RC Framed Multi Storey Cost Estimate Summary
Item Description Quantity Unit Rate (TTD) Amount (TTD)
1 Conc. for superstructure 1817.62 m3 $ 1,380.00 $ 2,508,315.60
2 Rebar for superstructure 319.33 Tonne $ 7,498.00 $ 2,394,336.34
3 Conc. for foundations 355.95 m3 $ 1,380.00 $ 491,211.00
4 Rebar for foundations 14.78 Tonne $ 7,498.00 $ 110,820.44
5 Formwork @ 25% materials $ 1,376,170.85
6 Decking pan 31639 ft $ 22.00 $ 696,058.00
7 Decking pan BRC 112 Nr. Rolls $ 449.00 $ 50,288.00
8 Blocks 108250 Nr. $ 4.50 $ 487,125.00
9 Bags of cement for blocks 660.19764706 Nr. $ 53.50 $ 35,320.57
10 Sand for blocks 58.455 m3 $ 200.00 $ 11,691.00
11 Gade slab BRC 15.0 Nr. Rolls $ 449.00 $ 6,735.00
Labour @ 65% of above $ 5,309,246.67
Total Structural $ 13,477,318.47
Total Services $ 6,738,659.23
Total Architectural $ 37,736,491.71
Total Struc,Arch.,Serv $ 57,952,469.41
Preliminaries @ 5% $ 2,897,623.47
Contingencies @15% $ 8,692,870.41
Construction Cost $ 69,542,963.30
Over Head & Profits @ 30% $ 20,862,888.99
Grand Total TOTAL $ 90,405,852.29
Total building sq footage= 66139 ft2
NOTES:-
1. Cost of land acquisition and external works not considered (pavement; drainage; ironmongery).
2. The cost of this earthquake-resistant RC Framed apartment building per sq ft total covered area is:
$TTD 1,366.91
TABLE: RC Framed Multi Storey Material List
Section Element Pieces Length Weight Weight Concrete Rebar Rebar
m kN Tonnes m3 % Tonnes
400x800 rc col Col's 408.00 1198.50 9036.93 906.96 383.57 0.53 203.29
300x700 rc bm Beam 567 2673.444 11593.981 1163.59 492.10 0.14 70.86
200x300 rc bm Beam 304 1301.084 1829.5599 183.62 77.66 0.14 11.18
300x500 rc bm Beam 126.00 449.74 1513.23 151.87 64.23 0.14 9.25
150 rc slab on deck Floor 6123m2 16229.411 1628.80 688.85 0.02 15.84
150 rc wall Wall 2620.08 262.95 111.21 0.08 8.90
Total Superstructure Concrete 42823.19 4297.79 1817.62 319.33
150 slab on grade Floor 2844.50 285.48 120.73
2.7x2.7X.5 Ftg. Floor 3006.07 301.69 127.59 0.06 7.66
1.8x1.8X.4 Ftg. Floor 122.15 12.26 5.18 0.06 0.31
400 Thk Pads Floor 590.06 59.22 25.04 0.06 1.50
3.0x3.0X.6 Ftg. Floor 508.96 51.08 21.60 0.06 1.30
300x500 rc gr bm Beam 93.00 420.07 1314.35 131.91 55.79 0.07 4.02
Total Foundation Concrete 8386.08 841.64 355.95 14.78
100 b/walls Wall 8660m2
Embodied Carbon
Material kWh/tonne kWh/m3 tonnes m3 Qty(kWh)
4" Blocks 1300 800 1006.725 1308742.5
Steel 13200 103000 334.11 4410252
Concrete 360 800 2173.57 1738856
Total= 7457850.5 kWh