TM-CC Public Works Contracts - Contractors
TM-CC Public Works Contracts - Contractors
Department of Finance
Training Manual
Tm-cc
PUBLIC WORKS CONTRACTS - CONTRACTORS
Public Works Construction Contracts
Training Manual
NOTICE
This training manual is both the course material from the training courses and a
reference document for government departments, bodies under their aegis, local
authorities or other relevant bodies in the new Public Works Contracts.
All parties must rely exclusively upon their own skill and judgment, or upon
those of their advisers when making use of this document. Neither the GCCC,
NPPU, Department of Finance, McCann FitzGerald, Project Management Ltd or
Tobin Consulting Engineers nor any other contributor, assumes any liability to
anyone for any loss or damage caused by any error or omission, whether such
error or omission is the result of negligence or any other cause. Any and all such
liability is disclaimed.
The contents hereof do not form part of, and shall not affect the interpretation
of, any contract.
This Training Manual was used for courses delivered to senior members of the
Public Sector during December 2006–January 2007 and reflects the versions of
the Public Works Contracts current at that time.
Readers should also refer to the Guidance Note on Public Works Contracts.
First published in February 2007 by the Department of Finance. Reissued May 2008.
© All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any
form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior written
permission of the Department of Finance.
V1.1
Contents
1. COURSE AGENDA 7
2. COURSE INTRODUCTION 15
2.1 Trainer Introductions 15
2.2 The Capital Works Management Framework 16
2.3 The Background 17
2.4 The New Forms of Contract 18
2.5 Timeline for Rollout 20
2.6 The Government’s Objectives 21
2.7 The Aim of this Course 21
2.8 The New Contracts as Enablers for Better Management 22
4. RISK MANAGEMENT 28
4.1 What is Risk? 28
4.2 The Broader Context 28
4.3 Risk Management Processes Generally 29
4.4 Commercial Context (Value for Money) 31
11.15 Section N 83
1. Course Agenda
1 Course Agenda
PART 2 DAY 1
• Model Forms
• Works Requirements
• Pricing Document
• Works Proposals
• Post Tender Documents
16:45–17:00 Summary • Key Messages MF
• Deferred questions arising during that day
PART 2 DAY 2
PART 3 DAY 1
PART 3 DAY 2
2 Course Introduction
2. Course Introduction
2.1 Trainer Introductions
Michael O'Reilly is a Partner in McCann FitzGerald Solicitors, specialising in
construction, planning and environmental law. He was initially with the practice
of Max W Abrahamson and, following the merger of the practices in April 1991,
became a partner in McCann FitzGerald, he is a Fellow of the Chartered
Institute of Arbitrators and a past Council member of the Irish branch of the
Institute. Together with Michael Roche and Barbara Maguire, Michael is co-
author of Irish Environmental Legislation published in 1999 by Round Hall Sweet
& Maxwell.
The aim of the Capital Works Management Framework is to ensure that there is an
integrated methodology and a consistent approach to the planning, management
and delivery of public capital works projects with the objectives of greater cost
certainty, better value for money and more efficient project delivery. The flow
chart below describes the framework.
This division reflects some fundamental differences between the civil engineering
and building sectors.
Civil engineering works such as roads, tunnels, bridges etc. are designed by Civil
Engineers acting [for the most part] under the direction of the Contracting
Authority and are carried out by civil engineering contractors.
Building works such as office buildings, schools and hospitals are designed by
Architects (with other consultants) again acting [for the most part] under the
direction of the Contracting Authority and are constructed by building
contractors.
In both sectors the standard forms of contract used in the past have been
published by the lead professionals’ professional institutions. In the case of
building works by the RIAI with the agreement of the Department of Finance, in
the case of civil engineering works by the IEI, now Engineers Ireland.
A number of contracting authorities have also used the various FIDIC and JCT
forms suitably amended for use in Ireland.
The old forms have not served the Public Sector well in the past, hence the
introduction of the new forms which:
Guidance Notes
(Under €5m)
Public Works Contract Public Works Contract for Minor Works Contract
for the Provision of the Provision of Civil for the Provision of
Building Works Engineering Works Building and Civil
Designed by the Designed by the Employer. Engineering Works
Employer. Designed by the Employer
Contracts 2 and 4 are new forms for works designed by the contractor and
throughout this manual are referred to as Design and Build Contracts.
Contract 5 above has been developed to both share and reduce the level of risk
transfer to small/medium sized contractors for projects of value less than €5m.
The new contracts are currently available at the free of charge following links:
http://www.finance.gov.ie/ViewDoc.asp?fn=/documents/publications/other/construct
reformdec06.htm&CatID=61&m=p
http://www.e-tenders.gov.ie/guides/guides_list.aspx?type=2
elements of the new forms of construction contracts. The request for any such
amendments from those bodies required to use the new contracts should be
submitted to the GCCC for consideration and approval as appropriate. Other
public bodies (such as commercial semi-state bodies) wishing to use the new
forms of construction contracts but with amendments, should also submit a
request to the GCCC for consideration and approval as appropriate.
Where the body procuring the public works project is not a government
department or a body under its aegis or a local authority or other relevant body
that provides public services (e.g. schools, voluntary hospitals, etc) and more
than 50% of the funding for the project comes from a source other than the
Exchequer, the government department or relevant body, as appropriate, should
decide if the new Public Works contracts will apply. If it is decided not to use
the new forms of construction contracts on a particular public works project,
the Accounting Officer/Accountable Officer in the government department or
the relevant public body must be satisfied that the contract terms in the other
contract being used are framed in a manner that seeks to protect public funds.
They must also be satisfied that the alternative contract conditions include the
provisions on Pay and Conditions of Employment (i.e. clause 5.3 in the new forms
of construction contracts). The rationale for this decision should be documented
in an appropriate and transparent manner.
Commercial semi-state bodies (e.g. ESB, BGE, An Post) are not required to use
the new forms of construction contracts on public works projects unless more
than 50% of the funding for the project concerned comes directly or indirectly
from the Exchequer.
To all new public works projects about to begin the planning stage on or
after Monday 19 February 2007.
To all new public works projects where planning has commenced but where
detailed tender documents have not been developed by Monday 19
February 2007.
For those public works projects where detailed development of tender
documents has commenced, contracting authorities can elect to use the
new forms of construction contracts on or after Monday 19 February 2007.
Where a contracting authority, following appropriate training, wants to use
the new forms of construction contracts on or after Monday 19 February
2007.
Where a contracting authority, following appropriate training, wants to use
the new forms of construction contracts on public works projects on a date
earlier than Monday 19 February 2007.
Move towards greater cost certainty at contract award stage and ensure as
far as practicable that the accepted tender prices and the final cost are the
same;
Award contracts on the basis of a lump-sum fixed-price to the greatest
extent possible;
Rebalance risk so that there is optimal allocation of risk;
Achieve value for money; and
Achieve more efficient delivery of the projects.
The contracts are legal documents written in ordinary language and are
designed to be easily understood, applied and interpreted by employers,
contractors and design teams;
The contracts are arranged and organised in a structure which helps the
user gain familiarity with their contents;
The actions by the parties are defined precisely so there should be few
disputes about who is to do what and when;
Change control processes are streamlined with reasonable certainty as to
their outcome;
Early warning procedures are built in for dealing with circumstances causing
delay and additional cost;
Such circumstances which confer entitlements to additional time and money
on the contractor are called Delay Events and Compensation Events
respectively and all are neatly captured in two adjoining sections – this
contrasts with say the old forms of contract where such clauses are
dispersed throughout the conditions;
Issues relating to assessment of Delay and Compensation Events are to be
resolved as projects proceed.
The new forms will promote best practice in project implementation by
employers, design teams and contractors with:
b. They have the same structure whether for building, civil engineering works;
traditional or design and build works;
c. Contracts are to be lump sum and largely fixed price with some exceptions;
l. There is provision to build into the contract period and contract sum for
delays that entitle the Contractor to extensions of time and additional
monies in a new concept called programme contingency this is not to be
confused with contractor’s float time;
n. Tenders are evaluated on the basis of the proposed contract sum and on
delay costs;
4 Risk Management
4. Risk Management
4.1 What is Risk?
An uncertain event or set of characteristics that, should it occur, will have an effect on the
achievement of one or more of the project’s objectives …….
Association of Project Managers
An uncertain event or condition that, if it occurs, has a positive or negative effect on at least
one project objective such as time, cost, scope or quality ……
PMBoK®
Risk is the likelihood of variation in the occurrence of an event, which may have either positive
or negative consequences.….
RAMP Institution of Civil Engineers & Faculty of Actuaries and Institute of
Actuaries
However, Irish construction and engineering projects face the same risk
pressures:
The risks that construction and engineering projects face are manifold and can
be classified under three headings:
The potential project delivery risks issues which can impact on time, cost and
quality on a project include incomplete or late project information, changes,
ground conditions, archaeology, bad weather, defects, inability to secure labour
and materials, etc. Typically these risks are allocated between the Employer and
Contractor by the conditions of contract. Obviously if such risks are effectively
managed at the outset their impact on project delivery can be effectively
reduced.
There are various published methodologies and software packages for risk
management and the detail of these is outside of the scope of this course,
however, a generic risk management process will usually involve the following
stages:
Identification;
Analysis;
Evaluation;
Risk treatment;
Reporting.
For each risk (other than those designated as negligible) the following treatment
options are available:
Example:
Reducing/Eliminating Risk
It is understood that there may be contaminated soil on the site of a proposed project
but there is no conclusive data on this matter. If the risk of this was to materialise
during construction it would cause significant delay and a cost overrun, the effects of
which would be greater than the actual cost of dealing with it in advance.
(i) Ignore it and deal with it if and when it arises during the construction;
(ii) Determine the full extent of the contaminated material and the nature and
toxicity of the contaminant by means of investigatory studies. The material can
then be dealt with (a) in an enabling works contract or (b) in the main contract.
A decision is made to determine the full extent of the contaminated material and the
nature and toxicity of the contaminant by means of investigatory studies. The
contaminated soil is then removed in an enabling works contract. In this instance
better information was obtained to reduce the uncertainty and the potential risk to the
main project was dealt with by having an enabling works contract.
Example:
A project involves extensive earthworks. Considerable site investigation has been carried
out and factual site investigation reports are available, indicating the likely nature of the
ground, including the location of bearing strata and the type of strata encountered. On the
basis of these reports, the Engineer has designed the foundations.
On the basis of the extensive site investigations, the Engineer considers that the ground
conditions likely to be encountered are quantifiable with a degree of certainty. A decision
is made that the Contractor should have responsibility for unforeseeable ground
conditions.
In this instance it was considered that there was sufficient site investigation information
available to enable the contractors assess and price the risk. Thus the risk was allocated to
the Contractor.
Example:
whether the risk can be effectively managed by the party allocated the risk
or whether the allocation causes a different, but more damaging risk;
whether the intended allocation of risk is effective and enforceable; and
does the risk allocation represent value for money?
5 Risk
Allocation,
In the selection of the procurement strategy for the project such as Traditional
or Design and Build, the Contracting Authority is making an important decision
on the allocation of the risk for design responsibility.
The Traditional contracts require that design information upon which tenders
are sought will be comprehensively developed and the Contracting Authority
retains responsibility and risk for:
There are particular projects that are not suited to the use of design-and-build
contracts – these include certain major alteration or refurbishment projects and
most maintenance projects.
Contracting Authorities should be aware that the tender evaluation and award
process for design-and-build contracts is more complex than for traditional
contracts. This increased complexity gives rise to greater risks regarding
transparency and objectivity in determining the most acceptable submission in
accordance with the award criteria
2. There is now an Irish standard form of contract for both building and civil
engineering works under which the Contractor has responsibility and risk
for design and completeness of design.
3. Contracts for the most part will be lump sum and the Contractors will own
the "quantities risk", however Contracting Authorities can make a choice
about the contractual status of the bill of quantities.
7. Contractors can be required to submit at the time of tender their "all in"
costs per day for events for which they are entitled to receive financial
compensation. This is their only entitlement for such events and as such
needs to be carefully estimated by contractors.
8. Force majeure and inability to secure labour and materials no longer entitles
Contractors to extensions of time.
9. There are mandatory procedures and notice periods which must be strictly
complied with by Contractors to receive extensions of time and additional
financial compensation where such entitlements exist.
10. The Contractor now has responsibility for the design by Specialists [the new
entity which replaces the nominated subcontractor/supplier];
11. The Contractor now owns the risk associated with appointing a
replacement Specialist in the event that such is required as a result of
default or insolvency of the Specialist.
12. Contracts are now effectively fixed price [except for hyperinflation and for
very long durations – more of which later].
The exceptions are those events that give rise to an entitlement to extensions to
the Date for Substantial Completion which are termed Delay Events, and those
events that alter the Contract Sum which are termed Compensation Events
Delay and Compensation Events are broadly defined in the Guidance Note as
follows:
Delay events are events which, if they occur, are not at the Contractor’s risk,
and subject to the compliance with the contract, entitle the Contractor to an
extension to the date for substantial completion of the works (and any affected
section) equal to the amount of delay, taking into account only site working
days.
Compensation events are events which, if they occur, are not at the
Contractor’s risk, and subject to the compliance with the contract, entitle the
Contractor to be compensated for the effect the events have on the cost of the
works.
EVENT
Compensation
Compensation
Compensation
Delay Event
Delay Event
Delay Event
[See Section K of
Event
Event
Event
Schedule Part 1]
1. The Employer’s
Representative gives the
Yes Yes Yes Yes Yes Yes
Contractor a Change
Order.
2. The Employer’s
Representative directs the
Contractor to search for
Defects or their cause
and no Defect is found,
Yes Yes Yes Yes Yes Yes
and the search was not
required because of a
failure of the Contractor
to comply with the
Contract
3. The Employer’s
Representative directs the
Yes Yes Yes Yes Yes Yes
Contractor to suspend
work under sub-clause 9.2
EVENT
Compensation
Compensation
Compensation
Delay Event
Delay Event
Delay Event
[See Section K of
Event
Event
Event
Schedule Part 1]
7. The Employer’s
Representative does not
give the Contractor an
instruction required
under sub-clause 4.5.4
within the time required Yes Yes Not Used Yes Yes
under sub-clause 4.11.2
when the Contractor has
asked for the instruction
in accordance with sub-
clause 4.11.1
EVENT
Compensation
Compensation
Compensation
Delay Event
Delay Event
Delay Event
[See Section K of
Event
Event
Event
Schedule Part 1]
EVENT
Compensation
Compensation
Compensation
Delay Event
Delay Event
Delay Event
[See Section K of
Event
Event
Event
Schedule Part 1]
EVENT
Compensation
Compensation
Compensation
Delay Event
Delay Event
Delay Event
[See Section K of
Event
Event
Event
Schedule Part 1]
Risk Nr 18- Has the necessity for an archaeological report been determined and an
Unforeseeable appropriate preliminary archaeological report been prepared?
items of
archaeological Contracting Authorities are strongly advised, where the works are to be
interest or located in archaeologically sensitive locations, at feasibility stage, to seek
human remains expert advice and make contact with the National Monuments Section
found on the (NMS) of the Department of the Environment, Heritage and Local
site Government, which is responsible for the Identification and designation
of sites through the Archaeology Survey of Ireland, if the works are to
be located in archaeologically sensitive locations. In the event that the
works may affect a designated site or area of archaeological potential,
Contracting Authorities should take account of the NMS Framework
Document on the Principles for the Protection of the Archaeological
Heritage. Where the NMS requires it, a preliminary archaeological
assessment (including site investigation if considered necessary) should
be undertaken.
Risk Nr 19- Where excavations are required, the project should be subjected to a
Unforeseeable carefully designed, executed and accurately documented site
ground investigations under a separate enabling work contract.
conditions,
man-made Contracting Authorities must make every effort to ensure that the
obstructions, accuracy and adequacy of the information gathered is correct. All tests,
[Traditional descriptions and reporting procedures should be in accordance with the
Contracts Only] current relevant codes of practice and leave no room for ambiguity. Site
investigation contractors should only employ trained and experienced
operators and supervisory staff so as to ensure the quality and integrity
of information. Contracting Authorities should consider employing their
own experienced experts on site to monitor site investigation activities
necessary for the duration of the site investigation works.
Risk Nr 20- Surveys which will be carried out during the preconstruction should
Unforeseeable identify the location and nature of any utilities traversing the site.
utilities in the
ground In carrying out these surveys particular care should be exercised on
[Traditional existing non Greenfield sites or on public roads to locate such utilities
Contracts Only] with a degree of certainty.
Risk Nr 21- Contracting Authorities should adopt a practical approach to the issue of
Owners of utilities. In some cases, a separate enabling works contract to relocate
Utilities fail to utilities in advance of the main contract may be advisable.
relocate or
disconnect A Contracting Authority should allocate the risk associated with
utilities in a relocation or disconnection of utilities to the Contractor when the
timely manner Contracting Authority has agreed procedures with utilities owners as to
their disconnection/relocation such that there is no risk, or that the risk
can be easily assessed and priced.
This topic is the subject of Guidance Note - Procurement Strategy and Contract
Type under the Capital Works Management Framework and will be touched on
very briefly here.
Employer Designed
The design process is contractually separate from construction and is carried out by
designers engaged directly by the Contracting Authority. Complete detailed
documentation is required before tenders can be invited for carrying out the work in
return for a lump sum price.
The Contractor is responsible for undertaking both the design and the construction of
the work in return for a lump sum price.
Selection of the procurement strategy for the project entails considering the
nature of the project, its risks and the programme available. For every project
the Employer should focus on time, cost, performance and quality, in relation
both to design and construction of the project in order to make an informed
decision on the procurement strategy.
Choice should be made always after a careful analysis of the situation and a list of
questions to be considered in determination of the procurement strategy is
presented below:
Accountability
Value for Money
For example – does
For example – which
the Employer aim for
approach deliver the
single point of
optimum whole life
contractual
cost ? PROCUREMENT responsibility
STRATEGY
Programme Certainty of
final cost
For example – is this
to be ‘fast track’ Which approach will
with the shortest maximise financial
overall programme a certainty ?
priority?
The Market Changes during
construction
For example – the For example – is
market receptiveness there a potential risk
to the approach of design changes
adopted – linked to during the course of
value for money 1
the works?
1
Note that these should be kept to an absolute minimum
Example:
The design and build route is selected as it provides a single point of contractual
responsibility and most likely has the shortest overall programme whilst providing
maximum financial certainty.
The Works The Traditional Forms require that the Works Requirements will
Requirements comprise comprehensive and well developed documentation which should
include for example:
Employers should note that the new forms of contract have no facility for
provisional sums or provisional quantities and therefore any works which
in the past were dealt with by these mechanisms will now be required to
be fully designed and time should be allowed in the programme for this.
The Works Requirements under the Design and Build forms by their very
nature are different to those of the Employer Designed forms and are
discussed further later
The Site Site risk issues such as archaeology, ground conditions and utilities should
be fully considered in order that appropriate and cost effective risk
allocation may be achieved. The need for any enabling works contracts
should also be considered as part of this strategy.
The The exact project programme for the Works with start and completion
Programme dates needs to be finalised for tenderers to estimate the fixed price
Dates addition for inflation. Subsequent changes to this after tenders have been
received are likely to have an impact on project costs and should be
avoided.
Programme Contingency
Retention percentage
Price variation options
In the old forms of contract (and in many other forms) the provisions are vague
enough to be interpreted in a wide manner and to give rise to claims from
contractors under a variety of heads and guises. The new forms do not permit
this. There is no looseness which would facilitate vague and imprecise claims
and all adjustments to the Contract Sum will require a specific reason in the
absence of which there is no provision for an adjustment.
The new forms of contract are designed to give meaning to the expression
"fixed price lump sum contract". With regard to the lump sum aspect the
Contractor is to be given full and clear information as to the works to be carried
out and the risks being allocated to the Contractor so as to enable him to fully
price the works including those risks. While there is provision within the
Contract for adjustment to the Contract Sum the areas of such adjustment are
very specifically set out and regulated and are subject to strict notice conditions.
It is therefore unlikely that such adjustments will arise without easily verifiable
justification.
The Contract is largely a fixed price although there is provision for adjustment in
the case of extreme price fluctuations.
As discussed elsewhere, some old forms are not entirely precise in their
allocation of risk as between the parties. In addition, in many instances the
Contractor is not given enough information at the appropriate time to enable
him price risk. This has resulted in claims and disputes. The new forms allocate
risk clearly and neither party should be in doubt as to the risks allocated to him
and for which he must make provision. Also, as is stated above, the Contractor
is to be given all information necessary to price such risks.
8.2 Specialists
Specialists can be procured in a number of ways:
(i) Specialists are named by the bidders in their Works Proposals. The
Contractor must have named its proposed specialists in its suitability
assessment submission. It is important to note that at least one of the
Contractor’s proposed specialists for each "specialism" must meet the
suitability assessment criteria, otherwise the Contractor will also fail to
prequalify. During the tender process, Contractors must confirm that the
specialist work will be carried out by the specialist(s) that were accepted as
part of the suitability assessment process. Note that any change by a
Contractor from its initially suitable specialist to another specialist should
be subject to a further suitability assessment by the Employer;
(a) Tenders are procured on a fixed price lump sum basis and there is no
subsequent negotiation of the fixed price addition as has heretofore been
the case;
(b) Where bills of quantities are used for civil engineering works, the tender is
the lump sum offer and not the rates in the bill of quantities;
(c) Daily rates for delay, all-in labour rates and percentage additions for
materials and plant are to be provided by tenderers. These will be required
to be taken into account in the evaluation of tender.
Where daily rates are tendered the following should be added to each
tender sum for the purpose of comparing tenders:
Where daily delay rates are not tendered (delay costs to be paid on
an actual cost basis), the following should be added to each tender sum for
the purpose of comparing tenders:
Example:
See Case Study Nr 2 and the Guidance Note on Public Works Contract
Such corrections and rebalancing are necessary so that the rates and prices
can be used to value work in interim progress valuations, and also that the
rates and prices can be used to value change orders should they arise.
9 Contract Administration
– What is New?
9.1 Time
Key Dates Designated Date – 10 days before the last date for submission of
tenders.
Programme Detailed requirements set out in Clause 4.9.1. Can be part of the
Works Proposals and therefore part of the Contract Documents.
Failure to provide or update the programme can entitle the
Employer to deduct money from payments to be made.
Delay Events Date for Substantial Completion only adjusted by Delay Events listed
in the Schedule Part 1K.
9.2 Cost
Cost Certainty Philosophy of contract set out in Article 4 of Agreement. "The
Contractor has included in the initial Contract Sum allowances for all
risks, customs, policies, practices, and other circumstances that may
affect its performance of the Contract, whether they could or could not
have been foreseen, except for events for which the Contract provides
for adjustment of the initial Contract Sum."
Price Variation Two approaches – PV1 or PV2. PV1 is a proven cost method and
under this the Contract Sum is fixed until 31 months after the
Contract Date. PV2 is the formula fluctuations method and under
this approach the Contract Sum is fixed for 36 months after the
Designated Date. There is also limited provision for recovery at
any time during the contract period for hyperinflation which is
defined.
Change Variations are now called Change Orders and are valued in
accordance with clause 10.6.
Compensation Listed in Part K of the Schedule Part 1 and entitlement is the period
Events of delay determined by the ER multiplied with the tendered cost
per site working day of delay. Note that there is also facility for the
entitlement of the Contractor to be assessed on the basis of
"expenses unavoidably incurred" by the Contractor if that option has
been prescribed at the time of tendering. There is no entitlement
to recovery of disruption costs or loss of productivity costs.
9.3 Quality
Fitness for Works Items and Works Items designed by the Contractor are
Purpose required to be fit for their purpose in the Works. The Contractor
is responsible for any design by Specialists and again such design is
required to be fit for purpose. Under the design and build forms
the Works are required to be fit for purpose.
4.5.4 Give an instruction necessary for Give a change order where physically
completion of Works impossible or contrary to Legal
Requirements to complete Works in
accordance with Works
Requirements.
4.15.1 Schedule meetings with the Consult with the Contractor and act
Contractor and others; reasonably in the timing and location
of meetings.
9.2 Suspend the Works; instruct the Examine Works and Works Items
Contractor to resume the Works affected by a suspension; determine
the extension of time and the
adjustment to the Contract Sum for
unavoidable deterioration of the
Works or Works Items arising from
the suspension.
9.7 Issue notice of taking over of part of Certify contract value of works to be
the Works. taken over.
There are two approaches, selectable at the discretion of the Employer in the
Schedule Part 1, viz:
The Formula Fluctuations Method (PV2) is based on the use of CSO Indices for
different categories of Materials, Fuels, CPI, as published mainly in the Wholesale
Price Indices. The weightings for each of Material, Fuel, Labour, non-reusable
temporary works and non recoverable overheads are established by the
Employer (or Contractor in DB) and the proportions of different fuels and
materials are also defined for use with these indices, and these proportions are
provided in the ITT.
All of the formulae used in PV2 have a common basic structure, i.e.
The sum Element at
Indexation
subject to x - Contractors = Amount Payable
factor
indexation Risk
The Guidance Note has several examples of how PV2 applies to Materials,
Labour, Fuel, and Non Reusable Temporary Works after the Base Date, and it
also includes examples of calculation of the Hyperinflation provision.
If, within the Contract Sum (less VAT and deductible amounts), Z, the fraction
of Materials is Y%, within which Ready Mix accounts for W%, of which in turn
P% is the value in the current Interim Valuation, then WYZP is the value of
Ready Mix subject to indexation in this Valuation. The foregoing formula may
also be expressed as:
⎧⎛ A1 − B1 ⎞ ⎫
⎨⎜ ⎟ − 0.1⎬ * (W * Y * Z * P ) = K
⎩⎝ B1 ⎠ ⎭
The term WYZP, as mentioned above, represents the sum which is subject to
the index calculation, for this particular material, in this particular Interim
Certificate.
These are the sums, under the headings of Ready Mix Concrete and Fabricated
Structural Steel, which appear in the PVC calculation in the current Interim
Valuation. However, it will only be the amounts in excess of €10,500 and
€5,880 respectively, ie 10% of WYZP, which will be recoverable, and then only if
the index uplift generates an excess.
Clearly, it is possible that the formula at the head of this section could give a
value which is negative, and this happens when the uplift from the indexation
calculation is less than 10%.
The Clauses of the Contract make it clear that when this happens, the outcome
is a zero recovery for the Contractor.
Hyperinflation is defined in the Contract, and it can apply at any time after the
Designated Date, which means it can apply as a relief even during the " fixed
price period" when normal price relief does not apply. The structure of the
In Employer Design Contracts, the Employer will define the weighting Y, and
weighting(s) W across a range of materials, by preparing two Tables, for
inclusion in the appendices to the ITT. It is important that the headings in the
table match those used by the CSO, so that there is unambiguously an index
available for each material category. Figure 1 illustrates how these weights apply
down the tree into each material category and interim certificate.
In Contractor Design, the Contractor will have to present his own weightings
against the corresponding materials categories, and good practice would then
require that this be taken into the account in the MEAT calculation as part of
tender appraisal. This might be done by declaring that tender comparisons would
be made, based on five ranked assumed materials values, with the highest five
weightings (for example) applied and taken to a sum itself taken into account in
the MEAT, to prevent any tendency to load a particular material category for
advantage.
A1=The Adjustment Index Figure for the relevant Material or Fuel Category
B1=The Base Index figure for the relevant Material or Fuel Category
If now the indices took the following values and we were considering a
September 2008 Interim Valuation:
The fractional amount of uplift, less the amount at the Contractors risk, can be
calculated as:
Having calculated the sum entering the PVC calculation, and the net uplift factor,
it remains to combine the two, in the following formula.
(W * Y * Z * P )* ⎧⎨⎛⎜ A1 − B1 ⎞⎟ − 0.1⎫⎬ = K
⎩⎝ B1 ⎠ ⎭
Z
Contract Sum
Excl. VAT, and Excluded Amounts
W
= > WYZP
Ready Mix
Base Date
Sum
Sun == 100%
100%
P
0% 4% 25% =
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
Example:
The Employer is otherwise ready to accept a tender to carry out certain works but has not
yet obtained possession of an important part of the Site. In such case the Employer should
never send out a Letter of Acceptance (as to do so would trigger the actual Starting Date
under the Contract) unless he is absolutely certain that he can obtain possession before the
date on which access to this part of the Site will actually have to be given pursuant to sub-
clause 7.1.1 of the Conditions (or unless the Contractor’s access to the Site is limited by the
Works Requirements). The Employer would not want to start time running on a process
that will require access by the Contractor to a part of the Site before he knows he will be
able to provide that access.
While the Letter of Acceptance provides for the incorporation into the Contract of post
tender clarifications, the Employer should be most careful not to break any EU public
procurement requirements by the inclusion in the Contract of items not tendered.
Another point worth noting is that it is intended that the Form of Tender will be a document
executed by the tenderers under seal so that when the Employer accepts the Tender the
resulting contract will be under seal.
10.2 Agreement
The Employer should ensure that the Agreement as provided in the Contract
Documents is completed fully and correctly:
date of Agreement;
names of contracting parties;
initial Contract Sum;
any post tender clarifications intended to be included as contract
documents.
He should ensure the Agreement is executed fully and properly by both parties,
note sealing requirements for companies:
While there is nothing particularly new in the Agreement it does state much
more clearly than in the old forms of agreement that the Contractor has fully
satisfied itself of all the risks involved in carrying out the Works and has priced
for them and included these in the initial Contract Sum.
It also sets out clearly the documents forming the Contract and, as has been
mentioned above, provides that the Contract takes effect from the Contract
Date.
Example:
In a contract in which the Letter of Acceptance was issued on the 10th January 2007 and the
Agreement is being executed on the 25th January 2007 the date to be inserted into the
Agreement will be the 25th January 2007 i.e. the date of the Agreement. This will not affect
the date from which the Contract takes effect i.e. the Contract Date...
This is something that will need to be considered very carefully by the Employer
and legal advice might well be required if there was doubt on the matter. It is
likely that this issue will in any event be addressed by the Letter of Acceptance.
In addition in this regard, attention must be paid to the EU public procurement
requirements.
The Employer will need to consider whether or not he intends to execute the
document under seal. In general contracts for substantial public works will be
executed by the Employer under seal and in accordance with the standing orders
of the entity in question. If not to be executed under seal then the Employer
will need to consider who is the proper person to execute and what are the
rules governing the execution under hand of a binding contract for the amount
in question so as to ensure that appropriate standing orders are followed.
Although the Contract will already have been formed by the issue of the Letter
of Acceptance, the Employer should, in order to avoid any confusion or dispute
on the matter at a later date, also consider in advance who on behalf of the
Contractor is to execute the document and to ensure that he is satisfied the
document is being executed in accordance with the regulatory requirements
governing that entity.
Again in accordance with the footnote at the end of the Agreement the
Employer must ensure that if the Contractor is made up of various entities, each
must execute.
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
The Employer should ensure all risk assessments, investigations and decisions
have been carried out in advance of Schedule completion.
11.2 Section A
The Employer must ensure that all addresses, fax numbers and e-mail addresses
are entered and are correct
Example:
The Employer will need to consider to what address notices under clauses 12 and 13 relating
to termination and dispute resolution respectively, are to be sent. This would for example
be important if the Employer was resident in different locations or had a number of offices.
There should be no room for confusion in relation to where such important notices are to
be sent.
Similarly, the address of the Employer’s Representative to which notices pursuant to clauses
9 and 10 relating to claims for extensions of time and/or adjustments to the Contract Sum
must be sent should be accurately set out so that no confusion exists in relation to whether
these notices have been served in time.
In relation to the potential limitations on the ER’s powers it will be important for
the Employer to consider carefully the limitations that should apply in each given
case. This because it is not necessarily a good thing to require an ER to revert to
the Employer every time he wishes to issue an instruction or a Change Order. In
addition, it should be borne in mind by the Employer that it will be necessary for
him to respond promptly to the ER in relation to any request for instructions in
order to avoid causing any delay to the Contractor.
Example:
In the completed case study the maximum adjustment to the Contract Sum as inserted is
€5,000 unless approved by the Employer. It would be essential for the Employer to consider
in advance and in the light of the size of the Contract in question whether or not such a
permitted adjustment is appropriate or whether it should be larger or smaller.
It should be noted however, that it is not intended for any alterations to the Schedule itself to
be made.
It might also be noted that if the ER were to exceed his authority under the Contract, any
instruction given by him will nevertheless have effect as if it were within his authority and the
Contractor is not under a duty to inquire as to whether the Employer has actually authorised
it.
11.3 Section B
All relevant design details (in the Traditional contract) or Employer’s
requirements must be available when Part 1 of the Schedule is being completed.
Historically in Irish Public Works Contracts (of the Traditional type) the design
detail provided to the Contractor varied from the very basic to the very
advanced. The New Forms seek to give full meaning and effect to the term
"fixed price lump sum contract" and in this context it is absolutely essential that
the design is fully developed before the Contractor is asked to price. If it is not,
this will give rise to the necessity for Change Orders and claims for adjustment
to the Contract Sum by the Contractor.
11.4 Section C
The decision as to whether the Employer requires the copyright in all
Contractor’s Documents must be made in advance of completion of Part 1 of
the Schedule
This part of the Schedule in conjunction with sub-clause 6.4 of the Conditions
allows the Employer the option of obtaining intellectual property rights in the
Contractor’s Documents and Works Items. It would be very important for the
Employer to decide if he requires such rights. In a Design and Build Contract it
would obviously be of far greater significance than in a traditional type of
contract. In a traditional type contract this would of course carry through from
the Conditions of Engagement where it would be of even greater relevance.
Thus there would probably be little point in having copyright in Contractor’s
Documents if the Employer did not ensure that he had copyright in the
Consultants’ design documents.
Example:
If the Works were a flagship building that the Employer wished should remain unique then he
might seek to obtain copyright in the design and other relevant documents. Then he would
be in a position to prevent the design and construction of the same building thus preserving
its uniqueness.
Alternatively, if the Works the subject of the Contract were the first in a series of such
structures to be erected around the country (e.g. schools, railway stations etc.) then the
Employer might feel that it would be important for him to have the right to copy all
documents and designs going forward. However, the Contractor takes no responsibility for
the use of the Contractor’s Documents other than in connection with the Works. (sub-
clause 6.4).
11.5 Section D
The Employer must consider carefully in relation to insurance
In addition there is a clear entitlement under the Contract and as set out in the
Schedule for the Employer to require that Professional Indemnity insurance be
taken out by the Contractor. While this would be perfectly normal in a
Contractor’s Design Contract it would be less usual in traditional forms.
Example:
If the Works involve any substantial degree of design on the part of the Contractor or on the
part of any Specialist then unless the Employer can be fully satisfied (which is highly unlikely)
that the Contractor and/or Specialist would be of sufficient stature to stand over any design
by them (and satisfy any loss arising from defects arising) or that the issue is covered by the
design team on the project (and their P.I. insurance) the Employer should require that
Professional Indemnity insurance is obtained.
This is because the Contractor is fully responsible for all design by itself or by Specialists to
the extent that they are fit for their intended purpose in the Works. If the Contract is for
Design and Build the Contractor is fully responsible for the fitness for purpose of the overall
design.
11.6 Section E
The Employer must state whether or not a Bond is required (note- default is
that a Bond is required). The Employer must provide for the amount of the
Bond as a percentage of the initial Contract Sum up to Substantial Completion
and thereafter (note – the level of the Bond depends on the size of the
Contract. It ranges from 25% to 12.5% (see Guidance Note section 2.3). There
is provision for the Bond to reduce by one half upon Substantial Completion of
the Works.
11.7 Section F
The Employer must state if collateral warranties are required from certain
Specialists and by what date.
Example:
Almost by definition it is likely that a Specialist will be carrying out a design function and in
many cases the Specialist company will be as substantial, if not more so, than the Contractor.
For instance, some of the larger mechanical and electrical contractors are substantially larger
than many of the contractors for whom they work as specialist sub-contractors. Accordingly,
unless the Employer feels that a separate warranty from the Specialist need not be provided
because of the likely stature of the Contractor (who he will not of course know when
completing the Schedule) and/or the fact that the type of work to be carried out by a
Specialist is unlikely to fail, it would be most unusual not to require such a warranty.
Example:
The Employer is entitled to withhold from payments to the Contractor, the amount set out
in the table in the Schedule (part1F) in the event that the Contractor fails to provide a
collateral warranty within the time he is obliged to do so (sub-clauses 5.5 and 11.4.1). The
Employer will need to consider the amount to be withheld on the Contractor and must insert
it in the Schedule. The money will be paid to the Contractor when he provides the required
warranty. However, if he has not done so by the date of issue of the Defects Certificate, the
withheld amount is deducted from the Contract Sum (sub-clause 11.4.5).
11.8 Section G
Unless the Contractor is required to insert the Date for Substantial Completion
in part 2 of the Schedule the Employer will need to consider the date.
If the Contractor is required to insert the Date for Substantial Completion the
Employer should consider imposing (via the Works Requirements) a minimum
period for completion in light of safety considerations (see comments on this
point elsewhere).
Example:
The rate of liquidated damages per day or per week will be inserted by the Employer and in
this regard the Employer should assess carefully the likely losses to be suffered by the
Employer should any Section or ultimately the entire Works be delayed due to the
Contractor’s default. The Employer should make sure that the amount in question is a
genuine pre-estimate of likely actual losses. In point of fact many Employers insert liquidated
damages that do not take into account all of their likely losses and accordingly such liquidated
damages are too low. Obviously, the Employer should be aware that a rate which is so high
that it bears no relationship to the anticipated actual losses is likely to be unenforceable as a
penalty.
If the Section is a very substantial part of the overall Works and represents 25%
of it in monetary terms, it may be appropriate to reduce the retention by a
similar percentage once that section is substantially complete. However, other
factors may come into play which would result in the reduction not equating
fully to the monetary relationship that the section bears to the overall works
11.9 Section H
The Employer must state whether or not the Employer’s Representative is
required to issue the certificate of Substantial Completion even if completion is
early (note – the default is that early certification is required).
The Employer will have to decide whether or not he is happy that the ER should
issue the Certificate of Substantial Completion if the Contractor completes either
a Section or the entire Works before the relevant Date for Substantial
Completion. As the default is that the ER will have to issue the Certificate the
decision on the Employer’s part is whether he would prefer not to take over the
Works or the Section early.
It might perhaps be that the Employer will not be ready for the Works until the
actual Date for Substantial Completion and will not want to take it on for that
reason, and particularly may not wish to have the obligation to insure, take over
and provide security for the building.
11.10 Section I
The Employer must insert the length of the initial Defects Period
Example:
The Employer might wish to consider whether either a shorter period of say 6 months or a
longer period of say 18 months for carrying out the snagging etc. is appropriate. This would
relate to the nature of the Works and whether the Employer feels that the Works are for
example a simple but urgent job where an initial defects period of 6 months would be ample
to have it fully completed.
11.11 Section J
The Employer should state whether random checks for employment records
may be made under sub-clauses 5.3 (note – default is that the sub-clause providing
for such checks is part of the Contract). Note also that Government policy is that,
subject to certain parameters, such checks are to be carried out (see below).
Example:
The Employer will need to decide whether he intends to allow for random checks to be made
under sub-clause 5.3. The default position is that such checks can be made but the Employer
may decide that in certain circumstances there is unlikely to be any necessity for them. One
would envisage that it might be appropriate to leave in the entitlement even if it is not utilised
by the Employer.
However, it is important to note that any such checks may only be used for the particular
purpose of checking on proper payment of work persons and cannot be used for any other
purpose. (sub-clause 5.3.5) For instance, the Employer could not use the checks to seek
evidence in relation to Contractor’s Claims.
Government policy is that if a Contract value is greater than €30 million and its duration is
over 18 months – such checks will be required.
11.12 Section K
The Employer should consider carefully in light of investigations made and of
information available to the Employer and possibly to be made available to the
The Schedule provides for a 10 year Return Period as the level of risk to be
allocated to the Contractor in this respect. This has a precise hydrological
meaning, as the event which, in a long record, is likely to be exceeded once in 10
years. It is not equivalent to an event which occurred within the last decade for
example. In a project lasting perhaps 24 – 36 months at construction stage,
there is a significant probability of the 10 year event occurring, be that rainfall, or
wind, or temperature. Furthermore, it is not impossible (although the
probability is low) that a 10 year Return Period event could occur twice within a
construction period. The Contractor carries that risk.
The Employer must insert in the Schedule, in the table provided, any additional
criteria decided upon as appropriate to the Works and the relevant weather
station at which those criteria will be measured.
It would seem appropriate that Met Éireann may have to be consulted on the
appropriate weather station to be entered in the Schedule by the Employer, as
the Climatological Station most representative of conditions at the Site of the
Works.
The Employer must insert the two thresholds for the Contractor’s Programme
Contingency pursuant to sub-clause 9.4 (note – these thresholds should be the
result of careful consideration by the Employer as to what is reasonable in all the
circumstances of the Contract).
The Employer must state whether the Contractor is to be paid his daily delay
costs (to be inserted by the Contractor in the Schedule part 2E at tender stage)
or his actual expenses unavoidably incurred (exclusive of profit).
The Employer must insert any additional categories of workmen to come within
the definition of craftsperson as set out in Part 2E of the Schedule (defined there
as persons described as craftsmen or electricians in employment agreements
registered under the Industrial Relations Acts).
The Employer must state whether the Contractor is to provide in his tender for
a single delay cost rate or for separate rates for particular periods or portions of
the Works. See Case Studies 1A and 1B.
11.13 Section L
The Employer must insert the required details in relation to interim payment
The Employer must consider what the period for payment on interim certificates
should be. This will obviously depend on the nature of the Works, the urgency
for payment on the part of whatever contractor is carrying out the Works and
of course the Employer’s cash flow. The normal period is monthly and this is
the default as set out in the Contract. The Employer might however in certain
circumstances opt for six weekly payments to fit in with his cash flow but this
would have a corresponding effect on the Contractor’s cash flow.
The Employer will wish to consider the minimum amount to be paid out on an
interim payment (other than retention released) and this will again depend on
the size of the level of administration involved in processing interim payments.
The default is that there is no minimum.
The Employer will have to decide upon the value of unfixed Works Items that
may be included in an interim payment. The default is 90%. The Employer may
feel that this is too high and that a smaller percentage would be appropriate in
view of the fact that these items are not yet included in the Works. Although
the Contract significantly reduces the risk of loss due to anything that prevents
Works Items being incorporated in the Works or delivered to the Site (where
not yet delivered) there is always the possibility that in the event of an
insolvency their incorporation (or if not on Site, their delivery) could be delayed
despite the fact that up to 90% of their value may have been discharged. (sub-
clause 11.2) In the event of serious issues arising the Employer may well be
entitled to call on the bond to be provided by the Contractor.
11.14 Section M
The Employer must state which of the two price variation options is to apply
pursuant to sub-clause 10.8 (note – if none specified, PV1 will apply, therefore it
is very important that the Employer addresses this issue carefully at this stage in
order to avoid possible conflict at a later stage)
11.15 Section N
The Employer must insert the name of the body that is to appoint the
conciliator for the purpose of sub-clause 13.1.2 in the event of a dispute arising
The Employer must insert the name of the body that is to appoint the arbitrator
for the purpose of sub-clause 13.2 in the event of a dispute arising that is not
resolved by conciliation.
The Employer will wish to consider what appointing body to nominate for the
appointment of the conciliator and the arbitrator pursuant to clause 13.
In this regard the Employer might wish to consider whether or not in the
context of a building contract the conciliator or arbitrator should definitely be
an Architect in which case he might feel it appropriate to utilise the RIAI as the
appointing body. This would result in the appointment of an Architect as the
conciliator or arbitrator. Alternatively, if the view is in a civil engineering project
that the conciliator should be an Engineer, then Engineers Ireland should perhaps
be the appointing body.
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
12.1 Section A
This section contains the addresses for sending notices and other
communications to the Contractor and is as important here as it is in part 1 of
the Schedule.
12.2 Section B
The Contractor states here if he intends to provide a parent company guarantee
for tender purposes.
12.3 Section C
This section contains the Contractor’s Works proposals
See notes in relation to the Works Proposals.
12.4 Section D
This section contains the Dates for Substantial Completion and will be
completed by the Contractor only if the Employer has not set out the relevant
date(s) in part 1. However, the Contractor is not permitted to insert any dates
for Sectional completion.
12.5 Section E
This section is where the Contractor sets out his tendered hourly rates for
labour and related costs – e.g. PRSI, tool money, travelling time and country
money etc. in respect of Craftspersons, General Operatives and Apprentices.
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
It is also important that the Contractor is provided with all relevant information
so as to enable him to price the risks being imposed on him. The Employer
should possibly furnish:
In the case of a Design and Build Contract the Works Requirements will contain
a robust output specification or specimen design so that the Contractor can fully
understand and price what is required of him and so that the Employer will get
what he requires.
Archaeological Surveys can range from a desk study level of detail, to a field
investigation with geophysics and investigation trenches, depending on the
known history of the site and the area. Fieldwork associated with archaeology
requires permissions from the NMS of the DoELG, and can involve a significant
lead-in time. It is clearly important, when the risk associated with archaeological
artefacts is being transferred to the Contractor, that the level of prior
investigation is selected to manage that risk transfer effectively, so that it is
appropriate to transfer it, and that such transfer represents value for money.
The Works Requirements should include, inter alia, the following items
Consents Consents
a. Planning and other consents obtained by a. Planning and other consents obtained by
the Employer. Refer to Guidance Note For the Employer. Refer to Guidance Note For
Public Works Contracts – Appendix Public Works Contracts – Appendix
Sections Sections
a. Definition of sections into which the Definition of sections into which the Works are
Works are divided for purposes of divided for purposes of sectional completion
sectional completion
Specialists Specialists
a. Designs to be prepared and/or works to a. Designs to be prepared and/or works to
be undertaken by Specialists be undertaken by Specialists
b. Novated specialists including details of the b. Novated specialists including details of the
original appointment and form of novation original appointment and form of novation
agreement agreement
Contract Contract
Form of Contract Form of Contract
Model forms as appropriate Model forms as appropriate
a. Form of performance bond a. Form of performance bond
b. Form of parent company guarantee b. Form of parent company guarantee
c. Form of novation and guarantee deed c. Form of novation and guarantee deed
d. Form of appointment of project supervisor d. Form of appointment of project supervisor
for construction stage only for construction stage only
e. Form of appointment of project supervisor e. Form of appointment of project supervisor
for construction stage and design process for construction stage and design process
f. Form of appointment of project supervisor f. Form of appointment of project supervisor
for design process only for design process only
g. Form of professional indemnity certificate g. Form of professional indemnity certificate
h. Form of collateral warranty h. Form of collateral warranty
i. Form of novation i. Form of novation
j. Form of rates and conditions of j. Form of rates and conditions of
employment certificate employment certificate
k. Form of bond – Unfixed works items k. Form of bond – Unfixed works items
l. Form of retention bond l. Form of retention bond
m. Form of conciliator's agreement m. Form of conciliator's agreement
n. Form of bond – Conciliator's n. Form of bond – Conciliator's
recommendations recommendations
Owner controlled insurances (if required) Owner controlled insurances (if required)
Arbitration rules to apply Arbitration rules to apply
Reports Reports
a. Special reporting requirements. Eg: a. Special reporting requirements. Eg:
planning software to be used. planning software to be used.
Quality Assurance and Testing (Where Quality Assurance and Testing (Where
not contained in the Specifications) not contained in the Specifications)
a. Quality assurance procedures a. Quality assurance procedures
b. Inspections b. Inspections
c. Items which are to be inspected or tested c. Items which are to be inspected or tested
before delivery to the Site including details before delivery to the Site including details
of the inspection or test of the inspection or test
d. Tests, description of the tests to be carried d. Tests, description of the tests to be carried
out by the Contractor, the Employer’s out by the Contractor, the Employer’s
Representative and others including those Representative and others including those
which must be passed before Substantial which must be passed before Substantial
Completion. Completion.
Title Title
a. Statement of any materials from excavation a. Statement of any materials from excavation
and demolition to which the Employer will and demolition to which the Employer will
retain title. retain title.
Example:
Works proposals from the Contractor will vary depending on whether the Contract is
Traditional or Design and Build.
With Traditional, the Contractor would be likely to prepare his intended sequence of work,
his programme, his resource allocation and his method statements as an integrated package of
information, in response to the Contract Documents, including whatever constraints are
stipulated by the Employer therein.
In a civil engineering project, for example, he would indicate how he proposed to deploy
available working space around structures, showing locations where he might safely stockpile
excavated material, or locate concrete batching plant and aggregate stockpiles materials, or
the like. Alternatively, he would outline other arrangements he may have made to obtain
additional lands, licences and permits in order to free up working space on a particularly
congested site. His sequences would address the question of re-use of materials, and disposal
of C&D wastes. If he considers that Road Closures are required to perform the works, he
would outline their sequence, duration, alternative routes to be used, and the like.
His proposed working methodologies would be described, including any measures for
environmental or HSW protection.
With Design and Build, the Works Proposals will include information similar to the foregoing,
but also the Contractor’s Design itself, including drawings of temporary and permanent
Works, finishes schedules, calculations and all necessary information to enable the ER to
technically assess the proposal in Tender Appraisal.
Evaluation of tenders;
Interim payment;
Valuation of change orders;
Calculation of price variation entitlements;
Recording and classification of costs in accordance with the CWMF.
Subject to the foregoing, bills of quantities (if used) should be prepared in
accordance with the standard methods of measurement approved by the GCCC
and should incorporate any GCCC amendments. Refer to Guidance Note.
Where bills of quantities are not provided by the Employer, such as for design
and build contracts, the Pricing Document will, subject to the foregoing, be
broken down to an acceptable level such as milestones. This detail however is
unlikely to be sufficient for the valuation of change orders and the Contract
Sum should be further broken down into parcels of work of similar character.
The following would be an example of such a trade breakdown for design and
build building contract. It is unlikely that all the headings given will be required
for a every project and in some cases the complexity of the work may require
additional parcels or sub-division of those listed. The breakdown should be given
separately for each building or discrete section of work.
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
"Contractors Documents"
"Contractor Things"
"Contractor's Personnel"
"Site"
Means any place the Works are to be carried out, or provided by the Employer
for the Works, where the Contractor is to operate Employer’s Facilities, or
Any places that is identified as part of the Site by the Works Requirements.
"Specialist"
Means
"Substantial Completion"
The Works are complete and can be taken over and used for their purpose
when:
"Interpretation"
Any reference to a "working day" is to a day that is not a weekend day, a public
holiday under the Organisation of Working Time Act 1997 or Good Friday.
"Inconsistencies"
1 The Agreement
2 The Letter of Acceptance
3 The Schedule
4 The Conditions
5 The Works Requirements
6 The Pricing Document
In the Traditional Form, the Contractor is obliged to ensure the Works are
constructed so as to be safe and without risk to safety and health and so as to
comply fully in all respects with the relevant statutory provisions
The Contractor also warrants that he is a competent person within the meaning
of that term in the Safety, Health and Welfare at Work Act 2005 for the
purpose of ensuring that the Works are safely constructed and comply with the
relevant statutory provisions.
In the Design and Build Form the Contractor is obliged to ensure the Works
are designed and capable of being constructed so as to be safe and without risk
to safety and health; that they can be maintained safely and without risk to health
during subsequent use; that they comply with the relevant statutory provisions.
In both Forms the Contractor warrants that he is competent to carry out the
Works and will allocate sufficient resources so as to comply with the relevant
statutory provisions.
The terms used in the clause including the "competent" and "relevant statutory
provisions" are to be construed pursuant to section 2 of the Safety, Health and
Welfare at Work Act, 2005.
The provisions in the Contracts in this regard are quite short and simple but as the laws
applicable to health and safety are now so strict in this jurisdiction, that is all that is
required.
The Employer bears certain risks in relation to loss of or damage to the Works.
These include the usual uninsurable risks relating to war, invasion, pressure
waves caused by aircraft, and contamination relating to explosive nuclear
weapons etc. The risk of terrorism is included as an Employer’s risk but only if
this is a permitted exclusion from the Contractor’s insurances relating to the
Works.
The Employer also bears the risk of damage to the Works from the use or
occupation of the Works by the Employer or the Employer’s Personnel (other
than as provided for in the Contract) but excluding loss or damage caused by
If Sub-clause 3.8 applies (only if so stated in the Schedule part 1D) the Employer
will bear responsibility for damage to existing facilities due to the usual property
risks of fire, flood, storm, pipes bursting etc.
The Employer also bears the risk of his design of the Works unless the design is
covered by professional indemnity insurance taken out by the Contractor. Sub-
clause 3.1(6)
Example:
If the Works are damaged because of any of the causes referred to in sub-clause 3.1 the
Employer will bear the risk and will have to pay to have the Works reinstated subject to an
entitlement to terminate the Contractor’s responsibility to complete the Works.
The Contractor has otherwise got full responsibility for the care of the Works and bears the
risk of loss and damage to the Works including Works Items, Contractors, Things, Works
Requirements, Works Proposals, and Contractor’s Documents together with anything the
Employer provides to the Contractor for the Works. These items are defined in the
Contract as "Risk Items".
The Contractor’s obligation runs from (and includes) the Starting Date up until
the issue of the Certificate of Substantial Completion of the Works (or if
completed in sections – the relevant Section). If part of the Works is taken over
before Substantial Completion the obligation ends for that part when the
Employer takes it over.
The Contractor still has some responsibility for damage to the Works after the
date of Substantial Completion. These include damage arising from defects or
from matters that occurred before Substantial Completion. In addition if any
damage to the Works is caused after Substantial Completion by activities of the
Contractor or those for whom he is responsible this is at the Contractor’s risk.
The Contractor is obliged to repair any loss or damage to any of the Risk Items
(this is irrespective of responsibility) and must do so at his own expense if the
insurance proceeds are insufficient for the purpose. The Contractor must in any
event repair any damage to the Works occurring before the issue of the Defects
Certificate if the Employer instructs him to do so (subject to payment for the
Works in the event that the risk is not one for which the Contractor is
responsible).
The Contractor must insure the Works and the other Risk Items, against loss or
damage and must procure that the Contractor, Employer, and other persons
nominated by the Employer are named as co-insured under the policy of
insurance. The insurance is to be kept in place until the date of the Certificate
of Substantial Completion. Where there are Sections the insurance must remain
in place until the Substantial Completion of the Section in question.
The Employer may require in the Schedule (part 1D) that the insurance for any
Section or part of the Works which has reached Substantial Completion is to be
extended until Substantial Completion of the entire of the Works.
The Contractor must maintain the insurance of the Works between Substantial
Completion and the issue of the Defects Certificate in respect of damage for
which he is responsible.
The insurance level must include as a minimum for the full reinstatement cost of
the property, demolition and debris removal, delivery, professional fees, inflation
during the construction and reinstatement periods and profit. The Employer is
entitled to insert in the Schedule (part 1D) any other property belonging to the
Employer that is to be included in the insurance of the Works and the indemnity
limit for such additional insurance.
In the event of a claim against the insurance the insurance proceeds (excluding
the insured sum for professional fees to be paid by the Employer) are to be paid
into a bank account in joint names of the Employer and Contractor and are to
be paid out to the Contractor on the basis of interim certificates by the ER
relating to the rectification of the loss or damage. The Employer is entitled to
be paid out of the account for costs incurred by it in this regard and is also
entitled to the balance remaining in the account after rectification work.
Example:
If the Works are fully insured in accordance with the provisions of sub-clause 3.3. and if a fire
that arises on Site damages a substantial portion of the Works, then the Contractor would
typically be instructed to repair the damaged Works which includes demolition of the
damaged part, removal of the debris from the Site, and reinstatement. Additional professional
fees would be incurred in dealing with design. The Contractor would submit interim
statements in accordance with the provisions of the Contract and the ER would certify
payment on foot of these.
The Insurer of the Works would pay out the insurance proceeds which (other than
professional fees in the circumstances of a traditional contract) would be paid into a joint
bank account set up by the Employer in the joint names of the Employer and the Contractor.
These monies would be paid out on foot of interim certificates by the ER as stated above. In
relation to professional fees, assuming this was a traditional form of contract; the Employer
would discharge the additional consultant’s fees and would be paid out of the bank account.
Subject to any entitlement which the insurer might have, the Employer would be paid the
balance remaining in the bank account after payment for the reinstatement of the Works.
The Contractor provides a full indemnity to the Employer and the Employer’s
employees against all liability and loss of or damage to the Employer’s property
including the Site arising from the performance of the Contract. If the Employer
states in the Schedule (part 1D) that sub-clause 3.8 will apply, then the Employer
bears the risk of existing facilities and their contents where owned by the
Employer and caused by the usual perils of:
Note that this indemnity does not cover liability for death, injury or illness of Contractors
Personnel (i.e. those covered by the Contractor’s Employer’s Liability insurance cover).
The Contractor must take out Employer’s Liability insurance for his own
personnel and in relation to Sub-Contractors he must either ensure that the
Sub-Contractors maintain the insurance or otherwise cover the risk himself
(sub-clause 3.6.2).
The Employer provides for the indemnity limits in respect of the Contractor’s
Public Liability and Employer’s Liability insurances in the Schedule (part 1D).
The only noteworthy point here is that the Public Liability policy is taken out with the Employer
and the Contractor as co-insured whereas in the past in building contracts it would have been in
the sole name of the Contractor with an indemnity to the Employer as principal and in the
engineering form it would have been joint insurance.
The Contractor is required to ensure that the Public Liability and Employer’s
Liability insurances are in place in the event of his return to the site (in
connection with the Works) even after the Defects Certificate is issued (sub-
clause 3.6.4).
The Employer is entitled to provide in the Schedule (part 1D) that the
Contractor should put in place Professional Indemnity insurance cover. The
minimum indemnity limit will be inserted in the Schedule (sub-clause 3.7).
The Employer should take care to monitor the Contractor’s insurances either
through the ER or directly through his own insurance advisors or by himself
particularly so as to make sure that the Contractor’s Professional Indemnity
insurance is renewed each year unless (which would be most unusual – one
insurance policy is actually taken out to cover a six year period).
It is provided in the Schedule that the sum indemnified may include defence
costs. The Employer should be careful if prosecuting a claim against an Insured
where such costs are included in the cover, to take cognisance of this fact as, if a
substantial legal defence was mounted to any claim the legal costs incurred by
the defendant would eat away at the limit of indemnity leaving a diminishing
"pool" for the Employer to claim against.
The Contractor must place his insurance with insurers approved by the
Employer and may only exclude from cover the exclusions listed in the schedule
(part 1D).
Any liability insurance where the Employer and Contractor are co-insured must
include various provisions so that the Insurer cannot claim against either of the
insured persons themselves and that they are each treated as if they were
separately insured.
The Contractor is obliged contractually to comply with all the terms of the
insurance policies.
The Contractor must provide evidence to the Employer that the insurances are
in effect and must provide copies of policies and receipts for premiums in this
regard. An Insurance Broker’s Certificate (or one from an underwriter) may be
provided in the case of Professional Indemnity insurance.
This is particularly important in the context of firstly checking on the Contractor’s insurances in
advance of his coming on site and secondly keeping a check on the Contractor’s insurance during
the course of the Works.
The Contractor must notify the Employer promptly of any cancellation, renewal,
non-renewal or material reduction of the terms of any policy.
While this clauses imposes a contractual obligation on the Contractor to notify of these events it
is imperative that the Employer or the E.R. keep an ongoing check on Contractor’s insurances as
it is possible that a Contractor who is in a position whereby some of his insurances are being
cancelled would not inform the Employer or the E.R. of this fact readily.
The Employer is of course entitled to take out insurance should the Contractor
fail to maintain them. However, it would not be possible for the Employer to
take out Professional Indemnity insurance in respect of Contractor or at least
not to do so without great difficulty.
Example:
If the Works involve very substantial and complex work over many adjoining areas with
numerous Specialists it might be deemed appropriate by the Employer to control the
insurance programme rather than running the risk of any insurance failures. However, careful
investigation would need to be done by the Employer in this regard particularly in relation to
the cost of taking out such a programme as it is unlikely to be as economic for an Employer
to take out such insurance as it would be for a Contractor to do so.
14.4 Management
Co-operation
The Contract provides for co-operation between both parties but very
importantly states that such co-operation does not alter the rights or duties of
the parties or imply any admission of responsibility.
The parties can (if circumstances otherwise permit) also enter into without
prejudice communications which would enable them to speak freely without fear
of any admission being used against them – (sub-clause 4.1.4).
He must also appoint a full-time supervisor on site with full authority to receive
instructions. This can be the same person as the Contractor’s Representative
(sub-clause 4.2).
Employer’s Representative
Example:
The Employer may wish to consider what profession is best suited to administer the Contract
taking into account the type of contract that it is and the best method of having it
administered. The Employer might consider that an Architect would be the best
administrator in the context of building works while an Engineer would be the best person to
administer the carrying out of a road or waterworks contract. However, under particular
circumstances the Employer might consider that a person with pure project management
experience and qualifications might be best suited to administer some very large scale
projects crossing over the divide between pure building and civil engineering with a view to
coordinating a large number of consultants.
Otherwise – the Employer must appoint the ER promptly after the Contract
Date and must notify the Contractor of his identity (sub-clause 4.3.1).
Any limits on the authority of the ER must be stated in the Schedule (Part 1A).
See the reference to this above in relation to the Schedule Part 1A where such
limitations are set out.
The Employer must give approvals in relation to any matters on which the
authority of ER is limited.
Example:
If the authority of the ER is limited in relation to say adjustments to the Contract Sum for a
single instruction then the Employer must be prepared to provide approvals when required
by the ER to do so in this context. The Employer must be aware that approvals will often be
required at relatively short notice and that unless they are approved promptly by him this
may hold up the provision of instructions to the Contractor with potential resultant delays to
the Works.
Replacement of ER
Example:
ER’s Communications
The various types of ER’s communications are set out at sub-clause 4.4 of the
Contract. They may consist of:
Directions;
Change Orders;
Objections under sub-clause 4.7;
Opinions, assessments determinations and certificates;
Other communications in accordance with the Contract.
ER’s Instructions
The Contractor must comply with any instruction of the ER (sub-clause 4.5.1).
The Contractor is entitled to give notice under clause 10.3 if he feels that an
instruction which the ER has issued as a direction is in fact, a Change Order.
The matter will then be resolved by the procedure set out in sub-clauses
10.3/10.5.
The Contract explicitly says that the ER may not give a Change Order after
Substantial Completion (except in relation to Defects or work carried out after
Substantial Completion) (sub-clause 4.5.3).
If the ER is of the view that it is physically impossible or illegal to carry out the
Works in accordance with the Works Requirements or if it is necessary in his
opinion, for the completion of the Works, he must give a Change Order and
must do so within the time allowed in sub-clause 4.11 (sub-clause 4.5.4).
ER’s instructions must in the normal way, be given in writing although this will
not be necessary in cases of emergency, provided the instructions are confirmed
in writing as soon as practicable.
Works Proposals
It is the responsibility of the Contractor to make sure that the Works Proposals
submitted by him comply with the Works Requirements.
In respect of any Works Proposals that do not comply with the Contract, the
Works Requirements or Legal Requirements or that are impossible to comply
with, the Contractor must propose a change to the Works Proposals. The
Change is submitted to the ER (sub-clauses 4.6.1 and 4.6.2).
Submissions by Contractor to ER
A detailed procedure for the making of any submissions required under the
Contract by the Contractor to the Employer is set out in the Contract (sub-
clause 4.7).
The Contractor may be required to provide documents for the consideration by the Employer’s
Representative. The Employer should ensure that he is given all copies of such submissions by
the ER so that he will be in a position to make any objection that he deems appropriate to such
submissions. Obviously, the Employer would only make such objections in accordance with the
Contract (see below).
This is an important point in that there is no longer any approval by the ER and therefore there
will be no opportunity for a Contractor to allege that the Employer has "assumed ownership of"
a proposal by the Contractor, giving credence for a claim for compensation in circumstances
where say, the proposal resulted in additional cost to the Contractor.
The Employer may agree to, or reject value engineering proposals from the
Contractor and any such rejection is conclusive.
The Employer should again ensure that he is in receipt of all such proposals in a
timely fashion so that he can make a considered decision in relation to the
proposal and agree to it or reject it. (sub-clause 4.7)
It is noteworthy that if there are any design changes to the Works arising out of or as part of the
value engineering proposals, the Contractor must undertake this design and be responsible for it
(sub-clause 4.8.4).
Programme
The Contractor must submit a detailed programme to the ER before the Starting
Date unless he has already done so with the Works Proposals updated as
necessary to show actual programme dates.
The requirements for the content of the programme are set out at sub-clause
4.9.1 at items (1) to (9) and are very comprehensive indeed. There is provision
for the ER to relax these requirements. Nevertheless, the ER should give careful
thought to any such relaxation.
It will be most important for the Employer in conjunction with the ER to ensure that the
Contractor’s programme is of an adequate quality so that it can be used as a tool to monitor the
Contractor’s Works and properly assess progress etc. It this regard it is noteworthy that there
are sophisticated computer programmes available for the purpose of assessing programmes to
ascertain their validity. It would be particularly important for the Employer that the
Contractor’s programme does (as it is required to do under sub-clause 4.9.2) provide adequate
periods of time for the Employer to comply with his obligations.
All programmes should show items 1-9 as set out in Clause 4.9.1 of the
Contract (subject to any relaxation of the requirements by the ER) (sub-clause
4.9.4).
Progress Reports
Progress Reports are extremely important and it will be essential for the
Employer to receive copies of them from the ER so that the Employer is kept
fully up to date on progress and can query the issues that he may wish to, when
attending at meetings with the ER and if necessary Site meetings. In particular,
and as referred to above it will be important for the Employer to monitor with
the ER details of when any Works Items or other things to be provided by the
Employer will be required and any that the Contractor says are outstanding. It
would also be vital where the Contractor has provided details of anything that
might have an adverse affect on the execution of the Works and where the
Contractor proposes that the Employer or the Employer’s Personnel take steps
to reduce those risks.
The Contractor must furnish progress reports within 7 days after the end of
each relevant month.
Progress Reports must include items 1-12 in sub-clause 4.10.2 unless this
requirement is relaxed by the ER or by the Works Requirements.
The form of the progress reports must be agreed with the ER.
The date by which the ER or the Employer must provide any required instruction,
Works Item or other thing to the Contractor is the latest of:
Example:
In a case where the Employer is required to give the Contractor any required Works Items
or other thing then it would be most important that the Employer is aware of all relevant
dates by which such items will be required well in advance from the ER so that he is in a
position to provide the items in a timely manner. If the item is going to require a long lead-in
time from the Employer’s point of view it may be appropriate that the date is stated in the
Works Requirements so that the Employer can work to it in order to avoid any question of
late provision of information and any resultant delays.
Example:
The Contractor may require additional information which the ER is not able to give and
which only the Employer can provide and in such case it will be incumbent on the Employer
to provide the information/Works Items by the requisite dates. If it were the case that there
was no date in the Contract or the Programme or that the Works Item was not available by
either of those dates and it was clear that the Contractor’s actual progress meant he was not
nearly ready to receive the Works Item despite notifying that it was required then the
Employer would, through the ER point out to the Contractor that he was not entitled to
Works Items/instruction etc. until the item was actually required. It might also be the case
that the Programme provided is out of date, in which case until it is updated and provided by
the Contractor it would be his actual progress that would apply. However, the Employer
should bear in mind that such circumstances could give rise to a dispute as the Contractor
may well say that he is in fact ready for the information or the Works Item.
Documents
The Contractor must keep all relevant documents on Site including contract
documents.
Example:
If a situation arose where the Employer became concerned that he was not being made aware
by the ER of all instructions being issued to the Contractor (although this would be unlikely
to arise in practice) he could insist that the ER authorise him to inspect the Contractor’s
documents being kept on Site where, assuming the Contractor was in compliance with the
requirements of sub-clause 4.11 he could assess all instructions provided by the ER and all
Contractor’s Documents (sub-clause 4.12) together with a log of instructions showing the
dates of issue and subsequent revisions.
Contractor’s Management
The Contractor is obliged to keep the ER fully informed about its arrangements
in advance and about their implementation. The Contractor is obliged to
furnish the ER with all information necessary to enable the ER to perform his
powers and duties (sub-clauses 4.13.5 and 4.13.6).
The Employer should ensure that the ER keeps the Employer in turn fully
informed about all of the Contractor’s arrangements so that he is in a position
to comment to the ER in relation to these where relevant.
Communications
This means that in interpreting the clauses, the spirit of the Contract and its
purpose and the purpose of the relevant sub-clause are to be used. This is to
get the parties and their representatives (including legal advisors) away from the
old ways of interpreting provisions by simply parsing and analysing the words
(sub-clause 4.14.1).
Meetings
The Employer could if he felt it was relevant and appropriate, have the ER invite
him to certain site meetings particularly if issues of relevance to him were likely
to be discussed. This would of course depend upon the Employer’s relationship
with the ER and the information that the Employer is in receipt of from the ER.
Of course, the Employer would only attend such a meeting for information
purposes and should not seek to give any instructions to the Contractor.
The Contractor is obliged also to notify the ER of any objection he has to the
minutes issued by the ER within 5 working days of receiving them (sub-clause
4.15.2).
Confidentiality
The Employer must keep the Contractor’s rates and prices and other records
specified as confidential by the Contractor, confidential (sub-clause 4.16.2).
Reference sub-clause 5
The Contractor is made specifically liable for all acts and omissions of
Contractor’s Personnel, including all Specialists and including their design work.
(Sub-clause 5.1). This is an important provision in that it removes one of the
problematic issues concerning nominated sub-contractors whereby a main
contractor was not liable for the design carried out by the sub-contractor. Now
the Contractor is fully liable as if the Specialist was a "domestic" sub-contractor.
(sub-clause 5.1)
The Contractor must ensure that rates of pay and conditions of employment
comply with law and with any registered employment agreements (sub-clause
5.3.2).
The Contractor himself must comply with and must ensure that the employers
of all other work persons (i.e. subcontractors) comply with all of the obligations
in clause 5.3.3(1) to (8). This involves:
The Employer may request and if he does so, the Contractor must provide to
him within 5 working days, a statement showing the wages and other payments
due in respect of each work person working for the Contractor and, in respect
of work persons not directly employed by the Contractor, ensure that the
relevant employer does the same.
If the Contractor does not comply, the Employer is entitled to estimate the
amount due to work persons and to deduct it from payments due to the
Contractor until satisfied that the persons have been paid. (sub-clause 5.3.6)
The Contractor must give a certificate together with each interim statement
stating that the requirements of payment to personnel etc. have been complied
with in relation to the Works the subject of the interim certificate. Failure to
do so, or to comply with the provisions of sub-clause 5.3 will render the
Contractor liable to the Employer for any investigation costs incurred. In
addition, no payment will be made to the Contractor for the work in question
until the certificate is furnished (sub-clause 5.3.7 and 11.4.4).
Example:
If the Employer becomes suspicious at any stage that the Contractor is not in compliance
with his obligations in relation to payment and conditions of work persons he should request
pursuant to sub-clause 5.3.3, the production of full wage records in relation to work persons
as he is entitled to do pursuant to the contract. The Employer may, if he is entitled to do so,
make a random check requiring production of records but even if he is not he is entitled to
full wage records of work persons as referred to above and is also entitled to a statement
showing the amount of wages or other payments due in respect of each work person and if it
is somebody employed by a Specialist or sub-contractor, the Contractor is obliged to ensure
that that the Specialist or sub-contractor does the same.
If the information is not forthcoming then the Employer should estimate the amount that
should have been paid to the work persons in question together with contributions to their
pension etc, deduct the estimated amount and hold it until satisfied that the proper amounts
have been paid.
If the Contractor does terminate his Contract with a Specialist, he must replace
the Specialist, having first submitted details of the proposed replacement to the
ER. There is an entitlement on the part of the ER to object to he proposed
replacement if, in his view, the proposed replacement does not have at least the
experience, qualifications, competence, technical capacity and financial standing
of the person he is replacing.
The concept of the Specialist is new. Nominated sub-contractors are now replaced by
Specialists for whom the Contractor is fully responsible. Specialists and the Specialist Works are
to be set out in the Works Requirements or in the Works Proposals. The most likely and
indeed the "default" scenario will be that the Contractor will provide his own Specialists in
relation to specific Works Items and will be suitability assessed with those Specialists and will
then include for them fully in the Contract Sum.
Example:
The Contractor, in pre-qualifying for a building or engineering project, includes for the
carrying out of certain work by Specialists (say mechanical and/or electrical work) Subsequent
to pre-qualification, the Contractor will include that Specialist in his Works Proposals and the
full price for those Specialist works is included in the Contract Sum. The administration of
that Specialist is then entirely the responsibility of the Contractor so far as the Employer is
concerned.
Alternatively, the Employer might decide, because of the long lead-in period for the Specialist
works, to enter into a contract with the Specialist in advance of contracting with the Main
Contractor. The name of the Specialist and all documentation relating to the Specialist must
be inserted into the Works Requirements for pricing by the Contractor. The Contractor
must then accept the transfer of that contract to him and the Contractor accepts all liability
for the work carried out by that Specialist.
The Employer should be especially careful to ensure that all work which may have to be
carried out by Specialists is considered carefully in advance of the Contract and the
preparation of the procurement documentation as the ER is not entitled to instruct the
Contractor to engage a particular specialist where he is not named in the Contract. In the
event that the Contractor terminates his contract with a Specialist having first submitted
details to the ER (or in circumstances where he is not required to furnish such details) the
Contractor will replace the Specialist but must first submit details of the replacement to the
ER.
In the above circumstances the ER may object to the replacement for the reasons set out
above (Sub-clause 5.4.6), in which case the Contractor may not go ahead with the
appointment. If the circumstances warranted it, at a future date the ER would arguably be
within his rights (in consultation with the Employer) to direct the Contractor to remove the
replacement from site if he was incompetent or if the ER was of the bona fide view that his
presence on site was not conducive to safety, health or good order (sub-clause 5.6). If this
course of action was to be seriously considered the ER would have to give the Contractor an
opportunity to allow the Specialist to perform and observe him so as to ascertain whether or
not such circumstances (warranting his removal from the Site) existed. To do otherwise
would arguably lead to a serious dispute with the Contractor. The entitlement of the ER
would arise from the fact that the term "Contractor’s Personnel" includes Sub-Contractors
and the term "Sub-Contractor" includes a Specialist.
The Contractor indemnifies the Employer against any breach of property rights
including intellectual property rights by him arising from
As has been stated above [see the notes re Schedule part 1C at 11.4 above] the
decision as to whether the Employer requires the copyright in all Contractor’s
Documents will be made in advance of the completion of Part 1 of the Schedule
Contractor’s Documents and Works Items. It would be very important for the
Employer to decide if he requires such a provision. In a Design and Construct
Contract it would obviously be of far greater significance than in a traditional
type of contract.
Example:
If it was the case that the Works the subject of the Contract were unique and if the Employer
wished to protect that uniqueness or if they were the first in a series of such structures to be
erected around the country (e.g. schools, railway stations etc.) then the Employer might well
feel that it would be important for him to have the copyright in all documents and designs
going forward. However, the Contractor takes no responsibility for the use of the
Contractor’s Documents other than in connection with the Works. (sub-clause 6.4)
Reference – clause 7
The Employer gives the Contractor a right to occupy the Site or relevant parts
as provided for in Works Requirements on or before the latest of dates set out
in sub-clause 7.1.1.
These are:
The Contractor is not entitled to exclusive possession of the Site and must
facilitate the Employer and others as named in the Works Requirements (sub-
clause 7.1.3).
The Contractor – once given occupation of the Site, is fully responsible for its
security (including in relation to protestors and trespassers) and the safety of all
persons entitled to be on it (sub-clauses 7.2 and 7.5).
The Contractor must ensure that the Works do not unnecessarily cause any
nuisance or interfere with the use of adjacent lands (sub-clause 7.5.1).
The Employer for its part must ensure Employer’s Personnel on site comply with
the reasonable safety rules of the Contractor as notified to them by him (sub-
clause 7.5.2).
Where the Employer states it in the Works Requirements he may have work
carried out on Site by Employer’s personnel and the Contractor must co-
operate with them and co-ordinate their activities with his own (sub-clause 7.6).
The Contractor is responsible for all access routes to the Site and within it and
for their maintenance. He must take all reasonable steps to ensure that
construction traffic does not damage roads, bridges or other property. He must
also provide all water and power on the Site (sub-clause 7.9).
On completion of the Works the Contractor must leave the Site in a proper
condition (sub-clause 7.10).
The permitted working times for the Contractor are set out in the Works
Requirements and he is confined to them except in cases of emergency or as
may otherwise be agreed with the ER (sub-clause 7.11).
In civil engineering contracts the Contractor must pay charges for Site
occupation (or occupation of any other place) or in relation to any Employer’s
facilities where provided for in the Works Requirements. The Employer is
entitled to deduct such charges from the Contractor’s payments. There is no
such provision in the Building Works forms. (sub-clause 7.12).
Reference – clause 8
In the traditional Contract the Contractor is obliged to ensure that the Works
are executed and completed:
required under the Contract) new (it might be that the Contractor is to use
recycled materials e.g. old slates or bricks) (sub-clause 8.1(2));
He is obliged to ensure that all materials and goods that are Works Items
are fit for the purpose for which they would normally be used and that any
Works Items selected or designed by the Contractor (including Specialists)
are fit for their intended purpose in the Works (sub-clauses 8.1(3) and (4));
In the Design and Build Form the Contractor is obliged to ensure that the
Works are designed, executed and completed:
The subtle difference in the wording as between the traditional Contract and the Design
and Build Contract reflects the fact that where the Contractor is not carrying out the
overall design he should not have the obligation of fitness for purpose of the overall
Works.
These provisions are onerous obligations and the Employer should be familiar with them
so as to be aware of what the Contractor is obliged to comply with. The provision is as
stated above, subtly worded and means that in the Traditional Contract (unlike the
Design and Build Contract) while the overall Works are not the Contractor’s
responsibility from a design standpoint, any Works items selected by him are in the
context of how they fit into the overall Works
In this regard it is important for the Employer to ensure that such quality
assurance procedures are inserted into the Works Requirements.
The ER is entitled to monitor, spot check and audit the Contractor’s procedures
in this regard (sub-clause 8.2).
The tests are to be set out in the Contract (in the Works Requirements or in
the case of Contractor’s Design, in the Works Proposals) and the Contractor is
obliged to carry them out, agreeing the time and place with the ER and giving
him an opportunity to attend.
In any event, the Contractor has to provide a certified copy of the test results
(sub-clause 8.4).
Where any test fails, the Contractor may be required to repeat it or may elect
to do so. The Contractor is obliged to pay the Employer for any costs incurred
as a result of retesting. Once a defect has been rectified, any test on the
relevant Works Item must be repeated if the ER requires that this be done
(sub-clause 8.4).
Although a provision in relation to testing would not have been set out in the old forms, it would
in all likelihood have been contained in the Preliminaries section of the BOQ or in the
Specification.
Provision is made at sub-clause 8.5 for the detection and remedying of defects in
the Works. The ER may instruct the Contractor to search for defects or
suspected defects including uncovering of any work etc.
If no defect is found, the cost of searching and any delay caused, will entitle the
Contractor to an extension of time and to compensation. (sub-clause 8.5 and
Schedule part 1K at item 2)
Remove the Works Item with the defect from the site;
Demolish the defective Works Item if incorporated in the Works;
Reconstruct, replace, or correct the Works Item in question;
Not to deliver the defective Works Item to the site if relevant.
Or the ER may do any combination of the above. (sub-clause 8.5.2)
As would be the case under the older forms of contract should the Contractor
fail to comply with a direction by the ER under sub-clause 8.5 within a
reasonable time, the Employer is entitled to have the work done by others and
the Contractor is obliged to pay for the costs of this. (sub-clause 8.5.3).
Should a defect be serious enough to deprive the Employer of the benefit of the
entire Works or any particular Section or other material part of the Works, the
ER may on behalf of the Employer reject the Works or the relevant Section and
in that case the Contractor must repay to the Employer any amounts that the
Employer has paid to the Contractor in respect of the Works (in the case of the
entire) or relevant part together with all relevant associated costs (sub-clause
8.5.5).
This provision, while available under forms such as FIDIC, is a new one and in the rare cases
where it might be used, could provide an important remedy, but subject to the ability of the
Contractor to pay.
The ER may only give such a direction or rejection under sub-clause 8.5 before
the Defects Certificate is issued (sub-clause 8.5.6).
The Contractor must complete all outstanding works and remedy any Defects as
are directed by the ER during the Defects Period. He must do this as soon as
practicable after Substantial Completion of the Works or of any Section (sub-
clause 8.6.1).
Sub-clause 8.7 provides for the ER to issue the Defects Certificate to the
Contractor and the Employer within 20 working days after the end of the
Defects Period. However, the issue of the Defects Certificate does not relieve
the Contractor of any responsibility for defects (unless they have been accepted
by agreement under sub-clause 8.5.4).
The Contract Date is the Date of issue of the Letter of Acceptance (note –
therefore issue of LOA is important as it starts time running for the purpose of
the Contract) (sub-clause 1.1).
The Starting Date is the date the Contractor intends to start the Works.
The Contractor must give at least 15 working days notice (unless a different
period is stated in the Works Requirements or a shorter period is agreed with
the ER) of the Starting Date (sub-clause 9.1).
The actual Starting Date must occur no later than 20 working days after the
Contract Date unless otherwise stated in the Works Requirements (sub-clause
9.1.1).
Example:
If the Letter of Acceptance issues in respect of the Contract on Friday 1 June 2007 that is the
Contract Date (sub-clause 1.1 and Agreement – Article 6). Unless otherwise stated in the
Works Requirement.
The Contractor must give notice of the Starting Date by Friday 7 June (in order to give at
least 15 working days notice)
The Starting Date must be by Friday 29 June (assuming no public holidays between 1st and 29th
June)
Note: If the starting date does not occur, the Employer may terminate the Contractor’s
obligation to complete the Works (sub-clause 12.1.1)
The Contractor must hand over all required documents before the Starting Date
(sub-clauses 9.1.2 and 4.9).
Agreement
Bond (if required)
parent company guarantee (if required)
appointment as PS(CS) (if Contractor or his nominee is PS(CS) plus
developed health and safety plan (as per Construction Regulations)
evidence of insurance
collateral warranties (unless a later date is agreed for their provision)
programme
The Employer, along with the ER should make sure that all are properly
executed and in an acceptable form.
This is not necessarily as straight forward as it might first appear. As all these
documents are required to be handed in by the Contractor before the Starting
Date it is likely that in many situations they will be handed in either all at once or
in circumstances which render the checking of them hurried and possibly
difficult. It is very easy to miss something that can later be crucial. It will
therefore be important that all documents are checked thoroughly.
Performance Bond (if required) – care should be taken to ensure that the Bond
is in the correct form (Model Form 6). If it is in the correct form then the
Employer must ensure that it has been properly executed and if it is a bond from
a foreign entity that a letter from a qualified lawyer practicing in that jurisdiction
is obtained in relation to its due execution and enforceability (in accordance with
sub-clause 2.7). [The surety should be authorised to transact guarantee business
in Ireland. This can be checked with the Financial Regulator].
Evidence of insurance – it is absolutely vital that the Contractor has all of the
insurances required by clause 3. It will be essential for the Employer to satisfy
himself whether by his own insurance advisers or otherwise that the policies are
in place and that they are to cover the requisite liability. For instance, that the
Public Liability and Contractor’s All Risks policies name the Employer and
Contractor as co-insured, that the minimum indemnity limits are those
contained in the Schedule part 1D, and that only the exclusions and the
maximum excesses permitted in the Schedule (Part 1D) apply.
On the Starting Date – the Contractor is obliged to start work on site and
proceed with the Works in accordance with Contract
Substantial Completion
Reference - Agreement, Schedule part 1D, part 1E, part 1G, part 1H, part 1I,
part 1K, part 2D
sub-clauses 1.1, 3.3, 4.5.3, 4.8.3, 4.9, 4.17, 8.6.1, 9.1, 9.3, 9.4, 9.5, 9.6, 9.7, 9.8,
10.3, 10.4, 10.5, 10.7, 11.1, 11.3, 11.5.
In order to insert the appropriate date in the Schedule the Employer will need
to consider the Date for Substantial Completion of the Works (and each Section
of the Works if there is to be sectional completion).
In this regard the Employer will doubtless consider the date by which the project
is required, the practical issues associated with its (design and) construction, for
instance, whether it is subject to matters such as tides (in relation to projects
such as outfalls) or seasonal issues (perhaps work in mountainous or boggy
areas).
The Contractor must complete the Works (or Section) by the relevant Date for
Substantial Completion.
The Date for Substantial Completion may be delayed as a result of Delay Events
as set out in the Schedule (part 1K) subject to the provisions of the Contract.
Where an extension of time is granted in accordance with the Contract, a new
Date for Substantial Completion applies. (sub-clause 9.3.2) Such an extension of
time will apply to the Works and to any Section (if there is sectional completion)
affected by the delay.
The Works are complete and can be taken over and used for their purpose.
There are no defects save:
While the Contractor’s basic obligation to complete the works by the Date for
Substantial Completion is no different to that in the old forms of contract, the
The Employer has a right to suspend the Works – through an instruction of the
ER
Upon the ER’s direction to resume, the Contractor and ER inspect the Works
and affected Works Items
If a suspension is not due to the Contractor’s default and is for more than 3
months – the Contractor may ask for permission to proceed
Example:
The Employer may encounter a situation where it is necessary to stop the Works proceeding
pending a re-assessment of the Works Requirements because of some extraneous event, for
instance, another project that is to link up with the Works and which may cause a substantial
redesign of part of the Works.
In such a case the Employer could utilise sub-clause 9.2 and require the ER to issue a direction
to the Contractor to suspend all or part of the Works. The Employer should liaise closely with
the ER and should ensure that the relevant dates are noted, for instance, when the period of
three months from the ER’s instruction will expire, when the Contractor may ask for permission
to proceed and particularly when the period of 28 days will expire subsequent to any such
request for permission.
This is to avoid a situation where the Employer’s default in responding to a request for such
permission results in the Contractor’s obligation to complete the Works being terminated or
the relevant part of the Works being treated as omitted.
There is provision in the Contract for partial takeover of the works before
substantial completion on 5 days notice to the Contractor. The Contractor has
no liability for delay in completing the relevant part once it is taken over.
Example:
The Employer may require part of the Works as a matter of urgency before the part has
achieved Substantial Completion. In such a case the Employer might wish to consider partial
take-over. It is not a decision that should be taken lightly as it can cause difficulties particularly
in relation to health and safety and in relation to insurances. It would be necessary to ensure in
conjunction with the ER and the Contractor that the part of the Works in question can be
adequately defined so that there is no doubt as to which part is in fact being taken over. For
preference one would wish that the part to be taken over can be delineated precisely by means
of a barrier or otherwise. There is also the possibility that because the Contractor will no
longer be liable for delay in completing the part, he may have no great desire to come back to
finish it and this should be borne in mind when making the initial decision. In addition, insurers
should be notified so that no confusion is caused by the take-over.
Liquidated Damages
Example:
The rate of liquidated damages per day or per week will be inserted by the Employer in the
Schedule part 1 G and in this regard the Employer should assess carefully the likely losses to be
suffered by him should either a Section or ultimately the entire Works be delayed due to the
Contractor’s default. In this regard the Employer should make sure that the amount in question
is a genuine pre-estimate of actual losses in order to avoid the possibility that the damages may
be unenforceable by reason of being a penalty.
In point of fact, many Employers insert liquidated damages that do not take into account all of
their likely losses and accordingly such liquidated damages are too low. In the case of Public
Works contracts, while it may be difficult to accurately assess the precise damages that will be
suffered, nevertheless an attempt should be made taking all possible areas of damage into
account such as interest on money borrowed. Obviously, the Employer should be aware of the
risk of inserting a rate that is so high that it is a penalty.
There is also provision here for reduction in retention on substantial completion of a Section
and in this regard the Employer should consider the relationship that the Section in question
bears to the overall works, for instance if the Section is a very substantial part of the Works and
represents 25% of it in monetary terms then it may be appropriate to reduce the retention by a
similar percentage once that Section is substantially complete. However, other factors may
come into play which would result in the reduction not being of similar proportions.
the delay
the cause
In addition
The Contractor must as soon as practicable after the First notice and in any
event within 40 working days after becoming aware of the delay, give the ER:
The contract provides, that if the Contractor has already given notice and details
under sub-clause 10.3 as he is obliged to do in any event, he does not have to
give further notice or details under sub-clause 9.3 (sub-clause 9.3).
Both the Contractor and ER must follow the procedures in clause 10 and the
entitlement to an extension of time is subject to the provisions of clause 10
(sub-clause 9.3.2).
The ER can revise an extension of time but can only bring the date(s) for
Substantial Completion of the Works (or any Section) forward when work is
omitted (and agreed with the Contractor).
Example:
The notice requirements in relation to delays and the granting of extensions of time are clearly
set out in the Contract and the Delay Events which give rise to an extension of time are clearly
set out in the Schedule. The ER will be required to assess whether the Notice Requirements
have been satisfied and whether the requisite information is being furnished by the Contractor
before granting any extension to the Date for Substantial Completion.
The ER will also have to consider very carefully whether, in the light of particular
circumstances, he might wish to grant an extension of time despite the fact that
no such extension has been sought by the Contractor (sub-clause 10.5.2).
The Employer provides in the Schedule for two (sequential) thresholds for delay
in Substantial Completion due to certain Compensation Events. The Contractor
prices these items and includes them in the initial Contract Sum and also in his
programme.
If a delay is caused to the Date for Substantial Completion of the Works due to
relevant Compensation Events but that delay remains below the first threshold –
the Contractor has no entitlement to an extension of time.
If the delay due to relevant Compensation Events exceeds the first threshold
then the ER deducts from that delay
But the total number of days to be deducted at (ii) above cannot exceed the
number of days in the second threshold.
Example:
Thus if the Employer had inserted 20 days for first threshold and 30 days for second threshold –
in respect of a 60 day delay (due to relevant Compensation Events) the Contractor would be
entitled to a 20 day extension of time i.e.
60 days less 20 days (first threshold period) = 40 days ÷ 2 (to get half of the excess over the
second threshold)= 20 days
As 20 days is less than the second threshold the figure of 20 days is also deducted
Therefore 60 days – (20 days + 20 days) = 20 days extension of time
Example:
In a situation where there was a delay of 100 site working days and assuming the first threshold
was 20 days and the second threshold was 30 days the calculation of any extension of time
would be as follows:
100 days less 20 days (first threshold) = 80 days ÷ 2 (to get half of excess over first threshold) =
40 days
As 40 days is greater than the second threshold, the second threshold of 30 days is used
Therefore 100 days – (20 days + 30 days) = 50 days extension of time
And see the examples in sub-clause 9.4.4
Reference sub-clause 10
The notice must state that it is given pursuant to sub-clause 10.3 of the Contract
and must comply with the provisions of sub-clause 4.14.
The Contractor must provide any additional information required by the ER.
Failure to give notice under this sub-clause will mean the Contractor has no
entitlement to the extension of time or adjustment sought (sub-clause 10.3.2 and
see sub-clause 10.5.2).
The requirements in relation to strict notice do not apply where the Contractor
has complied with a request for a proposal pursuant to sub-clause 10.4.
setting out the extension of time and adjustment to the Contract Sum
sought
proposing a final adjustment to the Contract Sum and Date for Substantial
Completion
providing any other reasonably required information (sub-clause 10.3.3)
The Contractor must keep detailed records of the event giving rise to the delay
and adjustment to the Contract Sum. These must include any records required
by the ER.
Proposed Instructions
The ER has 20 working days within which to respond to any Contractor’s claim
or proposal under sub-clauses 10.3 or 10.4.
The ER must:
The Contract also provides that the ER may make his own determination on any
extension of time, use of the programme contingency or adjustment to the
Contract Sum despite the Contractor not having made any claim or proposals
under sub-clauses 10.3 or 10.4. This is a very important potential relaxation of
the otherwise exacting provisions of the Contract in relation to notice of claims.
It will arguably impose an added responsibility on the ER to decide in each case
where he feels an extension of time or adjustment to the Contract Sum is
appropriate, whether or not to grant it where the Contractor would otherwise
have lost his entitlement because of a failure to give notice.
Where a proposal is sought by the ER under clause 10.4 the Contractor is not
entitled to implement such an instruction until confirmed by the ER.
As with extensions of time, the notice requirements in relation to Contractor's claims and
adjustments to the Contract Sum are exacting but once again are clearly set out in clause 10,
which also provides for notice requirements in relation to extensions of time (see sub-clause
10.3.1). The ER upon receipt of such notice will be obliged to deal with it in a very systematic,
efficient and transparent manner. It would be incumbent upon the ER in conjunction with the
Employer to set up a system for dealing with such claims so that they can be responded to
promptly and fully. As with notices of delay the ER will have to assess whether or not the
Contractor is prime facia entitled to an adjustment to the extension of time/Contract Sum or
any other entitlement claimed, and to assess whether or not he has provided all details
required under the Contract and within the relevant periods. In this regard the ER will be well
aware that the notice requirements under clause 10 are conditions precedent to the
Contractor’s entitlement.
Thus, if the Contractor fails to give notice in accordance with the sub-clause he will have no
entitlement to the extension of time or adjustment unless the ER uses his discretion under sub-
clause 10.5.2. It is possible that the Contractor may have fulfilled the requirements by means of
a proposal in relation to a proposed instruction pursuant to clause 10.4 and the ER will have to
be mindful of this.
The ER will need to keep careful sight of all details of continuing delay and cost received from
the Contractor, should have a firm and reasoned opinion on them and must be mindful of the
fact that he himself is subject to a 20 working day period within which to respond to
Contractor’s claims under sub-clause 10.3 or proposals under sub-clause 10.4. The ER will also
have to keep in focus in relation to delay claims the use of the programme contingency so that it
can be used where appropriate and the Contractor can be notified of the fact of its use and of
the remaining amount of the contingency.
Where a Compensation Event delays the carrying out of the Works so as to push the Contract
into a consecutive period of 7 or more non-working days that would not otherwise have
occurred the Contractor is entitled to compensation in respect of his expenses exclusive of
profit or loss of profit. This is to be included in addition to the Contract Sum for the delay
cost. However, the ER in assessing the amount should note that the amount to be paid in
respect of the non-working days is not to exceed the sum arrived at by multiplying the
Contractor’s tendered rate of delay cost by the non-working days being compensated for.
It should be noted that a non-working day is defined as "a day that, for good reason, is not a Site
Working Day [such as a trade holiday.]"
In a case where the Contractor is required to and does provide in the Schedule Part 2 in
respect of delay costs for parts of the Works then of course the rate quoted for the portion of
the Works when the delay occurred is to be used as assessed by the ER.
the rates in the Pricing Documents are to be used where the work is similar
and executed under similar conditions to those priced
Alternatively, the ER may direct that any additional or substituted work is valued
by reference to the actual cost of performing the work as follows:
the hours worked by each work person as identified by the Schedule (parts
1K and 2E) multiplied by the rate for that category of work person as per
the Schedule (part 2E)
the cost of materials used plus the percentage adjustment of that cost as
tendered and set out in the Schedule (part 2E)
the cost of plant used at rates in the document set out in the Schedule (part
1K) – if no rate in the Schedule – market rental can be used - adjusted per
the adjustment provided for in the Schedule (part 2E)
The Schedule Part 1 plays a role in assessing adjustments to the Contract Sum
by identifying Compensation Events. The Pricing Document has an even more
crucial role in providing the rates pursuant to which varied work will be paid for.
The Pricing Document is to be used where it contains rates applicable to the
additional, substituted or omitted work. If the nature of the work carried out is
different to that in the Pricing Document the ER will use those rates as the basis
for his evaluation. Otherwise he is to make a fair valuation which presumably
would be based upon rates for similar work in the locality carried out under
similar conditions.
The ER may use the cost of relevant materials together with the percentage in
the Schedule part 2E in valuing materials.
If the delay cost option is chosen by the Employer, the Contractor’s tendered
rate of delay costs is to be provided by him at tender stage (in the Schedule part
2E) in accordance with the instruction contained in the Schedule part 1K.
An important point of note is that for periods of concurrent delay – there will
be no increase in the Contract Sum if one of the causes of a delay is not a
Compensation Event (sub-clause 10.7.2).
The subject of liability for concurrent delays in construction has been the subject of much debate
in the past. The provision in the Contract makes it clear that concurrent delays (i.e. periods of
delay for which there are more than one cause) will not be compensated unless all are
Compensation Events. This can be argued for on the basis that there is in fact no net delay for
which the Employer has agreed to adjust the Contract Sum While it is unlikely that a contractor
would seek an extension of time due to a cause that was not a Compensation Event where such
delay was concurrent with a "compensatable delay", the ER ensure that extensions are granted
for such causes, using the discretion under sub-clause 10.5.2 if necessary.
Example:
For instance, if the same period of delay is due to a combination of the failure by the Employer
to give the Contractor a Works Item or other thing required by the Contractor after the
Contractor has asked for it (sub-clause 4.10) [both a Delay Event and a Compensation Event]
and say, a weather event as defined in the Schedule Part IK [a Delay Event but not a
Compensation Event] then the Contractor would not be entitled to any increase in the
Contract Sum for that period of concurrent delay.
the amount added to the Contract Sum must not exceed the amount
calculated by multiplying the Contractor’s tendered rate of delay cost by the
additional non-working days (sub-clause 10.7.3)
When the ER is calculating the adjustment to the Contract Sum in respect of the
delay caused by the Compensation Event, he uses the Contractor’s tendered
rate of delay costs to calculate the compensation in question.
Employer’s Claims
The Contract now expressly provides for the making of claims by the Employer
against the Contractor.
the Employer or ER must give notice of the event to the Contractor (and
the other)
The Employer is entitled to deduct from any money due to the Contractor
If the Employer becomes aware of a claim that he may have against the
Contractor it will be important for him to liaise with the ER in this regard.
Likewise if the ER considers that the Employer is entitled to claim monies from
the Contractor it would be incumbent upon him to discuss the matter with the
Employer and to assess whether or not such a claim is to be made. For instance,
if the Contractor has not provided a Collateral Warranty on time then the
amount referred to in sub-clause 11.4.1 and set out in the Schedule (Part IF) is
due from the Contractor to the Employer pursuant to sub-clause 11.4 and this
will be referred to in the notice. The notice should also include a clear
calculation and the proposed adjustment to the Contract Sum.
Once the Contractor has responded within the 20 working days time limit
available to him under sub-clause 10.9.2 the ER makes his determination and
once that determination has been made, the Employer is entitled to deduct the
amount determined (if any).
If the Contractor was for instance carrying out another contract for the
Employer elsewhere and substantial amounts are due to the Employer under
that Contract then the Employer is also entitled to deduct such an amount
pursuant to sub-clause 10.9.3.
The ER will have to ensure that in making any determination of sums due or
likely to become due by the Contractor to the Employer, he is careful that no
injustice is done to either party.
14.11 Payment
Interim Payment
at the periods for interim payments in the Schedule (part 1L) (provided the
minimum payment amount in the Schedule is reached)
on the issue of the Certificate of Substantial Completion for the Works or a
Section (sub-clause 11.1.1)
The ER must provide a payment certificate within 10 working days (with copy to
Employer) stating the amount the ER says is due including Employer’s claims and
liquidated damages with calculations and reasons for the amount in the
certificate.
The Contractor must furnish an invoice to the Employer who must pay within
15 days from receipt of the invoice by him.
Example:
Assuming the period for interim payment is confirmed as being monthly and assuming that the
minimum amount for interim payments has been reached the Contractor submits his interim
account to the ER in the normal way.
The ER calculates the amount to which the Contractor is entitled noting that the works must be
properly executed and calculating the value based on the Pricing Document. In addition the ER
will add in any amount the Contractor is entitled to be paid for Unfixed Works Items up to the
percentage stated in the Schedule part IL. If there are any adjustments to be made to the
Contract Sum for Compensation Events (i.e. for additional or substituted work under sub-clause
10.6 and/or delay costs under sub-clause 10.7) then these will be added together with any
amount in respect of price variations.
The Employer will then received a copy of the Payments Certificate which has been issued to
the Contractor (within 10 working days of the Contractor’s statement) and an invoice based on
the amount of that Payment Certificate. The Employer will have 15 days within which to pay the
amount due falling which the Employer will become liable to interest at the rate provided in the
European Communities (Late Payment in Commercial Transactions) Regulations, 2002.
Retention may also be deducted by the Employer from the payments to be made
– see notes on retention below (sub-clause 11.3).
It may be seen from the above that the timeframe for certification and payment
is very tight. This will require clear lines of communication between all relevant
parties so as to ensure there are no problems with payment to Contractors.
They are complete and substantially ready for incorporation in the Works
Title has been vested in the Employer
They are stored on the Site
They have not been brought onto the Site prematurely
If the Works Items have not been delivered to the Site following qualifications
apply:
Retention
The percentage for retention by the Employer is set out in the Schedule (part
IL).
However, the Contractor may provide a retention bond (in the form contained
in the Model Forms – Form 17 or in an approved form) and where he does so
within 10 working days of Substantial Completion he is entitled to invoice for
and be paid the balance of the retention money.
Where a retention bond is being provided similar considerations are applicable to the provision
of a performance bond. This means that the employer should ensure that the bond is in the
appropriate form (see Model Forms – Form 17 (which should be contained in the Works
Requirements and if not contained in the Works Requirements, the Employer will need to vet
the form to ensure that it is a satisfactory form. In this regard it might be appropriate to either
have it approved by the Employer’s legal advisers or at the very least to compare it with the
form in the Model Forms.
If the Contractor has not complied in full with his various obligations – there is
no obligation on the Employer to pay in full. The Contract provides for the
deduction or withholding of money from the Contractor under a number of
headings.
if collateral warranties are not provided in time (i.e. by the date set out in
the Schedule for their provision) – the Employer may deduct the amount
shown in the Schedule and hold it until the warranty is furnished
if a programme or progress report under sub-clauses 4.9 and/or 4.10 is not
provided in time – the Employer may deduct 15% of any payments due until
it is furnished
if the Contractor has not complied with the requirements of sub-clause 5.3
re proper payments to work persons – the Employer may estimate the
amount due to such work persons and deduct it until satisfied with the
situation
if the Contractor does not provide a certificate as required with his interim
statement that all work persons have been properly paid in respect of the
relevant work – the Employer may withhold payment for the (estimated
labour element of the) relevant work until receipt of the certificate The
Contractor is obliged to give the Employer any necessary information for
the estimation of the labour element (sub-clause 11.4)
Any deductions made as above are deducted from the Contract Sum if there has
been no compliance by the date of issue of the Defects Certificate
When the Employer is making payment to the Contractor he should have from
the ER a clear record of whether or not the Contractor is in compliance with
his obligations to provide Collateral Warranties, the programme and progress
reports. The Employer should also make sure that the ER is informing him as to
whether the Contractor has provided the Certificate required with sub-clause
5.3.7 (relating to proper payment of work persons) with his interim statement.
With regard to the provisions of clause 5.3 it is intended that the Contractor
himself will police the payment of all relevant work persons and the certification
under sub-clause 5.3.7 is part of this process. However, the Contract provides
at sub-clause 5.3.3(A)(2) when included by means of the Schedule (part 1J) for
random checks by the Employer and it is the policy of the Government that
such checks are to be made.
Example:
If a payment has been certified in a certain amount and the Employer is aware that the
Contractor has not provided a collateral warranty by the date stated in the Schedule (part 1F)
then the Employer may deduct the amount due pursuant to the Schedule (part 1F) until that
warranty has been provided. Similarly, in respect of the other items which the Contractor is
required to give and in respect of which the Employer is entitled to deduct monies.
The Employer will then received a copy of the Payments Certificate which has been issued to
the Contractor (within 10 working days of the Contractor’s statement) and an invoice based on
the amount of that Payment Certificate. The Employer will have 15 days within which to pay the
amount due falling which the Employer will become liable to interest at the rate provided in the
European Communities (Late Payment in Commercial Transactions) Regulations 2002.
While the certification provisions envisage that sums due from the Contractor to the Employer
are taken into account in the interim Payment Certificates (although the wording of sub-clause
11.1.2 might lead one to believe otherwise) it does appear from sub-clause 11.4 that even if they
were not, the Employer may deduct the relevant sums under sub-clause 11.4.
The final statement must include all sums the Contractor says are due under or
in connection with the Contract (sub-clause 11.5.1).
The Employer has no liability for matters not set out in the final statement
except for:
The ER must then issue a final payment certificate as soon as practical and no
later than three months after the Defects Certificate issues stating the amount
finally due from the Employer to the Contractor (or vice versa).
The final payment certificate amount will be the same as the penultimate
certificate amount except that it will include:
The Contractor issues an invoice in respect of any sums due on foot of the
penultimate or final payment certificates and the Employer must pay within 15
days after receiving the invoice.
Note: The payment of certificates whether interim, penultimate or final do not relieve the
Contractor of its obligations under the Contract or provide evidence that the work has been
executed properly.
The final payment process is a relatively straightforward one. For example, the
Employer will receive in the first instance the penultimate payment certificate
from the ER which will set out the amount due by the Employer to the
Contractor (assuming that there is money due). The Employer will then receive
an invoice from the Contractor in respect of the amount due on the invoice and
is obliged to pay it within 15 working days. Alternatively if the penultimate
payment certificate indicates that the Contractor owes money to the Employer
then the Employer should make a demand upon the Contractor in respect of the
amount whereupon the Contractor is obliged to pay within 10 working days of
receipt of that demand.
The Employer will expect to receive from the E.R a final payment certificate
showing the final amount due to the Contractor (or vice versa) within 3 months
after the issue of the Defects Certificate. This certificate will constitute the final
payment to be made by the Employer to the Contractor
The Employer must pay the amount due on foot of the final payment certificate
within 15 working days of receiving an invoice in this respect from the
Contractor failing which he will become liable to pay interest at the rate
provided in the European Communities (Late Payment in Commercial
Transactions) Regulations 2002.
Unless a specific time is stated any amount due is to be paid within 30 (calendar)
days of receipt of the relevant demand.
Practically all payments to be made under the Contract appear to be provided for with a specific
time being stated – i.e. 15 days or 10 days
14.12 Termination
Termination on Contractor Default
Reference clause 12
Where the Contractor consists of more than one entity or person and an
insolvency event occurs in relation to one of them the Employer may:
The Employer may also terminate if there is a failure on the part of the
Contractor to provide a replacement Guarantor and guarantee where the initial
Guarantor becomes insolvent or the guarantee becomes unenforceable
Example:
If the Contractor is in default of its obligations under the Contract e.g. failing to proceed with
the execution of the Works and failing to repair defective workmanship or otherwise failing to
comply with obligations under the Contract, the Employer should be kept informed of such
matters by ER It would be necessary for the Employer and ER possibly subject to receipt of
legal advice to assess precisely which of the provisions of sub-clause 12.1.1 that the Contractor
is failing to comply with. It is likely that if the question of termination is being contemplated at
all, that the matter has been going on for quite some time.
If however the Employer is indeed seriously contemplating termination then he should discuss
the matter in depth with the E.R and possibly with his legal adviser so that the correct approach
is taken. For instance, if the matter is one which can be rectified then it would be essential for
the ER to issue a formal direction to the Contractor to put the matter right and in this regard it
would be useful to formally state that if the matter is not rectified within 14 days, the Employer
intends to exercise his right to terminate the Contractor’s obligation to complete the Works.
The Contractor should then be given the 14 days within which to put the matter right and only
if he has not done so within that period should the Employer serve notice on the Contractor
pursuant to sub-clause 12.1 terminating his obligation to complete the Works. Legal advice
should be sought upon the format of the notice but in essence it must be clear and unequivocal
and preferably should state precisely what it is and the fact that it is a notice pursuant to sub-
clause 12.1 of the Contract. The notice should be sent in strict accordance with the provisions
of sub-clause 4.14 and to the person named in the Schedule part 2A.
It would also be important for the Employer and the ER to consider the position under the
Bond or Bonds that have been provided by the Contractor and whether notification of the
bondsman is appropriate (which is likely).
If the Contractor persistently fails to honour his obligations to pay work persons properly then
the Employer is entitled to serve notice of termination without the 14 day notice. Similarly, if an
Insolvency Event as defined in sub-clause 12.1.1 occurs then the Employer may serve a notice of
termination without any further notice.
The consequences of termination for default are set out in clause 12.2 and
include:
The Contractor must leave the Site and not remove any Works Items or
Contractor’s Things unless directed to do so
Payments are postponed
The ER makes an assessment (as soon as practical) of the amount due in
respect of work done and not yet paid (the "termination value")
The Employer engages other contractors to use the Works Items and
Contractor’s Things on the Site to complete the Works
The Contractor must assign sub-contracts and supply contracts etc. to the
Employer where directed to do so
The Employer has discretion to pay sub-contractors or suppliers amounts
already paid to the Contractor and the Contractor must re-pay those
amounts
The Contractor must hand over all Works Requirements and Contractor’s
Documents to the Employer
Once the Works have been completed the ER certifies the "termination
amount" which includes:
The certificate showing the termination value must in the case where the
Employer does not start completion of the Works within 6 months after
termination, issue as soon as practicable after the end of the 6 month period.
If (as would be normal) the termination amount is more than the termination
value the Contractor must pay the Employer the difference within 10 working
days of receiving the Employer’s demand. If the termination amount is less than
the termination value then the Employer pays the Contractor the difference on
receipt of an invoice.
As with all termination situations one of the crucial things that the Employer
would have to address immediately is securing the Site and this he should do, by
if necessary employing a security firm to see that the Contractor leaves the site
as he is required to do pursuant to sub-clause 12.2.1 in an orderly manner.
In securing the Site the Employer should note that the Contractor is not entitled
to remove Works Items or Contractor’s Things from the Site unless required to
do so by the Employer. However, the Employer will need to make a practical
assessment on this and the most important thing will be to ensure that all
Works Items necessary for completion of the Works are kept on Site.
It will obviously be necessary to complete the Works and the Employer should
liaise with the ER so as to assess what Specialist contracts or supply contracts
should be assigned to the Employer.
The Employer will also be engaging another contractor to complete the Works
and will also be making a call on the Performance Bond provided by the
Contractor.
After Substantial Completion the Employer will receive from the ER a certificate
indicating what if any amount is due by the Employer to the Contractor or by
the Contractor to the Employer. If, as is likely, an amount is due by the
Contractor to the Employer then the Employer should draft up and furnish a
demand for payment from the Contractor. Should there be an amount due to
the Contractor this will be payable by the Employer within 15 working days after
receiving an invoice from the Contractor furnished on foot of the ER’s
certification.
Failure by the Employer to pay any amounts due to the Contractor entitles the
Contractor to suspend the Works if no payment is made within 15 working days
after receipt by the Employer of a demand from the Contractor.
One important limitation on this power is that the Employer may not terminate
under it for the purpose of obtaining another Contractor to execute/complete
the works.
When the Employer terminates at his own election the consequences are set
out in sub-clause 12.6 of the Contract and include:
Example:
The Employer might become aware during the course of the project that the Works will no
longer be needed because of another larger project that is ongoing and that will effectively take
away the necessity for the Works (for instance a relief road that will not be needed because
another larger road scheme will cater for the traffic in question).
In such a case the Employer might wish to terminate the Contractor’s obligation to complete
the Works even though the Contractor is not in default. Where this arises the Employer
should serve notice on the Contractor terminating the Contractor’s obligation to complete and
stating that he is utilising the provisions of sub-clause 12.5 of the Contract. The notice should
provide that it will take effect 20 working days after it has been delivered to the Contractor.
As with all such notices the Employer should make absolutely sure that the notice is delivered
properly to the correct address for service of such notices in accordance with sub-clause 4.14.
The Employer should also obtain the original of the Performance Bond provided by the
Contractor and return this to the Contractor at the expiration of the 20 days notice.
Once again the Employer should ensure that the Site is adequately secured, that the Contractor
leaves the Site in an orderly manner and removes all of the Contractor’s Things. The Employer
should ensure that the ER obtains from the Contractor all Works Requirements and
Contractor’s Documents. Once the Contractor has provided a statement of the amounts
making up the termination sum to the ER the ER will provide (within 10 working days of
receiving the statement) a certificate to both the Employer and the Contractor showing the
amount due from the Employer to the Contractor (or vice versa). The Employer will then
receive an invoice from the Contractor (or if the amount is due from the Contractor to the
Employer the Employer should make a demand for payment of the sum) and the Employer is
obliged to pay within 15 days of receipt of the invoice (the Contractor must pay any sum due by
him within 10 days of the demand).
In a case of termination the Employer may need to consider whether the Contractor should be
kept on as Project Supervisor or otherwise, the urgent appointment of a replacement Project
Supervisor for the Construction Stage in relation to the final "mothballing" of the Works.
Alternatively if there is any part of the Works to be demolished then this would be a separate
project requiring a new Project Supervisor.
The payment by the Employer to the Contractor of the sums provided for in
clause 12 together with any other amounts due under the Contract before
termination are stated to be the Employer’s total liability to the Contractor.
(sub-clause 12.6)
Where the Employer is of the view that an entitlement has arisen on his part to
terminate the Contractor’s obligation to complete the Works, the Employer has
a discretion to refer the issue of his entitlement to conciliation. (sub-clause
12.9.1)
The appointed conciliator must give his recommendation within 21 days after his
appointment.
In the event that the Conciliator recommends that the Employer is entitled to
terminate the Contractor’s obligation to complete the Works for default and if
the Employer does so within 60 days after the recommendation it may be found
in subsequent arbitration proceedings that the Employer was not entitled to do
so. In such an event:
The Contractor has no other rights under the Contract or otherwise at law for
the termination
Example:
In certain circumstances where the Employer is of the view that he has become entitled to
terminate the Contractor’s obligation to complete the works pursuant to sub-clause 12.1 he
may, in view of the circumstances and the likelihood that the Contractor would challenge the
termination, wish to refer the question of his entitlement to terminate to conciliation. In
arriving at such a decision the Employer would in conjunction with the ER look at the facts giving
rise to the potential termination and consider whether they are absolutely clear-cut. In the
event that they are clear-cut then the Employer might not feel it was incumbent on him to
conciliate on the matter but if there was any doubt it might be safer for him to do so.
If the Employer decides to conciliate upon the matter then he will serve notice of the
conciliation on the Contractor pursuant to sub-clause 13.1 of the Contract.
If the Conciliator recommends that the Employer is entitled to terminate then the Employer
should do so within 60 days after the receipt of the Conciliator’s recommendation. The aim of
this procedure is, that by following it, the Employer should hopefully safeguard his position and if
the Contractor refers the entire matter to arbitration and it is ultimately held that the Employer
was not entitled to terminate then the provisions of sub-clause 12.9.3 will apply and the
termination will stand as if it was a termination at the Employer’s election.
In such a case the Employer will be entitled to engage another Contractor to complete the
Works although obviously those works will be substantially delayed.
The Contract provides that disputes arising in connection with, out of the
Contract or Works are to be referred to conciliation and ultimately to
arbitration if conciliation does not resolve the dispute.
The parties must appoint the conciliator within 10 working days of the referral
and in default the appointing body as set out in the Schedule (Part 1N) appoints.
The parties must make all information and documents available to the conciliator
that he requires.
The Conciliator must give his recommendation if the dispute is not resolved
within 42 days after his appointment (sub-clause 13.1.8).
Each party has 45 days in which to give notice of dissatisfaction to the other
party in writing (and specified to have been given under sub-clause 13.1). Such a
notice may issue in the event that no recommendation is given within 45 days of
the appointment (sub-clause 13.1.9).
Once notice of dissatisfaction has been given, either party may serve notice of
arbitration on the other (sub-clause 13.1.9).
The conciliation process is relatively straightforward. One thing that is new in the forms of
Contract is the provision at sub-clause 13.1.11 to the effect that if a payment of money is
recommended by the Conciliator the money is to be paid over upon the provision of a bond as
security. There is also provision for the repayment where applicable of money paid over on foot
of a conciliator’s recommendation or interest earned on such moneys where an arbitrator’s
award is for a lesser amount than the sum originally paid over. (sub-clause 13.1.1).
Example:
If the Employer has discharged the monies due on foot of the conciliator’s recommendation
and has received a bond from the Contractor
Firstly, when considering the form of bond to be furnished by the Contractor in exchange
for payment on foot of the recommendation it may be appropriate to consider carefully the
proposed expiry date of the bond. This is because the Employer may be confronted with an
arbitration which may drag on for a considerable period and a bond which will be due to
expire within a set period of time.
If payment has been made and a bond pursuant to Model Form 19 has been provided the
Employer should consider carefully his approach to the arbitration. It may be that because
the Contractor has received payment he does not want to pursue the arbitration or does
not wish to be the Claimant in the arbitration. However, it would be essential that the
Contractor is the Claimant in the arbitration (unless circumstances dictate that he should
not be) as otherwise it would become evident to the Arbitrator that payment has been made
on a Conciliator’s recommendation. It would therefore be essential that this be agreed
(preferably before payment over of the recommended amount) and that the Contractor
agrees to prosecute the arbitration promptly and efficiently.
Arbitration
The relevant arbitration rules are as set out in the Works Requirements.
Disputes under the Contract are subject to the jurisdiction of the Irish courts
and to the Public Works Arbitration Rules 2007.
14.14 Comparison of Traditional and Design & Build Forms for Building
Works
The following table tabulates the differences between the forms for Building
Works designed by the Employer and Building Works designed by the
Contractor.
Agreement
Article 1 The Contractor shall execute and The Contractor shall design, execute
complete the Works subject to and and complete the Works subject to
in accordance with the Contract, and in accordance with the Contract,
and shall comply with its other and shall comply with its other
obligations in the Contract. obligations in the Contract.
Article 4 The Contractor has satisfied itself The Contractor has satisfied itself
before entering into the Contract before entering into the Contract of
of all the circumstances that may all the circumstances that may affect
affect the cost of executing and the cost of designing, executing and
completing the Works and of the completing the Works and of the
correctness and sufficiency of the correctness and sufficiency of the
Contract Sum to cover the costs of Contract Sum to cover the costs of
performing the Contract. The performing the Contract. The
Contractor has included in the Contractor has included in the initial
initial Contract Sum allowances for Contract Sum allowances for all
all risks, customs, policies, risks, customs, policies, practices,
practices, and other circumstances and other circumstances that may
that may affect its performance of affect its performance of the
the Contract, whether they could Contract, whether they could or
or could not have been foreseen, could not have been foreseen,
except for events for which the except for events for which the
Contract provides for adjustment Contract provides for adjustment of
of the initial Contract Sum. the initial Contract Sum.
Agreement
Conditions
Definitions Starting Date means the day Starting Date means the day the
the Contractor proposes to start Contractor proposes to start
executing the Works, as notified work under the Contract, as
by the Contractor to the notified by the Contractor to the
Employer’s Representative under Employer’s Representative under
sub-clause 9.1. sub-clause 9.1.
2.4.1 If the Works Requirements say If the Works Requirements say that
that the Contractor is to be the Contractor is to be appointed
appointed project supervisor for project supervisor for the
the construction stage in construction stage or the design
accordance with the Safety, process or both in accordance with
Health and Welfare at Work the Safety, Health and Welfare at
(Construction) Regulations 2006 Work (Construction) Regulations
(the Construction 2006 (the Construction
Regulations) for the Works, or Regulations) for the Works, or a
a project including the Works, project including the Works, the
the Contractor shall accept the Contractor shall accept the
appointment by entering into the appointment by entering into the
appointment in the form in the appointment in the form in the
Works Requirements. If the Works Requirements. If the Works
Works Requirements say that an Requirements say that an individual
individual or body corporate or body corporate named in the
named in the Works Proposals is Works Proposals is to be
to be appointed project appointed project supervisor for
supervisor for the construction the construction stage or the
stage in accordance with the design process or both in
Safety, Health and Welfare at accordance with the Safety, Health
Work (Construction) Regulations and Welfare at Work
2006 (the Construction (Construction) Regulations 2006
3.1 (6) design of the Works by the Clause not in this Contract
Employer or by others for
whom the Employer is
responsible, but not if the
design is covered by insurance
required under clause 3.7.
4.6.3 Clause not in this Contract The Contractor adopts the Novated
Design Documents as Works
Proposals, and is fully responsible for
them. [The Contractor shall submit
any changes to the Novated Design
Documents to the Employer’s
Representative.]
4.8.1 The Contractor may give to the The Contractor may give to the
Employer’s Representative a Employer’s Representative a written
written value engineering proposal value engineering proposal that will,
that will, if adopted, either: if adopted, either:
(1) reduce the Contract Sum or (1) reduce the Contract Sum or
(2) accelerate the execution of the (2) accelerate the design or
Works, or otherwise be of execution of the Works, or
benefit to the Employer, with otherwise be of benefit to the
no increase to the Contract Employer, with no increase to
Sum. the Contract Sum.
4.11.2 The latest date for the Employer’s The latest date for the Employer to
Representative to give required give the Contractor any required
instructions, or the Employer to Works Item or other thing, shall be
give the Contractor any the latest of the following:
required Works Item or other
thing, shall be the latest of the
following:
(1) the date stated in the (1) the date stated in the Contract,
Contract, if any if any
(2) the date shown in the (2) the date shown in the
Contractor’s current Contractor’s current
programme programme
(3) the date for which the (3) the date for which the
Contractor first notifies the Contractor first notifies the
Employer’s Representative Employer’s Representative under
under this sub-clause that it is this sub-clause that it is required
required
(4) the date the Contractor requires
(4) the date the Contractor the instruction, Works Item or
requires the instruction, other thing in accordance with
Works Item or other thing in its actual progress.
accordance with its actual
progress.
4.16.3 This sub-clause 4.16 shall not This sub-clause 4.16 shall not prevent
prevent disclosure of information, disclosure of information, to the
to the extent permitted by Law: extent permitted by Law:
7.1.1 Clause not in this Contract (6) 10 working days (or another
period stated in the Works
Requirements) after the
Contractor has informed the
Employer’s Representative that
it is ready to start executing the
Works on the Site
7.1.1 Clause not in this Contract (8) 10 working days after the
Contractor has obtained all the
Consents it needs to start
executing the Works on the Site
and given copies to the
Employer’s Representative.
7.5.1 From and including the Starting From and including the date the
Date until the Employer’s Employer allows the Contractor to
Representative certifies the occupy and use the Site until the
Works or the relevant Section as Employer’s Representative certifies
Substantially Complete, or the the Works or the relevant Section as
Employer takes over the relevant Substantially Complete, or the
part of the Works under sub- Employer takes over the relevant
clause 9.7, the Contractor shall do part of the Works under sub-clause
all of the following [without 9.7, the Contractor shall do all of the
limiting other obligations]: following [without limiting other
obligations]:
7.7 The Contractor shall set out the The Contractor shall be responsible
Works by reference to the points, for the correct positioning of all parts
lines and levels of reference in the of the Works and shall rectify any
Works Requirements. The errors in the positions, levels,
Contractor shall be responsible for dimensions or alignment of the
the correct positioning of all parts Works.
of the Works and shall rectify any
errors in the positions, levels,
dimensions or alignment of the
Works. Before setting out the
Works the Contractor shall make
all reasonable efforts to verify the
accuracy of the setting out
information in the Works
Requirements.
8.1 The Contractor shall ensure all of The Contractor shall ensure all of
the following: the following:
(1) that the Works are executed (1) that the Works are designed,
and completed executed and completed
(i) in accordance with all the (i) in accordance with all the
requirements in, and requirements in, and
reasonably inferred from, reasonably inferred from,
the Contract [including, the Contract [including,
where so required by the where so required by the
Contract, in accordance Contract, in accordance
with Contractor’s with Contractor’s
Documents that have Documents that have been
been submitted to the submitted to the Employer’s
Employer’s Representative] and
Representative] and (ii) in a proper and
(ii) in a proper and workmanlike manner and
workmanlike manner and using good practice
using good practice
8.1 (3) that all materials and goods (3) that all materials and goods that
that are Works Items are Works Items are fit for their
[whether or not the intended purpose in the Works
Contractor is required to
select them] are fit for the
purpose for which they are
normally used
8.1 (4) that all Works Items selected (4) that the completed Works are
or designed by the Contractor fit for their intended purpose as
[including by any Specialist] are stated in or to be inferred from
fit for their intended purpose the Works Requirements.
in the Works.
8.3.1 The Contractor shall ensure that The Contractor shall ensure that the
the Employer’s Representative, and Employer’s Representative, and
anyone authorised by the anyone authorised by the Employer’s
Employer’s Representative, is able Representative, is able at all
at all reasonable times to have reasonable times to have access to
access to all places where the all places where the Works are being
Works are being executed designed or executed [whether or
[whether or not at the Site] and not at the Site] and any place where
any place where any Works Items any Works Items are produced,
are produced, stored, extracted or stored, extracted or prepared, or
prepared, or any other obligation any other obligation of the
of the Contractor under the Contractor under the Contract is
Contract is being performed, being performed, and are able there
and are able there to inspect, to inspect, test, observe and examine
test, observe and examine all all such items and activities.
such items and activities.
9.1.2 Before the Starting Date [unless Before the Starting Date [unless
already given by the Contractor already given by the Contractor
before the Contract Date, for before the Contract Date, for
example in response to a letter of example in response to a letter of
intent] the Contractor shall give intent] the Contractor shall give the
the Employer all of the following, Employer all of the following, all
all executed, as relevant, by the executed, as relevant, by the relevant
relevant persons: persons:
10.6.4 Clause not in this Contract (4) the cost of design, at the
tendered rates in the Pricing
Document.
(1) the Contract value of the (1) the Contract value of the
Works properly executed by Works properly designed and
the Contractor [according to executed by the Contractor
the Pricing Document] and [according to the Pricing
Document] and
12.1.1 (2) the Contractor abandons or, (2) the Contractor abandons or,
except where required or except where required or
permitted by the Contract, permitted by the Contract,
suspends the execution of the suspends the design or execution
Works of the Works
12.1.1 (3) the Contractor fails to (3) the Contractor fails to proceed
proceed regularly and diligently regularly and diligently with the
with the execution of the design and execution of the
Works Works
12.1.1 (5) the Starting Date has not (5) the Starting Date has not
occurred or the occurred or the Contractor has
Contractor has not not started work under the
started to execute the Contract within 6 weeks of the
Works on the Site within date the Contract requires
6 weeks of the date the
Contract requires
12.3 If the Employer fails to pay any If the Employer fails to pay any
amount due under a certificate amount due under a certificate
issued by the Employer’s issued by the Employer’s
Representative under the Representative under the Contract,
Contract, the Contractor may the Contractor may make of the
make of the Employer a written Employer a written demand for
demand for payment, and if the payment, and if the payment has not
payment has not been made within been made within 15 working days of
15 working days of the receipt of the receipt of the demand, the
the demand, the Contractor may, Contractor may, on giving notice to
on giving notice to the Employer, the Employer, suspend design and
suspend execution of the Works execution of the Works until the
until the amount has been paid. amount has been paid. On receiving
On receiving the payment, the the payment, the Contractor shall
Contractor shall resume resume design and execution of the
execution of the Works. Works.
(1) the Contractor has suspended (1) the Contractor has suspended
the execution of the Works the design and execution of the
for 15 working days in Works for 15 working days in
accordance with clause 12.3, accordance with clause 12.3, and
and the Employer has still not the Employer has still not paid
paid
12.5.2 The Employer may not terminate The Employer may not terminate the
the Contractor’s obligation to Contractor’s obligation to complete
complete the Works under this the Works under this sub-clause 12.5
sub-clause 12.5 for the purpose of for the purpose of retaining another
retaining another contractor to contractor to design and execute the
execute the Works. Works.
Schedule Part 1
Schedule Part 2
14.15 Comparison of Traditional and Design & Build Forms for Civil
Engineering Works
The following table summarises the differences between the forms for civil
engineering works designed by the employer and civil engineering works
designed by the contractor."
Agreement
Article 1 The Contractor shall execute and The Contractor shall design, execute
complete the Works subject to and in and complete the Works subject to
accordance with the Contract, and shall and in accordance with the Contract,
comply with its other obligations in the and shall comply with its other
Contract. obligations in the Contract.
Article 4 The Contractor has satisfied itself The Contractor has satisfied itself
before entering into the Contract of all before entering into the Contract of all
the circumstances that may affect the the circumstances that may affect the
cost of executing and completing the cost of designing, executing and
Works and of the correctness and completing the Works and of the
sufficiency of the Contract Sum to cover correctness and sufficiency of the
the costs of performing the Contract. Contract Sum to cover the costs of
The Contractor has included in the performing the Contract. The
initial Contract Sum allowances for all Contractor has included in the initial
risks, customs, policies, practices, and Contract Sum allowances for all risks,
other circumstances that may affect its customs, policies, practices, and other
performance of the Contract, whether circumstances that may affect its
they could or could not have been performance of the Contract, whether
foreseen, except for events for which they could or could not have been
the Contract provides for adjustment of foreseen, except for events for which
the initial Contract Sum. the Contract provides for adjustment
of the initial Contract Sum.
Article 5 The Contract consists of the following The Contract consists of the following
documents: documents:
Conditions
Definitions Starting Date means the day the Starting Date means the day the
Contractor proposes to start executing Contractor proposes to start work
the Works, as notified by the under the Contract, as notified by the
Contractor to the Employer’s Contractor to the Employer’s
Representative under sub-clause 9.1. Representative under sub-clause 9.1.
2.4.1 If the Works Requirements say that the If the Works Requirements say that
Contractor is to be appointed project the Contractor is to be appointed
supervisor for the construction stage in project supervisor for the
accordance with the Safety, Health and construction stage or the design
Welfare at Work (Construction) process or both in accordance with
Regulations 2006 (the Construction the Safety, Health and Welfare at
Regulations) for the Works, or a project Work (Construction) Regulations
including the Works, the Contractor 2006 (the Construction Regulations)
shall accept the appointment by entering for the Works, or a project including
into the appointment in the form in the the Works, the Contractor shall
Works Requirements. If the Works accept the appointment by entering
Requirements say that an individual or into the appointment in the form in
body corporate named in the Works the Works Requirements. If the
Proposals is to be appointed project Works Requirements say that an
supervisor for the construction stage in individual or body corporate named in
accordance with the Safety, Health and the Works Proposals is to be
Welfare at Work (Construction) appointed project supervisor for the
Regulations 2006 (the Construction construction stage or the design
Regulations) for the Works, or a project process or both in accordance with
including the Works, the Contractor the Safety, Health and Welfare at
shall ensure that the individual or body Work (Construction) Regulations
corporate named in the Works 2006 (the Construction Regulations)
Proposals accepts the appointment by for the Works, or a project including
entering into the appointment in the the Works, the Contractor shall
form in the Works Requirements. The ensure that the individual or body
Contractor shall, if appointed as project corporate named in the Works
supervisor, comply with its obligations Proposals accepts the appointment by
under the Construction Regulations in entering into the appointment in the
connection with that appointment. If the form in the Works Requirements. The
Employer terminates the appointment of Contractor shall, if appointed as
the Contractor or other person named project supervisor, comply with its
in the Works Proposals as project obligations under the Construction
supervisor for the construction stage as Regulations in connection with that
a result of that project supervisor’s appointment. If the Employer
failure to comply with its obligations, the terminates the appointment of the
Contractor shall pay to the Employer all Contractor or other person named in
the Employer’s cost resulting from the the Works Proposals as project
termination [including the cost of supervisor for the construction stage
appointing and fees and expenses paid to or the design process or both as a
a replacement project supervisor, or, if result of that project supervisor’s
the Employer acts as project supervisor failure to comply with its obligations,
itself, the Employer’s cost of doing so]. the Contractor shall pay to the
Employer all the Employer’s cost
resulting from the termination
[including the cost of appointing and
fees and expenses paid to a
replacement project supervisor, or, if
the Employer acts as project
supervisor itself, the Employer’s cost
of doing so].
2.5.1 The Contractor shall [without limiting The Contractor shall [without limiting
other obligations] ensure, so far as is other obligations] ensure, so far as is
practicable, that the Works are practicable that the Works:
constructed to be safe and without risk
to health, and that the Works comply in (1) are designed and are capable of
all respects, as appropriate, with the being constructed to be safe and
relevant statutory provisions. without risk to health and
(2) are constructed to be safe and
without risk to health and
(3) can be maintained safely and
without risk to health during use
and
(4) comply in all respects, as
appropriate, with the relevant
statutory provisions.
3.1 (6) design of the Works by the Clause not in this Contract
Employer or by others for whom
the Employer is responsible, but not
if the design is covered by insurance
required under clause 3.7.
4.5.4 The Employer’s Representative shall give Clause not in this Contract
an instruction that is, in the Employer’s
Representative’s opinion, necessary for
the completion of the Works. If, in the
Employer’s Representative’s opinion, it
is physically impossible or contrary to
Legal Requirements to complete the
Works in accordance with the Works
4.6.2 If any Works Proposals do not comply If any Works Requirements or Works
with the Contract or the initial Works Proposals do not comply with the
Requirements or Legal Requirements or Contract or Legal Requirements or
are physically impossible to comply with, are physically impossible to comply
the Contractor shall propose a change with, or if any Works Proposals do
to the Works Proposals as necessary. not comply with the initial Works
[There shall be no extension of time or Requirements, the Contractor shall
adjustment to the Contract Sum for propose a change to the Works
this.] If the Works Proposals need to be Requirements as necessary. The
changed because of a change to the change shall not take effect until it has
Works Requirements, the Contractor been agreed by the Employer’s
shall propose a change. The Contractor Representative. The Contractor shall
shall submit any change to the Works submit any change to the Works
Proposals to the Employer’s Proposals to the Employer’s
Representative. Representative. [There shall be no
extension of time, use of programme
contingency under sub-clause 9.4, or
adjustment to the Contract Sum for
changes or actions under this sub-
clause 4.6 or their consequences.]
4.6.3 Clause not in this Contract The Contractor adopts the Novated
Design Documents as Works
Proposals, and is fully responsible for
them. [The Contractor shall submit
any changes to the Novated Design
Documents to the Employer’s
Representative.]
4.8.1 The Contractor may give to the The Contractor may give to the
Employer’s Representative a written Employer’s Representative a written
value engineering proposal that will, if value engineering proposal that will, if
adopted, either: adopted, either:
(1) reduce the Contract Sum or (1) reduce the Contract Sum or
(2) accelerate the execution of the (2) accelerate the design or execution
Works, or otherwise be of benefit of the Works, or otherwise be of
to the Employer, with no increase benefit to the Employer, with no
to the Contract Sum. increase to the Contract Sum.
4.11.2 The latest date for the Employer’s The latest date for the Employer to
Representative to give required give the Contractor any required
instructions, or the Employer to give the Works Item or other thing, shall be
Contractor any required Works Item or the latest of the following:
other thing, shall be the latest of the
following: (1) the date stated in the Contract, if
any
(1) the date stated in the Contract, if
(2) the date shown in the
any
Contractor’s current programme
(2) the date shown in the Contractor’s
(3) the date for which the Contractor
current programme
first notifies the Employer’s
(3) the date for which the Contractor Representative under this sub-
first notifies the Employer’s clause that it is required
Representative under this sub-
(4) the date the Contractor requires
clause that it is required
the instruction, Works Item or
(4) the date the Contractor requires other thing in accordance with its
the instruction, Works Item or actual progress.
other thing in accordance with its
actual progress.
4.16.3 This sub-clause 4.16 shall not prevent This sub-clause 4.16 shall not prevent
disclosure of information, to the extent disclosure of information, to the
permitted by Law: extent permitted by Law:
(1) to the Contractor’s Personnel, the (1) to the Contractor’s Personnel, the
Employer’s Personnel or other Employer’s Personnel or other
professional advisors to the professional advisors to the
Contractor or Employer, who have Contractor or Employer, who
first entered an undertaking in the have first entered an undertaking
terms of this sub-clause 4.16, to the in the terms of this sub-clause
extent necessary for the execution 4.16, to the extent necessary for
of the Works or to enforce the the design or execution of the
Contract or Works or to enforce the
Contract or
7.1.1 Clause not in this Contract (6) 10 working days (or another
period stated in the Works
Requirements) after the
Contractor has informed the
Employer’s Representative that it
is ready to start executing the
Works on the Site
7.1.1 Clause not in this Contract (8) 10 working days after the
Contractor has obtained all the
Consents it needs to start
executing the Works on the Site
and given copies to the Employer’s
Representative.
7.5.1 From and including the Starting Date From and including the date the
until the Employer’s Representative Employer allows the Contractor to
certifies the Works or the relevant occupy and use the Site until the
Section as Substantially Complete, or Employer’s Representative certifies the
the Employer takes over the relevant Works or the relevant Section as
part of the Works under sub-clause 9.7, Substantially Complete, or the
the Contractor shall do all of the Employer takes over the relevant part
following [without limiting other of the Works under sub-clause 9.7, the
obligations]: Contractor shall do all of the following
[without limiting other obligations]:
7.7 The Contractor shall set out the Works The Contractor shall be responsible
by reference to the points, lines and for the correct positioning of all parts
levels of reference in the Works of the Works and shall rectify any
Requirements. The Contractor shall be errors in the positions, levels,
responsible for the correct positioning dimensions or alignment of the Works.
of all parts of the Works and shall rectify
any errors in the positions, levels,
dimensions or alignment of the Works.
Before setting out the Works the
Contractor shall make all reasonable
efforts to verify the accuracy of the
setting out information in the Works
Requirements.
8.1 The Contractor shall ensure all of the The Contractor shall ensure all of the
following: following:
(1) that the Works are executed and (1) that the Works are designed,
completed executed and completed
(i) in accordance with all the (i) in accordance with all the
requirements in, and reasonably requirements in, and
inferred from, the Contract reasonably inferred from, the
[including, where so required Contract [including, where so
by the Contract, in accordance required by the Contract, in
with Contractor’s Documents accordance with Contractor’s
that have been submitted to the Documents that have been
Employer’s Representative] and submitted to the Employer’s
Representative] and
(ii) in a proper and workmanlike
manner and using good practice (ii) in a proper and workmanlike
manner and using good
practice
8.1 (3) that all materials and goods that are (3) that all materials and goods that
Works Items [whether or not the are Works Items are fit for their
Contractor is required to select intended purpose in the Works
them] are fit for the purpose for
which they are normally used
8.1 (4) that all Works Items selected or (4) that the completed Works are fit
designed by the Contractor for their intended purpose as
[including by any Specialist] are fit stated in or to be inferred from
for their intended purpose in the the Works Requirements.
Works.
8.3.1 The Contractor shall ensure that the The Contractor shall ensure that the
Employer’s Representative, and anyone Employer’s Representative, and anyone
authorised by the Employer’s authorised by the Employer’s
Representative, is able at all reasonable Representative, is able at all reasonable
times to have access to all places where times to have access to all places
the Works are being executed [whether where the Works are being designed
or not at the Site] and any place where or executed [whether or not at the
any Works Items are produced, stored, Site] and any place where any Works
extracted or prepared, or any other Items are produced, stored, extracted
obligation of the Contractor under the or prepared, or any other obligation of
Contract is being performed, and are the Contractor under the Contract is
able there to inspect, test, observe and being performed, and are able there to
examine all such items and activities. inspect, test, observe and examine all
such items and activities.
9.1.2 Before the Starting Date [unless already Before the Starting Date [unless
given by the Contractor before the already given by the Contractor before
Contract Date, for example in response the Contract Date, for example in
to a letter of intent] the Contractor response to a letter of intent] the
shall give the Employer all of the Contractor shall give the Employer all
following, all executed, as relevant, by of the following, all executed, as
the relevant persons: relevant, by the relevant persons:
9.1.3 On the Starting Date, the Contractor On the Starting Date, the Contractor
shall start to execute the Works on the shall start work under the Contract.
Site. The Contractor shall, unless the The Contractor shall, unless the
Employer’s Representative directs Employer’s Representative directs
otherwise, proceed regularly and otherwise, proceed regularly and
diligently in order to achieve Substantial diligently in order to achieve
Completion of the Works and each Substantial Completion of the Works
Section by its Date for Substantial and each Section by its Date for
Completion. Substantial Completion.
10.6.4 Clause not in this Contract (4) the cost of design, at the tendered
rates in the Pricing Document.
11.1.2 The installment of the Contract Sum The installment of the Contract Sum
that the Contractor shall be entitled to that the Contractor shall be entitled to
be paid on an interim basis shall be: be paid on an interim basis shall be:
(1) the Contract value of the Works (1) the Contract value of the Works
properly executed by the properly designed and executed
Contractor [according to the by the Contractor [according to
Pricing Document] and the Pricing Document] and
12.1.1 (2) the Contractor abandons or, except (2) the Contractor abandons or,
where required or permitted by the except where required or
Contract, suspends the execution of permitted by the Contract,
the Works suspends the design or execution
of the Works
12.1.1 (3) the Contractor fails to proceed (3) the Contractor fails to proceed
regularly and diligently with the regularly and diligently with the
execution of the Works design and execution of the
Works
12.1.1 (5) the Starting Date has not occurred (5) the Starting Date has not
or the Contractor has not started occurred or the Contractor has
to execute the Works on the Site not started work under the
within 6 weeks of the date the Contract within 6 weeks of the
Contract requires date the Contract requires
12.3 If the Employer fails to pay any amount If the Employer fails to pay any amount
due under a certificate issued by the due under a certificate issued by the
Employer’s Representative under the Employer’s Representative under the
Contract, the Contractor may make of Contract, the Contractor may make of
the Employer a written demand for the Employer a written demand for
payment, and if the payment has not payment, and if the payment has not
been made within 15 working days of been made within 15 working days of
the receipt of the demand, the the receipt of the demand, the
Contractor may, on giving notice to the Contractor may, on giving notice to
Employer, suspend execution of the the Employer, suspend design and
Works until the amount has been paid. execution of the Works until the
On receiving the payment, the amount has been paid. On receiving
Contractor shall resume execution of the payment, the Contractor shall
the Works. resume design and execution of the
Works.
12.5.2 The Employer may not terminate the The Employer may not terminate the
Contractor’s obligation to complete the Contractor’s obligation to complete
Works under this sub-clause 12.5 for the Works under this sub-clause 12.5
the purpose of retaining another for the purpose of retaining another
contractor to execute the Works. contractor to design and execute the
Works.
Schedule Part 1
K7 The Employer’s Representative does not Schedule item not in this Contract
give the Contractor an instruction
required under sub-clause 4.5.4 within
the time required under sub-clause
4.11.2 when the Contractor has asked
for the instruction in accordance with
sub-clause 4.11.1
K 17 A difference between the Contract value Schedule item not in this Contract
of the Works according to the quantities
and descriptions in the Bill of Quantities
[taking into account the method of
measurement identified below when it
applies] and the Contract value of the
Works described in the Works
Requirements, because the Bill of
Quantities, when compared with the
Works Requirements:
K 19 The Contractor encounters on the Site Schedule item not in this Contract
unforeseeable ground conditions or
man-made obstructions in the ground,
other than Utilities
Schedule Part 2
Works designed by the Employer (the minor works contract) is in the same
form as the Public Works Contract for the Provision of Building Works and
Civil Engineering Works designed by the Employer (the Employer Designed or
traditional contracts).
The table below highlights the differences between the two forms of the above
mentioned contracts. Clause references in this comparison, unless stated
otherwise, relate to clauses in the traditional contracts.
2.7 Legal Opinion There is no clause requiring the provision of a legal opinion
relating to a Contractor who is not an individual or company
incorporated in Ireland.
3.9.3 Extensions and Part 1D of the Schedule does not provide scope for the
Additional Employer to specify extensions and additional requirements
Requirements in relation to insurances.
in the Schedule
3.9.9 Owner The minor works contract does not provide for the
Controlled insurance programme to be owner controlled.
Insurance
Programme
4.2.1(2) Supervisor The Contractor must appoint a supervisor to the site, but
unlike the traditional contracts the supervisor does not need
to be appointed on a full time basis
4.8 Value The minor works contract does not include a procedure for
Engineering value engineering.
4.9 Programme The content requirements for the programme are not as
detailed in the Minor Works Form. However, greater details
may be requested via the Works Requirements.
5.4 Sub-contractors Under the minor works contract if the Contractor intends to
and Specialists sub-contract part of the works, other than in accordance
with the contract, the Contractor should obtain the consent
of the Employer’s Representative (ER).
7.9 Access The minor works contract does not contain the traffic
obligations, set out in the traditional contracts, relating to the
transport of large loads.
7.11 Working Times There is no clause in the minor works contract relating to
the site working times of the Contractor’s personnel.
8.5 Rejection of The minor works contract does not contain a mechanism
Defects allowing the ER to reject the works if a defect deprives the
Employer of substantially the whole benefit of the works.
If the total number of site working days’ delay is less that the
number of site working days stated in the Schedule there
shall be no extension to the date for substantial completion.
9.7 Taking Over The minor works contract does not contain a provision
Part of the relating to the taking over of part of the works before
Works substantial completion by the Employer.
10.7.3 Delay Costs The traditional contracts contain a clause relating to the
scenario where, as a result of a compensation event the date
for substantial completion has been extended, so that there is
a period of 7 or more consecutive non-working days in the
time between the starting date and the date for
15 Case Study 1A
Completing the Schedule Part 1
Building Works
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
Building Works
Introduction
The contract is for the construction of a new civic office building for a local authority
Employer (LA County Council) on the site of its old fire station just outside of the
town centre. The LA CC has appointed consultants to design the building and the
form of contract to be used is the Public Works Contract for Building Works
Designed by the Employer.
The budget for the project is consistent with this cost plan and is extremely tight and
the County Manager has stipulated that cost certainty is of the utmost importance
and the project must be delivered within the cost plan.
Specifications and drawings have been drawn up for the Project by the Architect and
the Design Team. A Bill of Quantities has been prepared by the consultant
Chartered Quantity Surveyor.
The programme for the Project indicates that construction will commence on 29
November 2007 and be completed by 30 October 2009. It is intended that the
Council Chamber and accommodation for the elected representatives be completed
by 31 August 2009 as the existing premises have to be vacated by this date,
otherwise damages of €5,000 per week are payable to the landlord.
1. Archaeologist;
2. Asbestos removal;
3. Piling;
4. Curtain walling and glazing;
5. Lifts;
6. Mechanical and electrical installations;
7. Artwork;
8. Workstations and furniture.
A fairly detailed archaeological report on the proposed site has been prepared and
indicates some possible buried archaeological remains may exist from mid 1700s
which are not considered to be significant, however the planning conditions stipulate
that they should be fully recorded prior to their destruction or removal.
The site investigation carried out to date indicates nothing worrying from a
construction viewpoint. Surveys indicate that there are no utilities on the site.
The LA CC in the last substantial construction project carried out for it encountered
lengthy delays, including some three months due to exceptionally inclement weather
conditions. The conditions involved very heavy rainfall, coupled with high winds
which prevented progress.
The Task
Blank Schedule
SCHEDULE
PART 1
Details for sending notices under clauses 12 and 13 to the Employer are:
Address
………………………………………..
………………………………………..
………………………………………..
Address
………………………………………..
………………………………………..
………………………………………..
fax ………………………………………..
email ………………………………………..
Address
………………………………………..
………………………………………..
………………………………………..
Fax ………………………………………..
Email ………………………………………..
Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:
• Maximum adjustment to the Contract Sum for a single Change Order: €…………………………,
unless approved by the Employer
• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €…………………………, unless approved by the Employer
• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval
• The Employer will decide whether to accept or reject a value engineering proposal
• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment
• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment
• ….………………………………………………………………………………..
• ……………………………………………………………………………………
B Documents
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
If there is a Bill of Quantities, the method of measurement according to which it was prepared and
measurements are to be made is
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
except when any statement or general or detailed description of the work in the Contract shows to the
contrary.
Sub-clause 6.4
D Insurance
Clause 3
Insurance of the Works: minimum amount insured for professional fees ………% of
reinstatement cost (if none stated, 12.5%)
Minimum indemnity limits for public liability and employers’ liability Insurance:
• public liability insurance: €…………………………… for any one event, but this limit may
be on an annual aggregate basis for products liability, collapse, vibration, subsidence,
removal and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)
• employers’ liability insurance: €…………………………… for any one event. (If not
stated, €13,000,000)
• permitted exclusions from insurance of the Works and other Risk Items:
o use or occupation of the Works by the Employer except in connection with the
Works
o inventory losses
o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance
o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works
o mechanically propelled vehicles within the meaning of the Road Traffic Acts
o territorial limits
o offshore work
o insolvency
o contractual liability that would not apply in the absence of the contract
The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)
Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
…………………………………………………………………………………………………… and the
minimum sum for which this property is to be insured shall be €………………………
If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………
The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.
Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).
E Performance Bond
Sub-clause 1.5
A performance bond is/is not required. (Delete one. If none deleted, bond is required.)
The amount of the performance bond shall be ……………..% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and ……………..% of the initial Contract
Sum for the period stated in the form of bond in the Works Requirements. (If not stated, 25%
up to Substantial Completion, and 12.5% for 15 months after that.)
F Collateral Warranties
Sub-clause 5.5
Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:
H Early Completion
Sub-clause 9.6
The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)
I Defects Period
Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
Delay Compensation
Event
Event Event
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. A difference between the Contract value of the Works according
to the quantities and descriptions in the Bill of Quantities [taking
into account the method of measurement identified below when
it applies] and the Contract value of the Works described in the
Works Requirements, because the Bill of Quantities, when
compared with the Works Requirements: Yes
• includes an incorrect quantity or
• includes an item that should not have been included or
• excludes an item that should have been included or
• gives an incorrect item description
and the difference for an item in, or that should have been in, the
Bill of Quantities is more than €500
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes
19. The Contractor encounters on the Site unforeseeable ground
conditions or man-made obstructions in the ground, other than
Utilities Yes
20. The Contractor encounters unforeseeable Utilities in the ground
on the site Yes
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes
Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.
A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:
If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.
In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in
…………………………………………………………………………………………………………………..........
and any rates in the Pricing Document.
In sub-clause 9.4:
• the first threshold is ………………… Site Working Days of delay caused by Compensation
Events
• the second threshold is ………………… Site Working Days of delay caused by Compensation
Events
In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):
the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))
_________________________________________________________________________
_________________________________________________________________________
For purposes of clause 10.7, the Contractor is to tender (in part 2E):
L Payment Particulars
Clause 11
Minimum amount for interim payments, except release of retention, €………….…. (If none stated, there
is no minimum.)
When permitted by the Pricing Documents, up to _____% of the Contract value of unfixed Works Items
may be included in an interim payment. (If none stated, 90%).
M Price Variation
Sub-clause 10.8
Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).
Sub-clause 13.1.2
Sub-clause 13.2
The arbitration rules are the Public Works Arbitration Rules, 2007.
The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………
Worked Example
SCHEDULE
PART 1
Details for sending notices under clauses 12 and 13 to the Employer are:
Address
LA County Council
Four Courts
LA Town
County LA
Address
LA County Council
Four Courts
LA Town
County LA
fax ………………………………………..
email ………………………………………..
Address
50 The Heights
LA Town
County LA
Email [email protected]
Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:
• Maximum adjustment to the Contract Sum for a single Change Order: €5,000, unless approved
by the Employer
• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €30,000, unless approved by the Employer
• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval
• The Employer will decide whether to accept or reject a value engineering proposal
• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment
• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment
• ….………………………………………………………………………………..
• ……………………………………………………………………………………
B Documents
12345-WR-001
12345-BQ-001
If there is a Bill of Quantities, the method of measurement according to which it was prepared
and measurements are to be made is ARM3, 2003 except when any statement or general or
detailed description of the work in the Contract shows to the contrary.
Sub-clause 6.4
D Insurance
Clause 3
Insurance of the Works: minimum amount insured for professional fees 12.5% of reinstatement
cost (if none stated, 12.5%)
Minimum indemnity limits for public liability and employers’ liability Insurance:
• public liability insurance: €13,000,000 for any one event, but this limit may be on an
annual aggregate basis for products liability, collapse, vibration, subsidence, removal
and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)
• employers’ liability insurance: €13,000,000 for any one event. (If not stated,
€13,000,000)
• insurance of Works and other Risk Items: €10,000,000 (If not stated, €10,000)
• public liability: €10,000,000 in respect of property damage only (If not stated, €10,000).
There shall be no excess for death, injury or illness.
• permitted exclusions from insurance of the Works and other Risk Items:
o use or occupation of the Works by the Employer except in connection with the
Works
o inventory losses
o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance
o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works
o mechanically propelled vehicles within the meaning of the Road Traffic Acts
o territorial limits
o offshore work
o insolvency
o contractual liability that would not apply in the absence of the contract
The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)
Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
Artworks and the minimum sum for which this property is to be insured shall be €100,000
If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………
The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.
Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).
E Performance Bond
Sub-clause 1.5
A performance bond is/is not required. (Delete one. If none deleted, bond is required.)
The amount of the performance bond shall be 12.5% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and 6.25% of the initial Contract Sum for
the period stated in the form of bond in the Works Requirements. (If not stated, 25% up to
Substantial Completion, and 12.5% for 15 months after.)
F Collateral Warranties
Sub-clause 5.5
Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:
Section:
Council Chamber and
30 June 2009 €850 per day 50%
accommodation for elected
members
H Early Completion
Sub-clause 9.6
The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)
I Defects Period
The initial Defects Period is 12 months from the date of Substantial Completion of the Works
Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
Delay Compensation
Event
Event Event
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes No
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. A difference between the Contract value of the Works according
to the quantities and descriptions in the Bill of Quantities [taking
into account the method of measurement identified below when
it applies] and the Contract value of the Works described in the
Works Requirements, because the Bill of Quantities, when
compared with the Works Requirements: No No
• includes an incorrect quantity or
• includes an item that should not have been included or
• excludes an item that should have been included or
• gives an incorrect item description
and the difference for an item in, or that should have been in, the
Bill of Quantities is more than €500
18. An item of value or archaeological interest or human remains is
found on the Site, and it was unforeseeable Yes Yes
Delay Compensation
Event
Event Event
19. The Contractor encounters on the Site unforeseeable ground
conditions or man-made obstructions in the ground, other than
Utilities Yes No
20. The Contractor encounters unforeseeable Utilities in the ground
on the site Yes No
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes No
Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.
A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:
If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.
In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in UK Civil
Engineering Contractors Association Schedules of Dayworks carried out incidental to contract work
August 2003 reprint. (Note: Only Schedule 4 will apply). (Rates will be considered to be in euro) and
any rates in the Pricing Document.
In sub-clause 9.4:
• the first threshold is 21 Site Working Days of delay caused by Compensation Events
• the second threshold is 20 Site Working Days of delay caused by Compensation Events
In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):
the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
YES
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))
_________________________________________________________________________
_________________________________________________________________________
For purposes of clause 10.7, the Contractor is to tender (in part 2E):
L Payment Particulars
Clause 11
Minimum amount for interim payments, except release of retention, €50,000. (If none stated,
there is no minimum.)
When permitted by the Pricing Documents, up to 75% of the Contract value of unfixed Works
Items may be included in an interim payment. (If none stated, 90%).
M Price Variation
Sub-clause 10.8
Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).
Sub-clause 13.1.2
Failing agreement, the conciliator will be appointed by the President of the Royal Institute of the
Architects of Ireland.
Sub-clause 13.2
The arbitration rules are the Public Works Arbitration Rules, 2007.
The person or body to appoint the arbitrator (if not agreed by the parties) is President of the
Royal Institute of the Architects of Ireland.
16 Case Study 1B
Completing the Schedule Part 1
Civil Works
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
Section A includes the expected contact and correspondence details for the parties
and is similar to other forms.
The limit on authority of the ER to order any one variation has been set at €50,000
and the limit on the number of instructions changing the works requirement is set at
100. The Employer's approval is required to exceed either limit.
There has been no Bill of Quantities produced, but the Employer requires in Section
A that any Bill submitted by tenderers in support of their tender price should be
measured in accordance with the Method of Measurement for Roadworks of the
NRA.
In Section C, the Employer opts not to seek any copyright in the contract
documents.
In Section D, insurance limits have been selected at €13,000,000 for both EL and
PL insurance. PI insurance is selected at a level of €6,200,000 any one event and
an excess of €25,000 is deemed tolerable by the Employer in each case. PI
insurance will be kept in place for six (6) years from the date of Substantial
Completion and it needs to be in place from the earliest date that design work takes
place on the Project. These limits should be set with advice from Insurance
Specialists.
The Employer in this case has opted to have the Contractor extend insurance for the
Section which is to be completed early, until the Substantial Completion of the whole
of the Works.
In Section G, the Employer has required that the section of carriageway from
Ch .0m to Ch. 6330m, including the junctions at both ends, must be available to take
traffic at an earlier Substantial Completion date for that section and liquidated
damages have separately been calculated for this element and for the whole of the
Works as shown.
In Section H, the Employer has opted not to take on himself an obligation to issue a
Certificate of Substantial Completion if either the Works, or the nominated Section,
are completed before the scheduled dates.
The Section J Delay and Compensation events listing is different for the Contractor-
designed form of contract, as one might expect. The Employer has opted to pay
delay costs associated with archaeological finds, in the light of preparatory
investigative work, however he requires the Contractor to carry the risk associated
with Utilities relocation delay.
The First Threshold, for the purposes of sub-clause 9.4, has been set at 40 Site
Working Days and the Second Threshold has also been selected as 40 Site Working
Days. The Employer has opted to pay the tendered amount in the Schedule Section
2E as the preferred way of handling costs of delay due to Compensation Events.
As regards the weather event data entries in Schedule J, the Guidance Notes
discuss a 10 Year Return Period as the appropriate level of risk to transfer to the
Contractor in this respect. This has a precise hydrological meaning, as the event
which, in a long record, is likely to be exceeded once in 10 years. It is not equivalent
to the worst event which occurred within the past decade, for example. In a project
lasting perhaps 24-36 months at construction stage, there is a significant probability
of the 10 year event occurring, be that rainfall or wind or temperature. Furthermore,
it is not impossible (although the probability is low) that a 10 Year Return Period
event could occur twice within a construction period. The Contractor carries that
risk.
Note that the Schedule requires data for calendar months to be inserted. The
Contractor also carries the risk associated with exceptional weather events (of 10
Year Return Period or greater) which straddle two calendar months, without actually
producing 10 Year Return Period totals in either calendar month.
As regards sub-clause 10.6.3, the rates to be used to assess the cost of plant are
those used in the UK Civil Engineering Contractors Association "Schedule of
Dayworks carried out incidental to Contract Works" where the Sterling rates are
deemed to be converted to euro by multiplying by a factor of 1.27.
Blank Schedule
SCHEDULE
PART 1
Details for sending notices under clauses 12 and 13 to the Employer are:
Address
………………………………………..
………………………………………..
………………………………………..
Address
………………………………………..
………………………………………..
………………………………………..
fax ………………………………………..
email ………………………………………..
Address
………………………………………..
………………………………………..
………………………………………..
Fax ………………………………………..
Email ………………………………………..
Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:
• Maximum adjustment to the Contract Sum for a single Change Order: €…………………………,
unless approved by the Employer
• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €…………………………, unless approved by the Employer
• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval
• The Employer will decide whether to accept or reject a value engineering proposal
• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment
• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment
• ….………………………………………………………………………………..
• ……………………………………………………………………………………
B Documents
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
If there is a Bill of Quantities, the method of measurement according to which it was prepared and
measurements are to be made is
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
………………………………………..………………………………………..…………………………..
except when any statement or general or detailed description of the work in the Contract shows to the
contrary.
Sub-clause 6.4
D Insurance
Clause 3
Insurance of the Works: minimum amount insured for professional fees ………% of
reinstatement cost (if none stated, 12.5%)
Minimum indemnity limits for public liability and employers’ liability Insurance:
• public liability insurance: €…………………………… for any one event, but this limit may
be on an annual aggregate basis for products liability, collapse, vibration, subsidence,
removal and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)
• employers’ liability insurance: €…………………………… for any one event. (If not
stated, €13,000,000)
• permitted exclusions from insurance of the Works and other Risk Items:
o use or occupation of the Works by the Employer except in connection with the
Works
o inventory losses
o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance
o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works
o mechanically propelled vehicles within the meaning of the Road Traffic Acts
o territorial limits
o offshore work
o insolvency
o contractual liability that would not apply in the absence of the contract
The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)
Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
…………………………………………………………………………………………………… and the
minimum sum for which this property is to be insured shall be €………………………
If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………
The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.
Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).
E Performance Bond
Sub-clause 1.5
A performance bond is/is not required. (Delete one. If none deleted, bond is required.)
The amount of the performance bond shall be ……………..% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and ……………..% of the initial Contract
Sum for the period stated in the form of bond in the Works Requirements. (If not stated, 25%
up to Substantial Completion, and 12.5% for 15 months after that.)
F Collateral Warranties
Sub-clause 5.5
Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:
H Early Completion
Sub-clause 9.6
The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)
I Defects Period
Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. Not used
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. Not used
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
Delay Compensation
Event
Event Event
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. Not used
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes
19. Not used
20. Not used
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes
Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.
A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:
If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.
In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in
………………………………………………………………………………………………………………………...
and any rates in the Pricing Document.
In sub-clause 9.4:
• the first threshold is ………………… Site Working Days of delay caused by Compensation
Events
• the second threshold is ………………… Site Working Days of delay caused by Compensation
Events
In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):
the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))
_________________________________________________________________________
_________________________________________________________________________
For purposes of clause 10.7, the Contractor is to tender (in part 2E):
L Payment Particulars
Clause 11
Minimum amount for interim payments, except release of retention, €………….…. (If none stated, there
is no minimum.)
When permitted by the Pricing Documents, up to _____% of the Contract value of unfixed Works Items
may be included in an interim payment. (If none stated, 90%).
M Price Variation
Sub-clause 10.8
Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).
Sub-clause 13.1.2
Failing agreement, the conciliator will be appointed by ………………………………….
Sub-clause 13.2
The arbitration rules are the Public Works Arbitration Rules, 2007.
The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………
Worked Example
SCHEDULE
PART 1
Details for sending notices under clauses 12 and 13 to the Employer are:
Address
County Buildings
Casement Street
Address
County Buildings
Casement Street
County of Oldtown
Email [email protected]
Address
Email [email protected]
Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:
• Maximum adjustment to the Contract Sum for a single Change Order: €5,000, unless approved
by the Employer
• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period: €75,000.
• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval
• The Employer will decide whether to accept or reject a value engineering proposal
• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment
• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment
• ….………………………………………………………………………………..
• ……………………………………………………………………………………
B Documents
12345-PD-001
If there is a Bill of Quantities, the method of measurement according to which it was prepared
and measurements are to be made is
except when any statement or general or detailed description of the work in the Contract shows
to the contrary.
Any BoQ submitted should be measured in accordance with the Method of Measurement for
Roadworks by the NRA.
Sub-clause 6.4
D Insurance
Clause 3
Insurance of the Works: minimum amount insured for professional fees 7% of reinstatement
cost (if none stated, 12.5%)
Minimum indemnity limits for public liability and employers’ liability Insurance:
• public liability insurance: €13,000,000 for any one event, but this limit may be on an
annual aggregate basis for products liability, collapse, vibration, subsidence, removal
and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)
• employers’ liability insurance: €13,000,000 for any one event. (If not stated,
€13,000,000)
• insurance of Works and other Risk Items: €25,000 (If not stated, €10,000)
• public liability: €25,000 in respect of property damage only (If not stated, €10,000).
There shall be no excess for death, injury or illness.
• permitted exclusions from insurance of the Works and other Risk Items:
o use or occupation of the Works by the Employer except in connection with the
Works
o inventory losses
o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance
o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works
o mechanically propelled vehicles within the meaning of the Road Traffic Acts
o territorial limits
o offshore work
o insolvency
o contractual liability that would not apply in the absence of the contract
The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)
Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
Artworks and the minimum sum for which this property is to be insured shall be €100,000
If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………
The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.
Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for 6 years after Substantial Completion of the Works is certified
by the Employer's Representative. If required, the minimum indemnity limit for professional
indemnity insurance shall be €6,200,000 for each and every claim or series of claims arising
from the same originating cause/annual aggregate limit (delete one). The maximum excess
shall be €25,000 (if none stated, €50,000).
E Performance Bond
Sub-clause 1.5
A performance bond is/is not required. (Delete one. If none deleted, bond is required.)
The amount of the performance bond shall be 15% of the initial Contract Sum up to certification
of Substantial Completion of the Works, and 10% of the initial Contract Sum for the period
stated in the form of bond in the Works Requirements. (If not stated, 25% up to Substantial
Completion, and 12.5% for 15 months after.)
F Collateral Warranties
Sub-clause 5.5
Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:
H Early Completion
Sub-clause 9.6
The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)
I Defects Period
The initial Defects Period is 12 months from the date of Substantial Completion of the Works
Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes
Delay Compensation
Event
Event Event
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. Not used
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes Yes
19. Not used
20. Not used
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes No
Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.
A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:
If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.
In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in UK Civil
Engineering Contractors Association Schedules of Dayworks Carried Out Incidental to Contract Work
August 2003 reprint (Note: Only Schedule 4 will apply) (Rates will be considered to be in Euro) and any
rates in the Pricing Document.
In sub-clause 9.4:
• the first threshold is 40 Site Working Days of delay caused by Compensation Events
• the second threshold is 40 Site Working Days of delay caused by Compensation Events
In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):
the amount stated in Part 2E of this Schedule as the Contractor's daily rate of
YES
delay cost
the expenses (excluding profit and loss or profit) unavoidably incurred by the
Contractor
_________________________________________________________________________
_________________________________________________________________________
For purposes of clause 10.7, the Contractor is to tender (in part 2E):
L Payment Particulars
Clause 11
Minimum amount for interim payments, except release of retention, €150,000. (If none stated, there is
no minimum.)
When permitted by the Pricing Documents, up to 90% of the Contract value of unfixed Works Items may
be included in an interim payment. (If none stated, 90%).
M Price Variation
Sub-clause 10.8
Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV2 shall apply).
Sub-clause 13.1.2
Failing agreement, the conciliator will be appointed by the President of Engineers Ireland.
Sub-clause 13.2
The arbitration rules are the Public Works Arbitration Rules, 2007.
The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………
17 Case Study 2
Tender Evaluation
Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual
CASE STUDY 2
Tender Evaluation
Introduction
Tenders have been invited from tenderers under the Restricted Procedure for the
construction of the new local authority headquarters building for LA County Council.
The following values were inserted in Section 12.5 of the Instructions to Tenderers
for determining the comparative costs of tenderers:
The Task
SCHEDULE PART 2
TENDERER NR 1
A Communications
Sub-clause 4.14
The details for sending notices under clause 12 or 13 to the Contractor are:
Address
Build Ex Ltd
1 The Heights
LA Town
Co LA
Address
Build Ex Ltd
1 The Heights
LA Town
Co LA
Email [email protected]
The Contractor’s agent in the Republic of Ireland for service of legal process is:
Address
…………………………………………
…………………………………………
…………………………………………
Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).
Sub-clause 1.6
The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.
(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)
C Works Proposals
The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):
Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons
All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If either of the above is left blank, read as zero.)
The Contractor’s tendered rate of delay costs is: €5,000 excluding VAT per Site Working Day. (If
blank, read as zero.)
If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:
€ c
Sub-total € 34,480,000 00
SCHEDULE PART 2
TENDERER NR 2
A Communications
Sub-clause 4.14
The details for sending notices under clause 12 or 13 to the Contractor are:
Address
Build IT Ltd
20 The Heights
LA Town
Co LA
Address
Build IT Ltd
20 The Heights
LA Town
Co LA
Fax 04 6753896
Email [email protected]
The Contractor’s agent in the Republic of Ireland for service of legal process is:
Address
…………………………………………
…………………………………………
…………………………………………
Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).
Sub-clause 1.6
The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.
(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)
C Works Proposals
The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):
Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons
All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)
The Contractor’s tendered rate of delay costs is: €3,500 excluding VAT per Site Working Day. (If
blank, read as zero.)
If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:
€ c
Sub-total € 34,500,000 00
SCHEDULE PART 2
TENDERER NR 3
A Communications
Sub-clause 4.14
The details for sending notices under clause 12 or 13 to the Contractor are:
Address
Address
Fax …………………………….
Email …………………………….
The Contractor’s agent in the Republic of Ireland for service of legal process is:
Address
…………………………………………
…………………………………………
…………………………………………
Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).
Sub-clause 1.6
The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.
(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)
C Works Proposals
The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):
Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons
All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)
The Contractor’s tendered rate of delay costs is: €6,000 excluding VAT per Site Working Day. (If
blank, read as zero.)
If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:
€ c
Sub-total € 34,350,000 00
SCHEDULE PART 2
TENDERER NR 4
A Communications
Sub-clause 4.14
The details for sending notices under clause 12 or 13 to the Contractor are:
Address
Address
Fax 06 583345
Email [email protected]
The Contractor’s agent in the Republic of Ireland for service of legal process is:
Address
…………………………………………
…………………………………………
…………………………………………
Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).
Sub-clause 1.6
The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.
(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)
C Works Proposals
The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):
Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons
All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)
The Contractor’s tendered rate of delay costs is: €4,600 excluding VAT per Site Working Day. (If
blank, read as zero.)
If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:
€ c
Sub-total € 34,480,000 00
Materials
€150,000 Percentage addition to this for materials
Plant
€75,000 Percentage addition to this for plant
Delays
50 Days delay @ delay cost per day
VAT @ 13½%
Materials
€150,000 Percentage addition to this for materials 25% 37,500 5% 7,500 5% 7,500 2% 3,000
Plant
€75,000 Percentage addition to this for plant 10% 7,500 5% 3,750 5% 3,750 2% 1,500
Delays
50 Days delay @ delay cost per day €6,000 300,000 €5,000 250,000 €4,600 230,000 €3,500 175,000
18 Case Study 3
Some Contract Administration Issues
This case study refers to the project covered by Case Studies 1 and 2, the LA
County Council Civic Offices.
Three letters have been sent from the Contractor to the Employer's Representative
as follows:
Supplementaries
In the case of Letter Nr 1 What would the position have been if the Archaeologist
had been directly engaged by the Employer?
LETTER NR 1
BUILD IT LTD
20 The Heights
LA Town
Co LA
15 January 2008
Dear Sirs
I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 6 December 2007.
The Works Requirements indicate that the novated Specialist archaeological sub-
contractor would carry out its archaeological excavations during the period mid
November to mid December 2007 and we had programmed for this period and for the
attendance required. The archaeological activities will now not be completed until mid
January 2008, a whole month of delay because:
1. progress is significantly slower than had been anticipated due to the level of
detailed recording required no doubt reflecting the archaeological interest of
the buried ruins;
2. the week long exceptionally poor weather with very heavy snow during the
period 28 November to 4 December 2007 which meant that the
archaeologists could not get on to site, with the blanket of snow the ground
could not be seen, the site was unsafe and moreover the ground was too
hard to excavate because of ground frost and subsequently the effect of the
melting snow was that the excavations had to be pumped out to enable the
archaeologists work and the photographic record be generated. None of this
was anticipated.
This delay has caused a one month or 21 site working days to the Date for
Substantial Completion date as follows:
We consider that the facts of this matter have been well aired at recent site meetings and during
your site visits and that no further information should be necessary to enable us to demonstrate
our entitlement, or for you to make a decision. If however you require further information,
please do not hesitate to contact me.
Yours faithfully
Peter Rock
Contracts Manager
BUILD IT LTD
1. The Archaeology Specialist had previously indicated he would have four archaeologists
working on the Project in the event he only had two;
3. There was snow (50mm deep) and air temperatures below 0° Celsius during the period
28 November to 4 December 2007 and during this period the Archaeology Specialist
could not carry out any work;
4. The Employer's Representative has determined that the bad weather is not a weather
event;
5. After the snow melted, the Contractor had to pump out the excavations and provide
some additional earthwork support to enable the Archaeology Specialist continue
working safely and make up for the lost time.
LETTER NR 2
BUILD IT LTD
20 The Heights
LA Town
Co LA
30 January 2008
Dear Sirs
I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 17 January 2008.
All of the borehole logs in the site investigation reports indicate that rock is to be
encountered some 4-6m below existing ground level and below the formation level of
the proposed basement car park. In the event, significant outcrops of hard granite
rock have been encountered at 1.5m below the existing ground level and the
estimated quantity of rock to be removed is some 2,000cu m. This quantity has been
measured and agreed between Employer’s Quantity Surveyor and our Quantity
Surveyor. These outcrops are scattered throughout the site and it is unrealistic to
consider advancing parts of the works until these have been excavated.
This delay has caused a 51 working day delay to progress on site and the entitlement
for our extension of time is calculated as follows:
Less
We consider that the facts of this matter have been well aired at recent site meetings, during
your site visits and in discussions on site so no further information should be necessary to
enable us to demonstrate our entitlement, or for you to make a decision. If however you require
further information, please do not hesitate to contact me.
Yours faithfully
Peter Rock
Contracts Manager
BUILD IT LTD
1. The Contractor has indeed encountered hard granite rock on the site and the quantity is
in the region of 2,000cu m;
2. There was no indication of this rock in any of the site investigation reports and the site
investigation reports are found to be factually correct for the boreholes and trial pits that
were sunk;
3. The Contractor's estimate of the delay period of 51 working days has been examined by
the ER and is considered reasonable;
4. The Contractor is doing everything possible to mitigate the effects of the delay.
LETTER NR 3
PROPOSED INSTRUCTION
BUILD IT LTD
20 The Heights
LA Town
Co LA
15 September 2008
Dear Sirs
I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 1 August 2008.
The building has been designed to support and an additional 2nr floors and as a
result of a policy decision to relocate some staff from a government agency to the
building 1 nr additional floor will now be built. Planning and fire safety cert approval in
respect of this change have now been secured.
Preliminaries €420,000
—————
Sub-total €4,445,000
We estimate that delay will delay progress by some 150 days and as this is caused by
a compensation event and the programme contingency has been fully used up we
request that the Date for Substantial Completion be further extended to reflect this.
We also wish to put on record the point that we have raised at our recent meetings
that 150 days can only be our estimate of the delay at this stage – we will revert when
the exact delay is known.
Yours faithfully
Peter Rock
Contracts Manager
BUILD IT LTD
2. The Quantity Surveyor has agreed the quantities associated with the change;
3. The measured work has been priced at the rates in the Pricing Document and this has
been agreed to by the Quantity Surveyor;
4. The programme has been reviewed and the 150 days is considered reasonable,
however the original scope is still to be completed by the original date;
19.1 What of risks other than those listed in Schedule Part 1, Section K? If
they are to be the Contractors’, what is the mechanism of allocation
in the Contract Documents?
Part K of the Schedule Part 1 allocates certain risks to the Contractor, either by
the prescribed allocation, or by election of the Employer where this discretion is
permitted. Any other risks are deemed to be the Contractors’ risks, except
those giving rise to a change in the Works Requirements. The identification and
evaluation of risks would be part of the Risk Assessment and Management
process in the development of the Works Requirements.
Risks which materialise and require change in the Works Requirements are at
the Employers’ risk, accordingly robustness of risk assessment and evaluation,
and effective description and transfer in the Works Requirements are important
in the protection of the fixed price lump sum tender.
19.2 Is it intended that there will be individual items for risk in a Bill of
Quantities?
There should be separate items in the BoQ to allow for pricing of the risks listed
in Section K of Schedule Part 1 which are allocated to the Contractor as the
Method of Measurement may require.
Those other risks (other than those in Section K) are allocated by the
appropriate clauses of the Works Requirements, and the cost of providing for
them is included generally in the rates in the BoQ.
19.3 Does a project budget get revised as decisions are made on risk
transfer?
Risks that are not transferred to the Contractor, are retained by the Employer.
Accordingly decisions which transfer an appropriate risk into the contract scope,
essentially move that provision into the contract, across from the Employers’
budget for non contract items. These transfers represent movements of value
within an overall budget for contract- and non-contract items, which budget
should not change when the overall scope of work and timeframe do not
change. Where the risk transfer is well defined, well prepared and appropriate,
this transfer is a good value for money decision, that reduces the cost of a
project, compared to one where risks are not appropriately allocated. Guidance
on this issue can be found in the Guidance Note on Budget Development in the
Capital Works Management Framework.
19.4 Does the Contractor get paid the value of the risk item if the risk
does not arise?
Where work is proceeded with, and a risk associated with that work has been
transferred and priced, but the risk does not materialise, the Contractor is
entitled to be paid the cost of his provision for that risk, on the basis that, had
the risk occurred, that would have been his only entitlement for it, apart from
any reliefs specified under Schedule 1 Section K. Where an element of work is
not being proceeded with, then the contract sum would be reduced accordingly,
and risk associated with that element, and priced in the rates for it would be
credited out automatically in that calculated reduction.
19.8 The values selected for the contingent items in the MEAT example
may well result in loading of the bid rates in the Tender, especially
where, because of the choice of notional items below the Tender
Sum, there is little impact on the MEAT Comparative Cost?
These values are selected by the client and should be the expected value of the
item in question, having regard to professional judgement of the client or his
consultant and previous experience on similar projects. The expected value is
not so low as to encourage loading of rates and is not so high as to pack the
MEAT with contingent items.
19.9 If you start on an assumed Budget of less than €5m, working on the
Minor Works Form of Contract, and you drift over the limit as
tenders are received, do you have to change the form of contract to
be used?
Good budgeting should not leave you in this position, but you would have to
stay with the procurement choice originally made and run with the tendered
contract.
19.10 If you take tenders on one Form and found you had to use another,
could this be negotiated?
No form of negotiation on fundamental matters, particularly price, may take
place in the open or restricted procedure.
19.11 If the estimate is just under €5m can you opt to use the Main Form?
Yes, this option is available where it is appropriate to do so. One should
probably opt for the main contract form in the case stated.
19.12 If the second option is chosen on delay, i.e. where no rate has been
tendered, no delay element in the MEAT calculation ensues?
Where daily rates are not tendered, the Employer pays only for the cost of delay
actually incurred. This is not therefore an issue for assessment in the MEAT
calculation.
19.13 Will the Employer have to create a rule for rebalancing items in the
BOQ to ensure arithmetic errors are corrected to maintain the
lump sum bottom line as fixed? Are the potential number of
variables not very large, when the bottom line is being held? Should
there not be a commonality of approach because precedent will
apply across the board anywhere these contracts are used?
The approach on correction of tenders is set out in the Guidance Note in
Section 2.7.3. The example given in the GN related to correction of errors in
calculating VAT is also relevant. The fixed price lump sum tender total remains
unchanged in any correction of arithmetic error in the BoQ.
19.15 If the Tender wasn’t signed, or the Tender Sum wasn’t transferred,
from the BoQ to the Tender Form correctly, is the tender
disqualified?
It depends on the stated position on this point in the Instructions to Tenderers.
In the absence of a clear rule requiring disqualification, the Contracting
Authority has discretion. Is it a proportionate response to reject a tender for
such an oversight? It should be drafted so that no hair-trigger rejection
responses arise on matters which can easily be clarified without risk to
transparency or equal treatment.
19.18 Why not accept an offer of a "free" parent company guarantee in lieu
of the Bond?
Such an approach is contrary to good practice as described in the Guidance
Note. It should be remembered that problems with a contractor often have
their roots in a problem with the Parent Company itself, so that the Parent
Company Guarantee is not a robust guarantee in such circumstances. Refer to
the Guidance Note at Section 2.3.2.
19.19 If there’s an expiry date on a Bond, can you not have a position
where you threaten calling in Bond in order to get a Bond
extended?
It is safer to have a Bond whose expiry date is predicated upon an event such as
Substantial Completion (say, 15 months after its issue) in which case the
situation outlined is unlikely to arise. The difficulty in threatening to call in a
bond such as the Performance Bond to be provided by the Contractor under
the contract is that a call is only permitted where the Contractor is in breach or
has its obligation to complete terminated.
The Bid Bond is a mechanism which can be used if there is a concern that a
tenderer might not honour its tender or where a particular contract is
absolutely essential to a larger project and any withdrawal by the successful
tenderer would cause substantial losses etc. [see Guidance Note at Section
2.3.1.].
19.22 What if there is a design problem with the Works after six years and
before twelve years and the Contract has been executed under seal?
Where a contract has been executed under seal the time within which the
Employer may sue for any breach is independent of the date of the contract
execution but is referable to the date of the breach of contract itself. Thus in
the case outlined, the Employer could sue the relevant party for breach of
contract, within twelve years from the date of the breach itself. This is likely to
be the date that the actual defective design work was carried out although the
final date can sometimes be different, for instance, the date by which the
defective design could have been rectified by the guilty party.
Consultants will need ongoing annual renewal of PI but that’s really as far as
practicalities permit. There’s little point in pursuing a consultant for failing to
maintain annual cover out in year ten. If it’s not there, its not there, and the fact
of that is that he may not be worth pursuing in the absence of PI cover.
One should also keep sight of the fact that we are only speaking here of actions
for breach of contract. An Employer who has suffered loss as a result of
defective design could also proceed under the tort of negligence and would have
six years from when the damage actually occurred (not when it was discovered)
within which to sue.
19.31 Can you ask one tenderer to provide a Bid Bond and not others?
No
19.39 If a structure serves two purposes, must it be fit for both purposes?
This will depend upon the purpose of the structure under the Contract. It
would be most unlikely for a structure that has two purposes not to be required
to meet the requirement for both.
19.42 Does there need to be Model Forms included with each contract?
Reference to "Model Form 8" would be unambiguous, but it might be useful if
there was a pro-forma insertion checklist.
19.44 With respect to the Form of Tender, in the quasi-contract that exists
where a tender will be examined once it is validly submitted, where
is the Consideration for agreement to keep open the tender?
The consideration is generally regarded as the willingness of the contracting
authority to consider the tender in question.
19.49 If rates have no real meaning in relation to the lump sum, then is it
not open to possible abuse by Tenderers sprinkling mischievous
rates all over the place in a Pricing Document, all aimed at securing
later advantage at Change Orders?
It is part of tender assessment to check that rates in the BoQ reflect the value of
the work item, in so far as it is possible to do this. Rebalancing of rates may be
required to ensure that the scenario postulated in the question is avoided,
maintaining the tender total fixed, in accordance with the Guidance Note.
QUESTIONS ON SPECIALISTS
19.53 Can ER ask that a Specialist be removed from the Site or its contract
terminated?
The Specialist has the legal status of Contractors Personnel so you have the
option in accordance with the terms of the Contract. Thus at sub-clause 5.6, it
is provided that the ER may request the removal of any Contractor’s Personnel
from the Site for reasons of negligence, incompetence or that their presence is
not conducive to safety, health or good order
19.55 Why would a Contractor propose Specialists, why not just use them
as subcontractors?
If Employer nominates particular work categories as specialist areas, over which
he wishes to exercise a minimum quality threshold type of control, he may
designate these as Specialist areas, and the Tenderer has to make nominations.
Novation in this manner would be exceptional, rather than the norm. The
Employer, in preparing his contract with the Specialist to be novated, would
research the market to determine what minimum amendments to the standard
form might have to be made to attract interest from the Specialist market.
Having got unqualified tender responses, he then concludes his contract with the
Specialist. The Main Contractor is instructed that he must accept this novation,
in the Main Contract on the standard forms of contract without amendment. He
must then take a view on whatever risk premium he needs to neutralise the
effect to him of any special terms in the novated contract, so that he fully
addresses this in his own price.
19.62 The risk described in Part K No 8 of Schedule Part 1 uses the term
"Employers personnel". This could potentially mean Planning
Officers for a Local Authority. If they "interfere" in defence of a
planning permission or statutory duty, is this a compensation event?
There could conceivably be an argument that officers of a Local Authority not
connected with the project in question did interfere with the Contractor.
However, it is most unlikely that this would occur in such away as to give rise to
a claim. The inclusion of a Planning Permission within the general scope of the
term "Consent" creates an obligation on the Contractor to comply with this
consent. Other legislation, that the Employer may have a duty to check
compliance upon, is also included under "Law". If the Employer intervenes in his
capacity as designated enforcement body in relation to a statutory obligation, he
would be entitled to do so and there would be no entitlement to compensation
arising from this.
19.65 Does the figure entered under the second threshold on the
programme contingency in Schedule Part 1 have to be a cumulative
figure with respect to the first threshold?
No, the second threshold is not cumulative, it stands as a selection in itself
without regard to the numerical value selected for the first threshold.
GENERAL QUESTIONS
where the main services are taken to a terminal point outside a civil/building
works shell, and the shell is sized to accept the range of plant items likely to be
offered, and a phased handover allows the item to be installed and
commissioned on its own programme. This will allow the plant item to be
incorporated, without expensive consequential effects influencing other areas of
the contract, and without extra cost arising through Change Orders.
19.70 Insurance thresholds look the same in both the Minor Works and
the other Forms of Contract. Is this intended by the insurance
expertise advising on Conditions of Contract development?
Yes.
19.72 Does the €5m limit on the Minor Works Contract include VAT?
Yes, it is VAT inclusive.
19.75 What does Risk 12 in Section K of Schedule Part 1 refer to, in the
context of Clause 3.2?
If the Works suffer damage due to matters which are at the Contractor’s risk
under sub-clause 3.2 before Substantial Completion the Contractor is entitled to
an extension of time for completion (subject to clauses 9 and 10) but the event
is not a compensation event and he is not entitled to an adjustment of the
Contract Sum.
19.76 How far out do access routes go? If vehicle is taxed and licensed, is
he not entitled to use all roads?
Yes he is. However as between himself and the Employer, he is responsible for
ensuring that he can gain access via all intended access routes. He is also obliged
to take reasonable steps to see that the Site traffic obeys the law and does not
cause nuisance.
compliance with the instruction of a PSDP or PSCS does not give rise to an
increase in the cost of the contract, or an extension of time.
19.86 Clause 4.8.1 – Any Value Engineering proposal cannot increase the
Contract Sum. Does this preclude Client from accepting a beneficial
Whole Life Cost proposal, which increased the Contract Sum?
Could this be handled by Change Order?
Where the ITT permits variants, and subject to any conditions attaching to such
variants being met, it is possible at Tender Stage to accept variants which have a
Whole Life Cost advantage. Once the Contract is signed, it is intended that value
engineering proposals ought to be confined to reductions in the contract cost,
or expediting the date for Substantial Completion.
19.87 Under Clause 4.8.2, is it not advisable to have PSCS/PSDP certify that
no problem exists as part of considering a value engineering
proposal.
It would certainly be advisable to have the PSCS/PSDP involved so that he can be
aware of what is proposed, and so that he can agree that the change does not
compromise the position on safety, or introduce any issues outside the agreed
value engineering proposal. Clause 2.4.4 is now also relevant to this issue.
19.89 Does Clause 4.9.2 and 4.9.3 effectively permit Contractor to revise
dates for Substantial Completion, or at least set up acceleration
issues?
They require him to revise his programme i.e. his intended date for completing
the Works when this becomes necessary because of Delay Events etc. They do
no more than provide information to the ER and Employer in relation to the
state of progress of the Works at any given point in time. If the Contractor
seeks to use the programme to support claims he will have to formally make the
claim under Clause 10 and evidence it etc.
19.90 If the Contractor is potentially going to be paid Labour PVC after the
Base Date, why is there no provision to check that people are being
paid as required under PV1 or PV2? Clause 5.3.3.A specifically
excludes checking this point under that Clause?
Model Form 15 provides that the contractor must certify he is paying according
to legal obligations. He has this obligation in any case. The PVC provision says
what contract relief he will get, and this is a separate issue from his obligation to
pay Social Partnership rates, which he is obliged to do.
The PVC provision is a risk valuation and compensation factor, the obligation to
pay under Clause 5.3.3(a) is separate and checking compliance with this latter
obligation, which is all that the Clause can require.
19.93 Specialists Clause 5.4 – Clause 5.4.6 appears to give much greater
latitude to offer replacements and effectively negates Clause 5.4.5?
Clause 5.4.5 describes circumstances where a Specialist is not to be continued,
and Clause 5.4.6 is intended to show how a replacement is to be managed when
5.4.5 is used.
19.94 Clause 9.1.2 Before Start Date, does the Employer need sight of Tax
Clearance Cert, etc. Why is this left out of items listed in the Sub-
Clause?
These can go into the Letter of Intent under the indicated "catch all" clause at
the end.
19.95 Clause 9.1.2 – If within 20 days between Start Date and Letter of
Acceptance, he fails to provide any of the items listed, what is the
position?.
If he doesn’t provide the items, he’s in breach of contract. "Shall" under Clause
9.1.2 is quite strict. The Contract entitles the Employer to terminate the
Contractor’s obligation to complete if he does not remedy the breach within 14
days after receiving a direction to do so.
19.97 Insurance - Does Clause 10.9 give any comfort to employer who
discovers that PI has lapsed and he wishes to insure himself and
recover that cost?
It might possibly although such defects are often latent and arise after the
Contractor has left the Site. The question to ask is what is your real sanction in
this circumstance? If he’s a repeat customer of a repeat client, one might
recognise that he is likely to be in business and renewing PI policy (Although any
renewal is most unlikely to provide retroactive cover). Remember a PI policy is
primarily to protect the insured. (This contract does have a right of offset
against other contracts with the same Employer).
19.100 Are unforeseen services within a building, and not in the ground,
compensation events in Clause 10.10.1.3? of Minor Works
contract?
No they are not Compensation Events as listed in the Schedule part 1K (item
20) as it refers specifically to such services being in the ground. Accordingly
Clause 10.10.1.3 does not apply to them (as it only applies to Compensation
Events).
19.103 The Payment deadline under 11.1.4, taken with the Contractors’
powers of suspension under Clause 12.3 and the obligation to check
that payment on any application is properly due, all potentially
create a highly condensed sequence in time?
The provision of an interim statement starts a time sequence. The ER has to
examine the application to comply with his own implied obligations to test it
against Clause 11.4, and within 10 working days give a certificate. The Employer
makes a payment within 15 working days of receipt of an invoice. It should be
recalled that working days are referenced rather than calendar days.
19.104 Has "adjudicate" as used in clause 13.1.2 changed the role of the
Conciliator?
No – the term "Adjudicate" here is merely used to indicate that the conciliator
is to be a competent person to fill that role.
19.106 Will Met Éireann provide in a timely fashion the statistics needed for
the weather event? Is the description of the weather event precise
enough?
The 10 Year Return Period statistic can be calculated by standard hydrological
means from the annual maxima provided as raw data, either by Met Éireann, or
by the user.
19.108 If you request a proposal, but do not proceed with it, can you pay
the Contractor to prepare the proposal?
No
19.109 Health & Safety – What happens with initial PSDP in a DB? Does
each tenderer have to have a PSDP in preparing his bid?
A similar question arises for the Employer in that the Employer’s experts
including the ER will be assessing the tenders and indeed may have initiated the
design process by an indicative design or Employer’s Requirements. It might
therefore be more appropriate that the Employer appoints initially and then
passes on that role to the Contractor upon his appointment.
19.113 Definition of "Site" very wide, so how does it affect "unfixed works
items".
The definition of Site is clear enough so as to avoid confusion in most cases as to
whether Works Items are in fact on or off of the Site.
19.114 The Conciliators’ Award Bond, where does its cost lie if Arbitrator
finds the conciliation award was in fact correct?
It is likely that it will have to be borne by the party providing the bond.
However, the party has a choice as to whether he wishes to provide the bond
or not. It is likely that the choice would be to provide the bond in view of the
fact that he is getting payment. It might possibly be claimable in the arbitration
proceedings in the event that a final award had not been made at the relevant
stage.
19.115 Can you insist on having the Safety File before issuing a Certificate of
Substantial Completion?
It is the PSDP who is responsible for the Safety File under the new Regulations,
but if the Contractor has not handed over essential material for the PSDP to
include in the Safety File, it would be a valid reason for giving reasons to
withhold the Certificate. Otherwise, the Employer would be in control of an
As-Constructed Asset for which he didn’t have a Safety File.
19.118 Why no sectional completion in the Minor Works Form? Very many
minor projects involve extensions, followed by decanting to the new
area, with refurbishment of the old.
This has been taken under consideration. There is no impediment to inclusion
of a programming constraint in the Works Requirements to cover this situation.
19.123 There’s a different Base Date for PV1 than PV2, what is the
explanation?
PV1.1.1(a) p76 Base Date = 31st month after Contract Date
PV2 Appendix No. 1 p82(d) Base date = 37th calendar month after
Designated date.
Under PV1 if you sign up, and you take longer than 6 months to get the contract
signed, no extra disadvantage occurs to the Employer. Same effect really, but
some disadvantage to Employer in PV2, in that he has 36 months from the
Designated Date, so that slippage in signing up eats into his fixed price period.
Guidance Note Section 2.5.2 explains the position.
19.128 Could it happen that, in the Collateral Warranty, the access to the
Specialist is not as comprehensive as Employer assumed, because
contract between Contractor and Specialist may not cover what
Employer thought it did?
The plan is that the Employer will not concern itself with the contract between
the Contractor and the Specialist as the Contractor is fully liable for the
Specialist’s work (including design).