No:
Client : Project :
Dated :-
Rev:-0
Four laning of Parwanoo-Solan Section of NH-22
Page :- 010f 01
Barog Tunnel
SheetNo:-
SITE
Grade of Shotcrete
SHOTCRETE SITE CONTROL
Date of Spraying
Chainage
Location
Approved Mix Proportions
Batch Qty Cement 10mm Crushed Sand Natural Sand Water HRWR
Batch Weight Mix Data
Batch Moisture
Corrected
Quantity, Water Adjustment
Moisture Batch
Mix Ingredeints SSD condition Absorption Source Remarks
Content (%) quantity
(Kg) (%) (%) (Kg) (Kg)
--------m3
Cement
10mm
C.Sand
N.Sand
Water
Admixture
Initial 30minutes 1hr.
Slump
Concrete Temperature Air Temperature
………………………………………………………………………………………
Particulars of Specimen Cast ……………………………………………………………………………………
…………………………………………………………………………………..
……………………………………………………………………………………..
Approved by Engineer: Issued by Contractor:
Name: ................................ Name: ................................
Sign : ................................ Sign : ................................