Identifying Barriers in Lean Implementation in The Construction Industry
Identifying Barriers in Lean Implementation in The Construction Industry
ABSTRACT
With the rising attention on the topic of Lean construction and its benefits, more and more
companies aim to implement the Lean philosophy in their culture. Together with changing
the companies’ culture multiple challenges occur. Hence, it is of utmost importance to
identify factors, which lead to poor management in Lean construction activities. Therefore,
this paper intends to identify and categorize barriers leading to poor implementation of the
Lean philosophy. In this respect, a set of barrier groups comprising a total of twenty-seven
components were identified. A questionnaire was designed and administered to Lean
construction professionals in order to rank the importance level of the selected barriers.
The paper proposes that lack of ‘top management support’, ‘misperception about Lean
practices’, ‘lack of information sharing and integrated change control’ are the top three
barriers for Lean implementation. The findings of the study indicate that Lean
implementation might be conducted with higher efficiency and productivity by removing
the barriers for implementation. This study might guide Lean professionals to align their
strategies with Lean practices by knowing and recognizing the main barriers.
KEYWORDS
Lean construction, culture, collaboration, continuous improvement, barriers.
INTRODUCTION
Construction is a risky endeavor and it requires the application of well-set practices.
Bringing a new insight to construction industry, Lean construction appears as a new branch
of construction management (Ballard and Howell, 2004). Due to a lack of experience, Lean
construction projects are sometimes troublesome and challenging for contractors.
1
Assistant Professor, Dept. of Civil Eng., Gebze Technical University, Kocaeli, Turkey. Phone +90
5340540364, [email protected].
2
Research Fellow. Karlsruhe Institute of Technology (KIT), Institute of Technology and Management in
Construction, Gotthard-Franz-Str. 3 (Am Fasanengarten), Bldg. 50.31, D-76131 Karlsruhe, Germany.
Phone +49 (0) 721 608 45476, [email protected].
3
Research Fellow. Karlsruhe Institute of Technology (KIT), Institute of Technology and Management in
Construction, Gotthard-Franz-Str. 3 (Am Fasanengarten), Bldg. 50.31, D-76131 Karlsruhe, Germany.
Phone +49 (0) 721 608 45476, [email protected].
4
Professor. Karlsruhe Institute of Technology (KIT), Institute of Technology and Management in
Construction, Gotthard-Franz-Str. 3 (Am Fasanengarten), Bldg. 50.31, D-76131 Karlsruhe, Germany.
Phone +49 (0)721 608 42646, [email protected].
157
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
Meadows (2011) indicates that processes in the construction industry are more wasteful
than processes of any other industry. Hence, eliminating non-value adding activities is of
utmost importance in the construction industry to stay competitive. The Construction
Industry Institute (CII) reports that according to studies 57% of the construction work
results in waste (Aziz and Hafez, 2013; Lean Construction Institute, 2004). This
necessitates the effective implementation of strategies to minimize waste and promote
competitiveness (Porter, 1995).
Introducing Lean thinking to the construction industry is not only beneficiary for
practitioners but also for customers regarding the transparency and stability of the project.
Koskela (1992) considers Lean principles in the construction context and proposes methods
to manage construction projects accordingly (Koskela, 1992). Nevertheless, it is still
troublesome to accurately transfer Lean principles to construction projects and achieve an
efficient implementation by construction professionals. Moreover, most contractors are
reluctant to apply Lean principles since the implementation is perceived as expensive and
time consuming (Almanei et al. 2017; Okere 2017). Therefore, Lean implementation is
sometimes evaluated as a disadvantage for short term projects despite its advantages in
long-term. Hence, it might become difficult for contactors to recognize the benefits of Lean
practices.
To refute the idea that Lean construction principles are not beneficiary or only have
limited benefits for construction practitioners, a better understanding of Lean practices and
a clear definition of Lean implementation barriers is required. Thus, this study aims to
identify main barriers preventing construction practitioners from the benefits of Lean
practices. Additionally, the positive influence of an effective implementation of Lean
practices is outlined. In this respect, seven factor groups were identified comprising twenty-
seven components. The factor groups identified are namely the following: political,
economical, managerial, workforce, culture, communication, and technical. The study also
presents the results of a questionnaire administered to Lean professionals in the USA in
terms of ranking the identified barriers based on the order of importance.
RESEARCH METHOD
In the first step an in-depth literature review was conducted in order to identify barriers for
Lean implementation in construction. In the second step, an online survey was designed
and administered to the members of the Lean Construction Institute (LCI)
(https://www.leanconstruction.org/membership/members-sponsors/#Corporate%20
Members). The members were selected considering their level of expertise in practicing
Lean. A comprehensive list was generated after careful investigation of members’ expertise
and experience in Lean construction. Then, the survey was delivered online to come up
with a better response rate. The survey consisted of two sections: (1) general information
about the respondent, company, and project and (2) the barriers associated with Lean
implementation. After a brief overview of Lean Implementation in construction, findings
from literature review and the survey are presented in the following.
158
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Identifying Barriers in Lean Implementation in the Construction Industry
159
People, Culture and Change
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
Ayarkwa et al. (2012) studied the barriers existing in the Ghanaian construction industry
and listed “fragmented nature of the industry”, “extensive use of subcontractors”, “lack of
long-term relationship with subcontractors” as the top ranked barriers. Sarhan and Fox
(2013) identified “fragmentation and subcontracting”, “procurement and contracts”, and
“lack of adequate Lean awareness and understanding” as the key barriers in their study.
In this in-depth literature review, barriers of Lean implementation were identified and
a total of thirty-two barriers were developed. To come up with valid barriers, several pilot
studies were conducted. In these pilot studies, the barriers were discussed with three
university professors and four industry practitioners and some of the barriers were revised
to best reflect their corresponding factors. After careful consideration of barriers, some of
the barriers were either synthesized or removed where necessary. For example, lack of
information sharing and integrated change control were mostly listed as two separate
barriers in Okere’s (2017) study. However, these two barriers are strongly interrelated with
managing uncertainties and changes. Hence, the study evaluated these two as one barrier.
A similar approach was adopted for the remaining barriers. The barriers were carefully
determined considering most up-to-date data in construction projects. Moreover, barriers
were grouped with a systematic approach called PEST. With the PEST analysis,
influencing factors on an organization were systematically structured. PEST is an acronym
for ‘political’, ‘economical’, ‘socio-cultural’ and ‘technological’ (Steinmann and
Schreyögg 2006).
Based on this model and the literature study, twenty-seven barriers were identified for
Lean implementation. The factor groups and the respective barriers are shown in Figure 1.
These barriers are identified as the key barriers causing challenges in Lean implementation
in construction projects. As seen in Figure 1 most of the detected barriers can be found in
the socio-cultural area consisting of the managerial, cultural, communication and
workforce barriers. The definition of each barrier along with the evidence from literature
is presented in the following.
Political Barriers
Stringent requirements and approvals: Information flow and procedural documents might
take time and lead to deficiencies in Lean processes. This makes governmental
organizations hesitant about the benefits and applications of Lean practices. Hence,
stringent requirements and approvals might be a burden for governmental organizations
(Shang and Pheng 2014, Almanei et al. 2017).
Lack of knowledge in Lean: The Lean philosophy is still not yet entirely understood by
most of governmental authorities, so benefits are not conceived in turn. This might
negatively affect investment decisions in construction projects, where Lean practices are
planned to be applied (Sarhan and Fox 2013).
160
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Identifying Barriers in Lean Implementation in the Construction Industry
161
People, Culture and Change
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
Workforce Barriers
Problems in teamwork and diverging aims in Lean: Lack of coordination and
collaboration among team members might be observed when there are diverging aims
within the firm. This results in inefficient processes in Lean practices (Aziz and Hafez 2013,
Sarhan and Fox 2013, Shang and Pheng 2014, Jadhav et al. 2014).
Language problem for non-native speakers: Language is a barrier for most of the
construction workers. This makes e.g. some safety tips difficult to understand and results
in lower safety performance (Demirkesen and Arditi 2015). Educating construction
workers about language barriers and providing some tips might lead to enhanced Lean
performance. Thus, firms might develop ways to integrate non-native speakers in Lean
processes to overcome this barrier (Jadhav et al. 2014).
Employees’ resistance to Lean: Employees might resist to changes and this leads to
inefficient performance in Lean practices. Some lean tools such as poka yoke devices or
Kanban cards might be of interest to employees for the fact that they are not beware of
benefits of using these tools. Thus, resistance to change is a major barrier for firms aiming
to enhance Lean implementation performance (Aziz and Hafez 2013, Jadhav et al. 2014).
Stress and pressure in deadlines: Struggling with deadlines might create stress and
pressure for construction workers. This might lead to wrong or missing practices in Lean
(Aziz and Hafez 2013, Sarhan and Fox 2013, Howell et al. 2017).
Cultural Barriers
Resistance to change: Lean is a relatively new concept in the construction industry and
this makes Lean adoption lower than expected by the industry practitioners. This also leads
to lack of knowledge about the benefits of using Lean practices. Therefore, employees
develop resistance to change for the fact that they are either unfamiliar with the Lean tools
or its benefits. A company and project culture that is open for changes is required in order
to lead all employees in the Lean transformation process. The resistance to change stems
generally from the cultural background and is therefore listed as a major cultural barrier
(Kumar 2013, Sarhan and Fox 2013, Jadhav et al. 2014, Ogunbiyi 2014, Shang and Pheng
2014, Almanei 2017).
Diversity in adopting Lean culture: Diversity in cultural background generally leads to
different learning curves for differing groups. This leads to different levels of knowledge
about Lean practices. Some construction workers have a hard time to adopt a Lean culture
due to their diverse backgrounds and therefore they prefer to apply the conventional
working practices they are familiar with. Therefore, diversity might appear as a cultural
barrier for Lean implementation (Jadhav et al. 2014, Almanei et al. 2017).
Lack of long-term Lean philosophy: The adoption of the Lean philosophy is difficult for
industry practitioners due to the dynamic nature of the construction industry. Industry
practitioners mistrust the benefits that they will get by the use of Lean tools and this makes
Lean implementation rare due to challenges with time and budget (Ogunbiyi 2014, Shang
and Pheng 2014).
162
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Identifying Barriers in Lean Implementation in the Construction Industry
163
People, Culture and Change
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
Lean and perform more effectively in construction projects is needed. Hence, firms might
need to remove this barrier in order to experience higher rates of performance in Lean
projects (Salem et al. 2005, Kumar 2013, Sarhan and Fox 2013, Shang and Pheng 2014,
Jadhav et al. 2014, Ogunbiyi 2014).
Complexity in design: Designing for Lean and safe operations is more challenging than
traditional methods and this might lead to complexity in design, which makes design a
barrier for Lean projects (Aziz and Hafez 2013, Sarhan and Fox 2013). Nevertheless, it has
to be considered, that higher effort in design due to Lean practices results into stable
working processes on site since design and processes are accordingly aligned from the
beginning.
Inefficiency in Takt time planning: Multiple stakeholders and numerous interfaces might
lead to poor planning in terms of Takt time. This negates Lean activities for the project and
appears as a barrier for construction operations (Sundar et al. 2014).
Failure in operational excellence: Operational excellence is one of the objectives of Lean
practices. Failure in operational excellence is likely to yield deficiencies in Lean processes.
Therefore, it is considered as a technical barrier that firms need to address to better perform
in Lean implementation (Salem et al. 2005, Sarhan and Fox 2013).
Lack of knowledge in Last Planner implementation: Last planner is a critical tool of Lean
construction and failure to apply Last planner leads to unsuccessful operations in Lean
implementation. Thus, it is listed as one of the technical barriers that firms need to consider
aiming to achieve higher performance in Lean implementation (Aziz and Hafez 2013,
Salem et al. 2005).
164
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Identifying Barriers in Lean Implementation in the Construction Industry
Table 2 presents the results for the ranking of barriers for Lean implementation by Lean
practitioners. According to Table 2, it is shown that “Lack of top management support”
was rated as the top barrier (mean: 4.61). Secondly, “Misperception about Lean practices”
and “Lack of information sharing and integrated change control” were rated as the
following top barriers with average ratings of “4.14” and “4.09”, respectively. “Lack of
government support for research and collaboration in Lean” (mean: 3.04) and “Language
problem for non-native speakers” (mean: 3.30) were rated as moderately important in terms
of affecting Lean implementation.
165
People, Culture and Change
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
As survey findings indicated lack of top management was previously listed as a major
barrier by several researchers (Jadhav et al. 2014, Almanei et al. 2017, Okere 2017). This
proves the importance of top management support in conducting an efficient Lean
implementation program. When top management is involved in the processes of Lean,
implementation becomes smoother and more transparent leading to higher efficiency in
processes. The survey findings also implied that misperception about Lean practices is a
major barrier for construction firms in implementing Lean. This proves that the benefits of
implementing Lean has not yet well understood by the majority of construction
professionals. This might stem from the fact that Lean implementation is thought to be
costly and require special expertise for practicing efficiently (Jadhav et al. 2014, Almanei
et al. 2017). Lack of information sharing and control was also listed among top barriers of
Lean implementation by the survey respondents. This finding is in line with the statement
that uncertainties and changes in the project might be handled with effective
communication channels and lack of information sharing might lead to defective processes
in Lean implementation (Howell et al. 2017).
CONCLUSION
Lean implementation is a relatively new practice in the construction industry. Therefore,
certain concerns emerge for those, who aim to implement Lean in their projects. This study
focuses on determining the barriers hindering a successful Lean implementation. In this
respect, an in-depth literature review was assessed to reveal the barriers of Lean
implementation in the construction industry. Then, an online questionnaire was sent out to
members of the LCI for ranking the barriers based on a Likert scale. The questionnaire
results indicated that most important barriers can be found in the socio-cultural
background. The top three listed barriers are: ‘Lack of top management support’,
‘misperception about Lean practices’, ‘lack of information sharing and integrated change
control’. The study is expected to provide a roadmap for construction practitioners to best
practice Lean concepts.
ACKNOWLEDGMENTS
The authors would like to thank the members of Lean Construction Institute (LCI), who
took time responding the online questionnaire.
166
Proceedings IGLC – 27, July 2019, Dublin, Ireland
Identifying Barriers in Lean Implementation in the Construction Industry
REFERENCES
Almanei, M., Salonitis, K., and Xu, Y. (2017). “Lean implementation frameworks: the
challenges for SMEs.” Procedia CIRP, 63, 750-755.
Ayarkwa, J., Agyekum, K., Adinyira, E., and Osei-Asibey, D. (2012). “Barriers to
successful implementation of lean construction in the ghanaian building industry.”
Journal of Construction < http://dspace.knust.edu.gh/bitstream/123456789/10837/1/
BARRIERS%20TO%20SUCCESSFUL%20IMPLEMENTATION%20OF%20LEAN
%20CONST..pdf> (Jan 14, 2019).
Aziz, R.F., Hafez, S.M. (2013). “Applying lean thinking in construction and performance
improvement,” Alexandria Engineering Journal, 52(4), 679–695.
Ballard, G., Howell, G. (2004). “Competing Construction Paradigms.” Lean Construction
Journal, 1(1), 38-45.
Demirkesen, S., and Arditi, D. (2015). “Construction safety personnel's perceptions of
safety training practices.” International Journal of Project Management, 33(5), 1160-
1169.
Demirkesen, S., and Tommelein, I. D. (2016). “Lean Management Methods for Design and
Construction : Built-in-Quality and Safety-by-Design”, In Proceedings of Advances in
Civil Engineering Conference (ACE2016), Istanbul, Turkey.
Devaki, M. P., and Jayanthi, R. (2014). “Barriers to implementation of lean principles in
the Indian construction industry.” International Journal of Engineering Research &
Technology, 3(5), 1189-1192.
Habermann, M., Blackhurst, J., and Metcalf, A. Y. (2015). “Keep your friends close?
Supply chain design and disruption risk. ” Decision Sciences, 46(3), 491-526.
Howell G., Ballard G., and Demirkesen S. (2017). “Why Lean Projects Are Safer”, In LC3
2017: Proceedings of the 25th Annual Conference of the International Group for Lean
Construction (IGLC), Crete, Greece.
Jadhav, J., Mantha, S., and Rane, S. (2014). “Exploring barriers in lean
implementation.” International Journal of Lean Six Sigma, 5(2), 122-148.
Koskela, L. (1992). “Application of the new production philosophy to construction”,
Technical report No. 72, Centre for Integrated Facility Engineering, Stanford
University, CA.
Krafcik, J. F. (1988). “Triumph of the lean production system.” MIT Sloan Management
Review, 30(1), 41.
Kumar S. (2013). “Enablers of Lean Six Sigma Implementation in Business Environment :
A Review” In Proceedings of International Conference on Smart Technologies for
Mechanical Engineering, 409–417, Delhi Technological University, New Delhi, India.
Lean Construction Institute (LCI) (2004). “What is Lean Construction?.”
<http://www.leanuk.leanconstruction.org/whatis.htm> (Feb 24, 2018).
Liker, J. K., and Convis, G. L. (2012). The Toyota way to lean leadership. McGraw-Hill,
New York.
Meadows, D. (2011). “Designing out Waste.” Environmental Design and Construction
Magazine, <http://www.modular.org/marketing/documents/DesigningoutWaste_
EDC.pdf> (June 3, 2017).
167
People, Culture and Change
Demirkesen, S, Wachter, N., Oprach, S., Haghsheno, S
Mossman, A. (2009). “Why Isn't the UK Construction Industry Going Lean with Gusto?.”
Lean Construction Journal, 5(1) 24-36.
Ogunbiyi, O. (2014). “Implementation of the Lean Approach in Sustainable Construction :
A Conceptual Framework”, PhD Diss., University of Cental Lancashire, Lancashire,
UK.
Okere, G. O. (2017). “Barriers and enablers of effective knowledge management: A case
in the construction sector.” Electronic Journal of Knowledge Management, 15(2), 85.
Porter, M. (1985). Competitive Advantage. The Free Press, New York, NY.
Salem, O., Solomon, J., Genaidy, A. and Minkarah, I. (2006). “Lean construction: from
theory to implementation.” Journal of Management in Engineering, 22(4), 168-175.
Sarhan S., and Fox, A.(2013). “Barriers to Implementing Lean Construction in the UK
Construction Industry.” Built Hum. Environ. Rev., 6, 1–17.
Steinmann, H., and Schreyögg, G. (2006). Management: Grundlagen der
Unternehmensführung. 6th edition, Wiesbaden.
Sundar, R., Balaji, A. N., and Kumar, R. S. (2014). “A review on lean manufacturing
implementation techniques.” Procedia Engineering, 97, 1875-1885.
Wandahl, S. (2014). Lean construction with or without lean–challenges of implementing
lean construction. In Proceedings of the 22nd Annual Conference of the International
Group for Lean Construction (97-108). Oslo, Norway.
Womack, J. P., Womack, J. P., Jones, D. T., and Roos, D. (1990). Machine that changed
the world. Simon and Schuster Inc., New York, NY.
Womack, J. P., and Jones, D. T. (1996). Lean Thinking: Banish Waste and Create Wealth
in Your Corporation. Simon & Schuster Inc., New York, NY.