Program (Project) Evaluation & Review Technique (Pert) : Shahid Ali Khawaj
Program (Project) Evaluation & Review Technique (Pert) : Shahid Ali Khawaj
earliest finish time (EF) The earliest start time for the activity plus the time required to complete the activity
(the earliest an activity can be completed)
earliest start time (ES) The earliest time an activity can start once the previous dependent activities are
completed
expected time, T E Calculated using O, M and P, the expected time is: 𝑇𝐸=(Optimistic + 4 x Most likely +
Pessimistic ) / 6
forward pass The process to determine the early start or early finish times for activities in the critical
path method
GANTT chart A diagram that shows each task in a project as a block of calendar time. Each block is
labelled with the task description and the amount of time the block represents
BASIC TERMINOLOGIES Cont.
latest finish time (LF) The latest time an activity can be completed without delaying the entire project
latest start time (LS) The latest finish time minus the time required to complete the activity
most likely time (M) The project manager should have a high degree of certainty that a task will be
completed within this time
optimistic time (O) The shortest time that an activity is likely to take – there will be a small probability
(less than 5%) of this happening
pessimistic time (P) The project manager should be almost certain (e.g. 99%) that the task will be
completed within this time
Program Evaluation Review An implementation of the Critical Path Method where the time for each task is
Technique (PERT) chart estimated by using a weighted average based on a probabilistic estimation of the
optimal, most likely and a pessimistic time to complete the task
▪ The main objective of PERT is to facilitate decision making and to reduce both
the time and cost required to complete a project.
▪ The activities are the tasks required to complete a project. The milestones are
the events marking the beginning and the end of one or more activities. It is
helpful to list the tasks in a table that in later steps can be expanded to include
information on sequence and duration.
DETERMINE THE PROPER SEQUENCE OF
THE ACTIVITIES
▪ This step may be combined with the activity identification step since the activity
sequence is evident for some tasks. Other tasks may require more analysis to
determine the exact order in which they must be performed.
CONSTRUCT A NETWORK DIAGRAM
▪ Make adjustments in the PERT chart as the project progresses. As the project
unfolds, the estimated times can be replaced with actual times. In cases where
there are delays, additional resources may be needed to stay on schedule and
the PERT chart may be modified to reflect the new situation.
BENEFITS
PERT is useful because it provides the following information:
▪ Expected project completion time;
▪ Probability of completion before a specified date;
▪ The critical path activities that directly impact the completion time;
▪ The activities that have slack time and that can be lend resources to
critical path activities;
▪ Activity start and end date.
PREREQUISITES