RATE ANALYSIS FOR: 12mm THK Internal Plaster 238 SQM Item No. Particulars Unit Quantity Rate Cost

This document provides a rate analysis for 12mm thick internal plaster over 238 square meters. It details the materials, labor, and other costs required. The total rate per square meter is 238 rupees, which includes the costs of cement, sand, labor charges for plastering and scaffolding, tools, contingencies, overhead charges, and contractor profit.

Uploaded by

rohan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
16K views1 page

RATE ANALYSIS FOR: 12mm THK Internal Plaster 238 SQM Item No. Particulars Unit Quantity Rate Cost

This document provides a rate analysis for 12mm thick internal plaster over 238 square meters. It details the materials, labor, and other costs required. The total rate per square meter is 238 rupees, which includes the costs of cement, sand, labor charges for plastering and scaffolding, tools, contingencies, overhead charges, and contractor profit.

Uploaded by

rohan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

RATE ANALYSIS FOR : 12mm thk Internal Plaster 238 Sqm

ITEM NO. PARTICULARS UNIT QUANTITY RATE COST


Providing & applying cement plaster 12mm thick in a
single coat in cement mortar 1:4 with out neeru finish
to concrete or brick / siporex wall surfaces, ceilings or
any other surfaces to its true line & level, plumb, right
angles
Detailsetc. at allfor
of Cost heights.
10 SqmThe- (CM
rate 1:4)
shall also include
providing, erecting & dismantling of steel scaffolding,
A Materials:
curing, complete etc. All as per directions of Engineer
Cement
– in –charge Bags 0.920 ASL Supplied 0.00

Sand Cum 0.146 1323.11 193.17


Wastage @ 3% 5.80
A 198.97
B Labour:
Labour Charges for plastering Sqm 10.00 160.00 1600.00
Add for scaffolding Sqm 10.00 10.00 100.00
Add for Chicken mesh, nails etc Sqm 10.00 10.00 100.00
B 1800.00
A+B 1998.97

Add for Sundries i.e. Tools, Plants and contingencies 39.98


@ 2%
2038.95
Add for WC & Electricity charges @ 1.5% 30.58
2069.53
Add for Contractor's Profit & OH @ 15% 310.43
Cost Per 10 Sqm 2379.96
Cost Per 1 Sqm 238.00
Cost Per Sqm (Roundup) = 238.00