Sediment Basin Design Fact Sheet
Sediment Basin Design Fact Sheet
Symbol
Key Principles
1. Sediment trapping is primarily achieved through particle settlement. Some basins may
incorporate a filtration system within the outlet structure, but these filters are generally
unreliable. Consequently the focus should always remain on achieving effective particle
settlement.
2. Achieving optimum particle settlement relies upon achieving uniform flow conditions across
the settling pond, and if chemical dosing is required, selecting the most appropriate
flocculant and/or coagulant, and then achieving effective ‘mixing’ prior to the treated flows
entering the settling pond.
3. The size of the settling pond is directly related to the ‘volume’ of runoff and/or peak design
‘discharge’. Pond volume is critical for basins operate as plug flow systems; while the pond
surface area is critical for sediment basins that operate as continuous flow systems. Both
pond volume and surface area are critical for Type A basins.
4. It should be noted that even if a basin is full of water, it can still be effective in removing
coarse sediments from inflows. Therefore, unlike permanent stormwater treatment ponds,
flows in excess of the design storm should still be directed through the sediment basin.
Design Information
A sediment basin is a purpose built dam designed to collect and settle sediment-laden water. It
usually consists of an inlet chamber (forebay), a primary settling pond, a decant system, and a
high-flow emergency spillway.
This fact sheet summaries the design requirements for four types of sediment basins, Type A,
Type B, Type C and Type D basins. Detailed discussion on the design procedures is provided in
Book 2’s Appendix B (June, 2018).
In some situations, analysis of the soil and water characteristics will also guide the selection of
the basin type. If the local soil and water characteristics hinder the effective operation of a Type
A or B basin, then sufficient justification must be provided documenting why an alternative
sediment basin type has been adopted.
The sediment basin components and methodology utilised for Type A and B basins should
always be adopted wherever practical. Even without a treatment system, the design approach
promotes more effective settling compared to Type D basins that do not normally incorporate
automatic dosing, forebays and hydraulically efficient settling pond designs. If automated
chemical treatment is not incorporated into the operation of a basin, then the operational
requirements will need to be modified to that presented for Type A and B basins.
Jar testing is required in order to determine the chemical dosing requirements of sediment
basins. It is recommended that this analysis is undertaken prior to designing the basins as the
findings may influence the strategies adopted. It should be noted that the most suitable
flocculant and/or coagulant is likely to vary with different soil types. Consequently, there is the
need to proactively review the efficacy of these products over time as soil characteristics
change during the various construction phases of the project.
If the excavated basin is to be retained as a permanent land feature following the construction
period—for example as a stormwater detention/retention system—then the location of the basin
may in part be governed by the requirements of this final land feature. However, if the desired
location of this permanent land feature means that the basin will be ineffective in the collection
and treatment of sediment-laden runoff, then an alternative basin location will be required.
Discussion:
It should be remembered that it is not always necessary to restrict the site to the use of just one
sediment basin. In some locations it may be highly desirable to divide the work site into smaller,
more manageable sub-catchments, and to place a separate basin within each sub-catchment.
It is generally undesirable to divide a basin into a series of two or more in-line basins. Several
small basins operating in series can have significantly less sediment trapping efficiency than a
single basin. This is because of the remixing that occurs when flow from one basin spills into, or
is piped into, the subsequent basin. There are exceptions to this rule, such as:
• Type A basins where the combined basin volume satisfies the minimum volume
requirement, and at least one of the basins is able to, on its own, satisfy the minimum
surface area requirement.
• Type D basins where at least one of the basins has sufficient surface area and length to
width ratio to satisfy the requirements of a Type C basin. The combined settling volume of
the basins must not be less than that specified for a Type D basin.
• A series of Type C or D basins where each settling pond is connected by several pipes or
culverts evenly spaced across the full width of the basin. Such a design must minimise the
effects of inflow jetting from each pipe/culvert and allow an even distribution of flow across
the full basin width. In such cases the minor sediment remixing that occurs as flow passes
through the interconnecting pipes/culverts is usually compensated for by the improved
hydraulic efficiency of the overall basin surface area.
‘Clean’ water is defined as water that has not been contaminated within the property, or by
activities directly associated with the construction/building works.
The intent is to minimise the volume of uncontaminated water flowing to a basin at any given
time during the operation of the basin.
Discussion:
One of the primary goals of an effective erosion and sediment control program is to divert
external run-on water and any uncontaminated site water around major sediment control
devices such as sediment basins.
The effective catchment area may vary significantly during the construction phase as areas of
disturbance are first connected to a sediment basin, then taken off-line as site rehabilitation
occurs. It is considered best practice to prepare a Construction Drainage Plan (CDP) for each
stage of earth works.
In circumstances where the consequence of failure of the basin wall has significant
consequences for life and/or property, then all earth embankments in excess of 1 m in height
should be certified by a geotechnical engineer/specialist as being structurally sound for the
required design criteria and anticipated period of operation.
If public safety is a concern, and the basin’s internal banks are steeper than 1:5 (V:H), and the
basin will not be fenced, then a suitable method of egress during wet weather needs to be
installed. Examples include a ladder, steps cut into the bank, or at least one bank turfed for a
width of at least 2 m from the top of bank to the toe of bank.
The sizing of a Type A basin is governed by achieving or exceeding a minimum settling volume
(VS), and a minimum settling zone surface area (AS). It is generally advisable to optimise the
basin’s dimensions such that both the pond volume and surface area are minimised, thus
resulting in a basin that requires the minimum space and construction cost.
For a given low-flow decant rate (QA), there is an ‘optimum’ settling zone depth (DS) that will
allow the minimum settling volume and minimum settling zone surface area requirements to be
achieved concurrently. Conversely, for a given settling zone depth, there is an ‘optimum’ low-
flow decant rate that will also allow both of these design requirements to be achieved
concurrently.
If site conditions place restrictions on the total depth of the sediment basin (DT), then this will
directly impact upon the maximum allowable depth of the settling zone (DS); however, the
relationship between the settling zone depth and the total pond depth is complex, and depends
on a number of factors.
If it is possible to determine, or nominate, a desirable settling zone depth (DS), then the optimum
low-flow decant rate may be determined from Equation 1.
For a 1 year ARI design event, the coefficient ‘K’ may be estimated from Equation 2:
This means the ‘optimum’ low-flow decant rate can be estimated from Equation 3.
Alternatively, the designer may choose to nominate a low-flow decant rate (QA) based on the
desired number of floating decant arms, then determine an optimum settling pond depth (DS).
The total basin depth is made-up of various ‘layers’ or zones, as described in Table 5.
Table 5 – Components of the settling pond depth and volume (Type A basin)
Min. volume as a
Component Term Minimum depth Term percentage of the
settling volume, VS
Settling zone DS 0.6 m VS 100%
Total depth
Step 2A: Select a trial low-flow decant rate (QA) from Table 4
Alternatively, use equations 1 or 3 to determine an optimum decant rate—this is the low-flow
decant rate at maximum water level when all decant arms are operational.
A maximum decant rate of 9 L/s/ha is currently recommended until further field testing
demonstrates that higher rates will not cause scour (lifting) of the settled sediment.
Step 5A: Calculate the minimum, average, settling zone surface area (AS)
Calculate the minimum, average, settling zone surface area based on Equation 11 (below) and
the following design conditions:
• the expected settling rate of the treated sediment floc
• the expected water temperature within the pond during its critical operational phase.
It is noted that the water temperature within the settling pond is normally based on the
temperature of rainwater at the time of year when rainfall intensity is the highest.
The minimum settling zone surface area as generated by Equation 11 is referred to as the
‘average’ surface area, meaning that when multiplied by the settling zone depth, it will equal the
settling zone volume (VS). In most cases it can be assumed that this average surface area is the
same as the surface area at the mid-depth of the settling zone (AMid); however, this is not
always technically correct (even though the differences are usually minor).
Technically, the volume of the settling zone is not equal to the mid surface area times the depth,
but instead is a product of the Simpson’s Rule, Equation 6.
Step 6A: Calculate the minimum settling zone volume (VS) based on Equation 7 (below)
Low-flow decant rate ‘QA’ Coefficient ‘K’ for specific design events
3
L/s/ha m /s/ha 1 year 2 year 5 year
2 0.002 45.0 46.0 46.9
3 0.003 34.5 36.7 39.5
4 0.004 28.4 30.8 33.9
6 0.006 22.7 22.9 26.0
8 0.008 17.6 18.8 20.9
9 0.009 16.2 17.4 19.3
AS = KS QL (11)
where: AS = minimum, average, surface area of the settling zone [m2]
KS = sediment settlement coefficient = inverse of the settling velocity of the critical
particle size [s/m]
QL = the maximum low-flow decant rate prior to flows overtopping the emergency
spillway = QA*A [m3/s]
QA = the low-flow decant rate per hectare of contributing catchment [m3/s/ha]
A = area of the drainage catchment connected to the basin [ha]
Based on the results of Jar Testing, as per Appendix B, Section B3(v), select an appropriate
value of ‘KS’. from Table 8. If Jar Test results are not available, then choose KS = 12,000.
Jar test settlement after 15 min (mm) 50 75 100 150 200 300
Laboratory settlement rate (m/hr) 0.20 0.30 0.40 0.60 0.80 1.20
Factor of safety 1.33 1.33 1.33 1.33 1.33 1.33
Design settlement rate, vF (m/hr) 0.15 0.23 0.30 0.45 0.60 0.90
Design settlement coefficient, KS (s/m) 24000 16000 12000 8000 6000 4000
Minimum depth of the settling zone:
Minimum settling zone depth, DS (m) 0.6 0.6 0.6 0.68 0.90 1.35
Typical water temperatures for capital cities are provided in Table 9. The water temperature
within the settling pond is likely to be equal to the temperature of rainwater (approximately the
air temperature during rainfall) at the time of year when rainfall intensity is the highest.
There are two design options for sizing Type B basins, as outlined below:
(i) Option 1B is based on setting a minimum settling pond surface area (AS) and depth (DS)
such that the settled sediment has sufficient settlement time to reach the floor of the
basin, which means the sediment floc is able to form a ‘compact’ sediment blanket. It is
assumed that such a sediment blanket would have a greater resistance to the effects of
‘scour’ caused by the flowing supernatant.
(ii) Option 2B is based on providing sufficient time to allow the sediment floc to settle at least
600 mm below the floating decant arms, thus avoiding the risk of this, still suspended
sediment floc, being lifted towards the low-flow decant system. This design option allows
for the design of basins with a greater depth, but smaller surface area than option 1B.
Step 2B: Determine a design value for the sediment settlement coefficient (KS)
Determine a design value for the sediment settlement coefficient (KS) based on appropriate
local information about the settlement characteristics of the chemically treated sediment floc.
Based on the results of Jar Testing, select an appropriate value of ‘KS’. from Table 10.
Step 3B: Calculate the minimum required ‘average’ surface area (AS) of the settling zone
Calculate the minimum required ‘average’ surface area (AS) of the settling zone.
AS = KS Q (13)
where: AS = minimum, average, settling zone, surface area [m2]
KS = sediment settlement coefficient (Table 10)
= inverse of the settling velocity of the treated sediment blanket
Q = the design discharge = 0.5 Q1 [m3/s]
Jar test settlement after 15 min (mm) 50 75 100 150 200 300
Laboratory settlement rate (m/hr) 0.20 0.30 0.40 0.60 0.80 1.20
Factor of safety 1.33 1.33 1.33 1.33 1.33 1.33
Design settlement rate, vF (m/hr) 0.15 0.23 0.30 0.45 0.60 0.90
Design settlement coefficient, KS (s/m) 24000 16000 12000 8000 6000 4000
Minimum depth of the settling zone:
Minimum settling zone depth, DS (m) 0.5 0.5 0.5 0.68 0.90 1.35
Critical settling zone length before Step 5B begins to dictate the basin size:
Critical settling zone length (LS) before
Step 5B and Equation 16 begin to 180 120 90 81 81 81
dictate the basin size (m)
Step 4B: Determine the minimum depth of the settling zone (DS) from Table 10
If the sediment-flocculant partnership results in a poor sediment settlement rate, such as less
than 100 mm in 15 minutes, then the minimum depth of the settling zone (DS) is governed by
the minimum recommended depth of 0.5 m, which increases the volume of the settling zone
compared to those basins that utilise an more effective flocculant.
Step 5B: Check for the potential re-suspension of the settled sediment
A Type B basin does not incorporate a low-flow decant system, and thus the overflow spillway
functions as the sole point of discharge during storm events.
To avoid the re-suspension of the settled sediment, the clear water (supernatant) flow velocity
(vC) should not exceed 0.015 m/s (1.5 cm/s).
vC = Q/(DS . W S) [m/s] (14)
where: vC = flow velocity of the clear water supernatant [m/s]
DS = depth of the settling zone [m]
W S = average width of the settling zone [m]
For design option 1B, the supernatant velocity check outlined in Equation 14 will only become
critical when the length of the settling zone (LS) exceeds the critical value given by Equation 15
(also see Table 10).
LS(critical) = 0.015 . KS . DS [m] (15)
where: LS = average length of the settling zone [m]
If a larger sediment basin is required, then the settling zone must be re-sized with Equation 14
dictating the basin size rather than Equation 13. Thus the settling zone surface area (AS)
determine in Step 3B is no longer appropriate.
If the clear water supernatant velocity (vC) is set at the maximum allowable value of 0.015 m/s,
then Equation 14 can be rewritten as:
This means that either the depth (DS) and/or the width (W S) must be increased above the values
obtained in Step 3B.
LS = 3 W S (17)
Step 2B: Nominate the depth of the settling zone (DS), and the floc settling depth (DF)
For this design option, the depth of the settling zone is not limited to the nominated floc settling
depth (DF) as used in Step 2B above.
DF ≥ 0.6 (19)
The minimum settling zone depth is 0.6 m, which is an increase from the 0.5 m used in design
option 1B. This is because in this design option the sediment floc is considered to be still settling
as it approaches the overflow spillway, whereas in design option 1B the sediment floc is
assumed to have fully settled, and thus more resistant to disturbance.
DS is the effective depth of the settling zone (i.e. the maximum water depth above the sediment
storage zone). Increasing this depth will reduce the forward velocity of the settling sediment floc,
which increases the residence time and therefore the time available for the sediment floc to
settling the required floc settling depth, DF.
DS ≥ D F (20)
The nominated settling zone depth can be within the range of 0.6 to 2.0 m. The greater the
nominated depth, the smaller the required surface area of the basin, but the volume of the
settling zone (VS), and consequently the total basin volume, will essentially remain unchanged.
Step 3B: Calculate the ‘average’ surface area (AS) of the settling zone
The required ‘average’ surface area (AS) of the settling zone is given by Equation 21.
AS = (DF/DS) KS Q (21)
where: AS = minimum, average, settling zone, surface area [m2]
KS = sediment settlement coefficient (Table 11)
= inverse of the settling velocity of the treated sediment blanket
Jar test settlement after 15 min (mm) 50 75 100 150 200 300
Laboratory settlement rate (m/hr) 0.20 0.30 0.40 0.60 0.80 1.20
Factor of safety 1.33 1.33 1.33 1.33 1.33 1.33
Design settlement rate, vF (m/hr) 0.15 0.23 0.30 0.45 0.60 0.90
Design settlement coefficient, KS (s/m) 24000 16000 12000 8000 6000 4000
Step 4B: Check for the potential re-suspension of the settled sediment
A Type B basin does not incorporate a low-flow decant system, and thus the overflow spillway
functions as the sole point of discharge from the basin.
To avoid the re-suspension of the settling sediment floc, the clear water (supernatant) flow
velocity (vC) should not exceed 0.015 m/s (1.5 cm/s).
Increasing the width of the settling zone (W SF) can be problematic because it usually requires an
increase the length of the settling zone (LS).
In any case, the length of the settling zone (LC) should ideally be at least three times the width
of the settling zone (W C) measured at the overflow weir crest elevation, thus:
LC ≥ 3 W C (24)
Figure 3 – Type C sediment basin with riser pipe outlet (long section)
The minimum ‘average’ surface area of the settling zone (AS) is given by Equation 25.
AS = KS He Q (25)
Table 14 provides values for the sediment settlement coefficient (KA) for a ‘critical particle size,
d = 0.02 mm (0.00002 m), and various water temperatures and sediment specific gravities. The
hydraulic efficiency correction factor (He) depends on flow conditions entering the basin, and the
shape of the settling pond. Table 15 provides values of the hydraulic efficiency correction factor.
The minimum recommended depth of the settling zone (DS) is 0.6 m. The desirable minimum
length to width ratio at the mid-elevation of the settling zone is 3:1. Internal baffles may be
required in order to prevent short-circuiting if the length-to-width ratio is less than three.
Table 16 – Typical Type C & D dimensions for a total pond depth of 2.0 m
Table 17 – Typical Type C & D dimensions for a total pond depth of 3.0 m
The minimum volume of the upper settling zone is defined by Equation 26.
The minimum recommended depth of the settling zone is 0.6 m, or L/200 for basins longer than
120 m (where L = effective basin length). Settling zone depths greater than 1 m should be
avoided if particle settlement velocities are expected to be slow.
The desirable minimum length to width ratio is 3:1. The length to width ratio is important for
Type D basins because they operate as continuous-flow settling ponds once flow begins to
discharge over the emergency spillway.
Equation 27 and Appendix B of Book 2 provide R(Y%,5-day) values for various locations. It is highly
recommended that revised R(Y%,5-day) be determined for each region based on analysis of local
rainfall records wherever practicable.
Recommended application Y% K1 K2
Basins with design life less than 6 months 75% 12.9 9.9
Basins with a design life greater than 6 months 80% 17.0 11.2
Basins discharging to sensitive receiving waters. 85% 23.2 12.6
At the discretion of the regulatory authority 90% 33.5 14.2
At the discretion of the regulatory authority 95% 56.7 14.6
Unlike permanent stormwater treatment ponds and wetlands, Type D basins are not designed to
allow high flows to bypass the basin. Even when the basin is full, sediment-laden stormwater
runoff continues to be directed through the basin. This allows the continued settlement of
coarse-grained particles contained in the flow.
The volumetric runoff coefficient (Cv) is not the same as the discharge runoff coefficient (C)
used in the Rational Method to calculate peak runoff discharges. Typical values of the
volumetric runoff coefficient are presented in Table 19. For impervious surfaces a volumetric
runoff coefficient of 1.0 is adopted.
The coefficients presented in Table 19 apply only to the pervious surfaces with a low to medium
gradient (i.e. < 10% slope). Light to heavy clays compacted by construction equipment should
attract a volumetric runoff coefficient of 1.0. For loamy soils compacted by construction traffic,
adopt coefficient no less than those values presented for Group D soils.
For catchments with mixed surface areas, such as a sealed road surrounded by soils of varying
infiltration capacity, a composite coefficient must be determined using Equation 28.
Σ (C V,i . A i )
C V ( comp.) =
Σ( Ai ) (28)
where:
CV (comp.) = Composite volumetric runoff coefficient
CV ,i = Volumetric runoff coefficient for surface area (i)
Ai = Area of surface area (i)
The volumetric runoff coefficient for impervious surfaces directly connected to the drainage
system (e.g. sealed roads discharging concentrated flow to a pervious or impervious drainage
system) should be adopted as 1.0. The volumetric runoff coefficient for impervious surfaces not
directly connected to the drainage system (e.g. a footpath or sealed road discharging sheet flow
to an adjacent pervious surface) should be adopted as the average of the runoff coefficients for
the adjacent pervious surface and the impervious surface (assumed to be 1.0).
The recommended sediment storage volume may be determined from Table 20. Increasing the
volume of the sediment storage zone will likely decrease the frequency of required de-silting
operations, but will increase the size and cost of constructing the basin.
Alternatively, the volume of the sediment storage zone may be determined by estimating the
expected sediment runoff volume over the desired maintenance period.
For Type C & D basins, the need for flow control baffles should have been established in Step 6
based on the basin’s length to width ratio. Both inlet baffles (inlet chambers) and internal baffles
can be used to improve the hydraulic efficiency of Type C basins, thus reducing the size of the
settling pond through modifications to the hydraulic efficiency correction factor.
Outlet chambers are technically not flow control baffles, but are instead used to prevent
sediment settling around, and causing blockage to, certain types of decant structures. When
placed around riser pipe outlet systems (Type C basins), these chambers can reduce the
maintenance needs of the riser pipe.
When placed around low-set, floating skimmer pipes, these chambers can prevent settled
sediment stopping the free movement of these decant pipes. Outlet chambers are not required
on Type A basins because the floating decant system sits above the maximum allowable
elevation of the settled sediment.
The crest of these baffles should be set level with, or just below, the crest of the emergency
spillway in order to prevent the re-suspension of settled sediment during severe storms.
Figure 6 – Typical arrangement of internal flow control baffles (after USDA, 1975)
A critical component of in-line permeable baffles is the open area of the product. Too tight a
weave and the baffles will actually hinder performance, with too open a weave providing little
benefit. A 75% weave shade cloth or equivalent open area is recommended for in-line
permeable baffles. Note this is significantly more open than typical silt curtains used on
construction sites.
If flow enters the basin through pipes, then wherever practicable, the pipe invert should be
above the spillway crest elevation to reduce the risk of sedimentation within the pipe.
Submerged inflow pipes must be inspected and de-silted (as required) after each inflow event.
Where constraints do not allow a single inflow point, runoff can be discharged into the forebay in
multiple locations as shown in Figure 10. Multiple inlets may constrain the type, or govern the
number of chemical dosing units required. In a multiple inlet location, the objective is for
thorough mixing of the coagulant with all runoff. Consequently, where a single dosing system is
adopted, inflow direction and location should be designed to optimise mixing of all runoff in the
forebay.
In some circumstances a catchment will be able to enter the main basin from the side. In these
situations, a bund or drain should be placed along the length of the basin to direct runoff to the
inflow point where feasible as shown in Figure 11. This situation is likely to frequently occur on
linear infrastructure projects and can be managed through informative design and an
understanding of progressive earthworks levels.
If all runoff cannot practicably be diverted back to the forebay, then a drain or bund should be
constructed to divert the maximum catchment possible. The remaining catchment that cannot
be diverted to the inflow point can then be managed through erosion control, or localised
bunding to capture that runoff.
The inlet chamber (or forebay) should be sized at approximately 10% of the size of the main
basin cell, and have a minimum length of 5 m unless site constraints preclude this size. To
avoid re-suspension of floc particles a minimum depth of 1.0 m is recommended. Where site
constraints do not allow the construction of a forebay to the recommended dimensions,
monitoring of the performance of the forebay should be undertaken to determine the
requirement for any modifications.
A critical component of the inlet chamber is to spread flow into the main basin cell to promote
uniform flow to the outlet. To achieve uniform flow the construction of a level spreader is
required. The level spreader can be constructed of a range of material including timber,
concrete and aluminium. A typical detail of a level spreader is provided in Figure 12, however
alternative approaches can be adopted as long as the design intent is achieved. Care is to be
undertaken to minimise any potential for scour on the down-slope face of the level spreader.
Protection of the soil surface will be required with concrete, geotextile, plastic or as dictated by
the soil properties, slope of the batter face and flow velocity. The level spreader is to be
constructed 100–200 mm above the emergency spillway level or as required to ensure the level
spreader functions during high events and is not flooded due to water in the main basin cell.
It is critical that the spreader is level because any minor inaccuracy in construction can direct
flow to one side of the main basin cell resulting in short-circuiting and a significant reduction the
performance of the basin. Where long spreaders are installed, the use of a multiple V-notch weir
plate (Figure 13) is recommended to overcome difficulties with achieving the required
construction tolerances. A multiple V-notch weir plate can be fixed to a piece of timber
embedded in concrete.
The main disadvantage of using an inlet chamber is that it can complicate the de-silting process,
especially in small basins. Conversely, when used in large basins, an inlet chamber can reduce
the long-term cost of de-silting operations by retaining the bulk of the coarse sediment within the
inlet chamber where it can be readily removed by equipment such as a backhoe. In large
basins, the inlet chamber effectively operates as a pre-treatment pond.
Figure 14(a) – Porous barrier inlet chamber Figure 15(a) – Porous barrier with piped
inflow entering from side of basin
Figure 14(b) – Typical layout of inlet Figure 15(b) – Typical layout of inlet
chamber with opposing inlet pipe (Type C chamber with side inlet (Type D basin)
basin)
Figure 16(a) – Alternative inlet chamber Figure 17(a) – Alternative inlet chamber
Figure 16(b) – Barrier with single spill- Figure 17(b) – Barrier with multiple spill-
through weir per barrier through weirs
The inlet chamber may have a pond depth less than the depth of the main settling pond
(Figures 14b & 15b) in order to allow for easy installation and maintenance of the barrier. An
inlet chamber depth of around 0.9 m will allow the use of standard width Sediment Fence fabric
as the baffle material.
The use of shade cloth (width of around 2.2 m) will allow the formation of a deeper inlet
chamber, thus potentially reducing the frequency of de-silting operations.
Inflow pipes should ideally have an invert well above the floor of the inlet chamber to avoid
sedimentation within the pipe.
Type B basins may not require a formal decant system, other than that required to de-water the
basin prior to the next storm, or to extract the water for usage on the site.
Type C basins require a free-draining outlet system in the form of either a riser pipe outlet, or
floating decant system. Gabion wall, Rock Filter Dam, and Sediment Weir outlet systems are
not recommended unless a Type 2 sediment retention system has been specified.
Type D basins usually require a pumped discharge system similar to Type B basins. If a piped
outlet exists, then a flow control valve must be fitted to the outlet pipe to control the discharge.
Self-priming skimmer pipes are difficult to design and optimise. The Auckland-type, floating
decant systems is depicted in Figure 19. This outlet system achieve 4.5 L/s per decant arm.
Each decant arm has six rows of 10 mm diameter holes drilled at 60 mm spacings (totalling 200
holes) along the 2 m width of the decant arm.
If larger flow rates are required, multiple decants structures are to be installed. Flow rates can
be controlled through the sizing and number of holes in the decant, or by using an orifice plate
based on appropriate hydraulic calculations.
For small catchments, a single decant may be sufficient to achieve the required outflow rate. A
single decant arm can connect directly into a pipe through the sediment basin wall negating the
need for a manhole. Proprietary skimming systems are available and can be used as long as
they adhere to the design intent, and will not draw up floc particles due to concentrated flow.
Other types of outlet systems are described in Appendix B of Book 2 (IECA, 2008).
Photo 5 – Riser pipes under construction Photo 6 – Riser pipe with aggregate filter
In addition to the above, design of the emergency spillway must ensure that the maximum water
level within the basin during the design storm specified in Table 23 is at least:
• 300 mm below a basin embankment formed from fill
• 150 mm plus expected wave height for large basins with significant fetch length (note;
significant wind-generated waves can form on the surface of large basins).
The approach channel can be curved upstream of the spillway crest, but must be straight from
the crest to the energy dissipater. The approach channel should have a back-slope towards the
impoundment area of not less than 2% and should be flared at its entrance, gradually reducing
to the design width at the spillway crest.
All reasonable and practicable efforts must be taken to construct the spillway in virgin soil,
rather than within a fill embankment. Placement of an emergency spillway within a fill
embankment can significantly increase the risk of failure.
Anticipated wave heights may be determined from the procedures presented in the Shore
Protection Manual (Department of the Army, 1984).
The hydraulic design of sediment basin spillways is outlined in Section A5.4 of Appendix A –
Construction Site Hydrology and Hydraulics (IECA, 2008).
The downstream face of the spillway chute may be protected with concrete, rock, rock
mattresses, or other suitable material as required for the expected maximum flow velocity.
Grass-lined spillway chutes are generally not recommended for sediment basins due to their
long establishment time and relatively low scour velocity.
Care needs to be taken to ensure that flow passing through voids of the crest of a rock or rock
mattress spillway does not significantly reduce the basin’s peak water level, or cause water to
discharge down the spillway before reaching the nominated spillway crest elevation.
Unlike permanent stormwater treatment ponds and wetlands, construction site sediment basins
are not designed to allow high flows to bypass the basin. Even if the basin is hydraulically full,
sediment-laden stormwater runoff should continue to be directed through the basin. This allows
the continued settlement of coarse-grained particles contained in the flow. Thus a side-flow
channel does not need to be constructed to bypass high flow directly to the spillway.
For rock and rock mattress lined spillways, it is important to control seepage flows through the
rocks located across the crest of the spillway. Seepage control is required so that the settling
pond can achieve its required maximum water level prior to discharging down the spillway.
Concrete capping of the spillway crest (Photo 14) can be used to control excess seepage flows.
It is important to ensure that the spillway crest has sufficient depth and width to fully contain the
nominated design storm peak discharge. Photo 16 shows a spillway crest with inadequate depth
or flow profile.
Photo 15 – Spillway rock protection sits Photo 16 – Spillway crest with inadequate
above the embankment height depth or profile
On subdivisions and major road works, construction site sediment basins often represent a
significant opportunity for conversion into either: a detention/retention basin, bio-retention
system, wetland, or pollution containment system. In rural areas, basins associated with road
works are often constructed within adjacent properties where they remain under the control of
the landowner as permanent farm dams.
Sediment basins that are to be retained or transformed into part of the permanent stormwater
treatment system, may be required to pass through a staged rehabilitation process. In those
circumstances where it is necessary to temporarily protect newly constructed permanent
stormwater treatment devices (such as bio-retention systems and wetlands) from sediment
intrusion, there are a number of options as outlined in Appendix B of Book 2.
With appropriate site planning and design, the protection of these permanent stormwater
treatment devices is generally made easier if the sediment basin is designed with a pre-
treatment inlet pond as discussed in Step 9. The pre-treatment pond can remain as a coarse
sediment trap during the maintenance and building phases, thus protecting the newly formed
wetland or bio-retention system located within the basin’s main settling pond.
Continued operation of the sediment basin during the building phase of subdivisions (i.e.
beyond the specified maintenance phase) is an issue for negotiation between the regulatory
authority and the land developer on a case-by-case basis. Ultimately, the responsibility for the
achievement of specified (operational phase) water quality objectives rests with the current land
owner or asset manager.
Upon decommissioning of a sediment basin, all water and sediment must be removed from the
basin prior to removal of the embankment (if any). Any such material, liquid or solid, must be
disposed of in a manner that will not create an erosion or pollution hazard.
Table 24 provides an overview of the typical operational conditions of the various basins.
Whenever possible, water samples collected from the sediment basin must be tested in a
laboratory before discharge to prove that the suspended solid content is below recommended
level. It is strongly recommended that sufficient water testing is conducted in order to enable a
site-specific calibration between suspended solids concentrations (mg/L) and NTU turbidity
readings. This would allow utilisation of the turbidity meters to determine when water quality is
likely to have reached the equivalent of 50 mg/L.
Table 26 is presented as an alternative NTU-based water quality standard for sediment basins.
If the basin’s operation is managed through the use of a specified or determined NTU reading,
then water samples must still be taken daily during de-watering operations to determine the total
suspended solids (TSS) concentration. Both the TSS and NTU values must be recorded and
reported as appropriate.
In the case of a Type A basin, the term ‘fully drained’ means the basin has drained to the bottom
rest position of the floating decent system.
Technical Note 1: Recommended operational procedure for the retention of water within
Type A basins
If inflow to the basin has ceased, or the potential for basin overtopping is insignificant’ the valve
on the outlet pipe can be closed to hold runoff in the basin
If, prior to further rainfall, the water level has not been lowered to the bottom of the settling zone,
the valve should be opened, provided that the water quality is within the discharge limits. This
process should occur well in advance of rainfall occurring, as de-watering will take some time.
An alternative method is to raise the lower decant arms prior to a rainfall event occurring to
ensure runoff is captured in the basin. This process should only occur if it is reasonable to
expect that the basin capacity will not to be exceeded in the forecast rainfall event (i.e. forecast
rainfall has a 90% chance of being less than 50% of the basin’s available capacity).
Theoretically, Type B and Type C basins may be full, or partially-full, immediately prior to a
storm, but it is still desirable for these basins to be fully drained prior to accepting further inflows
in order to optimise the basin’s overall performance.
Technical Note 2: Recommended operational procedure for the retention of water within
Type B basins
The basin shall be fully de-watered if the forecast rainfall has a 90% chance of being less than
50% of the basin’s available capacity.
If the long-term operation of Type C basins within a given region identifies the presence of fast
and efficient settling sediments, and good water quality outcomes, then the low-flow drainage
system can be ignored/decommissioned, and the basins can be operated as a ‘wet ponds’.
Even if soil conditions satisfy the initial selection of a Type C basin, this does not guarantee that
the water quality achieved by the basin will satisfy the required environmental objectives. If a
Type C basin fails to regularly achieve the required water quality objectives, then the basin may
need to be converted to, or operated as, a Type B or Type D basin in order to satisfy specified
water quality objectives.
The operation of Type D basins is similar to Type A basins. In ideal circumstances, the treated
water can be retained within these basins for use on site, but the basins must be drained prior to
any storm that is likely to produce significant (i.e. measurable) basin inflows.
Table 27 provides the recommended de-silting trigger points for sediment basins.
Although it is desirable for sediment basins to achieve the desired water quality standard during
every storm, circumstances can exist that will cause uncontrolled discharges to exceed these
standards. Due to the inherent complexity and variability of rainfall events, and variations in the
performance of flocculants, it is possible for discharges above, say 50 mg/L, to occur. This of
course does not necessarily make such discharges either lawful or unlawful. The resulting legal
issues are complex and will likely vary from site to site.
Sediment basins are not designed to achieve a specific water quality; rather, they are designed
to either capture and treat a specific volume of runoff, or to treat discharges up to a specified
peak flow. A specific water quality cannot be guaranteed solely through the ‘sizing’ of the basin,
but must be achieved in association with site-specific water quality management practices, such
as those discussed above (Step 17). Sediment basins cannot perform in an appropriate manner
without the attentive input from suitably trained site personnel.
Irrespective of the circumstances, the operator should regularly inspect the critical design
features of the basin, and should review the basin’s performance against its design
expectations. If a water quality failure is observed, then the operator should endeavour to take
multiple samples during these releases to document the duration of such exceedances.
Adjustments to the basin, and the basin’s operation, should occur after each observed failure.
The use of such adaptive management practices is critical to achieving the optimum
performance of any sediment basin.
Being able to demonstrate that adaptive management practices are being implemented at the
site is an important consideration noted by regulators when determining whether all things
reasonable and practicable are being done to minimise sediment releases.
(i) Coagulation
A coagulant is utilised to neutralise or destabilise the charge on clay or colloidal particles. Most
clay particles in water are negatively charged and therefore any positive ion (cation) can be
used as a coagulant.
Charge neutralisation in water can occur very rapidly; therefore, mixing is important for effective
treatment of turbid water. After a short time, the ions form hydroxide gels which trap particles, or
bridge between particles creating a floc that may settle.
There is always the possibility of overdosing with coagulants and building up excess positive
charge, hence complying within the optimum dosage range is critical. When a cationic coagulant
is overdosed, the clay and colloidal particles will take on a positive charge and repel each other
and limit any settling. The dosage range of a coagulant will vary depending on site water
chemistry. Different coagulants also have an optimum pH range over which they are effective
and pH buffering may be required depending on the coagulant and water chemistry.
The flocs generated by coagulation are generally small and compact. They can also be broken
down under high velocity or high shear conditions.
(ii) Flocculation
Flocculation is a process of contact and adhesion whereby the particles of a dispersion form
larger-size clusters. Flocculation can occur through the use of a coagulant, flocculant, or both.
Coagulants achieve flocculation through charge neutralisation where as flocculants physically
bind clay and colloidal particles together.
The use of natural and synthetic polymeric flocculants can be used to generate larger more
stable flocs and may reduce treatment times. This is achieved by bringing dispersed particles
together increasing the effective particle size. Flocculants can be used alone, or in combination
with coagulants.
(iii) Ecotoxicity
The by-products of coagulants and flocculants can, in certain circumstances, become toxic to
aquatic life. A high or low water pH is often the trigger for the release of these materials in a
toxic form.
It is generally accepted that dissolved aluminium at a concentration between 0.050 and 0.100
mg/L and a pH between 6.5 and 8.0 presents little threat of toxicity. However, at lower pH, the
toxicity increases with an effect of possible major concern being the coagulation of mucus on
the gills of fish.
There is limited published data on the aquatic ecotoxicity of calcium based coagulants such as
calcium sulphate and calcium chloride.
Designers of chemical treatment systems must always seek the latest advice on the potential
impacts of coagulants and flocculants on receiving waters, and must have an adequate
understanding of the types of receiving water associated with any sediment basin design.
Ecotoxicity information has been adopted from the Auckland Regional Council TP226 and
TP227 documents.
Jar tests are conducted on a four or six-place gang stirrer. Jars (beakers) with different
treatment programs or the same product at different dosages are run side-by-side, and the
results compared to an untreated beaker. Where access to a laboratory is not practicable field
tests can be undertaken following a similar process to that described in the procedure with
stirring and settling timeframes in multiple beakers. Testing should be undertaken by a suitably
qualified person in the use of coagulants and flocculants.
Preference is given to the use of raw water collected on site which is representative of runoff
(including water temperature, which affect settlement characteristics) during the life cycle of the
sediment basin. Where raw water is not available representative soil from the site is to be mixed
with water to create indicative runoff water chemistry. To create a water sample from soil, a
recommended procedure is provided below.
Starting pH
Starting turbidity
Final pH
Final turbidity
Starting pH
Starting turbidity
Final pH
Final turbidity
Note:
[1] For the purposes of a floc report, ‘clarity’ is defined as a level of turbidity. Clarity can be estimated
visually or with the use of a turbidity meter.