Item No L B
Excavation Cum 1 4.5 3.4
PCC Cum 1 3.6 2.5
Bottom RCC Cum 1 3.5 2.4
Steel kg
Brick Work (Long Wall) Cum 2 3 0.5
Brick Work (Short Wall) Cum 2 1.9 0.5
PCC (Screed) Cum
PVC Pipe Mtr
Top Slab Cum 1 2.5 1.4
Manhole Cover 1
Plaster Sqm 2 1.9
Sqm 2 3
Item Quantity
Excavation 16.4475
H QUANTITY RCC (M-25) 1.9425
1.075 16.4475 PCC (M-20) 1.175
0.075 0.675 Steel 150
0.2 1.68 Brick Work 9.6775
150
PVC Pipe 2
1.975 5.925
1.975 3.7525 Plaster (16 mm , 1:3) 19.355
Manhole Cover
0.5
1.5
0.075 0.2625
1.975 7.505
1.975 11.85
Rate Amount
400 6579
10000 19425
7500 8812.5
53 7950
11000 106452.5
1000 2000
400 7742
2500
161461
Item No L B H
Excavation Cum 1 2.5 3.3
Brick Work Cum 1 2 3.3
1 2.5 3.3
Boulder
QUANTITY Rate Amount
16.190625 400 6476.25
10.362
16.190625
5.828625 11000 64114.875
70591.125
232052.125