Estimate

This document provides a bill of materials and cost estimates for the construction of a perimeter fence with gate in Maitum, Davao Oriental. It outlines 5 items of work including site works, formworks and scaffoldings, reinforced concrete works, masonry works, and structural steel works. The total direct cost of the project is estimated to be 120,873.25 PHP, which includes 92,465 PHP for materials and 28,408.25 PHP for labor and equipment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views1 page

Estimate

This document provides a bill of materials and cost estimates for the construction of a perimeter fence with gate in Maitum, Davao Oriental. It outlines 5 items of work including site works, formworks and scaffoldings, reinforced concrete works, masonry works, and structural steel works. The total direct cost of the project is estimated to be 120,873.25 PHP, which includes 92,465 PHP for materials and 28,408.25 PHP for labor and equipment.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROJECT: CONSTRUCTION OF PERIMETER FENCE WITH GATE

LOCATION: MAITUM, BRGY. DAHICAN, MATI CITY,DAVAO ORIENTAL


SUBJECT: BILL OF MATERIAL AND COST ESTIMATES
ITEM MATERIAL COST LABOR &
ITEM OF WORK TOTAL COST
NO. QTY. UNIT UNIT PRICE UNIT COST EQUIPMENT COST

I SITE WORKS 9,110.00

i.i Clearing of site 200 sq.m 30.00 6,000.00


i.ii Layout
#60 Layout String 1 rolls 120.00 120.00

2" x 2" x 12' Coco Lumber 30 bd.ft. 20.00 600.00

Assorted CW Nails 2 kgs. 70.00 140.00


i.iii Earthworks
Excavation (Column Footings) 15 cu.m. 2,250.00

Sub Total = 860.00 8,250.00 9,110.00

II FORMWORKS AND SCAFFOLDINGS 8,957.00

Materials
4'x8'x1/4 Ordinary Plywood 9 sheets 310.00 2,790.00

2''x3''x12' coco lumber" 100 bd.ft. 15.00 1,500.00

2" x 2" x 12' Coco Lumber 150 bd.ft. 15.00 2,250.00

Assorted CW Nails 5 kgs. 70.00 350.00

Sub Total = 6,890.00 2,067.00 8,957.00

III REINFORCED CONCRETE WORKS 28,706.25

Materials
Portland Cement 20 bags 260.00 5,200.00

Washed Gravel(includes gravel fill) 6 cu.m. 550.00 3,300.00

Washed Sand 6 cu.m. 550.00 3,300.00

12mmØx6m def bars (Grade 40)" 25 pcs. 180.00 4,500.00

10mmØx6m def bars (Grade 40)" 40 pcs. 150.00 6,000.00

#16 G.I Tie Wire 7 kgs. 95.00 665.00

Sub Total = 22,965.00 5,741.25 28,706.25

IV MASONRY WORKS 45,780.00

Materials
100mm thk. CHB 1,500 pcs. 15.00 22,500.00

Portland Cement 15 bags 260.00 3,900.00

Washed Sand 6 cu.m. 550.00 3,300.00

12mmØx6m def bars (Grade 40)" 20 pcs. 180.00 3,600.00

10mmØx6m def bars (Grade 40) 30 pcs. 150.00 4,500.00

#16 G.I Tie Wire 5 kg 70.00 350.00

Sub Total = 38,150.00 7,630.00 45,780.00

V STRUCTURAL STEEL WORKS 28,320.00

Materials
2''X3'' Rectangular Tube 25 pcs. 800.00 20,000.00

Welding Rods 2 boxes 1,800.00 3,600.00

4'' Cutting Disc 2 boxes 800.00 1,600.00

Sub Total = 23,600.00 4,720.00 28,320.00


TOTAL MATERIAL COST 92,465.00
TOTAL LABOR AND EQUIPMENT COST 28,408.25

TOTAL DIRECT COST 120,873.25

Owner:

PRC NO. :0143159


Reviewed by: PTR NO. :3714732C
PLACE ISSUED :DAVAO CITY
DATE ISSUED :1/31/2020
TIN NO. :702-013-579-000