0% found this document useful (0 votes)
49 views1 page

Building Works at Hougang Town Daily Site Record: Thursday, March 19, 2020

Work at the Hougang Town building site on March 19th included 14 grout piles being completed. Pile cap works were ongoing, with 2 out of 57 total pile caps completed so far. Excavation to the platform level was also in progress. Other activities mentioned were rebar installation at pile caps P40 and P41, soldier pile driving for ERSS works, 9 CBP pile hacking, and a noise level reading exceeding 91.6dB.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views1 page

Building Works at Hougang Town Daily Site Record: Thursday, March 19, 2020

Work at the Hougang Town building site on March 19th included 14 grout piles being completed. Pile cap works were ongoing, with 2 out of 57 total pile caps completed so far. Excavation to the platform level was also in progress. Other activities mentioned were rebar installation at pile caps P40 and P41, soldier pile driving for ERSS works, 9 CBP pile hacking, and a noise level reading exceeding 91.6dB.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

BUILDING WORKS AT HOUGANG TOWN

DAILY SITE RECORD Thursday, March 19, 2020 DAILY SITE PHOTO

Activities Location Description of works Remarks

PILE CAP STATUS


Pil e CAP works in progress.
total completed to date: 2 nos.
total Number OF Pile Caps 57 nos. 3.51%

MSCP PILES 100.00%


Structural work

CONTIGUOUS Bored Pile ( CBP ) 100.00%

GROUT PILES
EXCAVATION TO PLATFORM LEVEL IN
total completed to date: 114 nos. PROGRESS
Total number of GROUT Piles 141 nos. 80.85%
14 PILE GROUT Today
Architectural
work
M & E Work

14 GROUT PILES DONE TODAY DRIVING SOLDIER PILES FOR ERSS WORKS

MAIN CON STRUCTURAL ARCHITECTURAL M&E MACHINERY


ATTENDANCE
P Manager 1 Supervisor Generator 2
Site Supervisor 3 Safety officer 1 Excavator 2
08:30 17:30 Safety officer 1 Pil Rig Operator BIG BREAKER 1
Site engineer 1 Safety office 1
RTO 1 Rigger Worker 4 MINI EXCAVATOR 1
REMARKS Administrator 1 hacking team 2 vibro hammer 1
Coordinator 1 gen Worker 4 NEW crawler crane 1
G Worker 7 grout machine 1

Weather

FAIR

Manpower
8:30 18:00 TOTAL : 16 TOTAL : 12 TOTAL : 0 TOTAL : 0 28 PILE CAP P40 REBAR INSTALLATION IN PILE CAP P41 REBAR INSTALLATION IN
PROGRESS PROGRESS

Housekeeping work inprogress,

14 GROUT PILES DONE TODAY

DRIVING SOLDIER PILES FOR ERSS WORKS

REMARKS :
PILE CAP P40 REBAR INSTALLATION IN PROGRESS

PILE CAP P41 REBAR INSTALLATION IN PROGRESS

9CBP PILES HACKING DONE,5 HACKED USING BIG HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER, LEANCONCRETE DONE
2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS

noise level reading: AT 10:25AM NOISE READING Exceeded, reading AT 91.6dB 9CBP PILES HACKING DONE,5 HACKED USING BIG 2 PILE CAPS CAST OUT OF 57 TOTAL PILE CAPS
HYDRAULIC MACHINE BREAKER PLUS 4 TRIMMING
MANUAL HACKING USING JACK HAMMER,
LEANCONCRETE DONE

You might also like