0% found this document useful (0 votes)
491 views3 pages

Proposed Construction of One-Storey Masjid Cotabato City Bill of Materials

The document is a bill of materials outlining the estimated costs for concrete and rebar works for the proposed construction of a one-storey masjid in Cotabato City. It provides the quantities, unit costs, and total costs of materials needed for the concrete column footings, columns, beams, and rebar for the columns and beams. The estimated total cost for the concrete works is 26,950 Philippine pesos and the estimated total cost for the rebar works is 49,410 Philippine pesos.

Uploaded by

Nasroden Pagayao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
491 views3 pages

Proposed Construction of One-Storey Masjid Cotabato City Bill of Materials

The document is a bill of materials outlining the estimated costs for concrete and rebar works for the proposed construction of a one-storey masjid in Cotabato City. It provides the quantities, unit costs, and total costs of materials needed for the concrete column footings, columns, beams, and rebar for the columns and beams. The estimated total cost for the concrete works is 26,950 Philippine pesos and the estimated total cost for the rebar works is 49,410 Philippine pesos.

Uploaded by

Nasroden Pagayao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

PROJECT: PROPOSED CONSTRUCTION OF ONE-STOREY MASJID

LOCATION COTABATO CITY


OWNER:
SUBJECT: BILL OF MATERIALS

ITEM DESCRIPTION Quantity Unit Material Unit Cost Total

IV CONCRETE WORKS 7.57 cu.m.


4.1 COLUMN FOOTINGS 1.37 cu.m.
4.1.1 Cement 10.00 bags 250.00 2,500.00
4.1.2 Sand 1.00 cu.m. 600.00 600.00
4.1.3 Gravel 2.00 cu.m. 600.00 1,200.00
-
4.3 COLUMNS ( 0.25m X 0.25m) 3.50 cu.m.
4.3.1 Cement 32.00 bags 250.00 8,000.00
4.3.2 Sand 3.00 cu.m. 600.00 1,800.00
4.3.3 Gravel 5.00 cu.m. 600.00 3,000.00
-
4.4 BEAMS 2.70 cu.m.
4.4.1 Cement 25.00 bags 250.00 6,250.00
4.4.2 Sand 2.00 cu.m. 600.00 1,200.00
4.4.3 Gravel 4.00 cu.m. 600.00 2,400.00

SUB-TOTAL CONCRETE WORKS 26,950.00


VI REBAR WORKS -
6.1 COLUMN and FOOTING -
6.1.4 10 mm Ø RSB 88.00 pcs. 160.00 14,080.00
6.1.4 12 mm Ø RSB 56.00 pcs. 275.00 15,400.00
6.3.10 #16 GI Tie Wire 3.00 kgs 90.00 270.00
-
6.3 BEAMS - KGS -
6.3.2 10 mm Ø RSB 61.00 pcs. 160.00 9,760.00
6.3.3 12 mm Ø RSB 36.00 pcs. 200.00 7,200.00
6.3.10 #16 GI Tie Wire 30.00 kgs 90.00 2,700.00
-
-
-
footing: 0.098 1.372
coloumn: 0.25 3.5

beam: 2.7

ties/stirrups

476 523.6 87.26667

361 361 60.16667


CONRETE
unit no. of
volume/AREA members/LENGTH VOLUME
footing 0.363 9 3.267
COLUMN 1 0.8505 9 7.6545
COLUMN 2 0.1875 9 1.6875
BEAM 1 0.0875 40 3.5
BEAM 2 0.0875 10 0.875
BEAM 3 0.07 10 0.7
BEAM 4 0.06 2 0.12
ROOF BEAM 1 0.06 40 2.4
ROOF BEAM 2 0.0875 20 1.75
TIE BEAM 0.05 60 3
suspended slab 11.63 1 11.63
slab on ground 12.1 1 12.1
total

You might also like