Basic Electrical Design Calculations
Basic Electrical Design Calculations
In " Course EE-1: Beginners' Electrical Design Course " which is a preparation for
beginners in electrical design, I explained the following subjects:
1- The basic Concepts in electrical design (that every electrical designer must be
familiar with it).
Also, I listed the steps for electrical design process in the following two articles:
Electrical design process – part one
Electrical design process – part Two
Also, in " Course EE-2: Basic Electrical Design Course – Level I " which is the second
level for beginners in electrical design, I explained the following subjects:
1- How to determine the electrical requirements, needs and characteristics for any
building/project.
6- Solved examples.
7- ID-Spec software.
8- Preliminary electrical load estimation methods:
Space by space method,
Building method,
Area method.
Important!!!
Before proceeding with this new course, it is highly recommended to review
the previous two courses mentioned above.
Today, I will begin explaining the Third Course in electrical design series which is
" Course EE-3: Basic Electrical design course – Level II ", you can review the list of
contents of this course by click on its link.
I will begin with the first point; the branch circuit design calculations as follows.
1. Introduction
In low voltage distribution system, the power is transferred in the following manner:
Regardless of the wiring methods used for transferring electrical power, the
conductors carrying the power fall into one of two categories:
1. Feeders,
2. Branch-circuit conductors.
2. Difference between Service Conductors, feeders and Branch-circuit conductors
So, let’s know the difference between branch circuit and feeder as follows:
A- Service Conductors:
The conductors between the terminals of the electrical utility service equipment and
the main disconnect switch of the main distribution in the premises
The service conductor can be divided to (3) parts based on the service point as
follows:
1- Service Lateral: The underground conductors between the electrical utility service
equipment and the service point.
3- Service Drop: The overhead conductors between the utility electric supply system
and the service point.
Noting that The service point can be described as the point of demarcation between
where the serving utility ends and the premises wiring begins. The serving utility
generally specifies the location of the service point based on the conditions of service.
B- Feeder:
It is A conductor that originates at the main distribution or main disconnect device and
terminates at another distribution center, panelboard, or load center.
C- Branch circuit:
It is the portion of the wiring system extending past the final overcurrent device.
These circuits usually originate at a panel and transfer power to user load devices.
So, any circuit that extends beyond the final overcurrent protective device is called a
branch circuit (Some branch circuits originate at safety switches (disconnects)).
Example:
3. Essential definitions:
Some other definitions are essential to understanding branch circuits and feeders,
which are:
3.1 Service conductors: These conductors extend from the power company terminals
to the main service disconnect.
3.2 Sub-feeders: These conductors originate at distribution centers other than the
main distribution center and extend to panelboards, load centers, and disconnect
switches that supply branch circuits.
3.3 Panelboard: This can be a single panel or multiple panels containing switches,
fuses, and circuit breakers for switching, controlling, and protecting circuits.
The sum of the connected loads supplied by a feeder-circuit can be multiplied by the
demand factor to determine the load used to size the components of the system.
While, the sum of the maximum demand loads for two or more feeders is divided by
the diversity factor for the feeders to derive the Maximum Demand Load. Example:
Consider four individual feeder-circuits with connected loads of 250 kVA, 200 kVA, 150
kVA and 400 kVA and demand factors of 90%, 80%, 75% and 85% respectively. Use a
diversity factor of 1.5. calculate the Max demand load for the supply transformer.
Solution:
Calculating demand for feeder-circuits
The sum of the individual demands = 837.5 kVA If the main feeder-circuit were sized
at unity diversity:
For diversity factor of 1.5, a 600 kVA transformer could be used. This means that a
600 kVA transformer can be used instead of an 850 kVA when applying the 1.5 diversity
factor.
it is the power drawn from the supply circuit by a particular piece of equipment,
appliance, or luminaire (lighting fixture). A load can best be depicted as voltage drop.
Wherever there is voltage drop in an electrical circuit, there is a load being served.
The electrical load for and device/equipment can be expressed by (3) different ways
as follows:
1. Connected Load,
2. Calculated/Estimated Load,
3. Demand Load.
A- Connected Load:
Example:
A 60-watt light bulb connected to a 120- volt circuit will draw 1⁄2 ampere from the
voltage source.
This is the actual level of current flow obtained by dividing the 60 watts by the 120
volts
(60 watts/120 volts = .5 ampere) as required by the power formula. There is a load of
60 watts, or 1⁄2 ampere, on this circuit due to this one load.
The Total Connected Load: Many and various types of loads may be connected to the
same circuit and the total load for this circuit is determined by adding together all of
the connected loads.
B- Calculated/Estimated Load:
Examples:
1. The general lighting load is calculated from the total floor area of a
building.
2. A motor load is determined to be 125% of the motor’s FLA rating.
C- Demand Load:
The load remaining after the demand factors allowed by the NEC for a number of like
or similar loads have been employed.
Example:
A demand load reduction is allowed for the total load for the ranges of an apartment
building on the theory that not all ranges will be in use at the same time.
Demand loads apply when a load that is available to many areas of the structure will
not be fully loaded at the same time.
Example:
It is recognized by the NEC that not all of the outlets on all of the general use circuits
will be in use at the same time. Therefore, for dealing with feeders, the NEC allows
for de-rating of those loads to some lower level i.e. demand factors will apply only for
a group of loads originate from same distribution center.
A- Continuous loads: loads where the maximum current is expected to continue for 3
hours or more.
For more essential definitions, please view our Course " EC-1: Understanding NFPA 70
(National electrical code) course ".
B- Multi outlet branch circuit: A branch circuit with multiple loads which may be one
of two cases as follows:
If these loads are appliances and lighting loads, it will be called General
purpose branch circuit.
If these loads are appliances only, it will be called appliance branch circuit.
So, Appliance branch circuit: A branch circuit that supplies energy to one or more
outlets to which appliances are to be connected and that has no permanently
connected luminaires that are not a part of an appliance.
And, General purpose branch circuit: A branch circuit that supplies two or more
receptacles or outlets for lighting and appliances.
A- Two wire branch circuit: A branch circuit with one ungrounded conductors and one
grounded conductor.
Branch-circuit loads are classified According To Type of Load into five categories:
1. Branch-circuit Lighting loads.
2. Branch-circuit Receptacle loads.
3. Branch-circuit Equipment loads.
4. Branch-circuit Heating and cooling loads.
5. Branch-circuit Motor loads.
Today I will list additional types of branch circuits and explain the basic features for
any branch circuit as follows.
1- According to location
A- Indoor branch circuit:
It includes All branch circuits inside the premises for lighting, receptacles,
equipments, HVAC or other outlets.
The provisions for branch circuits supplying equipment listed in Table 210.2 amend or
supplement the provisions in this article and shall apply to branch circuits referred to
therein.
Also table 220.3 list the calculation of loads in specialized applications that are in
addition to, or modifications of, those Of general rules.
NEC code Chapters 5, 6, and 7 apply to special occupancies, special equipment, or
other special conditions. These chapters supplement or modify the general rules.
3- According to type of building
A- Dwelling Building
A building providing complete and independent living facilities for one or more
persons, including permanent provisions for living, sleeping, cooking, and sanitation.
B- Non-dwelling buildings
Conductors normally used to carry current shall be of copper unless otherwise noted.
The notation circular mils is used for Conductors larger than 4/0 AWG which will be
equal to 250,000 circular mils.
the notation MCM is used instead of circular mils, where MCM = 1000 circular mils.
so, a 250,000-circular-mil conductor was labeled 250 MCM.
the notation kcmil is used by both UL standards and IEEE standards instead of MCM.
where kcmil = MCM = 1000 circular mils.
Example
The circular mil area of a conductor is equal to its diameter in mils squared (1 in. =
1000 mils). What is the circular mil area of an 8 AWG solid conductor that has a
0.1285-in. diameter?
Solution
The rating of any branch circuit will be the maximum permitted ampere rating
or setting of the overcurrent device protecting this branch circuit.
Branch circuits serving only one device can have any rating, while a circuit
supplying more that one load is limited to ratings of 15, 20, 30, 40, or 50 amps.
Example:
A branch circuit wired with 10 AWG copper conductors has an allowable ampacity of at
least 30 amperes, If this branch-circuit overcurrent protective device is a 20-ampere
circuit breaker or fuse, what is the rating of this branch circuit?.
Solution:
the rating of this branch circuit is 20 amperes, based on the size or rating of the
overcurrent protective device.
The minimum number of branch circuits shall be determined from the total calculated
load and the size or rating of the circuits used. In all installations, the number of
circuits shall be sufficient to supply the load served.
I will explain the branch circuit design calculations as per the classification of branch
circuit according to type of load mentioned in Previous Article " Branch Circuit Design
Calculations – Part Two ".
Each lighting load is computed separately and then combined to determine the total
lighting load.
Also, I listed the (5) categories of Lighting Branch circuits, which were:
1. General lighting.
2. Show-window lighting.
3. Track lighting.
4. Sign and outline lighting.
5. Other lighting.
Today I will explain the design calculations for the general lighting branch
circuits as follows.
You can review the following previous articles for more information:
1.1 Definition:
General lighting outlets are those Outlets intended for general use for fixed-in-place
luminaires (lighting fixtures). They are only used for lighting for the normal use of the
occupants and Its intensity should be adequate for any type of work performed in the
area.
Determining the general lighting load as per NEC will be based on the load per area
method as follows:
The NEC cod introduce minimum general lighting loads (in VA/ft2) for various
types of buildings in Table 220.12.
Within the same building, there are normally several different types of areas
like storage, office, hallways, and cafeterias, these areas must be considered
separately if their (VA/ft2) values are available in table 220.12.
The general lighting load is calculated by multiplying the floor area (in ft2) of a
building by its unit load (in VA/ft2) derived from the above table.
If the load is continuous (as in Most commercial structures), the calculated load
is multiplied by 1.25 (the inverse of 80%) to determine the circuit requirements.
(Please review the definition for the term ―continuous loads‖ in Article)
The floor area for each floor shall be calculated from the outside dimensions of
the building, dwelling unit, or other area involved.
For dwelling units, the calculated floor area shall not include open porches,
garages, or unused or unfinished spaces not adaptable for future use (like some attics,
cellars, and crawl spaces).
Example#1:
A 25,000 ft2 office building is being designed. What is the general lighting load and
what load does the circuit need to supply?
Solution:
From Table 220.12, the unit load for an office building is 3.5 VA/ft2.
The general lighting load is determined by multiplying this value by the square footage
of the building:
The general lighting load = 3.5 VA/ft2 x 25,000 ft2 = 87,500 VA
So, the general lighting load is 87,500 volt-amperes.
However, the load is continuous and can only be 80% of the load supplied by the
circuit. This value must be multiplied by 1.25 to determine the circuit requirements:
The unit values herein are based on minimum load conditions and 100 percent
power factor (i.e. Load in VA = Load in Watt) and may not provide sufficient lighting
for the installation contemplated. So, the designer can choose a higher value based on
the existing design conditions.
Under any conditions, don’t use values less than that specified in table 220.12,
there are no exceptions.
The general lighting load unit values specified in table 220.12 includes the
following loads:
So, no need to add the above outlets in load calculations per NEC method.
The NEC method and table 220.12 are applied for any Additions to Existing
Installations for both dwelling and non-dwelling installations.
Energy saving–type calculations (which used to reduce the connected lighting
load and actual power consumption) are not permitted to be used to determine the
minimum calculated lighting load if they produce loads less than the load calculated
according to 220.12.
Example#2:
A (2) floors (basement and main) dwelling unit have dimensions as show in below
image. Calculate the total general lighting load for this unit and the Minimum Number
of General Lighting Branch Circuits.
Solution:
a- Basement area:
area ―A‖ = 17 FT 9 IN. X (4 FT 4 IN. + 18 FT 6 IN. + 6 FT 0 IN.) = 17 FT 9 IN. X 28 FT 10
IN. = 512.0 FT2
Note that as mentioned in notes for table 220.12, the crawl space and garage areas
are not considered as they are included in the NEC method calculation.
Step#2: The unit load listed in Table 220.12 shows 3 volt-amperes per ft2 for dwelling
units.
The general lighting load for the dwelling unit = 1816.5 ft2 x 3 watts per ft2 = 5449.5
watts
1.5 Notes for NEC method for calculation of lighting branch circuit load
Important!!!
The NEC doesn’t introduce a procedure for calculating the actual full load for
the individual lighting fixtures in a general lighting branch circuit.
If the required information for calculating the actual full load for every
individual lighting fixture in the circuit is available, in this time, you can calculate the
actual load for the lighting branch circuit by summing of actual full load for its
individual lighting fixtures.
In this case, you need to compare the values obtained from NEC method with
that obtained from actual load method and select the greater load value to be used in
the design.
But actually, The NEC method for calculation of lighting load is not required if
the actual full load for every individual lighting fixture in the circuit is determined.
Methods for determining the actual full load for every individual lighting fixture
in the circuit is explained in our course " Advanced Course for Lighting Design - Level
I " and I recommend reviewing these methods very well.
Section 220.18 (b) states that For circuits supplying lighting units that have
ballasts, transformers, autotransformers, or LED drivers, the calculated load shall be
based on the total ampere ratings of such units and not on the total watts of the
lamps. This means that we must take into account the losses in light fixture
switchgear (ballast, internal wiring, etc.) so, you must use the current rating of the
ballast, not the tube wattage.
Example#3:
A fluorescent lighting fixtures with 4 numbers 2 feet lamps, 18 watt/ lamp. Calculate
the actual load for this lighting fixture.
Solution:
So, we can’t know the actual losses, we will use the same equation in another form
The actual total load of fixture = 4 ballast x watt/ballast = 4 x 20 w = 80 watt
Example#4:
For the dwelling unit in example# 2 above, Calculate the Minimum Number of General
Lighting Branch Circuits.
Solution:
From example#2, the general lighting load for the dwelling unit = 5449.5 watts
However, the load is continuous and can only be 80% of the total load. This value must
be multiplied by 1.25 to determine the circuits requirements:
The total ampere = 6811.9 watts / 120 V = 56.77 A (note that , NEC method assumed
that PF=1)
Because it is not possible to have a partially powered electrical circuit that operates
properly, and because these are minimum units, the total number of branch circuits
with use of 15-ampere circuits is (4) circuits (3.78 circuits rounded up to 4 circuits)
and (3) circuits with use of 20-ampere branch circuits (2.84 circuits rounded up to 3
circuits).
1.7 Determination of maximum Permissible number of lighting fixtures on a
general lighting branch circuit
You need to review the definition for branch circuit rating explained in the previous
article " Branch Circuit Design Calculations – Part Two ".
Example#5:
A 4 feet long, two-lamp fluorescent fixture ballast draws 0.7 amps at 120 volts. How
many of these fixtures can be connected on a 20-amp circuit?
Solution:
This is a continuous load, so the current used by the lights can only be 80% of the
circuit current rating:
Allowable current = 20 A x 0.80 = 16 A
By dividing the allowable load by the load of each lamp, the total number of Fixtures
is determined:
Example#6:
In example#5, If some utilization equipment fastened in place will be added to the
circuit How many of these fixtures can be connected to the circuit?
Solution:
This is a continuous load, so the current used by the lights can only be 80% of the
circuit current rating:
Important!!
For good design, usually assume that the general lighting branch circuits will
have some utilization equipment fastened in place and must be derated to 50%
of its rating.
Lighting branch circuits that supply fixed lighting units with heavy-duty
Lampholders can have 30 A or 40 A ratings.
Lighting Outlets for heavy-duty Lampholders shall be calculated at a minimum
of 600 volt-amperes.
Use The above rules when it is applicable.
1. General lighting.
2. Show-window lighting.
3. Track lighting.
4. Sign and outline lighting.
5. Other lighting.
Also, in the previous Article " Branch Circuit Design Calculations – Part Three ", I
explained the following points:
Today I will explain the design calculations for other categories of lighting branch
circuits as follows.
You can review the following previous articles for more information:
Show Window: Any window used or designed to be used for the display of goods or
advertising material, whether it is fully or partly enclosed or entirely open at the rear
and whether or not it has a platform raised higher than the street floor level.
The Show-window lighting branch circuits are often used in commercial buildings.
As per section 210.62, At least one receptacle outlet shall be installed within 450 mm
(18 in.) of the top of a show window for each 3.7 linear m (12 linear ft) or major
fraction thereof of show window area measured horizontally at its maximum width.
1- To reduce the use of extension cords and floor receptacles which may cause
physical injury, the required receptacle outlet(s) installed within 18 in. of the top of
the show window. 2- Meaning of (12 linear ft) or major fraction is as follows:
If we have a show window with total length = 12 feet then, we will need one
receptacle,
If we have show window with total length = 13 feet (> 12) = 12 +1 then, we will
need (2) receptacles
If we have show window with total length = 5 feet (<12) then, we will need one
receptacle.
If we have show window with total length = 25 feet (> 12) = 2 x 12 +1 then, we
will need (3) receptacles
As per Sections 220.14(G) and 220.43(A), two options are permitted for the load
calculations for branch circuits serving show windows:
Option#1:
If the receptacle(s) required according to 210.62 supplies the show window lighting
load then the show window lighting load = 180 volt-amperes x number of receptacles
Option#2:
If the receptacle(s) required according to 210.62 don’t supplies the show window
lighting load then the show window lighting load = 200 volt-amperes x show-window
length (in feet) as shown in below image. And in this case: The show window total load
= load of receptacles + load of lighting = (180 VA X number of receptacles) + (200 VA x
show-window length (in feet)
Important!!!
If the maximum volt-ampere rating of the equipment and lights used for show
window lighting is known, then, calculate the show widow load as explained in
the above two options. then, you must select the greater load value to be used
for design of branch circuits and feeder.
Don’t forget …
The show window load is a continuous load and its value must be multiplied by
1.25 for determination of the circuit load requirements.
Important!!
If you need to determine the minimum number of feet of show window allowed
on a single branch circuit or/and maximum number of fixtures for a show
window, please follow the same procedure explained in previous article
" Branch Circuit Design Calculations – Part Two " for general lighting branch
circuit.
Example#1:
A department store has two lighted show windows, one 25 feet long and the other 20
feet long. What are the branch-circuit requirements for the show window load?
Solution:
Compute the load based on linear feet of show window:
Show-window load = 45 × 200 VA/ft = 9000 VA The lighting is a continuous load, so the
show window load is multiplied by 1.25 to determine the circuit load requirements:
Show-window load = 9000 VA × 1.25 = 11,250 VA
The circuits supplying power for the show-window lighting must have a minimum
capacity of 11,250 volt-amperes.
In addition, receptacles are required for every 12 feet of show window. A total of five
receptacles (two for the 20 feet window and three for the 25 feet window) are
needed. The receptacle load = 5 × 180 VA = 900 VA
The show window total load = 11,250 VA + 900 VA = 12,150 VA
3- Track Lighting
3.1 Definition:
From NEC section 410.2 the definition for track lighting is as follows: Lighting track is
a manufactured assembly designed to support and energize luminaires (lighting
fixtures) that are capable of being readily re-positioned on the track. Its length can be
altered by addition or subtraction of sections of track.
As per NEC section 220.43(B), an additional load of 150 volt-amperes shall be included
for every 600 mm (2 ft) of lighting track or fraction thereof.
Important!!!
As per Section 220.43(B) ,This method for calculations for Track Lighting Load
is applied for commercial buildings but it will not be applied for dwelling units
or guest rooms or guest suites of hotels or motels) because in these buildings
the track lighting load will not be added to the service load.
Example#2:
28 feet of track lighting is shown on the floor plans of a one-family dwelling. How
much additional load will this track lighting add to the service?
Solution:
In accordance with 220.43(B), no additional load is required for track lighting installed
in a dwelling unit.
Don’t forget …
If The Track lighting load is considered as a continuous load then its value must
be multiplied by 1.25 for determination of the circuit load requirements.
Important!!!
The actual track lighting fixtures are owner supplied, so, neither the quantity
of track lighting fixtures nor the lamp wattage is specified.
If the quantity of track lighting fixtures and the lamp wattage are known, then
calculate the total load of the track = quantity of track lighting fixtures x
number of lamps/fixture x lamp wattage, then, you must select the greater
load value to be used for design of branch circuits and feeder.
Important!!
The above design calculation method as per Section 220.43(B) is not intended
to determine the number of feet of track allowed on a single branch circuit
and/or the maximum number of fixtures on an individual track. If you need to
do this, please follow the same procedure explained in previous
article " Branch Circuit Design Calculations – Part Two " for general lighting
branch circuit.
Example#3:
A lighting plan shows 62.5 linear ft of single-circuit track lighting for a small
department store featuring clothing. What is the minimum calculated load associated
with the track lighting that must be added to the service or feeder supplying this
store?
Solution:
The minimum load for the lighting track that is added to the service and/or feeder
calculation is 4800 volt-amperes.
As per 220.43(B) exception, If the track lighting is supplied through a device that
limits the current to the track (a supplementary over-current protective device that
may be fuse or circuit breaker), the load shall be permitted to be calculated based on
the rating of the device used to limit the current.
I.e. the track lighting total load = voltage x device rating (Amps)
Example#4:
For department store in example#2, the entire length of the used track will be
supplied by a single 20-ampere, 120-volt branch circuit.
What is the minimum calculated load associated with the track lighting that must be
added to the service or feeder supplying this store?
Solution:
According to the exception to 220.43(B), the minimum calculated load to be added to
the service or feeder supplying this track light installation is calculated as follows: The
track lighting total load = 120 V x 20 A= 2400 VA
The minimum load for the lighting track that is added to the service and/or feeder
calculation is 2400 volt-amperes.
Branch Circuit Design Calculations – Part Five
In the previous article in our new course " Branch Circuit Design Calculations – Part
Two ", I listed the (5) categories of Lighting Branch circuits, which were:
1. General lighting.
2. Show-window lighting.
3. Track lighting.
4. Sign and outline lighting.
5. Other lighting.
Also, in the previous Article " Branch Circuit Design Calculations – Part Three ", I
explained the following points:
I explained how to design the show window and track lighting loads in the previous
article " Branch Circuit Design Calculations – Part Four".
Today I will explain the design calculations for sign and outline lighting branch
circuits as follows.
You can review the following previous articles for more information:
4.1 Definition
Sign and outline lighting illumination systems include, but are not limited to:
Sometimes due to size restrictions or other logistical factors, the electric sign can be
constructed in multiple factory-wired subassemblies (Section sign) that can be
assembled at the sign-installation location. The definition for section sign will be as
follows:
The Code includes several sections applicable to sign and outline lighting:
As per section 600.5 (A), At least one dedicated sign and outline branch circuit must
be provided for each commercial Space at each entrance of a commercial building /
occupancy accessible to pedestrians.
Important!!!
Sometimes, the designer may assign A group of branch circuits supplied by a
dedicated feeder for one sign lighting only, if there is need for installation of
aLarge sign with higher loads than that specified by section 220.14 (F) in below
and that usually be a multi section sign as described in the definitions in above.
The term ―dedicated‖ in above means that the branch circuit for sign and
outline lighting will not supply any other load.
Service hallways or corridors shall not be considered accessible to pedestrians,
no sign and outline lighting branch circuits will be added there.
The loads for branch circuits of sign and outline lighting shall be added in the
design stage of new commercial buildings for each commercial space as per 600.5 (A),
because it is not convenient to add it later when the space is occupied or when a new
occupant moves into an existing space.
Branch circuits that supply neon tubing installations shall not be rated in excess
of 30 amperes.
Branch circuits that supply all other signs and outline lighting systems shall be
rated not to exceed 20 amperes.
Important!!!
Large signs often have load requirements that exceed the ratings permitted
bysection 600.5(B) will be divided to group of branch circuits supplied by a
feeder which is not limited by the rating specified in 600.5(B).
Important!!!
In some cases, particularly for signs installed along highways, a utility
servicededicated to the sign is provided. The rating of the feeder or service is
not limited by the rating specified in 600.5(B).
As per NEC section 220.14 (F) , Sign and outline lighting outlets shall be calculated at a
minimum Load of 1200 volt-amperes for each required branch circuit specified in
600.5(A).
Important!!!
Section 220.14(F) assigns 1200 volt-amperes as a minimum circuit load for the
signs and outline lighting branch circuit, but If the actual load for a sign and
outline lighting unit is known to be larger than 1200 VA, then the actual load is
used for calculation purposes.
Fig.2
Important!!!
Sign and outline lighting shall be considered to be continuous loads and must
be multiplied by 1.25 for the purposes of feeder and protection calculations.
As per section 600.6, each sign and outline lighting unit must be controlled by
an externally operable and dedicated disconnecting means (switch or circuit
breaker) that opens all ungrounded Conductors simultaneously as shown
in Fig(2)above.
a- Location:
As per section 600.6(A), the following conditions shall be applied:
Fig.3
as in example#1 & 2 in Fig (3) above, The disconnecting means shall be within
sight of the sign or outline lighting system that it controls. and as in example#3 in Fig
(3) above, Where the disconnecting means is out of the line of sight from any section
that is able to be energized, the disconnecting means shall be capable of being locked
in the open position.
For signs or outline lighting systems operated by mechanical or
electromechanical controllers located external to the sign, the disconnecting means is
required to be located within sightof (as in example# 2&3 in Fig (3) above) or in the
same enclosure as the controller and must be capable of being locked in the open
position.
b- Rating:
As per 600.6(B), The switch or flasher (not a circuit breaker) required to control the
primary circuit of a transformer supplying a luminous gas tube, must have a current
rating that is at least twice the current rating of this transformer.
Important!!!
A disconnecting means shall not be required for cord-connected signs with an
attachment plug.
Example#1:
A hardware store measures 80 feet × 120 feet. A portion of the building (80 feet × 40
feet) is used for storage. The remainder of the building is used as a showroom. There
is a total of 45 feet of show windows, and there is one outdoor sign. What is the total
lighting load for this building?
Solution:
Each type of lighting load is computed separately and then combined to determine the
total lighting load.
Now the total lighting load of the building can be calculated by adding the parts
together:
Total lighting load of the building = 20,000 VA + 9000 VA + 1200 VA = 30,200 VA
These loads are all continuous, so the total load is multiplied by a factor of 1.25 to
determine the circuit requirements.
5.1 Definition
The additional lighting loads are those loads not covered by NEC Code such as:
1. Security lighting,
2. Parking area lighting,
3. Sidewalk lighting,
4. Roadway lighting,
5. Stadium lighting,
6. Tunnel Lighting.
5.2 Rules applied for Calculation of additional lighting loads
Unfortunately, The NEC code don’t provide calculation rules for lighting types included
under these additional lighting loads.
So, all additional lighting loads are calculated using the actual load designed by
professional lighting programs and methods as explained in our course " Advanced
Course for Lighting Design - Level I ".
Important!!!
All Additional lighting loads should be computed separately from the general
lighting load and then added to the general lighting load.
Don’t forget…
These additional lighting loads are considered continuous loads where
appropriate and must be multiplied by 1.25 for feeder and overcurrent
protection calculations.
Receptacle Branch Circuit Design Calculations –
Part One
In the previous article " Branch Circuit Design Calculations – Part One " in our new
course " Course EE-3: Basic Electrical design course – Level II ", I indicated that
Branch-circuit are classified According To Type of Load into five categories:
I explained the design calculations for the first type: lighting branch circuits in the
following Previous Articles:
Receptacles are one of the most popular terms in the NEC code because of its
importance especially in dwelling units and also in non-dwelling units as it is the
device responsible for feeding power to most of equipments.
NEC code includes large number of rules that are assigning the receptacle
requirements for special locations, special loads, special installation methods and
etc.
1- Introduction
Receptacle: A receptacle is a contact device installed at the outlet for the connection
of an attachment plug.
Important!!!
The number of receptacle Outlets my not equal to the number of receptacles
installed on these outlets. For example, a duplex receptacle has two contact
devices on the same receptacle outlet. In this case number of receptacles = 2
while the number of receptacle outlets = 1.
Multi-outlet Assembly: are metal or nonmetallic raceways that are usually surface,
flush, or freestanding mounted designed to hold branch circuit conductors and
receptacles, assembled in the field or at the factory.
The definition of multi-outlet assembly includes a reference to a freestanding
assembly with multiple outlets, commonly called a power pole as shown in below
image.
There are many types of Receptacles that had been classified according to many
factors such as:
Important!!!
These Receptacle classifications are made as per NEC code, there will be other
receptacle classifications as per other codes like IEC and BS but in this course I
will explain that based on the NEC code only.
a- Receptacle for dwelling loads: receptacles used for normal loads in dwelling units
like general receptacles, Electric Dryers and Electric Cooking Appliances. These
receptacles will have a maximum ampere of 30 A and voltage less than 600 V.
b- Receptacle for Non-dwelling loads: receptacles used for special loads for non
dwelling units like welding machines, heavy lamp holders, sign and outline lighting,
Show Windows and Fixed Multi-outlet Assemblies (power poles). These receptacles will
have a maximum ampere of 60 A and voltage less than 600 V.
a- Indoor Receptacles: Receptacles that will be used inside the building where there
are no abnormal weather conditions, it is usually general purpose receptacles.
d- Damp and wet location Receptacles: Receptacles that will be used in damp and
wet locations like in kitchen and indoor swimming pools, it is GFCI type.
a- Polarized Receptacles: Receptacles that have wider neutral slot and narrower hot
slot, the wider prong on the polarized plug will permit it to be plugged in only with
the correct polarity. The narrower prong is the "hot" lead and the switch to the
appliance is placed in that lead, guaranteeing that no voltage will reach the appliance
when it is switched off. A non-polarized plug may have the switch in the neutral leg
and thus be a shock hazard even when it is switched off as shown in the below image.
b- Non-polarized Receptacles: These outlets have two slots (hot and neutral) of the
same width.
b- Straight blade Receptacles: A non-locking receptacle into which mating plugs are
inserted at a right angle to the plane of the receptacle face.
Important!!!
Don’t be confused between duplex and twins receptacles, the duplex
receptacles are two receptacles installed on the same outlet/yoke but the
twins receptacles are two receptacles installed on two different outlets/yokes
i.e. twin duplex receptacles = double duplex receptacle.
50 A- Receptacles 60 A- Receptacles
Important!!!
In dwelling units, the maximum rating of Receptacles will be 30 A while in Non-
dwelling it will be 60A.
347 347/600
480
600
1- GFCI Receptacle: A receptacle with a built in circuit that will detect leakage
current to ground on the load side of the device. When the GFCI detects leakage
current to ground, it will interrupt power to the load side of the device, preventing a
hazardous ground fault condition. They can be used in indoor and outdoor locations.
GFCI Receptacle
Important!!!
The use of GFCI Receptacles can be used as replacements for Un-grounded
receptacles where a grounding means does not exist.
Important!!!
A receptacle supplying only a permanently installed fire alarm or burglar alarm
system shall not be required to have ground-fault circuit-interrupter
protection.
Important!!!
AFCI Receptacle must be installed to be the first receptacle outlet of the
branch circuit.
4- Switched Receptacle: A receptacle with built-in switch designed to turn on and off
the power for the connected equipment to that Receptacle.
16- According to Receptacle Usage
Important!!!
general use - outdoor receptacle outlets are not required for commercial,
institutional, and industrial occupancies, but as exception, outdoor receptacle
outlets shall be installed at an accessible location for the servicing of heating,
air-conditioning, and refrigeration equipment as per NEC 210.63 or at the
discretion of the designer or owner. This receptacle is required to be provided
with ground-fault circuit-interrupter protection. While an outdoor receptacle
outlet shall not be required at one and two-family dwellings for the service of
evaporative coolers.
1- Pin and sleeve (industrial) Receptacle: A Receptacle with round pin-type contacts
intended to mate with a connector having hollow cylindrical female contacts.
2- Hospital grade Receptacle: A receptacle designed to meet the performance
requirements of high-abuse areas typically found in health care facilities. These
receptacles are tested to the Hospital Grade requirements of Underwriters
Laboratories Inc. Standard 498.
Note: Outlets in damp or wet locations should always be installed with weather-
resistant covers.
10- Split circuit receptacles: A split receptacle has two outlets with each wired on a
different circuit or with one outlet live and the other switched. With a split receptacle
you can have a wall switch to turn a light on or off or remotely control one plug-in
location but not the other. Most duplex receptacles provide break-off tabs that allow
them to be converted into split-circuit receptacles.
b- Receptacles marked “AL-CU”: these receptacles will be used only with copper
conductors or copper-clad conductors.
b- Branch Circuit, Individual: A branch circuit that supplies only one utilization
equipment via a single receptacle.
Important!!!
A branch circuit supplying one duplex receptacle that supplies two cord-and-
plug-connected appliances or similar equipment is not an individual branch
circuit.
Today I will explain some basic principles and features of Receptacle branch circuits
before proceeding with the design calculations of such type of circuits.
Multiple Branch Circuits: are two or more branch circuits supply devices or equipment
on the same yoke.
while,
Branch Circuit, Multiwire: A branch circuit that consists of two or more ungrounded
conductors that have a voltage between them, and a grounded conductor that has
equal voltage between it and each ungrounded conductor of the circuit and that is
connected to the neutral or grounded conductor of the system.
What do you notice from the two definitions?
If we have two devices to be fed from two different receptacle outlets
installed on the same yoke, so we will need two different branch circuits, then we
have 4-wires(2 hot and 2 grounded) provided to this yoke. In this case we have a
multiple branch circuit.
But if we supply the same with a multiwire branch circuit, we will have 3 wires
only (2 hot, one common grounded)
Don't Forget….
There is difference between receptacle device and receptacle outlet as
explained before in the previous article.
Using three wires to do the work of four (in place of two 2-wire circuits),
Less raceway fill,
Easier balancing and phasing of a system,
Less voltage drop.
1- All conductors of a multiple branch circuit shall originate from the same panelboard
or similar distribution equipment.
For examples:
For a single-phase installation, the disconnecting means could be two single-
pole circuit breakers with an identified handle tie or a two-pole circuit breaker, as
shown in Fig.1 (top), or by a 2-pole switch, as shown in Fig.1 (bottom).
Fig (1)
Opening the neutral could cause unbalanced voltages, and a considerably higher
voltage would be impressed on one part of a multiwire branch circuit, especially if the
downstream line to- neutral loads were appreciably unbalanced.
Fig (2)
2- GFCI protection basics
Important!!!
As per NEC 406.5(G), A receptacle shall not be combined in enclosures with
other receptacles, snap switches, or similar devices, unless they are arranged
so that the voltage between adjacent devices does not exceed 300 volts or
unless they are installed in enclosures equipped with identified, securely
installed barriers between adjacent devices.
2.1 Definition:
As in image below that shows a typical circuit arrangement of a GFCI which operates
in the following procedure:
The line conductors are passed through a sensor and are connected to a shunt-
trip device.
As long as the current in the conductors is equal, the device remains in a closed
position.
If one of the conductors comes in contact with a grounded object, either
directly or through a person’s body, some of the current returns by an alternative
path, resulting in an unbalanced current.
The toroidal coil senses the unbalanced current, and a circuit is established to
the shunt-trip mechanism that reacts and opens the circuit.
Important!!!
The use of GFCI Receptacles can be used as replacements for Un-grounded
receptacles where a grounding means does not exist.
Important!!!
A receptacle supplying only a permanently installed fire alarm or burglar alarm
system shall not be required to have ground-fault circuit-interrupter
protection.
Important!!!
GFCIs do not protect persons from shock hazards where contact is between
phase and neutral or between phase-to-phase conductors.
1. portable types,
2. plug-in types,
3. circuit-breaker types,
4. types built into attachment plug caps,
5. receptacle types.
Each type has a test switch so that units can be checked periodically to ensure proper
operation.
Important!!!
All combined GFCI with receptacles must be readily accessible to be
periodically tested, by pressing the test button on the device and verify that all
receptacles protected through that GFCI device are de-energized.
3.1 Definitions:
From the above definition, the uses for such devices are for:
1. De-energizing the branch circuit when an arc fault is detected.
Also, AFCI devices may have the capability to perform other functions such as:
1. Overcurrent protection,
2. Ground-fault circuit interruption
3. Surge suppression.
Important!!!
AFCI devices must be tested to verify that arc detection is not unduly inhibited
by the presence of loads and circuit characteristics that may mask the
hazardous arcing condition.
Important!!!
AFCI devices must be tested for unwanted tripping due to the presence of
arcing that occurs in control and utilization equipment under normal operating
conditions or to a loading condition that closely like to an arcing fault, such as
a solid-state electronic ballast or a dimmed load.
1. Branch/feeder AFCI,
2. Combination AFCI,
3. Cord AFCI,
4. Outlet AFCI,
5. Portable AFCI.
The product standard requires specific marking on AFCI devices to indicate the type of
protection provided.
Important!!!
To provide the full range of AFCI protection covered in the UL standard for the
branch-circuit conductors and at the outlets supplied by the branch circuit, use
the combination- type AFCI devices not the Cord AFCI devices.
1. For all 15- and 20-ampere, 120-volt branch circuits that supply outlets
including receptacle, lighting, and other outlets located throughout a dwelling
unit except those outlets installed in kitchens, bathrooms, unfinished
basements, garages, and outdoors (in this case GFCI will be used).
2. For shared circuits like circuit that feed a bedroom and other areas such
as closets and hallways.
Important!!!
There is no prohibition against using AFCI protection on other circuits or
locations other than those specified in 210.12(A).
As per 210.12(B), the branch circuit shall be protected by one of the following:
Also, in the previous article " Receptacle Branch Circuit Design Calculations – Part
Two ", I explained basic principles, GFCI protection and AFCI protection for receptacle
branch circuits.
Today, I will explain the Receptacle Branch circuit calculations for both Dwelling and
Non-dwelling buildings as follows.
First: Receptacle Branch circuit calculations in dwelling buildings
1- Essential definitions:
In no case shall the load exceed the branch-circuit ampere rating. The following are
the permissible Receptacle Branch circuit ratings in dwelling buildings:
2- Only utilization equipment: with condition that the combined load for all
utilization equipment must not exceed the branch circuit rating.
Important!!!
Using fastened-in-place equipment is not permitted for the small-appliance
branch circuits, laundry branch circuits, and bathroom branch circuits
required in a dwelling unit and these branch circuits shall supply only their
receptacle outlets required by the code.
B) 30-Ampere Branch Circuits
Important!!!
A single receptacle installed on an individual branch circuit shall have an
ampere rating not less than that of the branch circuit.
A 40- or 50-ampere branch circuit shall be permitted to supply cooking appliances that
are fastened in place in any occupancy.
a Receptacle shall not supply a total cord-and plug- connected load in excess of the
maximum specified in Table 210.21(B)(2).
4- Voltage ratings for Receptacle Branch circuit
In dwelling units the voltage rating for Receptacle Branch circuit shall not exceed the
following:
For Receptacle Branch circuit that supplies Cord-and-plug-connected loads 1440 volt-
amperes, nominal, or less or less than 1⁄4 hp.
As per NEC section 220.14(I), Receptacle outlets load (see below image) shall be
calculated at not less than:
Step#1: Determine the maximum circuit power by Multiply the branch circuit
voltage and amperage.
Step#2: Then divide by 180 volt-amperes.
The result from Step#2 = the Max. Allowable single, duplex or triplex receptacles or a
combination of them on a branch circuit.
Example#1:
How many receptacles can be placed on a 120-volt, 20-amp circuit? How many can be
placed on a 120-volt, 15-amp circuit?
Solution:
Step#1:
Determine the maximum circuit power (for 20-amp circuit) = 120 V × 20 A = 2400 VA
Determine the maximum circuit power (for 15-amp circuit) 120 V × 15 A = 1800 VA
Step#2:
So,
6- The Minimum number of receptacle branch circuits for bank or office buildings
As per NEC section 220.14(J), if the number of receptacles is unknown so for bank and
office buildings, we can calculate the receptacles load by multiplying the area in ft2
by the unit value (1 VA/ft2).
To get the required number of receptacle branch circuits for bank or office buildings
make the following steps:
Step#1: Calculate the total receptacles load for the whole building as
explained above.
Step#2: Calculate the total receptacle circuit load in VA by multiplying its
voltage by its amperage as follows:
1. For 15-A Branch circuits = 120 V × 15 A = 1800 VA
2. For 20-A Branch circuits = 120 V × 20 A = 2400 VA
Step#3: Divide the total receptacle load for the whole building by the
maximum load per circuit to determine the minimum number of circuits.
Example#2:
Determine the total receptacle load for an 80 ft × 120 ft office building? And
determine the number of 15-amp circuits needed to supply the load. Noting that the
number of receptacles is unknown.
Solution:
Step#1:
The number of receptacles is unknown, so a receptacle load of 1 VA/ft2 can be
calculated:
Area = 80 ft × 120 ft = 9600 ft2
Step#2:
To determine the number of circuits required, first calculate the allowable load for a
single circuit:
The allowable load for a single circuit = 120 V × 15 A = 1800 VA
Step#3:
Divide the total receptacle load by the maximum load per circuit to determine the
minimum number of circuits:
In the broad sense, Receptacle in dwelling units may serve one of the following loads:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
Important!!!
The wall space behind the swing of a door is included in the measurement.
This does not mean that the receptacle outlet has to be located in that
space, only that the space is included in the wall-line measurement.
Important!!!
A receptacle controlled by a switch may result in the occupant using an
extension cord, run from an outlet or device that is not controlled by a
switch, to supply appliances or equipment that require continuous power,
such as an electric clock. So, this receptacle not considered as general-use
receptacle.
Also, I stated that a Receptacle in dwelling units may serve one of the following
loads:
You can review the following previous articles for more information:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
the locations of General-use Receptacle Loads as per NEC section 210.52 is controlled
by eleven (11) Rules as follows:
Important!!!
The primary objective of the requirements covering any of the dwelling
areas included in 210.52 is to minimize the need to use extension cords to
supply utilization equipment.
Important!!!
The wall space behind the swing of a door is included in the measurement.
This does not mean that the receptacle outlet has to be located in that
space, only that the space is included in the wall-line measurement.
Rule#2: electric baseboard heaters built-in receptacle (see below image)
Important!!!
A receptacle controlled by a switch may result in the occupant using an
extension cord, run from an outlet or device that is not controlled by a
switch, to supply appliances or equipment that require continuous power,
such as an electric clock. So, this receptacle not considered as general-use
receptacle.
Rule#7: hallways
As per NEC section 210.52(H), In dwelling units, hallways of 3.0 m (10 ft) or
more in length shall have at least one receptacle outlet.
The hallway length shall be considered the length along the centerline of
the hallway without passing through a doorway.
Important!!!
Rule#7 does not apply to common hallways of hotels, motels, apartment
buildings, condominiums, and similar occupancies.
Rule#8: foyers
As per NEC section 210.52(I), Foyers that are not part of a hallway in
accordance with 210.52(H) and that have an area that is greater than 5.6
m2 (60 ft2) shall have a receptacle(s) located in each wall space 900 mm (3
ft) or more in width and unbroken by doorways, floor-to-ceiling windows,
and similar openings.
Rule#9: Bathroom
Important!!!
As per NEC section 406.9(C), it is prohibited to install a receptacle within or
directly over a bathtub or inside a shower stall even if the receptacles are
installed in a weatherproof enclosure.
Important!!!
As per NEC section 210.11(C)(3), At least one 20-ampere branch circuit shall
be provided to supply bathroom receptacle outlet(s). This circuit is
permitted to supply the required receptacles in more than one bathroom as
show in above image (bottom).
Important!!!
If the circuit supplies the required receptacle outlet in only one bathroom,
it is allowed to also supply fastened-in-place equipment (lighting and an
exhaust fan) in that bathroom, provided the lighting and fan load does not
exceed 50 % of the branch-circuit ampere rating as per NEC section
210.23(A)(2).
For a one family dwelling and each unit of a two-family dwelling that is at
ground level, at least one receptacle outlet accessible while standing at
grade level and located not more than 2.0 m (6.5 ft) above grade shall be
installed at the front and at the back of each dwelling.
For each dwelling unit of a multifamily dwelling where the dwelling unit is
located at grade level and provided with individual exterior entrance/
egress, at least one receptacle outlet accessible from grade level and not
more than 2.0 m (6.5 ft) above grade shall be installed.
Important!!!
The receptacle outlet required for Balconies, Decks, and Porches can also
be used to meet the above outdoor receptacle requirements of One-Family,
Two-Family and Multifamily Dwellings.
Important!!!
Where detached garages are not supplied with electricity, receptacle
outlets do not have to be installed.
1.2 Calculation of general-use receptacles load
Example#1:
Solution:
No additional load calculation is required for these general-use receptacle loads, the
additional load to be added = Zero.
B- For branch circuit requirements (conductor ampacity & size and over-current
protection) calculation
This will be explained in coming articles, however you can review the calculation for
maximum number of allowable receptacles on a branch circuit and the minimum
required number of branch circuits for a dwelling building which were discussed before
in previous article " Receptacle Branch Circuit Design Calculations – Part Three ".
1.3 How to specify the required Type of general-use receptacles for each area?
1- Grounding type:
As per NEC section 406.4, Receptacles installed on 15- and 20-ampere branch circuits
shall be of the grounding type.
2- GFCI type:
As per NEC section 210.8 (A), all 125-volt, single-phase, 15- and 20-ampere
receptacles are GFCI for the following locations:
C- Unfinished basements
Unfinished basements are defined as portions or areas of the basement not intended
as habitable rooms and limited to storage areas, work areas, and the like.
All The receptacles in a work area of a basement, as shown in image below Rule#11,
must be GFCI type.
Important!!!
If the basement has some finished areas such as sleeping rooms or family
rooms, then all receptacles in such areas will not required to be GFCI
type as shown in image below Rule#11.
D- Crawl spaces
All receptacles installed in crawl spaces (at or below ground level) must be GFCI type.
E- Kitchens
I explained in above rule#5 that a general-use receptacle branch circuits must be
added to kitchens to serve Receptacles installed for disposals, dishwashers, and trash
compactors. These receptacles are not required to be GFCI type. The same is for
receptacle(s) installed behind a refrigerator to supply that appliance, not the
countertop, and will not be GFCI type.
H- Boathouses
Boathouse is A shed adjacent to a house at the edge of a river or lake used for housing
boats.
3- Weatherproof type
As per NEC section 406.9, the weatherproof feature is allowed for the following
locations:
A- Damp locations
All 15- and 20-ampere, 125- and 250-volt receptacles installed in a damp location shall
have an enclosure that is weatherproof whether or not the attachment plug cap is
inserted.
B- Wet locations
All 15- and 20-ampere, 125- and 250-volt receptacles installed in wet locations shall
have an enclosure for the receptacle that is weatherproof. A receptacle suitable for
wet locations shall also be considered suitable for damp locations.
Important!!!
Receptacle, located under roofed open porches, canopies, marquees, and
the like, and will not be subjected to a beating rain or water runoff, shall
be not weatherproof type.
the below image summarize the weatherproof features in all cases as per NEC section
406.9.
4- Tamper-Resistant type
Tamper-Resistant receptacles are intended to increase safety for children. All non-
locking type 125- volt, 15- and 20-ampere receptacles shall be listed tamper resistant
receptacles. the below image show the method of operation for Tamper-
Resistant feature:
The Receptacles in the following locations shall not be required to be tamper-
resistant:
1. Receptacles located more than 1.7 m (51⁄2 ft) above the floor (these
receptacles are not accessible and well out of reach of small children).
2. Receptacles that are part of a luminaire or appliance.
3. A single receptacle or a duplex receptacle located within dedicated
space for appliance that, in normal use, is not easily moved from one place to
another ( like dishwashers, refrigerators, washing machines, and the like )
5- AFCI type
All 15- and 20-ampere, 120-volt branch circuits that supply outlets including
receptacle, lighting, and other outlets located throughout a dwelling unit family
rooms, dining rooms, living rooms, parlors, libraries, dens, bedrooms, sunrooms,
recreation rooms, closets, hallways, or similar rooms or areas shall be AFCI type.Other
outlets installed in kitchens, bathrooms, unfinished basements, garages, and outdoors
will not be AFCI type.
Please, note the following:
Shared circuits between a bedroom and other areas such as closets and
hallways must have AFCI protection.
There is no prohibition against using AFCI protection on other circuits or
locations other than those specified in 210.12(A).
The AFCI device to be located at the first outlet supplied by a branch circuit in the
following cases:
1. If the wiring method from the branch-circuit overcurrent protective
device to the outlet is metallic conduit or tubing.
2. If the wiring method from the branch-circuit overcurrent protective
device to the outlet is Nonmetallic conduit or tubing that is encased in not less
than 2 inch of concrete.
Important!!!
Another method for applying AFCI protection for branch circuit that require
such protection is by installing A listed combination-type AFCI located at the
origin of the branch circuit (in panelboard for example).
The following table will summarize the required receptacle type for each location in
dwelling units:
Also, in previous article " Receptacle Branch Circuit Design Calculations – Part
Three ", I stated that a Receptacle in dwelling units may serve one of the following
loads:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
You can review the following previous articles for more information:
There are many NEC rules that control the number, location and type of small
appliances branch circuits including:
All Receptacle Outlets In the kitchen, pantry, breakfast room, dining room,
or similar area of a dwelling unit which serve Portable appliances used at a
kitchen counter, such as toasters, coffee makers, skillets, mixers, and the
like and after applying exceptions made by rules#6.
Rule#3: Receptacle Outlets served by small appliances branch circuits
(see fig.1)
The small appliance branch circuits are not permitted to serve any other
outlets, such as might be connected to exhaust hoods or fans, disposals, or
dishwashers.
Rule#7: kitchen and dining areas counters receptacles other than that
used for small appliances (see fig.1)
Countertops may be found In kitchens, pantries, breakfast rooms, dining rooms, and
similar areas of dwelling units, these countertops have receptacle outlets which will
be distributed in the countertop space as per the following rules:
Important!!!
Rule#11 will apply for island and peninsular countertop (see fig.4) with a
short dimension of at least 12 in. and a long dimension of at least 24
in. Noting that the measurement of a peninsular- type countertop is from
the edge connecting to the non-peninsular counter.
Receptacle outlets shall be located on or above, but not more than 500 mm
(20 in.) above, the countertop.
Rule#14: Guest Rooms and Guest Suites in dwelling units and that are
provided with permanent provisions for cooking (see fig.6)
Guest rooms and guest suites that are provided with permanent provisions
for cooking shall have branch circuits installed in the cooking area to meet
the above rules#1 to #13.
Fig.6
2.4 Calculation of general-use receptacles load
As per NEC section 220.52(A), in each dwelling unit, the load shall be calculated
at 1500 volt-amperes for each 2-wire small-appliance branch circuit. this load will be
added for other loads to perform the feeder and service calculations.
B- For branch circuit requirements (conductor ampacity & size and over-current
protection) calculation
This will be explained in coming articles, however you can review the calculation for
maximum number of allowable receptacles on a branch circuit which was discussed
before in previous article " Receptacle Branch Circuit Design Calculations – Part
Three ".
2.5 How to specify the required Type of receptacles for small appliances
branch circuits?
1- GFCI Type
As per NEC section 210.8 A (6), where the receptacles are installed to serve the
countertop kitchen appliances around a kitchen sink must be GFCI Type. See fig.7.
Fig.7
Important!!!
I explained in rule#5 in previous article ―Receptacle Branch Circuit Design
Calculations – Part Five― that a general-use receptacle branch circuits must
be added to kitchens to serve Receptacles installed for disposals,
dishwashers, and trash compactors. These receptacles are not required to
be GFCI type. The same is for receptacle(s) installed behind a refrigerator
to supply that appliance, not the countertop, and will not be GFCI type.
Important!!!
According to 406.5(E), receptacles installed to serve countertops cannot be
installed in the countertop in the face-up position because liquid, dirt, and
other foreign material can enter the receptacle.
2- Tamper-Resistant type
Tamper-Resistant receptacles are intended to increase safety for children. All non-
locking type 125- volt, 15- and 20-ampere receptacles shall be listed tamper resistant
receptacles. The Receptacles in the following locations shall not be required to be
tamper-resistant:
Receptacles located more than 1.7 m (51⁄2 ft) above the floor (these
receptacles are not accessible and well out of reach of small children).
Receptacles that are part of a luminaire or appliance.
A single receptacle or a duplex receptacle located within dedicated space for
appliance that, in normal use, is not easily moved from one place to another ( like
dishwashers, refrigerators, washing machines, and the like )
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
Definition:
As per NEC section 550.2 Laundry Area is An area containing or designed to
contain a laundry tray, clothes washer, or a clothes dryer.
There are many NEC rules that control the location and load of Laundry branch circuit
including:
In each dwelling unit, a load of not less than 1500 volt-amperes shall be
included for each 2-wire laundry branch circuit installed.
Where additional laundry branch circuits are provided, they also are
calculated at 1500 volt-amperes per circuit.
Important!!!
If Rule#3 above is applicable, then no Laundry load will be added for feeder
calculation of each dwelling unit and the Laundry branch circuits load will
be added to the ―house load‖ panelboard.
B- For branch circuit requirements (conductor ampacity & size and over-current
protection) calculation
This will be explained in coming articles, however you can review the calculation for
maximum number of allowable receptacles on a branch circuit which was discussed
before in previous article " Receptacle Branch Circuit Design Calculations – Part
Three ".
3.4 How to specify the required Type of receptacles for Laundry branch circuits?
A- GFCI Type
The type of 15- or 20-ampere, 125-volt receptacle that is required to be supplied from
the laundry branch circuit will depend on the washing machine location as follows: a-
If the washing machine is located in the bathroom:
As per NEC section 210.8 A (1), There are no exceptions to the bathroom GFCI
requirement. So, the 15- or 20-ampere, 125-volt receptacle must be GFCI
protected. b- If the washing machine is located in the Laundry Area or in a
kitchen:
B- Tamper-Resistant type
Important!!!
If a dwelling unit doesn’t include a clothes dryer, no Load for clothes dryer
will be added for feeder calculation of this dwelling unit.
Important!!!
A combination of clothes washer and clothes dryer (see below image) will be
handled in calculations as it is a clothes dryer. But the branch circuit and
125V receptacle outlet for laundry is still required i.e. minimum Laundry
requirements is mandatory while clothes dryer requirements is not.
Important!!!
Kilovolt-amperes (kVA) shall be considered equivalent to kilowatts (kW) for
clothes dryer loads.
As per NEC section 220.54, the load for household electric clothes dryers in
a dwelling unit(s) shall be either 5000 watts (volt-amperes) or the
nameplate rating, whichever is larger, for each dryer served.
Important!!!
The NEC does not prohibit applying the full load of all dryers to a service
and/or feeder calculation especially when all the clothes dryers are in a
common Laundry area in a multi-family dwelling because It is possible that
all dryers will be operating at one time in a laundry facility. But when each
tenant has separate clothes dryer, it is unlikely that all dryers will be in
operation simultaneously. So, Table 220.54 Demand Factors for Household
Electric Clothes Dryers will be used.
In multifamily dwelling, where two or more single-phase dryers are supplied by a
3-phase, 4-wire feeder or service, follow the below steps:
Step#1: Assign the maximum number of dryers connected between any two
phases.
Step#2: The total number of clothes dryers between two phases = 2 x the
maximum number of clothes dryers connected between any two phases ---- (Result#1)
Step#3: 2-phase Total ―connected load‖ for clothes = totals of all the clothes
dryers loads x (Result#1) ----- (Result#2)
Step#4: Based on The total number of clothes dryers between two phases
(Result#1), assign the demand factor from Table 220.54.
Step#5: 2-phase Total ―demand load‖ for clothes dryers = (Result#2) X Demand
factor ----- (Result#3)
Step#6: service 3-phase Total ―demand load‖ = (Result#3) X 3/2
Example#1:
What is the minimum service load for a 4.7 KW combination clothes washer and dryer?
Solution:
A combination of clothes washer and clothes dryer will be handled in calculations as it
is a clothes dryer.
So, the minimum service load for a 4.7 KW combination clothes washer and dryer =
5000 watts = 5 KW
Example#2:
3-phase Dryer load without applying the 220.54 demand factor = 5500 VA x 10 = 55,000
VA
Step#1: The maximum number of dryers connected between any two phases is 4
Step#2: Twice the maximum number of dryers connected between any two phases is
used as the basis for calculating the demand load = 4 dryers x 2 = 8 dryers
Step#3: 2-phase Total ―connected load‖= 8 x 5500 VA = 44,000 VA Step#4: from Table
220.54, for 8 dryers, demand factor = 60%
Important!!!
If the service-entrance ampacity calculated by the optional method is less
than 100A, re-calculate with using the standard method.
Important!!!
In NEC Optional calculation method, for a multifamily dwelling, Table
220.84 ―Optional Calculations — Demand Factors for Three or More
Multifamily Dwelling Units‖ will be used if the following conditions are
verified:
1. If No dwelling unit is supplied by more than one feeder
2. Each dwelling unit is equipped with electric cooking
equipment.
3. Each dwelling unit is equipped with either electric space
heating or air conditioning, or both.
Important!!!
The optional calculation can be used, provided all of the conditions for using
table 220.84 listed above are met. Otherwise, the calculation for the
multifamily dwelling is performed by using standard calculation method.
Important!!!
In Optional calculation method, note the following:
The dryer load is not subject to an individual demand factor as required by
table 220.54 for NEC Standard calculation method.
The nameplate of the clothes dryer will be used, even if it is less than 5000
watts.
Step#1: Total ―connected load‖ for clothes dryers = sum of all nameplate
rating of clothes dryers loads in each dwelling unit---- (Result#1).
Step#2: Based on the total number of dwelling units in this building, assign the
demand factor from Table 220.84.
Step#3: 3-phase service Total ―demand load‖ for clothes dryers = (Result#1) X
Demand factor.
Example#3:
What is the one-family dwelling load contribution for a 4.5KW clothed dryer?
Solution: The minimum load using the NEC standard calculation method for a clothes
dryer = 5000 watts
The load using the NEC optional calculation method for a clothes dryer = nameplate
rating = 4500 watts
Example#4:
Find the solution for the same multi-family dwelling building in example#1 by using
the NEC optional calculation method.
Solution:
Step#1: Total ―connected load‖ for clothes dryers =5500 VA X 10 = 55,000
VA Step#2: from Table 220.84, For 10 dwelling units, the demand factor = 43 %.
Step#3: 3-phase service Total ―demand load‖ for clothes dryers= 55,000 VA x 0.43 =
23,650 VA Service ampacity = 23,650VA /(208 V X1.732) = 66 A < 100 A, So the
calculation must be repeated using NEC standard calculation method.
B- For branch circuit requirements (conductor ampacity & size and over-current
protection) calculation
This will be explained in coming articles, however you can review the calculation for
maximum number of allowable receptacles on a branch circuit which was discussed
before in previous article " Receptacle Branch Circuit Design Calculations – Part
Three ".
4.4 How to specify the required Type of receptacles for Clothes dryer load?
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
Definition:
Cooking Unit, Counter-Mounted is a cooking appliance designed for
mounting in or on a counter and consisting of one or more heating elements,
internal wiring, and built-in or mountable controls.(see below image)
There are many NEC rules that control the location and load of Household cooking
appliances including:
Rule#2: Guest Rooms and Guest Suites in dwelling units and that are
provided with permanent provisions for cooking(see below image)
Guest rooms and guest suites that are provided with permanent provisions
for cooking shall have branch circuits installed in the cooking area to meet
the all of the requirements for dwelling units contained in Parts I, II, and III
of Article 210.
Important!!!
A portable cooking appliance (e.g., cord-and-plug-connected microwave
oven or hot plate) is not a permanent cooking facility.
Important!!!
In most dwellings the countertop receptacle outlets supply more of the
portable cooking appliances than the wall receptacles in the kitchen and
dining areas, hence the requirement for the counter areas to be supplied by
no fewer than two small-appliance branch circuits.
Important!!!
Kilovolt-amperes (kVA) shall be considered equivalent to kilowatts (kW) for
Electric Ranges and Other Cooking Appliances.
Important!!!
When the kilowatt rating fraction is 0.5 or more, it must be rounded up to
the next whole kilowatt rating i.e. 14.5 KW up to a 15 KW and When the
fraction is less than 0.5, it can be dropped i.e. 14.4 KW dropped to 14 KW.
As per NEC section 220.55, The load for household electric ranges, wall-
mounted ovens, counter-mounted cooking units, and other household
cooking appliances individually rated in excess of 1.75 kW shall be
permitted to be calculated in accordance with Table 220.55.
Important!!!
The table 220.55 is not applicable for ranges rated more than 27 kW
because ranges rated more than 27 kW would not be considered household
ranges.
The service load for one household cooking appliance is permitted to be computed by
using either the nameplate rating of the appliance or Table 220.55.
In this case, Procedure for calculating the service demand load will be as follows:
Step#1: Look in Left column of Table 220.55 for the number of appliances = 1
Step#2: Follow the row (for number of appliances = 1) across to the appropriate
column A, B or C.
Column A is used where the rating of the appliance is less than 3½ kW
Column B is used where the rating of the appliance is 3½ kW through 8¾ Kw
Column C is used where the rating of the appliance not over 12-kW.
Example#1:
12-kW electric range will be installed in a one-family dwelling, what is the service
demand load for this range?
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=1.
Step#2: Follow the row across to the appropriate column which will be Column C
Example#2:
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=1.
Step#2: Follow the row across to the appropriate column which will be Column C
Step#3: In accordance with Column C, The maximum load required for one 9-kW range
when calculating a service or feeder is 8 kW.
Example#3:
Step#1: Look in the left column of Table 220.55 for the number of appliances=1.
Step#2: Follow the row across to the appropriate column which will be Column A
Step#1: Look in Left column of Table 220.55 for the number of appliances,
Step#2: Follow the row (for number of appliances given) across to the appropriate
column A, B or C.
Column A is used where the rating of the appliances (have same rating) is less
than 3½ kW.
Column B is used where the rating of the appliances (have same rating) is 3½
kW through 8¾ KW
Column C is used where the rating of the appliances (have same rating) is not
over 12-kW.
Step#3: Service demand load calculation
Example#4:
A 10-unit apartment building will have a 12-kW range in each apartment. What is the
service demand load these ranges?
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=10.
Step#2: Follow the row across to the appropriate column which will be Column C
Step#3: In accordance with Column C, for the number of appliances=10, the maximum
service demand will be 25 kW
Example#5:
What is the service demand load for 40 wall-mounted ovens with same 3-kW rating?
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=25.
Step#2: Follow the row across to the appropriate column which will be Column A
Example#6:
What is the service demand load for 40 ranges with same 10-kW rating?
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=40.
Step#2: Follow the row across to the appropriate column which will be Column C
Step#3: In accordance with Column C, for the number of appliances=40, the maximum
service demand will be 15 kW + 1 kW for each range.
So, the maximum service demand = 15 kW + number of appliances = 15 + 40 = 55 KW
Example#7:
What is the service demand load for 60 ranges with same 12-kW rating?
Solution:
Step#1: Look in the left column of Table 220.55 for the number of appliances=60.
Step#2: Follow the row across to the appropriate column which will be Column C
Step#3: In accordance with Column C, for the number of appliances=60, the maximum
service demand will be 15 kW + 0.75 kW for each range.
The procedure is the same as in case#2 for individual Appliance but Steps#1, 2 and
3 will be repeated for each Appliance as follows:
Step#1: Look in Left column of Table 220.55 for the number of appliances,
Step#2: Follow the row (for number of appliances given) across to the appropriate
column A, B or C.
Column A is used where the rating of the appliances (have same rating) is less
than 3½ kW.
Column B is used where the rating of the appliances (have same rating) is 3½
kW through 8¾ KW
Column C is used where the rating of the appliances (have same rating) is not
over 12-kW.
Step#3: Service demand load calculation
Step#4: Sum individual service demand loads to get the total service demand load.
Example#8:
What is the service demand load for ten 2.5-kW ovens, ten 3-kW ovens, ten 5-kW
cooktops and ten 6-kW cooktops?
Solution:
Step#2: Because 20 ovens fall within the limits of Column A, the demand factor is 35
%.
Step#2: Because 20 ovens fall within the limits of Column B, the demand factor is 28
%.
Step#3: The calculated demand for the cooktops = 110 × 28% = 30.8 KW
Step#4: Now add the results to find the total demand load = 19.25 + 30.8 = 50.05 KW
Example#9:
What is the service demand load for five 3.5-kW wall-mounted ovens, five 5-kW
counter-mounted cooking units and ten 8-kW ranges?
Solution:
Step#1: the total number of units (5 + 5 + 10 = 20).
Step#2: Because none of the appliances are rated less than 3½ kW or more than 8¾
kW, the demand factor will come from Column B.
So, the demand factor percent across from 20 units (28 percent).
Step#3:
Step#4:
Step#1: Calculate the service demand Load for such appliances whether falling under
Column A or B
Step#3: Choose the lowest value between steps# 1 and 2 to be the service demand
Load.
Example#10:
What is the service demand load for 6 ranges with same 8-kW rating?
Solution:
Using the optional method for household cooking appliances with ratings Over 1 3 ⁄4
kW through 8 3⁄4 kW
Step#1: Calculate the service demand Load for such appliances whether falling under
Column A or B
In accordance with column B, the demand factor for 6 nos. appliances is 43% , so the
service demand load = 6 x 8 x 0.43 = 20.64 KW
In accordance with column C, for 6 nos. appliances, the Max. demand load = 21 KW
Step#3: Choose the lowest value between steps# 1 and 2 to be the service demand
Load.
So, the service demand Load = the lowest value between steps# 1 and 2 = 20.64 KW
Case#4: Individual / group of Ranges with equal (same) ratings Over 12 kW through
27 KW
For ranges individually rated more than 12 kW but not more than 27 kW, the
calculation procedure will be as follows:
Step#1: Calculate the maximum demand for the given number of ranges in Column C.
Example#11:
What is the service demand load for one 14-kW household electric range?
Step#3: the increased demand amount = Step#1 x Step#2 x 0.05 = 8x2x0.05 = 0.8 KW
For ranges individually rated more than 8 3⁄4 kW and of different ratings, but
none exceeding 27 kW, the calculation procedure will be as follows:
Step#1: Calculate the maximum demand for the given number of ranges in Column C.
Step#2: Calculate the Average Rating = sum of all appliances rating (using 12 kW for
any range rated less than 12 kW) / number of appliances
Example#12:
What is the service demand load for five 13-kW, five 15-kW and five 17-kW household
electric ranges?
Solution:
Step#4: the increased demand amount = Step#1 x Step#3 x 0.05 = 30x3x0.05 = 4.5 KW
Solution:
Step#2: the Average Rating = [(8 × 12) + (6× 13) + (6 × 15) / 20 = 13.2 KW
Notes:
Use 12 kW for any range rated less than 12 kW
13.2 KW will be dropped to 13 KW
Step#4: the increased demand amount = Step#1 x Step#3 x 0.05 = 35x1x0.05 = 1.75
KW
Important!!!
If the service-entrance ampacity calculated by the optional method is less
than 100A, re-calculate with using the standard method.
Important!!!
In NEC Optional calculation method, for a multifamily dwelling, Table
220.84 ―Optional Calculations — Demand Factors for Three or More
Multifamily Dwelling Units‖ will be used if the following conditions are
verified:
1. If No dwelling unit is supplied by more than one feeder
2. Each dwelling unit is equipped with electric cooking
equipment.
3. Each dwelling unit is equipped with either electric space
heating or air conditioning, or both.
For multifamily dwellings without electric cooking range (using gas cooking
ranges or other and may use electrical range in future) do the following:
1. Calculate the load of multifamily dwellings as per NEC
standard method
2. Calculate the load of multifamily dwellings as per NEC optional
method with adding electric cooking (based on 8 kW per unit)
3. Select the lowest load.
Important!!!
The optional calculation can be used, provided all of the conditions for using
table 220.84 listed above are met. Otherwise, the calculation for the
multifamily dwelling is performed by using standard calculation method.
Example#14:
A multifamily dwelling has 20 dwelling units, One-half of the dwelling units are
equipped with electric ranges not exceeding 12 kW each and other half of ranges are
gas ranges. What is the service demand load for these ranges?
Solution:
In accordance with column C in table 220.55, Max. demand load for One Electric range
= 8KW
Step#1: Look in the left column of Table 220.55 for the number of appliances=10.
Step#2: Follow the row across to the appropriate column which will be Column C
Important!!!
The branch-circuit load for one household cooking appliance is permitted to
be computed by using either the nameplate rating of the appliance or Table
220.55.
Important!!!
Where counter-mounted cooking appliances like the one pictured in below
image are used with a separate wall oven, it is permissible to run a single
branch circuit, sized according to Note 4 to Table 220.55, to the kitchen and
supply each with branch-circuit tap conductors installed as specified in
210.19(A)(3), Exception No. 1.
Important!!!
If a single branch circuit supplies a counter-mounted cooking unit and not
more than two wall-mounted ovens, all of which are located in the same
room, the nameplate ratings of these appliances can be added and the total
treated as the equivalent of one range, according to Note 4 of Table 220.55.
Important!!!
Where two or more single-phase ranges are supplied by a 3-phase, 4-wire
feeder or service, the total load shall be calculated on the basis of twice
the maximum number connected between any two phases.
Important!!!
Exception to Rule#9, Conductors tapped from a 50-ampere branch circuit
supplying electric ranges, wall-mounted electric ovens, and counter-
mounted electric cooking units shall have an ampacity of not less than 20
amperes and shall be sufficient for the load to be served. As illustrated in
fig. , this exception permits a 20-ampere tap if the following four
conditions are met:
Household cooking appliances branch circuit conductor ampacity & size and over-
current protectionwill be explained in coming articles, however you can review the
calculation for maximum number of allowable receptacles on a branch circuit which
was discussed before in previous article " Receptacle Branch Circuit Design
Calculations – Part Three ".
5.4 How to specify the required Type and Rating of receptacles for household
cooking appliances?
B- GFCI Type
As per NEC section 210.8 A (6), where the receptacles are installed to serve the
countertop kitchen appliances (counter-mounted cooking units) around a kitchen sink
must be GFCI Type. See below image.
But the receptacle serves Supplemental equipment and lighting on gas-fired ranges
and ovens will not be GFCI type as in above image.
According to 406.5(E), receptacles installed to serve countertops cannot be installed
in the countertop in the face-up position because liquid, dirt, and other foreign
material can enter the receptacle
C- Tamper-Resistant type
Tamper-Resistant receptacles are intended to increase safety for children.
Receptacles located more than 1.7 m (51⁄2 ft) above the floor (these
receptacles are not accessible and well out of reach of small children).
A single receptacle or a duplex receptacle located within dedicated space for
appliance that, in normal use, is not easily moved from one place to another ( like
dishwashers, refrigerators, washing machines, and the like ).
In article " Receptacle Branch Circuit Design Calculations – Part Three ", I stated
that a Receptacle in dwelling units may serve one of the following loads:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
Definition:
The term appliance designates utilization equipment commonly built in
standardized types and sizes and installed as a unit to perform specific
function(S) such as clothes washing, air conditioning, food mixing, deep
frying, etc.
Important!!!
The load for an appliance is simply the ampere rating of that appliance
which may be indicated on its nameplate and will be used in branch, feeder
and service load calculations.
Important!!!
Kilovolt-amperes (kVA) shall be considered equivalent to kilowatts (kW) for
Fastened-in-place Appliances.
Important!!!
No derating is allowed when there are only one, two, three fastened-in-
place appliances.
Example#1:
A one-family dwelling will have two feeders supplied by the service. One feeder will
provide power to a water heater and two attic ventilation fans. The other feeder will
provide power to a dishwasher, a kitchen-waste disposer and a trash compactor.
Where the 75 % demand factor to be applied?
Solution:
Since only three appliances are on each feeder, it is not permissible to apply the 75 %
demand factor to either feeder load calculation.
The demand factor can be applied to the service load calculation because it will
supply power to six fastened-in-place appliances.
Example#2:
What is the appliance load contribution, for a house that has a 1.2 KVA dishwasher, a
0.76 KVA garbage disposer, a 1.1 KVA trash compactor and a 4.5 KVA water heater?
Solution:
Example#3:
A 4.5-kilowatt (kW), 240-volt (V) water heater will be installed in each unit of a four-
unit multifamily dwelling. The water heaters are the only fastened-in-place appliance
in this multifamily dwelling. One service will supply all four units. Using the standard
method, what is the service load (after applying the demand factor) for fastened-in-
place appliances?
Solution:
Each unit has only one fastened-in-place appliance, the 75% demand factor will not
apply to the feeder for each dwelling unit.
Important!!!
If the service-entrance ampacity calculated by the optional method is less
than 100A, re-calculate with using the standard method.
Important!!!
In NEC Optional calculation method, for a multifamily dwelling, Table
220.84 ―Optional Calculations — Demand Factors for Three or More
Multifamily Dwelling Units‖ will be used if the following conditions are
verified:
1. If No dwelling unit is supplied by more than one feeder
2. Each dwelling unit is equipped with electric cooking
equipment.
3. Each dwelling unit is equipped with either electric space
heating or air conditioning, or both.
Important!!!
The optional calculation can be used, provided all of the conditions for using
table 220.84 listed above are met. Otherwise, the calculation for the
multifamily dwelling is performed by using standard calculation method.
Important!!!
The fastened-in-place appliances Load including water heater is given, do
not include water heat load to the general load as per 220.82(B)(3)d . But if
the water heater was not included with the fastened-in-place appliances,
add the nameplate rating of the water heater to the general loads covered
in 220.82(B).
Example#4:
what is the optional method service load calculation for a one-family dwelling with the
following fastened-in-place appliances: a dishwasher rated 10 amperes (A) at 120 volts
(V); a horsepower, 120V kitchen waste disposer; a trash compactor rated 7.5A at 120V;
and a 4.5 kilowatts (kW), 240V water heater?
Solution:
The optional method service load = 1.2 + 1.176 + 0.9 + 4.5 = 7.776 KVA
Example#5:
Find the optional method service load calculation for a 12-unit multifamily dwelling
with each unit containing the following fastened-in-place appliances: a dishwasher
rated 10 amperes (A) at 120V; 9.8 A, 120V kitchen waste disposer, and a 4.5 kW, 240V
water heater.
Solution:
The fastened-in-place appliance load for each unit = 1,200 + 1,176 + 4,500 = 6,876 VA
The fastened-in-place appliance service load for the building = 12 x 6,876 VA = 82,512
VA
Apply the Table 220.84 (in below image) for demand factor, of Multifamily dwelling,
since there are 12 units, the demand factor will be 41%.
The optional method demand load for this building = 82,512 VA x 41% = 33,830 VA
B- For branch circuit requirements (conductor ampacity & size and over-current
protection) calculation
As per NEC section 220.14 (A), an outlet for a specific appliance or other
load not covered in 220.14(B) through (L) shall be calculated based on the
ampere rating of the appliance or load served.
Example#6:
Solution:
Since the rating on the nameplate is 10 amperes, the branch-circuit load for this
dishwasher is 10 amperes.
Important!!!
Using fastened-in-place equipment is not permitted for the small-appliance
branch circuits, laundry branch circuits, and bathroom branch circuits
required in a dwelling unit and these branch circuits shall supply only their
receptacle outlets required by the code.
Important!!!
Small loads, such as those of 1440 volt-amperes or less and motors of less
than 1⁄4 horsepower, are limited to 120- volt circuits.
Branch Circuit Design Calculations – Part Nine
In article " Receptacle Branch Circuit Design Calculations – Part Three ", I stated
that a Receptacle in dwelling units may serve one of the following loads:
1. General-use Receptacle Loads,
2. Small appliance Loads,
3. Laundry Load,
4. Cloth dryer Load,
5. Household cooking appliances load,
6. Fastened-in-place Appliance loads,
7. Heating and air conditioning loads,
8. Motor loads.
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
Definitions:
A heat pump (see below image) is a device that acts as an air conditioner in
the summer and as a heater in the winter. Heat pumps look and function
exactly like an air conditioner except it has a reversible cycle.
7.1 Applied NEC Rules for Heating and air conditioning loads
There are many NEC rules that control the Heating and air conditioning
loads including:
220.50 Motors
220.51 Fixed Electric Space Heating
220.60 Noncoincident Loads
220.82(C) Heating and air conditioning loads in Dwelling Unit
220.83 Existing Dwelling Unit
220.85 two family dwelling
430.24 Several Motors or a Motor(s) and other Load(s)
440.3 Other Articles
440.6 Ampacity and Rating
Important!!!
Most service load calculations will include heating and/or air conditioning
equipment, but not all feeder load calculations will include these types of
loads. If the feeder will not supply power to heating and air conditioning
equipment, calculate just the general loads on this feeder. If a service will
not supply heating equipment calculate only the service for air condition
only. If a service will not supply power to heating and air conditioning
equipment, ignore this load in service load calculation.
The load for Room air conditioners shall be calculated at 100 % of its
ampere rating which may be indicated on its nameplate and will be used in
branch, feeder and service load calculations.
Example#1:
A dwelling unit has seven wall heaters; each heater is rated 3,000 watts at 240 volts.
How much load will these heaters add to a 240-volt, single-phase service? Assuming
that The air conditioning load will be less than the heating load.
Solution:
In accordance with 220.51, calculate the heaters service load at 100 %= 7 × 3,000 =
21,000 watts
Since the service voltage is known, the total current draw of the heaters can be
calculated by dividing the total watts by 240 volts
Central air conditioning and heating system Load shall be calculated at 100
% of its nameplate and will be a Noncoincident Load.
Important!!!
Depending on the design, the heating system and the air conditioning
system might be noncoincident loads.
Example#2:
What is the service load contribution for a dwelling that will have electric space
heaters and window air conditioners? The heat will consist of two rooms with space
heaters rated 1,500 watts each and three rooms with space heaters rated 2,250 watts
each.
The air conditioning will consist of four rooms with window air conditioning units rated
11.5 amperes at 240 volts. Assume space-heating watts are equivalent to volt-amperes
(VA).
Solution:
In this dwelling, the heat load and the air conditioning load are noncoincident loads.
The heat and the air conditioning will not be energized at the same time. Therefore,
compare the total heat load to the total air conditioning load and omit the smaller of
the two loads.
First: calculate the heat load The total heat load = 1,500 + 1,500 + 2,250 + 2,250 +
2,250 = 9,750 VA.
Second: calculate the air conditioning load
Start by finding the volt-amperes of each unit (VA = E × I) (assume power factor or PF
= 1.0).
The load of each air conditioner = 240 × 11.5 = 2,760 VA
The total air conditioner load = 2,760 VA × 4 = 11,040 VA
Since the air conditioner load is larger than the heat load, omit the heat load.
The service load contribution for the heating and air conditioning loads in this dwelling
is 11,040 VA
If the air conditioner compressors are the largest motors in this dwelling, multiply the
load of one compressor by 25 percent and add it to the service load calculation.
Rule#5: the air handler (or blower motor) is not a noncoincident load
Although the heating and air conditioning in package units and split systems
are noncoincident loads, the air handler (or blower motor) (or evaporator
motor) is not. Since the blower motor works with both the heating and air
conditioning system, it must be included in both calculations.
Example#3:
Solution:
The heat load= 9.6 KW × 1,000 = 9,600 watts The full-load current in amperes of a ½
hp, single-phase, 240-volt motor (from Table 430.248) = 4.9 A
The motor load = 4.9 A × 240 V = 1,176 VA
The service load for this package unit = 1,176 + 9,600 = 10,776 watts
Example#4:
A package unit has electric heat and air conditioning. The unit contains a compressor,
a blower motor, a condenser fan motor and electric heat. The compressor draws 23
amperes at 240 volts, the blower motor draws 5 amperes at 240 volts and the
condenser fan motor draws 2 amperes at 240 volts. The rating of the heat is 10 kW.
Assume heating kilowatt rating is equivalent to kilovolt-amperes. What is the service
load contribution for this heating/cooling package unit?
Solution:
The load of the air conditioner compressor =23 A × 240 V= 5,520 VA The load of the
blower motor = 5 A × 240 V = 1,200 VA
The load of the condenser fan motor = 2 A × 240 V = 480 VA
The total air conditioning load = 5,520 + 1,200 + 480 = 7,200 VA
Since the blower motor also works with the heat, the load of the blower motor must
be added to the heat load. So, the heat load = 10 KW× 1,000 = 10,000 + 1,200 = 11,200
VA
Since the heat load is larger than the air conditioner load, omit the air conditioner
load. The service load contribution for this package unit is 11,200 VA.
Important!!!
Unless it is the largest motor in the feeder or service load calculation, do
not multiply the full-load current of the motor by 125 percent.
Example#5:
In example#3, the blower motor in the heating/cooling package unit in the last
example will be the largest motor in the one-family dwelling. How much load will this
package unit add to a 240-volt, single-phase service?
Solution:
If the ½ hp blower motor is the largest motor in the calculation for the service, the
ampacity must not be less than 125 percent of the full-load current rating plus the
calculated load of the electric heat. Multiply the motor’s full-load current by 125
percent before adding it to the electric heat service load
The motor load = 4.9 A × 240 V = 1,176 VA The service load for this package unit =
1,176 x 1.25 + 9,600 = 11,070 watts
With a heat pump, the compressor (and accompanying motors) and some or
all of the electric heat can be on at the same time. The load contribution of
a heat pump is the air conditioning system load plus the maximum amount
of heat that can be on while the air conditioner compressor is on.
Example#6:
What is the service load contribution for a heat pump with supplementary heat? The
compressor draws 26.4 amperes at 240 volts, the blower motor draws 6.5 amperes at
240 volts and the condenser fan motor draws 3 amperes at 240 volts. The electric heat
in this unit has a rating of 15 kW. Assume heating kilowatt rating is equivalent to
kilovolt-amperes.
Solution:
The compressor and all of the heat in this heat pump can be energized at the same
time. The load of the air conditioner compressor = 26.4 × 240 = 6,336 VA
The load of the blower motor = 6.5 × 240 = 1,560 VA
The load of the condenser fan motor = 3 × 240 = 720
The total air conditioning load = 6,336 + 1,560 + 720 = 8,616 VA
Since the air conditioning system and all of the heat can be on at the same time, add
the two together to get the service load contribution.
The service load contribution for this heat pump = 8,616 + 15,000 = 23,616 VA
Important!!!
Noncoincident loads are not limited to heating and air conditioning systems.
Example#7:
What is the feeder load contribution for two 5-hp, 230-volt, single phase pump motors?
The motors will be wired so only one motor is in operation at any time.
Solution:
Because these two motors are noncoincident loads, it is permissible to omit the load
of one motor. Start by finding the full-load current (FLC) of one motor.
Full-load currents for single-phase, alternating-current motors are in Table
430.248. From Table 430.248, The FLC of this motor is 28 amperes.
The load of one motor = 28 A × 230 V = 6,440VA
Although there are two motors, they will never operate at the same time. Therefore,
only one motor must be added to the feeder calculation. The feeder load contribution
= 6,440 VA
If this motor is the highest-rated motor on this feeder, multiply the load of this motor
by 25 percent, and add it to the feeder load calculation.
Important!!!
In NEC Optional calculation method, for a multifamily dwelling, Table
220.84 ―Optional Calculations — Demand Factors for Three or More
Multifamily Dwelling Units‖ will be used if the following conditions are
verified:
1. If No dwelling unit is supplied by more than one feeder
2. Each dwelling unit is equipped with electric cooking
equipment.
3. Each dwelling unit is equipped with either electric space
heating or air conditioning, or both.
Important!!!
The optional calculation can be used, provided all of the conditions for using
table 220.84 listed above are met. Otherwise, the calculation for the
multifamily dwelling is performed by using standard calculation method.
As per NEC section 220.82 (C), for Heating and Air-Conditioning Load, The
largest of the following six selections (load in kVA) shall be included:
Example#8:
A central heating and air conditioning unit will be installed in a one-family dwelling.
The air conditioning system is electric, and the heating system is gas. The air
conditioner compressor has a rating of 16.6 amperes (A) at 230 volts (V). The
condenser fan motor has a rating of 2A at 115V and the air-handler (blower motor) has
a rating of 3.2A at 115V. Calculating by the optional method, how much air
conditioning load will be added to the general loads?
Solution:
First: calculating the volt-ampere (VA) load for each motor. The compressor load
=16.6 A x 230 V = 3,818 VA
The condenser fan load = 2 Ax 115 V = 230VA
The air handler load = 3.2 A x 115 V = 368VA
Second: add the air conditioning loads to find the total The service load = 3,818 + 230
+ 368 = 4,416 VA
Because air conditioning loads only exist, it will be calculated at 100 percent.
Important!!!
Where there is more than one air conditioning unit, the calculation method
is the same as it is for one air conditioning unit.
Example#9:
Four window air conditioners will be installed in a one-family dwelling. The heating
system is not electric. Two units are rated 12.5A at 230V and the other two are rated
8.5 amperes at 230 volts. Calculating by the optional method, how much air
conditioning load will be added to the general loads?
Solution:
Each of the larger air conditioners has a load = 12.5A x 230 V = 2,875 VA Each of the
smaller window units has a load = 8.5A x 230 V = 1,955 VA
The total load for all four units = 2,875 + 2,875 + 1,955 + 1,955 = 9,660 VA
The multiplication factor for four air conditioning units is the same as it is for one unit
at 100%
The service load for four air conditioning units = 9,660 VA x 100% = 9,660 VA
Case #2: Heat pumps equipped with or without electric supplemental heat
Case #3: When a heat pump is used with supplemental electric heat
In this case, multiply the nameplate rating(s) of the heat pump compressor by
100 percent and multiply the supplemental electric heating for central electric space-
heating systems by 65 percent.
Example#10:
Solution:
Multiply the backup heat by 65 percent. The backup or supplemental heat= 15,000 x
65% = 9,750 VA
The total heating and air conditioning load = 5,760 + 9,750 = 15,510 VA
Important!!!
Some heat pumps are designed so that only part of the electric heat will
operate while the compressor is in operation. If the heat pump compressor
is prevented from operating at the same time as the supplementary heat, it
does not need to be added to the supplementary heat for the total central
space-heating load.
Example#11:
Solution:
Because only part of the backup heat can operate while the compressor is running,
multiply the load of this part by 65 percent. The backup heat load = 10,000VA x 65% =
6,500 VA
The total heating and air conditioning load = 7,200 + 6,500 = 13,700 VA
Case#4: electric space heating by less than four separately controlled units
Example#12:
A total of three electric wall heaters will be installed in a one-family dwelling. Two of
the units are rated 3,000 watts (W) at 240 volts (V), and one unit is rated 4,800W at
240V. Each wall heater is separately controlled. This dwelling does not have an air
conditioning load. Calculating by the optional method and after applying the
appropriate demand factors, what is the heating load for these three electric space
heaters?
Solution:
The total rating for all three heaters = 3,000 + 3,000 + 4,800 = 10,800 VA
Because there are less than four separately controlled space heating units, multiply
the total rating by 65 percent. The total rating for all three heaters = 10,800VA x 65%
= 7,020 VA
Example#13:
Solution:
The total rating for all six heaters = 1,500 + 1,500 + 2,000 + 3,000 + 3,000 + 4,000 =
15,000 VA
Because there are at least four separately controlled space heating units, multiply the
total rating by 40 percent. The total rating for all six heaters = 15,000 x 40% = 6,000
VA
Case#6: using electric thermal storage (ETS) and other heat systems
Some electric utilities offer a discounted rate for kilowatt-hours used during
certain hours of the day and night. During off-peak hours, customers pay rates that are
less than rates during peak hours. During off-peak hours, electric elements are used to
heat ceramic bricks. The stored heat is then released throughout the day when rates
are higher. Many installations include multiple units placed throughout the house.
Since all of the electric thermal storage units could be heating bricks at the
same time, no demand factor can be applied to the units.
In this case, 100 percent of the nameplate ratings of electric thermal storage
(ETS) and other heat systems where the usual load is expected to be continuous at the
full nameplate value.
Example#14:
Four electric thermal storage units will be installed in a one-family dwelling. Two units
are rated 5.4 kilowatts (kW) at 240V and two units are rated 7.2 kW at 240V. This
dwelling does not have an air conditioning load. Calculating by the optional method
and after applying the appropriate demand factors, what is the heating load for this
dwelling?
Solution:
The total rating for all four units = 5.4 + 5.4 + 7.2 + 7.2 = 25.2 KVA
Because electric thermal storage system loads are calculated at 100 percent, 25.2 kVA
will be added to service load.
Important!!!
Depending on the design, the heating system and the air conditioning
system might be noncoincident loads.
Important!!!
Similarly, 220.82(C) requires that only the largest of the six choices needs to
be included in the feeder or service calculation.
Example#15:
Three window air conditioners and five separately controlled electric wall heaters will
be installed in a one-family dwelling. One window unit is rated 11.5 amperes at 240V
and the other two are rated 9 amperes at 240V. Two wall heaters are rated 2,000W at
240V, two heaters are rated 3,000W at 240V and one heater is rated 4,000W at 240V.
Calculating by the optional method, how much heating and air conditioning load will
be added to the general loads?
Solution:
The total load for all three units = 2,760 + 2,160 + 2,160 = 7,080 VA
Since the air conditioning load is calculated at 100 percent, the total air conditioning
load = 7,080 x 100% = 7,080 VA
The total rating for all five heaters = 2,000 + 2,000 + 3,000 + 3,000 + 4,000 = 14,000
VA
Because there are at least four separately controlled space heating units, multiply the
total rating by 40 percent. The total heating load = 14,000 x 40% = 5,600 VA
Because the heating and air conditioning systems in this example will not run
simultaneously, it is only required to include the larger of the two loads. The larger
load, after applying demand factors, is the air conditioning load. Add service load = air
conditioning load = 7,080 VA
Branch Circuit Design Calculations – Part Ten
In article " Receptacle Branch Circuit Design Calculations – Part Three " I stated
that a Receptacle in dwelling units may serve one of the following loads:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
In the previous Article " Heating and air conditioning loads – Part One ", I explained
the following points:
The rules applied in second method differ from a dwelling unit type to another. I
explained the rules for first dwelling type ―A single dwelling unit‖ in above previous
Article.
Today, I will continue explaining the rules for feeder and service calculation of
Heating and air conditioning loads as per NEC Optional calculation method for other
dwelling unit types which are:
1. A multifamily dwelling,
2. A two dwelling units,
3. An existing dwelling unit,
As per NEC section 220.84, for Multifamily Dwelling, the demand factors of
Table 220.84 shall be applied to the larger of the air-conditioning load or
the fixed electric space-heating load.
Rule#2: Calculation of feeder and service loads for air conditioning load
in Multifamily Dwelling
With the optional method multifamily dwelling load calculation, the air
conditioning load is calculated at 100 % of the nameplate rating.
Important!!!
The air conditioning load is calculated the same way in multifamily
dwellings as it is in one-family dwellings. In both types, the air conditioning
load is calculated at 100 percent of the nameplate rating.
Rule#3: Calculation of feeder and service loads for electric space heating
load in Multifamily Dwelling
With the optional method multifamily dwelling load calculation, the load for
space heating units must be added to the calculation at the nameplate
rating.
Important!!!
The electric space heating load is not calculated the same way in
multifamily dwellings as it is in one-family dwellings. With the optional
method one-family dwelling load calculation, it is permissible to apply a
demand factor to space heating units. The demand factor depends on the
number of units.
Don’t Forget…
When calculating a multifamily dwelling by the optional method, use the
larger of the air conditioning loads or the fixed electric space-heating load.
Example#1:
For a 30-unit multifamily dwelling that have electric space heaters and window air
conditioners as follows:
The heating for each unit will consist of two separately controlled wall heaters rated
2,250W each and one heater rated 1,500W.
The air conditioning for each unit will consist of two window air conditioning units
rated 11.5A at 240V
What is the optional method service load calculation (before applying the Table 220.84
demand factor)? (Assume space-heating watts are equivalent to volt-amperes).
Solution:
First: calculate the heat load for each unit by adding the nameplate rating of heat
units
The heat load for each unit = 2,250 + 2,250 + 1,500 = 6,000 VA So, the total heat load
for 30 units = 6,000 VA x 30 = 180,000 VA
Second: calculate the air conditioning load for each unit by Multiplying volts, amperes
and the number of air conditioners in each unit
The air conditioning load for each unit = 240V x 11.5A x 2 = 5,520 VA So, the total air
conditioning load for 30 units = 5,520 VA x 30 = 165,600 VA
Third: compare between the heating load and the air conditioning load for all units
Since the heating load is larger than the air conditioning load, omit the air
conditioning load.
The optional method service load calculation (before applying the Table 220.84
demand factor) for the heating and air conditioning loads in this 30-unit multifamily
dwelling = 180,000 VA
Important!!!
Do not assume the heating load will always be larger than the air
conditioning load. The heating system could be gas or oil. The dwelling
could also be located in a warm climate where the air conditioning load is
larger than the heating load.
Example#2:
For a 12-unit multifamily dwelling that has an identical central heating and air unit for
each dwelling unit as follows:
Each package unit will contain a compressor, a blower motor, a condenser fan motor
and electric heat. The compressor draws 23A at 240V, the blower motor draws 5A at
240V, and the condenser fan motor draws 2A at 240V. The rating of the electric heat is
5 kW.
What is the optional method service load calculation (before applying the Table 220.84
demand factor)? (Assume the heating kilowatt rating is equivalent to kilovolt-
amperes).
Solution:
First: calculate the air conditioning load for each unit and then for all units
The load of each air conditioner compressor =23A x 240 V = 5,520VA The load of each
blower motor =5 A x 240 V = 1,200 VA
The load of each condenser fan motor = 2A x 240 V = 480VA
So, the air conditioning load for each unit = 5,520 + 1,200 + 480 = 7,200 VA And the
total air conditioning load for 12 units = 7,200 VA x 12 = 86,400 VA
Second: calculate the heat load for each unit and then for all units
Since the blower motor also works with the heat, add the load of the blower motor to
the heat load The load of blower motor = 5 x 1,000 VA = 5,000 VA
So, the heating load for each unit = 5,000 + 1,200 = 6,200 VA And the total heating
load for 12 units = 6,200 x 12 = 74,400 VA
Third: compare between the heating load and the air conditioning load for all units
In this example, the air conditioning load is larger than the heating load; therefore,
omit the heating load.
The optional method service load calculation (before applying the Table 220.84
demand factor) for the heating and air conditioning system in this 12-unit multifamily
dwelling = 86,400 VA
Important!!!
Fixed electric space heating is not limited to space heaters and electric
strip heat that is part of a package unit or furnace. Fixed electric space
heating could also be a heat pump with supplementary heat.
With a heat pump, the compressor (and accompanying motors) and some or
all of the electric heat can be energized at the same time.
So, The load contribution of a heat pump = the air conditioning system load
+ the maximum amount of heat that can be on while the air conditioner
compressor is energized.
Example#3:
For a six-unit multifamily dwelling that has an identical heat pump for each dwelling
unit as follows:
Each unit’s compressor draws 26.8A at 240V, the blower motor draws 5.8A at 240V,
and the condenser fan motor draws 2.6A at 240V. The electric heat in this unit has a
rating of 15 kW. The compressor and all of the heat in this heat pump can be
energized at the same time.
What is the optional method service load calculation (before applying the Table 220.84
demand factor)? Assume the heating kilowatt rating is equivalent to kilovolt-amperes.
Solution:
First: calculate the air conditioning and heat loads for each heat pump
The load of the air conditioner compressor = 26.8 A x 240 V= 6,432 VA The load of the
blower motor = 5.8 A x 240 V= 1,392 VA
The load of the condenser fan motor = 2.6A x 240 V = 624 VA
So, the air conditioning load for each unit = 6,432 + 1,392 + 624 = 8,448 VA
Since the air conditioning system and all of the heat can be on at the same time, add
the two together
The air conditioning and heat loads for each heat pump = 8,448 + 15,000 = 23,448 VA
Second: calculate the air conditioning and heat loads for all heat pumps
The optional method service load calculation (before applying the Table 220.84
demand factor) for the heating and air conditioning system in this six-unit multifamily
dwelling = 140,688 VA
Example#4:
If the calculated services load for a 24- unit multifamily dwelling is 311,556 VA and
there is a requirement to supply power for it by using four feeders, each feeder will
supply power to six units.
Each unit in this multifamily dwelling will have 1,050 square feet of floor area, two
20- A small-appliance branch circuits, one 20A laundry branch circuit, fastened-in-
place appliances rated 6,600 VA, a range rated 12,000 VA, and an electric clothes
dryer rated 5,000 VA. The heating and air conditioning system in each unit will consist
of a compressor rated 4,200 VA, a blower motor rated 840 VA, a condenser fan motor
rated 360 VA and electric heat rated 5,000 VA
What is the optional method feeder load calculation for six units?
Solution:
Second: In accordance with 220.84(C)(2), The small-appliance branch circuit load for
six units = 2 x 1,500VA x 6 = 18,000 VA
Third: In accordance with 220.84(C)(3), use the nameplate ratings for the fastened-in-
place appliances, ranges and clothes dryers will be used:
The laundry branch circuit load for six units = 1,500VA x 6 = 9,000 VA.
The calculated load for the fastened-in-place appliances for six units = 6,600 VA X 6 =
39,600 VA
The calculated load for the ranges for six units = 12,000 VA X 6 = 72,000 VA
The calculated load for the clothes dryers for six units = 5,000 VA X 6 = 30,000 VA
Forth: In accordance with 220.84(C)(5), add to the load calculation the larger of the
air conditioning load or the fixed electric space heating load
The fixed electric space-heating load for six units = (electric heat load + blower motor
load) X 6 = (5,000 + 840) X 6 = 35,040 VA The total air conditioning unit for six units =
(compressor load + blower motor load + condenser fan motor load) x 6 = (4,200 VA +
840 VA +360 VA) x 6 = 32,400 VA
The air conditioning load is omitted because the heating load was larger.
Fifth: find the total connected load of the feeder
The total connected loads for a feeder supplying six units = 18,900 + 18,000 + 9,000 +
39,600 + 72,000 + 30,000 + 35,040 = 222,540 VA
Sixth: apply Table 220.84 demand factor (in below image) for six units is 44 percent.
The calculated load after applying the demand factor = 222,540 X 44% = 97,917.6 VA =
97,918 VA
Notes:
1. Not considering any house loads, the optional method feeder load
calculation for six units is 97,918 VA.
2. Do not divide the service load calculation by the number of feeders to
find the load of one feeder which will give incorrect answer as follows:
The feeder load = service load / number of feeders = 311,556 VA / 4 = 77,889
VA
While the correct calculated value for one feeder is 97,918 VA as calculated in
example#4 above.
Important!!!
The optional method load calculation for two dwelling units involves using
the optional method load calculation procedures for multifamily dwellings,
but not for two dwelling units. Perform the load calculation procedures in
220.84, but calculate these two dwelling units as if there were three
identical units.
Important!!!
In accordance with 220.85, it is necessary to calculate by both methods and
then select the lesser of the two loads.
Important!!!
Performing the optional method load calculation for two dwelling units
without performing the standard method load calculation is permissible, but
the result could be larger than the standard method load calculation.
Example#5:
A single feeder will supply two dwelling units. Each unit in this two-family dwelling
will have 1,800 square feet of floor area, two 20-ampere (A) small-appliance branch
circuits, one 20A laundry branch circuit, four fastened-in-place appliances with a total
rating of 9,156 VA, a range rated 12,000 VA and an electric clothes dryer rated 5,000
VA. The heating and air conditioning system in each unit will consist of a compressor
rated 4,200 VA, a blower motor rated 1,176 VA, a condenser fan motor rated 360 VA
and electric heat rated 10,000 VA.
What is the optional method feeder load calculation for this two-family dwelling?
Solution:
First: Start by calculating the load as per NEC standard method as follows:
1- As per 220.12, Calculate the general lighting and general use receptacle load at 3
VA per square foot
The general lighting and general use receptacle load for each unit = 1,800 ft2 x 3
VA/ft2 = 5,400 VA The general lighting and general use receptacle load for both units
=5,400 VA X 2 = 10,800 VA
2- As per 220.52(A) and (B), calculate the small-appliance and laundry branch-circuit
load at 1,500 VA for each circuit
The small-appliance and laundry branch-circuit load for each unit = 1,500VA X 3 =
4,500 VA The small-appliance and laundry branch circuit load for both units = 4,500VA
X 2 = 9,000 VA
The total general lighting load, including small-appliance and laundry branch circuits=
10,800 + 9,000 = 19,800 VA
3- Apply the Table 220.42 demand factors (in below image) to the general lighting
load.
The first 3,000 VA remain 3,000VA X 100% = 3,000VA The remaining =19,800 – 3,000 =
16,800 VA at 35 percent = 16,800 VA X 35% = 5,880 VA
So, the general lighting load for both units = 3,000 + 5,880 = 8,880 VA
4- The total fastened-in-place appliance load for both units = 9,156 x 2 = 18,312 VA
After applying the Section 220.53 demand factor, the fastened-in-place appliance load
= 18,312 X 75% = 13,734 VA
5- In accordance with 220.54, the electric clothes dryer load = 2 X 5,000 X100% =
10,000 VA
6- The maximum demand for two 12,000 VA ranges from Table 220.55 is 11,000 VA.
7- The heating load, with the blower motor, = 10,000 + 1,176 = 11,176 VA
This load is larger than the air conditioning load, and because of 220.60, it is
permissible to use only the larger of the noncoincident loads.
Therefore, the total heating load for both units = 11,176 VA X 2 = 22,352 VA
8- As required by 220.50 and 430.24, this calculation must include 25 percent of the
largest motor. Since the compressor was omitted, the largest motor is the blower
motor.
9- After applying all demand factors, the standard method load calculation for these
two dwelling units = 8,880 + 13,734 + 10,000 + 11,000 + 22,352 + 294 = 66,180 VA
Second: Perform the load calculation procedures in 220.84 (NEC optional method),
but calculate these two dwelling units as if there were three identical units.
1- As per 220.84(C)(1), Calculate the general lighting and general use receptacle load
at 3 VA per square foot
The general lighting and general use receptacle load for each unit = 1,800 ft2 x 3
VA/ft2 = 5,400 VA The general lighting and general use receptacle load for three units
= 5,400 VA X 3 = 16,200 VA
The small-appliance and laundry branch circuit load for each unit =1,500VA X 3 = 4,500
VA The small-appliance and laundry branch-circuit load for three units = 4,500 VA X 3
= 13,500 VA
3- In accordance with 220.84(C)(3), use the nameplate ratings for the fastened-in-
place appliances, ranges and clothes dryers.
The load for the fastened-in-place appliances, ranges and clothes dryers in each unit =
9,156 + 12,000 + 5,000 = 26,156 VA
The load for the fastened-in-place appliances, ranges and clothes dryers for three
units = 26,156 VA X 3 = 78,468 VA
4- In accordance with 220.84(C)(5), add to the load calculation the larger of the air
conditioning load or the fixed electric space heating load.
In this example, the heating load is larger than the air conditioning load, therefore
omit the air conditioning load. The heating load for each unit = 10,000 + 1,176 =
11,176 VA
5- The total connected load for three units = 16,200 + 13,500 + 78,468 + 33,528 =
141,696 VA
6- After finding the total connected loads, apply the Table 220.84 demand factor for
the number of dwelling units. The Table 220.84 demand factor for three units is 45
percent.
The calculated load after applying the demand factor =141,696 X 45% = 63,763 VA
Third: Compare between the results of standard and optional (as 3 units) loads and
select the lesser of the two loads.
The result of the standard load calculation was 66,180 VA.
The result of the Optional load calculation (as 3 units) was 63,763 VA
So, the calculated feeder load for these two dwellings is 63,763 VA.
Branch Circuit Design Calculations – Part Eleven
In article " Receptacle Branch Circuit Design Calculations – Part Three ", I stated
that a Receptacle in dwelling units may serve one of the following loads:
In the previous Article " Heating and air conditioning loads – Part One ", I
explained the following points:
The rules applied in second method differ from a dwelling unit type to another. I
explained the rules for first dwelling type ―A single dwelling unit‖ in Article " Heating
and air conditioning loads – Part One ".
Also, I explained the rules for dwelling unit type ―multifamily dwelling and two
dwelling units‖ in Article " Heating and air conditioning loads – Part Two "
Today, I will continue explaining the rules for feeder and service calculation of
Heating and air conditioning loads as per NEC Optional calculation method for the
forth case of dwelling unit which is existing dwelling unit.
Important!!!
The purpose of doing service and feeder calculations for an existing dwelling
unit is to determine if the existing service or feeder is of sufficient capacity
to serve a required additional loads or not.
Important!!!
For condition#1 in Rule#1 above, If the maximum demand data for a 1-
year period is not available, the calculated load shall be permitted to be
based on the maximum demand (measure of average power demand over a
15-minute period) continuously recorded over a minimum 30-day period
using a recording ammeter or power meter connected to the highest loaded
phase of the feeder or service, based on the initial loading at the start of
the recording. The recording shall reflect the maximum demand of the
feeder or service by being taken when the building or space is occupied and
shall include by measurement or calculation the larger of the heating or
cooling equipment load, and other loads that may be periodic in nature due
to seasonal or similar conditions.
Important!!!
For condition#2 in Rule#1 above, apply the NEC standard Calculation
method to get the total load as follows:
Where:
Existing Load Value = Max demand Value for a 1-year period from 220.87(1)
x 125%
New Load = Continuous loads x 125 % + Non-continuous loads x 100 %
Important!!!
If condition#2 in Rule#1 above is not verified, you need to increase ampacity
of the feeder and/or rating of the service to be able to add new loads to an
existing dwelling unit.
Example#1:
A business owner wants to add equipment to an existing building. The new equipment
will not replace any of the existing equipment. The existing service has a rating of
1,200 amperes (A). A peak-demand meter has been connected to the service for more
than a year. The maximum demand data from the peak-demand meter shows a
demand of 743A.
The new equipment that has a calculated load (in accordance with standard load
calculation procedures) of 251A. Does this existing service have an ampere rating high
enough for the existing loads and the new loads?
Solution:
Existing Load Value = Max demand Value for a 1-year period from 220.87(1) x 125% =
743 x 125% = 929 A
New Service Load = Existing Load Value + New Load = 929 + 251 = 1,180 A
Since the existing service is rated 1,200A, this installation will be Code-compliant
As per NEC section 220.83, The NEC optional calculation method for an
existing dwelling can only be used if the dwelling is supplied by a single-
phase service. The service can be fed from a 120/240-volt (V) or 208Y/120V
system but must be a 3-wire system.
For existing dwelling unit, it shall be permissible to calculate the total load by using
the NEC optional calculation method in the following two cases:
1. Where Additional Air-Conditioning Equipment or Electric Space-Heating
Equipment Is Not to Be Installed.
2. Where Additional Air-Conditioning Equipment or Electric Space-Heating
Equipment Is to Be Installed.
The following percentages shall be used for existing and additional new loads:
Percent of
Load (kVA)
Load
First 8 kVA of load at 100
Remainder of load at 40
Important!!!
The NEC optional calculation method for an existing dwelling shall Include
all of the existing loads and the new loads.
Example#2:
An addition will be built onto an existing one-family dwelling; the existing kitchen will
also be renovated. The area is 1,500 square feet. The existing dwelling has the
following loads:
Two small-appliance branch circuits;
One laundry branch circuit;
Two attic roof ventilators rated 506 VA each;
One motor rated 1,176 VA;
A range rated 8,000 VA;
A clothes dryer rated 5,000 VA;
And a water heater rated 4,500 VA.
The service supplying this existing dwelling is 120/240V, single phase, and is rated 100
A.
The addition built onto this dwelling will add 500 square feet of floor area. Therefore,
the total calculated floor area will be 2,000 square feet.
The existing range will be replaced by a new 12,000 VA range.
The kitchen renovation will also include two additional appliance loads: a dishwasher
rated 1,380 VA and a kitchen waste disposer rated 864 VA. Two more small-appliance
branch circuits will be installed, thus making a total of four small-appliance branch
circuits.
No additional air conditioning equipment or electric space-heating equipment will be
installed
Is this 100A service of sufficient capacity to serve these additional loads? If not, what
size service is required?
Solution:
When calculating an existing dwelling unit, include all the existing loads and all the
additional new loads.
The general lighting and general-use receptacle load = 2,000 ft2 x 3 VA /ft2= 6,000 VA
Second: calculate the small-appliance branch circuit and laundry branch circuit load
as specified in [220.83(A)(1)]
The small-appliance and laundry branch circuits load = (four small-appliance branch
circuits + one Laundry branch circuit) = 1,500 VA x 5 = 7,500 VA.
Other loads = new range load + clothes dryer load + water heater load = 12,000 VA +
5,000 VA + 4,500 VA = 21,500 VA
Fifth: Before applying the demand factor, the total for the existing loads and the new
loads = 6,000 + 7,500 + 4,432 + 21,500 = 39,432 VA
Sixth: In accordance with 220.83(A), calculate the first 8 kVA (8,000 VA) of load at 100
percent and the remainder of load at 40 percent.
Demand of existing loads and the new loads = 8,000 VA x 100 % + (39,432 – 8,000) x
40% = 20,573 VA
The minimum ampere rating required for this service = 20,573 VA ÷ 240 V = 85.7 A = 86
A.
Since the service supplying this dwelling is rated 100A, it is of sufficient capacity to
serve these additional loads.
In this case, the calculation is identical to that of case (A), But In this case,
there are additional loads for of air-conditioning or space-heating, so the
following will be applied for these loads:
The percentages in below image shall be used for existing and additional new loads.
Important!!!
The NEC optional calculation method for an existing dwelling shall Include
all of the existing loads and the new loads.
Example#3:
In example#2, before the job starts, the homeowners change their mind. They decide
to install a central air conditioning system that is rated 7,200 VA.
Is this 100A service of sufficient capacity to serve these additional loads plus the
central air conditioning unit? If not, what size service is required?
Solution:
Use rules as specified in 220.83(B), for existing and additional new loads where
additional air conditioning equipment or electric space-heating equipment is to be
installed.
From example#2, the Demand of existing loads and the new loads = 20,573 VA
As per Rule#4 above, the air conditioning system load must be added to the
calculation at 100 percent of nameplate rating
So, the Demand of existing loads and the new loads = 20,573 + 7,200 = 27,773 VA
The minimum ampere rating required for this service = 27,773 VA ÷ 240 V = 115.7 A =
116 A , which exceeds the 100 A old service rating
In accordance with 240.6(A), the next standard ampere rating above 116 is 125
amperes. Therefore, the minimum size service for this dwelling is 125 amperes.
Branch Circuit Design Calculations – Part Twelve
In article " Receptacle Branch Circuit Design Calculations – Part Three ", I stated
that a Receptacle in dwelling units may serve one of the following loads:
In the following paragraphs, I will explain Where and how to distribute each load
outlets in a dwelling building as per NEC code.
8- Motor loads
The motors exist in dwelling units as fastened in place appliances or separate motors
(air conditioning compressors, fan blower, etc.)
Important!!!
Most electrical equipment is rated in volt-amperes (VA) or watt input. While
motors traditionally have been rated in horsepower output (Some motors
are available with their output ratings expressed in watts and kilowatts).
Important!!!
Full-load currents for 3-phase motors are in Table 430.250,
Full-Load Current for Two-Phase Alternating- Current Motors (4-Wire)
are in Table 430.249,
Full-load currents for single-phase motors are in Table 430.248,
Full-Load Currents for Direct-Current Motors are in Table 430.247.
Important!!!
Kilovolt-amperes (kVA) shall be considered equivalent to kilowatts (kW) for
Fastened-in-place Appliances.
Important!!!
If the motor is one of the fastened-in-place appliances , Apply NEC section,
220.53, which states that ― It shall be permissible to apply a demand factor
of 75 % to the nameplate rating load of four or more appliances fastened-in-
place, that are served by the same feeder or service in a one-family, two-
family, or multifamily dwelling‖.
Important!!!
As per NEC section 220.53, electric ranges, clothes dryers, space-heating
equipment or air conditioning equipment must not be included with the
number of appliances that are fastened in place.
Also, All portable small Appliances for kitchen and others are not Fastened-
in-Place Appliances.
Important!!!
No derating is allowed when there are only one, two, three fastened-in-
place appliances.
Example#1:
Solution:
The load for these three appliances must be calculated at 100 percent.
Since the kitchen-waste (or garbage) disposer is a motor, the load must be determined
by multiplying the full-load current in Table 430.248 by the system voltage.
In accordance with Table 430.248, the full-load current of a ½-hp, 120-volt motor =
9.8 A
Note: Although the current value of 9.8 amperes is in the column titled ―115 volts,‖
the currents listed in this column are permitted for system voltage ranges of 110 to
120 volts (see the last sentence of the text in Table 430.248).
For the same case in example#, add a fourth appliance; a trash compactor rated 7.5
amperes at 120 volts, What is the total service load?
Solution:
The total before applying the demand factor = 1,200 + 1,176 + 900 + 4,500 = 7,776 VA
Next, because there are four appliances, multiply the load by the 75 percent demand
factor.
The calculated service load for these appliances = 7,776 × 0.75 = 5,832 VA
Important!!!
If the motor is air conditioning compressor, usually the air
conditioning compressor is the largest motor in dwelling units. in this case,
multiply the load of one compressor by 25 percent and add it to the service
load calculation.
But if the heating load is larger than the air conditioning load, and
because of 220.60 which states that‖ it is permissible to use only the larger
of the noncoincident loads‖ the air conditioning load will be omitted and
the air conditioning compressor will not be the largest motor in this case.
Example#3:
A single feeder will supply two dwelling units. Each unit in this two-family dwelling
will have 1,800 square feet of floor area, two 20-ampere (A) small-appliance branch
circuits, one 20A laundry branch circuit, four fastened-in-place appliances with a total
rating of 9,156 VA, a range rated 12,000 VA and an electric clothes dryer rated 5,000
VA. The heating and air conditioning system in each unit will consist of a compressor
rated 4,200 VA, a blower motor rated 1,176 VA, a condenser fan motor rated 360 VA
and electric heat rated 10,000 VA.
What is the feeder load calculation for this two-family dwelling?
Solution:
The general lighting and general use receptacle load for each unit = 1,800 ft2 x 3
VA/ft2 = 5,400 VA
The general lighting and general use receptacle load for both units =5,400 VA X 2 =
10,800 VA
2- As per 220.52(A) and (B), calculate the small-appliance and laundry branch-circuit
load at 1,500 VA for each circuit
The small-appliance and laundry branch-circuit load for each unit = 1,500VA X 3 =
4,500 VA
The small-appliance and laundry branch circuit load for both units = 4,500VA X 2 =
9,000 VA
The total general lighting load, including small-appliance and laundry branch circuits=
10,800 + 9,000 = 19,800 VA
3- Apply the Table 220.42 demand factors to the general lighting load.
So, the general lighting load for both units = 3,000 + 5,880 = 8,880 VA
4- The total fastened-in-place appliance load for both units = 9,156 x 2 = 18,312 VA
After applying the Section 220.53 demand factor, the fastened-in-place appliance load
= 18,312 X 75% = 13,734 VA
5- In accordance with 220.54, the electric clothes dryer load = 2 X 5,000 X100% =
10,000 VA
6- The maximum demand for two 12,000 VA ranges from Table 220.55 is 11,000 VA.
7- The heating load, with the blower motor, = 10,000 + 1,176 = 11,176 VA
This load is larger than the air conditioning load, and because of 220.60, it is
permissible to use only the larger of the noncoincident loads.
Therefore, the total heating load for both units = 11,176 VA X 2 = 22,352 VA
8- As required by 220.50 and 430.24, this calculation must include 25 percent of the
largest motor. Since the compressor was omitted, the largest motor is the blower
motor.
9- After applying all demand factors, the standard method load calculation for these
two dwelling units = 8,880 + 13,734 + 10,000 + 11,000 + 22,352 + 294 = 66,180 VA
Don’t Forget…
For example#3, NEC optional method for three identical units must be
calculated, because In accordance with 220.85, where two dwelling units
are supplied by a single feeder and the calculated load as per NEC standard
method exceeds that for three identical units calculated in accordance with
NEC optional method, the lesser of the two loads shall be permitted.
Example#4:
Solution:
The full-load current in amperes of a ½ hp, single-phase, 240-volt motor (from Table
430.248) = 4.9 A
Because the blower motor is the largest motor in the service load
The service load for this package unit = 10,776 + 1,176 x 25% = 11,070 watts
As per NEC section 220.82(B)(4), add the nameplate ampere (A) or kilovolt
ampere (kVA) rating of all permanently connected motors to the general
loads covered in 220.82(B). Include all motors that are not already included
with the general loads covered in 220.82(B)
Important!!!
Permanently connected motors must be added to the general loads when
calculating a feeder or service when calculated by the NEC optional method.
Although motors are listed separately, some or all of the motors may have
already been added to the load calculation as fastened-in-place appliances.
Important!!!
When calculating the feeder or service load of a dwelling unit by the
optional method, do not multiply the full-load current of permanently
connected motors by 125 percent.
Important!!!
Do not include heating and air conditioning equipment in the list with
permanently connected motors. Heating and air conditioning equipment is
covered in 220.82(C) and explained before in articles:
Example#5:
What is the optional method service load calculation (before applying the demand
factor) for a one-family dwelling with the following permanently connected motors:
Two automatic power attic roof ventilators rated horsepower (hp) at 115 volts
(V) each
A swimming pool pump rated 1 hp at 230V
Noting that the ampere rating of each motor is not known. These three motors have
not been included with the general loads covered in 220.82(B).
Solution:
Step#1: find the full-load current rating in amperes for each motor.
Since the ampere ratings for these motors are not known, use the values given in
Table 430.248 (which provides full-load currents in amperes for single-phase
alternating-current motors)
The full-load current for each of the automatic power attic roof ventilators = 4.4
A. The full-load current for the swimming pool pump = 10 A
The service load for these permanently connected motors (As per NEC optional
calculation method) = 506 + 506 + 2,300 = 3,312 VA
As per NEC section 220.84(C)(4), add the nameplate ampere (A) or kilovolt
ampere (kVA) rating of all permanently connected motors to other
categories of loads included in 220.84(C). Include all motors that are not
already included with the item 220.84(C)(3).
Important!!!
For multifamily dwelling load calculation, if there are any permanently
connected motors that have not been included, add the nameplate ampere
or kilovolt-ampere rating of those motors to the calculation.
Important!!!
Do not include motors that are part of the air conditioning system or motors
that are part of the fixed electric space-heating system. These motors will
be included as 220.84(C)(5) requires and as explained before in articles:
Important!!!
Include only permanently connected motors that are supplied from dwelling
units. Do not include permanently connected motors that are supplied by
house power.
Don’t Forget…
After calculation of feeder or service load calculation for a Multifamily
dwelling, apply the demand factors of table 220.84.
Example#6:
The load of a multifamily dwelling will be calculated by the optional method. Two
swimming pool pump motors and two automatic power attic roof ventilators will be
powered by the house panel. Can these permanently connected motors be included
with the connected loads to which Table 220.84 apply?
Solution:
Because these permanently connected motors are supplied by house power, do not
add them to the loads that will be calculated in accordance with Table
220.84(Optional Calculations — Demand Factors for Three or More Multifamily Dwelling
Units). These motors must be calculated in accordance with Part III of Article 220.
1. Industrial buildings
2. Commercial buildings
3. Residential buildings
4. Agricultural buildings
5. Educational buildings
6. Transportation buildings
7. Religious buildings
8. Parking and storage
9. Military buildings
10. Governmental buildings
11. Cultural buildings
12. Other buildings
In the current course" EE-3: Basic Electrical design course – Level II ", in Sixteen
Articles, I explained the design of the Dwelling type buildings; I explained Where and
how to distribute each type of load in a dwelling unit as per NEC code and how to
calculate its Demand load for feeder and service sizing calculations, and finally I
summarize the steps of calculating electrical load for any dwelling unit as per NEC
standard & Optional Calculation methods in two Excel sheets/calculator.
These Sixteen Articles for the electrical design of dwelling buildings are as follows:
Today, I will begin explaining the electrical design of Non-Dwelling Buildings as per
NEC Code.
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
Where and how to distribute each type of load in a dwelling unit as per NEC
code?
How to calculate its Demand load for feeder and service sizing calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
Schools
Existing Installations
New Restaurants
Lighting branch circuit ratings in non-dwelling units may have one of the following
ratings according to the type and application used as follows:
In the broad sense, lighting loads for Non-Dwelling buildings may be categorized as
follows:
1. General lighting.
2. Show-window lighting.
3. Track lighting.
4. Sign and outline lighting.
5. Other lighting.
Definition:
General lighting outlets are those Outlets intended for general use for fixed-
in-place luminaires (lighting fixtures). They are only used for lighting for the
normal use of the occupants and Its intensity should be adequate for any
type of work performed in the area.
Important!!!
The following Lighting fixtures are not included in General Lighting
category:
Determining the general lighting load as per NEC will be based on the load per area
method as follows:
Step#1: determine the general lighting load density (in VA/ft2) for the building
occupancy under design.
Rule#1: Applying Table 220.12
The NEC code introduces minimum general lighting loads (in VA/ft2) for
various types of buildings in Table 220.12.
Within the same building, there are normally several different types of
areas like storage, office, hallways, and cafeterias, these areas must be
considered separately if their (VA/ft2) values are available in table 220.12.
The floor area for each floor shall be calculated from the outside dimensions
of the building, or other area involved.
The calculated floor area shall not include open porches, garages, or unused
or unfinished spaces not adaptable for future use (like some attics, cellars,
and crawl spaces).
Step#3: calculate the general lighting load
The general lighting load is calculated by multiplying the floor area in (ft2) of a
building by its unit load (in VA/ft2) derived from table 220.12.
General lighting load in (VA) = Area of Occupancy in (ft2) X general lighting load
density in (VA/ft2)
Step#4: Apply lighting demand factor from table 220.42 for type of building under
design.
Important!!!
The demand factors of table 220.42 shall not apply to the calculated load of
feeders or services supplying areas in hospitals, hotels, and motels where
the entire lighting is likely to be used at one time, as in operating rooms,
ballrooms, or dining rooms.
Important!!!
For the purpose of determining the circuit requirements, If the General
Lighting load is continuous (as in Most commercial structures), the
calculated load is multiplied by 1.25 (the inverse of 80%).
Example#1:
A 25,000 ft2 office building is being designed. What is the general lighting load and
what load does the circuit need to supply?
Solution:
From Table 220.12, the unit load for an office building is 3.5 VA/ft2.
The general lighting load is determined by multiplying this value by the square footage
of the building:
However, the load is continuous and can only be 80% of the load supplied by the
circuit. This value must be multiplied by 1.25 to determine the circuit requirements:
1. The unit values herein are based on minimum load conditions and
100 percent power factor (i.e. Load in VA = Load in Watt) and may not
provide sufficient lighting for the installation contemplated. So, the
designer can choose a higher value based on the existing design
conditions.
2. Under any conditions, don’t use values less than that specified in
table 220.12, there are no exceptions.
Important!!!
The general lighting load unit values specified in table 220.12 for guest rooms
or guest suites of hotels and motels includes the following loads:
So, no need to add the above outlets in load calculations per NEC method.
Important!!!
The NEC method and table 220.12 are applied for any Additions to Existing
Installations for non-dwelling installations.
Important!!!
Energy saving–type calculations (which used to reduce the connected lighting
load and actual power consumption) are not permitted to be used to determine
the minimum calculated lighting load if they produce loads less than the load
calculated according to 220.12.
2.1.b Notes for NEC method for calculation of lighting branch circuit load
Important!!!
The NEC doesn’t introduce a procedure for calculating the actual full load for
the individual lighting fixtures in a general lighting branch circuit.
If the required information for calculating the actual full load for every
individual lighting fixture in the circuit is available, the following procedure
will be applied:
Important!!!
Actually, The NEC method for calculation of lighting load is not required if the
actual full load for every individual lighting fixture in the circuit is determined.
Methods for determining the actual full load for every individual lighting fixture
in the circuit is explained in our course and I recommend reviewing these
methods very well.
As per NEC Section 220.18 (b) states , circuits supplying lighting units that
have ballasts, transformers, autotransformers, or LED drivers, the
calculated load shall be based on the total ampere ratings of such units and
not on the total watts of the lamps.
This means that the losses in light fixture switchgear (ballast, internal
wiring, etc.) must be taken into account when calculating the actual full
load of light fixtures and the current rating of the ballast, not the tube
wattage, will be used.
Example#2:
A fluorescent lighting fixtures with 4 numbers 2 feet lamps, 18 watt/ lamp. Calculate
the actual load for this lighting fixture.
Solution:
The actual total load of fixture = 4 lamps x 18 watt/lamp + losses
So, we can’t know the actual losses, we will use the same equation in another form
1. Security lighting,
2. Parking area lighting,
3. Sidewalk lighting,
4. Roadway lighting,
5. Stadium lighting,
6. Tunnel Lighting.
Important!!!
All Additional lighting loads should be computed separately from the general
lighting load and then added to the general lighting load.
Don’t forget…
These additional lighting loads are considered continuous loads where
appropriate and must be multiplied by 1.25 for feeder and overcurrent
protection calculations.
Rule#6: Calculating the total lighting load for buildings having more than
one lighting category.
1. General lighting.
2. Show-window lighting.
3. Track lighting.
4. Sign and outline lighting.
5. Other lighting.
If more than one of the above lighting categories is existing in the same
building, Each lighting Category load is computed separately and then
combined to other lighting categories load to determine the total lighting
load.
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
1. Schools
2. Existing Installations
3. New Restaurants
I explained the Design Calculation for first type of Non-Dwelling Building loads which is
Lighting loads in Article.
Today, I will explain the second type of Non-Dwelling Building Loads which is
Receptacle Loads.
Second: Receptacle Loads – Part One
1- Introduction
Before we go ahead in explaining the design calculation for Receptacles Loads in Non-
Dwelling buildings, there are some parts explained previously in the design
calculations of Receptacles Loads of Dwelling buildings and are applicable also in Non-
dwelling buildings, these parts need to be reviewed from the following Articles:
In no case shall the load exceed the branch-circuit ampere rating. The following are
the permissible Receptacle Branch circuit ratings in dwelling buildings:
2- Only utilization equipment: with condition that the combined load for all
utilization equipment must not exceed the branch circuit rating.
Important!!!
A single receptacle installed on an individual branch circuit shall have an
ampere rating not less than that of the branch circuit.
A 40- or 50-ampere branch circuit shall be permitted to supply cooking appliances that
are fastened in place in any occupancy.
In other than dwelling units, such circuits shall be permitted to supply fixed lighting
units with heavy-duty lampholders, infrared heating units, or other utilization
equipment.
D) Branch Circuits Larger Than 50 Amperes
Branch circuits larger than 50 amperes shall supply only non-lighting outlet loads
especially on industrial premises where conditions of maintenance and supervision
ensure that only qualified persons service the equipment.
A receptacle shall not supply a total cord-and plug- connected load in excess of the
maximum specified in Table 210.21(B)(2) mentioned above.
In dwelling units the voltage rating for Receptacle Branch circuit shall not exceed the
following:
Circuits not exceeding 120 volts, nominal, between conductors shall be permitted to
supply the following:
1. The terminals of lampholders applied within their voltage ratings
Section 210.6(B)(1) allows lampholders to be used only within their voltage
ratings.
2. Auxiliary equipment of electric-discharge lamps Auxiliary equipment
includes ballasts and starting devices for fluorescent and high-intensity-
discharge (e.g., mercury vapor, metal halide, and sodium) lamps.
3. Cord-and-plug-connected or permanently connected utilization
equipment
Important!!!
In guest rooms or guest suites of hotels, motels, and similar occupancies,
the voltage shall not exceed 120 volts, nominal, between conductors that
supply the terminals of the following:
1. Luminaires,
2. Cord-and-plug-connected loads 1440 volt-amperes, nominal, or
less or less than 1⁄4 hp.
Circuits exceeding 120 volts, nominal, between conductors and not exceeding 277
volts, nominal, to ground shall be permitted to supply the following:
Important!!!
The requirements in (C) describes the voltage as ―volts, nominal, to
ground,‖ whereas (A), (B), (D), and (E) describe voltage as ―volts, nominal,
between conductors.‖ Luminaires listed for and connected to a 480-volt
source may be used in applications permitted by 210.6(C), provided the 480-
volt system is in fact a grounded wye system that contains a grounded
conductor (thus limiting the system ―voltage to ground‖ to the 277-volt
level).
Circuits exceeding 277 volts, nominal, to ground and not exceeding 600 volts, nominal,
between conductors shall be permitted to supply the following:
1. Not less than a height of 6.7 m (22 ft) on poles or similar structures for
the illumination of outdoor areas such as highways, roads, bridges, athletic
fields, or parking lots.
2. Not less than a height of 5.5 m (18 ft) on other structures such as
tunnels
Important!!!
For luminaire installations that are not on poles or in a tunnel, the branch
circuit Voltage is limited to 277 volts to ground.
(C) Luminaires powered from direct-current systems where the luminaire contains a
listed dc-rated ballast that provides isolation between the dc power source and the
lamp circuit and protection from electric shock when changing lamps.
As per NEC section 220.14(I), Receptacle outlets load shall be calculated at not less
than:
Example#1:
How many receptacles can be placed on a 120-volt, 20-amp circuit? How many can be
placed on a 120-volt, 15-amp circuit?
Solution:
Determine the maximum circuit power (for 20-amp circuit) = 120 V × 20 A = 2400 VA
Determine the maximum circuit power (for 15-amp circuit) 120 V × 15 A = 1800 VA
6- The Minimum number of receptacle branch circuits for bank or office buildings
As per NEC section 220.14(J), if the number of receptacles is unknown so for bank and
office buildings, we can calculate the receptacles load by multiplying the area in ft2
by the unit value (1 VA/ft2).
To get the required number of receptacle branch circuits for bank or office buildings
make the following steps:
Calculate the total receptacles load for the whole building as explained above.
Calculate the total receptacle circuit load in VA by multiplying its voltage by its
amperage as follows:
1. For 15-A Branch circuits = 120 V × 15 A = 1800 VA
2. For 20-A Branch circuits = 120 V × 20 A = 2400 VA
Divide the total receptacle load for the whole building by the maximum load
per circuit to determine the minimum number of circuits.
Example#2:
Determine the total receptacle load for an 80 ft × 120 ft office building? And
determine the number of 15-amp circuits needed to supply the load. Noting that the
number of receptacles is unknown.
Solution:
(b) To determine the number of circuits required, first calculate the allowable load for
a single circuit:
Divide the total receptacle load by the maximum load per circuit to determine the
minimum number of circuits:
Important!!!
As per NEC section 220.14(J), limit using the unit value (1 VA/ft2) for banks
and office buildings but it can be used also (as approximate) for other types
of buildings including dwelling ones.
Non-Dwelling Buildings Load Calculations- Part Three
In Article " Non-Dwelling Buildings Load Calculations- Part One ", I introduced a
List for ordinary Non-Dwelling Buildings Loads which was as follows:
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
1. Schools
2. Existing Installations
3. New Restaurants
I explained the Design Calculation for first type of Non-Dwelling Building loads which is
Lighting loads in Article " Non-Dwelling Buildings Load Calculations- Part One ".
Also, I explained part one of Design Calculation for second type; Receptacle loads for
Non-Dwelling Buildings in Article " Non-Dwelling Buildings Load Calculations- Part
Two ".
Today, I will explain the Design Calculation of Receptacle loads - second part for Non-
Dwelling Building Loads which is Receptacle Loads.
Important!!!
In Non-dwelling buildings (commercial and industrial buildings), many 120-
volt receptacles may be necessary to accommodate any devices that don’t
have special electrical requirements (General-use).
But The NEC code doesn’t specify the quantity and location of General-use
receptacles in Non-dwelling buildings, Unlike the dwelling buildings where
the NEC code specifies the quantity and location of General-use receptacles
as explained before in Article
Case#1: If the final customer requirements are known during the design
phase
Case#2: If the final customer requirements are not known
In this case, the designer must strive to create a design that provides for the
average user’s electrical needs and allows for flexibility for future additions
and expansions. For each area inside the building, the minimum number of
receptacle outlets should be determined by assuming there is no furniture in
that area and the following provisions will be done:
Important!!!
In case#2, after getting the permanent furniture layout of the building,
space, or area under designs, the practical locations of general-use
receptacles can be adjusted on this time.
1.1 Special Case: Locations and Minimum Quantity of General-use Receptacle Loads
in Guest Rooms, Guest Suites, Dormitories, and Similar Occupancies
Definitions:
Guest Room:
An accommodation combining living, sleeping, sanitary, and storage
facilities within a compartment.
Guest Suite:
An accommodation with two or more contiguous rooms comprising a
compartment, with or without doors between such rooms, that provides
living, sleeping, sanitary, and storage facilities.
Important!!!
Where receptacles are installed behind the bed, the receptacle shall be
located to prevent the bed from contacting any attachment plug that may
be installed or the receptacle shall be provided with a suitable guard. To
reduce the risk of fire to bedding material, receptacles located behind beds
must include guards if attachment plugs could contact the bed.
Within 900 mm (3 ft) (36 inch) of the outside edge of each basin.
on the side or face of the basin cabinet not more than 300 mm (12 in.)
below the basin countertop.
1- Grounding type
As per NEC section 406.4, Receptacles installed on 15- and 20-ampere branch circuits
shall be of the grounding type.
2- GFCI type
As per NEC section 210.8 (B), all 125-volt, single-phase, 15- and 20-ampere
receptacles are GFCI for the following locations:
A) Bathrooms
Some motel and hotel bathrooms have the basin located outside the door to the room
containing the tub, toilet, or another basin.
Definition:
A bathroom is defined in Article 100 as ―an area including a basin with one
or more of the following: a toilet, a urinal, a tub, a shower, a bidet, or
similar plumbing fixtures.‖
Important!!!
As per NEC section 406.9(C), it is prohibited to install a receptacle within or
directly over a bathtub or inside a shower stall even if the receptacles are
installed in a weatherproof enclosure.
Important!!!
As per NEC section 210.11(C)(3), At least one 20-ampere branch circuit shall
be provided to supply bathroom receptacle outlet(s). This circuit is
permitted to supply the required receptacles in more than one bathroom as
show in above image (bottom).
B) Kitchens
Definition:
Kitchen: is an area with a sink and permanent facilities for food preparation
and cooking.
Note that, A portable cooking appliance (e.g., cord-and-plug-connected
microwave oven or hot plate) is not a permanent cooking facility.
Kitchens, meeting the Article 100 definition above, in restaurants, hotels, schools,
churches, dining halls, and similar facilities are examples of the types of kitchens
covered by this requirement.
C) Rooftops
The receptacle shall be located on the same level and within 7.5 m (25 ft) of the
heating, air-conditioning, and refrigeration equipment. The receptacle outlet shall not
be connected to the load side of the equipment disconnecting means.
This receptacle improves worker safety by eliminating the need to employ makeshift
methods of obtaining 125-volt power for servicing and troubleshooting.
D) Outdoors
Other than the limited exclusions covered by the two exceptions to 210.8(B)(4), all
125-volt, single-phase, 15- and 20-ampere receptacles installed outdoors at
commercial, institutional, and industrial occupancies are required to be provided with
ground-fault circuit-interrupter protection.
1. Receptacles that are not readily accessible and are supplied by a branch
circuit dedicated to electric snow-melting, deicing, or pipeline and vessel
heating equipment shall be permitted to be installed in accordance with 426.28
or 427.22, as applicable.
2. In industrial establishments only, where the conditions of maintenance
and supervision ensure that only qualified personnel are involved, an assured
equipment grounding conductor program as specified in 590.6(B) (2) shall be
permitted for only those receptacle outlets used to supply equipment that
would create a greater hazard if power is interrupted or having a design that is
not compatible with GFCI protection.
Important!!!
Although commercial, institutional, and industrial occupancies are not
required to have outdoor receptacle outlets installed for general use, there
may be outdoor receptacle outlets installed to meet the requirement of
210.63 or at the discretion of the designer or owner.
E) Sinks
Where receptacles are installed within 1.8 m (6 ft) of the outside edge of the sink.
H) Garages, service bays, and similar areas where electrical diagnostic equipment,
electrical hand tools, or portable lighting equipment are to be used
3- Tamper-Resistant type
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
1. Schools,
2. Existing Installations,
3. New Restaurants.
I explained the Design Calculation for first type of Non-Dwelling Building loads which is
Lighting loads in Article " Non-Dwelling Buildings Load Calculations- Part One ".
Also, I explained parts one & Two of Design Calculation for second type; Receptacle
loads for Non-Dwelling Buildings in Articles:
Non-Dwelling Buildings Load Calculations- Part Two
Non-Dwelling Buildings Load Calculations- Part Three
Today, I will explain the Design Calculation of Receptacle loads - Third part for Non-
Dwelling Building Loads which is Receptacle Loads.
Important!!!
The receptacle outlets in Non-Dwelling Buildings will be counted to
calculate their load, unlike the Dwelling buildings where the General-Use
Receptacles Load is calculated with the general lighting Load by multiplying
Building Area in (ft2) with its power density in (VA/ft2) from table 220.42 in
below image.
Important!!!
General-Use Receptacles are not-continuous Loads, No need to multiply it
by 1.25 to calculate their contribution in the total load.
But, if a Receptacle is dedicated for a specific device, then the actual load
is used and If this dedicated load is continuous, then the 125% overrate is
appropriate.
Rule#1: General-Use Receptacle Load (see below image)
So, no need to add the above outlets in load calculations per NEC method.
Example#1:
For a commercial building having 75 duplex and 10 single receptacles, what is the
calculated load for these receptacles?
Solution:
As per NEC section 220.14(I), Receptacle outlets load shall be calculated at not less
than:
180 volt-amperes for each single receptacle, 180 volt-amperes for each multiple
receptacle (duplex or triplex) on one yoke/strap.
Important!!!
In Commercial and Industrial Buildings, it is common to use fixed multioutlet
assemblies, which can be classified to two types according to method of usage
as follows:
Important!!!
Fixed multioutlet assemblies in guest rooms or guest suites of hotels and motels
are included in The general lighting load unit values specified in table 220.12.
So, no need to add the Fixed multioutlet assemblies in load calculations for
these locations.
Example#2:
For a commercial building has 75 linear feet of fixed multioutlet assembly, with 15
feet of the assembly subject to simultaneous use. What is the calculated load for this
fixed multioutlet assembly?
Solution:
Length of fixed multioutlet assembly Portion for Non- simultaneous use (Light Use) =
75 – 15 = 60 linear feet.
Calculated load for Light use portion = (60/5) x 180 VA = 2,160 VA Calculated load for
Heavy use (simultaneous use) portion = 15 x 180 VA = 2,700 VA
Total calculated load for this fixed multioutlet assembly = 2,160 VA + 2,700 VA = 4,860
VA
The general lighting load, before applying demand factors, for hospital patient rooms
is 100,000 volt-amperes. The receptacle branch-circuit load, calculated in accordance
with 220.14(H) and (I), is 144,000 volt-amperes. What is the lighting and receptacle
load after demand factors?
Solution:
Since Hospital is one of the building types (other than dwelling units) listed in Table
220.42, the receptacle load could be added to the general lighting load and made
subject to the demand factors in Table 220.42.
Total load = lighting load + receptacles load = 100,000 VA+ 144,000 VA = 244,000 VA
Then apply demand factors for hospital from table 220.42 as follows:
The lighting and receptacle load, after applying Table 220.42 demand factors= 20,000
+ 38,800 = 58,800 VA
Example#4:
Solution:
Applying the demand factors in Table 220.44
Example#5:
A store has a total of 80 duplex receptacles. What is the receptacle load after demand
factors?
Solution:
Then, the receptacle load, after applying Table 220.44 demand factors= 10,000 + 2200
= 12,200 VA
As per NEC section 220.14(K), in bank and office buildings, if the number of
receptacles is known, then we can calculate the receptacles load to be the
larger of the following two loads:
Example#6:
In an 8,500 square foot bank, it is not known how many receptacles are there, what is
the calculated load for receptacles?
Solution:
As per NEC section 220.14(K), in bank and office buildings, if the number of
receptacles is unknown, we can calculate the receptacles load by multiplying the bank
or office building area in ft2 by the unit value (1 VA/ft2).
The calculated load for receptacles = 8500 ft2 x 1 VA/ft2 = 8,500 VA
Non-Dwelling Buildings Load Calculations- Part
Five
In Article " Non-Dwelling Buildings Load Calculations- Part One ", I introduced a
List for ordinary Non-Dwelling Buildings Loads which was as follows:
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
Schools,
Existing Installations,
New Restaurants.
I explained the Design Calculation for first type of Non-Dwelling Building loads which is
Lighting loads in Article " Non-Dwelling Buildings Load Calculations- Part One ".
Also, I explained parts one & Two of Design Calculation for second type; Receptacle
loads for Non-Dwelling Buildings in Articles:
Today, I will explain the Design Calculation of third type of loads in Non-Dwelling
Building Loads which is Kitchen Load.
Third: Kitchen Load
Definition:
Kitchen: An area with a sink and permanent provisions for food preparation
and cooking.
Important!!!
Kitchen equipment is not limited to restaurants; it can be a portion of a
load calculation for a school.
As per NEC section 220.56, it shall be permissible to calculate the load for
commercial electric cooking equipment, dishwasher booster heaters, water
heaters, and other kitchen equipment in accordance with Table 220.56 (see
below image). These demand factors shall be applied to all equipment that:
Important!!!
As per table 220.56, No derating is allowed for only one or two pieces of
kitchen equipment.
Important!!!
Because commercial electric cooking and other kitchen equipment is used
more intensively and for longer periods of time than electric cooking
equipment in a dwelling unit, the demand factors in Table 220.56 do not
provide a comparable demand to that permitted for dwelling unit cooking
appliances until there are six or more commercial appliances.
Important!!!
Because commercial electric cooking and other kitchen equipment is used
more intensively and for longer periods of time than electric cooking
equipment in a dwelling unit, the demand factors in Table 220.56 do not
provide a comparable demand to that permitted for dwelling unit cooking
appliances until there are six or more commercial appliances.
Important!!!
Unlike Table 220.55, Table 220.56 is not just for ranges and cooking
appliances; it will apply for all equipment that has either thermostatic
control or intermittent use as kitchen equipment (like commercial electric
cooking equipment, dishwasher booster heaters, water heaters, and other
kitchen equipment).
Rule#2: Comparing the demand load to the sum of the largest two
kitchen equipment loads
As per NEC section 220.56, the calculated demand load for the feeder or
service must not be less than the sum of the largest two kitchen equipment
loads. Two cases are available:
1. The demand load > the sum of the largest two kitchen
equipment loads, in this case, it is permissible to use the demand
load.
2. The demand load < the sum of the largest two kitchen
equipment loads, in this case, the demand load must not be used
and The minimum load will be the sum of the largest two kitchen
equipment loads.
Example#1:
What is the demand load for a restaurant with two 14-kW stoves, a 6-kW oven, a 5-kW
dishwasher, a 3-kW booster heater, and a 4-kW food waste disposer?
Solution:
The demand factor percent in Table 220.56 for six units is 65 percent.
The load after applying the Table 220.56 demand factor = 46 × 65% = 29.9 kW
Comparing the demand load to the sum of the largest two kitchen equipment loads
The absolute minimum rating is the total combined rating of the largest two kitchen
equipment loads = 14 + 14 = 28 KW
Since the demand load of 29.9 kW is higher than the sum of the two highest rated
units, it is permissible to use the demand load.
Example#2:
What is the demand load for the following commercial kitchen equipment: five 3-kW
ovens, one 5-kW cooktop and two 20-kW ranges?
Solution:
The demand factor percent in Table 220.56 for eight units is 65 percent. T
Since the demand load of 39 kW is lower than the sum of the two highest rated units,
the demand load must not be used.
Definition:
An instructional program Building: a building in which a discipline and an
organized sequence or grouping of courses leading to a defined objective
such as a major, degree, certificate, license, the acquisition of selected
knowledge or skills, or transfer to another institution of higher education.
For example A high School Classroom.
Important!!!
Household electric cooking equipment installed in other than dwellings units
and not in instructional programs must be calculated in accordance with
Table 220.56.
Example#3:
A high school classroom will be converted into a culinary arts classroom. Five 12-kW,
240-volt household electric ranges will be installed. A separate panelboard will be
installed to supply the ranges. What is the kilowatt-demand load for the feeder and
panelboard supplying power to these ranges?
Solution:
Since the ranges will be used in instructional programs and they are household electric
ranges. So, table 220.55 note#5 will be applied.
The feeder and panelboard could be sized on 100 percent of the equipment’s
nameplate ratings, which is 60 kW, but this is not necessary. Look in the left column of
Table 220.55 for five appliances.
Because of the range ratings, the maximum demand is in Column C. The maximum
demand required for five 12-kW, 240-volt house-hold electric ranges is 20 kW.
Example#4:
A high school classroom will be converted into a culinary arts classroom. Five 12-kW,
240-volt commercial electric ranges will be installed. A separate panelboard will be
installed to supply the ranges. What is the kilowatt-demand load for the feeder and
panelboard supplying power to these ranges?
Solution:
Since the ranges will be used in instructional programs and they are not household
(commercial) electric ranges.
Therefore, it is not permissible to apply the demand factors from Table 220.55.
Demand factors for commercial electric cooking equipment are in Table 220.56.
Look in the left column of Table 220.56 for five units of equipment and follow across
for the demand factor.
The feeder and panelboard supplying power to these five commercial ranges must be
capable of carrying a load of at least 42 kW
Non-Dwelling Buildings Load Calculations- Part Six
In Article " Non-Dwelling Buildings Load Calculations- Part One ", I introduced a
List for ordinary Non-Dwelling Buildings Loads which was as follows:
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
1. Schools,
2. Existing Installations,
3. New Restaurants.
I explained the Design Calculation for first type of Non-Dwelling Building loads which is
Lighting loads in Article " Non-Dwelling Buildings Load Calculations- Part One ",.
Also, I explained Design Calculation for second type; Receptacle loads for Non-
Dwelling Buildings in Articles:
And I explained the third type of Non-dwelling Loads; Kitchen Loads in Article " Non-
Dwelling Buildings Load Calculations- Part Five ".
Today, I will explain the Design Calculation of Heating, Ventilation and Air
conditioning Loads (Non-Coincident Loads) in Non-Dwelling Building.
You can review our course " Introduction to Heating, Ventilation and Air
Conditioning Systems " for more information.
Important!!!
Regardless of the type of structure—residential, commercial, or industrial,
the Heating, Ventilation and Air Conditioning Systems will be calculated by
NEC part III (standard method) in the following manner.
Definition:
A heat pump (see below image): a device that acts as an air conditioner in
the summer and as a heater in the winter. Heat pumps look and function
exactly like an air conditioner except it has a reversible cycle.
Important!!!
Most service load calculations will include heating and/or air conditioning
equipment, but not all feeder load calculations will include these types of
loads. If the feeder will not supply power to heating and air conditioning
equipment, calculate just the general loads on this feeder. If a service will
not supply heating equipment calculate only the service for air condition
only. If a service will not supply power to heating and air conditioning
equipment, ignore this load in service load calculation.
Important!!!
Cord and plug space heaters are not a permanent fixed heaters, then it will
not be included in load calculation in this step.
Fixed heating equipment, such as central heating systems, boilers, heating
cable, and unit heaters (baseboard, panel, and duct heaters) will be
included.
Important!!!
Fixed electric space heating shall be considered continuous load.
Example#1:
An Office has seven wall heaters; each heater is rated 3,000 watts at 240 volts. How
much load will these heaters add to a 240-volt, single-phase service? Assuming that
The air conditioning load will be less than the heating load.
Solution:
In accordance with 220.51, calculate the heaters service load at 100 %= 7 × 3,000 =
21,000 watts
Since the service voltage is known, the total current draw of the heaters can be
calculated by dividing the total watts by 240 volts
Central air conditioning and heating system Load shall be calculated at 100
% of its nameplate and will be a Noncoincident Load.
Important!!!
Depending on the design, the heating system and the air conditioning
system might be noncoincident loads.
Example#2:
What is the service load contribution for an Office Building that will have electric
space heaters and window air conditioners?
The heat will consist of two offices with space heaters rated 1,500 watts each and
three offices with space heaters rated 2,250 watts each.
The air conditioning will consist of four offices with window air conditioning units
rated 11.5 amperes at 240 volts. Assume space-heating watts are equivalent to volt-
amperes (VA).
Solution:
In this Office Building, the heat load and the air conditioning load are noncoincident
loads. The heat and the air conditioning will not be energized at the same time.
Therefore, compare the total heat load to the total air conditioning load and omit the
smaller of the two loads.
The total heat load = 1,500 + 1,500 + 2,250 + 2,250 + 2,250 = 9,750 VA.
Start by finding the volt-amperes of each unit (VA = E × I) (assume power factor or PF
= 1.0).
The service load contribution for the heating and air conditioning loads in this Office
Building is 11,040 VA
If the air conditioner compressors are the largest motors in this Office Building,
multiply the load of one compressor by 25 percent and add it to the service load
calculation.
Rule#5: the air handler (or blower motor) is not a noncoincident load
Although the heating and air conditioning in package units and split systems
are noncoincident loads, the air handler (or blower motor) (or evaporator
motor) is not. Since the blower motor works with both the heating and air
conditioning system, it must be included in both calculations.
Example#3:
Solution:
The full-load current in amperes of a ½ hp, single-phase, 240-volt motor (from Table
430.248) = 4.9 A
The service load for this package unit = 1,176 + 9,600 = 10,776 watts
Example#4:
A package unit has electric heat and air conditioning. The unit contains a compressor,
a blower motor, a condenser fan motor and electric heat. The compressor draws 23
amperes at 240 volts, the blower motor draws 5 amperes at 240 volts and the
condenser fan motor draws 2 amperes at 240 volts. The rating of the heat is 10 kW.
Assume heating kilowatt rating is equivalent to kilovolt-amperes. What is the service
load contribution for this heating/cooling package unit?
Solution:
Since the blower motor also works with the heat, the load of the blower motor must
be added to the heat load.
Since the heat load is larger than the air conditioner load, omit the air conditioner
load. The service load contribution for this package unit is 11,200 VA.
Important!!!
Unless it is the largest motor in the feeder or service load calculation, do
not multiply the full-load current of the motor by 125 percent.
Example#5:
In example#3, the blower motor in the heating/cooling package unit will be the
largest motor. How much load will this package unit add to a 240-volt, single-phase
service?
Solution:
If the ½ hp blower motor is the largest motor in the calculation for the service, the
ampacity must not be less than 125 percent of the full-load current rating plus the
calculated load of the electric heat.
Multiply the motor’s full-load current by 125 percent before adding it to the electric
heat service load
The service load for this package unit = 1,176 x 1.25 + 9,600 = 11,070 watts
With a heat pump, the compressor (and accompanying motors) and some or
all of the electric heat can be on at the same time. The load contribution of
a heat pump is the air conditioning system load plus the maximum amount
of heat that can be on while the air conditioner compressor is on.
Example#6:
What is the service load contribution for a heat pump with supplementary heat? The
compressor draws 26.4 amperes at 240 volts, the blower motor draws 6.5 amperes at
240 volts and the condenser fan motor draws 3 amperes at 240 volts. The electric heat
in this unit has a rating of 15 kW. Assume heating kilowatt rating is equivalent to
kilovolt-amperes.
Solution:
The compressor and all of the heat in this heat pump can be energized at the same
time.
Since the air conditioning system and all of the heat can be on at the same time, add
the two together to get the service load contribution.
The service load contribution for this heat pump = 8,616 + 15,000 = 23,616 VA
Important!!!
Noncoincident loads are not limited to heating and air conditioning systems.
Example#7:
What is the feeder load contribution for two 5-hp, 230-volt, single phase pump motors?
The motors will be wired so only one motor is in operation at any time.
Solution:
Because these two motors are noncoincident loads, it is permissible to omit the load
of one motor.
1. Lighting loads,
2. Receptacles Loads,
3. Kitchen Loads,
4. Heating, Ventilation and air conditioning Loads (Non-Coincident Loads),
5. Motor Loads,
6. Other Loads.
Again, but for above Non-Dwelling Buildings Loads, I will explain the following points:
1. Where and how to distribute each type of load in a dwelling unit as per
NEC code?
2. How to calculate its Demand load for feeder and service sizing
calculations?
Important!!!
All design Calculations for Non-dwelling Buildings will be as per NEC
standard calculation method but I will explain design calculations as per NEC
Optional calculation method only for the following Non-Dwelling buildings as
permitted by NEC, Part IV. Optional Feeder and Service Load Calculations:
1. Schools,
2. Existing Installations,
3. New Restaurants.
1- Load Calculation for Lighting Loads of Non-Dwelling Building in Article " Non-
Dwelling Buildings Load Calculations- Part One ".
4- Load Calculation for Heating, Ventilation and Air Conditioning Systems Loads (Non-
Coincident Loads) of Non-dwelling Building in Article " Non-Dwelling Buildings Load
Calculations- Part Six ".
Today, I will explain the Load Calculation for Motor and Other Loads of Non-Dwelling
Building.
Fifth: Motor Loads
Important!!!
Regardless of the type of structure—residential, commercial, or industrial,
the Motors Loads will be calculated by in the same manner.
The motors can be fastened in place appliances or separate motors (air
conditioning compressors, fan blower, etc.)
Important!!!
Most electrical equipment is rated in volt-amperes (VA) or watt input. While
motors traditionally have been rated in horsepower output (Some motors
are available with their output ratings expressed in watts and kilowatts).
As per NEC section 430.6(A)(1), Do not use the actual current rating marked
on the nameplate. When calculating motor loads, use the values given in
Tables 430.247 through 430.250.
Important!!!
Exceptions to 430.6(A)(1) :
1. Motors built for low speeds (less than 1,200 rpm) or high
torques for multispeed motors.
2. For equipment that employs a shaded-pole or permanent-split
capacitor-type fan or blower motor that is marked with the motor
type, use the full load current for such motor marked on the
nameplate of the equipment in which the fan or blower motor is
employed.
3. For a listed motor-operated appliance that is marked with both
motor horsepower and full-load current, use the motor full-load
current marked on the nameplate of the appliance.
Important!!!
Full-load currents for 3-phase motors are in Table 430.250,
Full-Load Current for Two-Phase Alternating- Current Motors (4-Wire) are in
Table 430.249,
Full-load currents for single-phase motors are in Table 430.248,
Full-Load Currents for Direct-Current Motors are in Table 430.247.
Important!!!
Kilovolt-amperes (kVA) shall be considered equivalent to kilowatts (kW) for
Fastened-in-place Appliances.
Important!!!
If the Largest motor is air conditioning compressor, in this case, multiply the
load of one compressor by 25 percent and add it to the service load
calculation
But if the heating load is larger than the air conditioning load, and because
of 220.60 which states that‖ it is permissible to use only the larger of the
noncoincident loads‖ the air conditioning load will be omitted and the air
conditioning compressor will not be the largest motor in this case.
Example#1:
For example, what is the minimum rating in amperes for conductors supplying a 2 hp,
230-volt, single-phase motor?
Solution:
Find the full-load current in amperes for the given motor. As shown in Table 430.248,
the current for a 2 hp, 230-volt motor is 12 amperes.
Example#2:
What is the minimum rating in amperes for conductors supplying a 10 hp, 208-volt, 3-
phase motor and a 7½ hp, 208-volt, 3-phase motor?
Solution:
The full-load current from Table 430.250 for a 10 hp, 208-volt, 3-phase motor is 30.8
amperes. The full-load current from the same table for a 7½ hp, 208-volt, 3-phase
motor is 24.2 amperes.
Multiply the highest full-load current by 125 percent = 30.8 x 125 % = 38.5 A
Now add to this value to the full-load current of the other motor= 38.5 + 24.2 = 62.7 A
So, the minimum rating in amperes for conductors supplying above motors is 62.7 A
Example#3:
what is the minimum rating in amperes for conductors supplying a 5 hp, 230-volt, 3-
phase motor; a 10 hp, 230-volt, 3-phase motor; a 15 hp, 230-volt, 3-phase motor; and
a 10 hp, 230-volt, single-phase motor?
Solution:
Full-load currents for 3-phase motors are in Table 430.250, and full-load currents for
single-phase motors are in 430.248.
The full-load current for a 5 hp, 230-volt, 3-phase motor is 15.2 amperes;
And the full-load current for a 10 hp, 230-volt, single-phase motor is 50 amperes
Although the 15 hp motor has the largest amount of horsepower, the motor with the
highest full-load current rating is the single-phase motor.
Multiply the motor with the highest full-load current rating by 125 percent = 50 × 125%
= 62.5 A Now add to this value to the full-load currents of the other motors = 62.5 +
15.2 + 28 + 42 = 147.7 = 148 A
So, the minimum rating in amperes for conductors supplying these motors is 148 A
Example#4:
Solution:
The full-load current in amperes of a ½ hp, single-phase, 240-volt motor (from Table
430.248) = 4.9 A
The service load for this package unit = 1,176 + 9,600 = 10,776 watts
Because the blower motor is the largest motor in the service load
The service load for this package unit = 10,776 + 1,176 x 25% = 11,070 watts
Example#5:
What is the minimum rating in amperes for conductors supplying a 10 hp, 208-volt, 3-
phase motor and three 3 hp, 120-volt, single-phase motors?
Solution:
The full-load current for a 10 hp, 208-volt, 3-phase motor is 30.8 amperes [Table
430.250].
Full-load currents for single-phase motors are in 430.248. Note that the currents listed
in the 115-volt column are permitted for system voltage ranges of 110 to 120 volts.
Although there are four motors total, there are only two motors on each phase
Because the motors are balanced between phases, the full-load current on each phase
= 30.8 + 34 = 64.8A.
Because the single phase motor is the largest motor, multiply its amperes by 125
percent = 34 × 125% = 42.5 A
Now add to this value the full-load currents of the other motor on the same phase =
42.5 + 30.8 = 73.3 A = 73 A
So, the minimum rating in amperes for conductors supplying these motors is 73 A
Definition:
Continuous Load: A load where the maximum current is expected to
continue for 3 hours or more.
Important!!!
The loads under the following categories are continuous loads :
1. General Lighting,
2. Track Lighting,
3. Show Window Lighting,
4. Sign and Outline Lighting.
While the Loads under the following categories are Not-continuous loads:
1. General-Use Receptacles,
2. Multioutlet Assemblies.
Definition:
All Other Loads: are the loads that don’t falling under one of the following
loads categories:
1. General lighting,
2. Track lighting,
3. Show window lighting,
4. Sign and outline lighting,
5. General-use receptacles,
6. Multioutlet assemblies,
7. Kitchen equipment,
8. HVAC loads,
9. Motor loads.
Rule#5: Other Loads
Example#6:
Solution:
The two loads; Parking- Lot Lighting and Water Heater are not falling under any
category from the definition of All Other Loads.
So, these Loads will be calculated as follows:
Parking- Lot Lighting is a continuous load, multiply its VA by 125% = 57 x 120 x 125% =
8,550 VA
As per NEC section 210.25(B), The systems, equipment, and lighting for
public or common areas are required to be supplied from a separate ―house
load‖ panelboard.
I also indicated that the NEC Optional calculation method can be applied only for the
following Non-Dwelling buildings as permitted by NEC, Part IV. Optional Feeder and
Service Load Calculations:
1. Schools,
2. Existing Installations,
3. New Restaurants.
Today, I will explain the load calculations for these special Non-Dwelling Buildings
(Schools, Existing Installations and New Restaurants) by using NEC optional method.
First: Schools
Important!!!
As with dwellings, there are two methods for calculating services or feeders
for schools as follows:
Rule#1: Condition for Using NEC Optional Load Calculation Method for
Schools
Important!!!
If, by using the NEC Standard Method, the ampacity of an individual feeder
is greater than the ampacity required for the entire building, it shall not be
required that the ampere rating of the feeder be larger than the ampere
rating of the service.
Rule#3: Load Calculation for Portable Classroom Buildings
Although many schools have portable classroom buildings, using the NEC
Optional Method to calculate loads to those portable classroom buildings
shall not be permitted. It must be calculated by NEC Standard Method.
This optional method calculation procedure for schools can be divided into four easy
steps as follows:
Important!!!
The connected load shall include all of the interior and exterior lighting,
power, water heating, cooking, other loads and the larger of the air
conditioning load or space heating load within the building or structure.
Important!!!
When calculating the total load of a school note the following:
Use only 100 percent of the load,
Do not multiply continuous loads by 125 percent,
Do not derate receptacle loads,
Do not derate cooking equipment,
Do not increase the largest motor by 25 percent.
Step#2: find the average volt-ampere per square foot (VA/ft2).
Step#4: multiplying the derated volt-ampere per square foot by the square-foot area
of the school to get the new derated feeder or service load of the school.
Example#1:
What is the service load calculation for a school with a total connected load of 750
kilovolt-amperes (kVA) and a floor area of 30,000 square feet?
Solution:
The average volt-amperes per square foot = 750,000 VA ÷ 30,000 ft2 = 25 VA/ft2
After applying the demand factors in table 220.86, the VA/ft2 = 3 + 12.75 + 1.25 = 17
VA/ft2
Step#4: multiplying the derated volt-ampere per square foot by the square-foot area
of the school to get the new derated feeder or service load of the school.
derated service load of the school = 17 VA/ft2 x 30,000 ft2 = 510,000 VA = 510 KVA
Important!!!
there are two methods for calculating services or feeders for Existing
Installations as follows:
Important!!!
For condition#1 in Rule#5 above, If the maximum demand data for a 1-
year period is not available, the calculated load shall be permitted to be
based on the maximum demand (measure of average power demand over a
15-minute period) continuously recorded over a minimum 30-day period
using a recording ammeter or power meter connected to the highest loaded
phase of the feeder or service, based on the initial loading at the start of
the recording. The recording shall reflect the maximum demand of the
feeder or service by being taken when the building or space is occupied and
shall include by measurement or calculation the larger of the heating or
cooling equipment load, and other loads that may be periodic in nature due
to seasonal or similar conditions.
Important!!!
For condition#2 in Rule#5 above, apply the NEC standard Calculation
method to get the total load as follows:
Important!!!
If condition#2 in Rule#5 above is not verified, you need to increase ampacity
of the feeder and/or rating of the service to be able to add new loads to an
existing dwelling unit.
Example#2:
A business owner wants to add equipment to an existing building. The new equipment
will not replace any of the existing equipment. The existing service has a rating of
1,200 amperes (A). A peak-demand meter has been connected to the service for more
than a year. The maximum demand data from the peak-demand meter shows a
demand of 743A.
The new equipment that has a calculated load (in accordance with standard load
calculation procedures) of 251A. Does this existing service have an ampere rating high
enough for the existing loads and the new loads?
Solution:
Existing Load Value = Max demand Value for a 1-year period from 220.87(1) x 125% =
743 x 125% = 929 A
New Service Load = Existing Load Value + New Load = 929 + 251 = 1,180 A
Since the existing service is rated 1,200A, this installation will be Code-compliant
Third: New Restaurants
Important!!!
As with dwellings and schools, there are two methods for calculating
services or feeders for New Restaurants as follows:
As 220.88 states, instead of using the NEC Standard Method in Part III of
Article 220, the calculation of a service or feeder load for a new restaurant
shall be permitted by the NEC Optional Method in accordance with Table
220.88.
Important!!!
In accordance with section 220.88, The feeder has overcurrent protection in
accordance with 240.4, and the service has overload protection in
accordance with 230.90.
Important!!!
In accordance with section 220.88, Feeder conductors shall not be required
to be of greater ampacity than the service conductors.
This optional method calculation procedure for New Restaurants can be divided into
four easy steps as follows:
Step#1: Find the new restaurant’s total connected load in kilovolt-amperes (kVA).
Important!!!
In accordance with the note under Table 220.88, the total connected load
must include all electrical loads, including both heating and cooling loads.
Important!!!
When calculating the total load of a new restaurant note the following:
Step#2: determine the type of the new restaurant: all electric and not all electric. If
it is all electric, use the second Column of table 220.88. If it is not all electric, use the
third column.
Step#3: Once the new restaurant’s total connected load has been calculated, select
the row with the range of numbers that includes the total connected load.
Step#4: get the new derated feeder or service load of the new restaurant as follows:
If the connected load is no more than 200 kVA, multiply the calculated load by
80 percent.
If the total connected load is more than 200 kVA, an additional math step is
required as per the appropriate row in table 220.88.
Example#3:
What is the optional method service load calculation for a new restaurant with a total
connected load of 180 kVA? This new restaurant will be all electric.
Solution:
Step#1: Find the new restaurant’s total connected load in kilovolt-amperes (kVA).
Step#2: determine the type of the new restaurant: all electric and not all electric.
The connected load is less than 200 kVA, multiply the connected load by 80 percent
The new derated service load of the new restaurant = 180 x 80% = 144 kVA
Example#4:
What is the optional method service load calculation for a new restaurant with a total
connected load of 394 kVA? This new restaurant will be all electric.
Solution:
Step#1: Find the new restaurant’s total connected load in kilovolt-amperes (kVA).
Step#2: determine the type of the new restaurant: all electric and not all electric.
Step#3: since the total connected load is given = 394 KVA, select the third row (326–
800 KVA).
Step#4: get the new derated service load of the new restaurant as follows:
Now multiply the amount over 325 by 50 percent = 69 KVA x 50% = 34.5 KVA
Finally, The optional method service load calculation for this new restaurant = 34.5
KVA + 172.5 KVA = 207 KVA
Example#5:
What is the optional method service load calculation for a new restaurant with a total
connected load of 455 kVA? This new restaurant will be supplied by natural gas and
electricity.
Solution:
Step#1: Find the new restaurant’s total connected load in kilovolt-amperes (kVA).
Step#2: determine the type of the new restaurant: all electric and not all electric.
Step#3: since the total connected load is given = 455 KVA, select the third row (326–
800 KVA).
Step#4: get the new derated service load of the new restaurant as follows:
Calculate the amount over 325= 455 – 325 = 130 KVA
Now multiply the amount over 325 by 45 percent = 130 KVA x 45% = 58.5 KVA
Finally, The optional method service load calculation for this new restaurant = 58.5
KVA + 262.5 KVA = 321 KVA
Important!!!
Farms usually have a dwelling unit and one or more additional buildings or
structures (Other than dwelling units). So, Total Farm load will include two
loads; Farm Dwelling Load and Farm Loads.
Rule#1: Farms Electrical Load Calculations
As per NEC Part V of Article 220, Farms Electrical Load Calculations will vary
based on the existing case of the following:
Case#1: If the Farm Dwelling load and Farm Loads are supplied by
separate services
Case#2: If the Farm Dwelling load and Farm Loads are supplied by one
Common service.
Case#1: If the Farm Dwelling load and Farm Load are supplied by separate services
As per NEC section 220.102(A), If the Farm Dwelling load and Farm Load are
supplied by separate services, calculate the Farm dwelling Load by either
Standard NEC Method in (Part III of Article 220) or Optional NEC Method
(Part IV of Article 220).
As per NEC section 220.102(B), If the Farm Dwelling load and Farm Load are
supplied by separate services, and Where a feeder or service supplies a farm
building or other load that has two or more separate branch circuits, the
load for feeders, service conductors and service equipment shall be
calculated in accordance with demand factors not less than indicated in
Table 220.102.
Procedures for calculating Farm Loads (Other Than Dwelling) with separate service
Calculating Farm Load (Other Than Dwelling) as per Table 220.12 will be done in four
steps as follows:
Step#1: compare the three following loads and select the largest:
Step#4: the service or feeder Loads for Farm Load = Sum of all loads from steps#1,2
and 3.
Example#1:
A farm dwelling and farm building will be supplied by separate services. What is the
minimum size service for the farm loads? The total ampere rating for all the farm
loads (including simultaneously operated loads) will be 385 amperes (A). All the loads
that are expected to operate simultaneously will have a total rating of 65A. The
largest motor will be a 10 horsepower (hp), 240-volt (V), single-phase motor. The farm
service will be supplied by a 120/240V, single-phase system.
Solution:
Calculate the service for this farm equipment in accordance with Table 220.102.
Step#1: compare the three following loads and select the largest:
a- All the loads that are expected to operate simultaneously will be 65A.
b- In accordance with Table 220.102, multiply the full-load current of the largest
motor by 125 percent. The full-load current for the 10-hp motor (from Table 430.248)
is 50A. After multiplying by 125 percent, the rating is = 50 A x 125% = 62.5 A
After comparing the three, the largest is 65A. This load will be added to the
calculation at 100 percent.
Step#4: the service or feeder Loads for Farm Load = Sum of all loads from steps#1, 2
and 3
The total rating after applying the demand factors = 65 + 30 + 65 = 160 A
This rating is not a standard rating. In accordance with 240.6(A), the next standard
ampere rating higher than 160 is 200.
So, the minimum size service for the farm loads in this example is 200 A.
Case#2: If the Farm Dwelling load and Farm Load are supplied by one Common
service.
As per NEC section 220.102(A), If the Farm Dwelling load and Farm Load are
supplied by separate services, calculate the Farm dwelling Load as per
below Table and according to existing case.
As per NEC section 220.103, If the Farm Dwelling load and Farm Load are
supplied by one Common service, apply demand factor of Table 220.103 for
calculating the total Farm load.
Important!!!
For Rule#5 above, the largest Motor Load must be multiplied by 125% before
applying demand factors of table 220.103.
Rule#6: Common Service Farm Load
As per Note under Table 220.103, Common Service Farm Load = Total Farm
Loads (calculated as per Rule#5 in above) + Farm Dwelling Load (calculated
as per Rule#4 in above)
Example#2:
One service will supply both a farm dwelling and farm equipment. What is the
minimum size service for the following loads? All the loads that are expected to
operate simultaneously will have a total rating of 60 amperes (A). The largest motor
will be a 10 horsepower (hp), 240-volt (V), single-phase motor. Another load will be
50A. The remaining loads will be 92A. The total load for the dwelling, calculated in
accordance with Part III in Article 220, is 110A. A 120/240V, single-phase system will
supply the farm service.
Solution:
Multiply the full-load current of the largest motor by 125 percent. The full-load
current for the 10-hp motor (from Table 430.248) is 50 A. After multiplying by 125
percent, the rating is = 50 A x 125% = 62.5 A.
- The motor load is the largest load. This load will be added to the calculation at 100
percent as per table 220.103.
- The next largest load (all the loads that are expected to operate simultaneously) is
60A.
The second largest load after applying the demand factor of table 220.103 = 60 A x
75% = 45 A
The third largest load after applying the demand factor of table 220.103 = 50 A x 65% =
32.5 A
- The remaining load, after applying the demand factor of table 220.103 = 92A x 50% =
46 A
The total load, after applying the demand factors of table 220.103 = 62.5 + 45 + 32.5 +
46 = 186 A
As specified in the note under Table 220.103, add the total farm loads (after demand
factors) to the farm dwelling unit load.
In this example, the farm dwelling unit was calculated in accordance with Part III in
Article 220 and the load is 110A.
The minimum ampere rating for the dwelling unit and farm equipment = 186 A+ 110 A=
296 A
This minimum rating is not a standard rating in accordance with 240.6(A). The next
standard ampere rating higher than 296 is 300.
So, the minimum size service for the farm loads and dwelling unit load in this example
is 300 A.
Example#3:
What is the minimum size service for a farm that will have the dwelling unit and four
barns supplied by the one service? The total load for the dwelling, calculated in
accordance with Part III in Article 220, is 147A. The barn loads are as follows: barn 1 =
103A; barn 2 = 84A; barn 3 = 72A; and barn 4 = 62A. A 120/240V, single-phase system
will supply the farm service.
Solution:
Calculate the barn loads separately from the dwelling unit load then multiply the barn
loads by the demand factor percentages in Table 220.103.
The largest load after applying the demand factor of table 220.103 = 103 A x 100% =
103 A
The second largest load after applying the demand factor of table 220.103 = 84 A x
75% = 63 A
The third largest load after applying the demand factor of table 220.103 = 72 A x 65% =
46.8 A
The remaining load, after applying the demand factor of table 220.103 = 62A x 50% =
31 A
The total load after applying the demand factors = 103 + 63 + 46.8 + 31 = 243.8 A
Now add the total farm loads (after demand factors) to the farm dwelling unit load.
The dwelling unit load is 147A.
The minimum ampere rating for the dwelling unit and the four barns = 243.8 + 147 =
390.8 A = 391 A
This minimum rating is not a standard rating in accordance with 240.6(A). The next
standard ampere rating higher than 391 is 400.
So, the minimum size service for the farm loads in this example is 400 A.
Important!!!
At the neutral point of the system, the vectorial sum of the nominal voltages from
all other phases within the system that utilize the neutral, with respect to
the neutral point, is zero potential.
In some type of delta system, not all phases utilize the neutral; as in below
image where phase (B) does not utilize the neutral.
Important!!!
The neutral load must be calculated in accordance section 220.61 even if the
feeder or service is calculated by the NEC standard method (Part III) or the NEC
optional method (Part IV).
As per NEC section 220.61(A), The feeder or service neutral load shall be the
maximum unbalance of the load determined by article 220. The maximum
unbalanced load shall be the maximum net calculated load between the neutral
conductor and any one ungrounded conductor.
For 3-wire, 2-phase or 5-wire, 2-phase systems, the maximum unbalanced load
shall be the maximum net calculated load between the neutral conductor and any
one ungrounded conductor multiplied by 140 percent.
Important!!!
When calculating the neutral load, it is not necessary to include loads that do not
contribute to the neutral current.
Example#1:
Solution:
Since the water heater is 240 volts, it will not contribute to the neutral current.
Therefore, 19 amperes can be omitted from the neutral load calculation.
The neutral load = highest calculated load – water heater Load = 92 – 19 = 73 amperes
Although the feeder conductors must have an ampere rating of at least 92 amperes,
the conductor feeding the neutral must have an ampacity of at least 73 amperes.
As per NEC section 220.61(B)(1), When calculating the feeder or service neutral
load, it is permissible to apply a demand factor of 70 percent to household electric
ranges, wall-mounted ovens, counter-mounted cooking units and electric dryers,
where the maximum unbalanced load has been determined in accordance with
Table 220.55 for ranges and Table 220.54 for dryers.
Example#2:
What is the minimum neutral load on the service for 5,500-watt clothes dryer installed
in a one-family dwelling?
Solution:
When calculating feeder or service neutral loads for clothes dryers, start by finding
the feeder or service load.
As per Table 220.54, because there is only one dryer, the minimum service load (at
100 percent) is 5,500 volt-amperes
Apply Rule#2 above; multiply the service load by 70 percent.
So, the minimum neutral load on the service = 5,500 VA × 70% = 3,850 VA
Example#3:
A 10-unit apartment building will have a 12-kW range in each apartment. What load
will these ranges add to a service neutral calculation?
Solution:
As per NEC section 220.61(B)(2), Where the calculated neutral current is more than
200 amperes, another reduction is permitted. Where the feeder or service is
supplied from a three-wire DC or single-phase AC system; a four-wire, three-phase,
three-wire, two-phase system; or a five-wire, two-phase system, it is permissible
to apply a demand factor of 70 percent to that portion of the unbalanced load in
excess of 200 amperes [220.61(B)(2)]. This demand factor is also in addition to any
demand factors that may have already been applied.
Example#4:
After calculating the service load for an office building by the NEC Standard
calculation, the neutral load is 216,000 volt-amperes. What is the neutral load after
applying the demand factor from 220.61(B)(2)? The electrical service will be supplied
by a 208Y/120-volt, three-phase, four-wire system.
Solution:
The demand neutral Load in excess of 200 amperes = 400 A × 70% = 280 A
Definition:
Nonlinear Load: A load where the wave shape of the steady-state current does not
follow the wave shape of the applied voltage.
Important!!!
As per Rule#3 above, where the feeder or service-neutral load exceeds 200
amperes, it is permissible to apply an additional demand factor of 70 percent to
that portion of the unbalanced load in excess of 200 amperes. But, As per Rula#5,
applying the 70 percent demand factor to reduce the neutral or grounded
conductor’s capacity is not permissible for that portion consisting of nonlinear
loads supplied from three-phase, 4-wire, wye-connected systems .
Example#5:
After calculating the service load for an office building by the basic calculation, the
neutral load is 216,000 volt-amperes. The major portion of the neutral load is
fluorescent luminaires and information technology equipment. The electrical service
will be supplied by a 208Y/120 volt, three-phase, 4-wire system. After demand
factors, what is the neutral load in amperes?
Solution:
Important!!!
If the neutral load calculated as per 220.61 is less than the calculated load of the
ungrounded (hot) conductors, it might be possible to reduce the size of the feeder
or service-neutral conductor to be smaller than the ungrounded conductors size,
but this is not a must, The installed neutral conductor can be the same size as the
ungrounded conductors.
Compare the minimum size required for the neutral calculated load with the
minimum size equipment-grounding conductor from table 250.122 (in below
image); then, select the larger of the two to be the size of the neutral conductor.
Example#6:
Based on the calculated neutral load only, the minimum size conductor from Table
310.16 is 4 AWG. (See image for table 310.16)
The neutral conductor must not be smaller than the required grounded electrode
specified in table 250.66 (in below image).
Electrical Rules and Calculations for Air-Conditioning
Systems – Part One
This is the first Article in our new Course HVAC-2: Electrical Rules and Calculations
for Air-Conditioning Systems, which will list, explain, and discuss with examples all
the topics covering the Electrical Rules and Calculations for Air-Conditioning Systems
which will include but not limited to the following points:
Introduction for Air-Conditioning Systems types,
Introduction for Types of Motors/compressors used for Air-Conditioning
Systems,
Electrical Wiring for different Air-Conditioning Systems types,
Types and locations of Disconnecting means,
Sizing of Disconnecting means,
Types of motor-compressor controllers,
Sizing of motor-compressor controllers ratings,
Sizing feeder/branch circuit overcurrent protective devices (OCPDs),
Sizing feeder/branch circuit conductors,
Sizing motor-compressor overload protection.
1. Heating systems,
2. Cooling systems.
Here, we are interested in the cooling systems or what we will called ― Air
Conditioning systems‖ in this course, which in turn divided to (4) sub-main
systems:
A- Unitary packaged systems (one pipe systems) which can be divided to:
Roof top packaged units (RPU) are an all in one air cooled A/C unit that
are installed on top of the roof and can provide cooling and heating. The
condensing unit and the air handler reside inside a single housing. In order to
connect the unit to the inside duct work, an opening on the roof for supply and
return air is necessary. The duct work distributes the air evenly through-out
the space. Heating can be provided by reversing the condensing unit (heat
pump) or connecting an electric heater, gas heater, or steam coil.
Indoor package units (IPU) are similar to rooftop units, but because the
unit is located inside, it requires a different way of cooling the condensing
unit. The most common way, is air-cooled using louvered openings (horizontal
angled slats that prevent outside weather to come inside, but allow air flow) to
get fresh outside air. In situations where there is no access to fresh outside air,
water cooled units are the best solution. Indoor units come in vertical, or space
saving horizontal configurations. These units are the same as roof top units in
the way they connect to duct work and have the same heating options as
mention in the roof top packaged units.
You may also have multiple air handlers connected to one condensing unit in
computer controlled split systems.
For more information about Special systems, please review Article " Air
Conditioning System Configurations – Part Three ".
Second: Introduction for Types of Motors/Compressors used in Air-
ConditioningSystems
A- Positive-Displacement Compressors:
1. Reciprocating compressors,
2. Screw Compressor,
3. Scroll Compressors.
B- Dynamic Compressors:
1. Centrifugal Compressors.
Reciprocating compressors are driven by a motor and use pistons, cylinders and
valves to compress the refrigerant. Reciprocating compressors are usually used
in smaller systems up to 100 tons.
These compressors are available in (2) configurations namely:
Construction:
Usage:
Capacity:
They are smaller, more compact and have less vibration than the open
compressor,
They have no external shaft; this eliminates mechanical problems with
shafts, belts, and sheaves and concern of refrigerant leakage,
In a hermetic unit the motor is located within the refrigerant
atmosphere. So, the motor is continuously cooled by the refrigerant vapor
flowing to the compressor section valves,
Lubrication is also simplified since both the motor and the compressor
operate in the same closed space with the oil.
The shaft is shorter and more rigid, the bearing arrangement is
simplified, the machine is quieter.
Construction:
Welded, hermetic machines are used for the smaller duties, up to about
70 kW of refrigeration and bolted, semi-hermetics are used for larger loads.
Packaged, water chilling units having multiple, semi-hermetic compressors are
used with capacities up to about 700 kW of refrigeration.
Construction:
Important Notes
1- Compressor Capacities:
In Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
One ", which was the first Article in our new Course HVAC-2: Electrical Rules and
Calculations for Air-Conditioning Systems, I explained the following points:
Today, I will explain Electrical Wiring for different Air-Conditioning Systems types.
In the detailed design phase, the electrical designer must size and select the
wires/cables, conduits, starters, disconnects and switchgear necessary for
supplying power and control to HVAC equipment. This information designed by the
electrical designer will be and must appear on the electrical drawings for proper
installation by the electrical contractor.
So, to determine the electrical equipment and power supply required for the HVAC
system proper operation, the electrical designer needs:
Knowing the size of the HVAC system (equipment types, locations, …),
Understanding how different HVAC equipment operates in a certain HVAC
system.
The above points can be fulfilled by understanding the electrical wiring diagram of
individual HVAC equipment and of the whole system also.
Note:
Also the HVAC designer will need to know the size of the electrical loads to assess
the impact of the heat generated by the electrical system on the HVAC load.
There are three basic types of wiring diagrams used in the HVAC/R industry today,
which are:
It is the most common type of wiring Diagrams. It is called ladder because the symbols
that are used to represent the components in the system have been placed on the
rungs of a ladder. ladder diagrams will be referred to as ―schematic‖ diagrams, or
simply ―schematics.‖ A typical schematic of a packaged air conditioner is shown
in Fig.3.
Fig.3
In electrical schematics, the symbols stand for various components in the circuit, and
the lines stand for the wires connecting them. The intention of the overall schematic
is to show how the circuit functions, not how it actually looks.
Note:
Before you begin looking at electrical schematic diagrams, though, remember that
there are always five basic components to any schematic:
1. A power supply,
2. A path for the power,
3. A load or component that operates from the power,
4. A switch or component that interrupts the power to the load,
5. A legend (see Fig.4)or key that explains what the various symbols and
abbreviations used in the wiring diagram.
Fig.4
In order to read electrical Schematics, you need to be familiar with the following:
Power Supplies,
Wiring,
Switches,
Loads.
A- Power Supplies: (see Fig.7)
Many different supply voltages are used in the HVAC/R industry, ranging from 575-V,
three-phase power supplies to 24-V control circuit voltages. Power supplies may be
indicated by solid lines or by dashed or dotted lines.
Fig.7
B- Wiring:
Most schematics use straight lines to represent the wires that connect
components to each other.
If two wires are connected internally, the connection usually is shown as a dot
(a solid black circle), as illustrated at those points marked ―A‖ in Fig.8.1. But note
that there is no dot to indicate a junction or connection at point ―B.‖ This means that
one wire simply crosses over the other wire.
Fig.8
Now look at Fig.8.2, crossover wires are shown with half circles or loops that
―jump‖ over other wires (see those points marked ―A‖). Note also that in this type of
diagram, junctions are shown without connection dots (see those points marked ―B‖).
Notes:
Not all manufacturers follow the same schematic diagram practices and you
will see several different styles of wiring diagrams.
If dots are used to show junctions, then intersecting lines without dots mean
that the two wires cross without connecting. If loops or jumps are used to depict
crossovers, then wires that meet—even without dots—are connected.
Every manufacturer can identify the wires used in electrical diagrams by one of the
following methods:
1. Using Different line thicknesses to represent different types of wires.
2. Using numbers or colors (or both) to help identify the various wires
found in a unit .
Fig.9
Note:
The used wiring identification method should be clearly indicated in the legend that
accompanies the drawing.
C- Switches:
A switch is a device that interrupts power to the load. It may be:
The switch can be in the closed position (Normally closed) (N/C) or in the open
position (Normally open) (N/O) (see Fig.10). You must note that in electrical wiring
schematic the position of the switch is shown as it appears when there is no power
applied to that circuit. If there is any deviation from this practice, there will be an
explanatory note on the schematic.
Fig.10
Fig.11
Note:
The dashed line in the switch symbols represents the mechanical connection that
makes the contacts move together, but these contacts are not connected electrically.
Pressure and temperature controls are switches; they also may be configured with
various combinations of poles and throws.
The position of the switch ―arm‖ in the schematic symbol indicates the operation of
the control. for examples: (see Fig.12)
Fig.12
The temperature switch (RS-2) is shown with the arm above the contacts. This
signifies that the switch opens on a rise in temperature and closes on a drop in
temperature.
The pressure switch (AFS-2) is shown with the arm below the contacts. This
signifies that the switch opens on a drop in pressure and closes on a rise in pressure.
For SPDT limit switch (LS), When there is an increase in temperature, the
contacts ―C‖ to ―N/C‖ move to the ―N/O‖ position. When the temperature decreases,
the contacts ―C‖ to ―N/O‖ move back to the ―N/C‖ position.
C.3 Electrically Controlled Switch:
a- Relays:
Relays are electrically operated control switches. The schematic symbols used
to represent relays are the same as those for manually operated switches, except that
relay symbols often include a solenoid coil.
There are several possible ways of depicting the solenoid coil. Fig.13 shows
two different schematic representations of a DPDT relay.
Fig.13
b- Contactors:
A contactor is a type of heavy-duty relay that handles higher voltages and
higher currents than a control relay. Contactors appear nearly identical to relays on
schematic diagrams.
Some manufacturers employ contactors that use a single set of contacts. A
―bus bar‖ is placed over the connection where the other set would be, as shown
in Fig.14.
Fig.14
D- Loads:(see Fig.15)
Loads are devices that consume power and convert it to some other form of energy,
such as motion or heat. They may be motors, heaters, lights, or other pieces of
equipment. A transformer is a type of power-consuming device, but rather than
converting energy, a transformer changes the voltage or current.
Fig.15
There are two basic configurations used in schematics today to show the approximate
placement of loads, switches, and different power or supply voltages. They are
: (see Fig.16)
1. Side-by-Side Arrangement,
2. Up-and-Down Arrangement.
A- Side-by-Side Arrangement:
As in roadmaps, almost all mapmakers place numbers and/or letters along the vertical
and horizontal edges of maps to help users find particular cities, towns, landmarks, or
other locations. Electrical schematics utilize a similar system.
Take a look at Fig.18. This is the same schematic of a packaged air conditioner that
you saw inFig.3, but notice that now a column of small numbers has been added,
running down the left hand side of the diagram. These numbers are used to indicate
the relative location of each horizontal line in the diagram.
Fig.18
Note:
If a line falls between two numbers, the number lower on the page generally is used as
the location reference.
This type of line-numbering system can be very useful in helping the reader identify
the location of a specific component on the schematic, as well as its controlling
switch. For examples:(see Fig.19)
Fig.19
In Fig.19A, ―C1‖ contacts are located on lines 7 and 11. Similarly, in Fig.19B, you can
find the high voltage switches ―IFR‖ and ―C1‖ on lines 28 and 35, respectively. Now
look at the lower portion of the wiring diagram in Fig.18 and locate the relay coils
―IFR‖ and ―C1‖ on lines 52 and 57.
B- Numbers on Right hand side of the diagram:
In Fig.19C, note that there are small numbers along the right hand side of the diagram
as well. These numbers designate the line location of relay contacts. The small
number 28 in the right-hand margin tells you the line location of the contacts
associated with relay coil ―IFR.‖ Look back at line 28 in Fig.19B, and you will find the
―IFR‖ contacts. Likewise, the numbers 7, 11, and 35 in the right-hand margin
of Fig.19C refer you to the lines where the contacts associated with relay coil ―C1‖
can be found.
C- Underlined Numbers:
In Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
One ", which was the first Article in our new Course HVAC-2: Electrical Rules
and Calculations for Air-Conditioning Systems, I explained the following points:
And in Article " Electrical Wiring Diagrams for Air Conditioning Systems – Part One ",
I explained the following points:
Importance of Electrical Wiring for Air Conditioning Systems,
How to get the Electrical Wiring for Air Conditioning systems?,
Types of Electrical Wiring Diagrams For Air Conditioning Systems,
How to read Electrical Wiring Diagrams?
Today, I will explain Electrical Wiring for different Air-Conditioning Systems Types
and Equipment.
The main types and equipments in common Air conditioning systems were:
Window air conditioning unit casing houses the following components: (see Fig.1)
Fig.1: Window Air Conditioning Units Construction
The Window air conditioning units are fed from single phase power source
(see Fig.3), so its branch circuit and its main power cord consisting of 3 wires (The
ground wire, hot wire and neutral wire).
The branch circuit will originate from one of the single pole Overcurrent
protective device OCPD included in an electrical panel.
Then go through raceway system (conduits, ducts, …) to a disconnect means of
some type suitable for the application .
Finally, the main power cord of the Window air conditioning unit is connected
to this disconnecting means from one side, the other side enters the casing of the unit
to be connected to the unit’s terminal box.
1.3 Electrical wiring connections inside The Window air conditioning units
Here we are interested on how the main power cord is connected inside the unit and
this can be explained as follow (see Fig.4):
Fig.4: Window Air Conditioning Unit Internal Electrical Wiring
1. The ground wire (either green or a bare wire) is screwed to the metal
casing of the unit.
2. Hot wire
3. Neutral wire.
B- Hot wire goes to the selector switch on a window unit to feed power to the vital
parts, compressor and fan motor as follows:
C- Neutral wire will be connected to fan motor and compressor without goes
through any switch. These connections are made on the wire connector in the
back of the selector switch so, all neutral wires are common to each other
because they are connected to the same point.
some examples for the complete electrical wiring diagrams for Window Air
Conditioning Unit are inFig.5.
Fig.5: Window Air Conditioning Unit Electrical Wiring Diagrams
Also, in Fig.6, you can find examples for the complete wiring diagrams for Window Air
Conditioning Unit which be mounted on the unit casing.
Fig.6: Window Air Conditioning Unit Electrical Wiring Diagrams - Factory built-
in
also, you can find examples for the complete wiring diagrams for Window Air
Conditioning Unit, touch and remote control type in Fig.7.
Fig.7: Window Air Conditioning Unit Electrical Wiring Diagrams - Touch and
Remote Control Type
1.4 The power flow inside a Typical Window air conditioning unit in the cooling
mode
When you turn the selector switch to cool mode, the power that came in
from the cord that connected to the selector via hot wire goes to the fan so the fan
operates.
The selector switch also sends the power via hot wire to the compressor,
but the compressor will not operate until the thermostat comes to the on position,
then the compressor will operates and the cooling cycle begin.
The split systems are individual systems in which the two heat exchangers are
separated (one outside, one inside) (see Fig.8). There are two main parts of the split
air conditioner which are:
Fig.8: Split air Cooling Units Construction
1. Outdoor unit,
2. Indoor unit.
1- Outdoor unit:
This unit is installed outside the room or office space which is to be cooled and houses
important components of the air conditioner like:
The compressor,
Condenser Cooling Fan,
Expansion Valve.
2- Indoor unit:
The most common type of the indoor unit is the wall mounted type though other types
like ceiling mounted and floor mounted are also used. The indoor unit produces the
cooling effect inside the room or the office and houses the following components:
2.2 The power flow in Branch circuit of a Typical split air conditioning unit
Single phase power source (see Fig.9 and Fig.11), so its branch circuit and its
main power cord consisting of 3 wires (The ground wire, hot wire and neutral wire).
Or
Three phase power source (see Fig.12), so its branch circuit and its main power
cord consisting of 5 wires (The ground wire, 3 hot wires and neutral wire).
Fig.9: Split air Cooling Units - Single Phase - Indoor feed Outdoor
Fig.10: Split air Cooling Units - Single Phase - Electrical Wiring
Diagram
Fig.11: Split air Cooling Units - Single Phase - Outdoor feed Indoor
Fig.12: Split air Cooling Units - Three Phase
Fig.13: Split air Cooling Units - Three Phase - Electrical Wiring
Diagram
The branch circuit will originate from one of the single pole/three pole
Overcurrent protective device OCPD included in an electrical panel.
Then go through raceway system (conduits, ducts, …) to a disconnect means of
some type suitable for the application.
After that, the main power cord of the split air conditioning unit is connected
to this disconnecting means from one side, the other side is connected to the terminal
box in the indoor unit (see Fig.9) or in the outdoor unit (see Fig.10)according to the
manufacturer’s recommendations and wiring diagrams.
Note:
if power source connections made in indoor unit, an indoor disconnecting means is
used and if power source connections made in outdoor unit, an outdoor disconnecting
means (see Fig.14) with suitable identity of protection (IP) is used (review the
manufacturer’s recommendations and wiring diagrams).
Finally, the power is transferred via 3-wire cable or 5-wire cable from the
terminal box in indoor unit to the terminal box in outdoor unit or vice versa as
indicated in the above point.
Note:
There is a signal cable also connecting the control in the indoor unit with the control
in the outdoor unit.
2.3 Electrical wiring connections inside The Split air conditioning units
The electrical wiring inside both of indoor and outdoor units is more complicated than
that of window air conditioning units. It is always factory wiring and from our point of
view as electrical power engineers, it will not affect our work at all. However, we
provide some examples for the electrical wiring diagrams including control wiring for
reference as in below Fig.15.
Fig.15: Split air conditioning units - Internal Electrical wiring Diagram
The power wiring for multi-split air conditioners will be as in Fig.17 below.
Fig.17: Multi-split air conditioners Power Wiring
in Fig.18, you can find examples for the complete wiring diagrams for Multi-split air
conditioners.
Fig.18: Multi-split air conditioners Electrical Wiring Diagram
4- Mini- Heat Pumps
The power wiring of Mini- Heat Pumps will look like that of the Split air Cooling
Units for far extent (seeFig.19).
Fig.19: Mini-Heat Pumps
However, you can find in below some examples for wiring diagrams for Mini-
Heat Pumps (see Fig.20) and you can compare them with that of Split air
Cooling Units especially in the power (high voltage) wiring.
Fig.20: Mini-Heat Pumps Electrical Wiring Diagram
A split system describes an air conditioning or heat pump system that is split into
two sections (see Fig.21)which are:
1. Outdoor section,
2. Indoor section.
Fig.21: Split Packaged Units Construction
1- Outdoor section:
The outdoor unit is located outside usually on the ground but sometimes on the
roof. It houses the following components:
Compressor(s),
Condenser coil(s),
Condenser fan(s),
Condenser's fan motor(s),
Fan grille,
Shut off valves,
Reversing valve,
Optional accessories (if any).
2- Indoor section:
The indoor section usually located in an interior closet or garage. It houses the
following components:
Blower(s),
Evaporator coil,
Thermal expansion valve(s) and distributor(s),
Bearings and shaft,
Optional accessories.
The Electrical wiring in Split Packaged units consists of 3 main parts as follows:
The branch circuit will originate from one of the three pole Overcurrent protective
device OCPD included in an electrical panel.
This includes the high voltage wiring inside air handler unit and inside
condenser/evaporator unit.
Inside the air handler unit, the high voltage wiring powers the indoor fan, the
heater and provide power for the transformer.
Inside the condenser/evaporator unit, the high voltage wiring powers the
outside fan and the compressor.
3- Low voltage control part:
1. A/C Mode,
2. Heat Mode.
Via the Y wire to turn on the outside fan and the compressor,
Via the G wire to turn on the indoor fan.
The thermostat usually have (5) positions which are Off – Cold – Auto – Heat – on.
You can find in below some examples for wiring diagrams for split packaged units with
different starting methods in Fig.27.
Fig.27: Electrical wiring of Split Packaged unit with different
Starting Methods
6- Unitary Packaged Units
Unitary packaged systems (see Fig.28) are by far the most commonly used air
conditioning equipment in commercial buildings. A packaged air conditioning unit is a
self-contained air conditioner. It provides the cooling, heating and the motion of the
air. All the components needed for cooling, heating, and air movement are assembled
in a steel casing. Most packaged units use semi hermetic compressors which mean
that the motor and compressor unit are mounted in one housing.
Fig.28: Rooftop packaged units Construction
Electrical Wiring Diagrams for Air Conditioning
Systems – Part Three
In Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
One ", which was the first Article in our new Course HVAC-2: Electrical Rules
and Calculations for Air-Conditioning Systems, I explained the following points:
And in Article " Electrical Wiring Diagrams for Air Conditioning Systems – Part One ",
I explained the following points:
Importance of Electrical Wiring for Air Conditioning Systems,
How to get the Electrical Wiring for Air Conditioning systems?,
Types of Electrical Wiring Diagrams For Air Conditioning Systems,
How to read Electrical Wiring Diagrams?
The main types and equipments in common Air conditioning systems were:
In Article " Electrical Wiring Diagrams for Air Conditioning Systems – Part Two ", I
explained the electrical wiring diagrams for some Typical Air conditioning equipments.
Today, I will explain Electrical Wiring Diagrams for other Typical Air-Conditioning
Equipment.
7- Chillers
Fig.1 below illustrates a typical HVAC system showing water and air heat
exchangers with the main components of the system which are:
Fig.1: Typical HVAC Central System
For more information about Chillers and their types, please review Article
" HVAC Systems Main Equipment ".
A type of condenser where refrigerant flows through the tubes and rejects heat
into a flow of ambient air, most chiller units are fitted with air cooled
condensers.
A type of chiller condenser that uses water to remove heat from the
refrigerant, this is normally a shell & tube type design.
2- Capillary Tube:
3- Compressor:
The main component in a chiller system, the compressor is used to increase the
pressure & temperature of the refrigerant vapour. Compressors are
usually reciprocating, scroll, centrifugal, or rotary screw types.
4- Condenser:
The part of a chiller system where the refrigerant vapour is converted to liquid
as it rejects heat.
5- Distributor:
A device used to supply uniform gas supply through a submerged coil in a tank
chiller evaporator.
6- Evaporator:
The part of the chiller system where cool liquid refrigerant absorbs heat from
the chilled water circuit. It is usually of shell & tube constructions and is the
exchanger where chilled water would be produced.
7- Expansion valve:
A device used to maintain the pressure difference between the high pressure &
low pressure sides of the chiller system.
A device installed in the liquid line to remove moisture and foreign matter,
designed to protect the chillers compressor.
It is used to isolate one part of the chiller system from the rest.
11- Sub-Cooler:
It is the lower portion of the chillers condenser that further cools the saturated
liquid refrigerant.
A section of pipe within the chiller system used to collect the refrigerant
vapour when it leaves the tubes of a submerged coil evaporator
A devise installed into the chillers suction line to remove foreign matter from
the refrigeration system
14- Cabinet:
Cabinet is made from heavy gauge galvanized steel. Steel sheet panels are zinc
coated and galvanized by hot dip process followed by air dry paint or backed on
electrostatic polyester dry powder coat.
The control panel design is equivalent to NEMA 4 (IP55) with hinged door for
easy access ensuring dust and weatherproof construction. Internal power and
control wiring is neatly routed, adequately anchored and all wires identified
with cable markers as per standards applicable to HVAC industry. The electrical
controls, used in the control panel, must be reliable in operation at high
ambient conditions for a long period.
Let’s take an example for Water Chillers like Air cooled screw water chillers
from Cooline Co. model # ASQ115B, the following electrical data for this model
will be as in Fig.5.
And a Typical Schematic Wiring Diagram (Part Winding Start) for this model is
indicated in Fig.7.
Fig.7: Cooline Co. model # ASQ115B -Typical Schematic Wiring Diagram
you can note that Fig.7, Fig.6 and Fig.5 must be identical for:
the number of compressors = 2.
the number of condenser fans = 8.
Also, the Legend, Notes & wiring diagram for optional items used for this model
is indicated in Fig.8.
Field power wiring is a single point connection; Main 3 phase power must be
supplied from a single field supplied and mounted Disconnect switch, using dual
element time delay fuse or circuit breaker with Rating as recommended by
manufacturer. Also, electrical lugs for incoming power are provided by
manufacturer.
B- Connection to the control and monitoring system:
Interlocking connections are needed with water flow switch, pumps, remote
monitoring system and two barrel units water temperature sensor, if any.
8.1 The Field Electrical Wiring for other Major Components in Central HVAC System
Field power wiring for other Major Components in Central HVAC System like Pumps,
Fans and AHUs are also a single point connection as in the case of Chillers but we must
use some type of motor starters or/and Variable frequency drives (VFDs) as follows:
If you will use DOL starters (see Fig.10), you must install a separate Disconnect
switch, using dual element time delay fuse or circuit breaker (see Fig.11) with Rating
as recommended by manufacturer.
Fig.10: Examples for DOL Starters
Fig.11: The Field Electrical Wiring for Loads with DOL Starters and
VFD
And if you use VFD which you must install a separate Disconnect switch, using
dual element time delay fuse or circuit breaker (see Fig.11) with Rating as
recommended by manufacturer.
But if you use DOL combination starters (see Fig.12) which come with a
Disconnect switch or circuit breaker built in the unit (see Fig.13). This will eliminate
the cost of wiring between separate disconnect means and starters.
Fig.12: Examples for DOL Combination Starters
Fig.13: The Field Electrical Wiring for Loads with DOL
Combination Starters
Also, I explained the electrical wiring diagrams for Typical Air conditioning equipments
in the following Articles:
Today, I will explain in detail Different Types, Locations and Sizes of Disconnecting
Means used for HVAC Systems.
In this Article and next Articles, you will learn the following:
And before proceeding with the above points, let’s take a general overview for NEC
Rules controlling motor loads of Air-Conditioning Systems.
Article 210 covers all branch circuits except for branch circuits that
supply only Non-Hermetic Refrigerant Motor-Compressor Loads, which are
covered in Article 430.
Article 430 shall apply where a branch circuit supplies air-conditioning
and refrigerating equipment that does not incorporate a hermetic refrigerant
motor-compressor.
The rules of Articles 422, 424, or 430, as applicable, shall apply to air-
conditioning and refrigerating equipment that does not incorporate a hermetic
refrigerant motor-compressor. This equipment includes devices that employ
refrigeration compressors driven by conventional motors, furnaces with air-
conditioning evaporator coils installed, fan-coil units, remote forced air-cooled
condensers, remote commercial refrigerators, and so forth.
2- Important Definitions
9- A general-use switch:
For stationary motor rated at 2 hp or less and 300 volts or less with the
condition that the switch having an ampere rating not less than twice the full-
load current rating of this stationary motor.
For Torque Motors.
For stationary motors rated at more than 40 hp dc or 100 hp ac, the
general-use switch must be marked ―Do not operate under load.‖
For motors of over 2 hp to and including 100 hp with an autotransformer-
type controller where all of the following provisions are met:
1. The motor drives a generator that is provided with overload
protection.
2. The controller is capable of interrupting the locked rotor current
of the motors, is provided with a no voltage release, and is provided
with running overload protection not exceeding 125 percent of the
motor full load current rating.
3. Separate fuses or an inverse time circuit breaker rated or set at
not more than 150 percent of the motor full-load current is provided in
the motor branch circuit.
10- A general-use snap switch suitable only for use on ac (not general-use
ac–dc snap switches):
Note:
Horsepower-rated attachment plugs, flanged surface inlets, receptacles, or
cord connectors shall not be required for cord-and-plug-connected appliances
in accordance with 422.33, room air conditioners in accordance with 440.63, or
portable motors rated 1⁄3 hp or less.
Note:
Demand factors authorized elsewhere in this Code shall be permitted to be
applied to the rating of a receptacle or of a separable connector.
Note:
If an appliance of more than 1⁄8 hp is provided with a unit switch in below
paragraph, the switch or circuit breaker serving as the other disconnecting
means shall be permitted to be out of sight from the appliance.
These switches are permitted as the disconnecting means where other means
for disconnection are provided in the following occupancies:
A- Multifamily Dwellings:
In multifamily dwellings, the other disconnecting means shall be within the
dwelling unit, or on the same floor as the dwelling unit in which the appliance
is installed, and shall be permitted to control lamps and other appliances.
B- Two-Family Dwellings:
In two-family dwellings, the other disconnecting means shall be permitted
either inside or outside of the dwelling unit in which the appliance is installed.
In this case, an individual switch or circuit breaker for the dwelling unit shall
be permitted and shall also be permitted to control lamps and other
appliances.
C- One-Family Dwellings:
In one-family dwellings, the service disconnecting means shall be permitted to
be the other disconnecting means.
D- Other Occupancies:
In other occupancies, the branch circuit switch or circuit breaker, where
readily accessible for servicing of the appliance, shall be permitted as the
other disconnecting means.
As per NEC 210.4 (B) Each multi-wire branch circuit shall be provided with a
disconnecting means that will simultaneously disconnect all ungrounded
conductors at the point where the branch circuit originates.
In Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
One ", which was the first Article in our new Course HVAC-2: Electrical Rules
and Calculations for Air-Conditioning Systems, I explained the following points:
And in Article " Electrical Wiring Diagrams for Air Conditioning Systems – Part One ",
I explained the following points:
Also, I explained the electrical wiring diagrams for Typical Air conditioning equipments
in the following Articles:
Electrical Wiring Diagrams for Air Conditioning Systems – Part Two
Electrical Wiring Diagrams for Air Conditioning Systems – Part Three
And in Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
Two ", I explained Types of Disconnecting Means for Air-Conditioning Systems
All the disconnecting means (or generally all the overcurrent protective
devices OCPD) in a building’s electrical distribution system are arranged,
with respect to their short circuit ratings /interrupting ratings, in two
combinations as follows:
Each system from the above can consist of all fuses, all circuit breakers, or
a combination of fuses and circuit breakers.
As In Fig.1 , fully rated system has protection devices tested to withstand the
fault current available at their respective applied location.
Fig.1: Example for Fully Rated System
Note:
Breakers and fuses part number listed on the panelboard /switchboard label, or
Tables of available fuse/circuit breaker series rated combinations published by
panelboard and switchboard manufacturers (see Fig.3).
Fig.3: Example for Series Rated Combinations Published by
Panelboard and Switchboard Manufacturers
Based on the above discussion, any disconnect means will be used either in
a fully Rated Combination System or in a Series Rated Combination System
as described in above.
As we stated above that a fully rated system consist of all fuses, all circuit
breakers, or a combination of fuses and circuit breakers. For this reason, we
will explain the identification/Marking of Fuses and Molded Case Circuit
breakers that widely used as disconnecting means for Air conditioning
systems.
Ampere rating,
Voltage rating,
Interrupting rating where other than 10,000 amperes,
Current limiting where applicable,
The name or trademark of the manufacturer.
Fig.5: Fuse Marking
C- Interchangeable Trip
A- General Marking B- Position Indication
Units
Type Designation, On and Off (Open Manufacturer’s
Manufacturer’s and Closed) Name,
Name, Trip and Reset, Ampere Rating,
Voltage Rating, Electrical Frame
Ampere Rating, Operation (On and Off), Designation,
Line and Load Electrical Magnetic
Identification. Operation (Trip and Settings.
Reset).
K- Circuit
J - Fused Circuit
I- Special Markings Breaker/Ground Fault
Breakers
Circuit Interrupter
Non-Conducting Line and Load ―Test‖ Function,
Enclosure, Identification, ―Class A‖
Ventilated Identification of Marking,
Enclosure, Fuses, Instructions,
40°C, No Open Fuse Terminal
Current Limiting, Tripping, Identification,
Class CTL, General Markings. General Markings.
Delta,
2-Pole — 3-Phase
Rated,
3-Pole — 1-Phase
Rated,
4-Pole — 3-Phase
Rated,
Multi-Wire
Circuit,
DC Rated 3-Pole,
100 Percent
Continuous Rated,
SWD,
Independent
Trip,
Special
Characteristics,
For Replacement
Not CTL,
Special Purpose
Not General,
HID,
Remotely
Operated Circuit
Breaker.
L- Circuit N- High-Fault
M- Circuit Breaker
Breaker/Equipment Protectors And
Surge-Protective
Ground Fault Accessory High-Fault
Device
Protection Modules
―Test‖ Function, Types, Type Designation,
Trip Level Voltage Manufacturer’s
Marking, Protection Rating, Name,
Instructions, Maximum Terminations,
Terminal Continuous Operating Circuit Breaker,
Identification, Voltage Rating (MCOV), Interrupting
Use Marking, Nominal Rating.
Discharge Current (In)
General Markings.
Rating,
Short-circuit
Current Rating (SCCR),
General Markings.
P- Circuit Breaker
O- Accessories Q- Circuit Protectors
Adapters
Ratings, Type Designation, Manufacturer’s
Shunt Trip, Manufacturer’s Name,
Separately Name, Voltage Rating,
Shipped, Terminations, Ampere Rating,
External Dropping Circuit Breaker, Reset
Resistor. Instructions. Instructions.
1. ON and OFF:
The ON and OFF (closed and open) positions of the handle must be marked
(NEC 240.81). These positions may also be marked with the internationally
recognized ―I‖ and ―O‖ symbols, although this is not a UL requirement. If these
markings are not visible when a motor operator is installed over the circuit
breaker markings, then they must appear on the motor operator. Motor
operators may be found in applications where remote or automatic operation
of a circuit breaker is required.
3. HACR type:This marking indicates the circuit breaker is suitable for use with
the group motor installations typically found in heating, air conditioning and
refrigeration equipment. The NEC 2005 no longer has this marking requirement.
The electrical industry determined that circuit breakers are considered suitable
for use with such equipment without any further testing, therefore, the HACR
marking is no longer required on air conditioning and refrigeration equipment
or on circuit breakers for use in these applications. The requirement for this
marking has also been removed from the UL 1995 product standard for HVAC
equipment.
1. Manufacturer’s Name:
This marking may be the manufacturer’s name, trademark or other recognized
means to identifying the company that made the circuit breaker.
2. Type Designation:
All circuit breakers are marked with a type designation, which may be a
catalog number prefix or a separate designation. Equipment labels, such as on
panelboards, will list the circuit breaker types suitable for use. Note that the
word ―type‖ may or may not be used on the circuit breaker or equipment
labels. It is important to review the markings on the equipment, such as a
panelboard, to make sure the circuit breaker designations on the equipment
match the marking on the circuit breaker.
3. Voltage Rating:
All circuit breakers must be marked with a voltage rating. If the rating is not
marked ―ac‖ or ―dc,‖ then it is suitable for both. 120/240 V rated circuit
breakers are suitable for use on single and three-phase 4-wire systems where
the line-to-ground voltage does not exceed 120 V. Wye rated circuit breakers
such as those rated 480Y/277 V, are suitable for use on three-phase 4-wire
systems where the voltage to ground does not exceed 277 V. Special attention
needs to be given to high leg or corner-grounded delta systems to insure that
the circuit breaker has the appropriate rating. A review to see that the circuit
breakers installed have a voltage rating suitable for the application is
paramount for a code-compliant installation (NEC 240.83(E)).
4. SWD:
15- or 20-A circuit breakers rated 347 V or less may be marked ―SWD,‖ meaning
that they are suitable for switching fluorescent lighting loads on a regular basis
(NEC 240.83(D)). These circuit breakers are evaluated for high endurance use,
since they will be used similar to a light switch.
5. HID:
50 A or less circuit breakers rated 480 V or less may be marked ―HID,‖ meaning
they are suitable for switching high intensity discharge or fluorescent lighting
loads on a regular basis. These circuit breakers may employ a different
construction than a standard SWD circuit breaker in order to address the high
inrush current resulting from the lower power factor created by the HID
lighting (NEC 240.83(D)). These circuit breakers also undergo additional
endurance evaluation to demonstrate their ability to perform the switching
duty.
2. Interrupting Ratings:
All circuit breakers with an interrupting rating more than 5000 A must be
marked with an interrupting rating (NEC 240.83(C)). Interrupting ratings are
stated in RMS symmetrical amperes. If the short-circuit current rating of the
equipment in which the circuit breaker is installed is less than the interrupting
rating of the circuit breaker, then the lesser rating applies. Circuit breakers
should be reviewed after installation to ensure they have an interrupting rating
suitable for the application. This marking may be found in any location except
the back of circuit breakers that are 1-½ inches wide per pole or less due to
the size constraint.
6. Tightening Torque:
The nominal torque for all field-wiring terminals must be marked. If the width
of the circuit breaker is 1-½ inches per pole or less, then this marking may be
found in any location except on the back.
Fig.9
1. “1 – 3” Marking:
A 2-pole circuit breaker used to protect a 3-phase load on a corner-grounded
delta system must be rated and marked for such an installation. Circuit
breakers marked ―1-phase – 3-phase‖ or ―1 – 3 ―are suitable for use on 3-phase
corner-grounded delta or single-phase circuits (NEC 240.85).
The marking of a series rated system will differ according to the two above
method used for arrangement of protective components as follows:
And in Article " Electrical Wiring Diagrams for Air Conditioning Systems – Part
One ", I explained the following points:
Also, I explained the electrical wiring diagrams for Typical Air conditioning
equipments in the following Articles:
And in Article " Electrical Rules and Calculations for Air-Conditioning Systems –
Part Two ", I explained Types of Disconnecting Means for Air-Conditioning Systems.
Also, in Article " Electrical Rules and Calculations for Air-Conditioning Systems – Part
Three ", I explained identification and Marking of Disconnecting Means for Air-
Conditioning Systems.
Today, I will explain in where to locate Disconnecting Means used for Air
Conditioning Systems.
There are several Rules in the NEC Code for a disconnecting means to be in
sight from the equipment that it controls.
Rule#1
Rule#2
NEC 430.102(B) requires that Disconnect must be in sight of motor location and
driven machinery. If the disconnect as required in 430.102(A) is in sight of the
controller, the motor location, and driven machinery, then that disconnect
meets the requirements of both 430.102(A) and 430.102(B). (seeFig.4)
Fig.4: The disconnecting means within sight of the motor,
controller and driven machinery locations
If, because of the nature of the installation, the disconnect is in sight of the
controller, but not in sight of the motor location and the driven machinery,
then, generally, another disconnect must be installed. (see Fig.5)
Note:
When providing more than one disconnecting means, At least one of them shall
be readily accessible as per NEC 430.107.
Rule#3
NEC 430.102(A) Exception No. 2 requires that A single disconnecting means may
be located adjacent to (or in sight from) a group of coordinated controllers,
where the controllers are mounted on a multi-motor continuous process
machine. (see Fig.6)
Note:
NEC Code uses the terms motor location and controller location instead of
motor and controller because in many instances, the motor or controller is
inside an enclosure and is out of sight until an access panel is removed. If the
terms motor and controller were to be used, then it would be mandatory to
install the disconnect inside of the enclosure. This is not always practical. The
Commercial Building's roof-top air-conditioning units are examples.
Rule#4
Exceptions to Rule#4:
Exception No. 1: Where a motor receives electric energy from more than
one source, the disconnecting means for the main power supply to the
motor shall not be required to be immediately adjacent to the motor,
provided the controller disconnecting means is capable of being locked in
the open position.
For motors over 600 volts, the controller disconnecting means may be out of
sight of the controller, provided the controller has a warning label
indicating the location and identification of the disconnecting means, which
must be capable of being locked in the open position.
430.102(B) exception
the disconnecting means may only be out of sight of the motor, if the
disconnecting means complying with 430.102(A) is individually capable of
being locked in the open position and meets the following cases:
Case#1:
If locating the disconnecting means close to the motor location and
driven machinery is impracticable due to the type of machinery, the type of
facility, lack of space for locating large equipment such as disconnecting
means rated over 600 volts, or any increased hazard to persons or property,
the disconnecting means is permitted to be located remotely.(see Fig.9)
Case#2:
In industrial installations, if all of the following conditions are
verified:
1. Industrial installations have written safety procedures.
2. The conditions of maintenance and supervision ensure only
qualified persons service the equipment.
Notes:
The provision for locking or attaching a lock to the disconnecting
means must be part of the disconnect and a permanent component of the
switch or circuit breaker. (see Fig.10)
The provision for locking (or adding a lock to) the disconnecting
means is on the switch or circuit breaker and remains in place whether or
not the lock is installed i.e. the lock is not readily removable or transferable
type. (seeFig.10)
Disconnect switches or circuit breakers that are located only behind
the locked door of a panelboard or within locked rooms do not comply with
the requirements of 430.102.
Second: for Air Conditioning Equipment
NEC 440.14
Note:
The main purpose of above rule is providing protection for service personnel
working on equipment located in attics, on roofs, or outside in a remote
location where it is difficult to gain access to a remote lockable disconnect
440.14 Exception 1
Note:
440.14 Exception 2
And as per 440.64 , A flexible cord that supplies a room air conditioner
can’t be longer than:
Topic Article
Introduction for Air-Conditioning
Systems Types,
Introduction for Types of Electrical Rules and Calculations for
Motors/Compressors used in Air- Air-Conditioning Systems – Part One
Conditioning Systems.
I explained the Electrical Wiring Diagrams for Air Conditioning Systems equipment in
the following Articles:
Topic Article
Importance of Electrical Wiring Electrical Wiring Diagrams for Air
for Air Conditioning Systems. Conditioning Systems – Part One
How to get the Electrical Wiring
for Air Conditioning systems?
Types of Electrical Wiring
Diagrams For Air Conditioning Systems.
How to read Electrical Wiring
Diagrams?
Today, I will explain how to size Disconnecting Means used for Air Conditioning
Systems.
Important Definitions
Full load current is the current drawn by a motor at its rated voltage,
speed, frequency and horsepower.
The term Full load current FLC is equivalent to the term Rated load
current RLC.
Note:
Locked Rotor Current, LRC is the steady-state current taken from the power
line with the rotor locked (stopped) and with the rated voltage and
frequency applied. Steady-state means that the motor starts at rest or zero
speed.
1- Knowing a motor's locked rotor amps (LRA) and acceleration time helps in
selecting upstream breakers. We make sure the circuit breaker or fuse can
supply the locked rotor amps long enough to get the motor load up to speed
and that it will trip if locked rotor amps continues beyond the allowable
stall time.
Note:
Compare the LRA of a motor to the instantaneous time current curve (not
the continuous current rating) for a protective device to see if the motor
will be allowed to start without causing a nuisance trip.
Introduction
As we stated before in Article Electrical Rules and Calculations for Air-
Conditioning Systems – Part Two that NEC Article 440 is in addition to or
amendatory of the provisions of Article 430 and other applicable articles.
Many requirements — for example, for disconnecting means, controllers,
single or group installations and sizing of conductors— are the same as or
similar to those applied in Article 430. So, Article 440 must be applied in
conjunction with Article 430.
So, let’s first study the disconnecting means sizing requirements as required
by NEC Article 430.
First: Sizing of Disconnecting means for Motor as per NEC Article 430
Example#1:
A 50 HP Motor, 3Ø, 460 V, Design B load. Determine the size of the disconnect
required for this motor.
Solution:
Get the full-load current (IFL) equivalent to the horsepower rating of each
motor from Table 430.250.
IFL = 65 A
So, the Ampere Rating of the disconnect must be at least 74.75 amps.
Exception#1:
Exception#2:
Step#1: Get the full-load current (IFL) equivalent to the horsepower rating
of each motor from Table 430.247, Table 430.248, Table 430.249, or Table
430.250.
Step#2: Calculate Equivalent full-load current for the combined load (I CFL)
as follows:
Equivalent full-load current for the combined load = Σ all full load currents,
including resistance loads
Step#3: Calculate the Min. ampere rating of disconnect switch (AR dis.min )
based on Equivalent full-load current for the combined load (I CFL ) as
follows:
Equivalent locked-rotor current for the combined load = Σ all Locked Rotor
currents, including resistance loads
Step#6: Select the disconnect means horsepower rating (HPR dis) that
correspond to Equivalent locked-rotor current (I CLR) for the combined load
from Table 430.251(A) or Table 430.251(B).
Step#7: get full load current from Table 430.247, Table 430.248, Table
430.249, or Table 430.250 that correspond to the disconnect means
horsepower rating (HPR dis) of step#6
Step#9: compare between disconnect means ampere rating (AR dis. Selected)
from step#8 and Min. ampere rating of disconnect means (AR dis.min ) from
step#3 as follows:
if (AR dis. Selected) from step#8 ≥ (AR dis.min) from step#3, then the horse
power rating of the disconnect means will be (HPR dis) from step#6.
if (AR dis. Selected) from step#8 <(AR dis.min) from step#3, repeat steps
#7,8 and 9 with next higher value of (HPR dis) obtained from step#6.
Note:
Exception:
A listed non-fused motor-circuit switch having a horsepower rating equal to
or greater than the equivalent horsepower of the combined loads,
determined by Case#1, shall be permitted to have an ampere rating less
than 115 percent of the sum of all currents at the full-load condition.
Table 430.251(A)
Table 430.251(B)
For small motors not covered by Table 430.247, Table 430.248, Table
430.249, or Table 430.250, the locked-rotor current (I LR) shall be assumed
to be six times the full-load current (I FL).
I LR =6I FL
Note:
Example#2:
A combined load consists of one 5-hp, one 3-hp, and two 1⁄2-hp motors, plus a
10-kW, all rated 240 volts, 3-phase. All motors are Design B motors. Determine
the size of the disconnect required for this combination load.
Solution:
Step#1: Get the full-load current (IFL) equivalent to the horsepower rating of
each motor from Table 430.250.
Step#1
Step#2: Calculate Equivalent full-load current for the combined load (I CFL)
Step#3: Calculate the Min. ampere rating of disconnect switch (AR dis.min )
based on Equivalent full-load current for the combined load (I CFL )
Step#4: Get the locked-rotor current (I LR) equivalent to the horsepower rating
of each motor from Table 430.251(B).
Step#4
Step#5: Calculate Equivalent locked-rotor current for the combined load (I CLR)
Step#6
Step#7: get full load current from Table 430.250 that correspond to the
disconnect means horsepower rating (HPR dis) of step#6
Step#8: calculate selected disconnect Ampere rating (AR dis. Selected) as follows:
Step#9: compare between disconnect means ampere rating (AR dis. Selected) from
step#8 and Min. ampere rating of disconnect means (AR dis.min ) from step#3 as
follows:
Since (AR dis. Selected) from step#8 = 48.3 A < (AR dis.min) from step#3 = 61.3A
Then go to the next higher value of (HPR dis) obtained from step#6 which is 20
HP which has full load current = 54 A and its (AR dis. Selected) = 1.15 x 54 = 62.1 A
> (AR dis.min) from step#3 = 61.3A
Step#9
Introduction
The used rating in determining the Ampere Rating of the disconnect means
for Hermetic Refrigerant Motor-Compressor and fans will be as follows:
Get the full-load current (I FL) equivalent to the horsepower rating of each
motor from Table 430.248, Table 430.249, or Table 430.250.
Then sum these motors full load currents with other full load currents of
resistance loads to get a combined full load current (I CFL-1) as follows:
Step#2: Calculate Equivalent Total full-load current for the combined load
(I FL-TOTAL) as follows:
Step#3: Calculate the Min. ampere rating of disconnect switch (AR dis.min )
based on Equivalent Total full-load current for the combined load (I FL-TOTAL)
as follows:
Then sum these motors locked-rotor currents with other full load currents of
resistance loads to get a combined locked-rotor current current (I CLR-1) as
follows:
Step#6: Select the disconnect means horsepower rating (HPR dis) that
correspond to Equivalent total locked-rotor current (ILR-TOTAL) for the
combined load from Table 430.251(A) or Table 430.251(B).
Step#7: get full load current from Table 430.248, Table 430.249, or Table
430.250 that correspond to the disconnect means horsepower rating
(HPR dis) of step#6.
Step#8: calculate selected disconnect Ampere rating (AR dis. Selected) as
follows:
Step#9: compare between disconnect means ampere rating (AR dis. Selected)
from step#8 and Min. ampere rating of disconnect means (AR dis.min ) from
step#3 as follows:
if (AR dis. Selected) from step#8 ≥ (AR dis.min) from step#3, then the horse
power rating of the disconnect means will be (HPR dis) from step#6.
if (AR dis. Selected) from step#8 <(AR dis.min) from step#3, repeat steps
#7,8 and 9 with next higher value of (HPR dis) obtained from step#6.
Note:
Where:
Exception:
For small motor compressors not having the locked-rotor current marked on
the nameplate, or for small motors not covered by Table 430.248, Table
430.249, or Table 430.250, the locked-rotor current (I LR) shall be assumed
to be six times the full-load current (I FL).
I LR =6I FL
Note:
Most Domestic and commercial buildings need a service hot water system. Depending
upon the type of building, this system could range from as small as an under sink
water heater for washing hands to a 10,000 gallon hot water storage tank system used
in a hospital laundry.
This Article is intended to help designers to choose the appropriate type and calculate
the required power rating for thee chosen type of Electrical Water Heater.
Before going on with the calculations, we need to give you a brief about the following
points:
With this brief, you will be familiar with the types and construction of common Water
Heaters.
A Hot water heating system has (4) major components (see Fig.1):
The most important components are the first and second ones.
1. Fuel combustion,
2. Solar energy collection,
3. Electrical conversion,
4. Recovered waste heat.
Direct heat transfer (see Fig.2) is from the combustion of fuels or direct
conversion of electrical energy into heat,
Fig (2): Direct Heat Transfer
Indirect heat transfer (see Fig.3) uses heat energy originating from remote
heat sources, such as boilers, solar heat collectors, cogeneration
refrigeration or waste heat.
Fig (3): Indirect Heat Transfer
This type of heaters incorporates the burner, storage tank, outer jacket,
insulation and controls in a single unit and is normally installed without
dependence on other hot water storage equipment (see Fig.4).
They are available in electric, liquid propane (LP) and natural gas models.
Natural gas and LP water heaters normally use less energy and are less
expensive to operate than electric models of the same size.
There are two types of Storage water heaters (Tank-Type) which are:
They are typically vertical, cylindrical tanks, usually standing on the floor or
on a platform raised a short distance above the floor (as in Fig.4). In houses
they can be mounted in the ceiling space over laundry-utility rooms. Typical
sizes for household use range from 75 to 400 liters (20 to 100 US gallons).
2.1.B Small Storage Water Heaters (Tank-Type)
Small storage tank water heaters, known as point of use (POU), utility or
mobile home water heaters, are good choices for adding hot water to small
buildings, shops or garages (see fig.5).
These water heaters usually range in size from 2.5 to 19 gallons. The largest
of these miniature units can also be used to provide hot water to secondary
bathrooms that may be situated far from your home's main water heater.
Solar powered water heaters have two main components (see Fig.6):
1. Solar collectors,
2. Storage tank.
1- Solar Collectors
Solar collectors are installed outside dwellings, typically on the roof or walls
or nearby,
2- Storage Tank
The potable hot water storage tank is typically a pre-existing or new
conventional water heater, or a water heater specifically designed for solar
thermal.
In this type (see Fig.7), the potable water is directly sent into the collector.
Many such systems are said to use integrated collector storage (ICS), as
direct-gain systems typically have storage integrated within the collector.
This type does not allow potable water through the panels, but rather pump
a heat transfer fluid (either water or a water/antifreeze mix) through the
panels (see Fig.8). After collecting heat in the panels, the heat transfer
fluid flows through a heat exchanger, transferring its heat to the potable
hot water.
Fig (8): Closed-Loop Solar Water Heater
When the panels are cooler than the storage tank or when the storage tank
has already reached its maximum temperature, the controller in closed-loop
systems will stop the circulation pumps.
They can called also on-demand water heaters, this type of heaters has
minimal storage capacity, they do not store hot water; rather they Heat water
as it passes through a series of coils in the unit (see Fig.9). They are available
in electric, LP and natural gas models. Most tankless units can provide up to 3.5
gallons of heated water per minute.
Fig (9): Instantaneous Water Heaters (Tankless-Type)
They usually include a flow switch as part of the control system. Tankless,
instantaneous water heaters are best used for a steady, continuous supply of
hot water. Tankless heaters may be installed throughout a household at more
than one point-of-use (POU), far from a central water heater, or larger
centralized models may still be used to provide all the hot water requirements
for an entire house.
Electric showers have a simple electric system, working like a coffee maker,
but with a larger water flow. A flow switch turns on the device when water
flows through it. Once the water is stopped, the device turns off
automatically. An ordinary electric shower often has three heat settings:
low (2.5 kW), high (5.5 kW) or cold (0 W) to use when a central heater
system is available or in hot seasons.
They are also called Heat Pump Water Heaters (HPWH), they have small
storage tanks that temper incoming cold water; This means hybrids only
have to increase water temperature from warm to hot as opposed to
tankless which has to raise completely cold water to hot. The defining
characteristics of a "hybrid water heater" are:
Many factors determine which water heater is best for your home. The three
main factors to consider when choosing your water heater are:
An undersized water heater will work harder and have a shorter lifespan. So
make sure to select a hot water heater that provides enough hot water for
your home. The typical capacities for different types of water heaters are as
follows:
Each offers unique advantages, and you can compare features and benefits
in the table below.
As per the user requirements, the selected fuel for the water heating
system can be one of the following:
1. Natural gas,
2. LP (liquid propane gas),
3. Electric,
4. Solar.
Most water heaters are fueled by gas or electricity. Refer to the table below
for comparison:
The used units expressing the recovery rate for water heaters are:
GPH (Gallons Per Hour): The amount of water, in gallons, that is used
each hour by the plumbing fixtures and equipment, such as dish machines.
GPM (Gallons Per Minute): The amount of water, in gallons, flowing
through a plumbing fixture or through an instantaneous water heater per
minute.
Common recovery rates for Electrical water heaters for given input power are
as in below table:
Recovery Rates in Gallons per hour – Electrical Water Heater
Common recovery rates for Gas water heaters for consumed BTU are as in
below table:
Recovery Rates in Gallons per hour – Gas Water Heater
BTU (British Thermal Unit): The quantity of heat required to raise the
temperature of one pound of water one degree F.
Once you know the capacity for your water heater, remember to take the
unit’s dimensions into consideration. You can follow the
following recommendations:
Whichever fuel source you use, a water heater can be the third largest
energy user in your home, so you’ll want a unit that offers energy and cost
savings. Fortunately, almost all water heaters offer increased efficiencies to
meet increasingly strict federal energy standards.
Energy factor EF and yearly operating costs can be found on the Energy
Guide label on the unit (see Fig.12).
Fig (12): Energy Guide Label
Energy factor EF measures how efficiently a unit converts energy into heat
as well as how much heat is lost during storage.
The higher the energy factor, the more energy efficient the water heater is.
Look for EF ratings as close to 1 as possible. Electric heaters tend to have
the highest EF ratings.
In the first Article " Electrical Water Heaters Power Rating Calculations – Part One",
we gave you a brief about the following points:
With this brief, you will be familiar with the types and construction of common Water
Heaters.
Today, we will explain in detail the Sizing and Power Rating Calculations for Water
Heaters.
First let's start from the beginning, you are the electrical designer for a new building
and you want to size and calculate the power rating for the electrical water heaters
that will be used through this building, so what is the first information that you must
know?
As a summary for the above design methodology which is represented in Fig.1, we are
going to calculate the following:
As we all know that there are different types of buildings/occupancies which they are
differentiated as per their main usage to the following main categories:
1. Industrial buildings,
2. Commercial buildings,
3. Residential buildings,
4. Agricultural buildings,
5. Educational buildings,
6. Transportation buildings,
7. Religious buildings,
8. Parking and storage,
9. Military buildings,
10. Governmental buildings,
11. Cultural buildings,
12. Other buildings.
For more information about the above types of buildings, please read our article
" Electrical Design Philosophy for Major Types of Buildings ".
The common Plumbing Facilities for included in any Type of the above Buildings are as
follows:
And to know the Minimum Number of Plumbing Facilities for a Given Type of
Building/Occupancy, you must use one of the two following methods:
1. Quantity survey,
2. Calculation by using Excel Spreadsheets.
1- Quantity survey:
In this method to get the number of Plumbing Facilities, A quantity survey will be done
from the architectural drawings of the new constructed buildings or by a site visit for
the existing/old buildings.
2- Calculation by using Excel sheets:
This method will be used only in two cases:
Case#1: Where you can't get the architectural drawings of the new constructed
building or,
Case#2: In the preliminary design phase where preliminary electrical load
calculations have to be done, In this case, we can Calculations Spreadsheet for
Minimum Number of Plumbing Facilities Required as per International Plumbing Code
(IPC).
The standard data used in this excel sheet are from International Plumbing Code (IPC)
that developed by the International Code Council (ICC).
This Excel Spreadsheet uses IPC - Table 403.1 for Minimum Number of Fixtures
Required (see Fig.2). The table specifying the minimum number of plumbing fixtures
required based on the following factors:
Advantages of using IPC - Table 403.1 for Minimum Number of Fixtures Required:
The IPC - Table 403.1 is based on various studies and is intended to provide
equal access to fixtures,
The IPC - Table 403.1 is very accurate since it is directly related to the
referenced building codes,
The IPC - Table 403.1 takes into consideration the female population and the
waiting period for the female population.
This worksheet lists the other worksheets in an index as shown in above Fig.3 ;
you can go to a specific worksheet by just clicking on its name.
You can email me directly by clicking on the phrase ―Designed by: Ali Hassan‖
for any inquiries or notes.
This worksheet includes also the general data about the project and the
designer which must be filled for every new project designed by this excel sheet.
2- Floor Input Data Sheet
In this sheet (see Fig.4), you must Input the following data:
a- Floor Level: input Floor level,
b- The Building Occupancy Type: Pick Building Classification from the dropdown
menu which includes (4) nos. of basic types of Building Occupancy as follows:
1. Business,
2. Assembly,
3. Institutional,
4. Residential.
c- The Occupancy Classification: Pick Occupancy type from the dropdown menu
which includes (26) nos. of Classifications of Occupancies as follows:
Asylums, reformatories,
Theaters Factory & Industrial
Etc
High Hazard (See Mercantile (See Section
Nightclubs
Section 403.2 & 403.3) 403.2, 403.3 & 403.5)
Restaurants Residential Care Hotels, Motels
d- The Area of the building in square footage (floor wise): Input square footage for
floor under design.
f- Number of Cells in Housing Pod: Input number of cells within housing pod. Program
assumes that cells are double bunked.
In this sheet (see Fig.5), the calculation of Minimum Number of Fixtures Required for
the floor under design will be done, you will find the following results:
1. Percentage of Males,
2. Percentage of Females,
3. Total number of people,
4. Number of men,
5. Number of women.
Details of calculated plumbing Facilities Required as follows:
1. Water closets,
2. Urinals,
3. Lavatories,
4. Bathtubs/Showers,
5. Drinking fountains,
6. Service sinks.
In bottom of this sheet, you will find the Totals of Calculated Plumbing Facilities
Required for Floor under design.
Note:
You must repeat the calculation for each floor to get the total Number of
Plumbing Facilities Required for it. These results will be used to calculate the total
demand of Water in GPH or GPM for the building floor under design.
This sheet (see Fig.6) includes the standard values of IPC - Table 403.1 for Minimum
Number of Plumbing Facilities required based on the factors described above.
To download your copy of Calculations Spreadsheet for Minimum Number
of Plumbing Facilities Required as per IPC code, please click on the link.
Note:
Non-registered members in Electrical-Knowhow website will not be able to
open and use this excel spreadsheet.