Jack Up Rig Satti Upgrade Plan

The document outlines the scope of work for installing an additional accumulator bottle rack and extending an existing platform on a jack up drilling rig. The contractor will install a new 14-bottle rack supplied by NOV next to the existing rack, requiring cutting, welding, and painting. The contractor will also extend the existing platform and relocate lighting and equipment to provide access to the new rack area per the supplied drawings. Inspections and testing will be conducted according to ABS and GOE standards.

Uploaded by

Kuna Stanbekov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
180 views6 pages

Jack Up Rig Satti Upgrade Plan

The document outlines the scope of work for installing an additional accumulator bottle rack and extending an existing platform on a jack up drilling rig. The contractor will install a new 14-bottle rack supplied by NOV next to the existing rack, requiring cutting, welding, and painting. The contractor will also extend the existing platform and relocate lighting and equipment to provide access to the new rack area per the supplied drawings. Inspections and testing will be conducted according to ABS and GOE standards.

Uploaded by

Kuna Stanbekov
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Upgrading Project of Jack Up

Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 1 of 6

Statement: The work described below shall be performed by the Contractor in accordance with the
Contract Agreement, and the requirements outlined below.

1. Introduction, Background and Summary


As per hydraulic volume calculation by NOV, additional accumulator bottle rack of 14 bottles to
be installed. NOV will supply accumulator skid with the same dimensions as original. New
location of the rack is beside of the existing.
In additional of skid installation, existing platform needs to be extended as preproposal to
provide access to junction boxes. Other details are shown below in detailed scope of work.

2. Applicable Rules, Codes and Standards


As per AA-103-010

3. General Specifications
As per AA-103-010

4. Names and abbreviations


As per AA-103-010

5. Owner Supplied Drawings and Data

File
Reference Rev. Date Description
Location
Additional Bottle rack installation with platform
O-JL-001 0 Attached
extension

M411-TG-H438-01 R4 Koomey unit platform and foundations

6. Owner Furnished Equipment (OFE)

Item Description Delivery Date


1 Accumulator bottle skid - NOV 05-May-2020

7. Builder Furnished Equipment (BFE)


The Contractor is to provide all scaffolding, fire cover, materials, labor, consumables, etc, unless
clearly noted otherwise, to effectively complete the entire scope of work in accordance with the
contract, specified Rules, Codes & Standards.

8. Detailed Scope of Work


➢ To cut and remove necessary items to allow installation of bottle rack and platform
extension
➢ To weld doublers and reinforcements below deck as per drawing O-JL-001
➢ Set up bottle rack by rigging gear and weld as per drawing O-JL-001
➢ To extend platform with handrail as per drawing O-JL-001
Upgrading Project of Jack Up
Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 2 of 6

➢ To relocate lighting fixtures as per proposal


➢ To relocate PAGA box as per proposal
➢ All paint damaged are needs to be painted as per Painting Rig Specification

9. Potential Conflicts/Special Considerations


The Contractor shall schedule activities relating to this scope so as to ensure minimum
interference with other scope activities in the area

10. Supporting Activities


All the penetrations through structures and bulkheads needs to be controlled by NDT
Paint damage to existing steel caused by cutting and welding for the new installation shall be
repaired as per as rig paint spec.
Contractor shall provide all necessary access platforms to complete the entire scope
Contractor shall provide transportation of the new material and equipment to the rig.
Contractor is responsible for the disposal of all debris and scrap materials.
Provide qualified fire watchmen.
Supply of all materials such as, piping, fittings, supports, brackets, clamps, nut and bolts, U
bolts, flanges, unions, joints, gaskets, etc are to be provided by the contractor , to complete the
work.

Note that this scope of work to be done in conjunction with other scopes of work.

11. Documentation Deliverables


Upon completion of the work, the Contractor shall supply three hard copies and two CD’s of a
quality package which shall include a build method statement, material certificates, applicable
welding procedure specifications, visual and dimensional inspection reports, NDE, coating
inspection reports and any other testing and commissioning reports as applicable.

12. Testing and Commissioning


All NDE and testing shall be as required by ABS and GOE

13. Inspection and Control Plan

ID Description Contractor Owner Class. Region Client Owner


QA PM
1 Fit up prior welding H
2 Welding W
3 Welding joints to primary structure R
3 Surface preparation for painting H
4 Painting – application of each layer W

H Holding point if work not accepted by entity shown


W Entity shown is called for witness
R Entity shown will receive copy of the report and
supporting documents (as applicable)
Upgrading Project of Jack Up
Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 3 of 6

14. Assumptions

Contractor shall comply with the safety rules and regulation of the rig.
All lifting shall be done by the CDC rig crew.
Contract to supply fire watch and Safety personnel for this work
Slings and shackles shall be certified for lifting

15. Photos
Upgrading Project of Jack Up
Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 4 of 6
Upgrading Project of Jack Up
Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 5 of 6
Upgrading Project of Jack Up
Author: John
AntosGuy
Dujic Ref: Q_8001/JL-220-001
Drilling Rig Satti
Installation of Accumulator Bottle rack with
Check By: Antos
John
Dujic
Guy Date: 28-OCT-2019
Koomey unit platform extension
Approved By: Jasna
JasnaFridel
Fridel Shipyard / Vendor Scope of Work Page: 6 of 6