0% found this document useful (0 votes)
80 views34 pages

Progress Format For CRIWMP

This monthly progress report summarizes the construction of a water supply project. It provides details on the overall progress of the project including insurance, site facilities, the raw water intake pump house, water treatment plant, and reservoirs. The report also discusses the progress of civil works, mechanical and electrical works, and pipe laying for various components of the project. Resource allocation of staff, machinery, and equipment is also reviewed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views34 pages

Progress Format For CRIWMP

This monthly progress report summarizes the construction of a water supply project. It provides details on the overall progress of the project including insurance, site facilities, the raw water intake pump house, water treatment plant, and reservoirs. The report also discusses the progress of civil works, mechanical and electrical works, and pipe laying for various components of the project. Resource allocation of staff, machinery, and equipment is also reviewed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 34

CRIWMP-Construction of …………………………RWSP

DEDURUOYA WATER SUPPLY PROJECT

CONTRACT NO:

MONTHLY PROGRESS REPORT

AUGUST 2020

EMPLOYER : UNDP

CONSULTANT : CEYWATER CONSULTANTS

CONTRACTOR :

Contents
1. PROJECT SUMMARY

Page | 1
1.1 Project Details

1.2 Scope of Work:


2. PROGRESS
2.1. OVERALL PROGRESS
2.2. INSURANCE, BONDS, PRELIMINARIES PROGRESS
2.3. SITE FACILITIES PROGRESS
2.4. RAW WATER INTAKE PUMP HOUSE, WATER TREATMENT PLANT AND RESERVIORS
/TOWERS CONSTRUCTION PROGRESS
2.5. TRANSMISSION PIPE LINE ERECTION PROGRESS
2.6. DISTRIBUTION PROGRESS
3 PROJECT SCHEDULES
3.1. CONSTRUCTION WORK SCHEDULEOVERALL SUPPLY PROGRESS
4. PAYMENTS
4.1. STATES OF PAY
5. QAQC, EMP AND HEALTH & SAETY PROGRESS
5.1. MONTHLY QUALITY ASSURANCE AND QUALITY CONTROL REPORTSMENTS
5.2. MONTHLY INSPECTION PROGRESS
5.3 MONTHLY ENVIRONMENTAL PROGRESS
5.4 MONTHLY SAFETY PROGRESS
6. RESOURCE ALLOCATION
6.1 ORGANIZATIONAL CHART
6.2 MANPOWER
6.2.1 OFFICE/SUPERVISORY STAFF
6.2.2 WTP/PUMP HOUSE
6.2.3 AT WTP SITE
6.2.4 AT PIPE LAYING

6.3 MACHINERY AND EQUIPMENT

6.3.1 WTP

6.3.2 Pipe Laying

7. WEATHER REPORT
8. PROGRESS PHOTOS`
8.1. INTAKE/PUMP HOUSE

8.2 WTP

8.3. PIPE LAYING

8.4. SAFETY PROGRESS

Page | 2
1. PROJECT SUMMARY
1.1. Project Details

Project Name : Construction of ……………….RWSS

Locations of the site : :

Name of Employer

Name of Consultant

Name of Contractor

Contract Amount

Date of Commencement
Date of Completion

1.2. Scope of Work:


Give details of

Treatment Plant

Intakes/pump house

Pumping main

Distribution/service connection

Raw water Sump

Treated water ump

Elevated Tower

Buildings

EMP/ any other

Page | 3
2. PROGRESS
2.1 OVERALL PROGRESS
Overall Progress Rate :
Up to July 2020 Up to Up to
June.
ITEM NO DESCRIPTION WTG July. 2020 July. 2020
2020
Plan Actual (Plan) (Actual)
(Actual)
    OVERALL PROGRESS 100.0%

1.0   Insurances & Bonds

2.0   Preliminaries & Site facilities

21 Contractors Facility

2.2 Engineer's Facility


2.3 Other Requirements
Raw Water Intake &
3.0  
Pumping Station
.. 3.1 Design & Engineering

  3.2 Manufacturing & Delivery

  3.3 Civil Works

Mechanical & Piping Erection


  3.4
works
Electrical & Instrumentation
  3.5
works
Water Treatment Plant including
4.0   waste water pipeline

4.1 Design & Engineering

  4.2 Manufacturing & Delivery

  4.3 Civil Works

Mechanical & Piping Erection


  4.4
works
Electrical & Instrumentation
  4.5
works

4.6 Testing and Commissioning

Page | 4
5.0   Pipe Laying Work

  7.1 Manufacturing & Delivery

  7.2 Transmission Pipeline

Distribution Pipeline including


  7.3
service connection

7.4 Testing and Commissioning

2.1.
2.2. INSURANCE, BONDS, PRELIMINARIES PROGRESS
Insurance, Bonds and Preliminaries Progress Rate : 100.00%

ITEM NO TASK NAME WEIGHTAGE % COMPLETED

1.0     INSURANCE & BONDS 100.0% 100.0%

  1.1   Insurance 50.0% 50.0%


  1.2   Performance Bond 40.0% 40.0%
  1.3   Retention Bond 10.0% 10.0%

2.3. SITE FACILITIES PROGRESS


Site Facilities Progress Rate :
2.0     PRELIMINARIES & SITE FACILITIES 100.0% 86.3%

  2.1   Contractors Facility


    2.1.1

    2.1.2

    2.1.3

    2.1.4

    2.1.5

  2.2   Engineer's Facility

Page | 5
    2.2.1

    2.2.2

    2.2.3

    2.2.4

    2.2.5

    2.2.6

2.4. RAW WATER INTAKE PUMP HOUSE, WATER TREATMENT PLANT AND RESERVIORS /TOWERS CONSTRUCTION
PROGRESS
  Task Name CIVIL MECH
I Construction of INTAKE PUMP HOUSE
II Construction of WTP
III Construction of Reservoirs/Towers

ITEM NO TASK NAME WEIGHTAGE COMPLETED %

    4.2.2 Raw Water Intake & Pump House

      Civil Works

      Excavation
      Foundation
      Wall
      Brick wall
      Roofing
      Plaster & Painting
      Doors and windows
      Finishing

      Mechanical Erection Works

      Erection of Raw water pump

      Erection of Raw water Suction/Discharge pipe Line

      Erection of valves and flow meter


      Testing of mechanical equipment

      Electrical Erection Works

      Erection of Cables
      Lighting Erection
      Earthing erection
      Electrical & Instrument Erection
      MCC panel Erection
      PLC panel Erection
      Termination & Dressing

5.
    WATER TREATMENT PLANT
0

Page | 6
5. CONSTRUCTION OF WATER TREATMENT
   
PLANT
2
    5.2.1 Site Works
    5.2.2 Cascade Aerator
      Civil Works
      Excavation
      Footings & Ground Beam Concreting
      Slab and Beam Concrete
      Wall Concrete
      Hydro testing
      Finishing
      Mechanical Works
      Installation of flow meter and valves
      Piping works
      Other Misc. Works
    5.2.4 Roughing Filter
      Civil Works
      Excavation
      Base Concreating
      Ferro Cement works
Pipe Fixing
      Filter Media
      Pipe Gallery Outlet Chamber
      Hydro test
      Finishing

      Erection of Mechanical & Piping Works

      Filter Inlet & Backwash valve Instalaltion

      Installation of Air blower with related work

      Valves and pipe installaion in filter gallery


      Pneumatic Air Line
      Submersible Dewatering Pump & Pipeline
      Placing of Filter Media

      Erection of Electrical & I Works

      Cable Erection
      Instruments Installation
      Other Misc Works
Slow sand Filter

    5.2.5 Civil Works

      Excavation
      Base Concreating
      Ferro Cement works
      Pipe Fixing
      Filter Media
      Pipe Gallery Outlet Chamber
      Hydro test
      Finishing
      Erection of Mechanical & Piping Works
      Filter Inlet & Backwash valve Instalaltion

Page | 7
      Installation of Air blower with related work
      Valves and pipe installaion in filter gallery
      Pneumatic Air Line
      Submersible Dewatering Pump & Pipeline
      Placing of Filter Media
      Erection of Electrical & I Works
      Cable Erection
      Instruments Installation
      Other Misc Works
      Other miscelaneous work

      Electrical Erection Works

      Cable tray erection work

      Cable erection

      Installation of panels

      Other miscelaneous work

6.
    CONSTRUCTION OF Towers
2
      Civil Works

      Preliminary Works (Set out/ Acces road, etc.,)

      Shaft concreting
      Slab concreting
      Ferro cement wall
      Roof dome Construction
      Hydro Test
      Finishing

      Mechanical erection Works

      Yard Piping works


      Valve erection

      E & I erection Works

      Instrumentation erection
      Electrical Lighting works

      pump house

      Civil works
      Excavation
      foundation
      Wall
      Roofing works
      Plastering & painting
      Finshing works
      Mechanical erection work
      Installation of Pen Stock gates
      Inlet Pipe Line connection
      Pumps installation
      Pump Suction & Discharge Pipe Line
      Other miscellaneous work
      Electrical erection work

      Cable tray erection work

Page | 8
      Cable erection

      Installation of panels

      Other miscellaneous work

2.5. TRANSMISSION PIPE LINE ERECTION PROGRESS


7.2 TRANSMISSION PIPELINE ERECTION

Sl. No Description

1 Excavation & Laying

2 1. Backfilling Including Compaction Test

3 Temporary Reinstatement

4 Pressure Testing

5 Chamber Construction

6 Fixing Valve & Fittings

7 Culvert Crossings

  CONSTRUCTION PROGRESS

Testing and Commissioning

Disinfection

Commissioning

2.6. DISTRIBUTION PROGRESS


DISTRIBUTION PIPE LINE
7.3 WEIGHTAGE COMPLETED %
ERECTION

Sl. No Description  

Page | 9
1 Excavation & Laying  
Backfilling Including Compaction
2  
Test
3 Temporary Reinstatement  

4 Pressure Testing  

5 Chamber Construction WEIGHTAGE COMPLETED %

6 Fixing Valve & Fittings  

7 Culvert Crossings  

CONSTRUCTION PROGRESS  

Testing and Commissioning  

Disinfection  

Commissioning  

2.7. OVERALL SUPPLY PROGRESS


Overall, supply progress : %

DESCRIPTION WEIGHTAGE COMPLETED %


ITEM NO
Overall Supply Completion  
4.1     Intake pump house
  4.1.1   Mechanical Equipment
  Intake Pump
   
  Valves
   
Flow meters

  4.1.2   Electrical Equipment


  Local Control Panel
   
  Instrumentation Panel
   
  Wireless Communication
   
  Ultrasonic level transmitter for Intake level
   
  Level switches for Intake Level
   
5.1     WATER TREATMENT PLANT

  5.1.1   Mechanical Equipment

Page | 10
  Surge tank
   
  Pumps
   
 
    Backwash Water pumps
  booster pumps
   
  Chlorine Dosing Pump
   
  Flowmeters
   
ITEM NO DESCRIPTION WEIGHTAGE COMPLETED %

  5.1.2   Electrical Equipment


  Local Control Panel
   
  Motor Control Centre
   
  Instrumentation Panel
   
  Remote I/O Communication Panel
   
  Wireless Communication
   
  Ultrasonic Level Transmitter
   
  Water Quality Monitor's Panel
   
  Diaphragm Pressure Switches
   
  Level Switches
   
  Cables
   

      Towers and Reservoir

      Mechanical Equipment
  Valves
   
  Transmission Pumps
   

   
  Electrical Equipment
  Distribution board
   
  Communication Panel
   
  Wireless Communication
   
  Motor Control panel
   
  Local Control Panel
   

   
  Instrumentation Panel
  Diaphragm Pressure Transmitter
   
  Ultrasonic level Transmitter
   
  Diaphragm Pressure switches
   
  Level Switches
   

Page | 11
7.1     DISTRIBUTION NETWORK
  7.1.1   PVC Pipes and Fittings

  7.1.2   DI Pipes & Fittings

Other DI Fittings and Valves


  7.1.4  

3. PROJECT SCHEDULES
3.1. CONSTRUCTION WORK SCHEDULE

Page | 12
4. PAYMENTS
4.1. STATES OF PAYMENTS

No Description Received Date Sum Remarks


1 Advance Payment
Total  

YEAR 2019/20
UNITS:USD *1000
Februar
Month January y March April May June July August September October November December Total
Payment recieved                      

Cumulative   - - - - - - - - - -

5. QAQC , EMP AND HEALTH & SAETY PROGRESS


5.1. MONTHLY QUALITY ASSURANCE AND QUALITY CONTROL REPORTS

Test Report Engineer's


No Date DESCRIPTION Result Remarks
No. Comments
Approved and  
1 Field density test at Road ……………………………….  
Continue
Field density test at Road Approved and  
2  
…………………………………….. Continue
Approved and  
3 Sample collection for proctor test feet  
Continue
28days cube test at …………………. Approved and  
4  
Continue
Approved and
5    
Trial mix Continue
Approved and
6    
Pressure testing at Continue
Approved and
7    
Soil investigation/sieve analysis Continue

5.2. MONTHLY INSPECTION PROGRESS

No RFI No. Date DESCRIPTION Result Engineer's Comments Remarks

Approved and
1  
Continue
 

Page | 13
 
Approved and
2  
Continue

Approved and  
3  
Continue
Approved and  
4  
Continue
Approved and  
5  
Continue
 
Approved and
6  
Continue

Page | 14
5.3. MONTHLY ENVIRONMENTAL PROGRESS

Client:-UNDP File
No:

CONSTRUCTION OF
……………………………..RWSS
Con:-CEYWATER
 

CONTRACTOR:-

Monthly Environmental Report


Construction period From: to
Contract No:
Data for Month of: 2019 May
Location:
Person in charge

Location Items Managing & Monitoring Report

Material transporting vehicles covered and vehicle driving speed


controlled on the roads in the site area.(< 10 kmph).
Air Quality / Dust control process managed on 95%.
Dust Control

Four or three times per day were arranged the watering process for
dust control in the dry season.

Concrete Truck mixer and Equipment cleaning and washing process


Water Quality properly arranged in separate, suitable & removable place.
Water
Treatmen Prevented mosquito breeding in site area.
t Plant
Dewatering system & waste water drains system properly arranged.
Reusable soil file was not blocked on the drainage paths on site.
Soil
ErosionContro
l Of Waste Maintained construction equipment in good condition, there was not
Earth pollution founded any oil or grease at sites.
Raining water dewatering process and drainage system arranged.
There was not a public complains about construction activities.
Noise Control
No any public complains about noise disturbance.

Page | 15
Task instructions were conducted according to the environmental
management plan for all workers
Workers are briefed on a regular basis on basics of health & safety.
?>
Security access point was safe and secured.
HSE instruction was conducted according to site activities for workers.
Health & All the personal found wearing 90% PPE at site.
Safety
Arrangements
All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
The condition of the workers camp is favorable between 80-85%.
No accident in during the month.
Dust control process managed on 90%.
Vehicle driving speed controlled on the roads in the site area. (< 10
kmph).

Water Quality Concrete Truck mixer and Equipment cleaning and washing process
properly arranged in separate, suitable & removable place.
Prevented mosquito breeding in site area.

Reusable soil file was not blocked on the drainage paths on site.
Soil Erosion/
Control Of
Waste/ Earth Maintained construction equipment in good condition,There was not
pollution founded any oil, grease or chemical in the site area.

Noise Control Noise level was within allowable limit, There was not generated high
noise by construction activities.
No any public complains about noise disturbance.

Task Instruction was conducted according to the Environmental


Management plan for all workers.
Workers are briefed on a regular basis on basics of health& safety.
Security access point was safe and secured.
Health &
Safety HSE instruction was conducted according to site activities for workers.
Arrangements

Drinking water supplied in quality condition (70%) to site for Staff &
all workers.
All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
All the personal found wearing 70 % PPE at site.

Page | 16
No accident at sites during the month.

Location Items Managing & Monitoring Report

Material transporting vehicles covered and vehicle driving speed


controlled on the roads in the site area.(< 10 kmph).
Air Quality / Dust control process managed on 95%.
Dust Control

Four or three times per day were arranged the watering process for
dust control in the dry season.

Concrete Truck mixer and Equipment cleaning and washing process


Water Quality properly arranged in separate, suitable & removable place.
Prevented mosquito breeding in site area.
Dewatering system & waste water drains system properly arranged.
Reusable soil file was not blocked on the drainage paths on site.
Soil Erosion/
Control Of
Waste/ Earth Maintained construction equipment in good condition, there was not
Pipe founded any oil or grease at sites.
pollution
laying
Works Raining water dewatering process and drainage system arranged.
There was not a public complains about construction activities.
Noise Control
No any public complains about noise disturbance.

Task instructions were conducted according to the environmenta


management plan for all workers
Workers are briefed on a regular basis on basics of health & safety.
Safety signage was found satisfactory.
Health & Security access point was safe and secured.
Safety HSE instruction was conducted according to site activities for workers.
Arrangements All the personal found wearing 90% PPE at site.

All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
The condition of the workers camp is favorable between 80-85%.
No accident in during the month.

Page | 17
5.4. MONTHLY SAFETY PROGRESS
File
Client:- UNDP No:
CONSTRUCTION OF ……………………………..RWSS
Consultant:-CEYWATER

 Contractor:  
Construction Start Date:
Construction period: From to
Date Submitted:
Location of construction:
Person in charge:
Monthly Safety Report
Number of Cases
Accidents / Incidents Types
Project Goal
Current Month
LTI    
RWC    
MTC    
FAC    
NMC    
* LTI - Lost Time Injury, RWC-Restricted Work Case, MTC-Medical Treatment Case, FAC-First Aid Case,
NMC-Near Miss Case
Current Month
OSHA RECORDABLE INCIDENTS:
Fall (e.g.,floors,platform,roofs) 0 0 0 0 0 0 0
Struck by (e.g.,falling objects, vehicles) 0 0 0 0 0 0 0
Caught in /between (e.g.,cave-ins, unguarded
machinary) 0 0 0 0 0 0 0
Electrical (e.g.,overhead power lines,power
tool/cords, outlets) 0 0 0 0 0 0 0
Other (e.g.,cuts, burns, and other items not covered
above) 0 0 0 0 0 0 0
Excavation
Scaffolding  
Electricity
Safety Arrangements for
Barricading
sing board
installments
Safety meetings/Tool box talking/Trainings
Disciplinary Actions
Safety inspection by special visitors(times)

Page | 18
6. RESOURCE ALLOCATION
6.
6.1. ORGANIZATIONAL CHART

6.2. MANPOWER
6.2.1 OFFICE/SUPERVISORY STAFF

26-June 25-July
N Fr Sa Th Sa Fr Sa Fr Sa Fr
Position Name
o i t Sun Mon Tue Wed r Fri t Sun Mon Tue Wed Thr i t Sun Mon Tue Wed Thr i t Sun Mon Tue Wed Thr i Sat
26 27 28 29 30   2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
  Main Contractor                                                              
1 Project Manager 1 1   1 1   1 1 1   0 0 0 0 0 0   0   0 0 0     0 1 1 1 1 1
4 Construction Manager 1 1   1 1   1 1 1   1 1 1 1 1 1   1   1 1 1     1 1 1 1 1 1
5 Civil Manager 1 1   1 1   1 1 1   1 1 1 1 1 1   1   1 1 1     1 1 1 1 1 1
7 Machanical Manager 1 1   1 1   1 1 1   1 1 1 1 1 1   1   1 1 1     1 1 1 1 1 1
13 QA/QC Engineer 1 0   1 1   1 1 1   1 1 1 1 1 0   1   1 1 1     1 1 1 1 1 0
16 Site Engineer 1 0   1 1   1 1 1   1 1 1 1 1 1   1   1 0 1     1 1 1 0 1 0
24 Technical Officer 1 1   1 1   1 1 1   1 1 1 1 1 1   1   1 1 1     1 1 1 1 1 1
25 Quantity Surveyor 1 1   1 1   1 1 1   1 1 1 1 1 1   1   1 1 1     1 1 1 1 1 0
26 Lab Technician 1 1   1 1   0 0 0   1 1 1 1 1 1   1   1 1 1     0 0 1 1 1 0

Total 15 18 17 22 21 20 14 16 17 17 18 18 15 15 19 21 21 18 0 18 16 16 0 16 16 15 12 16 18 16

6.2.2 AT WTP SITE


CRIWMP-Construction of ……………………… RWSS
Manpower Report Site : WTP
26-Apr 25-May
Sa
No Position Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri t Sun Mon Tue Wed Thu Fri Sat
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Office Staff 3 5 7 7 8 6 2 4 3 4 3 4 4 5 4 2 1 2 0 0 3 4 0 6 2 2 1 1 2 4

Page | 19
2 Engineer 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 0 0 1 1 0 1 1 1 1 1 0 1
3 E.A 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Quantity Surveyor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 Surveyor 0 0 1 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 0 1 1 1 0 1 1 1 1 0 0 1
6 Technical Officer 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 0 0 1
7 Safety Officer 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 1
8 Foreman / Supervisor 2 2 2 2 1 2 1 2 1 1 2 2 2 2 1 2 2 3 0 2 2 2 0 2 1 2 2 1 1 1
9 Pipe Fitter 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 2 0
10 Mason 0 4 7 9 8 7 2 6 8 10 8 12 6 8 8 10 17 8 0 11 7 11 0 16 17 10 13 9 14 9
13 Machine Operator 1 1 1 2 1 1 1 1 1 0 2 2 0 2 2 0 2 0 0 2 1 1 0 1 3 2 2 1 0 0
14 Bar-bender 8 5 5 4 4 9 9 9 8 9 9 10 8 9 14 4 5 5 0 9 8 10 0 10 12 11 11 7 8 11
15 Driver 3 2 3 2 2 2 2 2 3 2 2 2 4 2 2 0 2 5 0 2 2 2 0 2 2 2 2 2 2 0
16 Other Skilled Labour 3 4 5 4 0 3 4 3 4 2 0 1 2 1 3 2 1 0 0 4 3 0 0 4 2 1 1 2 1 0
17 Unskilled 35 40 38 36 33 35 46 30 34 43 40 37 40 0 31 29 34 18 0 34 26 27 0 30 27 26 34 22 26 27
18 Flagman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Mechanic 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20 Trainee 8 0 10 10 10 11 10 11 10 11 11 11 10 10 11 11 11 6 0 10 9 11 0 11 10 10 9 10 10 11
21 Other 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 0 0 0 0 0 0
22 Welder 0 3 2 3 1 3 2 1 2 3 4 4 3 5 4 3 0 4 0 3 2 4 0 0 4 4 4 4 4 4
23 Lab technician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
24 Helper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 8
74 85 102 102 93 104 97 103 112 105 115 97 64 108 96 107 77 0 104 74 102 0 117 116 104 103 81 91
Total 8 5

6.2.3 AT PIPE LAYING


CRIWMP-Construction of ……………………… RWSS
Manpower Report ( 25th May 2019) Site :
26-Apr 25-May
No Position Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Office Staff 3 5 7 7 8 6 2 4 3 4 3 4 4 5 4 2 1 2 0 0 3 4 0 6 2 2 1 1 2 4
2 Engineer 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 0 0 1 1 0 1 1 1 1 1 0 1
3 E.A 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Quantity Surveyor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 Surveyor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Page | 20
6 Technical Officer 2 2 3 3 2 2 2 2 2 3 2 2 2 2 1 3 1 1 0 2 2 3 0 2 2 1 1 0 2 2
7 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 1
8 Foreman / Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Pipe Fitter 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 Mason 3 2 4 3 4 3 6 6 5 4 7 6 4 4 2 3 3 3 0 4 4 2 0 3 0 1 1 2 2 3
11 Carpenter 4 3 5 5 2 5 5 5 3 3 5 5 5 5 4 4 4 1 0 1 3 3 0 4 4 4 2 4 2 5
12 Electrician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

13 Machine Operator 1 1 2 2 1 1 1 1 1 2 1 0 0 0 1 2 1 1 0 0 0 2 0 1 1 1 1 0 0 0
14 Bar-bender 6 5 6 5 1 6 4 4 3 3 4 0 4 6 5 5 4 2 0 0 1 2 0 3 4 2 1 3 2 3
15 Driver 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 0 0 0 0 0 2 1 1 0 1 1 2
16 Other Skilled Labour 0 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Unskilled 17 12 16 15 9 14 19 17 14 16 14 14 16 14 11 9 7 4 0 10 8 12 0 15 6 6 7 7 5 14
18 Flagman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Mechanic 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20 Trainee 0 0 0 0 0 0 1 1 0 0 0 0 1 0 0 0 1 1 0 4 1 0 0 0 2 2 2 2 2 2
21 Welder 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 0 0 1 1 0 1 1 1 0 0 0 1
22 Lab technician 0 0 2 1 1 1 1 1 0 1 1 1 1 0 0 2 0 0 0 1 0 1 0 1 1 1 1 1 0 1
23 Security 1 1 1 1 1 1 1 1 0 1 1 1 1 1 0 1 1 1 0 1 1 1 0 1 1 1 0 0 0 1
24 SK 2 2 2 2 2 2 2 2 1 1 1 1 1 1 2 1 1 1 0 1 0 2 0 2 1 1 1 1 1 1
25 Other 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 43 37 52 48 35 45 50 48 37 42 43 39 43 42 35 35 28 21 0 25 26 35 0 43 28 26 20 24 20 41

6.3. MACHINERY AND EQUIPMENT

6.3.1 WTP

CRIWMP-Construction of ……………………… RWSS


Machinery and Equipment ( 25th May 2019 ) Site : WTP
25-May
26-Apr
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
Description

26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
No Item

                                                   
 

1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Excavator  
2 Backhoe   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Page | 21
3 Bob Cat   0 0 0 0 0 0 1 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0
4 Generators   1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 0
5 Lorries   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 0
6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Tipper  
7 Crane   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 Tractor   2 2 2 2 1 0 1 1 2 2 1 2 2 2 2 2 2 1 0 1 1 1 0 1 1 2 1 1 0 0
9 Water Bowser   1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 0
10 Compactor(Roller)   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 JCB   1 1 1 1 1 0 1 1 0 0 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 1 1 0
12 Asphalt Pumper   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13 Ten Ton Roller   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 2 Ton Roller   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15 Boom Truck   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 Bob Cat   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Van   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18 Pump Car   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Drilling Machine   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total   5 5 5 5 4 0 5 4 5 5 4 5 5 5 5 5 5 4 0 4 4 4 0 4 4 6 4 4 4 0

6.3.2 Pipe Laying


CRIWMP-Construction of ……………………… RWSS
25-May
26-Apr    
Description

Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
No Item 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

                                                   
 

 
1 Excavator   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 Backhoe   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Boom Truck   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 Tipper   0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
6 Lorries   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Tractor   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 Crane   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Crew Cab   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 Compactor (Roller)   0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 Compactor (Wacker)   0 4 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Page | 22
12 Rammer   0 0 2 3 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
14 Submersible Pump   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15 Dewatering Pump   0 1 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 Generators   0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Water Bowser   0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18 Eng.Level   0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
19 JCB   0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
20 Drilling Machine   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
21 Flash Light   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
23 PE machine   0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total   0 19 19 19 9 0 4 10 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 0 0 0 0 0

Page | 23
7. WEATHER REPORT

8. PROGRESS PHOTOS`
7

Page | 24
8.1. INTAKE/PUMP HOUSE
PHOTO LOG
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME MAIN STRUCTURE DATE 20-05-2019
CONTENTS WORKS AT INTAKE STRUCTURE
`   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME MAIN STRUCTURE DATE 18-05-2019
CONTENTS INTAKE

8.2. WTP
PHOTO LOG

Page | 25
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME WATER TREATMENT PLANT DATE
CONTENTS
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME WATER TREATMENT PLANT DATE
CONTENTS

Page | 26
PHOTO LOG
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME WATER TREATMENT PLANT DATE 24-05-2019
CONTENTS CHEMICAL HOUSE BLOCKWORK
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME WATER TREATMENT PLANT DATE 10-05-2019
CONTENTS ADMINISTRATION BUILDING WALL PLASTERING WORK

Page | 27
8.3. PIPE LAYING

PHOTO LOG
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME POLPITHIGAMA DISTRIBUTION DATE 15-05-2019
CONTENTS CULVERT CROSSING WORK
   
   
   
   
   
   
   
   
   
   

Page | 28
   
   
   
   
   
   
SITE NAME DISTRIBUTION DATE
CONTENTS PVC PIPE LAYING
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
SITE NAME MADAGALLA HIRIPITIYA ROAD DATE 15-05-2019
CONTENTS PIPE TRENCH PREPARATION
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   

Page | 29
   
SITE NAME …………………………. ROAD DATE
CONTENTS PIPE LAYING WORK
PHOTO LOG
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   

8.4. SAFETY PROGRESS


PHOTO LOG
   
   
   
   
   

   
   
   
   
   
   
   
   
   
   
   

Page | 30
CONTENTS ROAD SAFETY ARRANGEMENT WORK AT PIPE LAYING
   
   
   
   
   
   
   
   
   
   
   
   
   
   
 
 
   
ROAD SAFETY ARRANGEMENT/TRAFIC CONTROL WORK AT
CONTENTS
PIPE LAYING
9
10
PHOTO LOG
   
   
   
   
   

   
   
   
   
   
   
   
   
   
   
   
CONTENTS SAFETY EQUIPMENT USING IN SITE
   
   
   

Page | 31
   
   
   
   
   
   
   
   
   
   
   
 
 

   
CONTENTS SAFETY EQUIPMENT USING IN SITE
11
12
13
PHOTO LOG
   
   
   
   
   

   
   
   
   
   
   
   
   
   
   
  PPE  
CONTENTS DUST CONTROLING WORK
   
   
   
   
   

Page | 32
   
   
   
   
   
   
   
   
   
 
 

   
CONTENTS SPEED LIMIT SIGN BOARD IN SITE

Page | 33
Page | 34

You might also like