. ( OPTCL )
JUL-20 DEC-20 RFD
SEP-20 MAR-21 RFD
JUL-20 JUN-20 RFD Commissioned 05/20.

DEC-20 RFD
JUL-20 JUL-20 RFD

JUL-20 DEC-20 RFD


DEC-20 MAR-21 RFD Voltage Ratio should be
400/220kV
D. ( PTCUL )
MAY-20 JUL-20 RFD WIP
ED ( PSTCL )
APR-20 JUN-20 RFD Commissioned 05/20.

APR-20 RFD

Page 10 of 13
NOV-20 RFD
APR-20 JUN-20 RFD Commissioned 05/20.
AUG-20 RFD
RVPNL )
OCT-20 SEP-20 RFD Electrical works: Work order
Issued to M/s Kay Cee Energy
and Infra Private limited, Kota
on Dated:-10.05.2018.

SEP-20 AUG-20 RFD NOA issued in favor of M/s


Kanohar. Wiring work under
progress.
JUL-20 DEC-20 RFD Work completed. Trf. Erected
and test charged from LV side
on dt 08.03.2020. Associated
line work under progress.

NTRANSCO )
SEP-20 SEP-20 RFD Work under progress.
NOV-20 DEC-20 RFD Work under progress.
JUN-20 JUL-20 RFD Works are nearing completion.

JUN-20 SEP-20 RFD 230KV GIS testing in


progress. 33KV VCB erection
in progress.
ED ( APTRANSCO )
MAY-20 JUN-20 RFD i) All PTR Bay Extension
works completed ii)ICT will be
alloted as per the load
requirement duly matching
with the commissioning
schedule of 220kV
downstream network
MAY-20 AUG-20 RFD Equipment foundation works
under progress.32 Nos out of
68 Nos Equipment foundations
completed.

MAY-20 AUG-20 RFD Equipment foundation works


under progress.36 Nos out of
52 Nos Equipment foundations
completed.

JUL-20 JUL-20 RFD Works are under progress.

Page 11 of 13
JUL-20 RFD Instead of constructing
seperate 400kV SS at
Mylavarm revised system
studies conducted for solar
power evacuation from solar
park at mylavaram by laying
220kV lines from pooling
stations to the existing 400kv
SS at Jammalamadugu.

JUL-20 JUL-20 RFD 90% of work completed.


ANSCO )
JUL-20 RFD
DEC-20 RFD
OCT-20 RFD

JUN-20 JUN-20 RFD

UPPTCL )
OCT-20 JUN-21 RFD work in progress.
JUN-20 DEC-20 RFD work in progress.
OCT-20 APR-21 RFD Work in progress.
SEP-20 FEB-21 RFD Work in progress.

AUG-20 RFD work in progress.


SEP-20 FEB-21 RFD work in progress.
OCT-20 RFD work in progress.
MAR-21 RFD work in progress.
SEP-20 RFD T/F-I 60 MVA charged on
15.11.2019
JUN-20 JAN-21 RFD work in progress.
OCT-20 RFD
MITED ( WBSETCL )
NOV-20 AUG-20 RFD Work under progress.
FEB-21 RFD
JAN-21 RFD

NOV-20 NOV-20 RFD Project progress affected due


to COVID-19.
Page 12 of 13
OCT-20 OCT-20 RFD project progress affected due
to COVID-19.

APR-20 JUL-20 RFD 1. 132kV transmission line has


to be constructed by TSECL
from P.K. Bari (TBCB) to P.K.
Bari (TSECL) to utilize the
system. 2. Allotment of 1.17
acres of Government land is
pending with Collector,
Unakoti 3. Delay due to
occurrence of Force Majeure
(FM) event i.e. outbreak of
COVID-19 and this FM event
has been intimated to all
LTTCs
APR-20 JUL-20 RFD 1. 132kV transmission line has
to be constructed by TSECL
from Surajmaninagar (TBCB)
to Surajmaninagar (TSECL) to
utilize the system. 2. Allotment
of 1.02 acres of Government
land is pending with Collector,
West Tripura 3. Delay due to
occurrence of Force Majeure
(FM) event i.e. outbreak of
COVID-19 and this FM event
has been intimated to all
LTTCs

Page 13 of 13