Project Management
Assignment # 1
Introduction & Definitions
Answer the following questions
Question 1
b) Explain briefly the five phases of a construction project and draw a bar chart
showing the sequence of these phases.
Question 2
Project Planning & Scheduling is a major topic in Project Management. Explain the
typical steps required to generate a Time Schedule for any construction Project.
Question 2
Draw the following network using Activity – On – Node (AON) for the following
project:
Activity Duration Depends on
A 2 --
B 5 A
C 7 A
D 9 B&C
Question 3
Draw the AON for the following project, Calculate the Early and Late times of
activities, Calculate Project Duration, Highlight the Critical Path on the network,
Calculate the Total Float for All activities, and Draw Bar based on early times:
Activity ID Depends on duration(weeks)
A --- 8
B --- 2
C A 5
D B 3
E B 12
F C, D 4
G C, D 6
Page 2 of 10 Dr. Yasser Elfahham & PM staff
Faculty of engineering Electric Engineering Department
Alexandria University
Project Management
Question 4
What is the Project duration (PDmin) for the next project by using Precedence
Diagramming Method (PDM)? Given that the Contract Duration (PDmax) = 45 days,
highlight and write the critical path.
Activity Predecessor (S) Quantity Production Rate
Units (Units/day)
A -- 1,000 200
B -- 500 150
C -- 700 300
D A 1,500 500
E A,B 2,200 220
F B 900 300
G E 1,750 750
H G 2,000 250
I F 5,000 800
J C,E 950 1,000
K J,H 777 140
Question 5
Duration
Activity ES LS
(week)
A 4 0 2
B 5 0 0
C 3 0 6
D 3 4 6
E 6 5 5
F 2 7 9
G 5 11 11
Question 2
For the project shown in the following table, you are required to:
1. Complete the missing data in the table
2. Draw the activity-on-node (AON) network if all Relations between activities are
FS=0. clarify the longest path on the network
activity Duration Early Early Late Late Total Free
(days) start finish start finish float Float
A 5 0 0
B 6 5 0
C 2 11 6
D 4 0 1
E 3 4 4
F 8 11 0
G 1 19 0
Page 4 of 10 Dr. Yasser Elfahham & PM staff
Faculty of engineering Electric Engineering Department
Alexandria University
Project Management
Assignment # 4
Project Calendar
Question 1
A security room project contains the following activities:
Activity ID A B C F
Activity Name footing R.C skeleton masonry finishing
Depends on --- A B C
Relationships SS=3
--- FS = 0 FS=2
&lag FF=5
Original
7 5 2 13
duration(day)
Given that the project starts on Monday, 1- 1 - 2018, the contractor considers Friday
and Saturday as weekends, and the period from 8 to 10 January 2018 is non- working
period. It is required to:
1. Calculate the CPM days and clarify the critical path on the network.
2. Calculate the project duration due to an increase of 3 days in the duration of
activity B
3. Calculate the activity dates considering the given calendar and draw the bar chart
using Calendar days.
Question 2
The following tables illustrate the data for the CPM diagram for a project. The project
start date is thursday1st March 2018; Workdays per week equal six, and the week start
on Saturday. It is required to find activity dates (ES, EF, LS, and LF)
Question 2
Draw the following network using AOA with the following data and Calculate the
Project duration:
Activity Depends on
A --
B --
C A
D B
E B
F A, B
G A
H D, G
I G
J H, I
Question 2
Draw the labor histogram based on early times.
Requirement:
1. Cash - Out flow (S - curve) considering Early times
2. Cash - Out flow (S - curve) considering Late times
Question # 2
The table shows the start and finish time for each activity in a construction project. The
activities costs and prices are also provided
Data: assume that a month has 30 days, calculations are prepared at the beginning
of each month.
It is required to:
1. Draw the cash Out flow (S-Curve)
2. Amount of money required after 3rd month
Question # 3
The activities for constructing an industrial workshop are listed in the next table