0% found this document useful (0 votes)
200 views2 pages

Cost Estimate Docking List-OB Indo Marine 1018

The document provides a docking list and cost estimate for dry docking the oil barge Indo Marine 1018. It includes details on the vessel specifications and a breakdown of work items and their costs. The work includes hull repairs and painting, outfitting repairs, tank cleaning and testing, and certification documentation. The total cost after a 5% discount is Rp 335,639,940.

Uploaded by

Ahmad Rezka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
200 views2 pages

Cost Estimate Docking List-OB Indo Marine 1018

The document provides a docking list and cost estimate for dry docking the oil barge Indo Marine 1018. It includes details on the vessel specifications and a breakdown of work items and their costs. The work includes hull repairs and painting, outfitting repairs, tank cleaning and testing, and certification documentation. The total cost after a 5% discount is Rp 335,639,940.

Uploaded by

Ahmad Rezka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DOCKING LIST OIL BARGE INDO MARINE 1018

"DRY DOCKING "

Ship Prticullar : Shipyard :

Name Of Vessel : OIL BARGE Indo Marine 1018 Yard Avaibility :

Kind Of Vessel : Barge Schedule :

Classification : BKI

LOA : 70,22 meter

Breadth : 18,29 meter

Depth : 4,88 meter

Draft : 3,9 meter

Volume Price
No Uraian Pekerjaan Percentage %
Qty Unit Item Total

A I. GENERAL SERVICE

1 Docking & Undocking 1 LS Rp 14.500.000 Rp 14.500.000

2 Docking / day 20 Hari Rp 1.450.000 Rp 29.000.000

3 Jasa asistensi naik & turun dock 1 LS Rp 2.500.000 Rp 2.500.000

4 Fasilitas alat berat selama kapal dock 1 LS Rp 5.000.000 Rp 5.000.000

5 Pembuatan docking report 4 Rangkap Rp 1.500.000 Rp 1.500.000

- Docking report

- Painting report

- Certificate antifouling

- Shell expansion drawing

Rp 52.500.000

B HULL & MARINE

I. REPLATING & ULTRASONIC TEST

1 UT pada plat Bottom, Lambung dan main deck (min 100 titik) 1 Ls Rp 8.000.000 Rp 8.000.000

Rp 8.000.000

II. SAND BLAST & PAINTING ( cat yard suplly )

1 Scraping tiram 1200 m2 Rp 10.000 Rp 12.000.000

2 Sandblast & Painting plat bottom (under water area)

Sandblast bottom (under water area)

Pengecatan Primer 1 x layer (150 µ) red 1200 m2 Rp 150.000 Rp 180.000.000

Pengecatan siller 1 x layer (100 µ)


Pengecatan AF / anti fouling 1 x layer (150 µ) Red brown

9 Pengecatan Ship name, port register, draft mark, plimsol


1 LS Rp 1.250.000 Rp 1.250.000

Rp 193.250.000
III.SEA CHEST, SEA VALVE & ZINC ANODE

1 Pemasangan Zinc Anode Lambung 44 pcs Rp 100.000 Rp 4.400.000


Material Zinc anode @ 8kg 44 pcs Rp 640.000 Rp 28.160.000

Rp 32.560.000
iV. OUTFITTING WORK

2 Perbaikan pad eye tire fender 15 Pcs Rp 125.000 Rp 1.875.000

Plate 12mm X 80 mm X 120mm

5 Bongkar & pasang tire fender 15 Pcs Rp 130.000 Rp 1.950.000

Tire fender, rantai & shackle


8 Perbaikan Pipa Handrail 6 meter Rp 784.000 Rp 4.704.000

Pipe 4" sch 80 seamless x 6m

10 Penggantian bollard buritan

Pipa 8" sch 80 seamless X 1000mm x 2 1 M Rp 2.233.000 Rp 2.233.000

Roundbar 2" X 200mm x 2 0,4 M Rp 583.000 Rp 233.200

Bracket, plate 10mm X200mm X 400mm 4 Pc Rp 125.000 Rp 500.000

13 Penggantian cover manhole 2 Set Rp 1.850.000 Rp 3.700.000

Plate 8 mm X 500mm X 650mm

Rubber packing + bolt & nut

16 Perbaikan engsel pintu emergency exit 4 Pcs Rp 250.000 Rp 1.000.000

Rp 16.195.200
VI. TANGKI

2 Free Gas tanki 21 Tanki Rp 500.000 Rp 10.500.000

3 Cleaning Tanki

Fuel Oil 21 Tanki Rp -

Freswater 2 Tanki Rp 2.000.000 Rp 4.000.000

Bongkar & pasang manhole 21 Pcs Rp -

Ganti rubber packing + bolt & nut 4 Set Rp 200.000 Rp 800.000

4 Air Pressure Test tanki 21 Tanki Rp 500.000 Rp 10.500.000

6 Vacum test 1 Ls Rp 3.500.000

Rp 25.800.000

C MACHINERY SYSTEM
E XII. DOCUMENT & CERTIFICATION

1 Re-Certificate Class and Syahbandar 1 Ls Rp 5.000.000 Rp 5.000.000

2 Re Calibration Tank 1 Ls Rp 10.000.000 Rp 10.000.000

4 Cleanliness Report 1 Ls Rp 10.000.000 Rp 10.000.000

5 Flow Meter 1 Ls Rp 5.000.000 Rp 25.000.000

GRAND TOTAL 353.305.200


DISCOUNT 5 % 17.665.260
TOTAL AFTER DISCOUNT 335.639.940