Building Works at Hougang Town Daily Site Record: Activities Location Description of Works Remarks

1) Pile cap works are in progress, with 10 out of 57 total pile caps completed so far, representing 17.54% completion. 2) Activities on site today included manually trimming and hacking 7 MSCP piles, rebar checking on three column stumps prior to casting, and casting three column stumps and two pile caps. 3) Overall progress includes 10 pile caps cast out of 57 total planned, representing 17.54% completion, along with three column stumps already cast.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
42 views1 page

Building Works at Hougang Town Daily Site Record: Activities Location Description of Works Remarks

1) Pile cap works are in progress, with 10 out of 57 total pile caps completed so far, representing 17.54% completion. 2) Activities on site today included manually trimming and hacking 7 MSCP piles, rebar checking on three column stumps prior to casting, and casting three column stumps and two pile caps. 3) Overall progress includes 10 pile caps cast out of 57 total planned, representing 17.54% completion, along with three column stumps already cast.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Tuesday, March 31, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks

PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 10 nos.
total Number OF Pile Caps 57 nos. 17.54%

MSCP PILES 100.00%


100.00%
Structural work

CONTIGUOUS Bored Pile ( CBP )


GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 48.23%

SITE VIEW
Architectural
work
M & E Work

WELDING OF BRACKETS AT SOLDIER PILES 3CBP MANUALY TRIMMED AND HACKED AT CC


TO INSTALL HORIZONTAL WALER SUPOORTS SIDE
AT ERSS HOUGANG ST.21 SIDE NEAR ECM
TANK

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 SMALL BREAKER 1
Site engineer 1 Safety office 1 New excavator 1
RTO 1 REBAR WORK 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 3 VIBRO hammer 1
Coordinator 1 gen Worker 4 crawler crane 1
G Worker 7 FORMWORK 4 HYDRAULIC BREAKER 1
AIR RECEIVER 3
Weather

FAIR

Manpower
8:30 17:30 TOTAL : 16 TOTAL : 17 TOTAL : 0 TOTAL : 0 33 TODAY 7 MSCP PILES MANUALLY TRIMMED REBAR CHECKED ON THREE COLUMN STUMP
AND HACKED PRIOR TO CASTING

Housekeeping work inprogress,

WELDING OF BRACKETS AT SOLDIER PILES TO INSTALL HORIZONTAL WALER


SUPOORTS AT ERSS HOUGANG ST.21 SIDE NEAR ECM TANK

3CBP MANUALY TRIMMED AND HACKED AT CC SIDE

TODAY 7 MSCP PILES MANUALLY TRIMMED AND HACKED

REMARKS :
REBAR CHECKED ON THREE COLUMN STUMP PRIOR TO CASTING

3 COLUMN STUMP CAST 3 COLUMN STUMP CAST CAST P27

CAST P27

TWO PILE CAPS CAST TODAY P 26 AND AT P27

TO DATE 10 PILE CAPS CAST OUT OF 57 PILE CAPS AT 17.54% COMPLETED AND 3
COLUMN STUMP ALREADY CAST

noise level reading: No record of Noise Exceeded

TWO PILE CAPS CAST TODAY P 26 AND AT TO DATE 10 PILE CAPS CAST OUT OF 57 PILE
P27 CAPS AT 17.54% COMPLETED AND 3 COLUMN
STUMP ALREADY CAST