Retail Permit To Work System - Job Hazard Analysis

The document outlines the job hazard analysis for work requiring a retail permit at a fuel station. It identifies 5 key job steps: 1) completing paperwork and conducting a toolbox talk, 2) isolating the work area, 3) isolating the power supply, 4) gas testing the tank sump, and 5) shutting down dispensers, pumps, and nitrogen purging. Hazards are identified for each step such as electrocution, fuel vapors, and traffic. Controls are also specified like using barricades, licensed electricians, gas detectors, locking out tag out procedures, and personal protective equipment.

Uploaded by

Santhosh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views

Retail Permit To Work System - Job Hazard Analysis

The document outlines the job hazard analysis for work requiring a retail permit at a fuel station. It identifies 5 key job steps: 1) completing paperwork and conducting a toolbox talk, 2) isolating the work area, 3) isolating the power supply, 4) gas testing the tank sump, and 5) shutting down dispensers, pumps, and nitrogen purging. Hazards are identified for each step such as electrocution, fuel vapors, and traffic. Controls are also specified like using barricades, licensed electricians, gas detectors, locking out tag out procedures, and personal protective equipment.

Uploaded by

Santhosh Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 7

RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

Will the work involve any of the activities below? (Circle any that apply)
Date: If ‘YES’ a Permit must be obtained

Prepared by:
Hot work in Hazardous areas Confined space entry Excavation >/= 1.2 m
Company:
Work on Flammable
Inerting or Gas Freeing Live Electrical Work
Retail Station Address: Gas Systems
Other (specify): Lifting
Asbestos Work Explosive Blasting work

Step
Job Steps Job Steps Hazards Job Steps Control
No.
Complete the Work Clearance Form (WCF) &  Unfamiliar with project scope &  TBT to be conducted by site In charge.
1
TBT. hazard involve in work  WCF & Safety document to be filled.

 Provide mobile barricade,


 Safety reflector jacket, helmet, safety shoes,
hand gloves & nose mask must be used on
 Traffic Hazard ,
site.
 Hit by vehicle,
2 Isolate work area / Install barricades  Provide sign board,
 Unauthorized person entry.
 Standing supervision to monitor traffic while
work on forecourt area,
 Only authorized person can enter into work
area.

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

 Accredited and experienced electrician to be


deployed for the work. (Safety passport is a
must – He cannot access site without this.)
 Cut off power supply of the STP. (LOTOTO)
Lock the switchboard circuits to the STP, Tag
3 Isolation of power supply  Electrocution
circuits, and test out isolation by trying to
start pump by lifting dispenser nozzle.
 Communication should be given to the
supervisor about applying/removal of
LOTOTO & shall be documented.
 Calibrated Gas tester available with
certificate and competency of the contractor
on its usage.
 Gas test to be conducted for LEL
 Fuel vapour  Leave the UGT sump open for some time to
 Defective gas detector allow vapour displacement if any
4 Gas-Test for the Tank Sump  Untrained person  All unsealed opening of the UGT/ TLD
 Fire hazard sensors /dip cap to be tightened not
 Body injury allowing vapour back to tank sump.
 Gas tester must be explosion proof
 Place the First aid kit & display ERP.
 Trained skilled & experience person only
allow to work

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

 GIDS Design standard for Fuel system


Mandatory standards, equipment
specification and assurance
 Local regulations
 Design Risk Assessment (DRA)
 Mandatory certification of the system
 Components
 Loss of containment leading to
 Provide regular maintenance, Critical
fatality,
Equipment Inspections (CEI) and testing.
 Personal injury,
 Use of accredited competent people with
 Environmental damage,
5 Shut Down DU ,STP & Nitrogen Purging approved equipment
 Asset damage
 Follow LOTOTO to isolate the energy
 Fire,
(electric, hydraulic, pressure, etc.).
 Explosion,
 Ensure proper commissioning of Fuel system
 Reputation damage.
equipment, installation and testing (GIDS
Documents).
 Carry out Last Minute Risk Assessment
 Execute the Emergency Response Plan.
 First aid Kits
 Safety reflector jacket, helmet, safety shoes,
hand gloves & nose mask must be used on
site.

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

 Provide standby fire Extinguisher,


 Provide sand buckets,
 Use anti spark tools.
 Water reflective vest while working at night,
 Isolate the work area & traffic management,
 Unauthorized tools.  Skilled & Trained person,
 Moving vehicle may hit to work  Standby supervision for High risk activities,
crew ( Where dispenser in  Trained & experience supervisor,
forecourt area),  JHA briefing to be done among the work
 Un skilled person, force team prior work,
 Lack of supervision,  Proper lighting arrangement to be done in
 Untrained supervisor, case of night work,
 Improper PPE,  Safety reflector jacket, helmet, safety shoes,
hand gloves & nose mask must be used on
 Slip fall,
site.
 Fumes.
 No hand phones allowed or smoking within
 Slippery surface,
the forecourt area
 Manual handling
 Keep body balance in correct position,
 Items/Equipment detaching from
6 Dismantling of Old DU(Tatsuno)  Ensure no slippery surface before start work.
the hoist and falling; incorrect
 Extra precaution to be taken.
manual handling during
lifting/hoisting  Apply any external mechanical support
where applicable (e.g. crane). The dispenser
 Electric shock
unit has weight 500 kgs approx. Eliminate
 Lack of ensured safe working area
any potential lifting/hoisting from person
 Positioning self in line with the
where applicable.
heavy equipment possible falling
 Fitness to Work of Crane Operator - Attend
pathway
annual physical examination and submit
 Failing to inspect the condition of
result of findings.
the lifting equipment and
 Certificate of Competency of Lifting
competence of operator
Equipment Operator
 Deviate from the approved work
- Bring certificate on site to show to auditors
methodology
-Contractor accreditation system
-Permit to Work system
-Safety/Worker Passport
-Lifting plans required.
-All workers to remain clear during lifting
operations (LSR's)

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

 Provide standby fire Extinguisher,


 Provide sand buckets,
 Use anti spark tools.
 Water reflective vest while working at night,
 Isolate the work area & traffic management,
 Skilled & Trained person,
 Standby supervision for High risk activities,
 Trained & experience supervisor,
 Unauthorized tools.  JHA briefing to be done among the work
 Moving vehicle may hit to work force team prior work,
crew ( Where dispenser in  Proper lighting arrangement to be done in
forecourt area), case of night work,
 Un skilled person,  Safety reflector jacket, helmet, safety shoes,
 Lack of supervision, hand gloves & nose mask must be used on
 Untrained supervisor, site.
 Improper PPE,  No hand phones allowed or smoking within
the forecourt area
 Slip fall,
 Keep body balance in correct position,
 Fumes.
 Ensure no slippery surface before start work.
 Slippery surface,
 Extra precaution to be taken.
 Manual handling
 Provide periodic material handling training
 Items/Equipment detaching from
7 Installation of new DU(Tokheim) to workers.
the hoist and falling; incorrect
manual handling during  Manual handling requirements to be
lifting/hoisting observed and when lifting items over 16kgs,
a second person is to help wherever
 Electric shock
possible.
 Lack of ensured safe working area
 Apply any external mechanical support
 Positioning self in line with the
where applicable (e.g. crane). The dispenser
heavy equipment possible falling
unit has approx 500 kgs weight. Eliminate
pathway
any potential lifting/hoisting from person
 Failing to inspect the condition of
where applicable
the lifting equipment and
 Fitness to Work of Crane Operator - Attend
competence of operator
annual physical examination and submit
 Deviate from the approved work
result of findings.
methodology
 Certificate of Competency of Lifting
Equipment Operator
- Bring certificate on site to show to auditors

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

Shell Retail Permit to Work _ Version 5.1


RETAIL PERMIT TO WORK SYSTEM –JOB HAZARD ANALYSIS

Personal Protective Equipment (PPE) appropriate to the task at hand shall be worn/used at all times.
Tick box any PPE that applies to this job

Any additional PPE appropriate to the task : Gas tester

List required equipment / tools (e.g fire extinguisher, barricading / signs , hand tools, mechanical tools, plant etc.):

Anti Sparking tools


Fire extinguisher

Barricading
Gas Tester

Crain

The work crew acknowledges that they understand and will comply with the precautions listed above

NAME: SIGNATURE:

NAME: SIGNATURE:

NAME: SIGNATURE:

NAME: SIGNATURE:

NAME: SIGNATURE:

Shell Retail Permit to Work _ Version 5.1