0% found this document useful (0 votes)
147 views275 pages

TM-CC Public Works Contracts - Contractors

Uploaded by

bgmladic
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views275 pages

TM-CC Public Works Contracts - Contractors

Uploaded by

bgmladic
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 275

An Roinn Airgeadais

Department of Finance

Training Manual

Tm-cc
PUBLIC WORKS CONTRACTS - CONTRACTORS
Public Works Construction Contracts
Training Manual

NOTICE
This training manual is both the course material from the training courses and a
reference document for government departments, bodies under their aegis, local
authorities or other relevant bodies in the new Public Works Contracts.

All parties must rely exclusively upon their own skill and judgment, or upon
those of their advisers when making use of this document. Neither the GCCC,
NPPU, Department of Finance, McCann FitzGerald, Project Management Ltd or
Tobin Consulting Engineers nor any other contributor, assumes any liability to
anyone for any loss or damage caused by any error or omission, whether such
error or omission is the result of negligence or any other cause. Any and all such
liability is disclaimed.

The contents hereof do not form part of, and shall not affect the interpretation
of, any contract.

This Training Manual was used for courses delivered to senior members of the
Public Sector during December 2006–January 2007 and reflects the versions of
the Public Works Contracts current at that time.

This manual refers to the following documents:

ƒ Public Works Contract for the Provision of Civil Engineering Works


Designed by the Employer.
ƒ Public Works Contract for the Provision of Civil Engineering Works
Designed by the Contractor.
ƒ Public Works Contract for the Provision of Building Works Designed by the
Employer.
ƒ Public Works Contract for the Provision of Building Works Designed by the
Contractor.
ƒ Minor Works Contract for the Provision of Building and Civil Engineering
Works Designed by the Employer.

Readers should also refer to the Guidance Note on Public Works Contracts.

First published in February 2007 by the Department of Finance. Reissued May 2008.

© All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted in any
form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior written
permission of the Department of Finance.

V1.1

Department of Finance Page 2


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Contents
1. COURSE AGENDA 7

2. COURSE INTRODUCTION 15
2.1 Trainer Introductions 15
2.2 The Capital Works Management Framework 16
2.3 The Background 17
2.4 The New Forms of Contract 18
2.5 Timeline for Rollout 20
2.6 The Government’s Objectives 21
2.7 The Aim of this Course 21
2.8 The New Contracts as Enablers for Better Management 22

3. THE NEW CONTRACTS – MAIN FEATURES 24


3.1 Structure of the Contract 24
3.2 Key Changes from the Old Contracts 26

4. RISK MANAGEMENT 28
4.1 What is Risk? 28
4.2 The Broader Context 28
4.3 Risk Management Processes Generally 29
4.4 Commercial Context (Value for Money) 31

5. RISK ALLOCATION, WHAT IS NEW? 34


5.1 Introduction 34
5.2 Selection of the Procurement Strategy 34
5.3 What is new in terms of risk allocation? 35
5.4 Delay and Compensation Events 36
5.5 Comparison of Risk Allocation Under the Various Forms 37
5.6 How Should Contracting Authorities Allocate Risk? 43

6. PRE CONSTRUCTION PLANNING OF PROJECTS,


WHAT IS NEW? 46
6.1 Introduction 46
6.2 Who to do the Design? 46
6.3 Factors to Consider in Selecting the Procurement Strategy 47
6.4 Alignment with Consultant’s Appointments 48
6.5 Which Form of Contract? 48

Department of Finance Page 3


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

6.6 The Impact on the Project Programme 48


6.7 Further Issues 49

7. THE BROAD LEGAL PERSPECTIVE, WHAT IS NEW? 52


7.1 The Broad Legal Prospective, What is new? 52

8. PROCUREMENT – WHAT IS NEW? 54


8.1 Introduction 54
8.2 Specialists 54
8.3 Evaluation of Tenders 55
8.4 Letter of Acceptance 56

9. CONTRACT ADMINISTRATION, WHAT IS NEW? 58


9.1 Time 58
9.2 Cost 58
9.3 Quality 59
9.4 Powers and Duties of the Employer’s Representative 60
9.5 Price Variation Clause 64

10. THE LETTER OF ACCEPTANCE AND AGREEMENT 71


10.1 Letter of Acceptance 71
10.2 Agreement 71

11. COMPLETING THE SCHEDULE PART 1 75


11.1 Introduction 75
11.2 Section A 75
11.3 Section B 76
11.4 Section C 76
11.5 Section D 77
11.6 Section E 78
11.7 Section F 78
11.8 Section G 79
11.9 Section H 79
11.10 Section I 80
11.11 Section J 80
11.12 Section K 80
11.13 Section L 82
11.14 Section M 82

Department of Finance Page 4


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

11.15 Section N 83

12. COMPLETING THE SCHEDULE PART 2 85


12.1 Section A 85
12.2 Section B 85
12.3 Section C 85
12.4 Section D 85
12.5 Section E 85

13. WORKS REQUIREMENTS, WORKS PROPOSALS AND


PRICING DOCUMENT 87
13.1 Works Requirements 87
13.2 Works Requirements Documents 87
13.3 Works Proposals 90
13.4 The Pricing Document 91

14. COMMENTARY ON THE CONDITIONS 95


14.1 Definitions 95
14.2 Health and Safety 97
14.3 Loss, Damage and Injury 97
14.4 Management 103
14.5 Contractor's Personnel 111
14.6 Property Rights 115
14.7 The Site 116
14.8 Quality Control 117
14.9 Time and Completion 120
14.10 Claims and Adjustments to Contract Sum 128
14.11 Payment 135
14.12 Termination 141
14.13 Dispute Resolution 147
14.14 Comparison of Traditional and Design & Build Forms for
Building Works 149
14.15 Comparison of Traditional and Design & Build Forms for
Civil Engineering Works 162
14.16 Minor Works Form 174

15. CASE STUDY 1A – COMPLETING THE SCHEDULE PART 1


BUILDING WORKS 176

Department of Finance Page 5


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

16. CASE STUDY 1B – COMPLETING THE SCHEDULE PART 1


CIVIL WORKS 198

17. CASE STUDY 2 – TENDER EVALUATION 219

18. CASE STUDY 3 – SOME CONTRACT ADMINISTRATION


ISSUES 239

19. FREQUENTLY ASKED QUESTIONS 254

Department of Finance Page 6


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

1. Course Agenda

1 Course Agenda

Department of Finance Page 7


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Course Agenda for 4 Day Course in


New Public Works Construction Contracts

PART 2 DAY 1

Time Module Detail Lead


09:30–10:00 Introduction • Trainer introductions by Chairman MF
• Group introductions
• Capital Works Management Framework
• Background
• New forms of contract
• Timeline for rollout
• Objectives
• The aims of this course
• The new contracts as an enabler for good
management
10:00–10:30 Introduction to • The main features of the new forms MF
New Forms • Structure of the contract
• Key changes from old standard forms
• Timing of decision on form of contract to
use in context of project life cycle, planning
• Alignment with consultant appointments MG
10:30–10:45 Tea/Coffee Break
10:45–11:15 Risk Management • What is risk? MG
• The broader context
• Risk management processes generally
• Commercial context (value for money)
11:15–11:45 Risk Allocation. • Introduction MG
What is new? • Selection of the procurement strategy
• What is new in terms of Risk Allocation?
• Delay and compensation events
• How should an Employer allocate risk?
11:45–12:15 Planning projects. • Introduction MF
What is new? • Who to do the design?
• Which form of contract?
• The impact on the project programme
• Further issues to be considered

Department of Finance Page 8


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

PART 2 DAY 1/Contd...


12:15–12:30 The broad legal • Lump Sum Contract MO'R
perspective. • Fixed Price
What is new?
• Limits on adjustment of Contract Sum
• Employer's Representative role
12:30–13:30 Lunch Break
13:30–14:45 Procurement. • Restricted and Open Procedures KK
What is new? • Specialists
• Evaluation of tenders
• Letter of Acceptance
14:45–15:15 Introduction to the • Agreement MO'R
new forms/Contd... • Letter of Acceptance

15:15–15:30 Tea/Coffee Break


15:30–16:45 Introduction to the • Schedule MO'R
new forms/Contd... • Conditions

• Model Forms
• Works Requirements
• Pricing Document
• Works Proposals
• Post Tender Documents
16:45–17:00 Summary • Key Messages MF
• Deferred questions arising during that day

Department of Finance Page 9


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

PART 2 DAY 2

Time Module Detail Lead


09:30–09:45 Introduction to • Review of Day 1 MF
Day 2 • Further questions from Day 1 Group
10:00–10:30 The Agreement • Its importance MO'R
Letter of • Its purpose
Acceptance
• Contract Sum
• Accepted Contract Sum
• Documents
• Contractor's warranties
• Effective date and execution
10:30–10:45 Tea/Coffee Break
10:45–12:15 Competing the • Discussion on the Schedule MO'R
Schedule Part 1 • Dealing with and considering each element
covered and also by reference to the
relevant contractual provisions and
commercial issues
• Introduction to Delay and Compensation
Events
• Dealing with and considering each element
covered and also be reference to the
relevant contractual provision and
commercial issues
12:15–12:30 The Schedule • Consideration of all relevant issues with MO'R
Part 2 respect to Part 2 of the Schedule
12:30–13:30 Lunch Break
13:30–14:00 The Works • Works Requirements MF
Requirements and • Works Proposals MO'R
Works Proposals
14:00–14:15 The Conditions • Key differences between forms MO'R
14:15–15:15 Case Study Nr 1 Case Study Nr 1 will involve completing Part MG
1 of the Schedule for:
• A roads project; or
• A building project
The aim of the exercise will be to challenge the
groups to consider, in each case, how a
decision should be arrived at as to how to
complete Part 1

Department of Finance Page 10


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

PART 2 DAY 2/Contd...


15:15–15:30 Tea/Coffee Break
15:30–16:30 Case Study Nr 1/ • Discussion on Case Study Nr 1
Contd...
16:30–17:00 Summary • Key Messages ALL
• Deferred questions arising during that day

Department of Finance Page 11


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

PART 3 DAY 1

Time Module Detail Lead


09:30–10:00 Introduction to • Review of Part 2 MG
Part 3 • Further questions from Part 2
10:00–10:30 The Conditions • Key Personnel MO'R
• Definitions
• Inconsistencies/Bond/Parent Company
Guarantee
10:30–10:45 Tea/Coffee Break
10:45–11:45 The Conditions/ • Loss, Damage and Indemnity Insurance MO'R
Contd... • Management
• Property Rights
11:45–12:00 The Conditions/ • Specialist Contractors MF
Contd... • The Site
12:00–12:30 The Conditions/ • Quality Control MO'R
Contd... • Time and Completion
12:30–13:30 Lunch Break
13:30–14:15 The Conditions/ • Compensation Events and Adjustments to MO'R
Contd... Contract Sum
• Contractor's Claims
• Employer's Claims
14:15–15:15 The Conditions/ Price Variation MG
Contd...
15:15–15:30 Tea/Coffee Break
15:30–15:45 The Conditions/ • Health & Safety MG
Contd...
15:45–16:30 The Conditions/ • Payment MO'R
Contd...
16:30–17:00 Summary • Key Messages MF
• Deferred questions arising during that day

Department of Finance Page 12


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

PART 3 DAY 2

Time Module Detail Lead


09:30–09:45 Introduction to • Review of Part 3 Day 1 MG
Day 2 • Further questions from Day 1
0945–10:30 The Conditions/ • Termination MO'R
Contd... • Dispute Resolution
10:30–10:45 Tea/Coffee Break
10:45–11:15 The Conditions/ • Minor Works Form MO'R
Contd...
11:15–12:15 The Conditions/ • Model Forms MO'R
Contd...
12:15–12:30 Case Study Nr 3 • Case Study covering both Building and MF
Civil Engineering Works dealing with
Delay and Compensation events
12:30–13:30 Lunch Break
13:30–15:15 Case Study Nr 3/ • Group work and presentations Group
Contd...
15:15–15:30 Tea/Coffee Break
15:30–16:15 Case Study Nr 3/ • Further questions from the floor Group
Contd...
16:15–17:00 Conclusion • Review of Course Group
• Summary of Conditions of Engagement key
learning MG
• Summary of Works Contracts key learning MF

Department of Finance Page 13


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

2 Course Introduction

Department of Finance Page 14


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

2. Course Introduction
2.1 Trainer Introductions
Michael O'Reilly is a Partner in McCann FitzGerald Solicitors, specialising in
construction, planning and environmental law. He was initially with the practice
of Max W Abrahamson and, following the merger of the practices in April 1991,
became a partner in McCann FitzGerald, he is a Fellow of the Chartered
Institute of Arbitrators and a past Council member of the Irish branch of the
Institute. Together with Michael Roche and Barbara Maguire, Michael is co-
author of Irish Environmental Legislation published in 1999 by Round Hall Sweet
& Maxwell.

Kevin Kelly is a Partner in McCann FitzGerald specialising in construction law.


He qualified in 1989 and has since worked in the area of construction law,
initially with the practice of Max W Abrahamson and then with McCann
FitzGerald following a merger of the two practices in 1991. Kevin has been
consulted by public authorities, private developers and contractors in connection
with major civil engineering and construction projects in Ireland and has
considerable experience in public procurement law.

Michael Garrick is a Director of Tobin Consulting Engineers and has worked


with Tobin for more than 25 years on Water Supply, Main Drainage, Waste
Water Treatment and Solid Waste Projects all over Ireland. He has appeared as
specialist hydrological expert related to Sworn Enquiries under 1942 Water
Supplies Act. He has extensive experience of major civil engineering works,
including preparation of formal Cost Benefit Analysis and Post Works EU Audits
in relation to them. He has extensive experience of different form of
construction contract in the Water Services Sector, including advice on litigation
aspects at Irish and European Court level. He has frequently worked in
multidisciplinary teams and currently works on a 45 MLD abstraction from the
Liffey for Fingal Co Council and a 40 MLD water supply abstraction project on
the River Barrow for Kildare Co Council with Nicholas O'Dwyer & Partners.
He is a guest lecturer in Hydraulics with the BE Civil Programme of NUIG.

Matt Farrelly is a Chartered Quantity Surveyor and Associate Director with


responsibility for the Cost Management/Quantity Surveying function in PM's
Dublin office. Along with a post graduate qualification in construction law, Matt
has contract administration experience on major project of value up to €500
million, under various forms of contract and procurement routes, including RIAI,
GDLA, IEI Forms, FIDIC Orange and Red Books, MF/1, JCT '81 and '87 and
bespoke forms. Key skills include cost management, value engineering,
commercial risk management and whole life costing. Matt has carried out
training in contract administration both internally in PM and for such bodies as
Greencore, Dublin Airport Authority, UCD and Bristol Myers Squibb.

Department of Finance Page 15


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

2.2 The Capital Works Management Framework


The Capital Works Management Framework is a series of documents which
collectively describe the operating environment, procedures and processes to be
followed for the delivery of capital works projects. It incorporates contractual
provisions, guidance material and technical procedures covering the public works
project lifecycle from inception to final project delivery and review.

The aim of the Capital Works Management Framework is to ensure that there is an
integrated methodology and a consistent approach to the planning, management
and delivery of public capital works projects with the objectives of greater cost
certainty, better value for money and more efficient project delivery. The flow
chart below describes the framework.

Department of Finance Page 16


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Participants should refer to the separate Guidance Notes prepared by the


GCCC as part of the Capital Works Management Framework, including:

ƒ Project Management Structure


ƒ Project Definition
ƒ Budget Development
ƒ Procurement Strategy and Contract Type
- Guidance Notes for Public Works Contracts
- Public Works Contracts (5)
- Arbitration Rules
- Model Forms
ƒ Consultants Appointment Process and Conditions of Engagement for
Construction Consultants
- Procurement Guidance Notes
- Suitability Assessment of Consultants for Category 12 Services for Both
Open and Restricted Procedures
- Standard Conditions of Engagement for Construction Consultants
ƒ Design Development and Procurement Process
- Design Process
- Suitability Assessment of Works Contractors for Both Open and
Restricted Procedures
- Procurement Guidance Notes
ƒ Design Cost Control Procedures
ƒ Tender Process
- Template Public Works Tender Document
ƒ Construction Process
ƒ Construction Cost Control
ƒ Project Review
ƒ Analysis of Outturn Costs

2.3 The Background


Public capital works projects generally fall into two sectoral classifications:

ƒ Civil Engineering Works;


ƒ Building Works.

This division reflects some fundamental differences between the civil engineering
and building sectors.

Civil engineering works such as roads, tunnels, bridges etc. are designed by Civil
Engineers acting [for the most part] under the direction of the Contracting
Authority and are carried out by civil engineering contractors.

Department of Finance Page 17


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building works such as office buildings, schools and hospitals are designed by
Architects (with other consultants) again acting [for the most part] under the
direction of the Contracting Authority and are constructed by building
contractors.

In both sectors the standard forms of contract used in the past have been
published by the lead professionals’ professional institutions. In the case of
building works by the RIAI with the agreement of the Department of Finance, in
the case of civil engineering works by the IEI, now Engineers Ireland.

A number of contracting authorities have also used the various FIDIC and JCT
forms suitably amended for use in Ireland.

The old forms have not served the Public Sector well in the past, hence the
introduction of the new forms which:

ƒ Reflect the latest thinking in project and risk management;


ƒ Are clear in terms of wording and in the allocation of risk;
ƒ Recognise the development of new procurement methods such as design
and build;
ƒ Support the certainty of outcome in terms of cost, quality and programme
that an effective capital asset delivery process demands.
In the private sector it now common practice for the equivalent private sector
forms, mainly the RIAI Form, to be heavily amended by clients’ solicitors with
the objective maximising financial certainty by risk allocation.

2.4 The New Forms of Contract


CAPITAL WORKS MANAGEMENT FRAMEWORK

Guidance Notes

Civil Engineering Minor Building & Civil


Building Works
Works Engineering Works

(Under €5m)

Public Works Contract Public Works Contract for Minor Works Contract
for the Provision of the Provision of Civil for the Provision of
Building Works Engineering Works Building and Civil
Designed by the Designed by the Employer. Engineering Works
Employer. Designed by the Employer

Public Works Contract Public Works Contract for


for the Provision of the Provision of Civil
Building Works Engineering Works
Designed by the Designed by the
Contractor. Contractor

Department of Finance Page 18


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

1. Public Works Contract for the Provision of Civil Engineering Works


Designed by the Employer (traditional contract)
2. Public Works Contract for the Provision of Civil Engineering Works
Designed by the Contractor (design and build contract)
3. Public Works Contract for the Provision of Building Works Designed by the
Employer (traditional contract)
4. Public Works Contract for the Provision of Building Works Designed by the
Contractor (design and build contract)
5. Minor Works Contract for the Provision of Building and Civil Engineering
Works Designed by the Employer (traditional contract)

Contracts 1 and 3 above replace previously used employer designed standard


forms and throughout this manual are referred to as the Traditional Contracts.

Contracts 2 and 4 are new forms for works designed by the contractor and
throughout this manual are referred to as Design and Build Contracts.

Contract 5 above has been developed to both share and reduce the level of risk
transfer to small/medium sized contractors for projects of value less than €5m.

The new contracts are currently available at the free of charge following links:

http://www.finance.gov.ie/ViewDoc.asp?fn=/documents/publications/other/construct
reformdec06.htm&CatID=61&m=p

http://www.e-tenders.gov.ie/guides/guides_list.aspx?type=2

On 19 May 2007 a charging mechanism will be introduced for the forms.

Contracting Authorities – called "Employers" in the public works contracts – are


now required to enter into fixed price lump sum contracts for public works,
tendered on a competitive basis, with appropriate risk allocated to the
contractor. This new arrangement will result in greater cost certainty, better
value for money and more efficient delivery of public capital projects. This risk
allocation is facilitated by the Contracting Authority providing appropriate
information in the tender documents for the tenderers to assess and price. The
information to be supplied will depend on the type of contract being used.

The new forms of construction contracts must be applied to traditional and


design and build public works in Ireland that are procured directly by a
government department, bodies under its aegis, including local authorities or
other relevant bodies that provide public services (e.g. schools, voluntary
hospitals, etc).

The new forms of construction contracts are to be used without amendments.


In this context, the new forms have been drafted in a way that better protects
the public sector client’s interest in order to achieve value for money outcomes
from public expenditure on public works projects. However, in exceptional and
rare circumstances, consideration can be given to amendments to non core

Department of Finance Page 19


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

elements of the new forms of construction contracts. The request for any such
amendments from those bodies required to use the new contracts should be
submitted to the GCCC for consideration and approval as appropriate. Other
public bodies (such as commercial semi-state bodies) wishing to use the new
forms of construction contracts but with amendments, should also submit a
request to the GCCC for consideration and approval as appropriate.

Where the body procuring the public works project is not a government
department or a body under its aegis or a local authority or other relevant body
that provides public services (e.g. schools, voluntary hospitals, etc) and more
than 50% of the funding for the project comes from a source other than the
Exchequer, the government department or relevant body, as appropriate, should
decide if the new Public Works contracts will apply. If it is decided not to use
the new forms of construction contracts on a particular public works project,
the Accounting Officer/Accountable Officer in the government department or
the relevant public body must be satisfied that the contract terms in the other
contract being used are framed in a manner that seeks to protect public funds.
They must also be satisfied that the alternative contract conditions include the
provisions on Pay and Conditions of Employment (i.e. clause 5.3 in the new forms
of construction contracts). The rationale for this decision should be documented
in an appropriate and transparent manner.

Commercial semi-state bodies (e.g. ESB, BGE, An Post) are not required to use
the new forms of construction contracts on public works projects unless more
than 50% of the funding for the project concerned comes directly or indirectly
from the Exchequer.

2.5 Timeline for Rollout


It is intended that the new forms of Construction Contracts for Public Works
will apply as follows:

ƒ To all new public works projects about to begin the planning stage on or
after Monday 19 February 2007.
ƒ To all new public works projects where planning has commenced but where
detailed tender documents have not been developed by Monday 19
February 2007.
ƒ For those public works projects where detailed development of tender
documents has commenced, contracting authorities can elect to use the
new forms of construction contracts on or after Monday 19 February 2007.
ƒ Where a contracting authority, following appropriate training, wants to use
the new forms of construction contracts on or after Monday 19 February
2007.
ƒ Where a contracting authority, following appropriate training, wants to use
the new forms of construction contracts on public works projects on a date
earlier than Monday 19 February 2007.

Refer to Department of Finance Circular 33/2006 for further information.

Department of Finance Page 20


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

2.6 The Government’s Objectives


The introduction of the new forms of contract supports the Government’s
objectives to:

ƒ Move towards greater cost certainty at contract award stage and ensure as
far as practicable that the accepted tender prices and the final cost are the
same;
ƒ Award contracts on the basis of a lump-sum fixed-price to the greatest
extent possible;
ƒ Rebalance risk so that there is optimal allocation of risk;
ƒ Achieve value for money; and
ƒ Achieve more efficient delivery of the projects.

2.7 The Aim of this Course


The aim of this course is to support deployment of the new forms by
introducing them to selected front line officers and to enable them share this
knowledge with those officers yet to be trained to roll out use of the forms on
the projects for which they are responsible.

Having completed the course, participants should have:

ƒ An appreciation of the Capital Works Management Framework;


ƒ An understanding of the key differences between the new forms and those
previously in use in their sectors;
ƒ An understanding of the principles of risk assessment and appropriate risk
allocation;
ƒ An understanding of how the new conditions of conditions can allocate
risks;
ƒ An understanding of the impact of the forms on the procurement process;
ƒ An understanding of the duties and obligations of the parties under the
forms;
ƒ An understanding of how to successfully employ the new forms to achieve
the overriding objectives of:
- Cost Certainty;
- Value for money; and
- Cost effective project delivery.

Department of Finance Page 21


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

2.8 The New Contracts as Enablers for Better Management


The new public works contracts are very much aligned with established project
management processes and their use will contribute to the effective management
of Capital Works Projects.

ƒ The contracts are legal documents written in ordinary language and are
designed to be easily understood, applied and interpreted by employers,
contractors and design teams;
ƒ The contracts are arranged and organised in a structure which helps the
user gain familiarity with their contents;
ƒ The actions by the parties are defined precisely so there should be few
disputes about who is to do what and when;
ƒ Change control processes are streamlined with reasonable certainty as to
their outcome;
ƒ Early warning procedures are built in for dealing with circumstances causing
delay and additional cost;
ƒ Such circumstances which confer entitlements to additional time and money
on the contractor are called Delay Events and Compensation Events
respectively and all are neatly captured in two adjoining sections – this
contrasts with say the old forms of contract where such clauses are
dispersed throughout the conditions;
ƒ Issues relating to assessment of Delay and Compensation Events are to be
resolved as projects proceed.
The new forms will promote best practice in project implementation by
employers, design teams and contractors with:

ƒ Better pre-construction planning of projects;


ƒ Promotion of completeness of design prior to construction;
ƒ Consideration at the outset of risk issues such as ground conditions,
archaeology;
ƒ Clear and decisive allocation of risk to drive accountability and motivate the
parties to actively contribute to project success;
ƒ More collaborative working between employers, design teams and
contractors over the life of the project;
ƒ Proactive cooperative management of the interactions between the parties
which will reduce the risk of time and cost over runs associated with capital
projects.

Department of Finance Page 22


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

3 The New Contracts


Main Features

Department of Finance Page 23


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

3. The New Contracts – Main Features


3.1 Structure of the Contract
The new public works contracts comprise the following elements regardless of
whether building or civil engineering, traditional or design and build:

ƒ A Letter of Acceptance issued by the Employer accepting the


Contractor’s successful tender. This should refer to and include any tender
clarifications. The issue of the Letter of Acceptance creates a binding
contract.
ƒ The Agreement between the Employer and the Contractor. This identifies
the date the contract is entered into, the parties to the contract, the
contract sum and any post tender clarifications.
ƒ The Contract Conditions which set out the roles and responsibilities of
the parties and the operational and management issues which will govern
the provision of the Works. This is subdivided into thirteen sections as
follows:
a. The Contract
b. The Law
c. Loss, Damage and Injury
d. Management
e. Contractor’s Personnel
f. Property
g. The Site
h. Quality Testing and Defects
i. Time and Completion
j. Claims and Adjustments
k. Payment
l. Termination
m. Disputes

ƒ The Schedule containing contract-specific information referred to in the


conditions but with substantially more information. This is the equivalent of
the Appendix in the GDLA and Appendix to Tender in the IEI 3rd Edition.
The Contracting Authority completes Part 1 and includes it in the tender
documents when inviting tenders. Part 2 consists of information filled in by
the Contractor and submitted with its tender. The completed Schedule
should be appended to the Letter of Acceptance.
ƒ The Works Requirements. For a traditional contract this includes
completed drawings, specifications, site investigation and other relevant
reports, consents, preliminary safety and health plan, etc. For a design and

Department of Finance Page 24


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

build contract this would comprise performance or output based


specifications as well as any developed design together with site
investigation or other reports, such relevant consents as have been
obtained, the preliminary safety and health plan etc.
ƒ The Pricing Document identified in the schedule and completed by the
Contractor including the bill of quantities (if any), pricing schedules, contract
sum analysis and/or other documents in which the Contractor provides its
detailed pricing proposals.
ƒ The Works Proposals state how the Contractor proposes to carry out
the works. When the Contractor has design responsibility the Works
Proposals include the Contractor’s design.
ƒ A suite of model forms for use during procurement and administration of
the contract comprising:
a. Form of Tender (F1)
b. Form of Bid Bond (F2)
c. Form of Letter to Apparently Unsuccessful Tenderer (F3)
d. Form of Letter of Intent (F4)
e. Form of Letter of Acceptance (F5)
f. Form of Performance Bond (F6)
g. Form of Parent Company Guarantee (F7)
h. Form of Novation and Guarantee Deed (F8)
i. Form of Appointment of Project Supervisor for Construction Stage
Only (F9)
j. Form of Appointment of Project Supervisor for Construction Stage and
Design Process (F10)
k. Form of Appointment of Project Supervisor for Design Process Only
(F11)
l. Form of Professional Indemnity Certificate (F12)
m. Form of Collateral Warranty (F13)
n. Form of Novation (F14)
o. Form of Rates and Conditions of Employment Certificate (F15)
p. Form of Bond – Unfixed Works Items (F16)
q. Form of Retention Bond (F17)
r. Form of Conciliator's Agreement (F18)
s. Form of Bond – Conciliator's Recommendation (F19)

Department of Finance Page 25


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

3.2 Key Changes from the Old Contracts


a. The contracts are written in plain English;

b. They have the same structure whether for building, civil engineering works;
traditional or design and build works;

c. Contracts are to be lump sum and largely fixed price with some exceptions;

d. There are no provisional sums or provisional quantities;

e. There are no PC Sums or nominated subcontractors, only Specialists who


will be regarded as "domestic";

f. The Contractor is responsible for design by Specialists.

g. Health and safety regulations are reflected in the forms;

h. There is provision for professional indemnity insurance;

i. There are detailed provisions dealing with management of the Works,


planning the Works, value engineering, communications, meetings, etc;

j. There is provision for Collateral Warranties;

k. Certain risks can be allocated between the parties;

l. There is provision to build into the contract period and contract sum for
delays that entitle the Contractor to extensions of time and additional
monies in a new concept called programme contingency this is not to be
confused with contractor’s float time;

m. Costs associated with delays which confer additional financial entitlements


on the Contractor can be tendered:

n. Tenders are evaluated on the basis of the proposed contract sum and on
delay costs;

o. There is provision for termination of the contract at the Employer’s


election;

p. The contracts effectively provide for exclusive remedies;

q. Disputes can be referred to conciliation and arbitration.

Department of Finance Page 26


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

4 Risk Management

Department of Finance Page 27


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

4. Risk Management
4.1 What is Risk?
An uncertain event or set of characteristics that, should it occur, will have an effect on the
achievement of one or more of the project’s objectives …….
Association of Project Managers

An uncertain event or condition that, if it occurs, has a positive or negative effect on at least
one project objective such as time, cost, scope or quality ……
PMBoK®

Risk is the likelihood of variation in the occurrence of an event, which may have either positive
or negative consequences.….
RAMP Institution of Civil Engineers & Faculty of Actuaries and Institute of
Actuaries

4.2 The Broader Context


Construction and engineering projects are risky ventures:
40% are late
50% over budget
30% fail to meet expectations of users
[Rethinking Construction UK DTI, 1998]

There are probably no similar statistics for Irish project outcomes.

However, Irish construction and engineering projects face the same risk
pressures:

ƒ Each project is unique;


ƒ Site conditions and constraints are highly variable;
ƒ The project teams of Contracting Authority, Design Team and Contractor
most likely will change from project to project, so lessons learned are
difficult to capture;
ƒ Projects can take a long time from inception to completion and people can
move on;
ƒ There are often competing pressures of time and budget;
ƒ The construction market is cyclical, subject to upswings and downswings
with consequent pressures on resources.

Department of Finance Page 28


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The risks that construction and engineering projects face are manifold and can
be classified under three headings:

Business Case Project Delivery Operational


Right Project Safety Owner Expectations
Right Location Quality Future Expansion
Interest Rates Cost Obsolescence
Legislative Time Maintenance
Demand/Availability Risk Availability
Market Whole Life Costs
Defects

The potential project delivery risks issues which can impact on time, cost and
quality on a project include incomplete or late project information, changes,
ground conditions, archaeology, bad weather, defects, inability to secure labour
and materials, etc. Typically these risks are allocated between the Employer and
Contractor by the conditions of contract. Obviously if such risks are effectively
managed at the outset their impact on project delivery can be effectively
reduced.

4.3 Risk Management Processes Generally


A risk management approach which is based solely on past experience and
dependent on judgement may work reasonably well in a stable low risk
environment but is unlikely to be effective for major projects.

Risk management is a structured approach to identifying, assessing and


controlling risks that emerge during the course of the project. Its purpose is to
support better decision-making through understanding the risks inherent in a
project and their likely impact. The benefits of formal risk management are:

ƒ It focuses the team on managing risk effectively by directly addressing issues


that threaten project success;
ƒ Confidence in the project outcome is increased;
ƒ It provides a mechanism for reporting risk on a regular basis to senior
management and escalating severe risk issues to appropriate levels; and
ƒ Projects can be considered on the basis that risks will be considered
rationally.

Department of Finance Page 29


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

There are various published methodologies and software packages for risk
management and the detail of these is outside of the scope of this course,
however, a generic risk management process will usually involve the following
stages:

ƒ Identification;
ƒ Analysis;
ƒ Evaluation;
ƒ Risk treatment;
ƒ Reporting.
For each risk (other than those designated as negligible) the following treatment
options are available:

ƒ Reducing or eliminating the risk;


ƒ Transferring the risk via the contract;
ƒ Transferring the risk by insuring for it;
ƒ Accepting the risk and managing it;
ƒ Obtaining better information to reduce the uncertainty.

Example:

Reducing/Eliminating Risk

It is understood that there may be contaminated soil on the site of a proposed project
but there is no conclusive data on this matter. If the risk of this was to materialise
during construction it would cause significant delay and a cost overrun, the effects of
which would be greater than the actual cost of dealing with it in advance.

The options available are:

(i) Ignore it and deal with it if and when it arises during the construction;
(ii) Determine the full extent of the contaminated material and the nature and
toxicity of the contaminant by means of investigatory studies. The material can
then be dealt with (a) in an enabling works contract or (b) in the main contract.

A decision is made to determine the full extent of the contaminated material and the
nature and toxicity of the contaminant by means of investigatory studies. The
contaminated soil is then removed in an enabling works contract. In this instance
better information was obtained to reduce the uncertainty and the potential risk to the
main project was dealt with by having an enabling works contract.

Department of Finance Page 30


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

Allocating Risk via the Contract

A project involves extensive earthworks. Considerable site investigation has been carried
out and factual site investigation reports are available, indicating the likely nature of the
ground, including the location of bearing strata and the type of strata encountered. On the
basis of these reports, the Engineer has designed the foundations.

The options available are:


(i) the Employer retains the risk of ground conditions;
(ii) the risk be allocated to the Contractor.

On the basis of the extensive site investigations, the Engineer considers that the ground
conditions likely to be encountered are quantifiable with a degree of certainty. A decision
is made that the Contractor should have responsibility for unforeseeable ground
conditions.

In this instance it was considered that there was sufficient site investigation information
available to enable the contractors assess and price the risk. Thus the risk was allocated to
the Contractor.

Example:

Accepting the Risk and Managing It

An existing hospital wing is to be refurbished. The refurbishment cannot commence until a


new block is completed under another contract and the existing wing is decanted to this.
If the Contractor is appointed for the refurbishment prior to the new block being
completed there is a potential risk of delay to site possession for the refurbishment and
consequent additional cost as a result. The refurbishment project dates are adjusted to
ensure there is no risk of delayed possession of the site for the refurbishment.

In this instance the risk was reduced and accepted.

Implementation of the decision to allocate a risk to the Contractor may involve


a financial premium and may introduce different but acceptable risks. Thus, in
taking a decision, consideration needs to be given to:

ƒ whether the risk can be effectively managed by the party allocated the risk
or whether the allocation causes a different, but more damaging risk;
ƒ whether the intended allocation of risk is effective and enforceable; and
ƒ does the risk allocation represent value for money?

4.4 Commercial Context (Value for Money)


The governing principle is that risks should be allocated to whichever party is
best placed to manage them. The optimal allocation of risk, rather than
maximising risk transfer, is the objective and careful balance is required in this
regard. Accordingly, the degree to which risk should be allocated to a
contractor depends on an assessment of each risk on a case by case basis.

Department of Finance Page 31


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Successful allocation of risk requires a clear understanding by the contracting


authority of the risks presented by a project, the broad impact that these risks
may have on the attractiveness of a project to tenderers and on costs, and the
limits to which a particular risk allocation might still be considered for value for
money.

Department of Finance Page 32


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

5 Risk
Allocation,

Department of Finance Page 33


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

5. Risk Allocation, What is New?


5.1 Introduction
The new forms of contract deal with risk allocation in two distinct ways:

ƒ By offering a choice of procurement strategy;


ƒ Within the conditions, by the allocation of risk and responsibility for certain
matters
5.2 Selection of the Procurement Strategy
The Selection of the most appropriate form of contract for the project is
covered by the Guidance Note Procurement Strategy and Contract Type.

In the selection of the procurement strategy for the project such as Traditional
or Design and Build, the Contracting Authority is making an important decision
on the allocation of the risk for design responsibility.

The Traditional contracts require that design information upon which tenders
are sought will be comprehensively developed and the Contracting Authority
retains responsibility and risk for:

ƒ Design of the works;


ƒ Completeness of the design of the works;
ƒ Changes to the design of the works.
Under the Design and Build contracts it is the Contractor who has responsibility
for:

ƒ Design of the works;


ƒ Completeness of the design of the works;
ƒ Changes to the design of the works.
However the Contracting Authority retains risk associated with any changes to
the Works Requirements.

There are particular projects that are not suited to the use of design-and-build
contracts – these include certain major alteration or refurbishment projects and
most maintenance projects.

Contracting Authorities should be aware that the tender evaluation and award
process for design-and-build contracts is more complex than for traditional
contracts. This increased complexity gives rise to greater risks regarding
transparency and objectivity in determining the most acceptable submission in
accordance with the award criteria

Department of Finance Page 34


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

5.3 What is new in terms of risk allocation?


1. The new forms for traditional contracts contemplate that the design by the
Employer’s consultants will be comprehensively developed – the contracts
do not provide for provisional sums or provisional quantities. thus there is a
greater onus on contracting authorities to ensure completeness of design.

2. There is now an Irish standard form of contract for both building and civil
engineering works under which the Contractor has responsibility and risk
for design and completeness of design.

3. Contracts for the most part will be lump sum and the Contractors will own
the "quantities risk", however Contracting Authorities can make a choice
about the contractual status of the bill of quantities.

4. A new concept called Programme Contingency is introduced and


Contractors are required to allow within the contract period and within the
Contract Sum for a specified delay period, attributable to events which
confer rights to extensions of time and financial compensation.

5. Risks associated with ground conditions, fossils, archaeology, human remains


and utilities are now specifically referred to in the building contract; the
GDLA form made no specific reference to these matters.

6. Employers can make choices at the time of tendering as to whether any of


the following matters confer upon the Contractor the right to recover
additional monies:

a. Unforeseeable fossils, archaeology, human remains;


b. Unforeseeable ground conditions [excepting under the Design & Build
Form];
c. Unforeseeable utilities [excepting under the Design & Build Form];
d. Unforeseeable delays by utilities companies in relocating or
disconnecting utilities.

7. Contractors can be required to submit at the time of tender their "all in"
costs per day for events for which they are entitled to receive financial
compensation. This is their only entitlement for such events and as such
needs to be carefully estimated by contractors.

8. Force majeure and inability to secure labour and materials no longer entitles
Contractors to extensions of time.

9. There are mandatory procedures and notice periods which must be strictly
complied with by Contractors to receive extensions of time and additional
financial compensation where such entitlements exist.

10. The Contractor now has responsibility for the design by Specialists [the new
entity which replaces the nominated subcontractor/supplier];

Department of Finance Page 35


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

11. The Contractor now owns the risk associated with appointing a
replacement Specialist in the event that such is required as a result of
default or insolvency of the Specialist.

12. Contracts are now effectively fixed price [except for hyperinflation and for
very long durations – more of which later].

5.4 Delay and Compensation Events


At its most fundamental level [and subject to narrowly defined exceptions] the
Contractor owns the commercial risk associated with providing the Works, in
accordance with the Works Requirements, by the Date for Substantial
Completion, for the Contract Sum.

The exceptions are those events that give rise to an entitlement to extensions to
the Date for Substantial Completion which are termed Delay Events, and those
events that alter the Contract Sum which are termed Compensation Events

Delay and Compensation Events are broadly defined in the Guidance Note as
follows:

Delay events are events which, if they occur, are not at the Contractor’s risk,
and subject to the compliance with the contract, entitle the Contractor to an
extension to the date for substantial completion of the works (and any affected
section) equal to the amount of delay, taking into account only site working
days.

Compensation events are events which, if they occur, are not at the
Contractor’s risk, and subject to the compliance with the contract, entitle the
Contractor to be compensated for the effect the events have on the cost of the
works.

The new conditions allow Contracting Authorities well defined choice as to


whether certain events are Compensation Events. Moreover through a new
mechanism of programme contingency which is discussed in greater detail later,
there are thresholds [a single threshold only in the Minor Works Form] that
apply before delay costs associated with Compensation Events become payable
by the Employer.

The Contractor’s contractual financial entitlement for a Compensation Event is


easily ascertainable since it can be requested to bid its delay cost per site
working day at the time of tender. This approach will promote resolution of
issues on projects as they arise and thus less adversarial relationships allowing
project teams to better direct their efforts at project delivery.

Department of Finance Page 36


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

5.5 Comparison of Risk Allocation Under the Various Forms


The following table is compiled from Section K of the Schedule Part 1 of the
traditional, design and build and minor works forms. It tabulates the permitted
Delay and Compensation Events under the forms. Where "Yes" is inserted in a
box an event is a delay or compensation event as appropriate. The converse
applies where "No" is inserted.

The pre-completed boxes cannot be changed however, Contracting Authorities


may select the risk allocation by inserting "Yes" or "No" in the boxes shaded
yellow.

Department of Finance Page 37


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

DESIGN & MINOR


TRADITIONAL
BUILD WORKS

EVENT

Compensation

Compensation
Compensation
Delay Event

Delay Event

Delay Event
[See Section K of

Event
Event

Event
Schedule Part 1]

1. The Employer’s
Representative gives the
Yes Yes Yes Yes Yes Yes
Contractor a Change
Order.

2. The Employer’s
Representative directs the
Contractor to search for
Defects or their cause
and no Defect is found,
Yes Yes Yes Yes Yes Yes
and the search was not
required because of a
failure of the Contractor
to comply with the
Contract

3. The Employer’s
Representative directs the
Yes Yes Yes Yes Yes Yes
Contractor to suspend
work under sub-clause 9.2

4. The Contractor suspends


work in accordance with Yes Yes Yes Yes Yes Yes
sub-clause 12.3

5. There is a factual error in


information about the Site
or setting out information
in the Works Yes Yes Not Used Yes Yes
Requirements. [This does
not include an error of
interpretation].

6. The Employer takes over


part of the Works before
Substantial Completion of Yes Yes Yes Yes Not Used
the Works and any
relevant Section.

Department of Finance Page 38


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

DESIGN & MINOR


TRADITIONAL
BUILD WORKS

EVENT

Compensation

Compensation
Compensation
Delay Event

Delay Event

Delay Event
[See Section K of

Event
Event

Event
Schedule Part 1]

7. The Employer’s
Representative does not
give the Contractor an
instruction required
under sub-clause 4.5.4
within the time required Yes Yes Not Used Yes Yes
under sub-clause 4.11.2
when the Contractor has
asked for the instruction
in accordance with sub-
clause 4.11.1

8. The Employer does not


allow the Contractor to
occupy and use a part of Yes Yes Yes Yes Yes Yes
the Site in accordance
with sub-clause 7.1.

9. The Employer does not


give the Contractor a
Works Item or other
thing as required by the
Yes Yes Yes Yes Yes Yes
Contract when the
Contractor has asked for
it in accordance with sub-
clause 4.11.1.

10. Employer’s Personnel


interfere with the
execution of the Works
on the Site, and the
Yes Yes Yes Yes Yes Yes
interference is
unforeseeable and not in
accordance with the
Contract

11. The Employer instructs


the Contractor under
sub-clause 3.2.3 to rectify
loss of or damage to Risk Yes Yes Yes Yes Yes Yes
Items for which the
Contractor is not
responsible.

Department of Finance Page 39


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

DESIGN & MINOR


TRADITIONAL
BUILD WORKS

EVENT

Compensation

Compensation
Compensation
Delay Event

Delay Event

Delay Event
[See Section K of

Event
Event

Event
Schedule Part 1]

12. Loss of or damage to the


Works that is at the
Contractor’s risk in Yes No Yes No Yes No
accordance with clause
3.2

13. A weather event as


Yes No Yes No Yes No
described below

14. A strike or lockout


affecting the construction
industry generally or a
significant part of it, and
Yes No Yes No Yes No
not confined to
employees of the
Contractor or any
Contractor’s Personnel.

15. Delay to the Works


caused by the order or
other act of a court or
other public authority
exercising authority under
Law, that did not arise as
a result of or in
connection with an act, Yes No Yes No Yes No
omission or breach of
Legal Requirements of the
Contractor or the
Contractor’s Personnel
or a breach of the
Contract by the
Contractor.

16. A breach by the Employer


of the Contract delaying
Yes Yes Yes Yes Yes Yes
the Works that is not
listed elsewhere in table

Department of Finance Page 40


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

DESIGN & MINOR


TRADITIONAL
BUILD WORKS

EVENT

Compensation

Compensation
Compensation
Delay Event

Delay Event

Delay Event
[See Section K of

Event
Event

Event
Schedule Part 1]

17. A difference between the


Contract value of the
Works according to the
quantities and
descriptions in the Bill of
Quantities [taking into
account the method of
measurement identified
below when it applies]
and the Contract value of
the Works described in
the Works Requirements,
because the Bill of
Quantities, when
compared with the
Works Requirements: No Not Used No
• includes an incorrect
quantity or
• includes an item that
should not have been
included or
• excludes an item that
should have been included
• gives an incorrect item
description and the
difference for an item in,
or that should have been
in, the Bill of Quantities is
more than €500.

18. An item of archaeological


interest or human
remains is found on the Yes Yes Yes Yes
Site, and it was
unforeseeable.

19. The Contractor


encounters on the Site
unforeseeable ground
conditions or man-made Yes Not Used Yes Yes
obstructions in the
ground, other than
Utilities.

Department of Finance Page 41


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

DESIGN & MINOR


TRADITIONAL
BUILD WORKS

EVENT

Compensation

Compensation
Compensation
Delay Event

Delay Event

Delay Event
[See Section K of

Event
Event

Event
Schedule Part 1]

20. The Contractor


encounters unforeseeable
Yes Not Used Yes Yes
Utilities in the ground on
the Site.

21. Owners of Utilities on the


Site do not relocate or
disconnect utilities as
stated in the Works
Requirements, when the
Yes Yes Yes Yes
Contractor has complied
with their procedures and
the procedures in the
Contract, and the failure
is Unforeseeable

Department of Finance Page 42


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

5.6 How Should Contracting Authorities Allocate Risk?


Risk Nr 17 The Guidance Note for Public Works Contract suggests that Employers
Differences should carefully consider the circumstances that warrant the use of Bills
between the of Quantities. The policy is to have design developed so that "No" can
Works be inserted in this box. This requires comprehensively developed design
Requirements documentation including, for example, completed reinforcement
and Bills of drawings and mechanical and electrical designs.
Quantities
[Traditional In circumstances where ground conditions risk [Risk Nr 19] is being
Contracts Only] passed on to the Contractor in traditional contracts "No" should always
be inserted.

Risk Nr 18- Has the necessity for an archaeological report been determined and an
Unforeseeable appropriate preliminary archaeological report been prepared?
items of
archaeological Contracting Authorities are strongly advised, where the works are to be
interest or located in archaeologically sensitive locations, at feasibility stage, to seek
human remains expert advice and make contact with the National Monuments Section
found on the (NMS) of the Department of the Environment, Heritage and Local
site Government, which is responsible for the Identification and designation
of sites through the Archaeology Survey of Ireland, if the works are to
be located in archaeologically sensitive locations. In the event that the
works may affect a designated site or area of archaeological potential,
Contracting Authorities should take account of the NMS Framework
Document on the Principles for the Protection of the Archaeological
Heritage. Where the NMS requires it, a preliminary archaeological
assessment (including site investigation if considered necessary) should
be undertaken.

Where practical, archaeological risks associated with sites should be


resolved by way of advance contracts.

A Contracting Authority should allocate archaeological risk to the


Contractor when, having completed a preliminary site investigation in
compliance with the NMS Framework, the Contracting Authority
decides that there is no risk, or that the risk can be easily assessed and
priced.

Risk Nr 19- Where excavations are required, the project should be subjected to a
Unforeseeable carefully designed, executed and accurately documented site
ground investigations under a separate enabling work contract.
conditions,
man-made Contracting Authorities must make every effort to ensure that the
obstructions, accuracy and adequacy of the information gathered is correct. All tests,
[Traditional descriptions and reporting procedures should be in accordance with the
Contracts Only] current relevant codes of practice and leave no room for ambiguity. Site
investigation contractors should only employ trained and experienced
operators and supervisory staff so as to ensure the quality and integrity
of information. Contracting Authorities should consider employing their
own experienced experts on site to monitor site investigation activities
necessary for the duration of the site investigation works.

Factual reports on the findings of the site investigations should be


included in tender documents.

Department of Finance Page 43


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Interpretative reports, where available, should also be included in the


tender documents strictly on the basis that they are being made available
without warranty as to their accuracy. It is important to stress that such
information is given without warranty.

Contracting Authorities should be careful as to how below ground


design information is presented in the Works Requirements, particularly
in relation to dimensions of depths, depths drawn to scale, pile lengths
or datum levels or bearing strata to be reached arising out of an
interpretation of site investigation material. To disclose such information
in the Works Requirements could result in a claim for re-measurement
if the actual information is different when the ground is opened up.

A Contracting Authority should allocate the risk associated with


unforeseeable ground conditions to the Contractor when, having
completed a thorough site investigation, either decides that there is no
risk, or that the risk can be easily assessed and priced by tenderers.

Risk Nr 20- Surveys which will be carried out during the preconstruction should
Unforeseeable identify the location and nature of any utilities traversing the site.
utilities in the
ground In carrying out these surveys particular care should be exercised on
[Traditional existing non Greenfield sites or on public roads to locate such utilities
Contracts Only] with a degree of certainty.

Contracting Authorities should adopt a practical approach to the issue of


utilities if possible dealing with them in enabling works contracts.

Contracting Authorities should allocate the risk associated with


unforeseeable utilities to the Contractor when, having completed a
thorough site survey, the Contracting Authority either decides that
there is no risk, or that the risk can be easily assessed and priced by
tenderers.

Risk Nr 21- Contracting Authorities should adopt a practical approach to the issue of
Owners of utilities. In some cases, a separate enabling works contract to relocate
Utilities fail to utilities in advance of the main contract may be advisable.
relocate or
disconnect A Contracting Authority should allocate the risk associated with
utilities in a relocation or disconnection of utilities to the Contractor when the
timely manner Contracting Authority has agreed procedures with utilities owners as to
their disconnection/relocation such that there is no risk, or that the risk
can be easily assessed and priced.

The overriding basis on which a Compensation Event risk is allocated to the


Contractor should be that there is a low level of risk or that the Contractor is
furnished with sufficient information to enable it assess and price the risk.

A project risk strategy that attempts to allocate all risk to a Contractor by


indiscriminate risk dumping is unlikely to achieve the objective of value for
money.

Department of Finance Page 44


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

6 Pre Construction Planning of


Projects What is New?

Department of Finance Page 45


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

6. Pre Construction Planning of Projects, What is


New?
6.1 Introduction
The new conditions of contract will impact on the pre construction stage of
projects in a number of ways:

1. Who is to do the design? An Employer led design team or Contractor led


team;
2. Which form of contract? – Building or Civil Engineering;
3. The impact on the programme of these choices.

6.2 Who to do the Design?


When approaching the question of the appropriate Public Works contract, the
first decision to be made is that of choice of procurement i.e. traditional or design
and build.

This topic is the subject of Guidance Note - Procurement Strategy and Contract
Type under the Capital Works Management Framework and will be touched on
very briefly here.

Employer Designed

The design process is contractually separate from construction and is carried out by
designers engaged directly by the Contracting Authority. Complete detailed
documentation is required before tenders can be invited for carrying out the work in
return for a lump sum price.

Design and Build

The Contractor is responsible for undertaking both the design and the construction of
the work in return for a lump sum price.

Selection of the procurement strategy for the project entails considering the
nature of the project, its risks and the programme available. For every project
the Employer should focus on time, cost, performance and quality, in relation
both to design and construction of the project in order to make an informed
decision on the procurement strategy.

Choice should be made always after a careful analysis of the situation and a list of
questions to be considered in determination of the procurement strategy is
presented below:

Department of Finance Page 46


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

6.3 Factors to Consider in Selecting the Procurement Strategy

The scope and


nature of
the works
For example – are Measure of control
The type of the the Works building by the Employer
project or civil engineering For example – should
For example – is this in nature? design and selection
a Greenfield or a of materials be wholly
refurb job or perhaps in the hands of the
restoration of a Contractor?
protected structure?

Accountability
Value for Money
For example – does
For example – which
the Employer aim for
approach deliver the
single point of
optimum whole life
contractual
cost ? PROCUREMENT responsibility
STRATEGY

Programme Certainty of
final cost
For example – is this
to be ‘fast track’ Which approach will
with the shortest maximise financial
overall programme a certainty ?
priority?
The Market Changes during
construction
For example – the For example – is
market receptiveness there a potential risk
to the approach of design changes
adopted – linked to during the course of
value for money 1
the works?

1
Note that these should be kept to an absolute minimum

Department of Finance Page 47


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

6.4 Alignment with Consultant’s Appointments


The scope of services from the selected consultants should reflect and be aligned
with the proposed procurement strategy for the project.

6.5 Which Form of Contract?


As between the building and civil engineering forms there are some minor
differences. However the form deployed will depend on whether the work is
predominantly of a civil engineering or building nature after which consideration
should be given as to whether to follow the traditional or design and build route

Example:

A Government department requires a new green-field office building to accommodate


some 200 staff to be provided on the outskirts of a major town. The options are:

(i) Traditional procurement


(ii) Design and build

The Client’s requirements can be readily defined and it is not considered to be


particularly complex project.

The design and build route is selected as it provides a single point of contractual
responsibility and most likely has the shortest overall programme whilst providing
maximum financial certainty.

6.6 The Impact on the Project Programme


Contracting Authorities need to be aware of the need to ensure that project
risk issues are effectively addressed in contract documentation. They
furthermore need to be aware, that workshops to identify these risks, with
Employer participation, are necessary and that there is adequate provision in the
project programme to allow time for this.

Contracting Authorities should be aware of the following factors which should


be considered when deciding on the programme for a project.

Department of Finance Page 48


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Works The Traditional Forms require that the Works Requirements will
Requirements comprise comprehensive and well developed documentation which should
include for example:

• in the case of reinforced concrete works, full reinforcement drawings


and not just estimated kilograms of reinforcement per m³ of concrete;
• details of builder’s work in connection with mechanical and electrical
services installations;

Employers should note that the new forms of contract have no facility for
provisional sums or provisional quantities and therefore any works which
in the past were dealt with by these mechanisms will now be required to
be fully designed and time should be allowed in the programme for this.

The Works Requirements under the Design and Build forms by their very
nature are different to those of the Employer Designed forms and are
discussed further later

The Site Site risk issues such as archaeology, ground conditions and utilities should
be fully considered in order that appropriate and cost effective risk
allocation may be achieved. The need for any enabling works contracts
should also be considered as part of this strategy.

The Employer has a judgement to make on the appropriate amount of


preliminary work to be carried out by way of investigatory contracts, to
transfer their risks in a cost effective manner and to permit tenderers
assess residual risk properly.

Specialists Requirements for any specialist contractors to carry out aspects of


projects should be identified at prequalification stage as should be the
manner in which the specialists are to be engaged.

The The exact project programme for the Works with start and completion
Programme dates needs to be finalised for tenderers to estimate the fixed price
Dates addition for inflation. Subsequent changes to this after tenders have been
received are likely to have an impact on project costs and should be
avoided.

6.7 Further Issues


Further issues that will need to be considered include

ƒ Limitations on the Employer's Representative's authority.


ƒ Copyright
ƒ Insurance requirements
ƒ Requirements for bonds
ƒ Other contractors on-site concurrently with the Works
ƒ Collateral warranties
ƒ Requirements for liquidated and ascertained damages
ƒ Meteorological information on the site or nearest climatological station
ƒ The basis for ascertainment of costs for compensation events

Department of Finance Page 49


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

ƒ Programme Contingency
ƒ Retention percentage
ƒ Price variation options

Department of Finance Page 50


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

7 The Broad Legal Perspective –


What is New?

Department of Finance Page 51


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

7. The Broad Legal Perspective, What is New?


7.1 The Broad Legal Prospective, What is new?
In the forms of contract presently used (the "old forms") the contract
administrator is specifically either the Architect or the Engineer. In the new
forms the contract administrator is the Employer’s Representative ("ER") who is
likely to be either an Architect, an Engineer or other technically appropriately
qualified person. His role is substantially the same as that of the Architect or
Engineer but there is provision for limitation on the ER’s powers.

In the old forms of contract (and in many other forms) the provisions are vague
enough to be interpreted in a wide manner and to give rise to claims from
contractors under a variety of heads and guises. The new forms do not permit
this. There is no looseness which would facilitate vague and imprecise claims
and all adjustments to the Contract Sum will require a specific reason in the
absence of which there is no provision for an adjustment.

The new forms of contract are designed to give meaning to the expression
"fixed price lump sum contract". With regard to the lump sum aspect the
Contractor is to be given full and clear information as to the works to be carried
out and the risks being allocated to the Contractor so as to enable him to fully
price the works including those risks. While there is provision within the
Contract for adjustment to the Contract Sum the areas of such adjustment are
very specifically set out and regulated and are subject to strict notice conditions.
It is therefore unlikely that such adjustments will arise without easily verifiable
justification.

The Contract is largely a fixed price although there is provision for adjustment in
the case of extreme price fluctuations.

As discussed elsewhere, some old forms are not entirely precise in their
allocation of risk as between the parties. In addition, in many instances the
Contractor is not given enough information at the appropriate time to enable
him price risk. This has resulted in claims and disputes. The new forms allocate
risk clearly and neither party should be in doubt as to the risks allocated to him
and for which he must make provision. Also, as is stated above, the Contractor
is to be given all information necessary to price such risks.

Department of Finance Page 52


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

8 Procurement, What is New?

Department of Finance Page 53


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

8. Procurement – What is New?


8.1 Introduction
The CWMF deals with Procurement in the following guidance documents:

ƒ Procurement Strategy & Contract Type;


ƒ Tendering Process;
ƒ Procurement Guidance for Suitability Assessment of Works Contractors;
ƒ Standard Instructions for Tendering.

In essence the public procurement regime is unchanged by the introduction of


the new Public Works Contracts, however, the new forms introduce some new
concepts and Contracting Authorities should be aware of how these should be
dealt with to ensure compliance with the public procurement regime.

The main changes are:

ƒ The suitability assessment and procurement of specialists – the entities


which replace the nominated sub-contractor
ƒ Evaluation of tenders
ƒ The letter of acceptance

8.2 Specialists
Specialists can be procured in a number of ways:

(i) Specialists are named by the bidders in their Works Proposals. The
Contractor must have named its proposed specialists in its suitability
assessment submission. It is important to note that at least one of the
Contractor’s proposed specialists for each "specialism" must meet the
suitability assessment criteria, otherwise the Contractor will also fail to
prequalify. During the tender process, Contractors must confirm that the
specialist work will be carried out by the specialist(s) that were accepted as
part of the suitability assessment process. Note that any change by a
Contractor from its initially suitable specialist to another specialist should
be subject to a further suitability assessment by the Employer;

(ii) The Employer may in exceptional circumstances name the proposed


Specialist in the Works Requirements. In these circumstances a separate
suitability assessment process and competition would have been held and
the Specialist’s tender included in the Works Requirements for the
Contractor to include in its tender;

(iii) The Employer may, in exceptional circumstances, create a panel of


specialists for a particular package and let tendering Contractors for the
main contract choose from the panel and/or add others they wish to

Department of Finance Page 54


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

propose by reference to the criteria given to them by the Employer and


against which the panel was chosen;

(iv) Specialists could be novated to the Contractor. This approach is broadly


similar to that mentioned at (ii) above and would be considered appropriate
for novated designers in a design and build scenario or where there are
exceptionally long lead items.

8.3 Evaluation of Tenders


The significant issues that arise with the introduction of the new contracts are:

(a) Tenders are procured on a fixed price lump sum basis and there is no
subsequent negotiation of the fixed price addition as has heretofore been
the case;

(b) Where bills of quantities are used for civil engineering works, the tender is
the lump sum offer and not the rates in the bill of quantities;

(c) Daily rates for delay, all-in labour rates and percentage additions for
materials and plant are to be provided by tenderers. These will be required
to be taken into account in the evaluation of tender.

Accordingly, the evaluation criterion used must be "most economically


advantageous tender" and not the "lowest tender".

Where daily rates are tendered the following should be added to each
tender sum for the purpose of comparing tenders:

− The product of the provisional number of days’ delay stated in the


tender documents and the tenderer’s daily rate of delay cost.

− The product of the provisional number of hours for each category of


craftsperson, apprentice and general operative stated in the tender
documents and the tenderer’s hourly rate for each.

− The provisional cost of materials and plant in relation to compensation


events stated in the tender documents multiplied by the tenderer’s
percentage adjustment for each.

Where daily delay rates are not tendered (delay costs to be paid on
an actual cost basis), the following should be added to each tender sum for
the purpose of comparing tenders:

− The product of the provisional number of hours for each category of


craftsperson, apprentice and general operative stated in the tender
documents and the tenderer’s hourly rate for each.

− The provision costs of materials and plant in relation to compensation


events stated in the tender documents multiplied by the tenderer’s
percentage adjustment for each.

Department of Finance Page 55


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

See Case Study Nr 2 and the Guidance Note on Public Works Contract

(d) In most circumstances there is a pricing document, which tenderers


complete during the tendering period.

When a successful tender is selected and prior to issue of the letter of


acceptance by the Employer, it may be necessary to deal with
inconsistencies between rates, balancing of rates and errors in the pricing
document – for example where not all of the items have been priced or
where items may have been front loaded.

Such corrections and rebalancing are necessary so that the rates and prices
can be used to value work in interim progress valuations, and also that the
rates and prices can be used to value change orders should they arise.

Dealing with errors, inconsistencies and rebalancing of rates should be done


and notified to the preferred bidder by the Employer before rejection of all
the other tenders in case the preferred bidder does not stand over his
tender.

In limited circumstances – usually only in the case of some design-and-build


contracts the pricing document may be very general. In these circumstances,
a number of milestone payments are normally established for interim
payment purposes. Where this is done it is preferable to indicate to bidders
in the tender documents the percentage payable at each milestone.

8.4 Letter of Acceptance


The issue of a letter of acceptance by an Employer to a tenderer forms a binding
contract. The letter must be signed by a person authorised to sign contracts on
behalf of the Employer. The Employer should make sure that all required
approvals and supporting documents are in place before the letter is issued. The
letter of acceptance should not be confused with the "Alcatel" letter or a letter
of intent.

Department of Finance Page 56


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

9 Contract Administration
– What is New?

Department of Finance Page 57


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

9. Contract Administration, What Is New?


The conditions set out the rights and obligations of the parties and the role the
Employer’s Representative plays in administering the contract. Before looking in
detail at the duties of the Employer’s Representative as Contract Administrator
it is useful to examine some of the key aspects of the conditions under specific
headings.

9.1 Time
Key Dates Designated Date – 10 days before the last date for submission of
tenders.

Contract Date – Date of issue by the Employer of the Letter of


Acceptance.

Starting Date – Within 20 days of the Contract Date and as notified


by the Contractor.

Date for Substantial Completion – Contract date for completion of


the Works. This is defined in Clause 1.1 which sets out all that is
required for this to occur.

There is provision for sectional completion.

Programme Detailed requirements set out in Clause 4.9.1. Can be part of the
Works Proposals and therefore part of the Contract Documents.
Failure to provide or update the programme can entitle the
Employer to deduct money from payments to be made.

Delay Events Date for Substantial Completion only adjusted by Delay Events listed
in the Schedule Part 1K.

Suspension Employer’s Representative has power to suspend progress of the


Works under clause 9.2 and the Contractor has power to suspend
progress under Clause 12.3

Liquidated No requirement for a Certificate of Non Completion prior to such a


Damages deduction.

Programme Contract period is to include for a programme contingency for both


Contingency the costs and delays arising from Compensation Events. This is not
to be expended against events which are Delay Events only. A
worked example of use of the programme contingency is given after
Clause 9.4.4 of the conditions.

9.2 Cost
Cost Certainty Philosophy of contract set out in Article 4 of Agreement. "The
Contractor has included in the initial Contract Sum allowances for all
risks, customs, policies, practices, and other circumstances that may
affect its performance of the Contract, whether they could or could not
have been foreseen, except for events for which the Contract provides
for adjustment of the initial Contract Sum."

Department of Finance Page 58


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Price Variation Two approaches – PV1 or PV2. PV1 is a proven cost method and
under this the Contract Sum is fixed until 31 months after the
Contract Date. PV2 is the formula fluctuations method and under
this approach the Contract Sum is fixed for 36 months after the
Designated Date. There is also limited provision for recovery at
any time during the contract period for hyperinflation which is
defined.

Change Variations are now called Change Orders and are valued in
accordance with clause 10.6.

Compensation Listed in Part K of the Schedule Part 1 and entitlement is the period
Events of delay determined by the ER multiplied with the tendered cost
per site working day of delay. Note that there is also facility for the
entitlement of the Contractor to be assessed on the basis of
"expenses unavoidably incurred" by the Contractor if that option has
been prescribed at the time of tendering. There is no entitlement
to recovery of disruption costs or loss of productivity costs.

Value Provision for sharing of savings resulting from acceptance of VE


Engineering proposals from the Contractor.

Employer’s There is provision for deduction of Employer's claims from


Claims payments due to the Contractor.

Interim Generally monthly. Note that there is now no automatic right of


Payment payment for unfixed Works Items (materials); unfixed Works Items
now required to be vested. The value of materials off site is
required to be bonded. Payment applications from the Contractor
are to be accompanied by certificates covering pay and conditions
of employment.

Final Payment Final statement to be submitted within 2 months after Substantial


Completion. Employer’s Representative has 3 months to issue
penultimate payment certificate from receipt of final statement or 5
months from substantial completion if final statement is not
provided.

Deductions The Employer is entitled to make deductions from payments due to


the Contractor for (i) Failure to provide collateral warranties; (ii)
Failure to provide or update a programme or progress report; (iii)
Failure to comply with clause 5.3 - Pay and Conditions of
Employment

9.3 Quality
Fitness for Works Items and Works Items designed by the Contractor are
Purpose required to be fit for their purpose in the Works. The Contractor
is responsible for any design by Specialists and again such design is
required to be fit for purpose. Under the design and build forms
the Works are required to be fit for purpose.

Quality Contractor required to have QA procedures.


Assurance

Defects Provision for replacement of defective Works Items and rejection


of Works in its entirety.

Department of Finance Page 59


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

9.4 Powers and Duties of the Employer’s Representative


The following tabulates the duties and powers of the Employer’s Representative
under the Conditions of Contract

Clause Powers Duties

1.1 Issue Change Order including


imposition or removal of constraints
on how the Works are to be
executed.

1.1 Determine that the Contactor has


reasonable grounds for not rectifying
minor defects.

4.1.3 Request clarifications, consultations,


workshops, exchange of information
or expertise.

4.2.3 Request removal of the Contractor’s


Representative or Supervisor for
misconduct, negligence or
incompetence.

4.3.2 Issue instructions outside of


limitations stated in Schedule Part 1

4.3.3 Delegate authority to named Notify the Contractor of such


representatives. delegation and any changes to the
delegation.

4.4.1 Give the Contractor instructions,


directions, change orders or make
objections.

4.4.2 Give the Contractor and Employer


opinions, assessments,
determinations, certificates and
other communications the
Employer’s Representative considers
appropriate.

4.5.2 & Determine whether or not an


Clause instruction is a change order.
10

4.5.3 Not give a change order to do work


after Substantial Completion except in
the case of defects or work that was
to be done after Substantial
Completion.

4.5.4 Give an instruction necessary for Give a change order where physically
completion of Works impossible or contrary to Legal
Requirements to complete Works in
accordance with Works
Requirements.

Department of Finance Page 60


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Clause Powers Duties

4.5.5 Issue instructions in writing. Confirm


verbal instructions in writing as soon
as practicable.

4.6.2 Consider any changes to the Works


Proposals.

4.7 Object to a submission of the


Contractor giving reasons; request
additional information; alter or
withdraw an objection

4.8.3 Determine reduction in Contract Communicate the Employer’s position


Sum and adjustment to the Date of on any VE proposal.
Substantial Completion arising from
a VE proposal.

4.9.1 Waive content of a programme.

4.9.3 Request a revised programme

4.10.1 Dictate format of progress reports

4.10.2 Waive Content of progress reports.

4.12 Access to Contract Documents

4.13.6 Request information from


Contractor

4.15.1 Schedule meetings with the Consult with the Contractor and act
Contractor and others; reasonably in the timing and location
of meetings.

4.15.2 Issue minutes of meetings within 5


working days

4.16 Notify the Contractor of secret or


confidential matters.

5.4.5 Request details on the termination


or repudiation of a contract between
the Contractor and a Specialist.

5.4.6 Object to the proposed replacement


of a Specialist.

5.6 Direct removal of workpersons.

7.5.1(1) Authorise personnel to be on Site.

Department of Finance Page 61


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Clause Powers Duties

7.5.2 Comply with reasonable safety rules


notified by the Contractor.

7.8 Issue instruction regarding


archaeological objects and human
remains.

7.11(2) Waive working times requirements


set out in the Works Requirements.

8.2 Monitor, audit or spot check the


contractors QA procedures.

8.3 Gain access, inspect, observe the


Works or anywhere that Works
Items are manufactured, stores,
extracted, tested, etc.

8.3.2 Request test certificates or other


information on the mode, place, time
of manufacture, or performance
capabilities or source of supply of a
Works Item

8.3.3 Inspect Works or Works Items

8.4.1 Agree the location and timing of


tests; attend tests; request test
results.

8.4.2 Request repeat tests where they


have failed.

8.4.3 Request the carrying out of further


tests.

8.5 Direct the Contractor to search for


defects; give direction on defects;
accept a defect with the Employer’s
consent and determine the
reduction in value of the Works;
notify the Contractor that the
Employer will not accept defect.

Reject the Works and/or a part


thereof.

8.6 Instruct the Contractor to rectify


defects; extend defects period and
issue an interim certificate to part
release retention monies.

8.7 Issue Defects Certificate

9.1 Reduce the notice period of the


Starting Date

Department of Finance Page 62


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Clause Powers Duties

9.2 Suspend the Works; instruct the Examine Works and Works Items
Contractor to resume the Works affected by a suspension; determine
the extension of time and the
adjustment to the Contract Sum for
unavoidable deterioration of the
Works or Works Items arising from
the suspension.

9.3 and Revise any determination of Determine the Contractor’s


10.5 extension of time previously given. entitlement to extensions of time, if
any.

9.4.6 Notify the Employer and Contractor


of the amount of programme
contingency used.

9.5 Agree reductions in the contract


period for omissions.

9.6.2 Issue Certificate of Substantial


Completion or reasons for not issuing
same.

9.7 Issue notice of taking over of part of Certify contract value of works to be
the Works. taken over.

10.3 Request further information on


Contractor’s claims; direct the
Contractor to maintain records.

10.4 Request proposals on Proposed


Instructions.

10.5 Respond within 20 days of receiving


claim or proposals in respect of a
proposed instruction.

In respect of claims or proposed


instructions

(1) Direct the Contractor to provide


additional information or revised
proposals (1 shot only at this) or (2)
Notify the Employer and Contractor
that the proposals are agreed or (3)
Determine the adjustment to the
Contract Sum and the extent of any
delay or extension of time or (4)
Notify the Contractor that the
proposed instruction will not be given.

10.6 Direct that additional work be


valued on a time and materials basis

10.7 Determine which rate for delay shall


be used where a number of rates are
provided.

Department of Finance Page 63


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Clause Powers Duties

10.9 Give notice of Employer’s Claims.


Determine Employer's claims.

11.1 Value unfixed Work Items for Issue payment certificates


interim certificates

11.3 Agree date for provision of


retention bond by the Contractor.

11.5 Issue penultimate payment certificate


within 3 months of receipt of the
Contractors statement.

Issue final payment certificate within 3


months after Defects Certificate

12.2 Direct the Contractor to assign Determine termination value in the


benefit of any sub-contract. event of default termination;

Issue certificate setting out the


termination amount

12.6.4 Determine amount due to Contractor


within 10 working days

9.5 Price Variation Clause


The Contracts are intended to be Fixed Price Lump Sum over a 36 month
period from the Designated Date (or Recovery Date if slippage due to the
Contractors’ delay in signing up to the Contract activates a Recovery Date) This
is the essential position, so that for practical purposes the detail of the Price
Variation Clauses may well not arise. Note however that it governs both
increase and decrease in the Contract Sum under the circumstances outlined in
Optional Clause PV1 and PV2.

There are two approaches, selectable at the discretion of the Employer in the
Schedule Part 1, viz:

(a) The Proven Cost Method (PV1), and


(b) The Formula Fluctuations Method (PV2)

PV1 The Proven Cost Method

This is an invoice-based system whereby the Contractor establishes his


entitlement after the Fixed Price period, by invoices which are checked by the
Employer as outlined in the Guidance Note. Note that the definition of Base
Date under PV1 is the first day of the 31st month after the Contract Date, so
that this approach guarantees the Employer his 30 months fixed price, even if
there should be delay in setting the Contract Date. Recovery of labour

Department of Finance Page 64


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

increases relate to general round percentage increases under Social Partnership


Agreements applied to the appropriate REA rates at the Base Date.

PV2 The Formula Fluctuation Method

The Formula Fluctuations Method (PV2) is based on the use of CSO Indices for
different categories of Materials, Fuels, CPI, as published mainly in the Wholesale
Price Indices. The weightings for each of Material, Fuel, Labour, non-reusable
temporary works and non recoverable overheads are established by the
Employer (or Contractor in DB) and the proportions of different fuels and
materials are also defined for use with these indices, and these proportions are
provided in the ITT.

All of the formulae used in PV2 have a common basic structure, i.e.
The sum Element at
Indexation
subject to x - Contractors = Amount Payable
factor
indexation Risk

The Guidance Note has several examples of how PV2 applies to Materials,
Labour, Fuel, and Non Reusable Temporary Works after the Base Date, and it
also includes examples of calculation of the Hyperinflation provision.

It is perhaps sufficient to explore the formula in relation to just one element,


Materials, in order to establish the common approach in the other cases.

The formula for use with PV2 in relation to Materials is:

{ W x Y x Z x P x (A1 – B1) } – (10% x W x Y x Z x P) = K


B1

K is the amount which is recoverable, under the particular material heading to


which the indices A1 and B1 apply via the CSO Wholesale Price Indices in Table
3A of their publication.

If, within the Contract Sum (less VAT and deductible amounts), Z, the fraction
of Materials is Y%, within which Ready Mix accounts for W%, of which in turn
P% is the value in the current Interim Valuation, then WYZP is the value of
Ready Mix subject to indexation in this Valuation. The foregoing formula may
also be expressed as:
⎧⎛ A1 − B1 ⎞ ⎫
⎨⎜ ⎟ − 0.1⎬ * (W * Y * Z * P ) = K
⎩⎝ B1 ⎠ ⎭

In this form it is perhaps more easily interpreted. The term (A1-B1)/B1 is


recognisable as the proportionate uplift in the index, at the later Interim
Valuation date, compared to its value at the Base Date, and the 0.1 is the
threshold up to which the Contractor still carries the risk. Note that this means
he only recovers the amount in excess of 10% of WYZP, and this is not
equivalent to saying "He bears the risk of the first 10% of the increase"; it is
more exacting than that.

Department of Finance Page 65


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The term WYZP, as mentioned above, represents the sum which is subject to
the index calculation, for this particular material, in this particular Interim
Certificate.

Calculation of the amount, subject to the price variation calculation, in an


interim certificate after the Base Date (except for Hyperinflation) would follow
along the lines of the following example, and the proportion factors in Figure 1.
Contract Sum (excluding VAT) and any price adjustments €6,285,000.00
under this Clause
Less excluded amounts (say) €285,000.00
Z = €6,000,000.00
W= nominal weighting attributed to the relevant
Material or Fuel Category. In this case:
Ready Mixed Concrete 20%
Fabricated structural steel 28%
Y= Nominal percentage of Materials in the Contract Sum.
In this Case 35%
P= Percentage of the amount of the relevant material Category in the relevant
Interim or Final Certificate related to the total amount of that Material category
in the Contract Sum In this case:
Ready Mixed Concrete 25%
Fabricated structural steel 10%

Applying these together we have:

Ready Mixed Concrete -


W x Y x Z x P= 20% x 35% x €6,000,000 x 25% = €105,000

Fabricated Structural Steel -


W x Y x Z x P= 28% x 35% x €6,000,000 x 10% = €58,800

These are the sums, under the headings of Ready Mix Concrete and Fabricated
Structural Steel, which appear in the PVC calculation in the current Interim
Valuation. However, it will only be the amounts in excess of €10,500 and
€5,880 respectively, ie 10% of WYZP, which will be recoverable, and then only if
the index uplift generates an excess.

Clearly, it is possible that the formula at the head of this section could give a
value which is negative, and this happens when the uplift from the indexation
calculation is less than 10%.

The Clauses of the Contract make it clear that when this happens, the outcome
is a zero recovery for the Contractor.

Hyperinflation is defined in the Contract, and it can apply at any time after the
Designated Date, which means it can apply as a relief even during the " fixed
price period" when normal price relief does not apply. The structure of the

Department of Finance Page 66


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Hyperinflation Formula is mathematically the same, except the 10% of WYZP


factor is 50% of WYZP in that instance. There are worked examples in the
Guidance Note of how the Hyperinflation Formula is to be applied.

Weightings for Materials, Fuel and Other Items

In Employer Design Contracts, the Employer will define the weighting Y, and
weighting(s) W across a range of materials, by preparing two Tables, for
inclusion in the appendices to the ITT. It is important that the headings in the
table match those used by the CSO, so that there is unambiguously an index
available for each material category. Figure 1 illustrates how these weights apply
down the tree into each material category and interim certificate.

In Contractor Design, the Contractor will have to present his own weightings
against the corresponding materials categories, and good practice would then
require that this be taken into the account in the MEAT calculation as part of
tender appraisal. This might be done by declaring that tender comparisons would
be made, based on five ranked assumed materials values, with the highest five
weightings (for example) applied and taken to a sum itself taken into account in
the MEAT, to prevent any tendency to load a particular material category for
advantage.

In the above example, the following indices are used:

A1=The Adjustment Index Figure for the relevant Material or Fuel Category

B1=The Base Index figure for the relevant Material or Fuel Category

If now the indices took the following values and we were considering a
September 2008 Interim Valuation:

Designated Date: 15 January, 2005


Base Date: 1 August, 2008

CSO Indices (Material Category) Jan-05 Aug-08 Sept-08


Ready mixed concrete 106 105.3 126.36
Fabricated structural steel 102 109 124

The fractional amount of uplift, less the amount at the Contractors risk, can be
calculated as:

Ready Mixed Concrete


⎧⎛ A1 − B1 ⎞ ⎫ ⎧⎛ 126.36 − 105.3 ⎞ ⎫
⎨⎜ ⎟ − 0.1⎬ = ⎨⎜ ⎟ − 0.1⎬ = 0.1
⎩⎝ B1 ⎠ ⎭ ⎩⎝ 105.3 ⎠ ⎭

Fabricated Structural Steel


⎧⎛ A1 − B1 ⎞ ⎫ ⎧⎛ 124.0 − 109.0 ⎞ ⎫
⎨⎜ ⎟ − 0.1⎬ = ⎨⎜ ⎟ − 0.1⎬ = 0.0376146
⎩⎝ B1 ⎠ ⎭ ⎩⎝ 109.0 ⎠ ⎭

Department of Finance Page 67


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Having calculated the sum entering the PVC calculation, and the net uplift factor,
it remains to combine the two, in the following formula.

(W * Y * Z * P )* ⎧⎨⎛⎜ A1 − B1 ⎞⎟ − 0.1⎫⎬ = K
⎩⎝ B1 ⎠ ⎭

Ready Mixed Concrete


⎧ ⎛ A1 − B 1 ⎞ ⎫
(W * Y * Z * P )* ⎨⎜ ⎟ − 0 . 1⎬ = K = 0 . 1 * € 105 , 000 = € 10 ,500
⎩ ⎝ B1 ⎠ ⎭

Fabricated Structural Steel

(W * Y * Z * P )* ⎧⎨⎛⎜ A1 − B1 ⎞⎟ − 0 .1⎫⎬ = K = 0 . 0376146 * € 58 ,800 = € 2 ,111


⎩⎝ B1 ⎠ ⎭

Total Price Variation payable €12,711

Department of Finance Page 68


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Figure 1 – The Elements of WYZP

Z
Contract Sum
Excl. VAT, and Excluded Amounts

NON – R TEMP NON A


LABOUR MATERIALS FUEL
WORKS OVERHEADS

W
= > WYZP

Ready Mix

Base Date

Sum
Sun == 100%
100%
P
0% 4% 25% =

Cert 1 Cert 2 This Cert Final Cert

Department of Finance Page 69


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

10 The Letter of Acceptance and Agreement

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

10. The Letter of Acceptance and Agreement


10.1 Letter of Acceptance
The Employer must draw up and send the letter as provided for at Model Form
5 of Guidance Note for Public Works Contract – and must ensure it is clearly dated
(note – Contract Date as defined in Sub-clause 1.1 of Conditions)

While there is nothing particularly unusual about the issue of a Letter of


Acceptance sub-clause 1.1 of the Conditions states that the Contract Date is the
date the Employer issued the Letter of Acceptance. In turn the Conditions
(sub-clause 9.1.1) provide that the Starting Date (the date the Contractor
proposes to start executing the Works) must occur within 20 working days
after the Contract Date. Thus, the issue of the Letter of Acceptance is of
importance in starting the entire construction project.

Example:

The Employer is otherwise ready to accept a tender to carry out certain works but has not
yet obtained possession of an important part of the Site. In such case the Employer should
never send out a Letter of Acceptance (as to do so would trigger the actual Starting Date
under the Contract) unless he is absolutely certain that he can obtain possession before the
date on which access to this part of the Site will actually have to be given pursuant to sub-
clause 7.1.1 of the Conditions (or unless the Contractor’s access to the Site is limited by the
Works Requirements). The Employer would not want to start time running on a process
that will require access by the Contractor to a part of the Site before he knows he will be
able to provide that access.

While the Letter of Acceptance provides for the incorporation into the Contract of post
tender clarifications, the Employer should be most careful not to break any EU public
procurement requirements by the inclusion in the Contract of items not tendered.

Another point worth noting is that it is intended that the Form of Tender will be a document
executed by the tenderers under seal so that when the Employer accepts the Tender the
resulting contract will be under seal.

10.2 Agreement
The Employer should ensure that the Agreement as provided in the Contract
Documents is completed fully and correctly:

date of Agreement;
names of contracting parties;
initial Contract Sum;
any post tender clarifications intended to be included as contract
documents.

Department of Finance Page 71


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

He should ensure the Agreement is executed fully and properly by both parties,
note sealing requirements for companies:

if joint venture – executed by all members


if partnership – executed by all

While there is nothing particularly new in the Agreement it does state much
more clearly than in the old forms of agreement that the Contractor has fully
satisfied itself of all the risks involved in carrying out the Works and has priced
for them and included these in the initial Contract Sum.

It also sets out clearly the documents forming the Contract and, as has been
mentioned above, provides that the Contract takes effect from the Contract
Date.

Example:

In a contract in which the Letter of Acceptance was issued on the 10th January 2007 and the
Agreement is being executed on the 25th January 2007 the date to be inserted into the
Agreement will be the 25th January 2007 i.e. the date of the Agreement. This will not affect
the date from which the Contract takes effect i.e. the Contract Date...

When inserting post-tender clarifications or other documents intended to be


included as Contract Documents the Employer will need to consider carefully
whether or not the format of the clarifications or document is such that the
document as a whole may be included as a Contract Document or whether only
that portion of it intended to become contractually binding should be included.

This is something that will need to be considered very carefully by the Employer
and legal advice might well be required if there was doubt on the matter. It is
likely that this issue will in any event be addressed by the Letter of Acceptance.
In addition in this regard, attention must be paid to the EU public procurement
requirements.

It would be most appropriate where post tender clarifications or portions of other


documents are to be included in the Contract to have these distilled down into the required
operative provisions for inclusion rather than including entire minutes or other documents.

The Employer will need to consider whether or not he intends to execute the
document under seal. In general contracts for substantial public works will be
executed by the Employer under seal and in accordance with the standing orders
of the entity in question. If not to be executed under seal then the Employer
will need to consider who is the proper person to execute and what are the
rules governing the execution under hand of a binding contract for the amount
in question so as to ensure that appropriate standing orders are followed.

Although the Contract will already have been formed by the issue of the Letter
of Acceptance, the Employer should, in order to avoid any confusion or dispute
on the matter at a later date, also consider in advance who on behalf of the
Contractor is to execute the document and to ensure that he is satisfied the
document is being executed in accordance with the regulatory requirements
governing that entity.

Department of Finance Page 72


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

For instance, if the Contractor is an Irish company it will generally be sufficient if


the Agreement is executed under seal by the Director and the Company
Secretary but it may be that at the last minute, only certain Directors are
available to execute the document. In that case Employer will need to satisfy
himself that they are empowered to do so and they should be able to satisfy him
in this regard. for example, by way of a resolution by the board of directors.

If the Contractor is not a company incorporated in Ireland, it should be


executed in accordance with the law of the relevant jurisdiction (where it is
incorporated). A legal opinion as to due execution and enforcement might
usefully be required. As the Contract is in place before the Agreement is
executed the provisions of sub-clause 2.7.1 would appear to apply in these
circumstances.

Again in accordance with the footnote at the end of the Agreement the
Employer must ensure that if the Contractor is made up of various entities, each
must execute.

Department of Finance Page 73


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

11 Completing the Schedule Part I

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

11. Completing the Schedule Part 1


11.1 Introduction
The Schedule is an important innovation in these forms of contract. While
other forms of contract used in Ireland do have appendices e.g. GDLA, IEI and
FIDIC etc. none of those appendices have the level of detail set out in Schedule
to the new forms. The Schedule gives all of the necessary practical information
to the parties but in addition sets out clearly matters such as for instance, the
amount that will be withheld from the Contractor if he fails to provide Collateral
Warranties. It also sets out a comprehensive list of Delay and Compensation
Events and gives the Employer an opportunity to allocate risk in certain very
important areas to the Contractor or to himself. In the older forms the
allocation of such risk was not always clear and could result in acrimony and
dispute between the Contractor and Employer. In the New Forms it is clearly
known from day 1 who bears the risk and there should be little room for
dispute.

The Employer should ensure all risk assessments, investigations and decisions
have been carried out in advance of Schedule completion.

11.2 Section A
The Employer must ensure that all addresses, fax numbers and e-mail addresses
are entered and are correct

Example:

See Case Study Nr 1 – The Schedule

The Employer will need to consider to what address notices under clauses 12 and 13 relating
to termination and dispute resolution respectively, are to be sent. This would for example
be important if the Employer was resident in different locations or had a number of offices.
There should be no room for confusion in relation to where such important notices are to
be sent.

Similarly, the address of the Employer’s Representative to which notices pursuant to clauses
9 and 10 relating to claims for extensions of time and/or adjustments to the Contract Sum
must be sent should be accurately set out so that no confusion exists in relation to whether
these notices have been served in time.

Insert any/all limitations on powers of Employer’s Representative (note – if none


entered, none will be considered to apply)

In relation to the potential limitations on the ER’s powers it will be important for
the Employer to consider carefully the limitations that should apply in each given
case. This because it is not necessarily a good thing to require an ER to revert to
the Employer every time he wishes to issue an instruction or a Change Order. In
addition, it should be borne in mind by the Employer that it will be necessary for
him to respond promptly to the ER in relation to any request for instructions in
order to avoid causing any delay to the Contractor.

Department of Finance Page 75


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

See Case Study Nr 1 – Completing the Schedule Part 1

Example:

In the completed case study the maximum adjustment to the Contract Sum as inserted is
€5,000 unless approved by the Employer. It would be essential for the Employer to consider
in advance and in the light of the size of the Contract in question whether or not such a
permitted adjustment is appropriate or whether it should be larger or smaller.

It should be noted however, that it is not intended for any alterations to the Schedule itself to
be made.

It might also be noted that if the ER were to exceed his authority under the Contract, any
instruction given by him will nevertheless have effect as if it were within his authority and the
Contractor is not under a duty to inquire as to whether the Employer has actually authorised
it.

11.3 Section B
All relevant design details (in the Traditional contract) or Employer’s
requirements must be available when Part 1 of the Schedule is being completed.

Insert details of Works Requirements and the Pricing Document.

Historically in Irish Public Works Contracts (of the Traditional type) the design
detail provided to the Contractor varied from the very basic to the very
advanced. The New Forms seek to give full meaning and effect to the term
"fixed price lump sum contract" and in this context it is absolutely essential that
the design is fully developed before the Contractor is asked to price. If it is not,
this will give rise to the necessity for Change Orders and claims for adjustment
to the Contract Sum by the Contractor.

See Section 13 below in relation to Works Requirements.

11.4 Section C
The decision as to whether the Employer requires the copyright in all
Contractor’s Documents must be made in advance of completion of Part 1 of
the Schedule

The Employer must state in the Schedule if property rights in documents is


required (note – if not stated, the rights do not transfer (save possibly due to the
general law).

This part of the Schedule in conjunction with sub-clause 6.4 of the Conditions
allows the Employer the option of obtaining intellectual property rights in the
Contractor’s Documents and Works Items. It would be very important for the
Employer to decide if he requires such rights. In a Design and Build Contract it
would obviously be of far greater significance than in a traditional type of
contract. In a traditional type contract this would of course carry through from
the Conditions of Engagement where it would be of even greater relevance.
Thus there would probably be little point in having copyright in Contractor’s

Department of Finance Page 76


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Documents if the Employer did not ensure that he had copyright in the
Consultants’ design documents.

Example:

If the Works were a flagship building that the Employer wished should remain unique then he
might seek to obtain copyright in the design and other relevant documents. Then he would
be in a position to prevent the design and construction of the same building thus preserving
its uniqueness.

Alternatively, if the Works the subject of the Contract were the first in a series of such
structures to be erected around the country (e.g. schools, railway stations etc.) then the
Employer might feel that it would be important for him to have the right to copy all
documents and designs going forward. However, the Contractor takes no responsibility for
the use of the Contractor’s Documents other than in connection with the Works. (sub-
clause 6.4).

11.5 Section D
The Employer must consider carefully in relation to insurance

ƒ the minimum levels of insurance required from the Contractor


ƒ the maximum excess levels to be permitted
ƒ the exclusions that may be permitted
ƒ which party will bear risk of existing property (the default is that the
Contractor bears the risk)
ƒ any property of Employer (other than Works and Works Items) to be
included in insurances
ƒ if terrorism insurance is required – the level of cover
ƒ if sectional completion, whether insurance cover is to be extended until the
entire Works are certified as complete
ƒ whether professional indemnity insurance cover is required and if so, the
cover required, the level of excess and the period of cover
ƒ Insert all relevant details into Schedule
The insurance and indemnity provisions are not greatly different from those
which would normally be provided for.

In addition there is a clear entitlement under the Contract and as set out in the
Schedule for the Employer to require that Professional Indemnity insurance be
taken out by the Contractor. While this would be perfectly normal in a
Contractor’s Design Contract it would be less usual in traditional forms.

However, it is often the case that such insurance is or should be required.

Department of Finance Page 77


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

If the Works involve any substantial degree of design on the part of the Contractor or on the
part of any Specialist then unless the Employer can be fully satisfied (which is highly unlikely)
that the Contractor and/or Specialist would be of sufficient stature to stand over any design
by them (and satisfy any loss arising from defects arising) or that the issue is covered by the
design team on the project (and their P.I. insurance) the Employer should require that
Professional Indemnity insurance is obtained.

This is because the Contractor is fully responsible for all design by itself or by Specialists to
the extent that they are fit for their intended purpose in the Works. If the Contract is for
Design and Build the Contractor is fully responsible for the fitness for purpose of the overall
design.

11.6 Section E
The Employer must state whether or not a Bond is required (note- default is
that a Bond is required). The Employer must provide for the amount of the
Bond as a percentage of the initial Contract Sum up to Substantial Completion
and thereafter (note – the level of the Bond depends on the size of the
Contract. It ranges from 25% to 12.5% (see Guidance Note section 2.3). There
is provision for the Bond to reduce by one half upon Substantial Completion of
the Works.

11.7 Section F
The Employer must state if collateral warranties are required from certain
Specialists and by what date.

Example:

Almost by definition it is likely that a Specialist will be carrying out a design function and in
many cases the Specialist company will be as substantial, if not more so, than the Contractor.
For instance, some of the larger mechanical and electrical contractors are substantially larger
than many of the contractors for whom they work as specialist sub-contractors. Accordingly,
unless the Employer feels that a separate warranty from the Specialist need not be provided
because of the likely stature of the Contractor (who he will not of course know when
completing the Schedule) and/or the fact that the type of work to be carried out by a
Specialist is unlikely to fail, it would be most unusual not to require such a warranty.

Example:

The Employer is entitled to withhold from payments to the Contractor, the amount set out
in the table in the Schedule (part1F) in the event that the Contractor fails to provide a
collateral warranty within the time he is obliged to do so (sub-clauses 5.5 and 11.4.1). The
Employer will need to consider the amount to be withheld on the Contractor and must insert
it in the Schedule. The money will be paid to the Contractor when he provides the required
warranty. However, if he has not done so by the date of issue of the Defects Certificate, the
withheld amount is deducted from the Contract Sum (sub-clause 11.4.5).

Department of Finance Page 78


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

11.8 Section G
Unless the Contractor is required to insert the Date for Substantial Completion
in part 2 of the Schedule the Employer will need to consider the date.

This will obviously be considered in conjunction with the Employer’s consultants


and by reference to the size of the job and the time frame within which the
Works are required. It may perhaps be that certain parts of the Works will be
required separately and in that context sectional completion might be envisaged
with separate Dates for Substantial Completion in each case.

If the Contractor is required to insert the Date for Substantial Completion the
Employer should consider imposing (via the Works Requirements) a minimum
period for completion in light of safety considerations (see comments on this
point elsewhere).

If sectional completion is required, the Employer must insert the rate of


liquidated damages for each Section and any reduction of retention moneys on
Substantial Completion of a Section

Note: LADs must be a genuine pre-estimate of actual losses so as not to be a


penalty and therefore unenforceable

Example:

The rate of liquidated damages per day or per week will be inserted by the Employer and in
this regard the Employer should assess carefully the likely losses to be suffered by the
Employer should any Section or ultimately the entire Works be delayed due to the
Contractor’s default. The Employer should make sure that the amount in question is a
genuine pre-estimate of likely actual losses. In point of fact many Employers insert liquidated
damages that do not take into account all of their likely losses and accordingly such liquidated
damages are too low. Obviously, the Employer should be aware that a rate which is so high
that it bears no relationship to the anticipated actual losses is likely to be unenforceable as a
penalty.

There is also provision here for a reduction in retention on Substantial


Completion of a Section and in this regard the Employer should consider the
relationship that the Section in question bears to the overall Works.

If the Section is a very substantial part of the overall Works and represents 25%
of it in monetary terms, it may be appropriate to reduce the retention by a
similar percentage once that section is substantially complete. However, other
factors may come into play which would result in the reduction not equating
fully to the monetary relationship that the section bears to the overall works

11.9 Section H
The Employer must state whether or not the Employer’s Representative is
required to issue the certificate of Substantial Completion even if completion is
early (note – the default is that early certification is required).

Department of Finance Page 79


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Employer will have to decide whether or not he is happy that the ER should
issue the Certificate of Substantial Completion if the Contractor completes either
a Section or the entire Works before the relevant Date for Substantial
Completion. As the default is that the ER will have to issue the Certificate the
decision on the Employer’s part is whether he would prefer not to take over the
Works or the Section early.

It might perhaps be that the Employer will not be ready for the Works until the
actual Date for Substantial Completion and will not want to take it on for that
reason, and particularly may not wish to have the obligation to insure, take over
and provide security for the building.

11.10 Section I
The Employer must insert the length of the initial Defects Period

Example:

The Employer might wish to consider whether either a shorter period of say 6 months or a
longer period of say 18 months for carrying out the snagging etc. is appropriate. This would
relate to the nature of the Works and whether the Employer feels that the Works are for
example a simple but urgent job where an initial defects period of 6 months would be ample
to have it fully completed.

11.11 Section J
The Employer should state whether random checks for employment records
may be made under sub-clauses 5.3 (note – default is that the sub-clause providing
for such checks is part of the Contract). Note also that Government policy is that,
subject to certain parameters, such checks are to be carried out (see below).

Example:

The Employer will need to decide whether he intends to allow for random checks to be made
under sub-clause 5.3. The default position is that such checks can be made but the Employer
may decide that in certain circumstances there is unlikely to be any necessity for them. One
would envisage that it might be appropriate to leave in the entitlement even if it is not utilised
by the Employer.

However, it is important to note that any such checks may only be used for the particular
purpose of checking on proper payment of work persons and cannot be used for any other
purpose. (sub-clause 5.3.5) For instance, the Employer could not use the checks to seek
evidence in relation to Contractor’s Claims.

Government policy is that if a Contract value is greater than €30 million and its duration is
over 18 months – such checks will be required.

11.12 Section K
The Employer should consider carefully in light of investigations made and of
information available to the Employer and possibly to be made available to the

Department of Finance Page 80


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Contractor, whether items 17 to 21 (outlined briefly below) (18 and 21 only in


the case of Design and Build Contracts) are to be Compensation Events.

17 errors in quantities and or descriptions in Bill of Quantities in excess of


€500

18 finds of unforeseeable archaeological interest on the Site

19 unforeseeable ground conditions or man-made obstructions in the


ground (not utilities)

20 unforeseeable utilities in the ground on Site

21 delays by utilities owners to relocate or disconnect utilities despite


compliance by the Contractor with their procedures

The Employer has to carefully consider whether it is necessary that any


additional criteria be applied to an event for it to qualify as a Weather Event as
defined in the Contract and which may give rise to an extension of time for
completion of the Works. The standard criteria listed in the definition of
"weather event" in the Schedule part 1K are rainfall, air temperature and wind
speed.

The Schedule provides for a 10 year Return Period as the level of risk to be
allocated to the Contractor in this respect. This has a precise hydrological
meaning, as the event which, in a long record, is likely to be exceeded once in 10
years. It is not equivalent to an event which occurred within the last decade for
example. In a project lasting perhaps 24 – 36 months at construction stage,
there is a significant probability of the 10 year event occurring, be that rainfall, or
wind, or temperature. Furthermore, it is not impossible (although the
probability is low) that a 10 year Return Period event could occur twice within a
construction period. The Contractor carries that risk.

The Employer must insert in the Schedule, in the table provided, any additional
criteria decided upon as appropriate to the Works and the relevant weather
station at which those criteria will be measured.

It would seem appropriate that Met Éireann may have to be consulted on the
appropriate weather station to be entered in the Schedule by the Employer, as
the Climatological Station most representative of conditions at the Site of the
Works.

The Employer must insert the two thresholds for the Contractor’s Programme
Contingency pursuant to sub-clause 9.4 (note – these thresholds should be the
result of careful consideration by the Employer as to what is reasonable in all the
circumstances of the Contract).

The Employer must state whether the Contractor is to be paid his daily delay
costs (to be inserted by the Contractor in the Schedule part 2E at tender stage)
or his actual expenses unavoidably incurred (exclusive of profit).

Department of Finance Page 81


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Employer must insert any additional categories of workmen to come within
the definition of craftsperson as set out in Part 2E of the Schedule (defined there
as persons described as craftsmen or electricians in employment agreements
registered under the Industrial Relations Acts).

The Employer must state whether the Contractor is to provide in his tender for
a single delay cost rate or for separate rates for particular periods or portions of
the Works. See Case Studies 1A and 1B.

11.13 Section L
The Employer must insert the required details in relation to interim payment

the period for payment


the minimum amount for payment
the value of unfixed Works Items that may be included in interim payment
(note – default is 90% of Contract value)
the percentage to be withheld as retention (note - default is 10%)

The Employer must consider what the period for payment on interim certificates
should be. This will obviously depend on the nature of the Works, the urgency
for payment on the part of whatever contractor is carrying out the Works and
of course the Employer’s cash flow. The normal period is monthly and this is
the default as set out in the Contract. The Employer might however in certain
circumstances opt for six weekly payments to fit in with his cash flow but this
would have a corresponding effect on the Contractor’s cash flow.

The Employer will wish to consider the minimum amount to be paid out on an
interim payment (other than retention released) and this will again depend on
the size of the level of administration involved in processing interim payments.
The default is that there is no minimum.

The Employer will have to decide upon the value of unfixed Works Items that
may be included in an interim payment. The default is 90%. The Employer may
feel that this is too high and that a smaller percentage would be appropriate in
view of the fact that these items are not yet included in the Works. Although
the Contract significantly reduces the risk of loss due to anything that prevents
Works Items being incorporated in the Works or delivered to the Site (where
not yet delivered) there is always the possibility that in the event of an
insolvency their incorporation (or if not on Site, their delivery) could be delayed
despite the fact that up to 90% of their value may have been discharged. (sub-
clause 11.2) In the event of serious issues arising the Employer may well be
entitled to call on the bond to be provided by the Contractor.

11.14 Section M
The Employer must state which of the two price variation options is to apply
pursuant to sub-clause 10.8 (note – if none specified, PV1 will apply, therefore it

Department of Finance Page 82


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

is very important that the Employer addresses this issue carefully at this stage in
order to avoid possible conflict at a later stage)

11.15 Section N
The Employer must insert the name of the body that is to appoint the
conciliator for the purpose of sub-clause 13.1.2 in the event of a dispute arising

The Employer must insert the name of the body that is to appoint the arbitrator
for the purpose of sub-clause 13.2 in the event of a dispute arising that is not
resolved by conciliation.

The Employer will wish to consider what appointing body to nominate for the
appointment of the conciliator and the arbitrator pursuant to clause 13.

The approved professional bodies are:

ƒ Bar Council of Ireland


ƒ Chartered Institute of Arbitrators – Irish Branch
ƒ Engineers Ireland
ƒ Law Society of Ireland
ƒ Royal Institute of the Architects of Ireland
ƒ Society of Chartered Surveyors

In this regard the Employer might wish to consider whether or not in the
context of a building contract the conciliator or arbitrator should definitely be
an Architect in which case he might feel it appropriate to utilise the RIAI as the
appointing body. This would result in the appointment of an Architect as the
conciliator or arbitrator. Alternatively, if the view is in a civil engineering project
that the conciliator should be an Engineer, then Engineers Ireland should perhaps
be the appointing body.

Alternatively, the Chartered Institute of Arbitrators – Irish Branch or one of the


other bodies listed might be the preferred option if neither of the above area of
expertise was required. For instance, if the dispute were purely a quantity
surveying issue then the Society of Chartered Surveyors might be more
appropriate.

Department of Finance Page 83


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

12 Completing the Schedule Part 2

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

12. Completing The Schedule Part 2


The Contractor completes the Schedule part 2.

12.1 Section A
This section contains the addresses for sending notices and other
communications to the Contractor and is as important here as it is in part 1 of
the Schedule.

12.2 Section B
The Contractor states here if he intends to provide a parent company guarantee
for tender purposes.

12.3 Section C
This section contains the Contractor’s Works proposals
See notes in relation to the Works Proposals.

12.4 Section D
This section contains the Dates for Substantial Completion and will be
completed by the Contractor only if the Employer has not set out the relevant
date(s) in part 1. However, the Contractor is not permitted to insert any dates
for Sectional completion.

12.5 Section E
This section is where the Contractor sets out his tendered hourly rates for
labour and related costs – e.g. PRSI, tool money, travelling time and country
money etc. in respect of Craftspersons, General Operatives and Apprentices.

He also sets out here:

ƒ His tendered percentage addition for materials


ƒ His tendered percentage addition or deduction for costs of plant
ƒ his tendered rate of delay costs per Site Working Day (for the entire
Works or portions of the Works) – (Note – if the tendered delay costs are left
blank by the Contractor or are stated as a negative, they are to be read as zero).

Department of Finance Page 85


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

13 Works Requirements, Works


Proposals and Pricing Document

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

13. Works Requirements, Works Proposals and


Pricing Document
13.1 Works Requirements
These contain the Employer’s requirements for the Works

It is also important that the Contractor is provided with all relevant information
so as to enable him to price the risks being imposed on him. The Employer
should possibly furnish:

ƒ site surveys subject to such caveats as may be appropriate (eg, that


interpretation is the responsibility of the Contractor)
ƒ archaeological surveys
ƒ utility details
It is essential therefore that the Employer does not proceed to tender
prematurely (ie, before fully detailed Works Requirements are prepared) despite
any pressures on him to do so.

In the case of a Design and Build Contract the Works Requirements will contain
a robust output specification or specimen design so that the Contractor can fully
understand and price what is required of him and so that the Employer will get
what he requires.

Archaeological Surveys can range from a desk study level of detail, to a field
investigation with geophysics and investigation trenches, depending on the
known history of the site and the area. Fieldwork associated with archaeology
requires permissions from the NMS of the DoELG, and can involve a significant
lead-in time. It is clearly important, when the risk associated with archaeological
artefacts is being transferred to the Contractor, that the level of prior
investigation is selected to manage that risk transfer effectively, so that it is
appropriate to transfer it, and that such transfer represents value for money.

Utility details would be approached initially by researching the as-constructed


records of the Utilities in question and from local knowledge. This might be
followed by cable detection surveys, and trial trenches to confirm the positions
of buried services.

Again these approaches represent a continuum of prior effort by the Employer


to manage risk to a level where it can be effectively transferred to the
Contractor.

13.2 Works Requirements Documents


The documents containing the Works Requirements provided by the Employer
are identified in Part One of the Schedule.

The Works Requirements should include, inter alia, the following items

Department of Finance Page 87


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Traditional Contracts Design & Build Contracts

Preliminary Particulars Preliminary Particulars


a. The name, nature and location of the a. The name, nature and location of the
Works; Works;
b. A general description of the Works b. General description of the Works
c. The names and addresses of the Employer c. The names and addresses of the Employer
and Consultants and Consultants

Consents Consents
a. Planning and other consents obtained by a. Planning and other consents obtained by
the Employer. Refer to Guidance Note For the Employer. Refer to Guidance Note For
Public Works Contracts – Appendix Public Works Contracts – Appendix

The Site The Site


a. Site boundaries a. Site boundaries
b. Means of access b. Means of access
c. Restrictions on access c. Restrictions on access
d. Position of the Works d. Position of the Works
e. Information on adjacent/abutting structures e. Information on adjacent/abutting structures
f. Limitations on use of (if any) f. Limitations on use of (if any)
g. Work to be carried on the site by the g. Work to be carried on the site by the
Employer’s Personnel or others Employer’s Personnel or others
concurrently with the Works concurrently with the Works
h. Facilities of the Employer to be operated h. Facilities of the Employer to be operated
and maintained by the Contractor and maintained by the Contractor
i. Specific site rules and regulations i. Specific site rules and regulations

Sections Sections
a. Definition of sections into which the Definition of sections into which the Works are
Works are divided for purposes of divided for purposes of sectional completion
sectional completion

Drawings, Specifications, Schedules Drawings, Specifications, Schedules and


and Reports Reports
a. General arrangement, working and Note that for Design and Build Contracts, such
construction drawings. information can consist of an output
b. Materials and Workmanship specifications specification setting out the functional
c. Performance specifications applicable to requirements that the facility should
contractor designed or specialist designed accommodate together with the expected
elements of the works. functional life, maintenance requirements, etc.
or it can contain a full specimen design.

A number of options exist:


a. Pure Output specification
b. Output specification and specimen design
c. Output specification and specimen design
which cannot be changed
d. More developed design

Specialists Specialists
a. Designs to be prepared and/or works to a. Designs to be prepared and/or works to
be undertaken by Specialists be undertaken by Specialists
b. Novated specialists including details of the b. Novated specialists including details of the
original appointment and form of novation original appointment and form of novation
agreement agreement

Department of Finance Page 88


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Traditional Contracts Design & Build Contracts

Restrictions and Obligations Restrictions and Obligations


a. Limitations on working hours a. Limitations on working hours
b. Hoardings, fences, screens, temporary b. Hoardings, fences, screens, temporary
roofs, advertising rights roofs, advertising rights
c. Maintenance and protection of existing c. Maintenance and protection of existing
services on, under or over the site services on, under or over the site
d. Execution of work in a specific order d. Execution of work in a specific order
e. Road closure restrictions, alternative route e. Road closure restrictions, alternative route
restrictions. restrictions.
f. Maintenance of specific temperature or f. Maintenance of specific temperature or
humidity levels humidity levels
g. Temporary accommodation and facilities g. Temporary accommodation and facilities
for the use of the Employer including for the use of the Employer including
heating, lighting, furnishing and attendance heating, lighting, furnishing and attendance
h. Installation of telephones and facsimile h. Installation of telephones and facsimile
machines for the use of the Employer machines for the use of the Employer
i. Any other obligation or restriction. i. Any other obligation or restriction.

Health & Safety Health & Safety


a. Appointment of PSCS a. Appointment of PSDP
b. Appointment of PSCS

Contract Contract
Form of Contract Form of Contract
Model forms as appropriate Model forms as appropriate
a. Form of performance bond a. Form of performance bond
b. Form of parent company guarantee b. Form of parent company guarantee
c. Form of novation and guarantee deed c. Form of novation and guarantee deed
d. Form of appointment of project supervisor d. Form of appointment of project supervisor
for construction stage only for construction stage only
e. Form of appointment of project supervisor e. Form of appointment of project supervisor
for construction stage and design process for construction stage and design process
f. Form of appointment of project supervisor f. Form of appointment of project supervisor
for design process only for design process only
g. Form of professional indemnity certificate g. Form of professional indemnity certificate
h. Form of collateral warranty h. Form of collateral warranty
i. Form of novation i. Form of novation
j. Form of rates and conditions of j. Form of rates and conditions of
employment certificate employment certificate
k. Form of bond – Unfixed works items k. Form of bond – Unfixed works items
l. Form of retention bond l. Form of retention bond
m. Form of conciliator's agreement m. Form of conciliator's agreement
n. Form of bond – Conciliator's n. Form of bond – Conciliator's
recommendations recommendations
Owner controlled insurances (if required) Owner controlled insurances (if required)
Arbitration rules to apply Arbitration rules to apply

Contractor’s Documents Contractor’s Documents


a. Documents to be provided a Documents to be provided
b. Submittal procedures b. Submittal procedures
c. Provision of data to facilitate the Employer c. Provision of data to facilitate the Employer
and/or other contractors and its timing and/or other contractors and its timing
d. Procedures which the Contractor is to d. Procedures which the Contractor is to
follow in carrying out his design. follow in carrying out his design.

Department of Finance Page 89


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Traditional Contracts Design & Build Contracts

Reports Reports
a. Special reporting requirements. Eg: a. Special reporting requirements. Eg:
planning software to be used. planning software to be used.

Confidential Matters Confidential Matters

Quality Assurance and Testing (Where Quality Assurance and Testing (Where
not contained in the Specifications) not contained in the Specifications)
a. Quality assurance procedures a. Quality assurance procedures
b. Inspections b. Inspections
c. Items which are to be inspected or tested c. Items which are to be inspected or tested
before delivery to the Site including details before delivery to the Site including details
of the inspection or test of the inspection or test
d. Tests, description of the tests to be carried d. Tests, description of the tests to be carried
out by the Contractor, the Employer’s out by the Contractor, the Employer’s
Representative and others including those Representative and others including those
which must be passed before Substantial which must be passed before Substantial
Completion. Completion.

Title Title
a. Statement of any materials from excavation a. Statement of any materials from excavation
and demolition to which the Employer will and demolition to which the Employer will
retain title. retain title.

Notes: Refer to Standard Template Public Works Tender Document.

Contracting authorities should consider the risks of including site


surveys, site investigation reports, archaeology reports, etc. in Works
Requirements. An alternative would be to provide such information
with tender documentation as relevant background information;
notwithstanding this, such documents should be accurate and
proportionate to the nature and scale of the proposed Works.

13.3 Works Proposals


These will include method statements, Contractor’s design and any other
information required by the Employer in relation to the carrying out of the
Works

Example:
Works proposals from the Contractor will vary depending on whether the Contract is
Traditional or Design and Build.

With Traditional, the Contractor would be likely to prepare his intended sequence of work,
his programme, his resource allocation and his method statements as an integrated package of
information, in response to the Contract Documents, including whatever constraints are
stipulated by the Employer therein.

In a civil engineering project, for example, he would indicate how he proposed to deploy
available working space around structures, showing locations where he might safely stockpile
excavated material, or locate concrete batching plant and aggregate stockpiles materials, or

Department of Finance Page 90


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

the like. Alternatively, he would outline other arrangements he may have made to obtain
additional lands, licences and permits in order to free up working space on a particularly
congested site. His sequences would address the question of re-use of materials, and disposal
of C&D wastes. If he considers that Road Closures are required to perform the works, he
would outline their sequence, duration, alternative routes to be used, and the like.

His proposed working methodologies would be described, including any measures for
environmental or HSW protection.

With Design and Build, the Works Proposals will include information similar to the foregoing,
but also the Contractor’s Design itself, including drawings of temporary and permanent
Works, finishes schedules, calculations and all necessary information to enable the ER to
technically assess the proposal in Tender Appraisal.

13.4 The Pricing Document


The Pricing Document can be a bill of quantities (traditional contracts only),
contract sum analysis or pricing schedule.

Its format and content should facilitate the following:

ƒ Evaluation of tenders;
ƒ Interim payment;
ƒ Valuation of change orders;
ƒ Calculation of price variation entitlements;
ƒ Recording and classification of costs in accordance with the CWMF.
Subject to the foregoing, bills of quantities (if used) should be prepared in
accordance with the standard methods of measurement approved by the GCCC
and should incorporate any GCCC amendments. Refer to Guidance Note.

Where bills of quantities are not provided by the Employer, such as for design
and build contracts, the Pricing Document will, subject to the foregoing, be
broken down to an acceptable level such as milestones. This detail however is
unlikely to be sufficient for the valuation of change orders and the Contract
Sum should be further broken down into parcels of work of similar character.

The following would be an example of such a trade breakdown for design and
build building contract. It is unlikely that all the headings given will be required
for a every project and in some cases the complexity of the work may require
additional parcels or sub-division of those listed. The breakdown should be given
separately for each building or discrete section of work.

Department of Finance Page 91


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Preliminaries Roofing and Cladding and Waterproofing


- Management, supervision and site - Each covering material separately including
administration all fittings, labours, etc. and in the case of
- Plant, tools and vehicles slate and tile including battens and
- Temporary works underfelt
- Health and safety - Metal flashings and gutters (but may be
- Transport included with coverings if not of significant
- Temporary accommodation value)
- Waste management - Damp proofing and tanking
- Insurances - Paving including skirtings, etc
- Consents - Roofing including skirtings, gutters, etc
- Form and Conditions of Contract
- Programme contingency
Woodwork – separately for softwood and
- Special obligations and restrictions
hardwood
- Bonds
- Carcassing to floors, partitions, etc.
- Other matters
- Prefabricated trusses
- Floor and wall boarding, battens, framing
Demolition
and fillets
- Each building separately
- Unframed second fixings
- Doors, door frames and linings
Alterations
- Windows and frames
- Each item of alteration work separately
- Stairs and balustrades
on a ‘room by room’ basis.
- Fittings
- Insulation
Excavation and Earthwork
- Ironmongery
- Site clearance, all excavation, supports,
surface treatment and disposal
- Filling – separately for each material Structural Steelwork
- Underpinning - Unfabricated steelwork
- Fabricated steelwork
Piling - Built-up members
- Each type separately - Corrosion protection and other coatings

Concrete Metalwork – separately for each material


- All unreinforced concrete - Windows and frames
- All reinforced concrete - Doors and frames
- Formwork - Stairs
- Reinforcement - Balustrades
- Precast units cast separately - Other composite items
- Composite, hollow block or other - Covers, gratings, plates, bars, etc
special construction each separately - Sheetmetal coverings

Brickwork, Blockwork and Stonework


Plumbing and mechanical engineering –
- All work separately for each kind of
separately for each system (e.g.
brick, block or stone including all
rainwater, sanitary, cold water, hot
labours, etc.
water, heating, air conditioning)
- Damp proof courses and sundries not
- Pipework
included above
- Ductwork
- Equipment and fittings
- Insulation
- Controls

Department of Finance Page 92


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Electrical installation – separately for Drainage and Site Services


each system - Pipe trenches and beds
- Equipment, control gear and fittings - Pipes – separately for each type
- Conduit, trunking and cables - Manholes & Chambers

Finishes – separately for each material Surface Pavings, Fencing and


- Walls and ceilings Landscaping
- Floors - Pavings by type, edgings,
- Suspended Ceilings - Fencing
- Dry linings and partitions - Grassing and landscaping

Glazing Fittings Equipment and Furniture


- Glazing generally - By type
- Special glazing
Design Fees
- Each service listed
Painting and Decorating
- New work internally
- New work externally
- Redecoration internally
- Redecoration externally

Note: Specialists should be included under the appropriate subdivision.

Where the breakdown is to be in accordance with a standard table of elements,


consideration should be given to allocation on a "trades within elements" basis.

Department of Finance Page 93


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14 Commentary on the Conditions

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14. Commentary on the Conditions


14.1 Definitions
Reference sub-clause 1.1

"Contractors Documents"

Means drawings, specifications and other written (including electronic) material


the Contractor prepares or uses relating to the Works, gives or is to give to
the Employer or other person

ƒ Under the Works Requirements


ƒ Under any Legal Requirements
ƒ To obtain any consent
In connection with a value engineering proposal (sub-clause 4.8).

"Contractor Things"

Means things the Contractor or Contractor's Personnel use (on or adjacent to


the Site) to execute the Works but excludes Works Items.

"Contractor's Personnel"

The term is very widely defined.

It means the Contractor’s Representative, his supervisor and all sub-contractors,


and other persons including all employees (of the Contractor and sub-
contractors) and other persons assisting the Contractor to carry out the Works
and working on or adjacent to the Site.

"Site"

Means any place the Works are to be carried out, or provided by the Employer
for the Works, where the Contractor is to operate Employer’s Facilities, or

Any places that is identified as part of the Site by the Works Requirements.

"Specialist"

Means

ƒ A Subcontractor or supplier of a Works Item named in the Contract


ƒ Contractor’s Personnel who do or are to do design
ƒ Contractor's Personnel specifically stated to be Specialists in the Works
Requirements

Department of Finance Page 95


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

"Site Working Day"

Means a day on which the Contractor is to carry out the Works.

"Substantial Completion"

This term is very widely defined.

The Works are complete and can be taken over and used for their purpose
when:

There are no defects save

ƒ ones accepted by the Employer (sub-clause 8.5.4)


ƒ minor defects
- that do not prevent use of Works for their purpose
- the Employer’s Representative agrees the Contractor has reasonable
grounds for not promptly fixing them
ƒ those whose fixing will not prejudice safe and convenient use of the Works
(or part)
All tests have been passed (that must be passed before Substantial Completion)

Documents required before Substantial Completion have been furnished

Collateral warranties have been provided in relation to the Works or relevant


part

See commentary on Substantial Completion below.

"Interpretation"

Reference sub-clause 1.2

Any reference to a "working day" is to a day that is not a weekend day, a public
holiday under the Organisation of Working Time Act 1997 or Good Friday.

"Inconsistencies"

Reference sub-clause 1.3

The order of precedence of the Contract documents is

1 The Agreement
2 The Letter of Acceptance
3 The Schedule
4 The Conditions
5 The Works Requirements
6 The Pricing Document

Department of Finance Page 96


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

7 The Works Proposals


8 Any other Contract documents

14.2 Health and Safety


Reference sub-clauses 1.1 and 2.5

In the Traditional Form, the Contractor is obliged to ensure the Works are
constructed so as to be safe and without risk to safety and health and so as to
comply fully in all respects with the relevant statutory provisions

The Contractor also warrants that he is a competent person within the meaning
of that term in the Safety, Health and Welfare at Work Act 2005 for the
purpose of ensuring that the Works are safely constructed and comply with the
relevant statutory provisions.

In the Design and Build Form the Contractor is obliged to ensure the Works
are designed and capable of being constructed so as to be safe and without risk
to safety and health; that they can be maintained safely and without risk to health
during subsequent use; that they comply with the relevant statutory provisions.

In both Forms the Contractor warrants that he is competent to carry out the
Works and will allocate sufficient resources so as to comply with the relevant
statutory provisions.

The terms used in the clause including the "competent" and "relevant statutory
provisions" are to be construed pursuant to section 2 of the Safety, Health and
Welfare at Work Act, 2005.

The provisions in the Contracts in this regard are quite short and simple but as the laws
applicable to health and safety are now so strict in this jurisdiction, that is all that is
required.

14.3 Loss, Damage and Injury


Employer’s Risks – Loss and Damage to the Works and Contractor’s
Care of the Works

Reference sub-clauses 3.1 and 3.2

The Employer bears certain risks in relation to loss of or damage to the Works.
These include the usual uninsurable risks relating to war, invasion, pressure
waves caused by aircraft, and contamination relating to explosive nuclear
weapons etc. The risk of terrorism is included as an Employer’s risk but only if
this is a permitted exclusion from the Contractor’s insurances relating to the
Works.

The Employer also bears the risk of damage to the Works from the use or
occupation of the Works by the Employer or the Employer’s Personnel (other
than as provided for in the Contract) but excluding loss or damage caused by

Department of Finance Page 97


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

the negligence of the Contractor or those for whom the Contractor is


responsible or which is caused by the Contractor’s breach of contract.

If Sub-clause 3.8 applies (only if so stated in the Schedule part 1D) the Employer
will bear responsibility for damage to existing facilities due to the usual property
risks of fire, flood, storm, pipes bursting etc.

The Employer also bears the risk of his design of the Works unless the design is
covered by professional indemnity insurance taken out by the Contractor. Sub-
clause 3.1(6)

Example:

If the Works are damaged because of any of the causes referred to in sub-clause 3.1 the
Employer will bear the risk and will have to pay to have the Works reinstated subject to an
entitlement to terminate the Contractor’s responsibility to complete the Works.

The Contractor has otherwise got full responsibility for the care of the Works and bears the
risk of loss and damage to the Works including Works Items, Contractors, Things, Works
Requirements, Works Proposals, and Contractor’s Documents together with anything the
Employer provides to the Contractor for the Works. These items are defined in the
Contract as "Risk Items".

The Contractor’s obligation runs from (and includes) the Starting Date up until
the issue of the Certificate of Substantial Completion of the Works (or if
completed in sections – the relevant Section). If part of the Works is taken over
before Substantial Completion the obligation ends for that part when the
Employer takes it over.

The Contractor still has some responsibility for damage to the Works after the
date of Substantial Completion. These include damage arising from defects or
from matters that occurred before Substantial Completion. In addition if any
damage to the Works is caused after Substantial Completion by activities of the
Contractor or those for whom he is responsible this is at the Contractor’s risk.

The Contractor is obliged to repair any loss or damage to any of the Risk Items
(this is irrespective of responsibility) and must do so at his own expense if the
insurance proceeds are insufficient for the purpose. The Contractor must in any
event repair any damage to the Works occurring before the issue of the Defects
Certificate if the Employer instructs him to do so (subject to payment for the
Works in the event that the risk is not one for which the Contractor is
responsible).

Insurance of the Works

Reference sub-clause 3.3, Schedule (part 1D)

The Contractor must insure the Works and the other Risk Items, against loss or
damage and must procure that the Contractor, Employer, and other persons
nominated by the Employer are named as co-insured under the policy of
insurance. The insurance is to be kept in place until the date of the Certificate

Department of Finance Page 98


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

of Substantial Completion. Where there are Sections the insurance must remain
in place until the Substantial Completion of the Section in question.

The Employer may require in the Schedule (part 1D) that the insurance for any
Section or part of the Works which has reached Substantial Completion is to be
extended until Substantial Completion of the entire of the Works.

The Contractor must maintain the insurance of the Works between Substantial
Completion and the issue of the Defects Certificate in respect of damage for
which he is responsible.

The insurance level must include as a minimum for the full reinstatement cost of
the property, demolition and debris removal, delivery, professional fees, inflation
during the construction and reinstatement periods and profit. The Employer is
entitled to insert in the Schedule (part 1D) any other property belonging to the
Employer that is to be included in the insurance of the Works and the indemnity
limit for such additional insurance.

In the event of a claim against the insurance the insurance proceeds (excluding
the insured sum for professional fees to be paid by the Employer) are to be paid
into a bank account in joint names of the Employer and Contractor and are to
be paid out to the Contractor on the basis of interim certificates by the ER
relating to the rectification of the loss or damage. The Employer is entitled to
be paid out of the account for costs incurred by it in this regard and is also
entitled to the balance remaining in the account after rectification work.

Example:

If the Works are fully insured in accordance with the provisions of sub-clause 3.3. and if a fire
that arises on Site damages a substantial portion of the Works, then the Contractor would
typically be instructed to repair the damaged Works which includes demolition of the
damaged part, removal of the debris from the Site, and reinstatement. Additional professional
fees would be incurred in dealing with design. The Contractor would submit interim
statements in accordance with the provisions of the Contract and the ER would certify
payment on foot of these.

The Insurer of the Works would pay out the insurance proceeds which (other than
professional fees in the circumstances of a traditional contract) would be paid into a joint
bank account set up by the Employer in the joint names of the Employer and the Contractor.
These monies would be paid out on foot of interim certificates by the ER as stated above. In
relation to professional fees, assuming this was a traditional form of contract; the Employer
would discharge the additional consultant’s fees and would be paid out of the bank account.
Subject to any entitlement which the insurer might have, the Employer would be paid the
balance remaining in the bank account after payment for the reinstatement of the Works.

Indemnity and Liability

Reference sub-clauses 3.4, 3.5, 3.6, 3.7, Schedule (part 1D)

The Contractor provides a full indemnity to the Employer and the Employer’s
employees against all liability and loss of or damage to the Employer’s property
including the Site arising from the performance of the Contract. If the Employer
states in the Schedule (part 1D) that sub-clause 3.8 will apply, then the Employer

Department of Finance Page 99


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

bears the risk of existing facilities and their contents where owned by the
Employer and caused by the usual perils of:

ƒ Fire, storm, tempest, flood


ƒ Bursting or overflowing of water tanks, apparatus or pipes
ƒ Explosion, impact, aircraft
ƒ Riot, civil commotion or malicious damage
The indemnity specifically excludes any liabilities of the Employer to the
Contractor under the Contract and also anything covered by the Employer’s
indemnities under sub-clauses 3.5 or 6.2

The Employer in turn indemnifies the Contractor pursuant to sub-clause 3.5


against liability arising from the Employer’s negligence or property damage
unavoidably arising from the execution of the Works (in accordance with the
Works Requirements).

Note that this indemnity does not cover liability for death, injury or illness of Contractors
Personnel (i.e. those covered by the Contractor’s Employer’s Liability insurance cover).

The Contractor is obliged to provide Public Liability insurance with the


Employer and the Contractor as co-insured parties from the Starting Date until
the issue of the Defects Certificate (sub-clause 3.6.1).

The Contractor must take out Employer’s Liability insurance for his own
personnel and in relation to Sub-Contractors he must either ensure that the
Sub-Contractors maintain the insurance or otherwise cover the risk himself
(sub-clause 3.6.2).

The Employer provides for the indemnity limits in respect of the Contractor’s
Public Liability and Employer’s Liability insurances in the Schedule (part 1D).

The only noteworthy point here is that the Public Liability policy is taken out with the Employer
and the Contractor as co-insured whereas in the past in building contracts it would have been in
the sole name of the Contractor with an indemnity to the Employer as principal and in the
engineering form it would have been joint insurance.

The Contractor is required to ensure that the Public Liability and Employer’s
Liability insurances are in place in the event of his return to the site (in
connection with the Works) even after the Defects Certificate is issued (sub-
clause 3.6.4).

The Employer is entitled to provide in the Schedule (part 1D) that the
Contractor should put in place Professional Indemnity insurance cover. The
minimum indemnity limit will be inserted in the Schedule (sub-clause 3.7).

The Contractor if required to do so, must put in place Professional Indemnity


Insurance from the Starting date until the sixth anniversary of the Certificate of
Substantial Completion (unless another period is provided for in the Schedule).

Department of Finance Page 100


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The insurance must cover (retroactively if necessary) any design by the


Contractor of the Works and Works items.

The Employer would be likely to require Professional Indemnity insurance in


most if not all instances where the Contract is one with Contractor’s Design.
Professional Indemnity insurance covers errors or omissions in design work and
in other professional duties. The Employer should require that the Contractor
puts in place Professional Indemnity insurance in most cases where there is an
element of design being carried out by the Contractor or Specialists. It would
be normal to require that such insurances are kept in place for at least six years
after Substantial Completion. This is because the statute of limitations in respect
of Professional Liability will run for at least this period. It is also likely that such
defects will come to light within such a period.

The Employer should take care to monitor the Contractor’s insurances either
through the ER or directly through his own insurance advisors or by himself
particularly so as to make sure that the Contractor’s Professional Indemnity
insurance is renewed each year unless (which would be most unusual – one
insurance policy is actually taken out to cover a six year period).

This is particularly important in the case of Professional Indemnity insurance


because such insurance operates on a "claims made" basis. That is to say, any
claim is covered by the insurance that is in place during the year in which the
claim is made.

Thus if the Contractor discontinues his Professional Indemnity insurance after 2


years and a claim is made in year 3 there will be no cover. The Employer in
completing the Schedule will also wish to consider the minimum indemnity limit.
This should be a reasonable sum by reference to the value of the Works, the
importance of the design work being carried out and the effect that a failure of
such design work would have. One would expect that Professional Indemnity
cover nowadays would be at the very least €6.5 million and possibly €10 million
in the aggregate.

The Employer is also entitled to stipulate that the professional indemnity


insurance will cover each and every event. In such a case the full insured sum
would be available for every claim raised by the Employer (within a particular
year of cover). However, the normal Professional Indemnity insurance by
Contactors is an aggregate sum for each year. That is to say a sum insured of
€10 million will cover all claims made against the Contractor during the year in
question. The risk with this type of cover is that the entire insured amount
could be used up by one single claim and in the event of other claims arising
there would be no insurance cover left to meet them.

It is provided in the Schedule that the sum indemnified may include defence
costs. The Employer should be careful if prosecuting a claim against an Insured
where such costs are included in the cover, to take cognisance of this fact as, if a
substantial legal defence was mounted to any claim the legal costs incurred by
the defendant would eat away at the limit of indemnity leaving a diminishing
"pool" for the Employer to claim against.

Department of Finance Page 101


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Contractor must place his insurance with insurers approved by the
Employer and may only exclude from cover the exclusions listed in the schedule
(part 1D).

Any liability insurance where the Employer and Contractor are co-insured must
include various provisions so that the Insurer cannot claim against either of the
insured persons themselves and that they are each treated as if they were
separately insured.

The Contractor is obliged contractually to comply with all the terms of the
insurance policies.

The Contractor must provide evidence to the Employer that the insurances are
in effect and must provide copies of policies and receipts for premiums in this
regard. An Insurance Broker’s Certificate (or one from an underwriter) may be
provided in the case of Professional Indemnity insurance.

This is particularly important in the context of firstly checking on the Contractor’s insurances in
advance of his coming on site and secondly keeping a check on the Contractor’s insurance during
the course of the Works.

The Contractor must notify the Employer promptly of any cancellation, renewal,
non-renewal or material reduction of the terms of any policy.

While this clauses imposes a contractual obligation on the Contractor to notify of these events it
is imperative that the Employer or the E.R. keep an ongoing check on Contractor’s insurances as
it is possible that a Contractor who is in a position whereby some of his insurances are being
cancelled would not inform the Employer or the E.R. of this fact readily.

The Employer is of course entitled to take out insurance should the Contractor
fail to maintain them. However, it would not be possible for the Employer to
take out Professional Indemnity insurance in respect of Contractor or at least
not to do so without great difficulty.

The Works Requirements may make provision for an owner controlled


insurance programme and in such a case the provisions of clause 3 are to be
amended accordingly (sub-clause 3.9.9).

Example:

If the Works involve very substantial and complex work over many adjoining areas with
numerous Specialists it might be deemed appropriate by the Employer to control the
insurance programme rather than running the risk of any insurance failures. However, careful
investigation would need to be done by the Employer in this regard particularly in relation to
the cost of taking out such a programme as it is unlikely to be as economic for an Employer
to take out such insurance as it would be for a Contractor to do so.

Department of Finance Page 102


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14.4 Management
Co-operation

Reference sub-clause 4.1

The Contract provides for co-operation between both parties but very
importantly states that such co-operation does not alter the rights or duties of
the parties or imply any admission of responsibility.

Examples of co-operation are given such as:

ƒ Negotiation of agreements provided for in the Contract;


ƒ Value Engineering;
ƒ Use of most effective and compatible electronic and other methods of
communicating and recording;
ƒ Efficient order and timing of information provided for in the Contract;
ƒ Minimising the effects of suspension;
ƒ Efforts by the Contractor to minimise delay and Compensation Events and
their effects; and
ƒ Contractor’s effective management.
This provision permits either the Employer or the Contractor to request
consultations, clarifications, workshops etc. even though not provided for
elsewhere in the Contract.

The parties can (if circumstances otherwise permit) also enter into without
prejudice communications which would enable them to speak freely without fear
of any admission being used against them – (sub-clause 4.1.4).

Contractor’s Representative and Supervisor

Reference sub-clause 4.2

The Contractor must appoint the Contractor’s representative before the


Starting Date with full authority to act on his behalf (sub-clause 4.2).

He must also appoint a full-time supervisor on site with full authority to receive
instructions. This can be the same person as the Contractor’s Representative
(sub-clause 4.2).

The ER may require removal of the representative or supervisor due to


misconduct, negligence or incompetence (sub-clause 4.2.3).

Employer’s Representative

Reference sub-clause 4.3

Department of Finance Page 103


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Appointment of Employer’s Representative

The Employer appoints the Employer’s Representative (ER) to administer the


Contract (note – likely to be his consulting engineer or architect but not
necessarily so under the Contract).

Example:

The Employer may wish to consider what profession is best suited to administer the Contract
taking into account the type of contract that it is and the best method of having it
administered. The Employer might consider that an Architect would be the best
administrator in the context of building works while an Engineer would be the best person to
administer the carrying out of a road or waterworks contract. However, under particular
circumstances the Employer might consider that a person with pure project management
experience and qualifications might be best suited to administer some very large scale
projects crossing over the divide between pure building and civil engineering with a view to
coordinating a large number of consultants.

The Employer should name the ER in the Schedule (part 1A).

Otherwise – the Employer must appoint the ER promptly after the Contract
Date and must notify the Contractor of his identity (sub-clause 4.3.1).

Any limits on the authority of the ER must be stated in the Schedule (Part 1A).

See the reference to this above in relation to the Schedule Part 1A where such
limitations are set out.

The Employer must give approvals in relation to any matters on which the
authority of ER is limited.

Example:

If the authority of the ER is limited in relation to say adjustments to the Contract Sum for a
single instruction then the Employer must be prepared to provide approvals when required
by the ER to do so in this context. The Employer must be aware that approvals will often be
required at relatively short notice and that unless they are approved promptly by him this
may hold up the provision of instructions to the Contractor with potential resultant delays to
the Works.

Replacement of ER

Reference sub-clause 4.3.5

Where relevant – the Employer can replace the ER (presumably he would in


such a case dismiss the ER pursuant to the terms of his conditions of
engagement) (sub-clause 4.3.5)

Department of Finance Page 104


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

In a situation where the Employer’s Representative is not performing as he is obliged to do so


pursuant to his own Conditions of Engagement then it may be necessary for the Employer to
terminate his appointment. However, the Employer should ensure that a replacement is
appointed as quickly as possible as the Employer will be obliged to carry out the ER’s
functions in the interim. The carrying out of the ER’s functions will place an additional
burden on the Employer to ensure that these functions are carried out properly and
professionally in order to avoid any disputes at a later stage

ER’s Communications

Reference sub-clause 4.4

The various types of ER’s communications are set out at sub-clause 4.4 of the
Contract. They may consist of:

ƒ Directions;
ƒ Change Orders;
ƒ Objections under sub-clause 4.7;
ƒ Opinions, assessments determinations and certificates;
ƒ Other communications in accordance with the Contract.
ER’s Instructions

Reference sub-clause 4.5

The Contractor must comply with any instruction of the ER (sub-clause 4.5.1).

The Contractor is entitled to give notice under clause 10.3 if he feels that an
instruction which the ER has issued as a direction is in fact, a Change Order.
The matter will then be resolved by the procedure set out in sub-clauses
10.3/10.5.

The Contract explicitly says that the ER may not give a Change Order after
Substantial Completion (except in relation to Defects or work carried out after
Substantial Completion) (sub-clause 4.5.3).

If the ER is of the view that it is physically impossible or illegal to carry out the
Works in accordance with the Works Requirements or if it is necessary in his
opinion, for the completion of the Works, he must give a Change Order and
must do so within the time allowed in sub-clause 4.11 (sub-clause 4.5.4).

ER’s instructions must in the normal way, be given in writing although this will
not be necessary in cases of emergency, provided the instructions are confirmed
in writing as soon as practicable.

Department of Finance Page 105


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Works Proposals

Reference sub-clause 4.6.1

It is the responsibility of the Contractor to make sure that the Works Proposals
submitted by him comply with the Works Requirements.

In respect of any Works Proposals that do not comply with the Contract, the
Works Requirements or Legal Requirements or that are impossible to comply
with, the Contractor must propose a change to the Works Proposals. The
Change is submitted to the ER (sub-clauses 4.6.1 and 4.6.2).

Submissions by Contractor to ER

Reference sub-clause 4.7

A detailed procedure for the making of any submissions required under the
Contract by the Contractor to the Employer is set out in the Contract (sub-
clause 4.7).

In the case of any document to be submitted to the ER:

ƒ The Contractor must give it together with all supporting documentation;


and
ƒ If requested, further additional information
ƒ Sufficient to enable the ER to review the matter.
The Contractor is not entitled to implement any submission until the period for
objection is ended and if the ER objects the Contractor must make a new
submission within the relevant period (sub-clauses 4.7.7 and 4.7.8).

Objecting to Submissions by Contractor

Reference sub-clause 4.7.2

The ER may object to submissions made by the Contractor. Such an objection


must be made within 10 working days of the receipt by him of sufficient
information to enable him to review the matter (sub-clauses 4.7.2 and 4.7.4).

The Contractor may be required to provide documents for the consideration by the Employer’s
Representative. The Employer should ensure that he is given all copies of such submissions by
the ER so that he will be in a position to make any objection that he deems appropriate to such
submissions. Obviously, the Employer would only make such objections in accordance with the
Contract (see below).

This is an important point in that there is no longer any approval by the ER and therefore there
will be no opportunity for a Contractor to allege that the Employer has "assumed ownership of"
a proposal by the Contractor, giving credence for a claim for compensation in circumstances
where say, the proposal resulted in additional cost to the Contractor.

Department of Finance Page 106


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The grounds for objection by the ER to a submission by the Contractor are


clearly set out at sub-clause 4.7.10 as follows:

To proceed on foot of the submission:

ƒ Would not comply with the Contract


ƒ Would have an adverse effect on the Employer or the public interest
ƒ Would impose an obligation on the Employer that the Contract does not
require him to bear
ƒ Would be contrary to a Legal Requirement
ƒ Would have an adverse effect on the Contractor’s ability to comply with the
Contract
ƒ Any other stated ground in the Contract

Consideration of Value Engineering Proposals

Reference sub-clause 4.8

The Contractor is entitled to submit value engineering proposals to the ER if


they would reduce the Contract Sum, accelerate the time for execution of the
Works or provide some other benefit to the Employer but with no additional
cost. In point of fact, as, the Contractor is not to be paid any extra for doing so,
it is highly unlikely that he would make any such proposal unless it represented a
significant benefit to him in terms of time or money.

The Employer may agree to, or reject value engineering proposals from the
Contractor and any such rejection is conclusive.

The Employer should again ensure that he is in receipt of all such proposals in a
timely fashion so that he can make a considered decision in relation to the
proposal and agree to it or reject it. (sub-clause 4.7)

It is noteworthy that if there are any design changes to the Works arising out of or as part of the
value engineering proposals, the Contractor must undertake this design and be responsible for it
(sub-clause 4.8.4).

Programme

Reference sub-clause 4.9

The Contractor must submit a detailed programme to the ER before the Starting
Date unless he has already done so with the Works Proposals updated as
necessary to show actual programme dates.

The requirements for the content of the programme are set out at sub-clause
4.9.1 at items (1) to (9) and are very comprehensive indeed. There is provision
for the ER to relax these requirements. Nevertheless, the ER should give careful
thought to any such relaxation.

Department of Finance Page 107


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

There are two provisions in the programming requirements of the Engineering


Works forms which are not in the Building Works forms and they relate to the
order and times for carrying out "trial operation" of Works Items and the
method by which the Contractor proposes to carry out the Works and any
temporary works.

It will be most important for the Employer in conjunction with the ER to ensure that the
Contractor’s programme is of an adequate quality so that it can be used as a tool to monitor the
Contractor’s Works and properly assess progress etc. It this regard it is noteworthy that there
are sophisticated computer programmes available for the purpose of assessing programmes to
ascertain their validity. It would be particularly important for the Employer that the
Contractor’s programme does (as it is required to do under sub-clause 4.9.2) provide adequate
periods of time for the Employer to comply with his obligations.

The Contractor must when directed by the Employer’s Representative submit a


revised programme where actual progress does not equate to the initial
programme. The revised programme must show any delay.

All programmes should show items 1-9 as set out in Clause 4.9.1 of the
Contract (subject to any relaxation of the requirements by the ER) (sub-clause
4.9.4).

If the Contractor fails to submit a revised programme within 15 working days of


a request from ER the Employer may withhold 15% of any payment due until it is
submitted.

Progress Reports

Reference sub-clause 4.10

Progress reports must be provided by the Contractor to the ER monthly from


the Starting Date to the completion of all work still outstanding at Substantial
Completion. Thus progress reports are required during the Defects Period in
respect of remedial work.

Progress Reports are extremely important and it will be essential for the
Employer to receive copies of them from the ER so that the Employer is kept
fully up to date on progress and can query the issues that he may wish to, when
attending at meetings with the ER and if necessary Site meetings. In particular,
and as referred to above it will be important for the Employer to monitor with
the ER details of when any Works Items or other things to be provided by the
Employer will be required and any that the Contractor says are outstanding. It
would also be vital where the Contractor has provided details of anything that
might have an adverse affect on the execution of the Works and where the
Contractor proposes that the Employer or the Employer’s Personnel take steps
to reduce those risks.

The Contractor must furnish progress reports within 7 days after the end of
each relevant month.

Progress Reports must include items 1-12 in sub-clause 4.10.2 unless this
requirement is relaxed by the ER or by the Works Requirements.

Department of Finance Page 108


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The form of the progress reports must be agreed with the ER.

Notice and Time for Employer’s Obligations

Reference sub-clause 4.11

The Contractor is required by the Contract to give at least 10 working days


notice of the date by which he requires instructions, Works Items or other
things from the ER or the Employer

The date by which the ER or the Employer must provide any required instruction,
Works Item or other thing to the Contractor is the latest of:

ƒ Any date shown in the Contract


ƒ Any date shown in the Contractor’s programme;
ƒ Any date for which the Contractor first notifies the ER that it is required
ƒ The date the Contractor actually needs it by reference to his progress.
(sub-clause 4.11.2)

Example:

In a case where the Employer is required to give the Contractor any required Works Items
or other thing then it would be most important that the Employer is aware of all relevant
dates by which such items will be required well in advance from the ER so that he is in a
position to provide the items in a timely manner. If the item is going to require a long lead-in
time from the Employer’s point of view it may be appropriate that the date is stated in the
Works Requirements so that the Employer can work to it in order to avoid any question of
late provision of information and any resultant delays.

Example:

The Contractor may require additional information which the ER is not able to give and
which only the Employer can provide and in such case it will be incumbent on the Employer
to provide the information/Works Items by the requisite dates. If it were the case that there
was no date in the Contract or the Programme or that the Works Item was not available by
either of those dates and it was clear that the Contractor’s actual progress meant he was not
nearly ready to receive the Works Item despite notifying that it was required then the
Employer would, through the ER point out to the Contractor that he was not entitled to
Works Items/instruction etc. until the item was actually required. It might also be the case
that the Programme provided is out of date, in which case until it is updated and provided by
the Contractor it would be his actual progress that would apply. However, the Employer
should bear in mind that such circumstances could give rise to a dispute as the Contractor
may well say that he is in fact ready for the information or the Works Item.

Documents

Reference sub-clause 4.12

The Contractor must keep all relevant documents on Site including contract
documents.

Department of Finance Page 109


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The documents to be kept on Site include:

ƒ Instructions from the ER


ƒ Contractor’s Documents
ƒ Details of all instructions and Contractor’s Documents showing the dates of
issue etc.
ƒ Where requested by the ER all publications named in the Contract and the
Contractor’s Documents.

Example:

If a situation arose where the Employer became concerned that he was not being made aware
by the ER of all instructions being issued to the Contractor (although this would be unlikely
to arise in practice) he could insist that the ER authorise him to inspect the Contractor’s
documents being kept on Site where, assuming the Contractor was in compliance with the
requirements of sub-clause 4.11 he could assess all instructions provided by the ER and all
Contractor’s Documents (sub-clause 4.12) together with a log of instructions showing the
dates of issue and subsequent revisions.

Contractor’s Management

Reference sub-clause 4.13

The Contractor must include details of his management arrangements in the


Works Proposals (sub-clause 4.13.2).

The Contractor is obliged to implement the arrangements and change them


where necessary for efficiency (sub-clause 4.13).

The Contractor is obliged to keep the ER fully informed about its arrangements
in advance and about their implementation. The Contractor is obliged to
furnish the ER with all information necessary to enable the ER to perform his
powers and duties (sub-clauses 4.13.5 and 4.13.6).

The Employer should ensure that the ER keeps the Employer in turn fully
informed about all of the Contractor’s arrangements so that he is in a position
to comment to the ER in relation to these where relevant.

Communications

Reference sub-clause 4.14

All communications are to be interpreted purposefully.

This means that in interpreting the clauses, the spirit of the Contract and its
purpose and the purpose of the relevant sub-clause are to be used. This is to
get the parties and their representatives (including legal advisors) away from the
old ways of interpreting provisions by simply parsing and analysing the words
(sub-clause 4.14.1).

Department of Finance Page 110


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

It is also noteworthy that communications by email are recognised as well as the


other more usual forms such as fax and post (sub-clause 4.14.3).

Meetings

Reference sub-clause 4.15

The Contractor's Representative must attend meetings as scheduled by the ER


He must arrange for any Contractor’s Personnel to attend if requested by the
ER.

The Employer could if he felt it was relevant and appropriate, have the ER invite
him to certain site meetings particularly if issues of relevance to him were likely
to be discussed. This would of course depend upon the Employer’s relationship
with the ER and the information that the Employer is in receipt of from the ER.
Of course, the Employer would only attend such a meeting for information
purposes and should not seek to give any instructions to the Contractor.

The Contractor is obliged also to notify the ER of any objection he has to the
minutes issued by the ER within 5 working days of receiving them (sub-clause
4.15.2).

Confidentiality

Reference sub-clause 4.16

The Employer must keep the Contractor’s rates and prices and other records
specified as confidential by the Contractor, confidential (sub-clause 4.16.2).

Note – the obligation ceases when the information is no longer commercially


sensitive and in any event within 5 years from when the information was given.

14.5 Contractor's Personnel


Contractor’s Personnel

Reference sub-clause 5

The Contractor is made specifically liable for all acts and omissions of
Contractor’s Personnel, including all Specialists and including their design work.
(Sub-clause 5.1). This is an important provision in that it removes one of the
problematic issues concerning nominated sub-contractors whereby a main
contractor was not liable for the design carried out by the sub-contractor. Now
the Contractor is fully liable as if the Specialist was a "domestic" sub-contractor.
(sub-clause 5.1)

Payment and Conditions of Employment

Reference sub-clauses 5.3, 11.4, Schedule (Part 1 J)

Copies of this very important sub-clause 5.3 must be prominently exhibited at


the Site.

Department of Finance Page 111


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Contractor must ensure that rates of pay and conditions of employment
comply with law and with any registered employment agreements (sub-clause
5.3.2).

The Contractor himself must comply with and must ensure that the employers
of all other work persons (i.e. subcontractors) comply with all of the obligations
in clause 5.3.3(1) to (8). This involves:

ƒ payment of all wages and other money due to work persons


ƒ making sure wages are paid in accordance with the Payment of Wages Act
1991 and are never more than a month in arrears
ƒ payment of all pension contributions and other amounts due to be paid on
behalf of the relevant person
ƒ making all deductions from payments to work persons required by law and
passing such deductions on as required by law
ƒ keeping proper records and producing them for inspection by the Employer
whenever required
ƒ the production of any other records re. rates of pay, pension and other
contributions for the Employer whenever required
ƒ respecting the legal right of work persons to be members of trade unions
ƒ observing all relevant safety law in relation to work persons on site and also
Industrial Relations Act, National Minimum Wages Act etc (sub-clause
5.3.3).
The Contract may state that the Employer is entitled to make random checks.
This will depend upon whether the Employer says in the Schedule part 1J that
sub-clause 5.3.3A (2) is to be included in the Contract (sub-clause 5.3.3A (2)).

The Employer may request and if he does so, the Contractor must provide to
him within 5 working days, a statement showing the wages and other payments
due in respect of each work person working for the Contractor and, in respect
of work persons not directly employed by the Contractor, ensure that the
relevant employer does the same.

If the Contractor does not comply, the Employer is entitled to estimate the
amount due to work persons and to deduct it from payments due to the
Contractor until satisfied that the persons have been paid. (sub-clause 5.3.6)

The Contractor must give a certificate together with each interim statement
stating that the requirements of payment to personnel etc. have been complied
with in relation to the Works the subject of the interim certificate. Failure to
do so, or to comply with the provisions of sub-clause 5.3 will render the
Contractor liable to the Employer for any investigation costs incurred. In
addition, no payment will be made to the Contractor for the work in question
until the certificate is furnished (sub-clause 5.3.7 and 11.4.4).

See comments on this issue at 11.11 above.

Department of Finance Page 112


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

If the Employer becomes suspicious at any stage that the Contractor is not in compliance
with his obligations in relation to payment and conditions of work persons he should request
pursuant to sub-clause 5.3.3, the production of full wage records in relation to work persons
as he is entitled to do pursuant to the contract. The Employer may, if he is entitled to do so,
make a random check requiring production of records but even if he is not he is entitled to
full wage records of work persons as referred to above and is also entitled to a statement
showing the amount of wages or other payments due in respect of each work person and if it
is somebody employed by a Specialist or sub-contractor, the Contractor is obliged to ensure
that that the Specialist or sub-contractor does the same.

If the information is not forthcoming then the Employer should estimate the amount that
should have been paid to the work persons in question together with contributions to their
pension etc, deduct the estimated amount and hold it until satisfied that the proper amounts
have been paid.

Sub-Contractors and Specialists

Reference sub-clauses 1.1 and 5.4

The Contractor is not entitled to sub-contract all of the Works.

In civil engineering contracts, the Contractor must submit details to the ER of


any Sub-Contractors (ie, including any Specialists) that it proposes to use for any
part of the Works (unless provided in the Contract or unless the Contract
provides for other procedures).

The term "Specialist" is defined in the Contract as:

ƒ A Sub-Contractor or supplier of a Works Item named in the Contract


ƒ Contractor's personnel who do or are to do design
ƒ Contractor's personnel stated in the Works Requirements to be Specialists
Where Specialists or other Contractor's personnel are specifically named in the
Contract, the Contractor is obliged to ensure that they are engaged for the
work in question. (They would be named by the Contractor in the Works
Proposal or, by the Employer in advance, in the Works Requirements.)

It may be that the Specialist named in the Works Requirement is already in a


contractual relationship with the Employer and in that case the Employer will
novate that Specialist Contract to the Contractor. In such a case, the Works
Requirements must include a copy of the Contract between the Employer and
the Specialist. The Contractor must then accept the novation (transfer) and the
Employer and the Contractor execute the Novation Agreement at the same
time as the Contract Agreement (see Model Form 9).

Unless a Specialist is named in the Contract, the ER cannot instruct the


Contractor to enter into a contract with that Specialist.

The Contractor is not entitled to allow to be terminated or to accept a


repudiation of his contract with a Specialist without first giving details to the ER.

Department of Finance Page 113


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

An exception to this obligation is when the Specialist becomes insolvent or has


committed a serious breach of health and safety law or has failed to put in place
or to maintain the required insurances.

If the Contractor does terminate his Contract with a Specialist, he must replace
the Specialist, having first submitted details of the proposed replacement to the
ER. There is an entitlement on the part of the ER to object to he proposed
replacement if, in his view, the proposed replacement does not have at least the
experience, qualifications, competence, technical capacity and financial standing
of the person he is replacing.

Where a collateral warranty is required from a Specialist, that should be


specified in the Schedule (Part 1F) with a certain date by which the Contractor
must provide the warranty (see Model Form 10).

The concept of the Specialist is new. Nominated sub-contractors are now replaced by
Specialists for whom the Contractor is fully responsible. Specialists and the Specialist Works are
to be set out in the Works Requirements or in the Works Proposals. The most likely and
indeed the "default" scenario will be that the Contractor will provide his own Specialists in
relation to specific Works Items and will be suitability assessed with those Specialists and will
then include for them fully in the Contract Sum.

The engagement of a Specialist by the Employer in advance of the Contractor's engagement is


unlikely to be the norm. In the event of a novation, the Contractor will have provided in the
Contract Sum for all work to be carried out by the Specialist for him.

Example:

The Contractor, in pre-qualifying for a building or engineering project, includes for the
carrying out of certain work by Specialists (say mechanical and/or electrical work) Subsequent
to pre-qualification, the Contractor will include that Specialist in his Works Proposals and the
full price for those Specialist works is included in the Contract Sum. The administration of
that Specialist is then entirely the responsibility of the Contractor so far as the Employer is
concerned.

Alternatively, the Employer might decide, because of the long lead-in period for the Specialist
works, to enter into a contract with the Specialist in advance of contracting with the Main
Contractor. The name of the Specialist and all documentation relating to the Specialist must
be inserted into the Works Requirements for pricing by the Contractor. The Contractor
must then accept the transfer of that contract to him and the Contractor accepts all liability
for the work carried out by that Specialist.

The Employer should be especially careful to ensure that all work which may have to be
carried out by Specialists is considered carefully in advance of the Contract and the
preparation of the procurement documentation as the ER is not entitled to instruct the
Contractor to engage a particular specialist where he is not named in the Contract. In the
event that the Contractor terminates his contract with a Specialist having first submitted
details to the ER (or in circumstances where he is not required to furnish such details) the
Contractor will replace the Specialist but must first submit details of the replacement to the
ER.

Department of Finance Page 114


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In the above circumstances the ER may object to the replacement for the reasons set out
above (Sub-clause 5.4.6), in which case the Contractor may not go ahead with the
appointment. If the circumstances warranted it, at a future date the ER would arguably be
within his rights (in consultation with the Employer) to direct the Contractor to remove the
replacement from site if he was incompetent or if the ER was of the bona fide view that his
presence on site was not conducive to safety, health or good order (sub-clause 5.6). If this
course of action was to be seriously considered the ER would have to give the Contractor an
opportunity to allow the Specialist to perform and observe him so as to ascertain whether or
not such circumstances (warranting his removal from the Site) existed. To do otherwise
would arguably lead to a serious dispute with the Contractor. The entitlement of the ER
would arise from the fact that the term "Contractor’s Personnel" includes Sub-Contractors
and the term "Sub-Contractor" includes a Specialist.

14.6 Property Rights


Infringement of Property Rights

Reference Sub-Clause 6.2

The Contractor indemnifies the Employer against any breach of property rights
including intellectual property rights by him arising from

ƒ the Contractor’s performance or non-performance of the Contract (unless


covered by the Employer’s indemnity to the Contractor)
ƒ any use of Works Items, Contractor’s Things, temporary works by the
Contractor, the Contractor’s Documents, by the Contractor or the
Contractor’s Personnel (or by or on behalf of the Employer on termination
of the Contractor’s obligation to complete the Works
ƒ any use by the Employer of the Works, Works Items or Contractor’s
Documents (for the purpose they were provided) (sub-clause 6.2.1)
The Employer indemnifies the Contractor in respect of liability from
infringement of property rights because of the unavoidable use by the
Contractor of the Works Requirements, Works Items or other items provided
by Employer or the use or occupation of the Site for the Works which is the
unavoidable result of carrying out the Works (sub-clause 6.2.2).

Property and Rights in Contractor’s Documents

Reference – sub-clause 6.4

As has been stated above [see the notes re Schedule part 1C at 11.4 above] the
decision as to whether the Employer requires the copyright in all Contractor’s
Documents will be made in advance of the completion of Part 1 of the Schedule

The Employer states in the Schedule if property rights in documents is required


(note – if not stated, the rights do not transfer).

Part IC of the Schedule in conjunction with sub-clause 6.4 of the Conditions


allows the Employer the option of obtaining intellectual property rights in the

Department of Finance Page 115


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Contractor’s Documents and Works Items. It would be very important for the
Employer to decide if he requires such a provision. In a Design and Construct
Contract it would obviously be of far greater significance than in a traditional
type of contract.

Example:

If it was the case that the Works the subject of the Contract were unique and if the Employer
wished to protect that uniqueness or if they were the first in a series of such structures to be
erected around the country (e.g. schools, railway stations etc.) then the Employer might well
feel that it would be important for him to have the copyright in all documents and designs
going forward. However, the Contractor takes no responsibility for the use of the
Contractor’s Documents other than in connection with the Works. (sub-clause 6.4)

14.7 The Site


Lands Made Available for the Works

Reference – clause 7

The Employer gives the Contractor a right to occupy the Site or relevant parts
as provided for in Works Requirements on or before the latest of dates set out
in sub-clause 7.1.1.

These are:

ƒ the Starting Date


ƒ the day after the Contractor has provided all the things he is obliged to
provide before the Starting Date
ƒ any date stated in the Works Requirements
ƒ the day after the Contractor submits his programme under sub-clause 4.8
ƒ the date stated for start of work on any part of the Site in the current
programme
ƒ the date the part of the Site is actually required.
The Contractor’s right to occupy the Site is not absolute and is subject to
whatever limits are inserted into the Works Requirements (sub-clause 7.1.2).

The Contractor is not entitled to exclusive possession of the Site and must
facilitate the Employer and others as named in the Works Requirements (sub-
clause 7.1.3).

The Contractor – once given occupation of the Site, is fully responsible for its
security (including in relation to protestors and trespassers) and the safety of all
persons entitled to be on it (sub-clauses 7.2 and 7.5).

The Contractor must ensure that the Works do not unnecessarily cause any
nuisance or interfere with the use of adjacent lands (sub-clause 7.5.1).

Department of Finance Page 116


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Employer for its part must ensure Employer’s Personnel on site comply with
the reasonable safety rules of the Contractor as notified to them by him (sub-
clause 7.5.2).

Where the Employer states it in the Works Requirements he may have work
carried out on Site by Employer’s personnel and the Contractor must co-
operate with them and co-ordinate their activities with his own (sub-clause 7.6).

The Contractor is responsible for setting out including rectification of errors


that arise. He must make all reasonable efforts to check information on setting
out in the Works Requirements before himself setting out the Works (sub-
clause 7.7).

If the Contractor finds fossils or archaeological artefacts or items of value or


geological interest etc. on or adjacent to the Site he must not disturb them but
must preserve them and notify the Employer (sub-clause 7.8).

The Contractor is responsible for all access routes to the Site and within it and
for their maintenance. He must take all reasonable steps to ensure that
construction traffic does not damage roads, bridges or other property. He must
also provide all water and power on the Site (sub-clause 7.9).

On completion of the Works the Contractor must leave the Site in a proper
condition (sub-clause 7.10).

The permitted working times for the Contractor are set out in the Works
Requirements and he is confined to them except in cases of emergency or as
may otherwise be agreed with the ER (sub-clause 7.11).

In civil engineering contracts the Contractor must pay charges for Site
occupation (or occupation of any other place) or in relation to any Employer’s
facilities where provided for in the Works Requirements. The Employer is
entitled to deduct such charges from the Contractor’s payments. There is no
such provision in the Building Works forms. (sub-clause 7.12).

14.8 Quality Control


Standard of Workmanship

Reference – clause 8

In the traditional Contract the Contractor is obliged to ensure that the Works
are executed and completed:

ƒ In accordance with the Contract (and as may be reasonably inferred from


it); and
ƒ In a proper and workmanlike manner using good practice (sub-clause
8.1(1));
ƒ He is also obliged to ensure that all Works Items comply with the Contract
and with the Legal Requirements, are of good quality and (unless otherwise

Department of Finance Page 117


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

required under the Contract) new (it might be that the Contractor is to use
recycled materials e.g. old slates or bricks) (sub-clause 8.1(2));
ƒ He is obliged to ensure that all materials and goods that are Works Items
are fit for the purpose for which they would normally be used and that any
Works Items selected or designed by the Contractor (including Specialists)
are fit for their intended purpose in the Works (sub-clauses 8.1(3) and (4));
In the Design and Build Form the Contractor is obliged to ensure that the
Works are designed, executed and completed:

ƒ In accordance with the Contract (and as may be reasonably inferred from


it); and
ƒ In a proper and workmanlike manner using good practice.
ƒ He is also obliged to ensure that all Works Items comply with the Contract
and with the Legal Requirements and are new and of good quality (unless
otherwise required under the Contract).
ƒ He is obliged to ensure that all materials and Works Items are fit for their
intended purpose and that the completed Works are fit for their intended
purpose as stated in or to be inferred from the Works Requirements (sub-
clause 8.1).

The subtle difference in the wording as between the traditional Contract and the Design
and Build Contract reflects the fact that where the Contractor is not carrying out the
overall design he should not have the obligation of fitness for purpose of the overall
Works.

These provisions are onerous obligations and the Employer should be familiar with them
so as to be aware of what the Contractor is obliged to comply with. The provision is as
stated above, subtly worded and means that in the Traditional Contract (unlike the
Design and Build Contract) while the overall Works are not the Contractor’s
responsibility from a design standpoint, any Works items selected by him are in the
context of how they fit into the overall Works

The Contractor is obliged to establish a quality control system such as is


required by the Works Requirements (sub-clause 8.2).

In this regard it is important for the Employer to ensure that such quality
assurance procedures are inserted into the Works Requirements.

The ER is entitled to monitor, spot check and audit the Contractor’s procedures
in this regard (sub-clause 8.2).

The ER is entitled by virtue of Sub-Clause 8.3 to inspect by himself or anyone


authorised by him the Works, or any place where Works Items are produced or
stored for quality control purposes.

The Contractor is obliged to give any details requested by the ER in relation to


the manufacture and supply of Works Items including any Test Certificates
required. He is also obliged to tell the ER before any Works Item is being
covered up or where it is going to be made difficult or impossible to inspect and

Department of Finance Page 118


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

to give the ER or his representative a reasonable opportunity to inspect (sub-


clause 8.3).

The tests are to be set out in the Contract (in the Works Requirements or in
the case of Contractor’s Design, in the Works Proposals) and the Contractor is
obliged to carry them out, agreeing the time and place with the ER and giving
him an opportunity to attend.

In any event, the Contractor has to provide a certified copy of the test results
(sub-clause 8.4).

Where any test fails, the Contractor may be required to repeat it or may elect
to do so. The Contractor is obliged to pay the Employer for any costs incurred
as a result of retesting. Once a defect has been rectified, any test on the
relevant Works Item must be repeated if the ER requires that this be done
(sub-clause 8.4).

Although a provision in relation to testing would not have been set out in the old forms, it would
in all likelihood have been contained in the Preliminaries section of the BOQ or in the
Specification.

Provision is made at sub-clause 8.5 for the detection and remedying of defects in
the Works. The ER may instruct the Contractor to search for defects or
suspected defects including uncovering of any work etc.

If no defect is found, the cost of searching and any delay caused, will entitle the
Contractor to an extension of time and to compensation. (sub-clause 8.5 and
Schedule part 1K at item 2)

If a defect is made known to the ER because of investigations or otherwise he


may tell the Contractor to:

ƒ Remove the Works Item with the defect from the site;
ƒ Demolish the defective Works Item if incorporated in the Works;
ƒ Reconstruct, replace, or correct the Works Item in question;
ƒ Not to deliver the defective Works Item to the site if relevant.
Or the ER may do any combination of the above. (sub-clause 8.5.2)

As would be the case under the older forms of contract should the Contractor
fail to comply with a direction by the ER under sub-clause 8.5 within a
reasonable time, the Employer is entitled to have the work done by others and
the Contractor is obliged to pay for the costs of this. (sub-clause 8.5.3).

Should a defect be serious enough to deprive the Employer of the benefit of the
entire Works or any particular Section or other material part of the Works, the
ER may on behalf of the Employer reject the Works or the relevant Section and
in that case the Contractor must repay to the Employer any amounts that the
Employer has paid to the Contractor in respect of the Works (in the case of the
entire) or relevant part together with all relevant associated costs (sub-clause
8.5.5).

Department of Finance Page 119


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

This provision, while available under forms such as FIDIC, is a new one and in the rare cases
where it might be used, could provide an important remedy, but subject to the ability of the
Contractor to pay.

The ER may only give such a direction or rejection under sub-clause 8.5 before
the Defects Certificate is issued (sub-clause 8.5.6).

There is further provision that a contractor is not entitled to any adjustment to


the Contract Sum or to any extension of time because of a direction given to
deal with any defect or breach of contract (sub-clause 8.5.6).

This would be perfectly normal in any of the previous forms of contract.

The Contractor must complete all outstanding works and remedy any Defects as
are directed by the ER during the Defects Period. He must do this as soon as
practicable after Substantial Completion of the Works or of any Section (sub-
clause 8.6.1).

The Contract provides that in the event of works remaining outstanding or


repair work not having been carried out by the end of the Defects Period, the
ER may extend the Defects Period for whatever length of time he regards as
appropriate in the circumstances. Similar considerations apply where the
Contractor has carried out outstanding work or rectified defects during the
Defects Period so that the Employer will have a full (or at least, extended)
Defects Period in respect of the work in question (sub-clause 8.6.2).

Sub-clause 8.7 provides for the ER to issue the Defects Certificate to the
Contractor and the Employer within 20 working days after the end of the
Defects Period. However, the issue of the Defects Certificate does not relieve
the Contractor of any responsibility for defects (unless they have been accepted
by agreement under sub-clause 8.5.4).

14.9 Time and Completion


Contract Date

Reference - The Agreement – Article 6, sub-clauses 1.1 and 9.1.1

The Contract Date is the Date of issue of the Letter of Acceptance (note –
therefore issue of LOA is important as it starts time running for the purpose of
the Contract) (sub-clause 1.1).

Start of the Works on Site

Reference – Letter of Appointment, Agreement – Article 6, the Schedule, sub-


clauses 1.1, 9.1. and 12.1.1 – item (5).

The Starting Date is the date the Contractor intends to start the Works.

The Contractor must give at least 15 working days notice (unless a different
period is stated in the Works Requirements or a shorter period is agreed with
the ER) of the Starting Date (sub-clause 9.1).

Department of Finance Page 120


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The actual Starting Date must occur no later than 20 working days after the
Contract Date unless otherwise stated in the Works Requirements (sub-clause
9.1.1).

Example:

If the Letter of Acceptance issues in respect of the Contract on Friday 1 June 2007 that is the
Contract Date (sub-clause 1.1 and Agreement – Article 6). Unless otherwise stated in the
Works Requirement.

The Contractor must give notice of the Starting Date by Friday 7 June (in order to give at
least 15 working days notice)

The Starting Date must be by Friday 29 June (assuming no public holidays between 1st and 29th
June)

Note: If the starting date does not occur, the Employer may terminate the Contractor’s
obligation to complete the Works (sub-clause 12.1.1)

The Contractor must hand over all required documents before the Starting Date
(sub-clauses 9.1.2 and 4.9).

ƒ Agreement
ƒ Bond (if required)
ƒ parent company guarantee (if required)
ƒ appointment as PS(CS) (if Contractor or his nominee is PS(CS) plus
developed health and safety plan (as per Construction Regulations)
ƒ evidence of insurance
ƒ collateral warranties (unless a later date is agreed for their provision)
ƒ programme

The documents must all be executed where execution is relevant.

The Employer, along with the ER should make sure that all are properly
executed and in an acceptable form.

This is not necessarily as straight forward as it might first appear. As all these
documents are required to be handed in by the Contractor before the Starting
Date it is likely that in many situations they will be handed in either all at once or
in circumstances which render the checking of them hurried and possibly
difficult. It is very easy to miss something that can later be crucial. It will
therefore be important that all documents are checked thoroughly.

Performance Bond (if required) – care should be taken to ensure that the Bond
is in the correct form (Model Form 6). If it is in the correct form then the
Employer must ensure that it has been properly executed and if it is a bond from
a foreign entity that a letter from a qualified lawyer practicing in that jurisdiction
is obtained in relation to its due execution and enforceability (in accordance with
sub-clause 2.7). [The surety should be authorised to transact guarantee business
in Ireland. This can be checked with the Financial Regulator].

Department of Finance Page 121


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Parent Company Guarantee (if required) – similar considerations relate to


Parent Company Guarantees. For instances, the Employer should be made
aware in advance as to who the Parent Company is and should satisfy itself that
that is in fact the parent company and should then satisfy itself that the guarantee
being furnished is from that entity. It should be in the correct form (Model
Form 7) and the comments above in relation to due execution and enforceability
apply.

With regard to the executed Appointment as PS (DP) or PS(CS) (Model Forms


9-11) if applicable – the comments in relation to appointment set out above
apply. Presumably if the Contractor has already executed the Agreement any
considerations relating to execution on its part will have been raised at that
stage and the Employer should take them into account. It may be appropriate
that the Employer should have the developed health and safety plan checked out
by its own health and safety advisers to ensure that it is in compliance.

Evidence of insurance – it is absolutely vital that the Contractor has all of the
insurances required by clause 3. It will be essential for the Employer to satisfy
himself whether by his own insurance advisers or otherwise that the policies are
in place and that they are to cover the requisite liability. For instance, that the
Public Liability and Contractor’s All Risks policies name the Employer and
Contractor as co-insured, that the minimum indemnity limits are those
contained in the Schedule part 1D, and that only the exclusions and the
maximum excesses permitted in the Schedule (Part 1D) apply.

Collateral Warranties (where relevant) – it will be important for the Employer


to check that the Collateral Warranties are provided (unless a later date has
been agreed) that they are in the correct forms, that they are properly
executed. In this regard it will be necessary to insist that where foreign
companies are executing warranties that a legal opinion in accordance with sub-
clause 2.7 is provided and that where the warranty is provided by an Irish entity
that they are properly executed.

The Contractor is also obliged to appoint the Contractor’s Representative and


fulltime Site supervisor.

On the Starting Date – the Contractor is obliged to start work on site and
proceed with the Works in accordance with Contract

Substantial Completion

Reference - Agreement, Schedule part 1D, part 1E, part 1G, part 1H, part 1I,
part 1K, part 2D

sub-clauses 1.1, 3.3, 4.5.3, 4.8.3, 4.9, 4.17, 8.6.1, 9.1, 9.3, 9.4, 9.5, 9.6, 9.7, 9.8,
10.3, 10.4, 10.5, 10.7, 11.1, 11.3, 11.5.

The Date for Substantial Completion is to be inserted by the Employer in the


Schedule part 1G or (if required to be inserted by the Contractor) -in part 2D.

Department of Finance Page 122


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In order to insert the appropriate date in the Schedule the Employer will need
to consider the Date for Substantial Completion of the Works (and each Section
of the Works if there is to be sectional completion).

In this regard the Employer will doubtless consider the date by which the project
is required, the practical issues associated with its (design and) construction, for
instance, whether it is subject to matters such as tides (in relation to projects
such as outfalls) or seasonal issues (perhaps work in mountainous or boggy
areas).

As there can be no compromise in relation to questions of Health and Safety it


would be important where the Contractor is himself asked to insert the Date
for Substantial Completion that the Employer consider any Health and Safety
impact of this. For instance it might be appropriate for the Employer to insert in
the Works Requirements, a minimum period for completion based upon his
estimate of what this should be in order to avoid any risks in respect of Health
and Safety.

The Contractor must complete the Works (or Section) by the relevant Date for
Substantial Completion.

The Date for Substantial Completion may be delayed as a result of Delay Events
as set out in the Schedule (part 1K) subject to the provisions of the Contract.
Where an extension of time is granted in accordance with the Contract, a new
Date for Substantial Completion applies. (sub-clause 9.3.2) Such an extension of
time will apply to the Works and to any Section (if there is sectional completion)
affected by the delay.

The term "Substantial Completion" is very comprehensively defined in sub-


clause 1.1

The Works are complete and can be taken over and used for their purpose.
There are no defects save:

ƒ Ones accepted by Employer (sub-clause 8.5.4)


ƒ Minor defects
- that do not prevent the use of the Works for their purpose
- The ER agrees that the Contractor has reasonable grounds for not
promptly fixing them
ƒ Those whose fixing will not prejudice safe and convenient use of the Works
(or part)
ƒ All tests have been passed (that must be passed before Substantial
Completion)
ƒ Documents required before Substantial Completion have been furnished
ƒ Collateral warranties have been provided in relation to the Works or
relevant part

While the Contractor’s basic obligation to complete the works by the Date for
Substantial Completion is no different to that in the old forms of contract, the

Department of Finance Page 123


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

actual requirements that have to be fulfilled before Substantial Completion are


perhaps set out more clearly than in the previously utilised forms.

In relation to Substantial Completion it would be necessary for the ER to satisfy


himself fully that the Works are in fact substantially complete. In this context it
will be necessary for the Employer to decide in conjunction with the ER whether
he will accept any defect with a proportional reduction in the Contract Sum.

The Contractor applies for a Certificate of Substantial Completion and the ER


must respond within 20 working days with:

ƒ a certificate of Substantial Completion; or


ƒ a list of reasons for not issuing the certificate

If it is so stated in the Schedule part 1H – the ER does not have to certify


Substantial Completion before the actual Date for Substantial Completion in
Contract (sub-clause 9.6)

The Certificate may list outstanding work

Right of Employer to Suspend Works

Reference sub-clause 9.2

The Employer has a right to suspend the Works – through an instruction of the
ER

The Contractor must suspend and protect the Works

Upon the ER’s direction to resume, the Contractor and ER inspect the Works
and affected Works Items

Where the Contractor is entitled to an adjustment in the Contract Sum or to an


extension of time because of the suspension – any cost of repairing Works Items
unavoidably damaged and any delay in doing the repair is included

If a suspension is not due to the Contractor’s default and is for more than 3
months – the Contractor may ask for permission to proceed

If no permission is forthcoming within 28 days Contractor may give notice to the


ER as follows:

ƒ if part only of Works affected – to treat the suspension instruction as a


Change Order omitting the part
ƒ if the entire Works is suspended the notice may provide that the
Contractor’s obligation to complete the Works is terminated
The suspension of the Works by direction of the ER is both a Delay Event and
Compensation Event. (sub-clause 9.2 and Schedule part 1K)

Department of Finance Page 124


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

The Employer may encounter a situation where it is necessary to stop the Works proceeding
pending a re-assessment of the Works Requirements because of some extraneous event, for
instance, another project that is to link up with the Works and which may cause a substantial
redesign of part of the Works.

In such a case the Employer could utilise sub-clause 9.2 and require the ER to issue a direction
to the Contractor to suspend all or part of the Works. The Employer should liaise closely with
the ER and should ensure that the relevant dates are noted, for instance, when the period of
three months from the ER’s instruction will expire, when the Contractor may ask for permission
to proceed and particularly when the period of 28 days will expire subsequent to any such
request for permission.

This is to avoid a situation where the Employer’s default in responding to a request for such
permission results in the Contractor’s obligation to complete the Works being terminated or
the relevant part of the Works being treated as omitted.

Partial Takeover by Employer

Reference sub-clause 9.7

There is provision in the Contract for partial takeover of the works before
substantial completion on 5 days notice to the Contractor. The Contractor has
no liability for delay in completing the relevant part once it is taken over.

Example:

The Employer may require part of the Works as a matter of urgency before the part has
achieved Substantial Completion. In such a case the Employer might wish to consider partial
take-over. It is not a decision that should be taken lightly as it can cause difficulties particularly
in relation to health and safety and in relation to insurances. It would be necessary to ensure in
conjunction with the ER and the Contractor that the part of the Works in question can be
adequately defined so that there is no doubt as to which part is in fact being taken over. For
preference one would wish that the part to be taken over can be delineated precisely by means
of a barrier or otherwise. There is also the possibility that because the Contractor will no
longer be liable for delay in completing the part, he may have no great desire to come back to
finish it and this should be borne in mind when making the initial decision. In addition, insurers
should be notified so that no confusion is caused by the take-over.

Liquidated Damages

Reference Schedule (part 1G) sub-clause 9.8.

See note re. Schedule (part IG at 11.8 above).

There is provision in the Contract for the deduction of liquidated damages


either in respect of the entire Works or any Section (or both) in the event that
Substantial Completion is not achieved by the required date for Substantial
Completion (sub-clause 9.8).

Department of Finance Page 125


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Example:

The rate of liquidated damages per day or per week will be inserted by the Employer in the
Schedule part 1 G and in this regard the Employer should assess carefully the likely losses to be
suffered by him should either a Section or ultimately the entire Works be delayed due to the
Contractor’s default. In this regard the Employer should make sure that the amount in question
is a genuine pre-estimate of actual losses in order to avoid the possibility that the damages may
be unenforceable by reason of being a penalty.

In point of fact, many Employers insert liquidated damages that do not take into account all of
their likely losses and accordingly such liquidated damages are too low. In the case of Public
Works contracts, while it may be difficult to accurately assess the precise damages that will be
suffered, nevertheless an attempt should be made taking all possible areas of damage into
account such as interest on money borrowed. Obviously, the Employer should be aware of the
risk of inserting a rate that is so high that it is a penalty.

There is also provision here for reduction in retention on substantial completion of a Section
and in this regard the Employer should consider the relationship that the Section in question
bears to the overall works, for instance if the Section is a very substantial part of the Works and
represents 25% of it in monetary terms then it may be appropriate to reduce the retention by a
similar percentage once that Section is substantially complete. However, other factors may
come into play which would result in the reduction not being of similar proportions.

Delays and Extensions of Time

Reference - Schedule (part 1K) sub-clauses 9.3 and 10.3.

The Contractor must give notice to the ER as soon as practicable of delay or


likely delay to the Works.

The notice must specify:

ƒ the delay
ƒ the cause

In addition

The Contractor must as soon as practicable after the First notice and in any
event within 40 working days after becoming aware of the delay, give the ER:

ƒ full details of the delay; and


ƒ its effect on progress
and

The Contractor must give further information to the ER as requested.

The contract provides, that if the Contractor has already given notice and details
under sub-clause 10.3 as he is obliged to do in any event, he does not have to
give further notice or details under sub-clause 9.3 (sub-clause 9.3).

The Contractor is entitled to an extension of time in the event of delay in


Substantial Completion due to a Delay Event where

Department of Finance Page 126


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

ƒ the delay is not due to Contractor’s default ( or that of Contractor’s


Personnel)
ƒ the Contractor cannot avoid the delay
ƒ he has taken all reasonable efforts to minimise the delay
ƒ no provision in the Contract says that he has no entitlement

Only Site Working Days are taken into account.

Both the Contractor and ER must follow the procedures in clause 10 and the
entitlement to an extension of time is subject to the provisions of clause 10
(sub-clause 9.3.2).

The ER can revise an extension of time but can only bring the date(s) for
Substantial Completion of the Works (or any Section) forward when work is
omitted (and agreed with the Contractor).

It is important to note that there is scope in sub-clause 10.5.2 for the ER to


grant an extension of time under clause 9 even if the Contractor has not done
so.

Example:

See Case Study Nr 3 – Delay and Compensation Events

The notice requirements in relation to delays and the granting of extensions of time are clearly
set out in the Contract and the Delay Events which give rise to an extension of time are clearly
set out in the Schedule. The ER will be required to assess whether the Notice Requirements
have been satisfied and whether the requisite information is being furnished by the Contractor
before granting any extension to the Date for Substantial Completion.

The ER will have to assess whether

ƒ there was a Delay Event


ƒ the Contractor has fulfilled his notice requirements
ƒ the Contractor is otherwise entitled to an extension of time in accordance
with sub-clause 9.3.2 and that the procedures in clause 10 have been
followed

The ER will also have to consider very carefully whether, in the light of particular
circumstances, he might wish to grant an extension of time despite the fact that
no such extension has been sought by the Contractor (sub-clause 10.5.2).

The Programme Contingency

Reference – Schedule (part 1K) sub-clause 9.4

The Programme contingency is provided for in the Schedule (part 1K).

The Employer provides in the Schedule for two (sequential) thresholds for delay
in Substantial Completion due to certain Compensation Events. The Contractor

Department of Finance Page 127


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

prices these items and includes them in the initial Contract Sum and also in his
programme.

If a delay is caused to the Date for Substantial Completion of the Works due to
relevant Compensation Events but that delay remains below the first threshold –
the Contractor has no entitlement to an extension of time.

If the delay due to relevant Compensation Events exceeds the first threshold
then the ER deducts from that delay

(i) the number of days stated in the first threshold,


(ii) half the number of days delay in excess of the first threshold.

But the total number of days to be deducted at (ii) above cannot exceed the
number of days in the second threshold.

Example:
Thus if the Employer had inserted 20 days for first threshold and 30 days for second threshold –
in respect of a 60 day delay (due to relevant Compensation Events) the Contractor would be
entitled to a 20 day extension of time i.e.
60 days less 20 days (first threshold period) = 40 days ÷ 2 (to get half of the excess over the
second threshold)= 20 days
As 20 days is less than the second threshold the figure of 20 days is also deducted
Therefore 60 days – (20 days + 20 days) = 20 days extension of time

On each assessment of extensions of time by the ER he must tell the Contractor


how much of the Programme Contingency has been used up.

Example:
In a situation where there was a delay of 100 site working days and assuming the first threshold
was 20 days and the second threshold was 30 days the calculation of any extension of time
would be as follows:
100 days less 20 days (first threshold) = 80 days ÷ 2 (to get half of excess over first threshold) =
40 days
As 40 days is greater than the second threshold, the second threshold of 30 days is used
Therefore 100 days – (20 days + 30 days) = 50 days extension of time
And see the examples in sub-clause 9.4.4

14.10 Claims and Adjustments to Contract Sum


Contractor's Claims

Reference sub-clause 10

The Contractor must give notice to the ER.

The notice must state that it is given pursuant to sub-clause 10.3 of the Contract
and must comply with the provisions of sub-clause 4.14.

Department of Finance Page 128


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Within a further 20 working days further details must be given as follows:

ƒ all relevant facts


ƒ a detailed calculation of the proposed adjustment to the Contract Sum
ƒ the amount of any other entitlement claimed
ƒ if an extension of time is relevant, the information required under sub-
clause 9.3 and a proposal regarding the extension and any use of the
Programme Contingency

The Contractor must provide any additional information required by the ER.

Failure to give notice under this sub-clause will mean the Contractor has no
entitlement to the extension of time or adjustment sought (sub-clause 10.3.2 and
see sub-clause 10.5.2).

The requirements in relation to strict notice do not apply where the Contractor
has complied with a request for a proposal pursuant to sub-clause 10.4.

Where there is a continuing delay/cost the Contractor must update the


information on a monthly basis as follows:

ƒ setting out the extension of time and adjustment to the Contract Sum
sought
ƒ proposing a final adjustment to the Contract Sum and Date for Substantial
Completion
ƒ providing any other reasonably required information (sub-clause 10.3.3)

The Contractor must keep detailed records of the event giving rise to the delay
and adjustment to the Contract Sum. These must include any records required
by the ER.

The Contractor must give the records to the ER if directed to do so (sub-clause


10.3.4).

Proposed Instructions

Reference sub-clause 10.4

The ER can require the Contractor to furnish proposals in relation to any


proposed instruction. The Contractor must respond with 20 working days after
being required to do so. The response must include:

ƒ details of any adjustment to the Contract Sum likely to result


ƒ information on any likely delay as required under clause 10
ƒ a proposal for using the Programme Contingency or for an extension of
time
ƒ if there is a proposal to omit work a revised programme and if appropriate,
a proposal re an earlier date for Substantial Completion

Department of Finance Page 129


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

ƒ any Contractor’s Documents needed in relation to the proposed instruction


or a timeline for their production

Employer's Representative Determination

Reference sub-clause 10.5

The ER has 20 working days within which to respond to any Contractor’s claim
or proposal under sub-clauses 10.3 or 10.4.

The ER must:

ƒ direct the provision of additional information (the Contractor has 10


working days and the ER another 10 working days after that [subject to the
ER not requiring any more information or proposals] to respond)
ƒ notify the Contractor that his proposals are agreed (and make any required
adjustment to the Contract Sum, grant an extension of time or use the
programme contingency)
ƒ assess any adjustments to the Contract Sum, the use of the programme
contingency or extension of time and notify the Contractor
ƒ if a proposal has been made by the Contractor under clause 10.4 notify him
that the instruction in question will not be given

The Contract also provides that the ER may make his own determination on any
extension of time, use of the programme contingency or adjustment to the
Contract Sum despite the Contractor not having made any claim or proposals
under sub-clauses 10.3 or 10.4. This is a very important potential relaxation of
the otherwise exacting provisions of the Contract in relation to notice of claims.
It will arguably impose an added responsibility on the ER to decide in each case
where he feels an extension of time or adjustment to the Contract Sum is
appropriate, whether or not to grant it where the Contractor would otherwise
have lost his entitlement because of a failure to give notice.

Where a proposal is sought by the ER under clause 10.4 the Contractor is not
entitled to implement such an instruction until confirmed by the ER.

Department of Finance Page 130


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

See Case Study Nr 3 – Delay and Compensation Events

As with extensions of time, the notice requirements in relation to Contractor's claims and
adjustments to the Contract Sum are exacting but once again are clearly set out in clause 10,
which also provides for notice requirements in relation to extensions of time (see sub-clause
10.3.1). The ER upon receipt of such notice will be obliged to deal with it in a very systematic,
efficient and transparent manner. It would be incumbent upon the ER in conjunction with the
Employer to set up a system for dealing with such claims so that they can be responded to
promptly and fully. As with notices of delay the ER will have to assess whether or not the
Contractor is prime facia entitled to an adjustment to the extension of time/Contract Sum or
any other entitlement claimed, and to assess whether or not he has provided all details
required under the Contract and within the relevant periods. In this regard the ER will be well
aware that the notice requirements under clause 10 are conditions precedent to the
Contractor’s entitlement.

Thus, if the Contractor fails to give notice in accordance with the sub-clause he will have no
entitlement to the extension of time or adjustment unless the ER uses his discretion under sub-
clause 10.5.2. It is possible that the Contractor may have fulfilled the requirements by means of
a proposal in relation to a proposed instruction pursuant to clause 10.4 and the ER will have to
be mindful of this.

The ER will need to keep careful sight of all details of continuing delay and cost received from
the Contractor, should have a firm and reasoned opinion on them and must be mindful of the
fact that he himself is subject to a 20 working day period within which to respond to
Contractor’s claims under sub-clause 10.3 or proposals under sub-clause 10.4. The ER will also
have to keep in focus in relation to delay claims the use of the programme contingency so that it
can be used where appropriate and the Contractor can be notified of the fact of its use and of
the remaining amount of the contingency.

Where a Compensation Event delays the carrying out of the Works so as to push the Contract
into a consecutive period of 7 or more non-working days that would not otherwise have
occurred the Contractor is entitled to compensation in respect of his expenses exclusive of
profit or loss of profit. This is to be included in addition to the Contract Sum for the delay
cost. However, the ER in assessing the amount should note that the amount to be paid in
respect of the non-working days is not to exceed the sum arrived at by multiplying the
Contractor’s tendered rate of delay cost by the non-working days being compensated for.

It should be noted that a non-working day is defined as "a day that, for good reason, is not a Site
Working Day [such as a trade holiday.]"

In a case where the Contractor is required to and does provide in the Schedule Part 2 in
respect of delay costs for parts of the Works then of course the rate quoted for the portion of
the Works when the delay occurred is to be used as assessed by the ER.

Assessment of Adjustments to the Contract Sum

Reference – Schedule (part 1K) and (Part 2E) sub-clause 10.6

Adjustments to the Contract Sum due to Compensation Events are made in


accordance with the provisions of sub-clause 10.6 as follows. Where there is
additional, substituted or omitted work

ƒ the rates in the Pricing Documents are to be used where the work is similar
and executed under similar conditions to those priced

Department of Finance Page 131


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

ƒ the rates in the Pricing Documents are to be used as a basis of assessment


where the work is not similar to that priced or is not carried out under
similar conditions
ƒ a fair valuation is to be made by the ER where the above do not apply

Alternatively, the ER may direct that any additional or substituted work is valued
by reference to the actual cost of performing the work as follows:

ƒ the hours worked by each work person as identified by the Schedule (parts
1K and 2E) multiplied by the rate for that category of work person as per
the Schedule (part 2E)
ƒ the cost of materials used plus the percentage adjustment of that cost as
tendered and set out in the Schedule (part 2E)
ƒ the cost of plant used at rates in the document set out in the Schedule (part
1K) – if no rate in the Schedule – market rental can be used - adjusted per
the adjustment provided for in the Schedule (part 2E)

The Schedule Part 1 plays a role in assessing adjustments to the Contract Sum
by identifying Compensation Events. The Pricing Document has an even more
crucial role in providing the rates pursuant to which varied work will be paid for.
The Pricing Document is to be used where it contains rates applicable to the
additional, substituted or omitted work. If the nature of the work carried out is
different to that in the Pricing Document the ER will use those rates as the basis
for his evaluation. Otherwise he is to make a fair valuation which presumably
would be based upon rates for similar work in the locality carried out under
similar conditions.

The ER is also entitled to direct that such additional or substituted work is


assessed on a cost plus basis (time and materials) by reference to the rates
provided for by the Contractor in the Schedule part 2E).

The Contractor is obliged to provide a rate for crafts persons, general


operatives and apprentices in the Schedule (part 2E) which will include for PRSI,
benefits, tool money, travelling time and country money. This is the rate that
may be used by the ER in calculating payment for additional or substituted work
pursuant to sub-clause 10.6.4. In addition the Contractor is to provide in the
Schedule (part 2E) his tendered percentage addition in respect of the cost of
materials and his tendered percentage addition (or deduction) for the costs of
plant inclusive of on-costs, overheads and profit exclusive of V.A.T.

The ER may use the cost of relevant materials together with the percentage in
the Schedule part 2E in valuing materials.

It should be noted that if the Contractor leaves his tendered percentage


additions/deductions blank or states them as a zero then these are read as zero.

Department of Finance Page 132


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Assessment of Delay Cost

Reference – Schedule part 1K and 2E and sub-clause 10.7

Where delay to the Date for Substantial Completion arises from a


Compensation Event, delay cost as inserted by the Contractor in the Schedule
(part 2E) is added to the Contract Sum.

Alternatively, depending on whether or not the Employer has selected this


option when completing the Schedule part1 K, the Contractor’s actual expenses
unavoidably incurred are to be used.

If the delay cost option is chosen by the Employer, the Contractor’s tendered
rate of delay costs is to be provided by him at tender stage (in the Schedule part
2E) in accordance with the instruction contained in the Schedule part 1K.

An important point of note is that for periods of concurrent delay – there will
be no increase in the Contract Sum if one of the causes of a delay is not a
Compensation Event (sub-clause 10.7.2).

The subject of liability for concurrent delays in construction has been the subject of much debate
in the past. The provision in the Contract makes it clear that concurrent delays (i.e. periods of
delay for which there are more than one cause) will not be compensated unless all are
Compensation Events. This can be argued for on the basis that there is in fact no net delay for
which the Employer has agreed to adjust the Contract Sum While it is unlikely that a contractor
would seek an extension of time due to a cause that was not a Compensation Event where such
delay was concurrent with a "compensatable delay", the ER ensure that extensions are granted
for such causes, using the discretion under sub-clause 10.5.2 if necessary.

Example:

For instance, if the same period of delay is due to a combination of the failure by the Employer
to give the Contractor a Works Item or other thing required by the Contractor after the
Contractor has asked for it (sub-clause 4.10) [both a Delay Event and a Compensation Event]
and say, a weather event as defined in the Schedule Part IK [a Delay Event but not a
Compensation Event] then the Contractor would not be entitled to any increase in the
Contract Sum for that period of concurrent delay.

In the event that a Compensation Event results in a holiday period of 7 or more


consecutive working days being included in the extended Contract period the
Contractor’s expenses (excluding profit and loss of profit) unavoidably incurred
are included in the assessment of the Contract Sum adjustment subject to the
following:

ƒ the amount added to the Contract Sum must not exceed the amount
calculated by multiplying the Contractor’s tendered rate of delay cost by the
additional non-working days (sub-clause 10.7.3)

The provisions in sub-clause 10.7 are exhaustive of the Contractor’s rights of


recovery in respect of loss or expense from delay or disruption, loss of
productivity etc (sub-clause 10.7.4).

No delay costs are payable in respect of extension of time for completion of


Sections.

Department of Finance Page 133


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Schedule at part 1K requires the Contractor to tender in part 2E either a


single rate for delay costs or, if required to do so, a separate rate for delay costs
for various portions of the Works. The Contractor sets out the tendered delay
costs in the Schedule at part 2E. These are rates per Site Working Day but
excluding VAT.

When the ER is calculating the adjustment to the Contract Sum in respect of the
delay caused by the Compensation Event, he uses the Contractor’s tendered
rate of delay costs to calculate the compensation in question.

As can be readily appreciated, the insertion by the Contractor of a delay rate in


the Schedule and its use by the Employer in compensating for relevant delays
that may occur, greatly simplifies the entire process of payment for delays to a
contract. When taken in conjunction with the provision in sub-clause 10.7.4 to
the effect that the Contractor has no other entitlement for delays, it should act
so as to avoid global and other claims for prolongation of contracts that have
dogged the industry over the years.

Employer’s Claims

Reference sub-clauses 10.9 and 11.4

The Contract now expressly provides for the making of claims by the Employer
against the Contractor.

Where the Employer or ER considers the Contract Sum ought be adjusted in


favour of the Employer or that a sum is due by the Employer to the Contractor

ƒ the Employer or ER must give notice of the event to the Contractor (and
the other)

The notice must include:

ƒ the details and facts giving rise to the claim


ƒ a calculation of the amounts in question and a proposal of the adjustment to
the Contract Sum

The Contractor has 20 working days to respond.

Within a further 20 working days (or if no response is received from the


Contractor, within 20 working days from the expiry of the initial 20 day period)
the ER determines the matter.

The Employer is entitled to deduct from any money due to the Contractor

ƒ any amount determined by the ER as due to him by the Contractor or likely


to become due under the Contract
ƒ any sum due to him from the Contractor under any contract (sub-clause
10.9.3)

Department of Finance Page 134


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

If the Employer becomes aware of a claim that he may have against the
Contractor it will be important for him to liaise with the ER in this regard.
Likewise if the ER considers that the Employer is entitled to claim monies from
the Contractor it would be incumbent upon him to discuss the matter with the
Employer and to assess whether or not such a claim is to be made. For instance,
if the Contractor has not provided a Collateral Warranty on time then the
amount referred to in sub-clause 11.4.1 and set out in the Schedule (Part IF) is
due from the Contractor to the Employer pursuant to sub-clause 11.4 and this
will be referred to in the notice. The notice should also include a clear
calculation and the proposed adjustment to the Contract Sum.

Once the Contractor has responded within the 20 working days time limit
available to him under sub-clause 10.9.2 the ER makes his determination and
once that determination has been made, the Employer is entitled to deduct the
amount determined (if any).

If the Contractor was for instance carrying out another contract for the
Employer elsewhere and substantial amounts are due to the Employer under
that Contract then the Employer is also entitled to deduct such an amount
pursuant to sub-clause 10.9.3.

The ER will have to ensure that in making any determination of sums due or
likely to become due by the Contractor to the Employer, he is careful that no
injustice is done to either party.

14.11 Payment
Interim Payment

Reference – Schedule part 1L and sub-clause 11

Interim payments arise:

ƒ at the periods for interim payments in the Schedule (part 1L) (provided the
minimum payment amount in the Schedule is reached)
ƒ on the issue of the Certificate of Substantial Completion for the Works or a
Section (sub-clause 11.1.1)

On these occasions the Contractor must provide a statement to the ER showing

ƒ the progress of the Works


ƒ the payment he says is due
ƒ a detailed breakdown of the sum
ƒ any supporting evidence the ER requires
ƒ a certificate pursuant to clause 5.3.7 (that the Contractor has complied with
clause 5.3 in relation to the work, the subject matter of the certificate)
ƒ on Substantial Completion – all amounts due on the Works or Section (see
sub-clause 11.5.1 in this regard)

Department of Finance Page 135


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Contractor is entitled to be paid

ƒ the Contract value of Works properly executed


ƒ any amount due for unfixed Works Items
ƒ any amounts due for Compensation Events
ƒ any amounts due for PV1 or PV2 (whichever is part of the Contract)
(sub-clause 11.1.2)

The ER must provide a payment certificate within 10 working days (with copy to
Employer) stating the amount the ER says is due including Employer’s claims and
liquidated damages with calculations and reasons for the amount in the
certificate.

The Contractor must furnish an invoice to the Employer who must pay within
15 days from receipt of the invoice by him.

Example:

Assuming the period for interim payment is confirmed as being monthly and assuming that the
minimum amount for interim payments has been reached the Contractor submits his interim
account to the ER in the normal way.

The ER calculates the amount to which the Contractor is entitled noting that the works must be
properly executed and calculating the value based on the Pricing Document. In addition the ER
will add in any amount the Contractor is entitled to be paid for Unfixed Works Items up to the
percentage stated in the Schedule part IL. If there are any adjustments to be made to the
Contract Sum for Compensation Events (i.e. for additional or substituted work under sub-clause
10.6 and/or delay costs under sub-clause 10.7) then these will be added together with any
amount in respect of price variations.

The Employer will then received a copy of the Payments Certificate which has been issued to
the Contractor (within 10 working days of the Contractor’s statement) and an invoice based on
the amount of that Payment Certificate. The Employer will have 15 days within which to pay the
amount due falling which the Employer will become liable to interest at the rate provided in the
European Communities (Late Payment in Commercial Transactions) Regulations, 2002.

Retention may also be deducted by the Employer from the payments to be made
– see notes on retention below (sub-clause 11.3).

It may be seen from the above that the timeframe for certification and payment
is very tight. This will require clear lines of communication between all relevant
parties so as to ensure there are no problems with payment to Contractors.

Unfixed Work Items

Reference sub-clause 11.2

The ER has a discretion to include in Interim Payments amounts in respect of


unfixed Works Items up to a maximum percentage of their value as set out in
the Schedule (Part 1L) (the default is 90%).

Department of Finance Page 136


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Payment for unfixed Works Items is subject to certain qualifications:

ƒ They are complete and substantially ready for incorporation in the Works
ƒ Title has been vested in the Employer
ƒ They are stored on the Site
ƒ They have not been brought onto the Site prematurely

If the Works Items have not been delivered to the Site following qualifications
apply:

ƒ They are complete and substantially ready for incorporation


ƒ Title has been vested in the Employer
ƒ They have been properly stored, set aside and clearly marked to show they
are destined for Site and are the property of the Employer
ƒ They must be clearly identified and a list provided to the ER with
documentary evidence that title is vested in the Employer
ƒ They must be insured as required under the Contract (including insurance in
transit)

A bond must be provided to the Employer in the form in the Works


Requirements or in an approved form in respect of the amount to be paid.
It is essential that the ER is rigorous in ensuring that any unfixed Works Items, which he is
considering including in an interim payment comply with all of the provisions of sub-clause 11.2
as the Employer may be incurring risk needlessly if the provisions are not complied with. For
instance, the risk that the supplier becomes insolvent and the goods are not released or that
there is an argument in relation to their ownership, or risk of damage being caused either when
stored or in transit, which is not adequately insured.

Retention

Reference Sub-clause 11.3

The percentage for retention by the Employer is set out in the Schedule (part
IL).

The Employer is entitled to deduct the retention percentage from Interim


Payments.

At Substantial Completion the Contractor is entitled to invoice for and to be


paid half of the retention and the remaining half is paid upon the issue of the
Defects Certificate.

However, the Contractor may provide a retention bond (in the form contained
in the Model Forms – Form 17 or in an approved form) and where he does so
within 10 working days of Substantial Completion he is entitled to invoice for
and be paid the balance of the retention money.

Similar considerations for repayment of retention apply in the case of Sections of


the Works.

Department of Finance Page 137


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Where a retention bond is being provided similar considerations are applicable to the provision
of a performance bond. This means that the employer should ensure that the bond is in the
appropriate form (see Model Forms – Form 17 (which should be contained in the Works
Requirements and if not contained in the Works Requirements, the Employer will need to vet
the form to ensure that it is a satisfactory form. In this regard it might be appropriate to either
have it approved by the Employer’s legal advisers or at the very least to compare it with the
form in the Model Forms.

Status of Payments to Contractor

Reference sub-clause 11.4

Payments are stated to be for compliance in full with Contractor’s obligations to


the date of payment

If the Contractor has not complied in full with his various obligations – there is
no obligation on the Employer to pay in full. The Contract provides for the
deduction or withholding of money from the Contractor under a number of
headings.

ƒ if collateral warranties are not provided in time (i.e. by the date set out in
the Schedule for their provision) – the Employer may deduct the amount
shown in the Schedule and hold it until the warranty is furnished
ƒ if a programme or progress report under sub-clauses 4.9 and/or 4.10 is not
provided in time – the Employer may deduct 15% of any payments due until
it is furnished
ƒ if the Contractor has not complied with the requirements of sub-clause 5.3
re proper payments to work persons – the Employer may estimate the
amount due to such work persons and deduct it until satisfied with the
situation
ƒ if the Contractor does not provide a certificate as required with his interim
statement that all work persons have been properly paid in respect of the
relevant work – the Employer may withhold payment for the (estimated
labour element of the) relevant work until receipt of the certificate The
Contractor is obliged to give the Employer any necessary information for
the estimation of the labour element (sub-clause 11.4)

Any deductions made as above are deducted from the Contract Sum if there has
been no compliance by the date of issue of the Defects Certificate

When the Employer is making payment to the Contractor he should have from
the ER a clear record of whether or not the Contractor is in compliance with
his obligations to provide Collateral Warranties, the programme and progress
reports. The Employer should also make sure that the ER is informing him as to
whether the Contractor has provided the Certificate required with sub-clause
5.3.7 (relating to proper payment of work persons) with his interim statement.
With regard to the provisions of clause 5.3 it is intended that the Contractor
himself will police the payment of all relevant work persons and the certification
under sub-clause 5.3.7 is part of this process. However, the Contract provides
at sub-clause 5.3.3(A)(2) when included by means of the Schedule (part 1J) for

Department of Finance Page 138


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

random checks by the Employer and it is the policy of the Government that
such checks are to be made.

Example:

If a payment has been certified in a certain amount and the Employer is aware that the
Contractor has not provided a collateral warranty by the date stated in the Schedule (part 1F)
then the Employer may deduct the amount due pursuant to the Schedule (part 1F) until that
warranty has been provided. Similarly, in respect of the other items which the Contractor is
required to give and in respect of which the Employer is entitled to deduct monies.

It is noteworthy that in relation to the Certificate to be provided by the Contractor pursuant


to sub-clause5.3.7 to the effect that work persons have been properly paid, unless the
Contractor provides the Certificate the Employer may deduct the entire payment in respect of
the Work Item in question and may ultimately permanently withhold the labour portion of the
amount in question.

The Employer will then received a copy of the Payments Certificate which has been issued to
the Contractor (within 10 working days of the Contractor’s statement) and an invoice based on
the amount of that Payment Certificate. The Employer will have 15 days within which to pay the
amount due falling which the Employer will become liable to interest at the rate provided in the
European Communities (Late Payment in Commercial Transactions) Regulations 2002.

While the certification provisions envisage that sums due from the Contractor to the Employer
are taken into account in the interim Payment Certificates (although the wording of sub-clause
11.1.2 might lead one to believe otherwise) it does appear from sub-clause 11.4 that even if they
were not, the Employer may deduct the relevant sums under sub-clause 11.4.

Final Payment to Contractor

Reference sub-clause 11.5

The Contractor must submit a final statement within 2 months of Substantial


Completion of the Works.

The final statement must include all sums the Contractor says are due under or
in connection with the Contract (sub-clause 11.5.1).

The Employer has no liability for matters not set out in the final statement
except for:

ƒ matters arising under the indemnity provisions in the Contract (such as


insurance claims), or
ƒ Compensation Events that occur after Substantial Completion
The ER must within three months of receipt of the final statement issue a
penultimate payment certificate indicating the amount due from the Employer to
the Contractor (or vice versa) less final retention.

The ER must then issue a final payment certificate as soon as practical and no
later than three months after the Defects Certificate issues stating the amount
finally due from the Employer to the Contractor (or vice versa).

Department of Finance Page 139


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The final payment certificate amount will be the same as the penultimate
certificate amount except that it will include:

ƒ The final retention payment


ƒ Any adjustments to the Contract Sum arising from Compensation Events
occurring after Substantial Completion
ƒ Amounts owed by the Contractor to the Employer not already included in
penultimate payment certificate (e.g. for defects not remedied)
ƒ Any deductions from the Contract Sum arising from Contractor’s default
(failure to provide documents etc)

The Contractor issues an invoice in respect of any sums due on foot of the
penultimate or final payment certificates and the Employer must pay within 15
days after receiving the invoice.

Note: The payment of certificates whether interim, penultimate or final do not relieve the
Contractor of its obligations under the Contract or provide evidence that the work has been
executed properly.

The final payment process is a relatively straightforward one. For example, the
Employer will receive in the first instance the penultimate payment certificate
from the ER which will set out the amount due by the Employer to the
Contractor (assuming that there is money due). The Employer will then receive
an invoice from the Contractor in respect of the amount due on the invoice and
is obliged to pay it within 15 working days. Alternatively if the penultimate
payment certificate indicates that the Contractor owes money to the Employer
then the Employer should make a demand upon the Contractor in respect of the
amount whereupon the Contractor is obliged to pay within 10 working days of
receipt of that demand.

The Employer will expect to receive from the E.R a final payment certificate
showing the final amount due to the Contractor (or vice versa) within 3 months
after the issue of the Defects Certificate. This certificate will constitute the final
payment to be made by the Employer to the Contractor

The Employer must pay the amount due on foot of the final payment certificate
within 15 working days of receiving an invoice in this respect from the
Contractor failing which he will become liable to pay interest at the rate
provided in the European Communities (Late Payment in Commercial
Transactions) Regulations 2002.

Time for Payment

Reference sub-clause 11.6

Unless a specific time is stated any amount due is to be paid within 30 (calendar)
days of receipt of the relevant demand.

Practically all payments to be made under the Contract appear to be provided for with a specific
time being stated – i.e. 15 days or 10 days

Department of Finance Page 140


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Interests pursuant to the Communities (Late Payment in Commercial


Transactions) Regulations 2002 applies to late payment.

14.12 Termination
Termination on Contractor Default

Reference clause 12

The Contract provides for termination of the Contractor’s obligation to


complete the Works for default and for termination without any default on the
part of the Contractor (sub-clauses 12.1.1 and 12.5)

Reasons for termination for default are:

ƒ Failure by Contractor to comply with contractual obligations (in the case of


defaults that can be corrected, failure to do so within 14 days from receipt
of direction in this regard)
ƒ Abandonment or suspension (unless permitted by the Contract) of the
Works
ƒ Failure to proceed regularly and diligently with the Works
ƒ Failure to provide or maintain insurances or Bond
ƒ Failure to commence work within 6 weeks of the date required under the
Contract or failure to initiate a Starting Date
ƒ Contractor’s warranties (any of them) are not true
ƒ A serious breach of Legal Requirements (including labour law) concerning
the Works
ƒ Breach of safety law or codes of practice concerning the Works
ƒ Failures relating to payment of work persons either persistently or within
14 days after notice from the Employer to rectify the matter
ƒ Sub-Contracting in breach of Contract
ƒ Insolvency as set out in the Contract
ƒ Incapacity (in the case of an individual)
(sub-clause 12.1)

Where the Contractor consists of more than one entity or person and an
insolvency event occurs in relation to one of them the Employer may:

ƒ Terminate the Contractor’s obligation to complete the Works or


ƒ Only terminate the obligation of the person concerned leaving the others
liable for performance of the Contract (including that of the defaulting
Contractor)

Department of Finance Page 141


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Employer may also terminate if there is a failure on the part of the
Contractor to provide a replacement Guarantor and guarantee where the initial
Guarantor becomes insolvent or the guarantee becomes unenforceable

ƒ The replacement Guarantee or Guarantor must be provided within 10


working days of the event giving rise to the replacement.

Example:

If the Contractor is in default of its obligations under the Contract e.g. failing to proceed with
the execution of the Works and failing to repair defective workmanship or otherwise failing to
comply with obligations under the Contract, the Employer should be kept informed of such
matters by ER It would be necessary for the Employer and ER possibly subject to receipt of
legal advice to assess precisely which of the provisions of sub-clause 12.1.1 that the Contractor
is failing to comply with. It is likely that if the question of termination is being contemplated at
all, that the matter has been going on for quite some time.

If however the Employer is indeed seriously contemplating termination then he should discuss
the matter in depth with the E.R and possibly with his legal adviser so that the correct approach
is taken. For instance, if the matter is one which can be rectified then it would be essential for
the ER to issue a formal direction to the Contractor to put the matter right and in this regard it
would be useful to formally state that if the matter is not rectified within 14 days, the Employer
intends to exercise his right to terminate the Contractor’s obligation to complete the Works.
The Contractor should then be given the 14 days within which to put the matter right and only
if he has not done so within that period should the Employer serve notice on the Contractor
pursuant to sub-clause 12.1 terminating his obligation to complete the Works. Legal advice
should be sought upon the format of the notice but in essence it must be clear and unequivocal
and preferably should state precisely what it is and the fact that it is a notice pursuant to sub-
clause 12.1 of the Contract. The notice should be sent in strict accordance with the provisions
of sub-clause 4.14 and to the person named in the Schedule part 2A.

It would also be important for the Employer and the ER to consider the position under the
Bond or Bonds that have been provided by the Contractor and whether notification of the
bondsman is appropriate (which is likely).

If the Contractor persistently fails to honour his obligations to pay work persons properly then
the Employer is entitled to serve notice of termination without the 14 day notice. Similarly, if an
Insolvency Event as defined in sub-clause 12.1.1 occurs then the Employer may serve a notice of
termination without any further notice.

Consequences of Termination for Default

Reference sub-clause 12.2

The consequences of termination for default are set out in clause 12.2 and
include:

ƒ The Contractor must leave the Site and not remove any Works Items or
Contractor’s Things unless directed to do so
ƒ Payments are postponed
ƒ The ER makes an assessment (as soon as practical) of the amount due in
respect of work done and not yet paid (the "termination value")

Department of Finance Page 142


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

ƒ The Employer engages other contractors to use the Works Items and
Contractor’s Things on the Site to complete the Works
ƒ The Contractor must assign sub-contracts and supply contracts etc. to the
Employer where directed to do so
ƒ The Employer has discretion to pay sub-contractors or suppliers amounts
already paid to the Contractor and the Contractor must re-pay those
amounts
ƒ The Contractor must hand over all Works Requirements and Contractor’s
Documents to the Employer

Once the Works have been completed the ER certifies the "termination
amount" which includes:

ƒ The additional cost of completing the Works


ƒ The loss and damage suffered by the Employer
ƒ The amounts due to the Employer by the Contractor

The certificate showing the termination value must in the case where the
Employer does not start completion of the Works within 6 months after
termination, issue as soon as practicable after the end of the 6 month period.

If (as would be normal) the termination amount is more than the termination
value the Contractor must pay the Employer the difference within 10 working
days of receiving the Employer’s demand. If the termination amount is less than
the termination value then the Employer pays the Contractor the difference on
receipt of an invoice.

As with all termination situations one of the crucial things that the Employer
would have to address immediately is securing the Site and this he should do, by
if necessary employing a security firm to see that the Contractor leaves the site
as he is required to do pursuant to sub-clause 12.2.1 in an orderly manner.

No further payments should be made by the Employer to the Contractor until


the certificate certifying the termination amount is issued by the ER.

In securing the Site the Employer should note that the Contractor is not entitled
to remove Works Items or Contractor’s Things from the Site unless required to
do so by the Employer. However, the Employer will need to make a practical
assessment on this and the most important thing will be to ensure that all
Works Items necessary for completion of the Works are kept on Site.

It will obviously be necessary to complete the Works and the Employer should
liaise with the ER so as to assess what Specialist contracts or supply contracts
should be assigned to the Employer.

The Employer will also be engaging another contractor to complete the Works
and will also be making a call on the Performance Bond provided by the
Contractor.

Department of Finance Page 143


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In making an assignment of any sub-contractor’s or supplier’s contracts the


Employer may have to arrange with them for payment by the Employer of
amounts that the Employer has already paid to the Contractor. This will be the
subject of a claim by the Employer against the Contractor.

After Substantial Completion the Employer will receive from the ER a certificate
indicating what if any amount is due by the Employer to the Contractor or by
the Contractor to the Employer. If, as is likely, an amount is due by the
Contractor to the Employer then the Employer should draft up and furnish a
demand for payment from the Contractor. Should there be an amount due to
the Contractor this will be payable by the Employer within 15 working days after
receiving an invoice from the Contractor furnished on foot of the ER’s
certification.

Non Payment by the Employer

Reference sub-clause 12.3

Failure by the Employer to pay any amounts due to the Contractor entitles the
Contractor to suspend the Works if no payment is made within 15 working days
after receipt by the Employer of a demand from the Contractor.

Termination at Employer’s Election

Reference sub-clause 12.5

The Employer is entitled by the Contract to terminate the Contractor’s


obligation to complete the Works at its election upon giving 20 working days
notice to the contractor.

One important limitation on this power is that the Employer may not terminate
under it for the purpose of obtaining another Contractor to execute/complete
the works.

When the Employer terminates at his own election the consequences are set
out in sub-clause 12.6 of the Contract and include:

ƒ The Contractor leaves the Site removing any Contractor’s Things


ƒ The Contractor must give the Employer all Works Requirements and all
Contractor’s Documents
ƒ The Contractor provides the ER with a statement showing:
- The unpaid value of the Works completed
- The Contractor’s demobilisation costs
- Any other amounts that the Contractor is entitled to under the
Contract excluding any damages
The sum of the above is known as the "termination sum".

The ER must issue a certificate to the Contractor within 10 working days of


receiving the statement of the termination sum. The certificate is to show the
amount due from the Employer to the Contractor or vice versa.

Department of Finance Page 144


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The Contractor’s Obligations under the Contract (excluding the obligation to


complete) survive termination.

Example:

The Employer might become aware during the course of the project that the Works will no
longer be needed because of another larger project that is ongoing and that will effectively take
away the necessity for the Works (for instance a relief road that will not be needed because
another larger road scheme will cater for the traffic in question).

In such a case the Employer might wish to terminate the Contractor’s obligation to complete
the Works even though the Contractor is not in default. Where this arises the Employer
should serve notice on the Contractor terminating the Contractor’s obligation to complete and
stating that he is utilising the provisions of sub-clause 12.5 of the Contract. The notice should
provide that it will take effect 20 working days after it has been delivered to the Contractor.
As with all such notices the Employer should make absolutely sure that the notice is delivered
properly to the correct address for service of such notices in accordance with sub-clause 4.14.
The Employer should also obtain the original of the Performance Bond provided by the
Contractor and return this to the Contractor at the expiration of the 20 days notice.

Once again the Employer should ensure that the Site is adequately secured, that the Contractor
leaves the Site in an orderly manner and removes all of the Contractor’s Things. The Employer
should ensure that the ER obtains from the Contractor all Works Requirements and
Contractor’s Documents. Once the Contractor has provided a statement of the amounts
making up the termination sum to the ER the ER will provide (within 10 working days of
receiving the statement) a certificate to both the Employer and the Contractor showing the
amount due from the Employer to the Contractor (or vice versa). The Employer will then
receive an invoice from the Contractor (or if the amount is due from the Contractor to the
Employer the Employer should make a demand for payment of the sum) and the Employer is
obliged to pay within 15 days of receipt of the invoice (the Contractor must pay any sum due by
him within 10 days of the demand).

In a case of termination the Employer may need to consider whether the Contractor should be
kept on as Project Supervisor or otherwise, the urgent appointment of a replacement Project
Supervisor for the Construction Stage in relation to the final "mothballing" of the Works.
Alternatively if there is any part of the Works to be demolished then this would be a separate
project requiring a new Project Supervisor.

Payment as an Exhaustive Remedy

Reference sub-clause 12.6

The payment by the Employer to the Contractor of the sums provided for in
clause 12 together with any other amounts due under the Contract before
termination are stated to be the Employer’s total liability to the Contractor.
(sub-clause 12.6)

Conciliation Relating to Termination

Reference sub-clauses 12.9 and 13.1

Where the Employer is of the view that an entitlement has arisen on his part to
terminate the Contractor’s obligation to complete the Works, the Employer has
a discretion to refer the issue of his entitlement to conciliation. (sub-clause
12.9.1)

Department of Finance Page 145


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The appointed conciliator must give his recommendation within 21 days after his
appointment.

In the event that the Conciliator recommends that the Employer is entitled to
terminate the Contractor’s obligation to complete the Works for default and if
the Employer does so within 60 days after the recommendation it may be found
in subsequent arbitration proceedings that the Employer was not entitled to do
so. In such an event:

ƒ The termination nevertheless stands as if it were a termination at the


Employer’s election
ƒ The Contractor is compensated as if the termination had been at the
Employer’s election i.e. the Contractor ‘s compensation is limited to the
unpaid value of completed Works, his demobilisation costs and any other
amounts to which he is entitled under the Contract
ƒ However, the Employer is entitled to engage another contractor to carry
out or complete the Works

The Contractor has no other rights under the Contract or otherwise at law for
the termination

Example:

In certain circumstances where the Employer is of the view that he has become entitled to
terminate the Contractor’s obligation to complete the works pursuant to sub-clause 12.1 he
may, in view of the circumstances and the likelihood that the Contractor would challenge the
termination, wish to refer the question of his entitlement to terminate to conciliation. In
arriving at such a decision the Employer would in conjunction with the ER look at the facts giving
rise to the potential termination and consider whether they are absolutely clear-cut. In the
event that they are clear-cut then the Employer might not feel it was incumbent on him to
conciliate on the matter but if there was any doubt it might be safer for him to do so.

If the Employer decides to conciliate upon the matter then he will serve notice of the
conciliation on the Contractor pursuant to sub-clause 13.1 of the Contract.

If the Conciliator recommends that the Employer is entitled to terminate then the Employer
should do so within 60 days after the receipt of the Conciliator’s recommendation. The aim of
this procedure is, that by following it, the Employer should hopefully safeguard his position and if
the Contractor refers the entire matter to arbitration and it is ultimately held that the Employer
was not entitled to terminate then the provisions of sub-clause 12.9.3 will apply and the
termination will stand as if it was a termination at the Employer’s election.

In such a case the Employer will be entitled to engage another Contractor to complete the
Works although obviously those works will be substantially delayed.

In looking at the circumstances surrounding a decision to terminate, the Employer would


obviously look at any delays for which he (the Employer) is responsible. In this regard attention
would have to be paid to whether notice has been given by the Contractor in respect of any
such delays within the time constraints set out in sub-clause 10.3 of the Contract. Failure by the
Contractor to comply with these notice provisions could (subject to the ER’s discretionary
power under sub-clause 10.5.2) could disentitle him in respect of his delay and/or compensation
claim. In the event that the Contractor is entitled then it would be appropriate for the
Employer to address this situation prior to any conciliation concerning the Employer’s right to
terminate.

Department of Finance Page 146


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14.13 Dispute Resolution


Conciliation

Reference sub-clause 13.1

The Contract provides that disputes arising in connection with, out of the
Contract or Works are to be referred to conciliation and ultimately to
arbitration if conciliation does not resolve the dispute.

Either party can request conciliation by a notice in writing specified to be a


notice under sub-clause 13.1 of the Contract.

The parties must appoint the conciliator within 10 working days of the referral
and in default the appointing body as set out in the Schedule (Part 1N) appoints.

The parties must make all information and documents available to the conciliator
that he requires.

The conciliator may

ƒ meet the parties separately or together


ƒ consider documents provided by one party and not shown to the other
ƒ carry out investigations without the parties
ƒ use specialist knowledge
ƒ get legal or technical advice
ƒ set out the procedures to be followed

The conciliator’s appointment may be set out in the Works Requirements or


otherwise as agreed.

The Conciliator must give his recommendation if the dispute is not resolved
within 42 days after his appointment (sub-clause 13.1.8).

Each party has 45 days in which to give notice of dissatisfaction to the other
party in writing (and specified to have been given under sub-clause 13.1). Such a
notice may issue in the event that no recommendation is given within 45 days of
the appointment (sub-clause 13.1.9).

Once notice of dissatisfaction has been given, either party may serve notice of
arbitration on the other (sub-clause 13.1.9).

If no notice of dissatisfaction is given within 45 days from receipt of the


recommendation – the recommendation becomes binding on both parties and
they can enforce it by reference to arbitration (sub-clause 13.1.10).

If a payment of money is recommended (even if notice of dissatisfaction is given)


the money must be paid once a bond is furnished as security by the party

Department of Finance Page 147


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

receiving payment (the form of bond may be provided in the Works


Requirements Model Form 17) (sub-clause 13.1.11) .

The conciliation is confidential.

The conciliation process is relatively straightforward. One thing that is new in the forms of
Contract is the provision at sub-clause 13.1.11 to the effect that if a payment of money is
recommended by the Conciliator the money is to be paid over upon the provision of a bond as
security. There is also provision for the repayment where applicable of money paid over on foot
of a conciliator’s recommendation or interest earned on such moneys where an arbitrator’s
award is for a lesser amount than the sum originally paid over. (sub-clause 13.1.1).

Example:

If the Employer has discharged the monies due on foot of the conciliator’s recommendation
and has received a bond from the Contractor

Firstly, when considering the form of bond to be furnished by the Contractor in exchange
for payment on foot of the recommendation it may be appropriate to consider carefully the
proposed expiry date of the bond. This is because the Employer may be confronted with an
arbitration which may drag on for a considerable period and a bond which will be due to
expire within a set period of time.

If payment has been made and a bond pursuant to Model Form 19 has been provided the
Employer should consider carefully his approach to the arbitration. It may be that because
the Contractor has received payment he does not want to pursue the arbitration or does
not wish to be the Claimant in the arbitration. However, it would be essential that the
Contractor is the Claimant in the arbitration (unless circumstances dictate that he should
not be) as otherwise it would become evident to the Arbitrator that payment has been made
on a Conciliator’s recommendation. It would therefore be essential that this be agreed
(preferably before payment over of the recommended amount) and that the Contractor
agrees to prosecute the arbitration promptly and efficiently.

Arbitration

Reference sub-clause 13.2

The final dispute resolution mechanism available to the parties is that of


arbitration.

The relevant arbitration rules are as set out in the Works Requirements.

The appointing body in respect of the arbitrator’s appointment in default of


agreement by the parties is that set out in the Schedule (Part 1N).

Disputes under the Contract are subject to the jurisdiction of the Irish courts
and to the Public Works Arbitration Rules 2007.

The Contractor is obliged to appoint an agent for service of proceedings in the


Schedule (part 2).

Department of Finance Page 148


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14.14 Comparison of Traditional and Design & Build Forms for Building
Works
The following table tabulates the differences between the forms for Building
Works designed by the Employer and Building Works designed by the
Contractor.

Building Works Building Works


Designed by Employer Designed by Contractor

Agreement

Article 1 The Contractor shall execute and The Contractor shall design, execute
complete the Works subject to and and complete the Works subject to
in accordance with the Contract, and in accordance with the Contract,
and shall comply with its other and shall comply with its other
obligations in the Contract. obligations in the Contract.

Article 4 The Contractor has satisfied itself The Contractor has satisfied itself
before entering into the Contract before entering into the Contract of
of all the circumstances that may all the circumstances that may affect
affect the cost of executing and the cost of designing, executing and
completing the Works and of the completing the Works and of the
correctness and sufficiency of the correctness and sufficiency of the
Contract Sum to cover the costs of Contract Sum to cover the costs of
performing the Contract. The performing the Contract. The
Contractor has included in the Contractor has included in the initial
initial Contract Sum allowances for Contract Sum allowances for all
all risks, customs, policies, risks, customs, policies, practices,
practices, and other circumstances and other circumstances that may
that may affect its performance of affect its performance of the
the Contract, whether they could Contract, whether they could or
or could not have been foreseen, could not have been foreseen,
except for events for which the except for events for which the
Contract provides for adjustment Contract provides for adjustment of
of the initial Contract Sum. the initial Contract Sum.

Agreement

Article 5 The Contract consists of the The Contract consists of the


following documents: following documents:

• this Agreement • this Agreement


• the Letter of Acceptance and • the Letter of Acceptance and
post- tender clarifications post-tender clarifications listed in
listed in it it
• the attached Conditions and • the attached Conditions and
completed Schedule completed Schedule
• the Works Requirements, • the Works Requirements,
completed Pricing Document, completed Pricing Document, and
and Works Proposals identified Works Proposals identified in the
in the attached Schedule attached Schedule [including any
Novated Design Documents].

Department of Finance Page 149


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

Conditions

Definitions Change Order means an Change Order means an


instruction of the Employer’s instruction of the Employer’s
Representative to change Representative to change [including
[including add to or omit from] add to or omit from] the Works or
the Works or to change [including to change [including impose or
impose or remove] constraints in remove] constraints in the
the Contract on how the Works Contract on how the Works are to
are to be executed. be designed or executed

Definitions Consent means planning Consent means planning


permission, order, approval, permission, order, approval,
certificate, fire certificate, license, certificate, fire certificate,
permit, environmental impact license, permit,
statement, or other consent environmental impact
required by Law for the statement, or other consent
execution or completion of the required by Law for the
Works, or identified as a design, execution or
Consent in the Works completion of the Works, or
Requirements. identified as a Consent in the
Works Requirements.

Definitions Definition not in this contract Novated Design


Documents means
specifications, drawings and
other documents identified
as Novated Design
Documents in the Schedule,
part 1 B, that have been
made by a designer whose
contract is or is to be
novated to the Contractor.

Definitions Starting Date means the day Starting Date means the day the
the Contractor proposes to start Contractor proposes to start
executing the Works, as notified work under the Contract, as
by the Contractor to the notified by the Contractor to the
Employer’s Representative under Employer’s Representative under
sub-clause 9.1. sub-clause 9.1.

Definitions Subcontractor means a Subcontractor means a person to


person to whom the execution whom the design or execution of
of part of the Works is part of the Works is subcontracted
subcontracted [by the [by the Contractor or another
Contractor or another Subcontractor].
Subcontractor].

Department of Finance Page 150


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

1.3.5 Clause not in this Contract The Employer’s Representative may


issue a direction to resolve any
inconsistency within the Works
Requirements, or between the
Works Requirements and other
parts of the Contract, and the
direction shall be conclusive.

1.7 Clause not in this Contract 1.7 Works Requirements

1.7.1. The Contractor has


satisfied itself before entering the
Contract of the adequacy of the
Works Requirements.

1.7.2. The Contractor is fully


responsible for the adequacy
of the Works Requirements,
but is not liable to the
Employer for either of the
following:
(1) statements of intended purpose
of the Works or parts of them
(2) criteria for testing or
performance of the completed
Works or part of them 1.7.3.

1.7.3 The Employer is not liable to


the Contractor for the Works
Requirements.

2.4.1 If the Works Requirements say If the Works Requirements say that
that the Contractor is to be the Contractor is to be appointed
appointed project supervisor for project supervisor for the
the construction stage in construction stage or the design
accordance with the Safety, process or both in accordance with
Health and Welfare at Work the Safety, Health and Welfare at
(Construction) Regulations 2006 Work (Construction) Regulations
(the Construction 2006 (the Construction
Regulations) for the Works, or Regulations) for the Works, or a
a project including the Works, project including the Works, the
the Contractor shall accept the Contractor shall accept the
appointment by entering into the appointment by entering into the
appointment in the form in the appointment in the form in the
Works Requirements. If the Works Requirements. If the Works
Works Requirements say that an Requirements say that an individual
individual or body corporate or body corporate named in the
named in the Works Proposals is Works Proposals is to be
to be appointed project appointed project supervisor for
supervisor for the construction the construction stage or the
stage in accordance with the design process or both in
Safety, Health and Welfare at accordance with the Safety, Health
Work (Construction) Regulations and Welfare at Work
2006 (the Construction (Construction) Regulations 2006

Department of Finance Page 151


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

Regulations) for the Works, or (the Construction Regulations)


a project including the Works, for the Works, or a project
the Contractor shall ensure that including the Works, the
the individual or body corporate Contractor shall ensure that the
named in the Works Proposals individual or body corporate
accepts the appointment by named in the Works Proposals
entering into the appointment in accepts the appointment by
the form in the Works entering into the appointment in
Requirements. the form in the Works
Requirements.
The Contractor shall, if appointed
as project supervisor, comply The Contractor shall, if appointed
with its obligations under the as project supervisor, comply with
Construction Regulations in its obligations under the
connection with that Construction Regulations in
appointment. If the Employer connection with that appointment.
terminates the appointment of If the Employer terminates the
the Contractor or other person appointment of the Contractor or
named in the Works Proposals as other person named in the Works
project supervisor for the Proposals as project supervisor for
construction stage as a result of the construction stage or the
that project supervisor’s failure design process or both as a result
to comply with its obligations, the of that project supervisor’s failure
Contractor shall pay to the to comply with its obligations, the
Employer all the Employer’s cost Contractor shall pay to the
resulting from the termination Employer all the Employer’s cost
[including the cost of appointing resulting from the termination
and fees and expenses paid to a [including the cost of appointing
replacement project supervisor, and fees and expenses paid to a
or, if the Employer acts as project replacement project supervisor, or,
supervisor itself, the Employer’s if the Employer acts as project
cost of doing so]. supervisor itself, the Employer’s
cost of doing so].

2.4.2 If the Contractor or a person If the Contractor or a person


named in the Works Proposals is named in the Works Proposals is
to be appointed as project to be appointed as project
supervisor for the construction supervisor for the construction
stage, the Contractor represents stage or the design process or
and warrants to the Employer both, the Contractor represents
that the Contractor or person and warrants to the Employer that
named in the Works Proposals is the Contractor or person named
competent and will allocate in the Works Proposals is
adequate resources to enable competent and will allocate
itself to perform its duties under adequate resources to enable
the Construction Regulations. itself to perform its duties under
the Construction Regulations.

Department of Finance Page 152


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

2.4.3 If the Contractor or a person If the Contractor or a person


named in the Works Proposals named in the Works Proposals is
is appointed as project appointed as project supervisor
supervisor for the construction for the construction stage or the
stage the Contractor shall ensure design process or both the
that the project supervisor has Contractor shall ensure that the
the insurances required of the project supervisor has the
project supervisor under its insurances required of the project
appointment. supervisor under its appointment

2.4.5 Clause not in this Contract The Contractor shall, before


Substantial Completion of the
Works or any Section, give the
Employer the documents required
for the safety file (as defined in the
Construction Regulations).

2.5.1 The Contractor shall [without The Contractor shall [without


limiting other obligations] ensure, limiting other obligations] ensure, so
so far as is practicable, that the far as is practicable that the Works:
Works are constructed to be safe
(1) are designed and are capable of
and without risk to health, and
being constructed to be safe and
that the Works comply in all
without risk to health and
respects, as appropriate, with the
relevant statutory provisions. (2) are constructed to be safe and
without risk to health and
(3) can be maintained safely and
without risk to health during use
and
(4) comply in all respects, as
appropriate, with the relevant
statutory provisions.

2.5.2 The Contractor represents and The Contractor represents and


warrants to the Employer that warrants to the Employer that the
the Contractor is, and will, while Contractor is, and will, while
performing the Contract, be a performing the Contract, be a
competent person for the competent person for the purpose of
purpose of ensuring, so far as is ensuring, so far as is reasonably
reasonably practicable, that the practicable, that the Works:
Works are constructed to be
(1) are designed and are capable of
safe and without risk to health
being constructed to be safe and
and that they comply in all
without risk to health and
respects, as appropriate, with the
relevant statutory provisions. (2) are constructed to be safe and
without risk to health and
(3) can be maintained safely and
without risk to health during use
and
(4) comply in all respects, as
appropriate, with the relevant
statutory provisions.

Department of Finance Page 153


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

3.1 (6) design of the Works by the Clause not in this Contract
Employer or by others for
whom the Employer is
responsible, but not if the
design is covered by insurance
required under clause 3.7.

4.5.4 The Employer’s Representative Clause not in this Contract


shall give an instruction that is,
in the Employer’s
Representative’s opinion,
necessary for the completion
of the Works. If, in the
Employer’s Representative’s
opinion, it is physically
impossible or contrary to Legal
Requirements to complete the
Works in accordance with the
Works Requirements, the
Employer’s Representative
shall give a Change Order.

The Employer’s Representative


shall give an instruction required
under this sub-clause 4.5.4 within
the time required by sub-clause
4.11.

4.6 4.6. Works Proposals 4.6. Works Requirements,


Works Proposals and
Novated Design Documents

4.6.2 If any Works Proposals do not If any Works Requirements or


comply with the Contract or the Works Proposals do not comply
initial Works Requirements or with the Contract or Legal
Legal Requirements or are Requirements or are physically
physically impossible to comply impossible to comply with, or if any
with, the Contractor shall propose Works Proposals do not comply with
a change to the Works Proposals the initial Works Requirements, the
as necessary. [There shall be no Contractor shall propose a change to
extension of time or adjustment the Works Requirements as
to the Contract Sum for this.] If necessary. The change shall not take
the Works Proposals need to be effect until it has been agreed by the
changed because of a change to Employer’s Representative. The
the Works Requirements, the Contractor shall submit any change
Contractor shall propose a to the Works Proposals to the
change. The Contractor shall Employer’s Representative. [There
submit any change to the Works shall be no extension of time, use of
Proposals to the Employer’s programme contingency under sub-
Representative. clause 9.4, or adjustment to the
Contract Sum for changes or actions
under this sub-clause 4.6 or their
consequences.]

Department of Finance Page 154


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

4.6.3 Clause not in this Contract The Contractor adopts the Novated
Design Documents as Works
Proposals, and is fully responsible for
them. [The Contractor shall submit
any changes to the Novated Design
Documents to the Employer’s
Representative.]

4.8.1 The Contractor may give to the The Contractor may give to the
Employer’s Representative a Employer’s Representative a written
written value engineering proposal value engineering proposal that will,
that will, if adopted, either: if adopted, either:

(1) reduce the Contract Sum or (1) reduce the Contract Sum or
(2) accelerate the execution of the (2) accelerate the design or
Works, or otherwise be of execution of the Works, or
benefit to the Employer, with otherwise be of benefit to the
no increase to the Contract Employer, with no increase to
Sum. the Contract Sum.

4.11.2 The latest date for the Employer’s The latest date for the Employer to
Representative to give required give the Contractor any required
instructions, or the Employer to Works Item or other thing, shall be
give the Contractor any the latest of the following:
required Works Item or other
thing, shall be the latest of the
following:

(1) the date stated in the (1) the date stated in the Contract,
Contract, if any if any
(2) the date shown in the (2) the date shown in the
Contractor’s current Contractor’s current
programme programme
(3) the date for which the (3) the date for which the
Contractor first notifies the Contractor first notifies the
Employer’s Representative Employer’s Representative under
under this sub-clause that it is this sub-clause that it is required
required
(4) the date the Contractor requires
(4) the date the Contractor the instruction, Works Item or
requires the instruction, other thing in accordance with
Works Item or other thing in its actual progress.
accordance with its actual
progress.

Department of Finance Page 155


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

4.16.3 This sub-clause 4.16 shall not This sub-clause 4.16 shall not prevent
prevent disclosure of information, disclosure of information, to the
to the extent permitted by Law: extent permitted by Law:

(1) to the Contractor’s Personnel, (1) to the Contractor’s Personnel,


the Employer’s Personnel or the Employer’s Personnel or
other professional advisors to other professional advisors to
the Contractor or Employer, the Contractor or Employer,
who have first entered an who have first entered an
undertaking in the terms of undertaking in the terms of this
this sub-clause 4.16, to the sub-clause 4.16, to the extent
extent necessary for the necessary for the design or
execution of the Works or to execution of the Works or to
enforce the Contract or enforce the Contract or

7.1.1 Clause not in this Contract (6) 10 working days (or another
period stated in the Works
Requirements) after the
Contractor has informed the
Employer’s Representative that
it is ready to start executing the
Works on the Site

7.1.1 Clause not in this Contract (8) 10 working days after the
Contractor has obtained all the
Consents it needs to start
executing the Works on the Site
and given copies to the
Employer’s Representative.

7.5.1 From and including the Starting From and including the date the
Date until the Employer’s Employer allows the Contractor to
Representative certifies the occupy and use the Site until the
Works or the relevant Section as Employer’s Representative certifies
Substantially Complete, or the the Works or the relevant Section as
Employer takes over the relevant Substantially Complete, or the
part of the Works under sub- Employer takes over the relevant
clause 9.7, the Contractor shall do part of the Works under sub-clause
all of the following [without 9.7, the Contractor shall do all of the
limiting other obligations]: following [without limiting other
obligations]:

7.6 Where so stated in the Works Where so stated in the Works


Requirements, the Employer may Requirements, the Employer may
arrange for work to be executed arrange for work to be executed on
on the Site by Employer’s the Site by Employer’s Personnel.
Personnel. The Contractor shall The Contractor shall co-operate
co-operate with such Employer’s with such Employer’s Personnel and
Personnel and shall as far as shall as far as practicable co-ordinate
practicable co-ordinate their their activities with the design and
activities with the execution of the execution of the Works.
Works.

Department of Finance Page 156


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

7.7 The Contractor shall set out the The Contractor shall be responsible
Works by reference to the points, for the correct positioning of all parts
lines and levels of reference in the of the Works and shall rectify any
Works Requirements. The errors in the positions, levels,
Contractor shall be responsible for dimensions or alignment of the
the correct positioning of all parts Works.
of the Works and shall rectify any
errors in the positions, levels,
dimensions or alignment of the
Works. Before setting out the
Works the Contractor shall make
all reasonable efforts to verify the
accuracy of the setting out
information in the Works
Requirements.

8.1 The Contractor shall ensure all of The Contractor shall ensure all of
the following: the following:
(1) that the Works are executed (1) that the Works are designed,
and completed executed and completed
(i) in accordance with all the (i) in accordance with all the
requirements in, and requirements in, and
reasonably inferred from, reasonably inferred from,
the Contract [including, the Contract [including,
where so required by the where so required by the
Contract, in accordance Contract, in accordance
with Contractor’s with Contractor’s
Documents that have Documents that have been
been submitted to the submitted to the Employer’s
Employer’s Representative] and
Representative] and (ii) in a proper and
(ii) in a proper and workmanlike manner and
workmanlike manner and using good practice
using good practice

8.1 (3) that all materials and goods (3) that all materials and goods that
that are Works Items are Works Items are fit for their
[whether or not the intended purpose in the Works
Contractor is required to
select them] are fit for the
purpose for which they are
normally used

8.1 (4) that all Works Items selected (4) that the completed Works are
or designed by the Contractor fit for their intended purpose as
[including by any Specialist] are stated in or to be inferred from
fit for their intended purpose the Works Requirements.
in the Works.

Department of Finance Page 157


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

8.3.1 The Contractor shall ensure that The Contractor shall ensure that the
the Employer’s Representative, and Employer’s Representative, and
anyone authorised by the anyone authorised by the Employer’s
Employer’s Representative, is able Representative, is able at all
at all reasonable times to have reasonable times to have access to
access to all places where the all places where the Works are being
Works are being executed designed or executed [whether or
[whether or not at the Site] and not at the Site] and any place where
any place where any Works Items any Works Items are produced,
are produced, stored, extracted or stored, extracted or prepared, or
prepared, or any other obligation any other obligation of the
of the Contractor under the Contractor under the Contract is
Contract is being performed, being performed, and are able there
and are able there to inspect, to inspect, test, observe and examine
test, observe and examine all all such items and activities.
such items and activities.

9.1.2 Before the Starting Date [unless Before the Starting Date [unless
already given by the Contractor already given by the Contractor
before the Contract Date, for before the Contract Date, for
example in response to a letter of example in response to a letter of
intent] the Contractor shall give intent] the Contractor shall give the
the Employer all of the following, Employer all of the following, all
all executed, as relevant, by the executed, as relevant, by the relevant
relevant persons: persons:

(1) the Agreement (1) the Agreement


(2) a performance bond, if (2) a performance bond, if required
required by the Contract by the Contract
(3) a parent company guarantee, if (3) a parent company guarantee, if
required by the Contract required by the Contract
(4) if the Works Requirements (4) if the Works Requirements state
state that the Contractor or that the Contractor or the
the Contractor’s nominee is to Contractor’s nominee is to be
be appointed as project appointed as project supervisor
supervisor for the for the construction stage or the
construction stage, the design process or both, the
required appointment, and the required appointment, and the
developed safety and health developed safety and health plan
plan required by the required by the Construction
Construction Regulations Regulations

9.1.3 On the Starting Date, the On the Starting Date, the


Contractor shall start to execute Contractor shall start work under
the Works on the Site. The the Contract. The Contractor shall,
Contractor shall, unless the unless the Employer’s Representative
Employer’s Representative directs otherwise, proceed regularly
directs otherwise, proceed and diligently in order to achieve
regularly and diligently in order Substantial Completion of the Works
to achieve Substantial and each Section by its Date for
Completion of the Works and Substantial Completion.
each Section by its Date for
Substantial Completion.

Department of Finance Page 158


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

10.6.4 Clause not in this Contract (4) the cost of design, at the
tendered rates in the Pricing
Document.

11.1.2 11.1.2 The installment of the 11.1.2 The installment of the


Contract Sum that the Contract Sum that the
Contractor shall be entitled to Contractor shall be entitled to
be paid on an interim basis be paid on an interim basis shall
shall be: be:

(1) the Contract value of the (1) the Contract value of the
Works properly executed by Works properly designed and
the Contractor [according to executed by the Contractor
the Pricing Document] and [according to the Pricing
Document] and

12.1.1 (2) the Contractor abandons or, (2) the Contractor abandons or,
except where required or except where required or
permitted by the Contract, permitted by the Contract,
suspends the execution of the suspends the design or execution
Works of the Works

12.1.1 (3) the Contractor fails to (3) the Contractor fails to proceed
proceed regularly and diligently regularly and diligently with the
with the execution of the design and execution of the
Works Works

12.1.1 (5) the Starting Date has not (5) the Starting Date has not
occurred or the occurred or the Contractor has
Contractor has not not started work under the
started to execute the Contract within 6 weeks of the
Works on the Site within date the Contract requires
6 weeks of the date the
Contract requires

12.3 If the Employer fails to pay any If the Employer fails to pay any
amount due under a certificate amount due under a certificate
issued by the Employer’s issued by the Employer’s
Representative under the Representative under the Contract,
Contract, the Contractor may the Contractor may make of the
make of the Employer a written Employer a written demand for
demand for payment, and if the payment, and if the payment has not
payment has not been made within been made within 15 working days of
15 working days of the receipt of the receipt of the demand, the
the demand, the Contractor may, Contractor may, on giving notice to
on giving notice to the Employer, the Employer, suspend design and
suspend execution of the Works execution of the Works until the
until the amount has been paid. amount has been paid. On receiving
On receiving the payment, the the payment, the Contractor shall
Contractor shall resume resume design and execution of the
execution of the Works. Works.

Department of Finance Page 159


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

12.4 The Contractor shall be entitled to The Contractor shall be entitled to


terminate the Contractor’s terminate the Contractor’s
obligation to complete the Works obligation to complete the Works by
by notice to the Employer if any of notice to the Employer if any of the
the following occur: following occur:

(1) the Contractor has suspended (1) the Contractor has suspended
the execution of the Works the design and execution of the
for 15 working days in Works for 15 working days in
accordance with clause 12.3, accordance with clause 12.3, and
and the Employer has still not the Employer has still not paid
paid

12.5.2 The Employer may not terminate The Employer may not terminate the
the Contractor’s obligation to Contractor’s obligation to complete
complete the Works under this the Works under this sub-clause 12.5
sub-clause 12.5 for the purpose of for the purpose of retaining another
retaining another contractor to contractor to design and execute the
execute the Works. Works.

Schedule Part 1

B The Works Requirements are … The Works Requirements are: …

The Pricing Documents is … The Novated Design Documents are:


The Pricing Documents is: …

K5 There is a factual error in information Schedule item not in this Contract


about the Site or setting out
information in the Works
Requirements. [This does not
include an error of interpretation.]

K7 The Employer’s Representative does Schedule item not in this Contract


not give the Contractor an instruction
required under sub-clause 4.5.4 within
the time required under sub-clause
4.11.2 when the Contractor has asked
for the instruction in accordance with
sub-clause 4.11.1

K 17 A difference between the Contract Schedule item not in this Contract


value of the Works according to the
quantities and descriptions in the
Bill of Quantities [taking into
account the method of
measurement identified below
when it applies] and the Contract
value of the Works described in the
Works Requirements, because the Bill
of Quantities, when compared with the
Works Requirements:

Department of Finance Page 160


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Building Works Building Works


Designed by Employer Designed by Contractor

• includes an incorrect quantity or


• includes an item that should not
have been included or
• excludes an item that should have
been included or
• gives an incorrect item description

and the difference for an item in, or


that should have been in, the Bill of
Quantities is more than €500.

K 19 The Contractor encounters on the Schedule item not in this Contract


Site unforeseeable ground conditions
or
man-made obstructions in the ground,
other than Utilities

K 20 The Contractor encounters Schedule item not in this Contract


unforeseeable Utilities in the ground
on the Site

A condition, circumstance or A condition, circumstance or


occurrence is unforeseeable if occurrence is unforeseeable if an
an experienced contractor experienced contractor tendering
tendering for the Works could for the Works could not have
not have reasonably foreseen it on reasonably foreseen it on the
the Designated Date, having Designated Date, having inspected
inspected the Site and its the Site and its surroundings and
surroundings and having satisfied having satisfied itself as to all matters
itself, insofar as practicable and concerning the Site.
taking into account any
information in connection with the
Site provided by the Employer, as
to all matters concerning the Site,
including its form and nature and
its geotechnical, hydrological and
climatic conditions.

Schedule Part 2

B Note: In open procedures, Note: Tenderers must name a


tenderers must name a guarantor if guarantor if parent company has
parent company is identified for been identified for purposes of pre-
purposes of satisfying tender qualification.
requirements. In restricted
procedures, tenderers must name a
guarantor if parent company has
been identified for purposes of pre-
qualification.

Department of Finance Page 161


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14.15 Comparison of Traditional and Design & Build Forms for Civil
Engineering Works
The following table summarises the differences between the forms for civil
engineering works designed by the employer and civil engineering works
designed by the contractor."

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

Agreement

Article 1 The Contractor shall execute and The Contractor shall design, execute
complete the Works subject to and in and complete the Works subject to
accordance with the Contract, and shall and in accordance with the Contract,
comply with its other obligations in the and shall comply with its other
Contract. obligations in the Contract.

Article 4 The Contractor has satisfied itself The Contractor has satisfied itself
before entering into the Contract of all before entering into the Contract of all
the circumstances that may affect the the circumstances that may affect the
cost of executing and completing the cost of designing, executing and
Works and of the correctness and completing the Works and of the
sufficiency of the Contract Sum to cover correctness and sufficiency of the
the costs of performing the Contract. Contract Sum to cover the costs of
The Contractor has included in the performing the Contract. The
initial Contract Sum allowances for all Contractor has included in the initial
risks, customs, policies, practices, and Contract Sum allowances for all risks,
other circumstances that may affect its customs, policies, practices, and other
performance of the Contract, whether circumstances that may affect its
they could or could not have been performance of the Contract, whether
foreseen, except for events for which they could or could not have been
the Contract provides for adjustment of foreseen, except for events for which
the initial Contract Sum. the Contract provides for adjustment
of the initial Contract Sum.

Article 5 The Contract consists of the following The Contract consists of the following
documents: documents:

• this Agreement • this Agreement


• the Letter of Acceptance and post- • the Letter of Acceptance and
tender clarifications listed in it post-tender clarifications listed in
it
• the attached Conditions and
completed Schedule • the attached Conditions and
completed Schedule
the Works Requirements, completed
Pricing Document, and Works Proposals • the Works Requirements,
identified in the attached Schedule completed Pricing Document, and
Works Proposals identified in the
attached Schedule [including any
Novated Design Documents].

Department of Finance Page 162


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

Conditions

Definitions Change Order means an instruction of Change Order means an instruction


the Employer’s Representative to change of the Employer’s Representative to
[including add to or omit from] the change [including add to or omit from]
Works or to change [including impose the Works or to change [including
or remove] constraints in the Contract impose or remove] constraints in the
on how the Works are to be executed. Contract on how the Works are to be
designed or executed.

Definitions Consent means planning permission, Consent means planning permission,


order, approval, certificate, fire order, approval, certificate, fire
certificate, licence, permit, certificate, licence, permit,
environmental impact statement, or environmental impact statement, or
other consent required by Law for the other consent required by Law for the
execution or completion of the Works, design, execution or completion of the
or identified as a Consent in the Works Works, or identified as a Consent in
Requirements. the Works Requirements.

Definitions Definition not in this contract Novated Design Documents


means specifications, drawings and
other documents identified as Novated
Design Documents in the Schedule,
part 1 B, that have been made by a
designer whose contract is or is to be
novated to the Contractor.

Definitions Starting Date means the day the Starting Date means the day the
Contractor proposes to start executing Contractor proposes to start work
the Works, as notified by the under the Contract, as notified by the
Contractor to the Employer’s Contractor to the Employer’s
Representative under sub-clause 9.1. Representative under sub-clause 9.1.

Definitions Subcontractor means a person to Subcontractor means a person to


whom the execution of part of the whom the design or execution of part
Works is subcontracted [by the of the Works is subcontracted [by the
Contractor or another Subcontractor]. Contractor or another
Subcontractor].

1.3.5 Clause not in this Contract The Employer’s Representative may


issue a direction to resolve any
inconsistency within the Works
Requirements, or between the Works
Requirements and other parts of the
Contract, and the direction shall be
conclusive.

Department of Finance Page 163


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

1.7 Clause not in this Contract 1.7 Works Requirements

1.7.1 The Contractor has satisfied


itself before entering the
Contract of the adequacy of the
Works Requirements.

1.7.2 The Contractor is fully


responsible for the adequacy of
the Works Requirements, but
is not liable to the Employer for
either of the following:

(1) statements of intended


purpose of the Works or
parts of them
(2) criteria for testing or
performance of the
completed Works or part
of them 1.7.3.

1.7.3 The Employer is not liable to


the Contractor for the Works
Requirements.

2.4.1 If the Works Requirements say that the If the Works Requirements say that
Contractor is to be appointed project the Contractor is to be appointed
supervisor for the construction stage in project supervisor for the
accordance with the Safety, Health and construction stage or the design
Welfare at Work (Construction) process or both in accordance with
Regulations 2006 (the Construction the Safety, Health and Welfare at
Regulations) for the Works, or a project Work (Construction) Regulations
including the Works, the Contractor 2006 (the Construction Regulations)
shall accept the appointment by entering for the Works, or a project including
into the appointment in the form in the the Works, the Contractor shall
Works Requirements. If the Works accept the appointment by entering
Requirements say that an individual or into the appointment in the form in
body corporate named in the Works the Works Requirements. If the
Proposals is to be appointed project Works Requirements say that an
supervisor for the construction stage in individual or body corporate named in
accordance with the Safety, Health and the Works Proposals is to be
Welfare at Work (Construction) appointed project supervisor for the
Regulations 2006 (the Construction construction stage or the design
Regulations) for the Works, or a project process or both in accordance with
including the Works, the Contractor the Safety, Health and Welfare at
shall ensure that the individual or body Work (Construction) Regulations
corporate named in the Works 2006 (the Construction Regulations)
Proposals accepts the appointment by for the Works, or a project including
entering into the appointment in the the Works, the Contractor shall
form in the Works Requirements. The ensure that the individual or body
Contractor shall, if appointed as project corporate named in the Works
supervisor, comply with its obligations Proposals accepts the appointment by
under the Construction Regulations in entering into the appointment in the

Department of Finance Page 164


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

connection with that appointment. If the form in the Works Requirements. The
Employer terminates the appointment of Contractor shall, if appointed as
the Contractor or other person named project supervisor, comply with its
in the Works Proposals as project obligations under the Construction
supervisor for the construction stage as Regulations in connection with that
a result of that project supervisor’s appointment. If the Employer
failure to comply with its obligations, the terminates the appointment of the
Contractor shall pay to the Employer all Contractor or other person named in
the Employer’s cost resulting from the the Works Proposals as project
termination [including the cost of supervisor for the construction stage
appointing and fees and expenses paid to or the design process or both as a
a replacement project supervisor, or, if result of that project supervisor’s
the Employer acts as project supervisor failure to comply with its obligations,
itself, the Employer’s cost of doing so]. the Contractor shall pay to the
Employer all the Employer’s cost
resulting from the termination
[including the cost of appointing and
fees and expenses paid to a
replacement project supervisor, or, if
the Employer acts as project
supervisor itself, the Employer’s cost
of doing so].

2.4.2 If the Contractor or a person named in If the Contractor or a person named


the Works Proposals is to be appointed in the Works Proposals is to be
as project supervisor for the appointed as project supervisor for the
construction stage, the Contractor construction stage or the design
represents and warrants to the process or both, the Contractor
Employer that the Contractor or person represents and warrants to the
named in the Works Proposals is Employer that the Contractor or
competent and will allocate adequate person named in the Works Proposals
resources to enable itself to perform its is competent and will allocate
duties under the Construction adequate resources to enable itself to
Regulations. perform its duties under the
Construction Regulations.

2.4.3 If the Contractor or a person named in If the Contractor or a person named


the Works Proposals is appointed as in the Works Proposals is appointed as
project supervisor for the construction project supervisor for the
stage the Contractor shall ensure that construction stage or the design
the project supervisor has the process or both the Contractor shall
insurances required of the project ensure that the project supervisor has
supervisor under its appointment. the insurances required of the project
supervisor under its appointment.

2.4.5 Clause not in this Contract The Contractor shall, before


Substantial Completion of the Works
or any Section, give the Employer the
documents required for the safety file
(as defined in the Construction
Regulations).

Department of Finance Page 165


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

2.5.1 The Contractor shall [without limiting The Contractor shall [without limiting
other obligations] ensure, so far as is other obligations] ensure, so far as is
practicable, that the Works are practicable that the Works:
constructed to be safe and without risk
to health, and that the Works comply in (1) are designed and are capable of
all respects, as appropriate, with the being constructed to be safe and
relevant statutory provisions. without risk to health and
(2) are constructed to be safe and
without risk to health and
(3) can be maintained safely and
without risk to health during use
and
(4) comply in all respects, as
appropriate, with the relevant
statutory provisions.

2.5.2 The Contractor represents and The Contractor represents and


warrants to the Employer that the warrants to the Employer that the
Contractor is, and will, while performing Contractor is, and will, while
the Contract, be a competent person performing the Contract, be a
for the purpose of ensuring, so far as is competent person for the purpose of
reasonably practicable, that the Works ensuring, so far as is reasonably
are constructed to be safe and without practicable, that the Works:
risk to health and that they comply in all
respects, as appropriate, with the (1) are designed and are capable of
relevant statutory provisions. being constructed to be safe and
without risk to health and
(2) are constructed to be safe and
without risk to health and
(3) can be maintained safely and
without risk to health during use
and
(4) comply in all respects, as
appropriate, with the relevant
statutory provisions.

3.1 (6) design of the Works by the Clause not in this Contract
Employer or by others for whom
the Employer is responsible, but not
if the design is covered by insurance
required under clause 3.7.

4.5.4 The Employer’s Representative shall give Clause not in this Contract
an instruction that is, in the Employer’s
Representative’s opinion, necessary for
the completion of the Works. If, in the
Employer’s Representative’s opinion, it
is physically impossible or contrary to
Legal Requirements to complete the
Works in accordance with the Works

Department of Finance Page 166


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

Requirements, the Employer’s


Representative shall give a Change
Order. The Employer’s Representative
shall give an instruction required under
this sub-clause 4.5.4 within the time
required by sub-clause 4.11.

4.6 4.6 Works Proposals 4.6 Works Requirements, Works


Proposals and Novated
Design Documents

4.6.2 If any Works Proposals do not comply If any Works Requirements or Works
with the Contract or the initial Works Proposals do not comply with the
Requirements or Legal Requirements or Contract or Legal Requirements or
are physically impossible to comply with, are physically impossible to comply
the Contractor shall propose a change with, or if any Works Proposals do
to the Works Proposals as necessary. not comply with the initial Works
[There shall be no extension of time or Requirements, the Contractor shall
adjustment to the Contract Sum for propose a change to the Works
this.] If the Works Proposals need to be Requirements as necessary. The
changed because of a change to the change shall not take effect until it has
Works Requirements, the Contractor been agreed by the Employer’s
shall propose a change. The Contractor Representative. The Contractor shall
shall submit any change to the Works submit any change to the Works
Proposals to the Employer’s Proposals to the Employer’s
Representative. Representative. [There shall be no
extension of time, use of programme
contingency under sub-clause 9.4, or
adjustment to the Contract Sum for
changes or actions under this sub-
clause 4.6 or their consequences.]

4.6.3 Clause not in this Contract The Contractor adopts the Novated
Design Documents as Works
Proposals, and is fully responsible for
them. [The Contractor shall submit
any changes to the Novated Design
Documents to the Employer’s
Representative.]

4.8.1 The Contractor may give to the The Contractor may give to the
Employer’s Representative a written Employer’s Representative a written
value engineering proposal that will, if value engineering proposal that will, if
adopted, either: adopted, either:

(1) reduce the Contract Sum or (1) reduce the Contract Sum or
(2) accelerate the execution of the (2) accelerate the design or execution
Works, or otherwise be of benefit of the Works, or otherwise be of
to the Employer, with no increase benefit to the Employer, with no
to the Contract Sum. increase to the Contract Sum.

Department of Finance Page 167


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

4.11.2 The latest date for the Employer’s The latest date for the Employer to
Representative to give required give the Contractor any required
instructions, or the Employer to give the Works Item or other thing, shall be
Contractor any required Works Item or the latest of the following:
other thing, shall be the latest of the
following: (1) the date stated in the Contract, if
any
(1) the date stated in the Contract, if
(2) the date shown in the
any
Contractor’s current programme
(2) the date shown in the Contractor’s
(3) the date for which the Contractor
current programme
first notifies the Employer’s
(3) the date for which the Contractor Representative under this sub-
first notifies the Employer’s clause that it is required
Representative under this sub-
(4) the date the Contractor requires
clause that it is required
the instruction, Works Item or
(4) the date the Contractor requires other thing in accordance with its
the instruction, Works Item or actual progress.
other thing in accordance with its
actual progress.

4.16.3 This sub-clause 4.16 shall not prevent This sub-clause 4.16 shall not prevent
disclosure of information, to the extent disclosure of information, to the
permitted by Law: extent permitted by Law:

(1) to the Contractor’s Personnel, the (1) to the Contractor’s Personnel, the
Employer’s Personnel or other Employer’s Personnel or other
professional advisors to the professional advisors to the
Contractor or Employer, who have Contractor or Employer, who
first entered an undertaking in the have first entered an undertaking
terms of this sub-clause 4.16, to the in the terms of this sub-clause
extent necessary for the execution 4.16, to the extent necessary for
of the Works or to enforce the the design or execution of the
Contract or Works or to enforce the
Contract or

7.1.1 Clause not in this Contract (6) 10 working days (or another
period stated in the Works
Requirements) after the
Contractor has informed the
Employer’s Representative that it
is ready to start executing the
Works on the Site

7.1.1 Clause not in this Contract (8) 10 working days after the
Contractor has obtained all the
Consents it needs to start
executing the Works on the Site
and given copies to the Employer’s
Representative.

Department of Finance Page 168


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

7.5.1 From and including the Starting Date From and including the date the
until the Employer’s Representative Employer allows the Contractor to
certifies the Works or the relevant occupy and use the Site until the
Section as Substantially Complete, or Employer’s Representative certifies the
the Employer takes over the relevant Works or the relevant Section as
part of the Works under sub-clause 9.7, Substantially Complete, or the
the Contractor shall do all of the Employer takes over the relevant part
following [without limiting other of the Works under sub-clause 9.7, the
obligations]: Contractor shall do all of the following
[without limiting other obligations]:

7.6 Where so stated in the Works Where so stated in the Works


Requirements, the Employer may Requirements, the Employer may
arrange for work to be executed on the arrange for work to be executed on
Site by Employer’s Personnel. The the Site by Employer’s Personnel. The
Contractor shall co-operate with such Contractor shall co-operate with such
Employer’s Personnel and shall as far as Employer’s Personnel and shall as far
practicable co-ordinate their activities as practicable co-ordinate their
with the execution of the Works. activities with the design and execution
of the Works.

7.7 The Contractor shall set out the Works The Contractor shall be responsible
by reference to the points, lines and for the correct positioning of all parts
levels of reference in the Works of the Works and shall rectify any
Requirements. The Contractor shall be errors in the positions, levels,
responsible for the correct positioning dimensions or alignment of the Works.
of all parts of the Works and shall rectify
any errors in the positions, levels,
dimensions or alignment of the Works.
Before setting out the Works the
Contractor shall make all reasonable
efforts to verify the accuracy of the
setting out information in the Works
Requirements.

8.1 The Contractor shall ensure all of the The Contractor shall ensure all of the
following: following:

(1) that the Works are executed and (1) that the Works are designed,
completed executed and completed

(i) in accordance with all the (i) in accordance with all the
requirements in, and reasonably requirements in, and
inferred from, the Contract reasonably inferred from, the
[including, where so required Contract [including, where so
by the Contract, in accordance required by the Contract, in
with Contractor’s Documents accordance with Contractor’s
that have been submitted to the Documents that have been
Employer’s Representative] and submitted to the Employer’s
Representative] and
(ii) in a proper and workmanlike
manner and using good practice (ii) in a proper and workmanlike
manner and using good
practice

Department of Finance Page 169


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

8.1 (3) that all materials and goods that are (3) that all materials and goods that
Works Items [whether or not the are Works Items are fit for their
Contractor is required to select intended purpose in the Works
them] are fit for the purpose for
which they are normally used

8.1 (4) that all Works Items selected or (4) that the completed Works are fit
designed by the Contractor for their intended purpose as
[including by any Specialist] are fit stated in or to be inferred from
for their intended purpose in the the Works Requirements.
Works.

8.3.1 The Contractor shall ensure that the The Contractor shall ensure that the
Employer’s Representative, and anyone Employer’s Representative, and anyone
authorised by the Employer’s authorised by the Employer’s
Representative, is able at all reasonable Representative, is able at all reasonable
times to have access to all places where times to have access to all places
the Works are being executed [whether where the Works are being designed
or not at the Site] and any place where or executed [whether or not at the
any Works Items are produced, stored, Site] and any place where any Works
extracted or prepared, or any other Items are produced, stored, extracted
obligation of the Contractor under the or prepared, or any other obligation of
Contract is being performed, and are the Contractor under the Contract is
able there to inspect, test, observe and being performed, and are able there to
examine all such items and activities. inspect, test, observe and examine all
such items and activities.

9.1.2 Before the Starting Date [unless already Before the Starting Date [unless
given by the Contractor before the already given by the Contractor before
Contract Date, for example in response the Contract Date, for example in
to a letter of intent] the Contractor response to a letter of intent] the
shall give the Employer all of the Contractor shall give the Employer all
following, all executed, as relevant, by of the following, all executed, as
the relevant persons: relevant, by the relevant persons:

(1) the Agreement (1) the Agreement


(2) a performance bond, if required by (2) a performance bond, if required
the Contract by the Contract
(3) a parent company guarantee, if (3) a parent company guarantee, if
required by the Contract required by the Contract
(4) if the Works Requirements state (4) if the Works Requirements state
that the Contractor or the that the Contractor or the
Contractor’s nominee is to be Contractor’s nominee is to be
appointed as project supervisor for appointed as project supervisor
the construction stage, the required for the construction stage or the
appointment, and the developed design process or both, the
safety and health plan required by required appointment, and the
the Construction Regulations developed safety and health plan
required by the Construction
Regulations

Department of Finance Page 170


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

9.1.3 On the Starting Date, the Contractor On the Starting Date, the Contractor
shall start to execute the Works on the shall start work under the Contract.
Site. The Contractor shall, unless the The Contractor shall, unless the
Employer’s Representative directs Employer’s Representative directs
otherwise, proceed regularly and otherwise, proceed regularly and
diligently in order to achieve Substantial diligently in order to achieve
Completion of the Works and each Substantial Completion of the Works
Section by its Date for Substantial and each Section by its Date for
Completion. Substantial Completion.

10.6.4 Clause not in this Contract (4) the cost of design, at the tendered
rates in the Pricing Document.

11.1.2 The installment of the Contract Sum The installment of the Contract Sum
that the Contractor shall be entitled to that the Contractor shall be entitled to
be paid on an interim basis shall be: be paid on an interim basis shall be:

(1) the Contract value of the Works (1) the Contract value of the Works
properly executed by the properly designed and executed
Contractor [according to the by the Contractor [according to
Pricing Document] and the Pricing Document] and

12.1.1 (2) the Contractor abandons or, except (2) the Contractor abandons or,
where required or permitted by the except where required or
Contract, suspends the execution of permitted by the Contract,
the Works suspends the design or execution
of the Works

12.1.1 (3) the Contractor fails to proceed (3) the Contractor fails to proceed
regularly and diligently with the regularly and diligently with the
execution of the Works design and execution of the
Works

12.1.1 (5) the Starting Date has not occurred (5) the Starting Date has not
or the Contractor has not started occurred or the Contractor has
to execute the Works on the Site not started work under the
within 6 weeks of the date the Contract within 6 weeks of the
Contract requires date the Contract requires

12.3 If the Employer fails to pay any amount If the Employer fails to pay any amount
due under a certificate issued by the due under a certificate issued by the
Employer’s Representative under the Employer’s Representative under the
Contract, the Contractor may make of Contract, the Contractor may make of
the Employer a written demand for the Employer a written demand for
payment, and if the payment has not payment, and if the payment has not
been made within 15 working days of been made within 15 working days of
the receipt of the demand, the the receipt of the demand, the
Contractor may, on giving notice to the Contractor may, on giving notice to
Employer, suspend execution of the the Employer, suspend design and
Works until the amount has been paid. execution of the Works until the
On receiving the payment, the amount has been paid. On receiving
Contractor shall resume execution of the payment, the Contractor shall
the Works. resume design and execution of the
Works.

Department of Finance Page 171


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

12.4 The Contractor shall be entitled to The Contractor shall be entitled to


terminate the Contractor’s obligation to terminate the Contractor’s obligation
complete the Works by notice to the to complete the Works by notice to
Employer if any of the following occur: the Employer if any of the following
occur:
(1) the Contractor has suspended the
execution of the Works for 15 (1) the Contractor has suspended the
working days in accordance with design and execution of the
clause 12.3, and the Employer has Works for 15 working days in
still not paid accordance with clause 12.3, and
the Employer has still not paid

12.5.2 The Employer may not terminate the The Employer may not terminate the
Contractor’s obligation to complete the Contractor’s obligation to complete
Works under this sub-clause 12.5 for the Works under this sub-clause 12.5
the purpose of retaining another for the purpose of retaining another
contractor to execute the Works. contractor to design and execute the
Works.

Schedule Part 1

B The Works Requirements are … The Works Requirements are: …

The Pricing Documents is … The Novated Design Documents are:


The Pricing Documents is: …

K5 There is a factual error in information Schedule item not in this Contract


about the Site or setting out information
in the Works Requirements. [This does
not include an error of interpretation.]

K7 The Employer’s Representative does not Schedule item not in this Contract
give the Contractor an instruction
required under sub-clause 4.5.4 within
the time required under sub-clause
4.11.2 when the Contractor has asked
for the instruction in accordance with
sub-clause 4.11.1

K 17 A difference between the Contract value Schedule item not in this Contract
of the Works according to the quantities
and descriptions in the Bill of Quantities
[taking into account the method of
measurement identified below when it
applies] and the Contract value of the
Works described in the Works
Requirements, because the Bill of
Quantities, when compared with the
Works Requirements:

Department of Finance Page 172


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Civil Engineering Works Civil Engineering Works


Designed by Employer Designed by Contractor

• includes an incorrect quantity or


• includes an item that should not
have been included or
• excludes an item that should have
been included or
• gives an incorrect item description

and the difference for an item in, or that


should have been in, the Bill of
Quantities is more than €500.

K 19 The Contractor encounters on the Site Schedule item not in this Contract
unforeseeable ground conditions or
man-made obstructions in the ground,
other than Utilities

K 20 The Contractor encounters Schedule item not in this Contract


unforeseeable Utilities in the ground on
the Site

A condition, circumstance or A condition, circumstance or


occurrence is unforeseeable if an occurrence is unforeseeable if an
experienced contractor tendering for experienced contractor tendering for
the Works could not have reasonably the Works could not have reasonably
foreseen it on the Designated Date, foreseen it on the Designated Date,
having inspected the Site and its having inspected the Site and its
surroundings and having satisfied itself, surroundings and having satisfied itself
insofar as practicable and taking into as to all matters concerning the Site.
account any information in connection
with the Site provided by the Employer,
as to all matters concerning the Site,
including its form and nature and its
geotechnical, hydrological and climatic
conditions.

Schedule Part 2

B Note: In open procedures, tenderers Note: Tenderers must name a


must name a guarantor if parent guarantor if parent company has been
company is identified for purposes of identified for purposes of pre-
satisfying tender requirements. In qualification.
restricted procedures, tenderers must
name a guarantor if parent company has
been identified for purposes of pre-
qualification.

Department of Finance Page 173


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

14.16 Minor Works Form


The Minor Works Contract for the provision of Building and Civil Engineering

Works designed by the Employer (the minor works contract) is in the same
form as the Public Works Contract for the Provision of Building Works and
Civil Engineering Works designed by the Employer (the Employer Designed or
traditional contracts).

The table below highlights the differences between the two forms of the above
mentioned contracts. Clause references in this comparison, unless stated
otherwise, relate to clauses in the traditional contracts.

Clause Ref Clause Minor Works Contract

1.6 Parent There is no requirement on the Contractor to provide the


Company parent company guarantee by the starting date.
Guarantee

2.7 Legal Opinion There is no clause requiring the provision of a legal opinion
relating to a Contractor who is not an individual or company
incorporated in Ireland.

3.3.1 Insurance of Unlike the traditional contracts, Part 1D of the Schedule in


Employer’s the minor works contract does not provide for a list of
Property additional Employer’s property which the Contractor must
insure.

3.9.3 Extensions and Part 1D of the Schedule does not provide scope for the
Additional Employer to specify extensions and additional requirements
Requirements in relation to insurances.
in the Schedule

3.9.9 Owner The minor works contract does not provide for the
Controlled insurance programme to be owner controlled.
Insurance
Programme

4.2.1(2) Supervisor The Contractor must appoint a supervisor to the site, but
unlike the traditional contracts the supervisor does not need
to be appointed on a full time basis

4.8 Value The minor works contract does not include a procedure for
Engineering value engineering.

4.9 Programme The content requirements for the programme are not as
detailed in the Minor Works Form. However, greater details
may be requested via the Works Requirements.

4.10 Progress The content requirements of progress reports in the minor


Reports works contract are not as detailed as those in the traditional
contracts.

Department of Finance Page 174


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Clause Ref Clause Minor Works Contract

5.4 Sub-contractors Under the minor works contract if the Contractor intends to
and Specialists sub-contract part of the works, other than in accordance
with the contract, the Contractor should obtain the consent
of the Employer’s Representative (ER).

7.9 Access The minor works contract does not contain the traffic
obligations, set out in the traditional contracts, relating to the
transport of large loads.

7.11 Working Times There is no clause in the minor works contract relating to
the site working times of the Contractor’s personnel.

8.5 Rejection of The minor works contract does not contain a mechanism
Defects allowing the ER to reject the works if a defect deprives the
Employer of substantially the whole benefit of the works.

9.4 Programme The programme contingency regime in the minor works


Contingency contract differs from the traditional contracts. In the minor
works contract there is only one threshold in relation to the
number of site working days’ delay.

If the total number of site working days’ delay is less that the
number of site working days stated in the Schedule there
shall be no extension to the date for substantial completion.

If the total number of site working days’ delay exceeds the


threshold stated in the Schedule only the days in excess of
the threshold may be added to the Date of Substantial
Completion.

As in the traditional contracts, this clause does not apply to


extensions of time resulting from delay events which are not
compensation events

9.7 Taking Over The minor works contract does not contain a provision
Part of the relating to the taking over of part of the works before
Works substantial completion by the Employer.

10.7.3 Delay Costs The traditional contracts contain a clause relating to the
scenario where, as a result of a compensation event the date
for substantial completion has been extended, so that there is
a period of 7 or more consecutive non-working days in the
time between the starting date and the date for

substantial completion, which would not have occurred were


it not for the occurrence of the compensation event. In such
instances the calculation of the adjustment to the contract
sum should account for the period of non-working days.
There is no equivalent clause in the minor works contract.

Department of Finance Page 175


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

15. Case Study 1A – Completing the Schedule Part


1 Building Works

15 Case Study 1A
Completing the Schedule Part 1
Building Works

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1A – Completing the Schedule Part 1

Building Works

Introduction

The contract is for the construction of a new civic office building for a local authority
Employer (LA County Council) on the site of its old fire station just outside of the
town centre. The LA CC has appointed consultants to design the building and the
form of contract to be used is the Public Works Contract for Building Works
Designed by the Employer.

The various parties and consultants are:

The Employer: LA County Council


The Courthouse
LA Town
County LA

The Architect: Santiago Balaclava & Associados SA


Paseo D Felipe VI
08028 Barcelona
España

The Structural Engineer: Telford, Brunel & Eiffel


35 The Heights
LA Town
County LA

The Mechanical & Electrical Consultant: Stephenson, Edison & Babbage


46 The Heights
LA Town
County LA

The Quantity Surveyor: Willis Sealy Partnership


50 The Heights
LA Town
County LA

The Architect was appointed to the project following an architectural competition.

The 11,000sq m building is intended to be a flagship piece of architecture for the


county and to contribute to urban regeneration within the county town. It is to be a
steel framed structure with reinforced concrete basement for car parking to maximise
site utilisation.

The cost plan indicates an estimated construction cost of €40,000,000, including


furniture and fittings and VAT but excluding professional fees. The existing stores
[which has a fibrous cement roof] was build in the 1950s and is to be demolished as
part of the construction contract and monies are allowed in the cost plan for this.

The budget for the project is consistent with this cost plan and is extremely tight and
the County Manager has stipulated that cost certainty is of the utmost importance
and the project must be delivered within the cost plan.

Department of Finance Page 177


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

LA CC is currently residing at a number of addresses and its annual rental bill is


€500,000 per annum. The existing Council Chamber and offices for elected
representatives is located in a building which is rented at a rent of €30,000 per
annum (this is included in the total rental figure mentioned above).

Specifications and drawings have been drawn up for the Project by the Architect and
the Design Team. A Bill of Quantities has been prepared by the consultant
Chartered Quantity Surveyor.

The programme for the Project indicates that construction will commence on 29
November 2007 and be completed by 30 October 2009. It is intended that the
Council Chamber and accommodation for the elected representatives be completed
by 31 August 2009 as the existing premises have to be vacated by this date,
otherwise damages of €5,000 per week are payable to the landlord.

It is envisaged that a number of Specialists be engaged by the Contractor on the


Works and these include:

1. Archaeologist;
2. Asbestos removal;
3. Piling;
4. Curtain walling and glazing;
5. Lifts;
6. Mechanical and electrical installations;
7. Artwork;
8. Workstations and furniture.

A fairly detailed archaeological report on the proposed site has been prepared and
indicates some possible buried archaeological remains may exist from mid 1700s
which are not considered to be significant, however the planning conditions stipulate
that they should be fully recorded prior to their destruction or removal.

The site investigation carried out to date indicates nothing worrying from a
construction viewpoint. Surveys indicate that there are no utilities on the site.

The LA CC in the last substantial construction project carried out for it encountered
lengthy delays, including some three months due to exceptionally inclement weather
conditions. The conditions involved very heavy rainfall, coupled with high winds
which prevented progress.

The Task

Delegates are requested to complete the Schedule Part 1 contained overleaf.

Department of Finance Page 178


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1A – Completing the Schedule

Blank Schedule

SCHEDULE

PART 1

(Completed by the Employer before Tender)

A Employer’s Representative and Communications

Sub-clause 4.3 and 4.14

Details for sending notices under clauses 12 and 13 to the Employer are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

Details for sending other notices to the Employer are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

fax ………………………………………..
email ………………………………………..

The Employer’s Representative is: ……………………………………………………………………..

Details for sending notices to the Employer’s Representative are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

Fax ………………………………………..
Email ………………………………………..

Department of Finance Page 179


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:

• Maximum adjustment to the Contract Sum for a single Change Order: €…………………………,
unless approved by the Employer

• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €…………………………, unless approved by the Employer

• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval

• The Employer will decide whether to accept or reject a value engineering proposal

• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment

• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment

• ….………………………………………………………………………………..

• ……………………………………………………………………………………

B Documents

The Works Requirements are:

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

The Pricing Document is:

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

If there is a Bill of Quantities, the method of measurement according to which it was prepared and
measurements are to be made is

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

Department of Finance Page 180


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

except when any statement or general or detailed description of the work in the Contract shows to the
contrary.

C Property in Contractor’s Documents

Sub-clause 6.4

Ownership in Contractor’s Documents and Works Items described in sub-clause 6.4.2


does/does not transfer to the Employer in accordance with sub-clause 6.4. (If neither deleted,
read as ‘does not’)

D Insurance

Clause 3

Insurance of the Works: minimum amount insured for professional fees ………% of
reinstatement cost (if none stated, 12.5%)

Minimum indemnity limits for public liability and employers’ liability Insurance:

• public liability insurance: €…………………………… for any one event, but this limit may
be on an annual aggregate basis for products liability, collapse, vibration, subsidence,
removal and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)

• employers’ liability insurance: €…………………………… for any one event. (If not
stated, €13,000,000)

Maximum excess for Insurance:

• insurance of Works and other Risk Items: €……………………………(If not stated,


€10,000)

• public liability: €…………………………. in respect of property damage only (If not


stated, €10,000). There shall be no excess for death, injury or illness.

• employers’ liability: no excess

Permitted exclusions from the Insurances:

• permitted exclusions from all Insurances

o war, invasion, act of foreign enemies, hostilities (whether war is declared or


not), civil war, rebellion, revolution, insurrection or military or usurped power or
martial law

o pressure waves caused by aircraft or other airborne objects travelling at sonic


or supersonic speeds

o contamination by radioactivity or radioactive, toxic, explosive or other


hazardous properties of any explosive nuclear assembly or its components, in
each case not caused by the Contractor or the Contractor’s Personnel

o terrorism (delete if terrorism insurance is required)

o asbestos (delete if asbestos insurance is required)

Department of Finance Page 181


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

• permitted exclusions from insurance of the Works and other Risk Items:

o use or occupation of the Works by the Employer except in connection with the
Works

o unless otherwise specified in the Works Requirements, cost of making good


defects in the Works but not damage caused by such defects to other sound
parts of the Works

o wear, tear, normal upkeep or normal repair or gradual deterioration

o inventory losses

o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance

o failure of information technology

o mechanical or electrical breakdown but not resulting damage

o cessation of the Works for more than three months

• permitted exclusions from public liability insurance

o persons under a contract of service or apprenticeship with the insured

o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works

o defective workmanship or materials but not resulting damage

o mechanically propelled vehicles within the meaning of the Road Traffic Acts

o loss or damage due to design

o gradual pollution or contamination

o territorial limits

o unless otherwise specified in the Works Requirements, aircraft and waterborne


craft

o fines, penalties, liquidated damages

• permitted exclusions from employer’s liability insurance

o offshore work

o liability compulsorily insurable under the Road Traffic Acts

• permitted exclusions from professional indemnity insurance

o persons under a contract of service or apprenticeship with the insured

Department of Finance Page 182


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

o ownership, use, occupation or leasing of mobile or immobile property

o effecting or maintenance of insurance of or in connection with the provision of


finance or advice on financial matters

o dishonest, malicious, criminal or deliberate illegal acts

o libel and slander

o insolvency

o fines, penalties, liquidated damages or any penal, punitive, exemplary, non-


compensatory or aggravated damages

o failure of information technology

o contractual liability that would not apply in the absence of the contract

Optional insurance provisions:

The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)

Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
…………………………………………………………………………………………………… and the
minimum sum for which this property is to be insured shall be €………………………

If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………

The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.

Required Extensions to Insurance:

Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).

E Performance Bond

Sub-clause 1.5

A performance bond is/is not required. (Delete one. If none deleted, bond is required.)

The amount of the performance bond shall be ……………..% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and ……………..% of the initial Contract

Department of Finance Page 183


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Sum for the period stated in the form of bond in the Works Requirements. (If not stated, 25%
up to Substantial Completion, and 12.5% for 15 months after that.)

F Collateral Warranties

Sub-clause 5.5

Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:

Category of Specialist Date for warranty Amount withheld

G Dates for Substantial Completion, Sections, Liquidated Damages, Retention

[Employer to complete names Date for Substantial


Reduction in
of sections] Completion (unless to be
retention on
completed by Contractor
Substantial
in part 2) Rate of Liquidated
Completion
Damages
of Section
(Last day of period
starting on the Contract
%
Date or date)

The Works € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

H Early Completion

Sub-clause 9.6

The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)

Department of Finance Page 184


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

I Defects Period

The initial Defects Period is ………………………………. from the date of Substantial


Completion of the Works

J Random Checks for Employment Records

Sub-clause 5.3.3A(2) shall be/shall not be part of the Contract.

Delete as applicable. If neither is deleted, read as “shall be”.

K Delay Events, Compensation Events, Programme Contingency, Delay Costs,


Adjustments
(Sub-clauses 9.3, 9.4, 10.1, 10.7)

Delay Events and Compensation Events are as follows:


(Employer to complete the shaded boxes “Yes” or “No”)

Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No

Department of Finance Page 185


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Delay Compensation
Event
Event Event
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. A difference between the Contract value of the Works according
to the quantities and descriptions in the Bill of Quantities [taking
into account the method of measurement identified below when
it applies] and the Contract value of the Works described in the
Works Requirements, because the Bill of Quantities, when
compared with the Works Requirements: Yes
• includes an incorrect quantity or
• includes an item that should not have been included or
• excludes an item that should have been included or
• gives an incorrect item description
and the difference for an item in, or that should have been in, the
Bill of Quantities is more than €500
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes
19. The Contractor encounters on the Site unforeseeable ground
conditions or man-made obstructions in the ground, other than
Utilities Yes
20. The Contractor encounters unforeseeable Utilities in the ground
on the site Yes
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes

In the above table:

Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.

A condition, circumstance or occurrence is unforeseeable if an experienced contractor tendering for


the Works could not have reasonably foreseen it on the Designated Date, having inspected the Site and
its surroundings and having satisfied itself, insofar as practicable, and taking into account any
information in connection with the Site provided by the Employer as to all matters concerning the Site,
including its form and nature and its geotechnical, hydrological and climatic conditions.

A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:

Department of Finance Page 186


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

• cumulative rainfall for the month


• number of days in the month with rainfall exceeding 20mm
• number of days with minimum air temperature less than 0° Celsius
• number of days with maximum mean 10 minute wind speed exceeding 20 metres per second
• …………………………………………………………………………………………………

If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.

In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in
…………………………………………………………………………………………………………………..........
and any rates in the Pricing Document.

In sub-clause 9.4:

• the first threshold is ………………… Site Working Days of delay caused by Compensation
Events

• the second threshold is ………………… Site Working Days of delay caused by Compensation
Events

In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):

the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))

The definition of craftspersons in part 2E includes the following additional categories:

_________________________________________________________________________
_________________________________________________________________________

For purposes of clause 10.7, the Contractor is to tender (in part 2E):

• a single rate for delay costs


• separate rates for delay costs for each of the following periods/portions of the Works:
o ______________________
o ______________________
o ______________________

If the above are blank, Contractor is to tender a single rate

L Payment Particulars

Clause 11

Period for interim payment is ………………. (If none stated, monthly.)

Minimum amount for interim payments, except release of retention, €………….…. (If none stated, there
is no minimum.)

When permitted by the Pricing Documents, up to _____% of the Contract value of unfixed Works Items
may be included in an interim payment. (If none stated, 90%).

The retention percentage is …………….%. (If none stated, 10%.)

Department of Finance Page 187


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

M Price Variation

Sub-clause 10.8

Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).

N Conciliation and Arbitration

Sub-clause 13.1.2

Failing agreement, the conciliator will be appointed by ………………………………….

Sub-clause 13.2

The arbitration rules are the Public Works Arbitration Rules, 2007.

The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………

Department of Finance Page 188


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1A – Completing the Schedule

Worked Example

SCHEDULE

PART 1

(Completed by the Employer before Tender)

A Employer’s Representative and Communications

Sub-clause 4.3 and 4.14

Details for sending notices under clauses 12 and 13 to the Employer are:

For the attention of: Director of Services

Address

LA County Council
Four Courts
LA Town
County LA

Details for sending other notices to the Employer are:

For the attention of: Mr A Jones

Address

LA County Council
Four Courts
LA Town
County LA

fax ………………………………………..

email ………………………………………..

The Employer’s Representative is: Santiago Balaclava & Associados SA

Details for sending notices to the Employer’s Representative are:

For the attention of: Peter Wood-Steele

Address

50 The Heights
LA Town
County LA

Fax 021 8559000

Email [email protected]

Department of Finance Page 189


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:

• Maximum adjustment to the Contract Sum for a single Change Order: €5,000, unless approved
by the Employer

• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €30,000, unless approved by the Employer

• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval

• The Employer will decide whether to accept or reject a value engineering proposal

• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment

• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment

• ….………………………………………………………………………………..

• ……………………………………………………………………………………

B Documents

The Works Requirements are:

12345-WR-001

The Pricing Document is:

12345-BQ-001

If there is a Bill of Quantities, the method of measurement according to which it was prepared
and measurements are to be made is ARM3, 2003 except when any statement or general or
detailed description of the work in the Contract shows to the contrary.

C Property in Contractor’s Documents

Sub-clause 6.4

Ownership in Contractor’s Documents and Works Items described in sub-clause 6.4.2


does/does not transfer to the Employer in accordance with sub-clause 6.4. (If neither deleted,
read as ‘does not’)

D Insurance

Clause 3

Insurance of the Works: minimum amount insured for professional fees 12.5% of reinstatement
cost (if none stated, 12.5%)

Minimum indemnity limits for public liability and employers’ liability Insurance:

• public liability insurance: €13,000,000 for any one event, but this limit may be on an
annual aggregate basis for products liability, collapse, vibration, subsidence, removal
and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)

Department of Finance Page 190


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

• employers’ liability insurance: €13,000,000 for any one event. (If not stated,
€13,000,000)

Maximum excess for Insurance:

• insurance of Works and other Risk Items: €10,000,000 (If not stated, €10,000)

• public liability: €10,000,000 in respect of property damage only (If not stated, €10,000).
There shall be no excess for death, injury or illness.

• employers’ liability: no excess

Permitted exclusions from the Insurances:

• permitted exclusions from all Insurances

o war, invasion, act of foreign enemies, hostilities (whether war is declared or


not), civil war, rebellion, revolution, insurrection or military or usurped power or
martial law

o pressure waves caused by aircraft or other airborne objects travelling at sonic


or supersonic speeds

o contamination by radioactivity or radioactive, toxic, explosive or other


hazardous properties of any explosive nuclear assembly or its components, in
each case not caused by the Contractor or the Contractor’s Personnel

o terrorism (delete if terrorism insurance is required)

o asbestos (delete if asbestos insurance is required)

• permitted exclusions from insurance of the Works and other Risk Items:

o use or occupation of the Works by the Employer except in connection with the
Works

o unless otherwise specified in the Works Requirements, cost of making good


defects in the Works but not damage caused by such defects to other sound
parts of the Works

o wear, tear, normal upkeep or normal repair or gradual deterioration

o inventory losses

o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance

o failure of information technology

o mechanical or electrical breakdown but not resulting damage

o cessation of the Works for more than three months

• permitted exclusions from public liability insurance

o persons under a contract of service or apprenticeship with the insured

Department of Finance Page 191


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works

o defective workmanship or materials but not resulting damage

o mechanically propelled vehicles within the meaning of the Road Traffic Acts

o loss or damage due to design

o gradual pollution or contamination

o territorial limits

o unless otherwise specified in the Works Requirements, aircraft and waterborne


craft

o fines, penalties, liquidated damages

• permitted exclusions from employer’s liability insurance

o offshore work

o liability compulsorily insurable under the Road Traffic Acts

• permitted exclusions from professional indemnity insurance

o persons under a contract of service or apprenticeship with the insured

o ownership, use, occupation or leasing of mobile or immobile property

o effecting or maintenance of insurance of or in connection with the provision of


finance or advice on financial matters

o dishonest, malicious, criminal or deliberate illegal acts

o libel and slander

o insolvency

o fines, penalties, liquidated damages or any penal, punitive, exemplary, non-


compensatory or aggravated damages

o failure of information technology

o contractual liability that would not apply in the absence of the contract

Department of Finance Page 192


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Optional insurance provisions:

The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)

Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:

Artworks and the minimum sum for which this property is to be insured shall be €100,000

If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………

The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.

Required Extensions to Insurance:

Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).

E Performance Bond

Sub-clause 1.5

A performance bond is/is not required. (Delete one. If none deleted, bond is required.)

The amount of the performance bond shall be 12.5% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and 6.25% of the initial Contract Sum for
the period stated in the form of bond in the Works Requirements. (If not stated, 25% up to
Substantial Completion, and 12.5% for 15 months after.)

F Collateral Warranties

Sub-clause 5.5

Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:

Category of Specialist Date for warranty Amount withheld


Archaeologist 1 December 2007 €1,000
Asbestos removal 2 February 2008 €10,000
Piling 2 March 2008 €50,000
Curtain walling and glazing 6 January 2009 €10,000
Lifts 1 April 2009 €3,000
Mechanical and electrical installations 1 November 2008 €30,000
Artwork July 2009 €1,000
Workstations and furniture 1 July 2009 €10,000

Department of Finance Page 193


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

G Dates for Substantial Completion, Sections, Liquidated Damages, Retention

[Employer to complete names Date for Substantial


Reduction in
of sections] Completion (unless to be
retention on
completed by Contractor
Substantial
in part 2) Rate of Liquidated
Completion
Damages
of Section
(Last day of period
starting on the Contract
%
Date or date)

The Works 1 November 2009 €2,800 per day

Section:
Council Chamber and
30 June 2009 €850 per day 50%
accommodation for elected
members

H Early Completion

Sub-clause 9.6

The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)

I Defects Period

The initial Defects Period is 12 months from the date of Substantial Completion of the Works

J Random Checks for Employment Records

Sub-clause 5.3.3A(2) shall be/shall not be part of the Contract.

Delete as applicable. If neither is deleted, read as “shall be”.

K Delay Events, Compensation Events, Programme Contingency, Delay Costs,


Adjustments
(Sub-clauses 9.3, 9.4, 10.1, 10.7)

Delay Events and Compensation Events are as follows:


(Employer to complete the shaded boxes “Yes” or “No”)

Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes

Department of Finance Page 194


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Delay Compensation
Event
Event Event
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes No
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. A difference between the Contract value of the Works according
to the quantities and descriptions in the Bill of Quantities [taking
into account the method of measurement identified below when
it applies] and the Contract value of the Works described in the
Works Requirements, because the Bill of Quantities, when
compared with the Works Requirements: No No
• includes an incorrect quantity or
• includes an item that should not have been included or
• excludes an item that should have been included or
• gives an incorrect item description
and the difference for an item in, or that should have been in, the
Bill of Quantities is more than €500
18. An item of value or archaeological interest or human remains is
found on the Site, and it was unforeseeable Yes Yes

Department of Finance Page 195


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Delay Compensation
Event
Event Event
19. The Contractor encounters on the Site unforeseeable ground
conditions or man-made obstructions in the ground, other than
Utilities Yes No
20. The Contractor encounters unforeseeable Utilities in the ground
on the site Yes No
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes No

In the above table:

Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.

A condition, circumstance or occurrence is unforeseeable if an experienced contractor tendering for


the Works could not have reasonably foreseen it on the Designated Date, having inspected the Site and
its surroundings and having satisfied itself, insofar as practicable, and taking into account any
information in connection with the Site provided by the Employer as to all matters concerning the Site,
including its form and nature and its geotechnical, hydrological and climatic conditions.

A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:

• cumulative rainfall for the month


• number of days in the month with rainfall exceeding 20mm
• number of days with minimum air temperature less than 0° Celsius
• number of days with maximum mean 10 minute wind speed exceeding 20 metres per second
• …………………………………………………………………………………………………

If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.

In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in UK Civil
Engineering Contractors Association Schedules of Dayworks carried out incidental to contract work
August 2003 reprint. (Note: Only Schedule 4 will apply). (Rates will be considered to be in euro) and
any rates in the Pricing Document.

In sub-clause 9.4:

• the first threshold is 21 Site Working Days of delay caused by Compensation Events

• the second threshold is 20 Site Working Days of delay caused by Compensation Events

In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):

the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
YES
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))

Department of Finance Page 196


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

The definition of craftspersons in part 2E includes the following additional categories:

_________________________________________________________________________
_________________________________________________________________________

For purposes of clause 10.7, the Contractor is to tender (in part 2E):

• a single rate for delay costs


• separate rates for delay costs for each of the following periods/portions of the Works:
o ______________________
o ______________________
o ______________________

If the above are blank, Contractor is to tender a single rate

L Payment Particulars

Clause 11

Period for interim payment is monthly (If none stated, monthly.)

Minimum amount for interim payments, except release of retention, €50,000. (If none stated,
there is no minimum.)

When permitted by the Pricing Documents, up to 75% of the Contract value of unfixed Works
Items may be included in an interim payment. (If none stated, 90%).

The retention percentage is 3%. (If none stated, 10%.)

M Price Variation

Sub-clause 10.8

Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).

N Conciliation and Arbitration

Sub-clause 13.1.2

Failing agreement, the conciliator will be appointed by the President of the Royal Institute of the
Architects of Ireland.

Sub-clause 13.2

The arbitration rules are the Public Works Arbitration Rules, 2007.

The person or body to appoint the arbitrator (if not agreed by the parties) is President of the
Royal Institute of the Architects of Ireland.

Department of Finance Page 197


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

16. Case Study 1B – Completing the Schedule Part 1


Civil Works

16 Case Study 1B
Completing the Schedule Part 1
Civil Works

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1B – Completing the Schedule Part 1

Civil Engineering Works

Case Study on a Design-Build Project in the Roads Sector

This Project concerns the construction by a Design-Build, or Contractor-Design,


Contract of a single carriageway road of 17km in extent, with a number of junctions
and one bridge at a river crossing. The estimated cost of the Project is €38.5m.
Specimen Designs for the Bridge and for the Carriageway have been prepared as
part of preliminary work and these are made available to tenderers on a non-
contractual basis as an appendix to the Works Requirements.

It is necessary to complete Schedule 1 for the Project.

Section A includes the expected contact and correspondence details for the parties
and is similar to other forms.

The Employer has separately conducted a procurement competition for appointment


of Materials Quality Assurance services. Irish Pavement Materials Quality
Assurance Ltd are the successful service providers, a contract has been drawn up
and the Employer intends to novate that contract to the successful DB Contractor.
This information is also entered in Section A and the contract is appended to the
Works Requirements in Section B.

The limit on authority of the ER to order any one variation has been set at €50,000
and the limit on the number of instructions changing the works requirement is set at
100. The Employer's approval is required to exceed either limit.

There has been no Bill of Quantities produced, but the Employer requires in Section
A that any Bill submitted by tenderers in support of their tender price should be
measured in accordance with the Method of Measurement for Roadworks of the
NRA.

In Section C, the Employer opts not to seek any copyright in the contract
documents.

In Section D, insurance limits have been selected at €13,000,000 for both EL and
PL insurance. PI insurance is selected at a level of €6,200,000 any one event and
an excess of €25,000 is deemed tolerable by the Employer in each case. PI
insurance will be kept in place for six (6) years from the date of Substantial
Completion and it needs to be in place from the earliest date that design work takes
place on the Project. These limits should be set with advice from Insurance
Specialists.

The Employer in this case has opted to have the Contractor extend insurance for the
Section which is to be completed early, until the Substantial Completion of the whole
of the Works.

In Section E, a performance bond is selected at 15% of the Contract Sum, reducing


to 10% at the Date of Substantial Completion and this bond will be in place until a
date 12 months after the date of Substantial Completion.

Collateral Warranties are to be sought from a number of Specialists in Section F,


including the Culvert Design, the Bridge Design and the Landscaping Design, with
the dates for the warranties and the withheld amounts in the event of late delivery set
out.

Department of Finance Page 199


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In Section G, the Employer has required that the section of carriageway from
Ch .0m to Ch. 6330m, including the junctions at both ends, must be available to take
traffic at an earlier Substantial Completion date for that section and liquidated
damages have separately been calculated for this element and for the whole of the
Works as shown.

In Section H, the Employer has opted not to take on himself an obligation to issue a
Certificate of Substantial Completion if either the Works, or the nominated Section,
are completed before the scheduled dates.

The Defects Period is nominated at 12 months from the Date of Substantial


Completion in Section I.

The Section J Delay and Compensation events listing is different for the Contractor-
designed form of contract, as one might expect. The Employer has opted to pay
delay costs associated with archaeological finds, in the light of preparatory
investigative work, however he requires the Contractor to carry the risk associated
with Utilities relocation delay.

The First Threshold, for the purposes of sub-clause 9.4, has been set at 40 Site
Working Days and the Second Threshold has also been selected as 40 Site Working
Days. The Employer has opted to pay the tendered amount in the Schedule Section
2E as the preferred way of handling costs of delay due to Compensation Events.

As regards the weather event data entries in Schedule J, the Guidance Notes
discuss a 10 Year Return Period as the appropriate level of risk to transfer to the
Contractor in this respect. This has a precise hydrological meaning, as the event
which, in a long record, is likely to be exceeded once in 10 years. It is not equivalent
to the worst event which occurred within the past decade, for example. In a project
lasting perhaps 24-36 months at construction stage, there is a significant probability
of the 10 year event occurring, be that rainfall or wind or temperature. Furthermore,
it is not impossible (although the probability is low) that a 10 Year Return Period
event could occur twice within a construction period. The Contractor carries that
risk.

Note that the Schedule requires data for calendar months to be inserted. The
Contractor also carries the risk associated with exceptional weather events (of 10
Year Return Period or greater) which straddle two calendar months, without actually
producing 10 Year Return Period totals in either calendar month.

Met Éireann should be consulted on the statistics to be entered in the Schedule by


the Employer, drawn from the Climatological Station most representative of the
conditions at the site of the Works.

As regards sub-clause 10.6.3, the rates to be used to assess the cost of plant are
those used in the UK Civil Engineering Contractors Association "Schedule of
Dayworks carried out incidental to Contract Works" where the Sterling rates are
deemed to be converted to euro by multiplying by a factor of 1.27.

In Section K, interim payments are intended to be monthly on a project of this size


and the minimum amount for an interim payment has been set at €150,000.
Retention has been set at 10%.

The President of Engineers Ireland has been nominated in Schedule Section L as


the person who will appoint a Conciliator, should one be required.

Department of Finance Page 200


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1B – Completing the Schedule Part 1

Blank Schedule

SCHEDULE

PART 1

(Completed by the Employer before Tender)

A Employer’s Representative and Communications


Sub-clause 4.3 and 4.14

Details for sending notices under clauses 12 and 13 to the Employer are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

Details for sending other notices to the Employer are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

fax ………………………………………..
email ………………………………………..

The Employer’s Representative is: ……………………………………………………………………..

Details for sending notices to the Employer’s Representative are:

For the attention of: ………………………………………..

Address

………………………………………..

………………………………………..

………………………………………..

Fax ………………………………………..
Email ………………………………………..

Department of Finance Page 201


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:

• Maximum adjustment to the Contract Sum for a single Change Order: €…………………………,
unless approved by the Employer

• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period €…………………………, unless approved by the Employer

• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval

• The Employer will decide whether to accept or reject a value engineering proposal

• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment

• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment

• ….………………………………………………………………………………..

• ……………………………………………………………………………………

B Documents

The Works Requirements are:

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

The Novated Design Documents are:

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

The Pricing Document is:

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

Department of Finance Page 202


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

If there is a Bill of Quantities, the method of measurement according to which it was prepared and
measurements are to be made is

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

………………………………………..………………………………………..…………………………..

except when any statement or general or detailed description of the work in the Contract shows to the
contrary.

C Property in Contractor’s Documents

Sub-clause 6.4

Ownership in Contractor’s Documents and Works Items described in sub-clause 6.4.2


does/does not transfer to the Employer in accordance with sub-clause 6.4. (If neither deleted,
read as ‘does not’)

D Insurance

Clause 3

Insurance of the Works: minimum amount insured for professional fees ………% of
reinstatement cost (if none stated, 12.5%)

Minimum indemnity limits for public liability and employers’ liability Insurance:

• public liability insurance: €…………………………… for any one event, but this limit may
be on an annual aggregate basis for products liability, collapse, vibration, subsidence,
removal and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)

• employers’ liability insurance: €…………………………… for any one event. (If not
stated, €13,000,000)

Maximum excess for Insurance:

• insurance of Works and other Risk Items: €……………………………(If not stated,


€10,000)

• public liability: €…………………………. in respect of property damage only (If not


stated, €10,000). There shall be no excess for death, injury or illness.

• employers’ liability: no excess

Permitted exclusions from the Insurances:

• permitted exclusions from all Insurances

o war, invasion, act of foreign enemies, hostilities (whether war is declared or


not), civil war, rebellion, revolution, insurrection or military or usurped power or
martial law

o pressure waves caused by aircraft or other airborne objects travelling at sonic


or supersonic speeds

Department of Finance Page 203


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

o contamination by radioactivity or radioactive, toxic, explosive or other


hazardous properties of any explosive nuclear assembly or its components, in
each case not caused by the Contractor or the Contractor’s Personnel

o terrorism (delete if terrorism insurance is required)

o asbestos (delete if asbestos insurance is required)

• permitted exclusions from insurance of the Works and other Risk Items:

o use or occupation of the Works by the Employer except in connection with the
Works

o unless otherwise specified in the Works Requirements, cost of making good


defects in the Works but not damage caused by such defects to other sound
parts of the Works

o wear, tear, normal upkeep or normal repair or gradual deterioration

o inventory losses

o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance

o failure of information technology

o mechanical or electrical breakdown but not resulting damage

o cessation of the Works for more than three months

• permitted exclusions from public liability insurance

o persons under a contract of service or apprenticeship with the insured

o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works

o defective workmanship or materials but not resulting damage

o mechanically propelled vehicles within the meaning of the Road Traffic Acts

o loss or damage due to design

o gradual pollution or contamination

o territorial limits

o unless otherwise specified in the Works Requirements, aircraft and waterborne


craft

o fines, penalties, liquidated damages

Department of Finance Page 204


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

• permitted exclusions from employer’s liability insurance

o offshore work

o liability compulsorily insurable under the Road Traffic Acts

• permitted exclusions from professional indemnity insurance

o persons under a contract of service or apprenticeship with the insured

o ownership, use, occupation or leasing of mobile or immobile property

o effecting or maintenance of insurance of or in connection with the provision of


finance or advice on financial matters

o dishonest, malicious, criminal or deliberate illegal acts

o libel and slander

o insolvency

o fines, penalties, liquidated damages or any penal, punitive, exemplary, non-


compensatory or aggravated damages

o failure of information technology

o contractual liability that would not apply in the absence of the contract

Optional insurance provisions:

The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)

Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:
…………………………………………………………………………………………………… and the
minimum sum for which this property is to be insured shall be €………………………

If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………

The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.

Required Extensions to Insurance:

Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for ……… years after Substantial Completion of the Works is
certified by the Employer's Representative. If required, the minimum indemnity limit for
professional indemnity insurance shall be €…………………………… for each and every claim
or series of claims arising from the same originating cause/annual aggregate limit (delete one).
The maximum excess shall be €…………………………… (if none stated, €50,000).

Department of Finance Page 205


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

E Performance Bond

Sub-clause 1.5

A performance bond is/is not required. (Delete one. If none deleted, bond is required.)

The amount of the performance bond shall be ……………..% of the initial Contract Sum up to
certification of Substantial Completion of the Works, and ……………..% of the initial Contract
Sum for the period stated in the form of bond in the Works Requirements. (If not stated, 25%
up to Substantial Completion, and 12.5% for 15 months after that.)

F Collateral Warranties

Sub-clause 5.5

Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:

Category of Specialist Date for warranty Amount withheld

G Dates for Substantial Completion, Sections, Liquidated Damages, Retention

[Employer to complete names Date for Substantial


Reduction in
of sections] Completion (unless to be
retention on
completed by Contractor
Substantial
in part 2) Rate of Liquidated
Completion
Damages
of Section
(Last day of period
starting on the Contract
%
Date or date)

The Works € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

Section: € ……… per ………

Department of Finance Page 206


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

H Early Completion
Sub-clause 9.6

The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)

I Defects Period

The initial Defects Period is ………………………………. from the date of Substantial


Completion of the Works

J Random Checks for Employment Records

Sub-clause 5.3.3A(2) shall be /shall not be part of the Contract.

Delete as applicable. If neither is deleted, read as “shall be”.

K Delay Events, Compensation Events, Programme Contingency, Delay Costs,


Adjustments
(Sub-clauses 9.3, 9.4, 10.1, 10.7)

Delay Events and Compensation Events are as follows:


(Employer to complete the shaded boxes “Yes” or “No”)

Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. Not used
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. Not used
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes

Department of Finance Page 207


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Delay Compensation
Event
Event Event
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. Not used
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes
19. Not used
20. Not used
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes

In the above table:

Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.

A condition, circumstance or occurrence is unforeseeable if an experienced contractor tendering for


the Works could not have reasonably foreseen it on the Designated Date, having inspected the Site and
its surroundings and having satisfied itself, insofar as practicable, and taking into account any
information in connection with the Site provided by the Employer as to all matters concerning the Site,
including its form and nature and its geotechnical, hydrological and climatic conditions.

A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:

• cumulative rainfall for the month


• number of days in the month with rainfall exceeding 20mm
• number of days with minimum air temperature less than 0° Celsius
• number of days with maximum mean 10 minute wind speed exceeding 20 metres per second
• …………………………………………………………………………………………………

If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.
In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in
………………………………………………………………………………………………………………………...
and any rates in the Pricing Document.

Department of Finance Page 208


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In sub-clause 9.4:

• the first threshold is ………………… Site Working Days of delay caused by Compensation
Events

• the second threshold is ………………… Site Working Days of delay caused by Compensation
Events

In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):

the daily rate tendered by the Contractor in the Schedule, Part 2E (clause
10.7.1(1))
the expenses unavoidably incurred as a result of the delay (clause 10.7.1(2))

The definition of craftspersons in part 2E includes the following additional categories:

_________________________________________________________________________
_________________________________________________________________________

For purposes of clause 10.7, the Contractor is to tender (in part 2E):

• a single rate for delay costs


• separate rates for delay costs for each of the following periods/portions of the Works:
o ______________________
o ______________________
o ______________________

If the above are blank, Contractor is to tender a single daily rate

L Payment Particulars
Clause 11

Period for interim payment is ………………. (If none stated, monthly.)

Minimum amount for interim payments, except release of retention, €………….…. (If none stated, there
is no minimum.)

When permitted by the Pricing Documents, up to _____% of the Contract value of unfixed Works Items
may be included in an interim payment. (If none stated, 90%).

The retention percentage is …………….%. (If none stated, 10%.)

M Price Variation
Sub-clause 10.8

Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV1 shall apply).

N Conciliation and Arbitration

Sub-clause 13.1.2
Failing agreement, the conciliator will be appointed by ………………………………….

Sub-clause 13.2
The arbitration rules are the Public Works Arbitration Rules, 2007.

The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………

Department of Finance Page 209


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 1B – Completing the Schedule Part 1

Worked Example

SCHEDULE

PART 1

(Completed by the Employer before Tender)

A Communications and Employer’s Representative

Sub-clause 4.3 and 4.14

Details for sending notices under clauses 12 and 13 to the Employer are:

For the attention of: Mr A Kelly, Contracting Authority Project Manager

Address

County Buildings
Casement Street

Details for sending other notices to the Employer are:

For the attention of: The County Secretary

Address

County Buildings
Casement Street
County of Oldtown

Fax 00 353 601 93454

Email [email protected]

The Employer’s Representative is: Justin Wright Ltd Consulting Engineers

Details for sending notices to the Employer’s Representative are:

For the attention of: Mr John Wright

Address

100 Block 9 Uptown Business Park


Oldtown

Fax 00 353 601 84344

Email [email protected]

Department of Finance Page 210


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Limitations on the Employer’s Representative’s authority to perform his functions and powers under the
Contract:

• Maximum adjustment to the Contract Sum for a single Change Order: €5,000, unless approved
by the Employer

• Maximum cumulative value of adjustments to the Contract Sum for Change Orders in any three
month period: €75,000.

• The Employer’s Representative shall not make a Change Order causing or contributing to a
reduction in safety, scope, quality or usefulness of the Works without the Employer’s approval

• The Employer will decide whether to accept or reject a value engineering proposal

• The Employer’s Representative is to consult with the Employer in relation to any adjustment to
the Contract Sum before determining the adjustment

• Where the Employer has appointed a quantity surveyor, the Employer’s Representative is to
consult with the quantity surveyor in relation to any adjustments to the Contract Sum before
determining the adjustment

• ….………………………………………………………………………………..

• ……………………………………………………………………………………

B Documents

The Works Requirements are:

(1) The Employer's Requirements


(2) The published EIS
(3) Contract Drawings (Land Take, Centrelines, Fence Lines)
(4) The National Contract Requirements of Irish Pavement Materials Quality Assurance Ltd

The Pricing Document is:

12345-PD-001

If there is a Bill of Quantities, the method of measurement according to which it was prepared
and measurements are to be made is

No Bill of Quantities provided

except when any statement or general or detailed description of the work in the Contract shows
to the contrary.

Any BoQ submitted should be measured in accordance with the Method of Measurement for
Roadworks by the NRA.

C Property in Contractor’s Documents

Sub-clause 6.4

Ownership in Contractor’s Documents and Works Items described in sub-clause 6.4.2


does/does not transfer to the Employer in accordance with sub-clause 6.4. (If neither deleted,
read as ‘does not’)

Department of Finance Page 211


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

D Insurance

Clause 3

Insurance of the Works: minimum amount insured for professional fees 7% of reinstatement
cost (if none stated, 12.5%)

Minimum indemnity limits for public liability and employers’ liability Insurance:

• public liability insurance: €13,000,000 for any one event, but this limit may be on an
annual aggregate basis for products liability, collapse, vibration, subsidence, removal
and weakening of supports and sudden and accidental pollution. (If not stated,
€6,500,000.)

• employers’ liability insurance: €13,000,000 for any one event. (If not stated,
€13,000,000)

Maximum excess for Insurance:

• insurance of Works and other Risk Items: €25,000 (If not stated, €10,000)

• public liability: €25,000 in respect of property damage only (If not stated, €10,000).
There shall be no excess for death, injury or illness.

• employers’ liability: no excess

Permitted exclusions from the Insurances:

• permitted exclusions from all Insurances

o war, invasion, act of foreign enemies, hostilities (whether war is declared or


not), civil war, rebellion, revolution, insurrection or military or usurped power or
martial law

o pressure waves caused by aircraft or other airborne objects travelling at sonic


or supersonic speeds

o contamination by radioactivity or radioactive, toxic, explosive or other


hazardous properties of any explosive nuclear assembly or its components, in
each case not caused by the Contractor or the Contractor’s Personnel

o terrorism (delete if terrorism insurance is required)

o asbestos (delete if asbestos insurance is required)

• permitted exclusions from insurance of the Works and other Risk Items:

o use or occupation of the Works by the Employer except in connection with the
Works

o unless otherwise specified in the Works Requirements, cost of making good


defects in the Works but not damage caused by such defects to other sound
parts of the Works

o wear, tear, normal upkeep or normal repair or gradual deterioration

o inventory losses

Department of Finance Page 212


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

o loss of use or any consequential loss of any nature including penalties for
delay, non-completion or non-compliance

o failure of information technology

o mechanical or electrical breakdown but not resulting damage

o cessation of the Works for more than three months

• permitted exclusions from public liability insurance

o persons under a contract of service or apprenticeship with the insured

o property of the insured or in the insured’s custody or control other than existing
premises and their contents temporarily occupied for the purposes of the
Works

o defective workmanship or materials but not resulting damage

o mechanically propelled vehicles within the meaning of the Road Traffic Acts

o loss or damage due to design

o gradual pollution or contamination

o territorial limits

o unless otherwise specified in the Works Requirements, aircraft and waterborne


craft

o fines, penalties, liquidated damages

• permitted exclusions from employer’s liability insurance

o offshore work

o liability compulsorily insurable under the Road Traffic Acts

• permitted exclusions from professional indemnity insurance

o persons under a contract of service or apprenticeship with the insured

o ownership, use, occupation or leasing of mobile or immobile property

o effecting or maintenance of insurance of or in connection with the provision of


finance or advice on financial matters

o dishonest, malicious, criminal or deliberate illegal acts

o libel and slander

o insolvency

Department of Finance Page 213


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

o fines, penalties, liquidated damages or any penal, punitive, exemplary, non-


compensatory or aggravated damages

o failure of information technology

o contractual liability that would not apply in the absence of the contract

Optional insurance provisions:

The Employer shall/shall not have the risk of loss of and damage to its existing facilities and
parts of the Works it uses or occupies, in accordance with sub-clause 3.8. (Delete as
applicable. If none deleted, the Employer shall not have this risk and sub-clause 3.8 shall not
apply.)

Insurance of the Works and other Risk Items shall include the following property of the
Employer, other than the Works and Works Items:

Artworks and the minimum sum for which this property is to be insured shall be €100,000

If Insurance of the Works and other Risk Items is to include terrorism cover, the minimum sum
insured shall be €……………………………

The Contractor shall/is not required to (delete one) extend the insurance of the Works and
other Risk Items for a Section that has reached Substantial Completion until the Employer’s
Representative issues the certificate of Substantial Completion for the whole Works.

Required Extensions to Insurance:

Professional indemnity insurance is/is not (delete one) required. (If neither deleted,
professional indemnity insurance is not required.) If required, the professional indemnity
insurance is to be kept in place for 6 years after Substantial Completion of the Works is certified
by the Employer's Representative. If required, the minimum indemnity limit for professional
indemnity insurance shall be €6,200,000 for each and every claim or series of claims arising
from the same originating cause/annual aggregate limit (delete one). The maximum excess
shall be €25,000 (if none stated, €50,000).

E Performance Bond

Sub-clause 1.5

A performance bond is/is not required. (Delete one. If none deleted, bond is required.)

The amount of the performance bond shall be 15% of the initial Contract Sum up to certification
of Substantial Completion of the Works, and 10% of the initial Contract Sum for the period
stated in the form of bond in the Works Requirements. (If not stated, 25% up to Substantial
Completion, and 12.5% for 15 months after.)

F Collateral Warranties

Sub-clause 5.5

Collateral warranties are required from the following categories of Specialists, by the following
dates; and the amount withheld from payments under sub-clause 11.4.1 are as follows:

Department of Finance Page 214


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Category of Specialist Date for warranty Amount withheld


Landscaping Design 14 February 2010 €50,000
Culvert Design 3 June 2008 €100,000
Bridge Design 3 June 2008 €150,000

G Dates for Substantial Completion, Sections, Liquidated Damages, Retention

[Employer to complete names Date for Substantial


of sections] Completion (unless to be
Reduction in
completed by Contractor
retention on
in part 2) Rate of Liquidated
Substantial
Damages
Completion
(Last day of period
of Section
starting on the Contract
Date or date)

The Works 16 August 2010 €50,000 per week From 10% of


Contract
Value to 5%

Section: 8 December 2008 €50,000 per week €100 per day

H Early Completion

Sub-clause 9.6

The Employer’s Representative is/is not required to issue the certificate of Substantial
Completion if the Works or a Section reaches Substantial Completion before its Date for
Completion. (If neither deleted, read as ‘is required’)

I Defects Period

The initial Defects Period is 12 months from the date of Substantial Completion of the Works

J Random Checks for Employment Records

Sub-clause 5.3.3A(2) shall be/shall not be part of the Contract.

Delete as applicable. If neither is deleted, read as “shall be”.

Department of Finance Page 215


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

K Delay Events, Compensation Events, Programme Contingency, Delay Costs,


Adjustments
(Sub-clauses 9.3, 9.4, 10.1, 10.7)

Delay Events and Compensation Events are as follows:


(Employer to complete the shaded boxes “Yes” or “No”)

Delay Compensation
Event
Event Event
1. The Employer’s Representative gives the Contractor a Change
Order Yes Yes
2. The Employer’s Representative directs the Contractor to search
for Defects or their cause and no Defect is found, and the search
was not required because of a failure of the Contractor to comply
with the Contract Yes Yes
3. The Employer’s Representative directs the Contractor to
suspend work under sub-clause 9.2 Yes Yes
4. The Contractor suspends work in accordance with sub-clause
12.3 Yes Yes
5. There is a factual error in information about the Site or setting
out information in the Works Requirements. [This does not
include an error of interpretation] Yes Yes
6. The Employer takes over part of the Works before Substantial
Completion of the Works and any relevant Section Yes Yes
7. The Employer's Representative does not give the Contractor an
instruction required under sub-clause 4.5.4 within the time
required under sub-clause 4.11.2 when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
8. The Employer does not allow the Contractor access to and use
of a part of the Site in accordance with sub-clause 7.1 Yes Yes
9. The Employer does not give the Contractor a Works Item or
other thing as required by the Contract when the Contractor has
asked for the instruction in accordance with sub-clause 4.11.1 Yes Yes
10. Employer’s Personnel interfere with the execution of the Works
on the Site, and the interference is unforeseeable and not in
accordance with the Contract Yes Yes
11. The Employer instructs the Contractor under sub-clause 3.2.3 to
rectify loss of or damage to Risk Items for which the Contractor
is not responsible Yes Yes
12. Loss of or damage to the Works that is at the Contractor’s risk in
accordance with clause 3.2 Yes No
13. A weather event as described below Yes No
14. A strike or lockout affecting the construction industry generally or
a significant part of it, and not confined to employees of the
Contractor or any Contractor’s Personnel Yes No
15. Delay to the Works caused by the order or other act of a court or
other public authority exercising authority under Law, that did not
arise as a result of or in relation to an act, omission or breach of
Legal Requirements of the Contractor or the Contractor’s
Personnel or a breach of the Contract by the Contractor Yes Yes

Department of Finance Page 216


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Delay Compensation
Event
Event Event
16. A breach by the Employer of the Contract delaying the Works
that is not listed elsewhere in this table. Yes Yes
17. Not used
18. An item of value or archaeological or geological interest or
human remains is found on the Site, and it was unforeseeable Yes Yes
19. Not used
20. Not used
21. Owners of Utilities on the Site do not relocate or disconnect
Utilities as stated in with the Works Requirements, when the
Contractor has complied with their procedures and the
procedures in the Contract, and the failure is unforeseeable Yes No

In the above table:

Utilities means conducting media or apparatus for water, sewage, electricity, gas, oil,
telecommunications, data, steam, air, or other services, and associated apparatus or structures.

A condition, circumstance or occurrence is unforeseeable if an experienced contractor tendering for


the Works could not have reasonably foreseen it on the Designated Date, having inspected the Site and
its surroundings and having satisfied itself, insofar as practicable, and taking into account any
information in connection with the Site provided by the Employer as to all matters concerning the Site,
including its form and nature and its geotechnical, hydrological and climatic conditions.

A weather event is when for any month between the Contract Date and the Date for Substantial
Completion of the Works, the value for any of the weather listed below, as measured at ………………
weather station, is higher than the highest value occurring at least once every 10 years in the
corresponding month of the year, on average according to historical data from the same station:

• cumulative rainfall for the month


• number of days in the month with rainfall exceeding 20mm
• number of days with minimum air temperature less than 0° Celsius
• number of days with maximum mean 10 minute wind speed exceeding 20 metres per second
• …………………………………………………………………………………………………

If no weather station is named above, the weather station nearest the Site shall be used. If the weather
station named above, or the nearest one, does not measure or record data for any of the above
weather, the nearest station to the Site that measures and records that data shall be used for that
weather.

In sub-clause 10.6.4(3), the rates to be used to determine the cost of plant are the rates in UK Civil
Engineering Contractors Association Schedules of Dayworks Carried Out Incidental to Contract Work
August 2003 reprint (Note: Only Schedule 4 will apply) (Rates will be considered to be in Euro) and any
rates in the Pricing Document.

In sub-clause 9.4:

• the first threshold is 40 Site Working Days of delay caused by Compensation Events

• the second threshold is 40 Site Working Days of delay caused by Compensation Events

Department of Finance Page 217


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

In sub-clause 10.7, the amount to be added for delay cost is (whichever is marked "yes"):

the amount stated in Part 2E of this Schedule as the Contractor's daily rate of
YES
delay cost
the expenses (excluding profit and loss or profit) unavoidably incurred by the
Contractor

The definition of craftspersons in part 2E includes the following additional categories:

_________________________________________________________________________
_________________________________________________________________________

For purposes of clause 10.7, the Contractor is to tender (in part 2E):

• a single rate for delay costs


• separate rates for delay costs for each of the following periods/portions of the Works:
o ______________________
o ______________________
o ______________________

If the above are blank, Contractor is to tender a single rate

L Payment Particulars

Clause 11

Period for interim payment is monthly (If none stated, monthly.)

Minimum amount for interim payments, except release of retention, €150,000. (If none stated, there is
no minimum.)

When permitted by the Pricing Documents, up to 90% of the Contract value of unfixed Works Items may
be included in an interim payment. (If none stated, 90%).

The retention percentage is 10%. (If none stated, 10%.)

M Price Variation

Sub-clause 10.8

Clause PV1/Clause PV2 attached to this Schedule is part of the Contract. (Delete as
applicable. If none deleted, Clause PV2 shall apply).

N Conciliation and Arbitration

Sub-clause 13.1.2

Failing agreement, the conciliator will be appointed by the President of Engineers Ireland.

Sub-clause 13.2

The arbitration rules are the Public Works Arbitration Rules, 2007.

The person or body to appoint the arbitrator (if not agreed by the parties) is ……………………
……………………………………………………………………………………………………

Department of Finance Page 218


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

17. Case Study 2 – Tender Evaluation

17 Case Study 2
Tender Evaluation

Department of Finance
National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 2

Tender Evaluation

Introduction

Tenders have been invited from tenderers under the Restricted Procedure for the
construction of the new local authority headquarters building for LA County Council.

The criterion for evaluation of tenders is MEAT.

Tenders have been received from five Contractors Nr 1, Nr 2, Nr 3, Nr 4 and NR 5,


as follows:

Tenderer Amount (Incl VAT)


Tenderer Nr 3 €39,054,750
Tenderer Nr 1 €39,206,800
Tenderer Nr 4 €39,207,550
Tenderer Nr 2 €39,236,250
Tenderer Nr 5 €40,100,361

The following values were inserted in Section 12.5 of the Instructions to Tenderers
for determining the comparative costs of tenderers:

5,000 hours of craftspersons time


3,000 hours of general operative time
1,000 hours of apprentice time
€150,000 of materials cost
€75,000 of plant cost
50 site work days of delay

The pages hereafter contain the following:

(a) Blank Schedule Part 2;


(b) Blank Summary of the Pricing Document;
(c) The Schedules Part 2 submitted by tenderers, together with completed
summaries of the pricing document; and
(d) A pro forma summary tender evaluation tender

The Task

Delegates are requested to complete the pro forma commercial tender


evaluation sheet.

Department of Finance Page 220


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

SCHEDULE PART 2

TENDERER NR 1

(Completed by the Contractor and provided with Tender)

A Communications

Sub-clause 4.14

The details for sending notices under clause 12 or 13 to the Contractor are:

For the attention of: Mr Peter Rock

Address

Build Ex Ltd
1 The Heights
LA Town
Co LA

The details for sending other notices to the Contractor are:

For the attention of: Mr John Doyle

Address

Build Ex Ltd
1 The Heights
LA Town
Co LA

Fax 012 567835

Email [email protected]

The Contractor’s agent in the Republic of Ireland for service of legal process is:

For the attention of: …………………………………………

Address

…………………………………………

…………………………………………

…………………………………………

Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).

Department of Finance Page 221


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

B Parent Company Guarantee

Sub-clause 1.6

The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.

(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)

C Works Proposals

The Works Proposals are the following

As contained in Document 1853-WP-001

D Dates for Substantial Completion

Date for Substantial Completion Number of


Working Days after the Contract Date (to be
completed by Contractor in Tender ONLY if not
completed by Employer in Part 1)
The Works
Section: (Employer to complete)

Section: (Employer to complete)

Section: (Employer to complete)


Section: (Employer to complete)

E Adjustments to the Contract Sum

Sub-clauses 10.7 and 10.8

The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):

• Craftspersons €28 per hour


• General Operatives €26 per hour
• Apprentices €20 per hour

Craftspersons means those categories of work persons described as “craftsmen” or “electricians” in


employment agreements registered under the Industrial Relations Acts 1946 to 2004, and, any
additional categories listed in Part 1K

General Operatives means all direct labour other than craftspersons

Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons

The Contractor’s tendered percentage addition for costs of materials 5%

The Contractor’s tendered percentage addition/deduction for costs of plant 5%

Department of Finance Page 222


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If either of the above is left blank, read as zero.)

The Contractor’s tendered rate of delay costs is: €5,000 excluding VAT per Site Working Day. (If
blank, read as zero.)

If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:

Period/portion of the Works (part 1K) Tendered Rate

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

Department of Finance Page 223


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Summary of Pricing Document – Tenderer Nr 1

€ c

Bill Nr 1 Preliminaries & Insurances (06) (07) 3,950,000 00

Bill Nr 2 Substructure (1-) 1,400,000 00

Bill Nr 3 Structure (2-) 8,960,000 00

Bill Nr 4 Structure Completions (3-) 3,710,000 00

Bill Nr 5 Finishes (4-) 2,550,000 00

Bill Nr 6 Services (Mainly piped and ducted) (5-) 3,960,000 00

Bill Nr 7 Services (Mainly electrical) (6-) 2,970,000 00

Bill Nr 8 Fittings and Furniture (7-) 960,000 00

Bill Nr 9 Site Generally (-0) 6,020,000 00

Sub-total € 34,480,000 00

Value added tax @ 13½% 4,525,200 00

Value added tax @ 21% 201,600 00

Total Amount of Tender to Form of Tender € 39,206,800 00

Department of Finance Page 224


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

SCHEDULE PART 2

TENDERER NR 2

(Completed by the Contractor and provided with Tender)

A Communications

Sub-clause 4.14

The details for sending notices under clause 12 or 13 to the Contractor are:

For the attention of: Managing Director

Address

Build IT Ltd
20 The Heights
LA Town
Co LA

The details for sending other notices to the Contractor are:

For the attention of: Mr Peter Rock

Address

Build IT Ltd
20 The Heights
LA Town
Co LA

Fax 04 6753896

Email [email protected]

The Contractor’s agent in the Republic of Ireland for service of legal process is:

For the attention of: …………………………………………

Address

…………………………………………

…………………………………………

…………………………………………

Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).

Department of Finance Page 225


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

B Parent Company Guarantee

Sub-clause 1.6

The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.

(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)

C Works Proposals

The Works Proposals are the following

As contained in Document 24936/WP/001

D Dates for Substantial Completion

Date for Substantial Completion Number of


Working Days after the Contract Date (to be
completed by Contractor in Tender ONLY if not
completed by Employer in Part 1)
The Works
Section: (Employer to complete)

Section: (Employer to complete)

Section: (Employer to complete)


Section: (Employer to complete)

E Adjustments to the Contract Sum

Sub-clauses 10.7 and 10.8

The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):

• Craftspersons €28 per hour


• General Operatives €26 per hour
• Apprentices €22 per hour

Craftspersons means those categories of work persons described as “craftsmen” or “electricians” in


employment agreements registered under the Industrial Relations Acts 1946 to 2004, and, any
additional categories listed in Part 1K

General Operatives means all direct labour other than craftspersons

Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons

The Contractor’s tendered percentage addition for costs of materials 2%

The Contractor’s tendered percentage addition/deduction for costs of plant 2%

Department of Finance Page 226


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)

The Contractor’s tendered rate of delay costs is: €3,500 excluding VAT per Site Working Day. (If
blank, read as zero.)

If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:

Period/portion of the Works (part 1K) Tendered Rate

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

Department of Finance Page 227


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Summary of Pricing Document – Tenderer Nr 2

€ c

Bill Nr 1 Preliminaries & Insurances (06) (07) 3,600,000 00

Bill Nr 2 Substructure (1-) 1,500,000 00

Bill Nr 3 Structure (2-) 9,050,000 00

Bill Nr 4 Structure Completions (3-) 3,600,000 00

Bill Nr 5 Finishes (4-) 2,700,000 00

Bill Nr 6 Services (Mainly piped and ducted) (5-) 4,050,000 00

Bill Nr 7 Services (Mainly electrical) (6-) 2,990,000 00

Bill Nr 8 Fittings and Furniture (7-) 1,050,000 00

Bill Nr 9 Site Generally (-0) 5,960,000 00

Sub-total € 34,500,000 00

Value added tax @ 13½% 4,515,750 00

Value added tax @ 21% 220,500 00

Total Amount of Tender to Form of Tender € 39,236,250 00

Department of Finance Page 228


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

SCHEDULE PART 2

TENDERER NR 3

(Completed by the Contractor and provided with Tender)

A Communications

Sub-clause 4.14

The details for sending notices under clause 12 or 13 to the Contractor are:

For the attention of: Managing Director

Address

Build All Ltd


157 The Heights
LA Town
Co LA

The details for sending other notices to the Contractor are:

For the attention of: Mr John O'Brien

Address

Build All Ltd


157 The Heights
LA Town
Co LA

Fax …………………………….

Email …………………………….

The Contractor’s agent in the Republic of Ireland for service of legal process is:

For the attention of: …………………………………………

Address

…………………………………………

…………………………………………

…………………………………………

Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).

Department of Finance Page 229


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

B Parent Company Guarantee

Sub-clause 1.6

The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.

(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)

C Works Proposals

The Works Proposals are the following

As contained in Document 5893-WP-002

D Dates for Substantial Completion

Date for Substantial Completion Number of


Working Days after the Contract Date (to be
completed by Contractor in Tender ONLY if not
completed by Employer in Part 1)
The Works
Section: (Employer to complete)

Section: (Employer to complete)

Section: (Employer to complete)


Section: (Employer to complete)

E Adjustments to the Contract Sum

Sub-clauses 10.7 and 10.8

The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):

• Craftspersons €39 per hour


• General Operatives €30 per hour
• Apprentices €24 per hour

Craftspersons means those categories of work persons described as “craftsmen” or “electricians” in


employment agreements registered under the Industrial Relations Acts 1946 to 2004, and, any
additional categories listed in Part 1K

General Operatives means all direct labour other than craftspersons

Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons

The Contractor’s tendered percentage addition for costs of materials 25%

The Contractor’s tendered percentage addition/deduction for costs of plant 10%

Department of Finance Page 230


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)

The Contractor’s tendered rate of delay costs is: €6,000 excluding VAT per Site Working Day. (If
blank, read as zero.)

If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:

Period/portion of the Works (part 1K) Tendered Rate

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

Department of Finance Page 231


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Summary of Pricing Document – Tenderer Nr 3

€ c

Bill Nr 1 Preliminaries & Insurances (06) (07) 3,930,000 00

Bill Nr 2 Substructure (1-) 1,370,000 00

Bill Nr 3 Structure (2-) 8,950,000 00

Bill Nr 4 Structure Completions (3-) 3,650,000 00

Bill Nr 5 Finishes (4-) 2,500,000 00

Bill Nr 6 Services (Mainly piped and ducted) (5-) 4,100,000 00

Bill Nr 7 Services (Mainly electrical) (6-) 2,950,000 00

Bill Nr 8 Fittings and Furniture (7-) 900,000 00

Bill Nr 9 Site Generally (-0) 6,000,000 00

Sub-total € 34,350,000 00

Value added tax @ 13½% 4,515,750 00

Value added tax @ 21% 189,000 00

Total Amount of Tender to Form of Tender € 39,054,750 00

Department of Finance Page 232


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

SCHEDULE PART 2

TENDERER NR 4

(Completed by the Contractor and provided with Tender)

A Communications

Sub-clause 4.14

The details for sending notices under clause 12 or 13 to the Contractor are:

For the attention of: Managing Director

Address

Build Now Ltd


20 The Heights
LA Town
Co LA

The details for sending other notices to the Contractor are:

For the attention of: Ms Kate O'Shea

Address

Build Now Ltd


20 The Heights
LA Town
Co LA

Fax 06 583345

Email [email protected]

The Contractor’s agent in the Republic of Ireland for service of legal process is:

For the attention of: …………………………………………

Address

…………………………………………

…………………………………………

…………………………………………

Note: An agent in the State must be named if the Contractor’s registered office (or other principal
place of business) is outside the State).

Department of Finance Page 233


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

B Parent Company Guarantee

Sub-clause 1.6

The Contractor shall provide a parent company guarantee in the form in the Works Requirements from:
……………………………………………………………………………………………………………
(name and address of parent company, registered address and place where incorporated or organised).
If none named, no parent company guarantee required.

(NOTE: In open procedures, tenderers must name a guarantor if parent company is identified for
purposes of satisfying tender requirements. In restricted procedures, tenderers must name a guarantor
if parent company has been identified for purposes of pre-qualification..)

C Works Proposals

The Works Proposals are the following

As contained in Document 467-WP-001

D Dates for Substantial Completion

Date for Substantial Completion Number of


Working Days after the Contract Date (to be
completed by Contractor in Tender ONLY if not
completed by Employer in Part 1)
The Works
Section: (Employer to complete)

Section: (Employer to complete)

Section: (Employer to complete)


Section: (Employer to complete)

E Adjustments to the Contract Sum

Sub-clauses 10.7 and 10.8

The Contractor’s tendered daily rates for labour and related costs (including PRSI, benefits, tool money,
travelling time and country money):

• Craftspersons €30 per hour


• General Operatives €27 per hour
• Apprentices €25 per hour

Craftspersons means those categories of work persons described as “craftsmen” or “electricians” in


employment agreements registered under the Industrial Relations Acts 1946 to 2004, and, any
additional categories listed in Part 1K

General Operatives means all direct labour other than craftspersons

Apprentices means categories of work persons under a contract of apprenticeship for trades whose
practitioners fall within the above definition of Craftspersons

The Contractor’s tendered percentage addition for costs of materials 5%

The Contractor’s tendered percentage addition/deduction for costs of plant 5%

Department of Finance Page 234


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

All of the above shall include on-costs, overheads and profit, and exclude VAT.
(If both of the above is left blank, read as zero.)

The Contractor’s tendered rate of delay costs is: €4,600 excluding VAT per Site Working Day. (If
blank, read as zero.)

If part 1K states that separate rates for to be tendered for separate periods/portions of the Works, the
Contractor’s tendered rates are as follows:

Period/portion of the Works (part 1K) Tendered Rate

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

o …………………………... € …………………………... per Site Working Day

Department of Finance Page 235


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Summary of Pricing Document – Tenderer Nr 4

€ c

Bill Nr 1 Preliminaries & Insurances (06) (07) 3,800,000 00

Bill Nr 2 Substructure (1-) 1,450,000 00

Bill Nr 3 Structure (2-) 9,100,000 00

Bill Nr 4 Structure Completions (3-) 3,540,000 00

Bill Nr 5 Finishes (4-) 2,700,000 00

Bill Nr 6 Services (Mainly piped and ducted) (5-) 3,900,000 00

Bill Nr 7 Services (Mainly electrical) (6-) 2,980,000 00

Bill Nr 8 Fittings and Furniture (7-) 970,000 00

Bill Nr 9 Site Generally (-0) 5,950,000 00

Sub-total € 34,480,000 00

Value added tax @ 13½% 4,523,850 00

Value added tax @ 21% 203,700 00

Total Amount of Tender to Form of Tender € 39,207,550 00

Department of Finance Page 236


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Case Study 2 – Tender Evaluation


Attachment Nr 3 – TO BE COMPLETED BY DELEGATES
Tender Nr 3 Tender Nr 1 Tender Nr 4 Tender Nr 2
€ € € €
Bill Nr 1 Preliminaries & Insurances (06) (07) 3,930,000 3,950,000 3,800,000 3,600,000
Bill Nr 2 Substructure (1-) 1,370,000 1,400,000 1,450,000 1,500,000
Bill Nr 3 Structure (2-) 8,950,000 8,960,000 9,100,000 9,050,000
Bill Nr 4 Structure Completions (3-) 3,650,000 3,710,000 3,540,000 3,600,000
Bill Nr 5 Finishes (4-) 2,500,000 2,550,000 2,700,000 2,700,000
Bill Nr 6 Services (Mainly piped and ducted) (5-) 4,100,000 3,960,000 3,990,000 4,050,000
Bill Nr 7 Services (Mainly electrical) (6-) 2,950,000 2,970,000 2,980,000 2,990,000
Bill Nr 8 Fittings and Furniture (7-) 900,000 960,000 970,000 1,050,000
Bill Nr 9 Site Generally (-0) 6,000,000 6,020,000 5,950,000 5,960,000

Sub-total 34,350,000 34,480,000 34,480,000 34,500,000


Value added tax @ 13½% 4,515,750 4,525,200 4,523,850 4,515,750
Value added tax @ 21% 189,000 201,600 203,700 220,500

Total Amount of Tender as Forms of Tender € 39,054,750 39,206,800 39,207,550 39,236,250

TENDERED TENDERED TENDERED TENDERED


QUANTITY Labour VALUE EXTENSION VALUE EXTENSION VALUE EXTENSION VALUE EXTENSION

5,000 Hours Craftspersons


3,000 Hours General Operatives
1,000 Hours Apprentices

Materials
€150,000 Percentage addition to this for materials

Plant
€75,000 Percentage addition to this for plant

Delays
50 Days delay @ delay cost per day

VAT @ 13½%

CALCULATION OF SUBMITTED TENDER €

Note: Tender Nr 5 was found to be non-compliant.

Department of Finance Page 237


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Case Study 2 – Tender Evaluation


Attachment Nr 4 – Worked Solution
Tender Nr 3 Tender Nr 1 Tender Nr 4 Tender Nr 2
€ € € €
Bill Nr 1 Preliminaries & Insurances (06) (07) 3,930,000 3,950,000 3,800,000 3,600,000
Bill Nr 2 Substructure (1-) 1,370,000 1,400,000 1,450,000 1,500,000
Bill Nr 3 Structure (2-) 8,950,000 8,960,000 9,100,000 9,050,000
Bill Nr 4 Structure Completions (3-) 3,650,000 3,710,000 3,540,000 3,600,000
Bill Nr 5 Finishes (4-) 2,500,000 2,550,000 2,700,000 2,700,000
Bill Nr 6 Services (Mainly piped and ducted) (5-) 4,100,000 3,960,000 3,990,000 4,050,000
Bill Nr 7 Services (Mainly electrical) (6-) 2,950,000 2,970,000 2,980,000 2,990,000
Bill Nr 8 Fittings and Furniture (7-) 900,000 960,000 970,000 1,050,000
Bill Nr 9 Site Generally (-0) 6,000,000 6,020,000 5,950,000 5,960,000

Sub-total 34,350,000 34,480,000 34,480,000 34,500,000


Value added tax @ 13½% 4,515,750 4,525,200 4,523,850 4,515,750
Value added tax @ 21% 189,000 201,600 203,700 220,500

Total Amount of Tender as Forms of Tender € 39,054,750 39,206,800 39,207,550 39,236,250

TENDERED TENDERED TENDERED TENDERED


QUANTITY Labour VALUE EXTENSION VALUE EXTENSION VALUE EXTENSION VALUE EXTENSION

5,000 Hours Craftspersons 39 195,000 28 140,000 30 150,000 28 140,000


3,000 Hours General Operatives 30 90,000 26 78,000 27 81,000 26 78,000
1,000 Hours Apprentices 24 24,000 20 20,000 25 25,000 22 22,000

Materials
€150,000 Percentage addition to this for materials 25% 37,500 5% 7,500 5% 7,500 2% 3,000

Plant
€75,000 Percentage addition to this for plant 10% 7,500 5% 3,750 5% 3,750 2% 1,500

Delays
50 Days delay @ delay cost per day €6,000 300,000 €5,000 250,000 €4,600 230,000 €3,500 175,000

VAT @ 13½% 88,290 67,399 67,129 56,633

COMPARATIVE COST OF TENDERS € 39,797,040 39,773,449 39,771,929 39,712,383

Note: Tender Nr 5 was found to be non-compliant.

Department of Finance Page 238


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

18. Case Study 3 – Some Contract Administration


Issues

18 Case Study 3
Some Contract Administration Issues

Department of Finance Page 239


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

CASE STUDY 3 – Some Contract Administration Issues

Delay and Compensation Events

This case study refers to the project covered by Case Studies 1 and 2, the LA
County Council Civic Offices.

Three letters have been sent from the Contractor to the Employer's Representative
as follows:

Letter Nr 1 Letter Nr 1 dated 15 January 2008 Items of archaeological


interest

Letter Nr 2 Letter Nr 2 dated 30 January 2008 Unforeseen ground


conditions

Letter Nr 3 Letter Nr 3 dated 30 September 2008 Proposed Instruction

Accompanying each letter is a set of facts as determined by the Employer's


Representative.

Delegates are requested to draft a response to each letter.

Supplementaries

In the case of Letter Nr 1 What would the position have been if the Archaeologist
had been directly engaged by the Employer?

Department of Finance Page 240


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

LETTER NR 1

ITEMS OF ARCHAEOLOGICAL INTEREST

BUILD IT LTD
20 The Heights
LA Town
Co LA

15 January 2008

Santiago Balaclava & Associados SA


50 The Heights
LA Town
County LA

Dear Sirs

Building Contract for LA County Council Civic Offices Building


Notice Pursuant to Clause 10.3 of the Contract

I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 6 December 2007.

1.0 The Facts

The Works Requirements indicate that the novated Specialist archaeological sub-
contractor would carry out its archaeological excavations during the period mid
November to mid December 2007 and we had programmed for this period and for the
attendance required. The archaeological activities will now not be completed until mid
January 2008, a whole month of delay because:

1. progress is significantly slower than had been anticipated due to the level of
detailed recording required no doubt reflecting the archaeological interest of
the buried ruins;

2. the week long exceptionally poor weather with very heavy snow during the
period 28 November to 4 December 2007 which meant that the
archaeologists could not get on to site, with the blanket of snow the ground
could not be seen, the site was unsafe and moreover the ground was too
hard to excavate because of ground frost and subsequently the effect of the
melting snow was that the excavations had to be pumped out to enable the
archaeologists work and the photographic record be generated. None of this
was anticipated.

2.0 The Effects

This delay has caused a one month or 21 site working days to the Date for
Substantial Completion date as follows:

Delay Event (Weather Event) 5 working days delay

Compensation Event (Items of Archaeological 21 working days delay (to be drawn


Interest) down from programme contingency)

Department of Finance Page 241


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Hire and Operation of Pumping Equipment/Earthwork Support €

Pump – 4 days @ 24 hours @ €7.00/hr 672.00

Labour Attendance – 32 hours @ €26/hr 832.00


40 hours (T&1/2) @ €36.00/hr 1,400.00

Earthwork Support Trench sheeting per hirer's invoice 2,700.00


————
Additional Cost (Excluding VAT) €5,604.00
————

We consider that the facts of this matter have been well aired at recent site meetings and during
your site visits and that no further information should be necessary to enable us to demonstrate
our entitlement, or for you to make a decision. If however you require further information,
please do not hesitate to contact me.

Yours faithfully

Peter Rock
Contracts Manager
BUILD IT LTD

The facts as determined by the Employer's Representative

1. The Archaeology Specialist had previously indicated he would have four archaeologists
working on the Project in the event he only had two;

2. The Contractor was genuinely delayed by the Archaeology Specialist;

3. There was snow (50mm deep) and air temperatures below 0° Celsius during the period
28 November to 4 December 2007 and during this period the Archaeology Specialist
could not carry out any work;

4. The Employer's Representative has determined that the bad weather is not a weather
event;

5. After the snow melted, the Contractor had to pump out the excavations and provide
some additional earthwork support to enable the Archaeology Specialist continue
working safely and make up for the lost time.

Department of Finance Page 242


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

LETTER NR 2

UNFORESEEN GROUND CONDITIONS

BUILD IT LTD
20 The Heights
LA Town
Co LA

30 January 2008

Santiago Balaclava & Associados SA


50 The Heights
LA Town
County LA

Dear Sirs

Building Contract for LA County Council Civic Offices Building


Notice Pursuant to Clause 10.3 of the Contract

I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 17 January 2008.

1.0 The Facts

All of the borehole logs in the site investigation reports indicate that rock is to be
encountered some 4-6m below existing ground level and below the formation level of
the proposed basement car park. In the event, significant outcrops of hard granite
rock have been encountered at 1.5m below the existing ground level and the
estimated quantity of rock to be removed is some 2,000cu m. This quantity has been
measured and agreed between Employer’s Quantity Surveyor and our Quantity
Surveyor. These outcrops are scattered throughout the site and it is unrealistic to
consider advancing parts of the works until these have been excavated.

2.0 The Effects

This delay has caused a 51 working day delay to progress on site and the entitlement
for our extension of time is calculated as follows:

Delay caused by rock 51 working days

Less

Delay to first threshold 21 working days

Delay to second threshold 20 working days


————————
Extension of time required 10 working days
————————

Department of Finance Page 243


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

3.0 Proposed Adjustment to Contract Sum

The proposed adjustment to the contract sum is as follows:

Additional preliminaries for 10 site working days


delay @ €3,500 €35,000

Extra cost of excavating in rock 2,000cu m @ €40/cu m €80,000


————
Sub-total €115,000

VAT @ 13.5% €15,525


————
Total €130,525
————

We consider that the facts of this matter have been well aired at recent site meetings, during
your site visits and in discussions on site so no further information should be necessary to
enable us to demonstrate our entitlement, or for you to make a decision. If however you require
further information, please do not hesitate to contact me.

Yours faithfully

Peter Rock
Contracts Manager
BUILD IT LTD

The facts as determined by the Employer's Representative

1. The Contractor has indeed encountered hard granite rock on the site and the quantity is
in the region of 2,000cu m;

2. There was no indication of this rock in any of the site investigation reports and the site
investigation reports are found to be factually correct for the boreholes and trial pits that
were sunk;

3. The Contractor's estimate of the delay period of 51 working days has been examined by
the ER and is considered reasonable;

4. The Contractor is doing everything possible to mitigate the effects of the delay.

Department of Finance Page 244


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

LETTER NR 3

PROPOSED INSTRUCTION

BUILD IT LTD
20 The Heights
LA Town
Co LA

15 September 2008

Santiago Balaclava & Associados SA


50 The Heights
LA Town
County LA

Dear Sirs

Building Contract for LA County Council Civic Offices Building


Proposed Instruction for an Additional Floor

I refer to the above Project and now provide substantiation in respect of the delay and
compensation event notified to you in our letter dated 1 August 2008.

1.0 The Facts

The building has been designed to support and an additional 2nr floors and as a
result of a policy decision to relocate some staff from a government agency to the
building 1 nr additional floor will now be built. Planning and fire safety cert approval in
respect of this change have now been secured.

2.0 Proposed Adjustment to Contract Sum

The proposed adjustment to the contract sum is as follows:

Estimated delay costs for 150 working days


delay @ €3,500 €525,000

Measured work value €3,500,000

Preliminaries €420,000
—————
Sub-total €4,445,000

VAT @ 13.5% €660,075


—————
Total €5,045,075
—————

Department of Finance Page 245


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

3.0 The Effects

We estimate that delay will delay progress by some 150 days and as this is caused by
a compensation event and the programme contingency has been fully used up we
request that the Date for Substantial Completion be further extended to reflect this.
We also wish to put on record the point that we have raised at our recent meetings
that 150 days can only be our estimate of the delay at this stage – we will revert when
the exact delay is known.

If you require further information, please do not hesitate to contact me.

Yours faithfully

Peter Rock
Contracts Manager
BUILD IT LTD

The facts as determined by the Employer's Representative

1. The Employer has requested this additional change;

2. The Quantity Surveyor has agreed the quantities associated with the change;

3. The measured work has been priced at the rates in the Pricing Document and this has
been agreed to by the Quantity Surveyor;

4. The programme has been reviewed and the 150 days is considered reasonable,
however the original scope is still to be completed by the original date;

5. The Employer's Representative considers that it should be possible to complete the


original scope by the contract date for Substantial Completion;

6. The programme contingency has been used by earlier compensation events.

Department of Finance Page 246


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19 Frequently Asked Questions

Department of Finance Page 253


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19. Frequently Asked Questions


QUESTIONS ON RISK

19.1 What of risks other than those listed in Schedule Part 1, Section K? If
they are to be the Contractors’, what is the mechanism of allocation
in the Contract Documents?
Part K of the Schedule Part 1 allocates certain risks to the Contractor, either by
the prescribed allocation, or by election of the Employer where this discretion is
permitted. Any other risks are deemed to be the Contractors’ risks, except
those giving rise to a change in the Works Requirements. The identification and
evaluation of risks would be part of the Risk Assessment and Management
process in the development of the Works Requirements.

Risks which materialise and require change in the Works Requirements are at
the Employers’ risk, accordingly robustness of risk assessment and evaluation,
and effective description and transfer in the Works Requirements are important
in the protection of the fixed price lump sum tender.

19.2 Is it intended that there will be individual items for risk in a Bill of
Quantities?
There should be separate items in the BoQ to allow for pricing of the risks listed
in Section K of Schedule Part 1 which are allocated to the Contractor as the
Method of Measurement may require.

Those other risks (other than those in Section K) are allocated by the
appropriate clauses of the Works Requirements, and the cost of providing for
them is included generally in the rates in the BoQ.

19.3 Does a project budget get revised as decisions are made on risk
transfer?
Risks that are not transferred to the Contractor, are retained by the Employer.
Accordingly decisions which transfer an appropriate risk into the contract scope,
essentially move that provision into the contract, across from the Employers’
budget for non contract items. These transfers represent movements of value
within an overall budget for contract- and non-contract items, which budget
should not change when the overall scope of work and timeframe do not
change. Where the risk transfer is well defined, well prepared and appropriate,
this transfer is a good value for money decision, that reduces the cost of a
project, compared to one where risks are not appropriately allocated. Guidance
on this issue can be found in the Guidance Note on Budget Development in the
Capital Works Management Framework.

Department of Finance Page 254


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.4 Does the Contractor get paid the value of the risk item if the risk
does not arise?
Where work is proceeded with, and a risk associated with that work has been
transferred and priced, but the risk does not materialise, the Contractor is
entitled to be paid the cost of his provision for that risk, on the basis that, had
the risk occurred, that would have been his only entitlement for it, apart from
any reliefs specified under Schedule 1 Section K. Where an element of work is
not being proceeded with, then the contract sum would be reduced accordingly,
and risk associated with that element, and priced in the rates for it would be
credited out automatically in that calculated reduction.

19.5 Are methodologies put forward for the assessment of approach to


the allocation of risk?
The Training Manual includes a section on Risk Management. Risks are first
identified and evaluated, and the best way of treating risks is identified before
they are allocated to the party best able to manage them. Risks may need to be
further evaluated, by means of investigatory work, before they can be allocated.

Methodologies include the use of risk workshops, where, under the


chairmanship of an experienced facilitator, risks are identified and their expected
likelihood and impact are defined under the broad headings of Safety, Planning,
Finance, Design, Construction, and Operation. Once the risks are identified, the
method of treating these risks must then be aligned with the drafting of the
Works Requirements, and with the selections made, in Schedule Part 1
particularly.

QUESTIONS ON PROCUREMENT & TENDER ASSESSMENT

19.6 Is there guidance on the relative merits of using the Open or


Restricted procedures?
The relative merits of these procedures are discussed in the Guidance Note on
the Works Contracts. The Open Procedure has advantages, particularly
programming, but it has the risk that a bidder may prepare a tender and not pass
the prequalification phase. As with all procedures, it is necessary to ensure that
you do not mix selection and award criteria.

19.7 If the Tender Sum exceeds the Budget, is a Bill of Reductions


exclusively a post contract issue?
Yes, but you must be aware of making a "material change" in cutting back the
scope of work on which the contract is procured, potentially to the disadvantage
of the other tenderers. Also, unless the procurement process is definitively
complete, this process could involve an element of post tender negotiation,
which is prohibited.

Department of Finance Page 255


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.8 The values selected for the contingent items in the MEAT example
may well result in loading of the bid rates in the Tender, especially
where, because of the choice of notional items below the Tender
Sum, there is little impact on the MEAT Comparative Cost?
These values are selected by the client and should be the expected value of the
item in question, having regard to professional judgement of the client or his
consultant and previous experience on similar projects. The expected value is
not so low as to encourage loading of rates and is not so high as to pack the
MEAT with contingent items.

19.9 If you start on an assumed Budget of less than €5m, working on the
Minor Works Form of Contract, and you drift over the limit as
tenders are received, do you have to change the form of contract to
be used?
Good budgeting should not leave you in this position, but you would have to
stay with the procurement choice originally made and run with the tendered
contract.

19.10 If you take tenders on one Form and found you had to use another,
could this be negotiated?
No form of negotiation on fundamental matters, particularly price, may take
place in the open or restricted procedure.

19.11 If the estimate is just under €5m can you opt to use the Main Form?
Yes, this option is available where it is appropriate to do so. One should
probably opt for the main contract form in the case stated.

19.12 If the second option is chosen on delay, i.e. where no rate has been
tendered, no delay element in the MEAT calculation ensues?
Where daily rates are not tendered, the Employer pays only for the cost of delay
actually incurred. This is not therefore an issue for assessment in the MEAT
calculation.

19.13 Will the Employer have to create a rule for rebalancing items in the
BOQ to ensure arithmetic errors are corrected to maintain the
lump sum bottom line as fixed? Are the potential number of
variables not very large, when the bottom line is being held? Should
there not be a commonality of approach because precedent will
apply across the board anywhere these contracts are used?
The approach on correction of tenders is set out in the Guidance Note in
Section 2.7.3. The example given in the GN related to correction of errors in

Department of Finance Page 256


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

calculating VAT is also relevant. The fixed price lump sum tender total remains
unchanged in any correction of arithmetic error in the BoQ.

19.14 Can the Contracting Authority reject an abnormally low tender?


Yes, nothing has changed with respect to this aspect of procurement procedure,
and an abnormally low tender may be rejected, provided that due process under
the EU Directives has been followed in arriving at the conclusion that the tender
is abnormally low.

19.15 If the Tender wasn’t signed, or the Tender Sum wasn’t transferred,
from the BoQ to the Tender Form correctly, is the tender
disqualified?
It depends on the stated position on this point in the Instructions to Tenderers.
In the absence of a clear rule requiring disqualification, the Contracting
Authority has discretion. Is it a proportionate response to reject a tender for
such an oversight? It should be drafted so that no hair-trigger rejection
responses arise on matters which can easily be clarified without risk to
transparency or equal treatment.

19.16 In a Contractor Designed contract, why introduce craftsmen rates or


the like in the MEAT calculation, or in valuing change orders. There
is no facility for monitoring these things in Design-Build?
Even where this is no BoQ, there is still a need to have a means to value Change
Orders, and these rates are likely to be required for this purpose.

19.17 What of variants where the workload of assessment of the tenders


or the criteria for award conflicts with the variant offered? For
example, a high density development option in parallel with an
Employer-preferred low density main design?
Tender appraisal workload isn’t hugely different than is normal with variants at
present and is accepted as covered in the services. Variants rules need to be
prescribed in the Instructions to Tenderers to prevent variants at odds with the
Contracting Authority's fundamental or core objectives emerging. Additional
costs arising from accommodating a variant, or consequential costs in
building/civil engineering, need to be planned for through risk assessment, then
addressed and locked into the fixed price.

19.18 Why not accept an offer of a "free" parent company guarantee in lieu
of the Bond?
Such an approach is contrary to good practice as described in the Guidance
Note. It should be remembered that problems with a contractor often have
their roots in a problem with the Parent Company itself, so that the Parent
Company Guarantee is not a robust guarantee in such circumstances. Refer to
the Guidance Note at Section 2.3.2.

Department of Finance Page 257


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.19 If there’s an expiry date on a Bond, can you not have a position
where you threaten calling in Bond in order to get a Bond
extended?
It is safer to have a Bond whose expiry date is predicated upon an event such as
Substantial Completion (say, 15 months after its issue) in which case the
situation outlined is unlikely to arise. The difficulty in threatening to call in a
bond such as the Performance Bond to be provided by the Contractor under
the contract is that a call is only permitted where the Contractor is in breach or
has its obligation to complete terminated.

QUESTIONS ON CONTRACT FORMALITIES, PROFESSIONAL INDEMNITY


INSURANCE AND FITNESS-FOR-PURPOSE STANDARD

19.20 On signing of contract documents, are there protocols on signing


every page, or on signing a particular number of copies?
There are no protocols and there is no need to sign every page. However, if
there are a large number of documents involved, it may be appropriate to have
the parties sign or initial each bound document for identification purposes. The
potential necessity for initialling or signing individual pages only becomes relevant
if there are loose pages that ought to be identified separately.

19.21 What if the Contractor is tardy or reluctant to seal the contract?


The Contractor is required to execute its tender under seal and the acceptance
of the tender will create a contract under seal.

The Bid Bond is a mechanism which can be used if there is a concern that a
tenderer might not honour its tender or where a particular contract is
absolutely essential to a larger project and any withdrawal by the successful
tenderer would cause substantial losses etc. [see Guidance Note at Section
2.3.1.].

19.22 What if there is a design problem with the Works after six years and
before twelve years and the Contract has been executed under seal?
Where a contract has been executed under seal the time within which the
Employer may sue for any breach is independent of the date of the contract
execution but is referable to the date of the breach of contract itself. Thus in
the case outlined, the Employer could sue the relevant party for breach of
contract, within twelve years from the date of the breach itself. This is likely to
be the date that the actual defective design work was carried out although the
final date can sometimes be different, for instance, the date by which the
defective design could have been rectified by the guilty party.

Consultants will need ongoing annual renewal of PI but that’s really as far as
practicalities permit. There’s little point in pursuing a consultant for failing to

Department of Finance Page 258


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

maintain annual cover out in year ten. If it’s not there, its not there, and the fact
of that is that he may not be worth pursuing in the absence of PI cover.

One should also keep sight of the fact that we are only speaking here of actions
for breach of contract. An Employer who has suffered loss as a result of
defective design could also proceed under the tort of negligence and would have
six years from when the damage actually occurred (not when it was discovered)
within which to sue.

19.23 If the Contracting Authority issues a Letter of Acceptance, is there


not an attraction for the (now) Contractor to decline to execute a
contract under seal?
This can be avoided by requiring that the Tenderer seal the Form of Tender. If
he doesn’t seal it, it can be sent it back for sealing, and if the tenderer refuses,
this might be considered grounds to reject the bid. The Model Form requires
the tender to be sealed.

19.24 Is it appropriate for a "Letter of Intent" to a Consortium to require


that they put in place the Joint Venture legal entity so that you can
send a "Letter of Acceptance" to the "Contractor" as it seems to be
worded?
It may be that the Contractor will be an unincorporated group, i.e. it may not
form any separate legal entity. The Contractor will then be all of the members
having joint and several responsibility. Thus, each of the members of the
consortium will be individually responsible for the carrying out of the entire of
the Works.

19.25 How important is it that the €1 exchanges hands in the collateral


warranty?
It is executed under seal in any case and so it is not necessary. Even it were not
executed under seal it would not be vital.

19.26 Is the Performance Bond required on date of issue of Letter of


Acceptance?
Evidence for the imminent availability of the Bond is perhaps as best you can get.
An updated letter from the Bonding company, to the effect that they are
endorsing a prior letter provided at the time of tender, and stating that there is
no impediment to issue of the Bond, might fulfil this requirement. Clause 9.1.2
lists what is needed and the Start Date runs from Letter of Acceptance.

19.27 Occupancy Vs Possession of the Site; what are the implications,


generally or on insurances?
Contractor should experience no great difference. Contracts have been
referred to Insurance sector for consultation and this was not an issue of

Department of Finance Page 259


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

importance. The fundamental issue is that the Contractor is not entitled to


exclusive occupancy of the Site. There is an entitlement of Employer to have his
own contractors on site if he wishes to do.

19.28 Can assignment take place by Employer onto other parties?


There is no specific provision for Employer to assign. However, as a matter of
law, he would be entitled to assign the benefit of the contract without the
consent of the Contractor.

19.29 Form of Retention Bond – is it included in the Tender Documents?


Will its cost not exceed the interest value of the Retention Money?
Almost by definition, if he needs this money badly, will the cost of
the Retention Bond not be very high?
It is a matter for the Contractor to consider the value to him of release of the
Retention money, in exchange for provision of a Retention Bond.

19.30 Form of Tender says he (can't/won't) withdraw. What if he makes a


mistake and there is a Bid Bond in place?
In the quasi-contract that exists as a matter of agreeing to consider a tender,
you could relax that position, but it would have to be an agreed relaxation. A
Bid Bond is rare and might be used where there is "history" of withdrawal and
you see an offender coming through in Pre-Qualification but it is not intended to
penalise anyone on a Bid Bond issue. Is the error so serious he risks going
under in the Contract? If so, you might prefer to release him.

19.31 Can you ask one tenderer to provide a Bid Bond and not others?
No

19.32 If PI Insurance is needed from a Contractor, under the Restricted


Procedure, do you not have to prequalify tenderers on ability to get
"fit for purpose PI insurance"?
Insurance industry have looked at all the provisions of the contract, and it
presumably recognises the issue of the fitness for purpose obligation. When one
looks at the actual requirement in the contract in this regard it merely requires
that the Contractor has PI cover per the limits in the Contract but does not say
he must insure against a fitness for purpose obligation.

Presumably if this is not insurable in the general market it will simply be


something that the Contractor does not have cover for and accordingly,
something for which he bears any additional risk.

19.33 Can Contractor in a DB Contract require a collateral agreement


from his Consultant in favour of the Client, so the latter has access
to PI cover of the Consultant?

Department of Finance Page 260


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

Although the Consultant agrees by the Conditions of Engagement that he is


willing to be novated to the Contractor, neither those conditions nor the
Novation Agreement itself requires him to actually enter into the collateral
agreement. Thus, in a situation where such a novation is anticipated, it would be
necessary for the Employer to provide a copy of the warranty to the Consultant
with a requirement that it be executed at the time of novation. In addition, the
requirement that the Contractor provides a warranty from the Consultant (as a
Specialist) would be provided for in the Schedule to the construction contract at
part 1F).

19.34 When is PI Insurance required from a Contractor in a traditional


Contract?
It is not necessarily appropriate to automatically seek PI cover from a
Contractor in traditional contracts. However, one must recognise the fact that
the Contractor may have some small design function. Even if a Specialist has PI
cover and a collateral warranty is in place, it may be felt appropriate to have the
additional protection of PI cover for the Contractor, particularly as the
Contractor has full responsibility in any event for all design by Specialists. In
theory at least, the Specialist might disappear, their PI cover might be
discontinued and the Employer might be left with a worthless collateral warranty
and nobody but the Contractor to pursue for a serious design defect. In such
circumstances the Employer might be glad of the Contractor’s PI cover.

19.35 Are the PI Insurance cover requirements effectively double counting


as between the Contractor and Specialists?
The requirement of PI cover from the Contractor is an optional one and need
not be availed of unless it is deemed appropriate. There may be a degree of
overlap with PI in a Contractor Designed contract, where there are Specialists,
but it might be necessary if the Contractor becomes insolvent, to have recourse
to the warranty of the Specialist with respect to design done by him, and not
done by others. [And see also the comments above in relation to PI cover.]

19.36 The design obligation of the Contractor in a Design and Build


Contract is one of "fitness for purpose", If one looks at the
collateral agreement, to be provided by any of the Specialists the
obligation worded there however is not necessarily "fitness for
purpose" but may be "reasonable skill and care".
The Employer would have to be careful so as to ensure that in seeking collateral
warranties from various Specialists, he has adequate protection and that if a
Specialist is providing an element for inclusion into the Works which must be fit
for its specific purpose so that the rest of the Works will function, then he
should require an obligation of fitness for its purpose. However, whichever
obligation the Employer requires, the Contractor will, nevertheless have his
obligation as referred to above.

Department of Finance Page 261


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.37 Road Traffic Act insurance is a permitted exclusion under the


contracts but is this appropriate?
The Contracts were carefully considered by distinguished insurance
professionals and it was regarded as appropriate to exclude such matters,
presumably because this insurance is in any event required by law and the
Contractor is required to comply with all laws.

19.38 What does "fit for intended purpose" mean?


In the case of goods or a manufactured product it means fit for the purpose for
which such goods or items are normally used. In the case of a design it means
that the overall building or plant will be suitable for its intended function (as
made known in the Employer’s Requirements).

19.39 If a structure serves two purposes, must it be fit for both purposes?
This will depend upon the purpose of the structure under the Contract. It
would be most unlikely for a structure that has two purposes not to be required
to meet the requirement for both.

19.40 Do you need two sets of contract documentation?


There is only one contract but there can be as many originals as people require.
It is usual to have one original set of Contract Documents for each party
executing the Contract.

19.41 What are appropriate excess limits for PI Insurance?


Very low excess limits are hard to get in the insurance market but an excess of
80–100k looks pretty high; one around €50k seems more appropriate for larger
companies, and even this is too high for smaller companies. In many cases a limit
of between €10,000 and €25,000 would be appropriate, and the excess level
should be reasonable having regard to the range of firm sizes quoting for the
project.

19.42 Does there need to be Model Forms included with each contract?
Reference to "Model Form 8" would be unambiguous, but it might be useful if
there was a pro-forma insertion checklist.

19.43 Why no separate Model Form for appointment of PSDP?


There is a Model Form 10 covering the PSDP.

Department of Finance Page 262


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.44 With respect to the Form of Tender, in the quasi-contract that exists
where a tender will be examined once it is validly submitted, where
is the Consideration for agreement to keep open the tender?
The consideration is generally regarded as the willingness of the contracting
authority to consider the tender in question.

19.45 PI Insurance extends for 6 years. What is the position if the


Consultant is no longer in business?
The insurance will lapse (unless he has taken out run-off cover). PI tends to be
year-to-year and on a "claims made" basis

19.46 Assignment of Collateral Warranties? If it’s a PI level for required


design specialists, does Employer have to increase the PI cover when
assigned to a higher risk function (example:-sweetshop now
becoming heavily loaded warehouse store).
You can only look for the appropriate level of PI from the outset, or else change
by agreement.

QUESTIONS ON STATUS OF THE BILL OF QUANTITIES

19.47 What is the function of a Bill of Quantities, when remeasurement of


work no longer applies?
The Bill of Quantities still serves a number of purposes, even when
remeasurement no longer applies. It serves cost-effective tendering, by drawing
the works items and their descriptions, which comprise the Lump Sum, into a
common document for all tenderers to price on a like-for-like basis. It further
assists the tender evaluation process by providing information on the balance of
pricing in the tender. It is used in contract management to assist in interim
certification, to predict cash flow, to assist in valuation of Change Orders and to
support calculation of price variation entitlements. Finally it is used to record
and classify costs in accordance with the Capital Works Management
Framework.

19.48 Can a Bill be both a Works Requirements document and a Pricing


Document?
The Bill of Quantities can be a Works Requirements document, as well as a
Pricing Document. In the former role, it is normal to strike out the quantities
themselves, leaving the item descriptions to stand, to be interpreted collectively
with the other Works Requirements Documents in the order of priority stated
in the Contract.

Department of Finance Page 263


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.49 If rates have no real meaning in relation to the lump sum, then is it
not open to possible abuse by Tenderers sprinkling mischievous
rates all over the place in a Pricing Document, all aimed at securing
later advantage at Change Orders?
It is part of tender assessment to check that rates in the BoQ reflect the value of
the work item, in so far as it is possible to do this. Rebalancing of rates may be
required to ensure that the scenario postulated in the question is avoided,
maintaining the tender total fixed, in accordance with the Guidance Note.

QUESTIONS ON SPECIALISTS

19.50 In Specialist procurement, how can the following scenario be


handled?
a. Top of range Specialists are put forward by Tenderer
b. They are successfully prequalified
c. The Tenderer pitches his tender at a level which inherently
presumes someone cheaper will later be acceptable, and he
persists with applications to agree substitution until the Specialist
in his presumed price range gets accepted?
The same prequalification thresholds and criteria used in the original
prequalification process will apply to any later substitution.

19.51 In the Prequalification stage for Specialist, if the only one in a


particular Specialist category fails to prequalify, the whole bid fails. Is
there a contradiction between this and permitting substitution of
Specialists for a successful tenderer after the award stage?
There is no contradiction when the same prequalification criteria are used to
admit any substitute, the standard for acceptance of a substitute Specialist is not
less than that used to prequalify Specialists at tender stage.

19.52 Are Specialists separately bonded?


No, they are part of the main contract, covered with respect to responsibilities
by the Contractor, as if they were his own personnel, and therefore covered by
his bond.

19.53 Can ER ask that a Specialist be removed from the Site or its contract
terminated?
The Specialist has the legal status of Contractors Personnel so you have the
option in accordance with the terms of the Contract. Thus at sub-clause 5.6, it
is provided that the ER may request the removal of any Contractor’s Personnel

Department of Finance Page 264


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

from the Site for reasons of negligence, incompetence or that their presence is
not conducive to safety, health or good order

19.54 Is a Designer a subcontractor?


A Designer may be a subcontractor although he need not be e.g. if he were
working purely as a Consultant to the Employer. If he is doing design work for
the Contractor then he is by definition, a Specialist.

19.55 Why would a Contractor propose Specialists, why not just use them
as subcontractors?
If Employer nominates particular work categories as specialist areas, over which
he wishes to exercise a minimum quality threshold type of control, he may
designate these as Specialist areas, and the Tenderer has to make nominations.

19.56 If Contractor is responsible anyway, why have a Collateral Warranty


with the Specialist?
If Specialist is considering terminating his contract with the Contractor, he has
to give notice to Employer, who has "step in" rights under which he may require
the Specialist to continue working directly for him under the Contract, under
Clauses 5.4 and 12.1. Also, if the Contractor becomes insolvent, the Employer
can pursue the Specialist under his Collateral Warranty. This may provide him
with rights of recovery additional to those he would have if no contractual link
was in place and he was forced to proceed in the tort of negligence only. If the
Contractor becomes insolvent, and the Employer wishes to retain the Specialist,
he could novate that Specialist to a new Contractor employed to finish the
works.

19.57 Does something done by a Specialist have to comply with Works


Requirement to be fit for purpose? If for example, there’s a piece of
work which fulfils its purpose, but supporting paperwork required in
Works Requirements is not complete?
This would depend on the terms of the Contractor’s sub-contract with the
Specialist. However the terms of this document are most unlikely to be less
stringent than the Contractor’s Contract with the Employer and the provisions
of this Contract will of course, include the Works Requirements.

19.58 Does a Specialist have to be named in the Contract?


No, but if an entity is doing design, it is a Specialist. Normally a Specialist is
named in the Works Requirements, or in the Works Proposals, and in the case
of substitution, then the substitute Specialist becomes part of the Works
Proposals.

Department of Finance Page 265


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.59 What form of contract would be used with a Novated Specialist?


Effectively the same form as main form (or other back to back form), but with
some differences between selections in Schedule Part 1. Whichever form of
Contract is used by the Employer, it would go straight across to the Main
Contract, unaltered.

Novation in this manner would be exceptional, rather than the norm. The
Employer, in preparing his contract with the Specialist to be novated, would
research the market to determine what minimum amendments to the standard
form might have to be made to attract interest from the Specialist market.
Having got unqualified tender responses, he then concludes his contract with the
Specialist. The Main Contractor is instructed that he must accept this novation,
in the Main Contract on the standard forms of contract without amendment. He
must then take a view on whatever risk premium he needs to neutralise the
effect to him of any special terms in the novated contract, so that he fully
addresses this in his own price.

19.60 Is it possible to novate the Specialists as a mechanism to shoehorn


Nominated Subcontractors into these Contracts?
Novation is a non preferred form of procuring Specialists. The Employer does
not need to use this mechanism to achieve the benefits of nomination without its
problems.

QUESTIONS ON COMPLETION OF THE SCHEDULES

19.61 "Date" for Substantial Completion. Does it have to be a real date?


Not necessarily. It could be either a fixed date or as is more likely, as a duration
from the date of the Letter of Acceptance.

19.62 The risk described in Part K No 8 of Schedule Part 1 uses the term
"Employers personnel". This could potentially mean Planning
Officers for a Local Authority. If they "interfere" in defence of a
planning permission or statutory duty, is this a compensation event?
There could conceivably be an argument that officers of a Local Authority not
connected with the project in question did interfere with the Contractor.
However, it is most unlikely that this would occur in such away as to give rise to
a claim. The inclusion of a Planning Permission within the general scope of the
term "Consent" creates an obligation on the Contractor to comply with this
consent. Other legislation, that the Employer may have a duty to check
compliance upon, is also included under "Law". If the Employer intervenes in his
capacity as designated enforcement body in relation to a statutory obligation, he
would be entitled to do so and there would be no entitlement to compensation
arising from this.

Department of Finance Page 266


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.63 The definition of unforeseeable includes the phrase "having inspected


the site and surroundings" What if a landowner prevents access to the
site at the time the tenderer wishes to examine it?
This is a risk which would emerge at the Clients’ own workshop on risk, and the
Client would have to consider the need to arrive at a point of closure on all his
contract planning before going to tender. If the land has been acquired, the
Client has legal rights to prevent such action by owners of adjacent lands etc.
which he should enforce. If such inspection by tenderers is frustrated as
described, then the Client should review his risk allocation selections during the
tender period, and decide if, given all the information provided to tenderers, it
remains value for money to allocate risk as he proposes to do.

19.64 With Subsoil Investigation contracts, the Contracting Authority often


cannot guarantee the factual accuracy of the SI Report and, if it
included in the Works Requirements, is there therefore relief under
Schedule Part 1 Section K Risk 5 for "factual error in works
requirements"?
Contracting Authorities should carefully review their management and
supervision of subsoil investigation contracts to ensure that SI Contractors are
held to their responsibilities under their contracts to ensure their reports are
factually correct. If the SI Report is included in the Works Requirements, then
factual error (and this must be outside the question of error of interpretation)
will have implications under Risk 5. Presumably, if such an issue did arise and
caused loss to the Employer, he would have an entitlement to pursue the site
investigation contractor pursuant to that contract.

19.65 Does the figure entered under the second threshold on the
programme contingency in Schedule Part 1 have to be a cumulative
figure with respect to the first threshold?
No, the second threshold is not cumulative, it stands as a selection in itself
without regard to the numerical value selected for the first threshold.

Department of Finance Page 267


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

QUESTIONS ON ENABLING CONTRACTS AND INVESTIGATION


CONTRACTS

19.66 If one has an archaeological report, and it has described findings in


one area of the site, and it recommends, and the Employer provides,
a supervising archaeologist for elsewhere, in what sense are later
artefacts that may be found ever "foreseeable" or " unforeseeable"?
If they are deemed "foreseeable" by the Employer, in defence of a
claim, how can he resist the import of a question as to why, if they
are now "foreseeable", did not the original archaeological
investigation extend to unearthing them?
If an archaeological report such as the one described is made known to the
Contractor when tendering it would be very difficult for him to argue that he
could not have foreseen other such finds on the Site when the definition of
"unforeseeable" is taken into account. It is of course always possible that in such
a case the Contractor might say that the report indicated clearly that no other
finds existed, but such an argument would depend on the actual circumstances
prevailing at the time and the wording of the report itself.

GENERAL QUESTIONS

19.67 On the scope of coverage of these contracts in the Public Sector,


Circular 33/06 indicates exemptions apply where the agency is not a
government department, or body under its aegis, and where more
than 50% of the funding comes from a source other than the
exchequer. In relation to this funding rule, does it include instances
where the Client makes assets available, such as land for an
interchange or site?
If the land or similar asset has been provided as a quid pro quo, when it would
otherwise have been paid for from the capital budget, the value should be taken
into account in assessing whether the new forms of contract should apply.

19.68 Contractor puts forward an alternative model equivalent in safety


and suitability, but its key dimensions are different and its tying-in
characteristics with other services are different, how is
consequential change cost following model selection to be dealt
with?
In Employer Design, as part of risk assessment during detailed design, the
potential constraints in building works or M&E Services, of making particular
selections of major plant items, need to be examined. Cost effective design
provision, by way of adequate dimensioning of rooms, sizing of ducting for
connecting services etc., in order to permit a range of plant item choices to
remain open, and to accommodate the most advantageous plant item choice, is
encouraged. This could be accommodated under a " Shell and Fit-out " basis,

Department of Finance Page 268


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

where the main services are taken to a terminal point outside a civil/building
works shell, and the shell is sized to accept the range of plant items likely to be
offered, and a phased handover allows the item to be installed and
commissioned on its own programme. This will allow the plant item to be
incorporated, without expensive consequential effects influencing other areas of
the contract, and without extra cost arising through Change Orders.

19.69 It is noted that Standard Methods of Measurement are amended by


the Department of Finance in the appendices to align them with the
fixed price lump sum concept. Are the NRA rules of measurement
also to be amended in the same way?
There will be changes to align the NRA Method of Measurement to the
principles in the new contracts.

19.70 Insurance thresholds look the same in both the Minor Works and
the other Forms of Contract. Is this intended by the insurance
expertise advising on Conditions of Contract development?
Yes.

19.71 Do all of the Contract Document features apply to Minor Works?


Mostly yes, the Guidance Note has a comparison table at Appendix A. The most
notable difference is the single threshold for the Programme Contingency in the
Minor Works form.

19.72 Does the €5m limit on the Minor Works Contract include VAT?
Yes, it is VAT inclusive.

19.73 Is it necessary to have a Performance Bond for a small contract, for


example Portacabins valued at say €600k, involving no more than
three certificates over 4 months?
Yes. While the sum in a given contract may appear small, the problem of several
contracts for the same Client with one contractor may aggregate the exposure
to a much larger figure.

19.74 Do Liquidated Damages have to be related to a loss or if not, does


there have to be a bonus?
Yes they are related to a loss, in that the LDs must be a pre-estimate of loss and
the pre-estimate must be genuine, but there’s no implied bonus. Penalties
(monetary deductions greater than and unrelated to any pre-estimated loss) are
unenforceable and the presence of a bonus provision will not act as a saver. If
there was a bonus, it might give an indication to a court of the importance of
programme to the client.

Department of Finance Page 269


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.75 What does Risk 12 in Section K of Schedule Part 1 refer to, in the
context of Clause 3.2?
If the Works suffer damage due to matters which are at the Contractor’s risk
under sub-clause 3.2 before Substantial Completion the Contractor is entitled to
an extension of time for completion (subject to clauses 9 and 10) but the event
is not a compensation event and he is not entitled to an adjustment of the
Contract Sum.

19.76 How far out do access routes go? If vehicle is taxed and licensed, is
he not entitled to use all roads?
Yes he is. However as between himself and the Employer, he is responsible for
ensuring that he can gain access via all intended access routes. He is also obliged
to take reasonable steps to see that the Site traffic obeys the law and does not
cause nuisance.

19.77 What is the difference between "part" and "Section"


Section has a definition in terms of the contract, but a part can be any part of
the works.

19.78 Can contracts with seasonal constraints be procured out of season


and novated into main contract?
You have to signal this intent in the Works Requirements.

QUESTIONS ON CLAUSES OF THE CONTRACT

19.79 Contract refers to relevant statutory provisions in Clause 2.5. With


respect to possible law changes, is a "catch all" not required?
Refer to "Legal requirement" definition [Clause 2.2] and to the interpretation
provision at sub-clause 1.2.2 (6) where it is stated that references to any Law
includes any amendments and replacements. It covers the matter of the
question.

19.80 Clause 3.3.1 What is meant by "profit". Why would reinstatement


value for building include "profit"?
The Contractor may have to re-build the Works if for instance they are burned
down due to no fault of his, simply because he has responsibility for the Works
and for their ultimate completion. It is regarded as reasonable that the
Contractor in carrying out such re-building work should be entitled to his
reasonable profit as otherwise he would effectively be carrying out what could
be a complete reconstruction for nothing.

Department of Finance Page 270


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.81 Is it necessary to have all the reporting requirements and


programming requirements in Clause 4 on the Minor Works Form?
The reporting requirements as contained in the full contract forms are not
contained in the Minor Works form, which has a far simpler provision in this
regard. In the full contract forms the provisions may be relaxed by the Works
Requirements or by the ER. It is in any event not a bad thing to have clear
evidence that the contract is being managed properly, regardless of its size.

19.82 With respect to Article 4 of the Agreement; Is there any significance


to be read into the phrase "initial Contract Sum", and the use of
"initial" as a possible qualifying adjective? Could the use of a different
phrase earlier in the paragraph be construed as referring to two
different sums?
The word "initial" is merely explanatory and is intended to indicate the Contract
Sum before it becomes subject to any adjustment in accordance with contract.

19.83 Is there a potential in a Claim for a Contractor to invoke Clause 4.1


on co-operation? Can a Contractor seek ER’s records in support of
his claim, perhaps arguing for these in an effort to minimise delay?.
He is obliged to keep his own records. Clause 4.1 can’t be used to fish for
information and co-operation would not extend to an obligation by the ER to
compensate for the Contractors failure to supply and keep his own records.

19.84 Clause 4.3.2 – Where authority limitations are stated in Contract,


these are limitations between the ER and Employer in the
Conditions of Engagement contract? What is their standing in the
Construction Contract Schedule 1?
Their standing is simply to make the Contractor aware of the limitations agreed
between the Employer and the ER in his Conditions of Engagement. This will
avoid any possible claim by the Contractor that he was entitled to assume that
the ER had all of the powers normally associated with his role and without any
restrictions that might result in the Employer’s permission being sought for
decisions.

19.85 What is the breadth of scope of "physically impossible" or "contrary


to Legal Requirements", Clause 4.5.4? Is it the ER’s subjective view
of an H&S issue? Is this potentially exploitable under H&S issues?
This might ultimately have to be defined in Arbitration or by a Court in any
particular case. "Physically impossible" doesn’t just relate to where the task in
question simply cannot be done in any circumstances, It may for instance be
possible with unlimited money. If however, it becomes so unfeasible in that
extremely large sums of money has to be thrown at it, it may be regarded as
being effectively impossible. It should be noted that Clause 2.4.4 indicates that

Department of Finance Page 271


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

compliance with the instruction of a PSDP or PSCS does not give rise to an
increase in the cost of the contract, or an extension of time.

19.86 Clause 4.8.1 – Any Value Engineering proposal cannot increase the
Contract Sum. Does this preclude Client from accepting a beneficial
Whole Life Cost proposal, which increased the Contract Sum?
Could this be handled by Change Order?
Where the ITT permits variants, and subject to any conditions attaching to such
variants being met, it is possible at Tender Stage to accept variants which have a
Whole Life Cost advantage. Once the Contract is signed, it is intended that value
engineering proposals ought to be confined to reductions in the contract cost,
or expediting the date for Substantial Completion.

19.87 Under Clause 4.8.2, is it not advisable to have PSCS/PSDP certify that
no problem exists as part of considering a value engineering
proposal.
It would certainly be advisable to have the PSCS/PSDP involved so that he can be
aware of what is proposed, and so that he can agree that the change does not
compromise the position on safety, or introduce any issues outside the agreed
value engineering proposal. Clause 2.4.4 is now also relevant to this issue.

19.88 Where is Employers right to object to a programme? It is a fait


accompli on presentation?
In Clause 4.7, there is a right for the ER to object in writing to any document or
proposed course of action submitted by the Contractor as a requirement of the
contract. This would include a programme. If the Employer has specific
requirements or restrictions, they should be included in the Works
Requirements and any programme submitted should highlight compliance with
them.

19.89 Does Clause 4.9.2 and 4.9.3 effectively permit Contractor to revise
dates for Substantial Completion, or at least set up acceleration
issues?
They require him to revise his programme i.e. his intended date for completing
the Works when this becomes necessary because of Delay Events etc. They do
no more than provide information to the ER and Employer in relation to the
state of progress of the Works at any given point in time. If the Contractor
seeks to use the programme to support claims he will have to formally make the
claim under Clause 10 and evidence it etc.

Department of Finance Page 272


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.90 If the Contractor is potentially going to be paid Labour PVC after the
Base Date, why is there no provision to check that people are being
paid as required under PV1 or PV2? Clause 5.3.3.A specifically
excludes checking this point under that Clause?
Model Form 15 provides that the contractor must certify he is paying according
to legal obligations. He has this obligation in any case. The PVC provision says
what contract relief he will get, and this is a separate issue from his obligation to
pay Social Partnership rates, which he is obliged to do.

The PVC provision is a risk valuation and compensation factor, the obligation to
pay under Clause 5.3.3(a) is separate and checking compliance with this latter
obligation, which is all that the Clause can require.

19.91 Under Clause 5.3 is the Contractor obliged to indemnify the


Employer against costs incurred by non-compliance?
Clause 5.3.8 says yes, and if the Employer demands payment, it is deductible,
ultimately on the Employers Representative decision.

19.92 Is there an obligation on Client to ensure that employees are paid up


members of Construction Workers Pension Scheme?. Should it be
in Model Form 15?
If a Contractor from abroad is about to start, how can he provide this evidence
in response to a Letter of Intent? He can’t do it, therefore, you can’t insist on it.
Clause 5.3 does insist he does so in future under the Contract. A Certificate of
Intent to do this is permissible, but seeking proof of past compliance is
discriminatory. Compliance with the construction workers pension provisions
in a Registered Employment Agreement is what is required during the Contract.

19.93 Specialists Clause 5.4 – Clause 5.4.6 appears to give much greater
latitude to offer replacements and effectively negates Clause 5.4.5?
Clause 5.4.5 describes circumstances where a Specialist is not to be continued,
and Clause 5.4.6 is intended to show how a replacement is to be managed when
5.4.5 is used.

19.94 Clause 9.1.2 Before Start Date, does the Employer need sight of Tax
Clearance Cert, etc. Why is this left out of items listed in the Sub-
Clause?
These can go into the Letter of Intent under the indicated "catch all" clause at
the end.

Department of Finance Page 273


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.95 Clause 9.1.2 – If within 20 days between Start Date and Letter of
Acceptance, he fails to provide any of the items listed, what is the
position?.
If he doesn’t provide the items, he’s in breach of contract. "Shall" under Clause
9.1.2 is quite strict. The Contract entitles the Employer to terminate the
Contractor’s obligation to complete if he does not remedy the breach within 14
days after receiving a direction to do so.

19.96 Clause 10.5 Determination by ER. If he doesn’t respond within time


for response, and Contractor has complied with notice provisions, is
Claim accepted by default?
No – technically the Employer would be in breach of contract but it is unlikely
there would be any loss. The determination would issue late although it might
be the subject of further comment in any dispute resolution process if it arose.

19.97 Insurance - Does Clause 10.9 give any comfort to employer who
discovers that PI has lapsed and he wishes to insure himself and
recover that cost?
It might possibly although such defects are often latent and arise after the
Contractor has left the Site. The question to ask is what is your real sanction in
this circumstance? If he’s a repeat customer of a repeat client, one might
recognise that he is likely to be in business and renewing PI policy (Although any
renewal is most unlikely to provide retroactive cover). Remember a PI policy is
primarily to protect the insured. (This contract does have a right of offset
against other contracts with the same Employer).

19.98 When would Employer submit a Claim, if he wants to recover


money for work not done, does he have to use Clause 10.9?
He should certainly make the claim under Clause 10.9 and give the appropriate
notice. If the omission only came to light after the Final Certificate he could still
pursue the Contractor under the Contract.

19.99 Clause 10.9.3(2) – Is the Employer potentially doing the calculation


related to claims here? The phrase "any contract" could also mean
this contract, not necessarily "any other contract".
The Employer would have to do the calculation of the amount due under
another contract. The phrase "under any contract" with a small "c" would not
be construed as the Contract with a capital "C"

Department of Finance Page 274


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.100 Are unforeseen services within a building, and not in the ground,
compensation events in Clause 10.10.1.3? of Minor Works
contract?
No they are not Compensation Events as listed in the Schedule part 1K (item
20) as it refers specifically to such services being in the ground. Accordingly
Clause 10.10.1.3 does not apply to them (as it only applies to Compensation
Events).

19.101 Is there provision for milestone payments in the DB Form of


Contract?
Not strictly at present, but Part L could reference milestones in accordance with
the Pricing Document, and milestone payments can be identified in the Pricing
Document. Clause 11 as drafted would appear to be capable of accommodating
this.

19.102 Clause 11.1.1.2 "upon issue of Certificate of Substantial Completion


of Works", does (a), (b), (c), (d), not follow from that? Should not
(2)(a)(b)(c) and (d) relate to (1) also relate to Interim Payments.
Note "at each of the following times".
Yes – it is clear from the wording as set out above that the statement showing
the matters at (1)–(4) is required at both interim statements and at Substantial
Completion. There is no time extension for issues arising in an Interim
Certificate. If in doubt, they would not be paid until the following certificate.

19.103 The Payment deadline under 11.1.4, taken with the Contractors’
powers of suspension under Clause 12.3 and the obligation to check
that payment on any application is properly due, all potentially
create a highly condensed sequence in time?
The provision of an interim statement starts a time sequence. The ER has to
examine the application to comply with his own implied obligations to test it
against Clause 11.4, and within 10 working days give a certificate. The Employer
makes a payment within 15 working days of receipt of an invoice. It should be
recalled that working days are referenced rather than calendar days.

19.104 Has "adjudicate" as used in clause 13.1.2 changed the role of the
Conciliator?
No – the term "Adjudicate" here is merely used to indicate that the conciliator
is to be a competent person to fill that role.

Department of Finance Page 275


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.105 Employer Inspection of Payment records imposes very strict


obligations on Contractor and Specialists.
Other agencies have contracted qualified advisers and they will instruct that
service provider to inspect multiple sites on a sample basis for below threshold
projects.

19.106 Will Met Éireann provide in a timely fashion the statistics needed for
the weather event? Is the description of the weather event precise
enough?
The 10 Year Return Period statistic can be calculated by standard hydrological
means from the annual maxima provided as raw data, either by Met Éireann, or
by the user.

19.107 What is the practical means of assessment of "Expenses unavoidably


incurred by Contractor?"
ER would have to assess this on submission by the contractor. No forensic
scrutiny of records is implied and you can’t trawl using other inspection powers
under the Contract. Presumably the Contractor would be happy to co-operate
on such a matter.

19.108 If you request a proposal, but do not proceed with it, can you pay
the Contractor to prepare the proposal?
No

19.109 Health & Safety – What happens with initial PSDP in a DB? Does
each tenderer have to have a PSDP in preparing his bid?
A similar question arises for the Employer in that the Employer’s experts
including the ER will be assessing the tenders and indeed may have initiated the
design process by an indicative design or Employer’s Requirements. It might
therefore be more appropriate that the Employer appoints initially and then
passes on that role to the Contractor upon his appointment.

19.110 What of a train of conciliators recommendations, with a total


amount of money deemed unacceptable by the Employer? The
clause as phrased appears to require that the Conciliator shall not
be an Arbitrator?
The provisions of the Contract would apply to each and every recommendation
of the conciliator. It is intended that he not act as an arbitrator in resolving the
dispute – thus, his role is to facilitate the parties in structured negotiations
leading hopefully to an amicable resolution of the matters at issue. It is also
intended that he should not be "the arbitrator" under this Contract.

Department of Finance Page 276


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.111 How do you know when you are in dispute?


If either party notifies to this effect, but there are cases where occurrence of
dispute is itself a matter for decision. However the problem rarely arises as
parties generally know when a dispute has arisen.

19.112 If appointing body is used, will it be their rules?


Conciliation rules are in the Contract and the Dept. of Finance have developed
Arbitration Rules, which apply.

19.113 Definition of "Site" very wide, so how does it affect "unfixed works
items".
The definition of Site is clear enough so as to avoid confusion in most cases as to
whether Works Items are in fact on or off of the Site.

19.114 The Conciliators’ Award Bond, where does its cost lie if Arbitrator
finds the conciliation award was in fact correct?
It is likely that it will have to be borne by the party providing the bond.
However, the party has a choice as to whether he wishes to provide the bond
or not. It is likely that the choice would be to provide the bond in view of the
fact that he is getting payment. It might possibly be claimable in the arbitration
proceedings in the event that a final award had not been made at the relevant
stage.

19.115 Can you insist on having the Safety File before issuing a Certificate of
Substantial Completion?
It is the PSDP who is responsible for the Safety File under the new Regulations,
but if the Contractor has not handed over essential material for the PSDP to
include in the Safety File, it would be a valid reason for giving reasons to
withhold the Certificate. Otherwise, the Employer would be in control of an
As-Constructed Asset for which he didn’t have a Safety File.

19.116 Hyperinflation – Is there an entitlement for hyperinflation for


subsequent months after the hyperinflation month?
No, there is no continuing relief if the index stays high.

19.117 Should there be a requirement to nominate a Temporary Works


Designer as a Specialist in order to clarify role of PSDP related to
these? Can this be included in the Works Requirements?
This is a matter for Contracting Authorities to decide.

Department of Finance Page 277


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.118 Why no sectional completion in the Minor Works Form? Very many
minor projects involve extensions, followed by decanting to the new
area, with refurbishment of the old.
This has been taken under consideration. There is no impediment to inclusion
of a programming constraint in the Works Requirements to cover this situation.

19.119 Is it necessary to include the Model Form of Parent Company


Guarantee in Pre-Qual document as an indication of the guarantee
which will be required prior to any Contract?
It is worthwhile including the Model form as an indication of the requirement if a
Parent Company Guarantee is relied upon, and in general references to "Model
forms" should be clarified as referring to the Department of Finance Model
Forms.

19.120 With respect to Unfixed Work Items in Interim Payments, and


Clause 11.2. Can there be a formal Vesting Certificate drafted for
use by the Contractor?
This has been taken under consideration.

19.121 In relation to Asbestos, what precisely is the guidance on it?


Delete the exclusion if you suspect you may encounter it. This is so that
insurance for asbestos is required. As "ordinary" contractors will normally not
deal with asbestos and will not have insurance cover for it, the Contract is likely
to use a Specialist who will be qualified to handle it. However as the Contract
stands – the Contractor will have to provide insurance cover.

19.122 Are we looking for Contract-specific insurance now if the parties


have to be co-insured?
The practical implication is that there will be a schedule of co-insured parties
attaching to the Contractors insurances and changing from time to time.

19.123 There’s a different Base Date for PV1 than PV2, what is the
explanation?
PV1.1.1(a) p76 Base Date = 31st month after Contract Date
PV2 Appendix No. 1 p82(d) Base date = 37th calendar month after
Designated date.

Under PV1 if you sign up, and you take longer than 6 months to get the contract
signed, no extra disadvantage occurs to the Employer. Same effect really, but
some disadvantage to Employer in PV2, in that he has 36 months from the
Designated Date, so that slippage in signing up eats into his fixed price period.
Guidance Note Section 2.5.2 explains the position.

Department of Finance Page 278


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.124 Does the definition of "Site" potentially designate the Contractors


fabrication yard as part of the Site, thereby essentially neutralising
the provisions governing payment for materials fabricated but not
fixed in the Works?
The definition would not include the fabrication yards unless they were stated to
be so in the Contract as a place where the Works are to be executed or are
identified as the Site in the Works Requirements.

19.125 If in law you hold money that might belong to a subcontractor at


some remove, is there a vulnerability to suit?
It is possible but the Employer is only likely to withhold such money from the
Contractor because the Contractor has not paid it. Ultimately the Employer
could end up holding money owed to another entity but presumably the
intention would be to pay it over subject to satisfactory proof etc.

19.126 Residual Risk in a Defects Period? What if Employer puts a high


value on the residual risk and is it possible the monies withheld
might exceed value for remedying the defect?
If you cannot extend Defects period on an item that was repaired, and you
withhold money, and you methodically set out how you calculate your exposure,
it is more difficult to challenge it as a penalty. The more intangible the value
elements, the less defensible that would be.

19.127 Collateral warranty, when the Specialist is a designer, is there a


potential tension arising from the fitness for purpose obligation of
the Contractor?
The obligation of reasonable skill and care is what is stated in the Conditions of
Engagement and it would be unfair of Contracting Authority to attempt to
impose any higher standard via collateral warranty. There is a tension, the
collateral warranty highlights it. Where an Employer has engaged a Consultant,
under the COE and novated him, under the COE its liability is "reasonable skill
and care".

19.128 Could it happen that, in the Collateral Warranty, the access to the
Specialist is not as comprehensive as Employer assumed, because
contract between Contractor and Specialist may not cover what
Employer thought it did?
The plan is that the Employer will not concern itself with the contract between
the Contractor and the Specialist as the Contractor is fully liable for the
Specialist’s work (including design).

Department of Finance Page 279


National Public Procurement Policy Unit
Public Works Construction Contracts
Training Manual

19.129 The limitations on the ER will be known to Contractor, if the ER


exceeds them, is the Contractor protected? If the ER is replaced
and Employer acts in that role, can the position be free of bias?
Contractor has protection of the Contract and does not need to look behind ER
authority limits.

19.130 In absence of Framework Agreements, what would be the lowest


value for use in the Minor Works?
There is no lower limit it is €5m down to zero.

Department of Finance Page 280


National Public Procurement Policy Unit

You might also like