0% found this document useful (0 votes)
323 views3 pages

5 APQP 1 of 3

The document outlines Indico Motors' quality procedure for advance product quality planning (APQP). It establishes guidelines for preparing a quality plan before developing a new or modified product. A cross-functional team is formed representing key departments. They identify customer requirements, develop a timing plan, and conduct various quality activities like failure mode analysis and process capability studies. This includes production trials, testing samples, and submitting them to the customer for approval before regular production begins. The procedure aims to satisfy customers and ensure quality is built into new products from the start.

Uploaded by

P G Suman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
323 views3 pages

5 APQP 1 of 3

The document outlines Indico Motors' quality procedure for advance product quality planning (APQP). It establishes guidelines for preparing a quality plan before developing a new or modified product. A cross-functional team is formed representing key departments. They identify customer requirements, develop a timing plan, and conduct various quality activities like failure mode analysis and process capability studies. This includes production trials, testing samples, and submitting them to the customer for approval before regular production begins. The procedure aims to satisfy customers and ensure quality is built into new products from the start.

Uploaded by

P G Suman
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

INDICO MOTORS PVT. LTD.

M-25P & M-26, IV Phase, Adityapur Industrial Area, Gamharia, Jamshedpur – 832108.
Procedure No. : IM / QP / 7.1
Rev No : 00
QUALITY PROCEDURE Rev Date :
Page : 01 of 03
TITLE : ADVANCE PRODUCT QUALITY PLANNING
0.1 Purpose : To establish a procedure providing guideline for preparing a ‘Product Quality Plan’ in
Advance of development of a new or modified product that will satisfy the customer.
0.2 Scope : Application to all new / modified component during its production or development.
0.3 Reference : Clause No 7.1 of IATF 16949:2016 and Quality Manual.
0.4 Definition : MD – Managing Director, FMEA – Failure Mode Effect Analysis, APQP – Advanced
Product Quality Planning, SPC – Statistical Process Control, MSA – Measurement System Analysis,
PPAP – Production Part Approval Process.
Sl. ACTIVITY Responsibility Ref. Doc /
No. Record

5.0 A cross functional team comprising representatives from the following area MD
is formed to carry out APQP for the item taken up for development.

 Product development.
 Production
 Quality
 Purchase
Involvement of representative from Supplier / External expert is also sought,
as and when required.

6.0 As APQP team leader is identified and responsibility is assigned to each MD


team member.

7.0 Customer Requirements are obtained from the following sources. APQP Team

 Customer drawing supplied by customer.


 Standard referred to in the drawing of supplied separately.
 Customer Requirement Evaluation Format.
 Manufacturing feasibility report.

8.0 A timing plan defining various tasks / assignments to be completed within a APQP Team
time frame is prepared indicting PDC for various activities as per checklist.

9.0 The preliminary special characteristics for the product is identified and listed APQP Team
based on customer supplied documents (Para 7.0) or from experience.
A comprehensive and critical review of all engineering requirements, related
technical information and design factor is carried out as per checklist.

10. The availability of production facilities / tools and gauges, new die & APQP Team
inspection gauges are studied and procurement action taken as per checklist.

Prepared By: Approved By: Review & Release


Controlled By:

MR Director Management Representative


No Copying or extraction from this document without IMPL’s Permission Issue No: 01
Effective Date:
INDICO MOTORS PVT. LTD.
M-25P & M-26, IV Phase, Adityapur Industrial Area, Gamharia, Jamshedpur – 832108.
Procedure No. : IM / QP / 7.1
Rev No : 00
QUALITY PROCEDURE Rev Date :
Page : 02 of 03
TITLE : ADVANCE PRODUCT QUALITY PLANNING
Sl. ACTIVITY Responsibility Ref. Doc /
No. Record

11.0 Packaging standard as per specified by customer is followed in case no APQP Team
packing standard is specified by customer, the one existing in company for
similar product is followed.

12.0 Requirement of any new supplier for the product is identified by the team
at these stages.

13.0 A review of product / process quality system is done as per checklist.

14.0 Review and defining process flow is done as per checklist.

15.0 Development of floor plan lay out is done indicating inspection point /
control chart locations, visual aids storage area for non – conforming
product as per checklist.

16. Development of failure mode and effect analysis is done as per procedure
IM / QP / 7.3.1.1 using checklist. QP stand for Quality Procedure

17. Development of pre launch control plan is done as per procedure IM/ QP /
7.3.1.1 using checklist.

18. Job instruction sheet is developed for the operating personnel for the
purpose of process operation.

19. Planning for measurement system analysis is done for measuring devices
appearing in the pre launch control plan.

20. Planning for preliminary process capability study Pp/Ppk is done for
critical / major characteristics appearing in the pre launch control plan.

21. Production trial run is conducted for minimum of one body sample as
agreed by the customer.

22. Preliminary process capability study Pp/Ppk is done for the characteristics
already identified in Para 20.

23. Measurement system analysis is done as per procedure IM/ QP / 7.6.1

Prepared By: Approved By: Review & Release


Controlled By:

MR Director Management Representative


No Copying or extraction from this document without IMPL’s Permission Issue No: 01
Effective Date:
INDICO MOTORS PVT. LTD.
M-25P & M-26, IV Phase, Adityapur Industrial Area, Gamharia, Jamshedpur – 832108.
Procedure No. : IM / QP / 7.1
Rev No : 00
QUALITY PROCEDURE Rev Date :
Page : 03 of 03
TITLE : ADVANCE PRODUCT QUALITY PLANNING
Sl. ACTIVITY Responsibility Ref. Doc /
No. Record

24. Dimensional & metallurgical testing / inspection of sample parts is APQP Team
evaluated as required by the customer or as per PPAP requirement.

25. Representative sample 1 no preferably or as specified by the customer are


taken randomly from production trial run and sent to customer along with
supporting documents and records as per PPAP procedure for approval.

26. Based on customer feedback necessary modification is done in the pre


launch control plan. Pre launch control plan after necessary modification if
any are regularized, as production control plan for commencement of
regular production.

27. Preliminary process monitoring instruction (PMI) is modified suitably as


per production control plan and distributed to all operation personnel for
the purpose of process operation.

28. Product quality planning summary & sign off is completed as per format.

29. Based on feedback from the customer, ongoing improvement on


continuous basis is followed.

30. At the end of each phase of product development, the progress of status of
various activities is reviewed by the upper management and necessary
corrective measures are initiated accordingly as per the concern resolution
format.

Prepared By: Approved By: Review & Release


Controlled By:

MR Director Management Representative


No Copying or extraction from this document without IMPL’s Permission Issue No: 01
Effective Date:

You might also like