Progress Format For CRIWMP
Progress Format For CRIWMP
CONTRACT NO:
AUGUST 2020
EMPLOYER : UNDP
CONTRACTOR :
Contents
1. PROJECT SUMMARY
Page | 1
1.1 Project Details
6.3.1 WTP
7. WEATHER REPORT
8. PROGRESS PHOTOS`
8.1. INTAKE/PUMP HOUSE
8.2 WTP
Page | 2
1. PROJECT SUMMARY
1.1. Project Details
Name of Employer
Name of Consultant
Name of Contractor
Contract Amount
Date of Commencement
Date of Completion
Treatment Plant
Intakes/pump house
Pumping main
Distribution/service connection
Elevated Tower
Buildings
Page | 3
2. PROGRESS
2.1 OVERALL PROGRESS
Overall Progress Rate :
Up to July 2020 Up to Up to
June.
ITEM NO DESCRIPTION WTG July. 2020 July. 2020
2020
Plan Actual (Plan) (Actual)
(Actual)
OVERALL PROGRESS 100.0%
21 Contractors Facility
Page | 4
5.0 Pipe Laying Work
2.1.
2.2. INSURANCE, BONDS, PRELIMINARIES PROGRESS
Insurance, Bonds and Preliminaries Progress Rate : 100.00%
2.1.2
2.1.3
2.1.4
2.1.5
Page | 5
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.4. RAW WATER INTAKE PUMP HOUSE, WATER TREATMENT PLANT AND RESERVIORS /TOWERS CONSTRUCTION
PROGRESS
Task Name CIVIL MECH
I Construction of INTAKE PUMP HOUSE
II Construction of WTP
III Construction of Reservoirs/Towers
Civil Works
Excavation
Foundation
Wall
Brick wall
Roofing
Plaster & Painting
Doors and windows
Finishing
Erection of Cables
Lighting Erection
Earthing erection
Electrical & Instrument Erection
MCC panel Erection
PLC panel Erection
Termination & Dressing
5.
WATER TREATMENT PLANT
0
Page | 6
5. CONSTRUCTION OF WATER TREATMENT
PLANT
2
5.2.1 Site Works
5.2.2 Cascade Aerator
Civil Works
Excavation
Footings & Ground Beam Concreting
Slab and Beam Concrete
Wall Concrete
Hydro testing
Finishing
Mechanical Works
Installation of flow meter and valves
Piping works
Other Misc. Works
5.2.4 Roughing Filter
Civil Works
Excavation
Base Concreating
Ferro Cement works
Pipe Fixing
Filter Media
Pipe Gallery Outlet Chamber
Hydro test
Finishing
Cable Erection
Instruments Installation
Other Misc Works
Slow sand Filter
Excavation
Base Concreating
Ferro Cement works
Pipe Fixing
Filter Media
Pipe Gallery Outlet Chamber
Hydro test
Finishing
Erection of Mechanical & Piping Works
Filter Inlet & Backwash valve Instalaltion
Page | 7
Installation of Air blower with related work
Valves and pipe installaion in filter gallery
Pneumatic Air Line
Submersible Dewatering Pump & Pipeline
Placing of Filter Media
Erection of Electrical & I Works
Cable Erection
Instruments Installation
Other Misc Works
Other miscelaneous work
Cable erection
Installation of panels
6.
CONSTRUCTION OF Towers
2
Civil Works
Shaft concreting
Slab concreting
Ferro cement wall
Roof dome Construction
Hydro Test
Finishing
Instrumentation erection
Electrical Lighting works
pump house
Civil works
Excavation
foundation
Wall
Roofing works
Plastering & painting
Finshing works
Mechanical erection work
Installation of Pen Stock gates
Inlet Pipe Line connection
Pumps installation
Pump Suction & Discharge Pipe Line
Other miscellaneous work
Electrical erection work
Page | 8
Cable erection
Installation of panels
Sl. No Description
3 Temporary Reinstatement
4 Pressure Testing
5 Chamber Construction
7 Culvert Crossings
CONSTRUCTION PROGRESS
Disinfection
Commissioning
Sl. No Description
Page | 9
1 Excavation & Laying
Backfilling Including Compaction
2
Test
3 Temporary Reinstatement
4 Pressure Testing
7 Culvert Crossings
CONSTRUCTION PROGRESS
Disinfection
Commissioning
Page | 10
Surge tank
Pumps
Backwash Water pumps
booster pumps
Chlorine Dosing Pump
Flowmeters
ITEM NO DESCRIPTION WEIGHTAGE COMPLETED %
Mechanical Equipment
Valves
Transmission Pumps
Electrical Equipment
Distribution board
Communication Panel
Wireless Communication
Motor Control panel
Local Control Panel
Instrumentation Panel
Diaphragm Pressure Transmitter
Ultrasonic level Transmitter
Diaphragm Pressure switches
Level Switches
Page | 11
7.1 DISTRIBUTION NETWORK
7.1.1 PVC Pipes and Fittings
3. PROJECT SCHEDULES
3.1. CONSTRUCTION WORK SCHEDULE
Page | 12
4. PAYMENTS
4.1. STATES OF PAYMENTS
YEAR 2019/20
UNITS:USD *1000
Februar
Month January y March April May June July August September October November December Total
Payment recieved
Cumulative - - - - - - - - - -
Approved and
1
Continue
Page | 13
Approved and
2
Continue
Approved and
3
Continue
Approved and
4
Continue
Approved and
5
Continue
Approved and
6
Continue
Page | 14
5.3. MONTHLY ENVIRONMENTAL PROGRESS
Client:-UNDP File
No:
CONSTRUCTION OF
……………………………..RWSS
Con:-CEYWATER
CONTRACTOR:-
Four or three times per day were arranged the watering process for
dust control in the dry season.
Page | 15
Task instructions were conducted according to the environmental
management plan for all workers
Workers are briefed on a regular basis on basics of health & safety.
?>
Security access point was safe and secured.
HSE instruction was conducted according to site activities for workers.
Health & All the personal found wearing 90% PPE at site.
Safety
Arrangements
All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
The condition of the workers camp is favorable between 80-85%.
No accident in during the month.
Dust control process managed on 90%.
Vehicle driving speed controlled on the roads in the site area. (< 10
kmph).
Water Quality Concrete Truck mixer and Equipment cleaning and washing process
properly arranged in separate, suitable & removable place.
Prevented mosquito breeding in site area.
Reusable soil file was not blocked on the drainage paths on site.
Soil Erosion/
Control Of
Waste/ Earth Maintained construction equipment in good condition,There was not
pollution founded any oil, grease or chemical in the site area.
Noise Control Noise level was within allowable limit, There was not generated high
noise by construction activities.
No any public complains about noise disturbance.
Drinking water supplied in quality condition (70%) to site for Staff &
all workers.
All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
All the personal found wearing 70 % PPE at site.
Page | 16
No accident at sites during the month.
Four or three times per day were arranged the watering process for
dust control in the dry season.
All deep excavation areas covered using hard barricade & tarpaulin to
protect work force.
The condition of the workers camp is favorable between 80-85%.
No accident in during the month.
Page | 17
5.4. MONTHLY SAFETY PROGRESS
File
Client:- UNDP No:
CONSTRUCTION OF ……………………………..RWSS
Consultant:-CEYWATER
Contractor:
Construction Start Date:
Construction period: From to
Date Submitted:
Location of construction:
Person in charge:
Monthly Safety Report
Number of Cases
Accidents / Incidents Types
Project Goal
Current Month
LTI
RWC
MTC
FAC
NMC
* LTI - Lost Time Injury, RWC-Restricted Work Case, MTC-Medical Treatment Case, FAC-First Aid Case,
NMC-Near Miss Case
Current Month
OSHA RECORDABLE INCIDENTS:
Fall (e.g.,floors,platform,roofs) 0 0 0 0 0 0 0
Struck by (e.g.,falling objects, vehicles) 0 0 0 0 0 0 0
Caught in /between (e.g.,cave-ins, unguarded
machinary) 0 0 0 0 0 0 0
Electrical (e.g.,overhead power lines,power
tool/cords, outlets) 0 0 0 0 0 0 0
Other (e.g.,cuts, burns, and other items not covered
above) 0 0 0 0 0 0 0
Excavation
Scaffolding
Electricity
Safety Arrangements for
Barricading
sing board
installments
Safety meetings/Tool box talking/Trainings
Disciplinary Actions
Safety inspection by special visitors(times)
Page | 18
6. RESOURCE ALLOCATION
6.
6.1. ORGANIZATIONAL CHART
6.2. MANPOWER
6.2.1 OFFICE/SUPERVISORY STAFF
26-June 25-July
N Fr Sa Th Sa Fr Sa Fr Sa Fr
Position Name
o i t Sun Mon Tue Wed r Fri t Sun Mon Tue Wed Thr i t Sun Mon Tue Wed Thr i t Sun Mon Tue Wed Thr i Sat
26 27 28 29 30 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Main Contractor
1 Project Manager 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 1 1 1 1 1
4 Construction Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
5 Civil Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7 Machanical Manager 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
13 QA/QC Engineer 1 0 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 0
16 Site Engineer 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 1 0 1 0
24 Technical Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
25 Quantity Surveyor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0
26 Lab Technician 1 1 1 1 0 0 0 1 1 1 1 1 1 1 1 1 1 0 0 1 1 1 0
Total 15 18 17 22 21 20 14 16 17 17 18 18 15 15 19 21 21 18 0 18 16 16 0 16 16 15 12 16 18 16
Page | 19
2 Engineer 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 0 0 1 1 0 1 1 1 1 1 0 1
3 E.A 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Quantity Surveyor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 Surveyor 0 0 1 1 1 1 1 1 1 1 1 1 0 0 1 1 1 1 0 1 1 1 0 1 1 1 1 0 0 1
6 Technical Officer 0 0 0 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 0 0 1
7 Safety Officer 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 1
8 Foreman / Supervisor 2 2 2 2 1 2 1 2 1 1 2 2 2 2 1 2 2 3 0 2 2 2 0 2 1 2 2 1 1 1
9 Pipe Fitter 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 2 0
10 Mason 0 4 7 9 8 7 2 6 8 10 8 12 6 8 8 10 17 8 0 11 7 11 0 16 17 10 13 9 14 9
13 Machine Operator 1 1 1 2 1 1 1 1 1 0 2 2 0 2 2 0 2 0 0 2 1 1 0 1 3 2 2 1 0 0
14 Bar-bender 8 5 5 4 4 9 9 9 8 9 9 10 8 9 14 4 5 5 0 9 8 10 0 10 12 11 11 7 8 11
15 Driver 3 2 3 2 2 2 2 2 3 2 2 2 4 2 2 0 2 5 0 2 2 2 0 2 2 2 2 2 2 0
16 Other Skilled Labour 3 4 5 4 0 3 4 3 4 2 0 1 2 1 3 2 1 0 0 4 3 0 0 4 2 1 1 2 1 0
17 Unskilled 35 40 38 36 33 35 46 30 34 43 40 37 40 0 31 29 34 18 0 34 26 27 0 30 27 26 34 22 26 27
18 Flagman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Mechanic 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20 Trainee 8 0 10 10 10 11 10 11 10 11 11 11 10 10 11 11 11 6 0 10 9 11 0 11 10 10 9 10 10 11
21 Other 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 0 0 0 0 0 0
22 Welder 0 3 2 3 1 3 2 1 2 3 4 4 3 5 4 3 0 4 0 3 2 4 0 0 4 4 4 4 4 4
23 Lab technician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
24 Helper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 8
74 85 102 102 93 104 97 103 112 105 115 97 64 108 96 107 77 0 104 74 102 0 117 116 104 103 81 91
Total 8 5
Page | 20
6 Technical Officer 2 2 3 3 2 2 2 2 2 3 2 2 2 2 1 3 1 1 0 2 2 3 0 2 2 1 1 0 2 2
7 Safety Officer 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 1
8 Foreman / Supervisor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Pipe Fitter 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 Mason 3 2 4 3 4 3 6 6 5 4 7 6 4 4 2 3 3 3 0 4 4 2 0 3 0 1 1 2 2 3
11 Carpenter 4 3 5 5 2 5 5 5 3 3 5 5 5 5 4 4 4 1 0 1 3 3 0 4 4 4 2 4 2 5
12 Electrician 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13 Machine Operator 1 1 2 2 1 1 1 1 1 2 1 0 0 0 1 2 1 1 0 0 0 2 0 1 1 1 1 0 0 0
14 Bar-bender 6 5 6 5 1 6 4 4 3 3 4 0 4 6 5 5 4 2 0 0 1 2 0 3 4 2 1 3 2 3
15 Driver 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1 1 0 0 0 0 0 2 1 1 0 1 1 2
16 Other Skilled Labour 0 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Unskilled 17 12 16 15 9 14 19 17 14 16 14 14 16 14 11 9 7 4 0 10 8 12 0 15 6 6 7 7 5 14
18 Flagman 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Mechanic 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
20 Trainee 0 0 0 0 0 0 1 1 0 0 0 0 1 0 0 0 1 1 0 4 1 0 0 0 2 2 2 2 2 2
21 Welder 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 0 0 1 1 0 1 1 1 0 0 0 1
22 Lab technician 0 0 2 1 1 1 1 1 0 1 1 1 1 0 0 2 0 0 0 1 0 1 0 1 1 1 1 1 0 1
23 Security 1 1 1 1 1 1 1 1 0 1 1 1 1 1 0 1 1 1 0 1 1 1 0 1 1 1 0 0 0 1
24 SK 2 2 2 2 2 2 2 2 1 1 1 1 1 1 2 1 1 1 0 1 0 2 0 2 1 1 1 1 1 1
25 Other 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 43 37 52 48 35 45 50 48 37 42 43 39 43 42 35 35 28 21 0 25 26 35 0 43 28 26 20 24 20 41
6.3.1 WTP
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
No Item
1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Excavator
2 Backhoe 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Page | 21
3 Bob Cat 0 0 0 0 0 0 1 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0
4 Generators 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 0
5 Lorries 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 1 0
6 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Tipper
7 Crane 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 Tractor 2 2 2 2 1 0 1 1 2 2 1 2 2 2 2 2 2 1 0 1 1 1 0 1 1 2 1 1 0 0
9 Water Bowser 1 1 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 0
10 Compactor(Roller) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 JCB 1 1 1 1 1 0 1 1 0 0 1 1 1 1 1 1 1 0 0 1 1 1 0 1 1 1 1 1 1 0
12 Asphalt Pumper 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
13 Ten Ton Roller 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
14 2 Ton Roller 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15 Boom Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 Bob Cat 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Van 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18 Pump Car 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
19 Drilling Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 5 5 5 5 4 0 5 4 5 5 4 5 5 5 5 5 5 4 0 4 4 4 0 4 4 6 4 4 4 0
Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
No Item 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Excavator 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
2 Backhoe 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
4 Boom Truck 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
5 Tipper 0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
6 Lorries 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
7 Tractor 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
8 Crane 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9 Crew Cab 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
10 Compactor (Roller) 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 Compactor (Wacker) 0 4 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Page | 22
12 Rammer 0 0 2 3 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
14 Submersible Pump 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
15 Dewatering Pump 0 1 0 0 0 0 0 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
16 Generators 0 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
17 Water Bowser 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
18 Eng.Level 0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
19 JCB 0 4 4 4 2 0 1 2 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0
20 Drilling Machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
21 Flash Light 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
23 PE machine 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total 0 19 19 19 9 0 4 10 8 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 0 0 0 0 0
Page | 23
7. WEATHER REPORT
8. PROGRESS PHOTOS`
7
Page | 24
8.1. INTAKE/PUMP HOUSE
PHOTO LOG
SITE NAME MAIN STRUCTURE DATE 20-05-2019
CONTENTS WORKS AT INTAKE STRUCTURE
`
SITE NAME MAIN STRUCTURE DATE 18-05-2019
CONTENTS INTAKE
8.2. WTP
PHOTO LOG
Page | 25
SITE NAME WATER TREATMENT PLANT DATE
CONTENTS
SITE NAME WATER TREATMENT PLANT DATE
CONTENTS
Page | 26
PHOTO LOG
SITE NAME WATER TREATMENT PLANT DATE 24-05-2019
CONTENTS CHEMICAL HOUSE BLOCKWORK
SITE NAME WATER TREATMENT PLANT DATE 10-05-2019
CONTENTS ADMINISTRATION BUILDING WALL PLASTERING WORK
Page | 27
8.3. PIPE LAYING
PHOTO LOG
SITE NAME POLPITHIGAMA DISTRIBUTION DATE 15-05-2019
CONTENTS CULVERT CROSSING WORK
Page | 28
SITE NAME DISTRIBUTION DATE
CONTENTS PVC PIPE LAYING
SITE NAME MADAGALLA HIRIPITIYA ROAD DATE 15-05-2019
CONTENTS PIPE TRENCH PREPARATION
Page | 29
SITE NAME …………………………. ROAD DATE
CONTENTS PIPE LAYING WORK
PHOTO LOG
Page | 30
CONTENTS ROAD SAFETY ARRANGEMENT WORK AT PIPE LAYING
ROAD SAFETY ARRANGEMENT/TRAFIC CONTROL WORK AT
CONTENTS
PIPE LAYING
9
10
PHOTO LOG
CONTENTS SAFETY EQUIPMENT USING IN SITE
Page | 31
CONTENTS SAFETY EQUIPMENT USING IN SITE
11
12
13
PHOTO LOG
PPE
CONTENTS DUST CONTROLING WORK
Page | 32
CONTENTS SPEED LIMIT SIGN BOARD IN SITE
Page | 33
Page | 34