BUILDING WORKS AT HOUGANG TOWN
DAILY SITE RECORD Thursday, March 19, 2020 DAILY SITE PHOTO
Activities Location Description of works Remarks
PILE CAP STATUS
Pil e CAP works in progress.
total completed to date: 2 nos.
total Number OF Pile Caps 57 nos. 3.51%
MSCP PILES 100.00%
Structural work
CONTIGUOUS Bored Pile ( CBP ) 100.00%
GROUT PILES
EXCAVATION TO PLATFORM LEVEL IN
total completed to date: 114 nos. PROGRESS
Total number of GROUT Piles 141 nos. 80.85%
14 PILE GROUT Today
Architectural
work
M & E Work
14 GROUT PILES DONE TODAY DRIVING SOLDIER PILES FOR ERSS WORKS
MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY
ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator BIG BREAKER 1
Site engineer 1 Safety office 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 grout machine 1
Weather
FAIR
Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 PILE CAP P40 REBAR INSTALLATION IN PILE CAP P41 REBAR INSTALLATION IN
PROGRESS PROGRESS
Housekeeping work inprogress,
14 GROUT PILES DONE TODAY
DRIVING SOLDIER PILES FOR ERSS WORKS
REMARKS :
PILE CAP P40 REBAR INSTALLATION IN PROGRESS
PILE CAP P41 REBAR INSTALLATION IN PROGRESS
9CBP PILES HACKING DONE,5 HACKED USING BIG HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER, LEANCONCRETE DONE
2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
noise level reading: AT 10:25AM NOISE READING Exceeded, reading AT 91.6dB 9CBP PILES HACKING DONE,5 HACKED USING BIG 2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER,
LEANCONCRETE DONE