BUILDING WORKS AT HOUGANG TOWN
DAILY SITE RECORD Tuesday, March 31, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 10 nos.
total Number OF Pile Caps 57 nos. 17.54%
MSCP PILES 100.00%
100.00%
Structural work
CONTIGUOUS Bored Pile ( CBP )
GROUT PILES 100.00%
TOWER CRANE PILE CAP CAST 100.00%
CAPPING BEAMS CAST TO DATE 48.23%
SITE VIEW
Architectural
work
M & E Work
WELDING OF BRACKETS AT SOLDIER PILES 3CBP MANUALY TRIMMED AND HACKED AT CC
TO INSTALL HORIZONTAL WALER SUPOORTS SIDE
AT ERSS HOUGANG ST.21 SIDE NEAR ECM
TANK
MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY
ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 SMALL BREAKER 1
Site engineer 1 Safety office 1 New excavator 1
RTO 1 REBAR WORK 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 3 VIBRO hammer 1
Coordinator 1 gen Worker 4 crawler crane 1
G Worker 7 FORMWORK 4 HYDRAULIC BREAKER 1
AIR RECEIVER 3
Weather
FAIR
Manpower
8:30 17:30 TOTAL : 16 TOTAL : 17 TOTAL : 0 TOTAL : 0 33 TODAY 7 MSCP PILES MANUALLY TRIMMED REBAR CHECKED ON THREE COLUMN STUMP
AND HACKED PRIOR TO CASTING
Housekeeping work inprogress,
WELDING OF BRACKETS AT SOLDIER PILES TO INSTALL HORIZONTAL WALER
SUPOORTS AT ERSS HOUGANG ST.21 SIDE NEAR ECM TANK
3CBP MANUALY TRIMMED AND HACKED AT CC SIDE
TODAY 7 MSCP PILES MANUALLY TRIMMED AND HACKED
REMARKS :
REBAR CHECKED ON THREE COLUMN STUMP PRIOR TO CASTING
3 COLUMN STUMP CAST 3 COLUMN STUMP CAST CAST P27
CAST P27
TWO PILE CAPS CAST TODAY P 26 AND AT P27
TO DATE 10 PILE CAPS CAST OUT OF 57 PILE CAPS AT 17.54% COMPLETED AND 3
COLUMN STUMP ALREADY CAST
noise level reading: No record of Noise Exceeded
TWO PILE CAPS CAST TODAY P 26 AND AT TO DATE 10 PILE CAPS CAST OUT OF 57 PILE
P27 CAPS AT 17.54% COMPLETED AND 3 COLUMN
STUMP ALREADY CAST