2-STOREY MULTIPURPOSE
BUILDING
PROJECT SUMMARY
Project Title: 2-Storey Multipurpose Building
Construction Type: New Building
Project Budget: 5 Million Pesos
Project Timeframe: 5 years
Project Objective:
To build a low-cost 2-storey multipurpose building with low maintenance cost
that can accommodate a sports program alongside the customary social and
arts pursuits.
BUILDING ACCOMMODATIONS
Outdoor: Second Floor:
– Small Parking Space – Office
– 2 Meeting Rooms / Discussion
Ground Floor: Rooms
– Basketball Court / Assembly Space with – Utility Room
Stage – Comfort Room
– Comfort Rooms / Dressing Rooms
– Storage Room
– Utility Room
MATERIAL COST
Item Description Material Cost Item Description Material Cost
A. Carpentry Materials D. Structural Materials …
Coco Lumber ₱ 8,400.00 I-Beams and Bolts ₱ 450,000.00
Ordinary Plywood ₱ 9,900.00 Steel Decks ₱ 70,000.00
Nails ₱ 600.00 Welding Rod ₱ 6,000.00
Ceiling Materials ₱ 15,000.00 E. Plumbing Materials …
B. Electrical Materials … Water Line & Sewer Line ₱ 50,000.00
Breakers ₱ 720.00 Urinal & Toilet ₱ 21,000.00
Lighting ₱ 5,000.00 Wash Basin ₱ 14,000.00
Wires ₱ 6,500.00 F. Roof Framing and Roofing ₱ 75,000.00
Switch ₱ 2,000.00 G. Ceiling Materials ₱ 20,000.00
Outlet ₱ 2,000.00 H. Doors and Windows ₱ 40,000.00
C. Masonry Materials … I. Finishing …
Concrete Cement ₱ 180,000.00 Tile Works Materials ₱ 45,000.00
Concrete Hollow Blocks ₱ 30,000.00 Painting Materials ₱ 35,000.00
Sand and Gravel ₱ 55,000.00 J. Automatic Sprinkler System ₱ 25,000.00
Rebars ₱ 50,000.00
Tie Wire 5,000.00 TOTAL: ₱ 1, 221, 120.00
LABOR COST
Job Description Salary per Month
Site Engineer (1) ₱ 30, 000.00
Foreman (1) ₱ 12, 500.00
Masons (3) ₱ 30, 000.00
Carpenters (2) ₱ 20, 000.00
Welders (3) ₱ 30, 000.00
Construction Labors (3) ₱ 22, 500.00
Steel Man (2) ₱ 20, 000.00
Equipment Operators (2) ₱ 20, 000.00
Painters (2) ₱ 20, 000.00
Roofer (2) ₱ 20, 000.00
TOTAL: ₱ 225, 000.00
• COMPUTATIONS
• COMPUTATIONS
• COMPUTATIONS
• TOTAL COST COMPUTATIONS
Overall Material Cost:
Overall Material Cost ₱ 1,940,606.40
Estimated Labor Cost (30%) ₱ 1,500,000.00
₱ 1,940,606.40
TOTAL COST: ₱ 3,440,606.40 Estimated Labor Cost:
30% of the Budget
=(₱ 5,000,000.00)(0.3)
₱ 1,500,000.00