Shewaferahu Tilahun PDF
Shewaferahu Tilahun PDF
By
Shewaferahu Tilahun
June, 2016
Addis Ababa
Ethiopia
ADDIS ABABA UNIVERSITY
SCHOOL OF GRADUATE STUDIES
By
Shewaferahu Tilahun
3.
Chairman Signature Date
Causes and Effects of Delay on Higher Educational Building Projects in Addis Ababa
Acknowledgements
These acknowledgements attempt to thank people who in some way supported, guided and
encouraged me along the way to completing this thesis. I would like to express my sincere
gratitude to the following people. Without their assistance, encouragement, suggestion and
commitment this work would not have been a reality.
Firstly, from the depth of my heart I would like to express sincere gratitude and appreciation to
my advisor professor Dr.-Ing. Abebe Dinku for his continued support, generous academic advice,
discussions, suggestions and encouragement.
I would also like to express gratitude to all my friends and colleagues, especially to Samson
Shimeles, Temesgen Abebe and Solomon Dinberu, thank you for your enormous help in
collecting the surveys, advice and encouragement.
Sincere gratitude and appreciation goes to all professionals, engineers, contractors and consultants
who participated in the questionnaire, interview and case study. Special thanks to the Office for
Building, Ground and Infrastructure of the Addis Ababa University.
Finally, to my family, a very special thank for all their sacrifice, patience, love and support
throughout my studies.
Table of Contents
Abbreviations .......................................................................................................................i
Acknowledgement...............................................................................................................ii
List of Tables.....................................................................................................................vii
List of Figures ..................................................................................................................viii
Abstract ..............................................................................................................................ix
1. INTRODUCTION ...........................................................................................................1
1.1. Background...............................................................................................................1
1.2. Problem Statement....................................................................................................2
1.3. Research Questions...................................................................................................3
1.4. Research Objectives...................................................................................................3
1.4.1. General Objectives ...................................................................................... 3
1.4.2. Specific Objectives...................................................................................... 3
1.5. Scope of the Study....................................................................................................3
1.6. Research Methodology .............................................................................................4
1.7. Outline of the Research ............................................................................................4
2. LITERATURE REVIEW ................................................................................................6
2.1. General .....................................................................................................................6
2.2. Construction Project Planning..................................................................................6
2.2.1. Stages of Planning ..........................................................................................8
2.2.1.1. Pre-contract stage .......................................................................................8
2.2.1.2. Contract stage .............................................................................................9
2.3. Project Scheduling....................................................................................................9
2.3.1. Scheduling Techniques .................................................................................10
2.3.1.1. Bar (Gantt) chart.......................................................................................10
2.3.1.2. Network scheduling..................................................................................10
2.3.1.2.1. Critical Path Method (CPM) ..................................................... 11
2.3.1.2.2. Project Evaluation and Review Technique (PERT) .................. 11
2.4. Definition of Delay.................................................................................................12
2.5. Classification of delays ..........................................................................................12
2.5.1. Excusable Delays ..........................................................................................13
2.5.2. Excusable compensable Delay......................................................................14
2.5.3. Excusable Non-compensable Delay .............................................................14
2.5.4. Non-excusable Delay ....................................................................................14
2.5.5. Concurrent Delays ........................................................................................15
2.5.6. Compensable or Non-compensable Delays ..................................................16
2.6. Causes of Delay......................................................................................................17
2.7. Effects of Delay......................................................................................................20
References .........................................................................................................................57
Appendix A - Research Proposal
Appendix B - Questionnaire Survey
Abbreviations
CD Calendar days
List of Tables
Table 4.11 Importance Index for most important factors from overall results 34
List of Figures
ABSTRACT
The construction industry is one of the main sectors that provide important ingredients for the
development of an economy. Construction is a tool through which a society achieves its goals of
urban and rural development.
However it is becoming more complex because of the sophistication of the construction process
itself and the large number of parties involved in the construction process, i.e., clients, contractors,
consultants, users, designers, subcontractors, regulators, and suppliers.
This eventually leads to delay in the completion of the project. Construction delay defined as
“time over run either beyond completion date specified in a contract or beyond the date that parties
agree upon for delivery of a project.” It is slipping over its planned schedule and is considered as
common problem in construction projects.
Delay in construction project completion is a global phenomenon that occurs in the construction
industry and considered as one of the most common problems causing a multitude of negative
effects on the project and its participating parties especially where the government projects are
concerned and in the construction industry of Ethiopia is no exception.
The objective of this study is to identify the major causes and factors of construction delays, their
effects on the successful completion of projects, and provide suggestions to minimize delays in
the construction of Educational Building projects under Addis Ababa University.
This study uses a comprehensive literature review to design and conduct a survey to investigate
delay causes and then filtered based on appropriateness to the Ethiopian Construction Industry as
well as the Educational Building Projects at Addis Ababa University. A specific survey was
conducted thru case study for selected projects to examine the most critical delay factors and their
effects. A general survey was distributed thru questionnaire to examine the correlation of the most
critical factors of delay and its relative effect on the project with respect to time, cost and quality.
Data was collected and analyzed using the ‘Relative Importance Index (RII)’ whereby the score
with the highest RII is one that mostly influences the delay.
Key words: Educational building construction projects, Construction Delays, Causes of Delay,
Effects of delay, Addis Ababa University
1. INTRODUCTION
1.1. Background
Higher educational institutions are function to develop human resources that are able to adapt
and compete in a society. The idea of the knowledge society is increasingly becoming
widespread in the move towards globalization.
Modern construction projects are characterized by new standards, advanced technologies,
multiparty participation, and frequent owner-desired changes. Coupled with this inherent
uncertainties and complexities in the physical, financial, and economic environment in which
most projects are performed. Such conditions have made completing projects on schedule and
on budget a difficult task to accomplish, often leading to claims on cost compensations and/or
time extensions. This eventually leads to delay in the completion of the project.
Delay is defined as the time over run either beyond completion date specified in a contract or
beyond the date that the parties agree upon for delivery of a project. Delay in construction project
is considered one of the most common problems causing a multitude negative effect on the
project and its participating parties. Therefore, it is essential to identify the actual causes of delay
in order to minimize and avoid the delays and their corresponding effects.
Delays in construction can cause a number of changes in a project such as late completion, lost
productivity, acceleration, increased costs, and contract termination. A delay in an activity may
not result in the same amount of project delay. A delay caused by a party may or may not affect
the project completion date and may or may not cause damage to another party. A delay may
occur concurrently with other delays and all of them may impact the project completion date.
Delays caused by the client such as failure to allocate sufficient fund, slow decision making
coupled with delay caused by consultant such as late submission of drawings and specifications,
frequent change orders, and inadequate site information generates claims from both the main
contractors and subcontractors which many times entail lengthy court proceedings with huge
impacts. Delays caused by contractors generally attributes to poor managerial skills, lack of
effective planning and poor financial management have led to a contractor’s downfall.
The effect of delay may include time overrun, cost overrun, disputes, litigation and total
abandonment (Murali and Yau, 2006). Some studies directly examine delays, attempt to identify
their causes and recommend ways to avoid them. Construction project delays have a weakening
effect on parties (Owner, Contractor, and Consultant) to a contract in terms of a growth in
Shewaferahu Tilahun, AAU, AAiT, Department of Civil & Environmental Engineering 1
Thesis on Causes and Effects of Delay on Educational Building Projects in Addis Ababa University
This thesis examines causes and effects of delay in an integrated manner and determine how
critical delay causes are most influential in project performance. This will provide owners,
Consultants and construction organizations involved in construction projects with the foundation
on which such strategies – on how to avoid delays - can be developed in the future. This thesis
focuses on Educational Building Construction Projects in Addis Ababa University, which were
assessed for delay causes and examines the corresponding effects identified and provide
recommendation based on the findings to improve project performance within the higher
education building projects as well as the general public construction projects.
Delays in a construction project is counted as a common problem and became a cause for projects
completion with huge cost overrun (requiring higher budget than estimated), extended
completion time, inferior quality deliverables and contract termination. In recent time it was an
accepted phenomena to have delays in construction projects completion time. For the client,
construction delay is a loss of revenue, lack of productivity, dependency on existing facilities,
etc. For the contractor, construction delay is the higher costs, longer work duration, increased
labor cost, higher material and equipment costs etc. Completion of construction projects on
specified time or time agreed by the parties indicates their efficiency. The delays in construction
projects happen because of various factors or causes. These causes lead to the delay in
construction completion, and this delay ultimately leads to negative effects on the construction
project.
In Ethiopian construction practice, it is very rare that construction projects are completed on the
time specified or agreed upon. There are many educational building construction projects in
Addis Ababa University, which suffered delay or in some cases suffered suspension or
abandonment.
The methodology adopted for this research comprises three stages as follows:
Stage 1. Literature Review to determine the research focus. Local and International studies
conducted particularly on related works and construction delays in general were
reviewed.
Stage 3. Case Study: a minimum of four sample projects of educational buildings in Addis
Ababa University were analyzed. Projects were selected based on critical cases
among completed and those under construction.
This thesis format follows the logical steps of establishing the research questions, developing
the methodology, gathering and analyzing data, and drawing conclusions. The Thesis is
organized into six chapters as follows:
Chapter 1 discusses the introduction of the research by highlighting the research problems,
research purpose, research objectives, proposed methodology and research organization.
Chapter 3 describes the data collection method, analysis techniques and statistics used to
identify causes of delay on educational building projects in Addis Ababa. It also explains the
analysis used to determine the correlation between critical delay causes and its effect on
project delivery performance measures.
Chapter 4 presents the findings and discussion based on the results obtained from
questionnaire responses.
Chapter 5 presents the case study selected from completed and ongoing building projects in
Addis Ababa University which is believed to be significant to the study.
Chapter 6 is the conclusion and recommendation chapter and discusses the research
conclusions, limitations of the research, contribution to new knowledge, and provides
recommendations based on the findings.
2. LITERATURE REVIEW
2.1 General
Increasing uncertainties in technology, budget and construction processes make the construction
industry dynamic. Building projects are now much more complex and difficult and hence the
building project team faces unprecedented challenges. The study on causes of construction delay
and its effects on the project performance is a means of understanding and thus improving the
effectiveness of construction projects.
The timely completion of a construction project is seen as a major criterion of project success by
clients (Bowen, Hall, Edwards, Pearl & Cattell, 2002). The inability of a project to be completed
in accordance with the proposed time schedule maybe as a result of delay. Stumpf (2000) viewed
delay as an incident that extends the time required to perform the tasks under a contract. It usually
shows up as additional days of work or as a delayed start of an activity (Sweis, Hammad &
Shboul, 2008).
Delays in construction can cause a number of changes in a project such as late completion, lost
productivity, acceleration, increased costs, and contract termination. The party experiencing
damages and the parties responsible for them in order to recover time and cost. However, in
general delay situations are complex in nature. A delay in an activity may not result in the same
amount of project delay. A delay caused by a party may or may not affect the project completion
date and may or may not cause damage to another party. A delay may occur concurrently with
other delays and all of them may impact the project completion date.
One of the objectives of this research is to understand critical causes and effects of delays on the
Addis Ababa University Building Construction Projects. This chapter defines and describes
factors and causes of delay to construction projects as identified in the literature.
SCHEDULING
Fig. 2.1 General Framework for the Planning Process (A. De Marco, 2011)
The effective planning, scheduling and control of construction projects is necessary. The benefits
of implementing and maintaining this set of three management systems are reduces delay, cost
overrun and minimize disputes (Callahan et al. 1992). These benefits accrue to the Contractor,
Owner, suppliers and workers in the form of improvements in productivity, quality and resource
utilization.
The objective of construction planning is to identify discrete activities or tasks that can be
planned, estimated, scheduled, executed and controlled to ensure successful completion of
construction projects. In addition, an effective planning must address the following questions
like what is to be done, what are the activities, how it is to be done, when it is to be done, where
it is to be done, what is needed to do it, who is to do it and how to ensure that it is done (Chitkrara
,2001).
PLANNING
STAGES
PRE-CONTRACT
CONTRACT STAGE
STAGE
Deciding the overheads, and margin of profit and finalizing the tender price for
completing the work within the stipulated time
Scheduling is the process of developing the work plan to a time frame, set date-wise in a logical
sequence: it is a time table for action indicating the start and completion of each activity. Sidney
(2002) defines scheduling as a tool that provides participants in the project with an orderly, time
related sequence of events to follow in order to effect timely completion of the project.
SCHEDULING
TECHNIQUES
to be used as an effective management tool for planning, scheduling and controlling complex
projects. The most common network analysis techniques used for planning, scheduling and
controlling of projects are Critical Path Method (CPM) and Project Evaluation & Review
Technique (PERT). Their common features are that they make use of the network model for
depicting the time plan of the project: apply the critical path concept for determining the project
duration and identifying critical activities and employ network analysis technique for controlling
the project -time objectives [8]. When using network techniques, the interrelationship of all
operations is clearly shown. The normal bar chart does not do this, and consequently requires
the dependence of one operation on another to be remembered by the planner; this is extremely
difficult with large projects, and in addition the technical staff assigned to carry out the work has
to be informed how dependent one operation is on another. When a delay occurs, and networks
are being used, critical operations will stand out as requiring particular attention [10]
using three-time duration estimation method: Optimistic, most likely, and pessimistic. For
computation of critical path, the PERT three-time probabilistic network is converted into a
single-time deterministic CPM model. These estimates then are used to calculate the expected
time for an activity.
Benjamin (1976) has identified some of the following advantages of PERT scheduling technique:
PERT essentially forces the detailed definition of tasks, task sequences, and task
interrelationships.
PERT enables management and engineering to predict with some degree of certainty the
probable time that it will take to achieve an objective.
PERT enables the rapid assessment of progress and the detection of problems and delays.
DELAY
- No Time
Entitlement for Time
- Non-Compensable
Compensable
Non-Compensable
These are some examples of non-excusable delays (Al- Gahtani and Mohan 2007):
i. Late performance of contractor and/or sub-contractors
ii. Untimely performance by suppliers
iii. Faulty workmanship by the contractor or sub-contractors
iv. A project-specific labor strike caused by either the contractor’s unwillingness to
meet with labor representative or by unfair labor practices
When the non-excusable delay is on the critical path and the excusable delay is non-
critical, no extension of time is due.
When the non-excusable delay is non-critical and the excusable delay is on the critical
path, extension of time is due even if the non-excusable delay commenced early in the
non-critical chain of activities in so far as the non-excusable delay does not impact the
critical activity.
When both excusable and non-excusable delays are critical and commenced together and
cease at the same time, both the employer and Contractor should bear responsibility for
them. The Contractor is entitled to extension and is not entitled to associate costs even if
the excusable delay is a compensable delay.
When an excusable delay occurs first on a critical path followed by a non-excusable delay
on a parallel critical path, the dominant cause of delay should be the deciding factor.
For example, if two delays are concurrent, and one is five days long and the second is seven days
long, the second concurrent delay will only extend the contract completion time by two days.
In a study of the significant factors that cause delay of construction projects (Alaghbari, Kadir,
Salim and Ernawati, 2007), classified the factors into four major groups, these are contractor
factor, consultant factor, client factors and external factors. Financial problems, shortage of
materials and poor site management practices were considered the top most factors. Client
related factors included delayed payments, slow decision-making, frequent change orders, bid
award for lowest price and contract scope changes. The most important factors by consultant
were provision of incomplete design, poor supervision, slowness to give instructions and lack of
experience. External causes identified included shortage of materials availability, poor site
conditions and lack of equipment and tools in the market. In a related study of the causes and
effects of delay in Malaysia construction industry Sambasivan & Soon (2007) found poor site
management, inadequate experience’ and poor subcontractors among the major causes of time
delays on construction projects.
Projects can be delayed for a large number of reasons and usually impact on cost and time.
Battaineh et al. (2002) studied causes of construction delay in Jordan. Results of the survey
indicated Contractors and Consultants agreed that Owner interference, inadequate Contractor
experience, financing and payments, labor productivity, slow decision making, improper
planning, and Sub-contractors are among the top ten significant factors.
Mansfield et al (1994) studied the causes of delay and cost overrun in construction projects in
Nigeria. The results showed that the most important factors are financing and payments, poor
contract management, changes in site conditions, shortage of material, and improper planning.
Similarly, Aibinu et al (2002) made a research on effects of construction delays in Nigeria. The
findings showed that time and cost overruns were frequent effects of delay. Delay had significant
effect on completion cost and time of 61 building projects studied. Client-related delay is
significant in Nigeria.
Assaf et al. (2006) conducted a survey on time performance of different types of construction
projects in Saudi Arabia to determine the causes of delay and their importance according to each
of the project participants, i.e., the Owner, Consultant and the Contractors. The survey included
23 Contractors, 19 Consultants, and 15 Owners. Seventy-three causes of delay were identified
during the research. 76% of the Contractors and 56% of the Consultants indicated that Average
of time overrun is between 10% and 30% of the original duration. The most common cause of
delay identified by all the three parties is “change order”. Surveys concluded that 70% of projects
experienced time overrun and found that 45 out of 76 projects considered were delayed. Neal
(2007) in his study showed that 40% of the projects studied in the UK have over-run their original
contract period.
Ogunlana et al. (1996) studied the delays in building project in Thailand, as an example of
developing economies. He concluded that the problems of the construction industry in
developing economies could be nested in three layers: (1) problem of shortages or inadequacies
in industry infrastructure, mainly supply of resources; (2) Problems caused by Clients and
Consultants; and (3) Problems caused by incompetence of Contractors.
Sambasivan et al. (2007) surveyed causes and effects of delays in Malaysian construction
industry. The study identified 10 most important causes of delay from a list of 28 different causes
and 6 different effects of delay. Ten most important causes were: (1) Contractor’s improper
planning, (2) Contractor’s poor site management, (3) inadequate Contractor experience, (4)
inadequate Client’s finance and payments for completed work, (5) problems with Sub-
contractors, (6) shortage of material,(7) labor supply, (8) equipment availability and failure, (9)
lack of communication between parties, and (10) mistakes during the construction stage.
Rizwan et al. (2007) conducted a research on delays in construction industry of Pakistan. A delay
criticality index was used to identify the major delay causes in the industry which, in descending
order of criticality, were found to be: change orders, labor productivity issues, poor site
management and supervision, inspections/audits, poor cost estimation and control, inadequate
project scheduling, defective design, inefficient construction methods, delayed payments, and
incomplete construction drawings. In addition, the percentage allocation of responsibility for
overall delay causes, according to Contractors’ perceptions, was as follows:
Contractors=48.75%, Consultants=17.5%, Owners=16.25 %, government=8.75%, and shared
=8.75%.
Kumaraswamy et al. (1997) carried out a study on causes of time overruns in Hong Kong
construction projects. He revealed that the five principal and common factors of delays are: (1)
Shewaferahu Tilahun, AAU, AAiT, Department of Civil & Environmental Engineering 18
Thesis on Causes and Effects of Delay on Educational Building Projects in Addis Ababa University
poor risk management and supervision, (2) unforeseen site conditions, (3) slow decision making,
(4) Client-initiated variations, and (5) necessary variations of works.
Shakeel et al. (2006) made an investigation of significant causes of delay in the UAE
construction industry. In the study, they indicated that the effects of construction delays are not
confined to the construction industry only, but influence the overall economy of a country like
UAE, where construction plays a major role in its development and contributes 14% to the GDP.
Thus, it is essential to define the most significant causes of delay in order to avoid or minimize
their impact on construction projects. The research disclosed that 50% of the construction
projects in UAE encounter delays and are not completed on time. The top 10 most significant
causes of construction delays have been identified by this research. Approval of drawings,
inadequate early planning and slowness of the Owners' decision-making process are the top
causes of delay in the UAE construction industry.
Mezher et al. (1998) conducted a survey of the causes of delays in the construction industry in
Lebanon from the view point of Owners, Contractors and architectural/engineering firms. It was
found that Owners had more concerns with regard to financial issues; Contractors regarded
contractual relationships the most important, while Consultants considered project management
issues to be the most important causes for delays.
Ahmed et al. (2005) under his study of construction delays in Florida identified the six (6) most
critical causes of delays in ascending order of criticality were found to be :( 1) changes in
specifications, (2) inspections, (3) Incomplete drawings, (4) changes in drawings, (5) change
order, (6) building permits approval.
Abdo (2006) made a survey on delays in public building construction projects in Ethiopia. The
result of the research indicated that 94% of the 52 surveyed public building projects undertaken
by local Contractors between the years 1995 to 2005 have encountered delays. Moreover, the
time extension ranges from 10% to 367% and the Average delay is found to be 89.9%. The most
frequent causes of delay which in descending order of criticality were found to be: (1) necessary
variations, (2) delayed payments, (3) scarcity of materials, (4) late material supply, (5) less
emphasis to planning, (6) sub-surface condition, (7) changes in design, (8) material and labor
price escalation, (9)unrealistic time schedule, and (10) failure to update schedules on time.
Divya.R and S.Ramya (2015), mentioned the possible following factors causing delays in
construction projects in Malaysia:
4) Arbitration
5) Litigation and
6) Abandonment
B.P.Sunjka, et al stated that poor quality completed projects and bad public relations are also
the effects caused due to delay in construction projects in addition to the above six effects.
Cost, time, and quality have proven their importance as the primary success factors of a project.
According to Ahmed, et al delays on construction project is a universal phenomenon. They are
usually accompanied by cost overruns. Delay has a negative effect on clients, contractors, and
consultants in terms of growth in adversarial relationships, mistrust, litigation, arbitration, and
cash-flow problems. A project may be regarded as a successful endeavor until it satisfies the
cost, time, and quality limitations applied to it. However, it is not uncommon to see a
construction project failing to achieve its goal within the specified cost, time, and quality.
Aibinu and Jagboro (2002) studied the effects of construction delays on project delivery in
Nigerian construction industry. The six effects of delay that were identified includes: time
overrun, cost overrun, dispute, arbitration, total abandonment and litigation. Koushki and Kartam
(2004) concluded that time and cost overrun were the impact of the material selection time, their
availability in the local market and the presence of the supervising engineer. It is important to
improve the estimated activity duration according to the actual skills levels, unexpected events,
efficiency of work time, mistakes and misunderstanding (Lock, 1996). Delays influence
negatively on the contractors performance and contribute to adverse impacts in construction
projects such as contract disputes, low productivity and increase in construction costs that will
also influence on the pre-determined of construction project objectives. From the comprehensive
literature review, six major effects of delay in the construction projects were identified as
follows:
Similarly, Sambasivan et al. (2007) identified six most frequently observed effects of delays in
his survey on causes and effects of delays in Malaysian construction industry. These were: (1)
time over-run, (2) cost overrun, (3) disputes, (4) arbitration, (5) litigation, and (6) total
abandonment.
other hand, Aibinu and Jagboro (2002) studied the effects of construction delays on project
delivery in Nigerian construction industry. They identified time overrun as one of the major
effects of delay.
2.7.3 Disputes
Disputes are the effects of major causes of delays in construction projects such as causes of
Client related, Contractor related, Consultant related and external related that may be arisen
during the construction projects among the project parties. Lack of communication may also
leads to misunderstandings, conflicts and disputes. Hence it necessitates the project managers to
have effective communication skills which are one of the significant soft skills (People skills)
with the project parties involving in construction projects. Based on Murali et al., (2007) the
factors such as lack of communication between the various parties, problem with neighbors,
unforeseen site conditions, delay in payments for completed work, improper construction
method, delay caused by the subcontractor and discrepancies in contract documents will give
rise to disputes between the various parties. Furthermore, if the disputes cannot be solved
amicably or easily it can lead to arbitration or litigation.
2.7.4 Arbitration
According to Murali et al., (2007) delays caused by either client or contractor related factors
such as change order, delayed progress payment, contractor’s non-performance and lack of
communication between parties which may rise disputes will be settled through arbitration
process. For these circumstances, it is necessitate having a competent third party that can settle
the disputes amicably or easily without going to court.
2.7.5 Litigation
Based on Murali et al., (2007) when the delays caused by client related, contract related, labor
related and external related factors such as delay in payment for completed works, problems with
site conditions and less labor supply where eventually rise the disputes to be settled by the
litigation process. The parties involved in the construction projects use litigation as a last
alternative to settle the disputes.
Cost Time
Overrun Overrun Dispute
Figure 2.5 Fish-Bone Diagram of six effects of the construction delays. (Abedi M. 2012)
3. RESEARCH METHODOLOGY
= ……………………...Equation 3.1.
Where,
RII = Relative Importance Index,
, , , , = Number of respondents answer each factor
1, 2, 3, 4, 5 = weight given for each factor (ranging from 1 to 5),
A = highest weight (i.e. 5 in our case),
N = total number of respondents.
The importance indices were calculated for all delay causes and the delay causes were ranked
accordingly. In order to identify how project delay can be mitigated, it is important to identify
the responsible party. Therefore, the responsibility of the delay causes is illustrated in the factor
or category column.
Finally, the findings have been summarized and presented by using different diagrammatical
tools plus supported with further descriptions.
In addition, analysis for case study were conducted for selected higher educational building
projects those seriously hampered and affected by project delay. This helps the researcher to
show the critical causes and effects of delay in the Ethiopian context.
4.1. Introduction
The findings and discussion below is devised in three parts corresponding to the research questions
and also the sections of the questionnaire. The first part presents survey distribution and response
rates by sector organization, respondents’ designation and experience in the Ethiopian building
construction industry. The second part of the results and discussion contains the findings of the
questions directed towards identifying the importance of delay causes and raking in the level of their
severity. 51 potential delay causes were selected from previous studies and grouped in category wise.
These delay causes had a five point scale ranged from 1 to 5 in a level of importance from Non
important to Extremely Important cause to project delays and the results are discussed. In the third
part respondents were asked to identify the most important and frequent effect of construction delay.
Similarly to the causes, nine potential effects were selected from previous studies. These effects of
delay had also a five point scale ranged from 1 to 5 and the results of the questions are presented and
discussed accordingly.
The following tables, Table 4.1 and 4.2 show the distribution profile of the respondents’
organization in terms of type and respondents designation respectively.
The designation of the respondents shows a relatively wider variety of professionals which are
relevant to the construction delay analysis. The respondents have been assigned as senior project
managers, quantity surveyors, contract administrators, planning engineer and construction
supervisors.
Table 4.3 below shows respondents’ general and specific work experience in the construction
industry and building construction projects respectively.
On the percentage of years of work experience of the respondents, (12) 27.27% of the
respondents have 5-10 years of work experience, (7) 15.91% of the respondents have 11-15 years
of work experience, (9) 20.46% of the respondents have 16-20 years of work experience, (16)
36.36% of the respondents have more than twenty (20) years of work experience in the building
construction sector.
The respondents also suggested to consider bid award for lowest price is also one of the potential
cause of project delay, because the lowest bidders might be low qualified contractors.
Consequently, poor performance will occur that will affect the project schedule.
From Table 4.4 the results show that the respondent ranked the most important client related delay
causes in the construction of Addis Ababa Public projects were Financial arrangement and
inadequate fund allocation (RII=0.809), change and variation order during construction
(RII=0.805), Delay to effect progress payment (RII=0.791), unrealistic contract duration
(RII=0.773) and Slow decision making (RII=0.759)
As shown on the above table, the most important and highly ranked contractor related delay causes
in the construction of HEB projects, are inefficient planning and scheduling (RII=0.800), Inaccurate
cost estimation (RII=0.723), Inappropriate construction method (RII=0.714), poor site management
(RII=0.686), poor coordination and communication (RII=0.686), Inadequate experience of
contractor’s technical staff (RII=0.645), delay in subcontractors’ work (RII=0.627) and reworks
due to errors during construction (RII=0.591).
The results of the questionnaire survey showed that, the most important and highly ranked
Consultant related delay causes in the construction of HEB projects, are Mistakes and discrepancies
in design documents (RII=0.864), frequent change and variation order (0.855), Unclear and
inadequate details in drawings (RII=0.836), Slow response and inspection (RII=0.823), Inaccurate
site investigation (RII=0.809), Poor contract management (RII=0.782) and change in material type
and specification.
The most important and highly ranked material related delay causes in the construction of HEB
projects, are Delay in material delivery (RII=0.864), Shortage of construction materials
(RII=0.859), Change in material type during construction (RII=0.795), Late procurement of
materials (RII=0.786), Rise in material price (RII=0.736), quality of materials (0.709) and
Inadequate material (RII=0.691)
The most important and highly ranked equipment related delay causes in the construction of HEB
projects, are Shortage of construction Equipment (RII=0.709), Equipment breakdown (RII=0.636),
Low productivity and efficiency of equipment (RII=0.573), Low level of operator’s skill
(RII=0.564) and Shortage of equipment parts (RII=0.555).
The most important and highly ranked labor related delay causes in the construction of HEB
projects, are Low labor productivity (RII=0.732), Shortage of labor (RII=0.691), Non-attendance
(RII=0.482), Labor injuries (RII=0.473), Labor strikes (RII=0.455) and personal conflict among
laborers is (RII=0.386).
As shown on Table 4.10 above, the most important and highly ranked external factor of delay causes
in the construction of HEB projects, are Rise in price of material (RII=0.700), Unforeseen site
condition (RII=0.645), Delay in providing services from utilities (water, electricity, etc)
(RII=0.577), Delay in obtaining permit (RII=0.555), Weather condition (RII=0.477), Regulatory
changes (RII=0.473), Government policies (RII=0.427), and Natural disasters (RII=0.350).
Table 4.11 - Importance Index for Most Important Factors from Overall Results
Rank Delay Causes RII Factor (Category)
1 Mistakes and discrepancies in design documents 0.864 Consultant
2 Delay in material delivery 0.864 Material/ Contractor
3 Shortage of construction materials 0.859 External
4 Frequent change and variation order 0.855 Consultant
5 Unclear and inadequate details in drawings 0.836 Consultant
6 Slow response and inspection 0.823 Consultant
7 Finance arrangement and inadequate fund allocation 0.809 Client
8 Inaccurate site investigation 0.809 Consultant
9 Change and variation order during construction 0.805 Client
10 Inefficient planning and scheduling 0.800 Contractor
11 Delay to effect progress payment 0.791 Client
12 Late procurement of materials 0.786 Contractor
13 Poor contract management 0.782 Consultant
Unrealistic contract duration and imposed
14 0.773 Client
requirement
15 Change in material type during construction 0.759 Consultant
16 Slow Decision making 0.759 Client
17 Rise in material price 0.736 External
18 Low labor productivity 0.732 Contractor
19 Inaccurate cost estimation 0.723 Contractor
20 Inappropriate construction method 0.714 Contractor
As shown on Table 4.11, from the overall results obtained from the questionnaire response, delay
causes that hamper the performance as well as timely delivery of the project are presented in the
level of their severity.
10%
30%
25%
35%
Contractor
Consultant
Client
External
Figure 4.1 above shows, besides the influence of unbalanced questionnaire distribution among
parties as shown in table 4.1 earlier, according to respondents’ ranking, out of the top twenty most
potential delay causes, 35% originated by the consultants, 30% originated by the contractors, 25%
ranked as originated by clients and delay causes originated by external factors ranked least by 5%.
The desire to finish a project on time, under the planned budget, and with the highest quality is
common goals for all contracting parties, including the Owner, Contractor and Consultant. Delay
usually result in losses of one form or another for everyone. The causes lead to the effects of delay
on construction projects. The nine effects of delay identified were:
1) Time overrun
2) Cost overrun
3) Wastage and underutilization of resources
4) Tying down of Client’s capital due to non-completion of the project
5) Abandonment of the project
6) Dispute between parties
7) Reduced profit or total lose
8) Arbitration
9) Litigation and court case
In this respect the respondents asked to rate their agreement on the effect of delay by correlating to
delay causes using five points scale (Strongly disagree, disagree, slightly disagree, agree and
strongly agree) having a score from 1 to 5 respectively. Participants were also asked to correlate
the effects with causes of delay and space is provided to give their comment (Appendix B).The
importance and ranking of effects of delay resulted by the research methodology of questionnaire
survey and evaluated by statistical formula for each factor group are shown below.
Results from Table 4.11 shows that Time overrun ranked the highest with RII of 0.964, while cost
overrun or increase in final cost of the project is ranked second with RII of 0.891. Wastage and
under- utilization of man-power and resources has RII value of 0.805. Time in every phase of
project life is really essential, when a contract is done and the date is given, the effect of delay really
affects time and money. Dispute among parties involved is ranked forth with RII value of 0.768.
Time affects every other factor, the increase in final cost; more money has to be spent. Delay will
also cause wastage and underutilization of man power and resource. Tying down of client capital
due to non-completion of the project is ranked fifth with RII of 0.741 because; the client cannot get
the intended service if the work is not completed on time. Abandonment of the project was ranked
seventh with RII values and 0.577. Arbitration and litigation were ranked sixth and eighth with RII
values of 0.636 and 0.568 respectively. There is a close interrelation among these three effect.
Dispute among parties involved can induce litigation and arbitration and if the decision of the
arbitration panel is not acceptable to either of the parties involved, this can lead to big time legal
battle which can truncate the progress of the work..
The correlation between the causes and effects of delay shows that the time overrun refers to late
completion or late delivery, from the time specified or agreed by all parties, of construction project.
The main causes for the time overrun are financial problems, late payments for the completed work
and ongoing work, change orders, inefficient planning and scheduling, poor site management, delay
in material delivery, etc.
Cost overrun refers to the increased costs of labor, working force, materials and equipment etc. The
main causes for the cost overrun are change orders, mistakes in the contract, changes in drawings,
inaccurate cost estimation, etc.
Wastage and underutilization of resources refers to idle manpower, lower productivity of workers
and equipment, etc. The main causes for the underutilization of resources are late procurement and
material delivery, slow response and approval, change orders, inadequate material supply, changes
in drawings, weather condition, unforeseen site condition, etc.
Disputes among parties refer to the disagreement between different parties in the construction
project. The main causes for disputes are slow or late payments for completed or ongoing work,
poor communication and coordination, client interference.
Litigation and court cases refers to a legal proceeding in a court to solve the problems and it takes
a long time to solve the problems. The main causes of litigation and court cases are late or no
payments for completed work, rise in material price, etc.
Abandonment refers to stopping every work or suspending the project for long time. The main
causes for abandonment are regulatory changes, finances and payments, natural disasters etc.
The outcome of analysis from this study can be said to be of great relevance to the construction
industry. Majority of the respondents are fully involved in the construction industry with at least 10
years of construction experience, meaning that the respondents have wealth of knowledge and could
supply the necessary information on the question sent out in the questionnaires. The professionals
represented were the Contractors having the highest percentage of 52.5% followed by the
Consultants having 35% then the Clients having 7.5% and Subcontractors having the least
percentage of 5%.
There are many factors that induce delay on construction projects, however in this study the factors
are limited to 52 factors causing delay and they were ranked according to the Relative Importance
Index. The factors includes: lack of funds to finance the project to completion, changes in drawings,
lack of effective communication among the parties involved , lack of adequate information from
consultants, slow decision making, unrealistic contract duration and variations. Also, project
management problem, mistake and discrepancies in contract document, equipment availability and
failure, mistakes during construction, bad weather, fluctuation in prices of building materials, and
ineffective planning and scheduling, low labor productivity and many more.
Analysis was also carried out on the effect of delay on the project work. Time overrun, increase in
final cost of project, wastage and under-utilization of man-power and resources, tying down of
client capital due to non-completion of the project, dispute among parties involved were ranked
highest. Time is factor that is very essential in all activities that has to be carried out, in the contract
document a specific time phase is given for delivery of project and if the time is being exceeded
more money is often spent which could lead to increase in final cost of project and also wastage
and under-utilization of man-power and resources. The client’s capital has to be withheld due to
non-completion of the project which could result into dispute, litigation and arbitration among the
workers and management. Also delay can lead to reduced profit for Contractor and abandonment
of building project by the client.
5.1. Black Lion Hospital, Maintenance of Technical & HIK Wing Project
The Maintenance of Technical & HIK Wing Project is located in the Black Lion Hospital Medical
Faculty Compound. The project comprises of a maintenance of HIK Wing, which is under
construction by a local contractor NKH construction. (See Appendix C-1 for project details and
information). The project commenced on May 27, 2013 and supposed to be completed on May 26,
2014 with a contract period of 365 days. The initial contract amount of the project was ETB
89,001,607.88 but revised to ETB 111,132,773.14 including a supplementary works amounting to
ETB 22,131,165.26. The amount of work executed until December 31, 2015 was ETB
81,730,815.50 which is 73.54% of the contract amount. The project is delayed by 582 days
excluding the time required to complete the project in the future.
As per the data collected from the Consultant, Contractor and Employer, the major causes of delay
on this project are originated by the Employer, Contractor and Consultant.
released. The Consultant has evaluated the Contractor’s claim and approved only 86 days (23.56%
of the contract period).
The Contractor also submitted his 2nd claim for time extension after 79 days of the 1st one citing the
same reason which is delay to give possession. In the 2nd time extension claim they requested a total
of 115 days but similarly the Consultant granted only 86 days. As per the approved schedule the
Contractor planned to execute 56.83% of the total contract amount between the periods February
to May 2014 but the actual achievement was only 2.13%. In both claims the Contractor didn’t
accompanied any financial compensation claim.
approved 172 days out of the requested 231 days. Therefore, the Contractor is accountable for the
remaining 410 days. This implies that the Contractor’s ineffective planning (in terms of resource
and work break down) coupled with failure to revise the schedule regularly in view of the project
situation contributed for the delay.
Project Particulars
Client [Owner] Addis Ababa University
Consultant CDSCo
Contractor Asmelash and Sons Construction PLC
Specific Location Samba Nekersa
Contract Type Admeasurement [Unit rate]
Initial Contract Amount ETB 179,944,468.08
Addition [Supplementary works] ETB 37,542,243.13
Revised Contract Amount ETB 217,486,711.21
Initial Contract Period 540 Days
Total Amount of Work executed until December 2015 216,788,184.57
Executed Vs Contract 120.48%
Time elapsed up to December 2015 1426 Days
Elapsed time Vs Contract 264.07%
Total days delay beyond contract period 886 Days
Time extension granted based on claim #1 & #2 508 Days
Unjustifiable delay 378 days + Time for remaining works
support his claim were Contractor’s ineffective planning and failure to revise the master schedule
regularly in view of the project situation.
way, insisted to commence the work in the meantime to work on price adjustment. The Consultant
took the assignment to prepare a revised contract agreement for signing. Until the project abandoned
on September 2011 the adjustment issue were not finalized.
notices to improve its performance but no action had been taken until the contract termination came
in to effect on April 2014 after the total abandonment for 941 days. Currently, the project was
awarded to another contractor with a contract amount of ETB 61,918,466.00 to complete the
remaining works.
Consultant CDSCo
After collection of the required information from the consultant, interview has been conducted with
the contractor technical personnel. The main reason for the delay as well as the abandonment of the
project was foreign currency devaluation that occurred in the year 2010. The contractor had 17
projects during the time when exchange rate was changed and most of them were awarded with a
very marginal and fragile contract prices.
6.1. Conclusions
Based on the literature reviews, the results of questionnaire responses and case studies the following
conclusions are drawn.
A. The following causes are identified as a potential delay causes on the projects
1. Mistakes and discrepancies in design documents, frequent design change and variation
order during construction, unclear and inadequate details in drawings, slow response and
inspection, poor contract management, inaccurate site investigation and change in
material type during construction as consultants’ responsibility;
2. Delay in material delivery, inefficient planning and scheduling, late procurement of
materials, low labor productivity, inappropriate cost estimation and improper
construction method as contractor’s responsibility;
3. Finance arrangement and inadequate fund allocation, change and variation order during
construction, delays to effect progress payment, unrealistic project duration and slow
decision making as client’s responsibility
4. Shortage of construction materials and rise in material prices as external causes.
5. Unanticipated Government regulation change in exchange rate devaluation
6. Consultant’s inability and failure to manage the contract as per the conditions and
standards of the specification.
7. Findings of the case study witnessed none of the projects completed within the contract
period. The total delay ranges from 200% to 329% of the initial contract times excluding
the time required to complete the projects.
8. The AAU hired CDSCo for many of its projects to provide consultancy and supervision
services. In fact CDSCo is a well experienced leading grade 1 consultancy firm in the
country. But the quality of the service they are providing as well as the frequency and
level of mistakes they are doing is apparent to their experience, particularly in design,
document preparation and level of accuracy and contract management of educational
building projects.
B. Time overrun, cost overrun, Inferior quality deliverables, loss of unutilized (idle) resources
and tying down of client’s capital, abandonment and contract termination are the effects of
the delay encountered so far.
C. Besides all, other non-quantifiable delay damages that cannot be stated in terms of money
such as inferior quality end product, inability to provide service and/or loss of client
opportunities.
6.2. Recommendations
These delays are badly affecting the construction of the Addis Ababa University educational
building projects and it is needed to find a solution for countering the delays. The solution to avoid
and/or to counter delays is to avoid and lessen the causes related with delays, and in result there
will be lesser effects of delays on the educational building projects.
It is suggested to deal with the causes and find a solution so that these causes not happen or happen
very less. Based on the findings of the research, the following recommendations were proposed.
To avoid time and cost overruns, Contractors should setup sufficient storage area or prepare
procurement plan to properly utilize advance payments and secure required construction
materials especially that are scarce in the local markets.
Contractors should give due attention for time value of money.
Contractors should carefully estimate the costs during pricing and proper working
methodology to be adopted.
The client should determine the required duration of project and impose realistic duration
to avoid time and cost overruns.
Clients must have strong economical ability and financial arrangement for project, effect
progress payments on time
Client must give proper time and priority on its construction project and tacking
appropriately time verdict.
The Client should minimize change orders and make timely decisions as much as possible
to avoid cost and time overruns.
The communication and coordination between the stake holders also have to be improved.
The Client should exercise to work with various consultancy firms, this will provide them
competitive consultancy fee, adequate consultancy service and better achievement.
The government should consider a cost compensation at least for ongoing projects.
Regulatory bodies require to set measures against to non-performance, delay damages and
default of consultants.
Regulatory changes to be discussed among all concerned stakeholders prior to
implementation.
References
14. Harry Kent: Policy Statement for Calculating Delays and Damages in the city of Mesa,
Arizona Dec.6,1995, wwwcityofmesa.org
15. Iulian Trofin: Impact of Uncertainty on Construction Project Performance using Linear
Scheduling- A Master’s Thesis submitted to University of Florida, 2004
16. Jackson, M.J: Productivity engineering and management, productivity measurement,
evaluation, planning, and improvement in manufacturing and service organization, 1995
17. Junaid Ahcom: A Model for Benchmarking Contractors Project Management elements in
Saudi Arabia, MSc Thesis, 2004
18. KK Chitkara: Construction Project Management (Planning, Scheduling & Controlling),
2003
19. Kumaru Yogeswaran, Mohan M.Kumaraswamy, and Douglas R.A.Miller: Claims for
Extensions of Time in Civil Engineering Projects – Construction Management &
Economics, 16, 283-293, 1997
20. Last & Faoro: Calculating Delay claims- An overview of the Components, 2000
21. Mattila G.K. and Abraham M.D.: Linear Scheduling- Past research efforts and future
directions, Engineering Construction & Architectural Management, 5, 294 – 302, 1998
22. M. E. Abd El-Razek, H. A. Bassioni and A. M. Mobarak, Causes of Delay in Building
Construction Projects in Egypt. Journal of Construction Engineering and Management, 10,
pages 831-841, 2008
23. M. Haseeb, Xinhai Lu, Aneesa Bibi, Wahab Rabbani, Problems of Projects and Effects
of delays in the Construction Industry of Pakistan, Australian Journal of Businees and
Management Research, Vol. 1, No 5, pages 41-50, September 2011
24. M. Haseeb, Xinhai Lu, Aneesa Bibi, Maloof-ud-Dyian and Wahab Rabbani, Cause and
Effects of delays in Large Construction Projects of Pakistan, Kuwait Chapter of Arabian
Journal of Business and Management review, Vol. 1, No 4, pages 18-42, December 2011
25. Mengesha Wubishet Jekale. (2004). Performance for Public Construction Projects in
Developing Countries: Federal road and Educational Building Projects in Ethiopia
Norwegian University of Science and Technology: Doctoral Thesis 2004; 45-47
26. Murali Sambasivan and Yau Wen Soon: “Causes & Effects of Delays in Malaysian
Construction Industry.” International Journal of Project Management, volume 25, issue 5,
July 2007, pages 517-526
27. N. Hamzah et al., (2011). Factors Contribute to Delay Project Construction in Higher
Learning Education Case Study, Research journal of Engineering and Technology. 5(11).
3112-3116
28. N.R.Mansfield, O.O.Ugwu and T.Doran: “Causes of Delay and Cost overruns in Nigerian
Construction Projects.” International Journal of Project Management vol12 issue 4 (1994),
pages.254-260
29. Neal Morris, Pinsent Masons: “Dealing with Delay.” Press article, Feb.2007
30. Rizwan U.Farooqui, Syed M.Ahmed, and Muhammad Saqib: “ Delays in Construction
– An Empirical study of Contractors’ perceptions in Pakistan Construction industry” paper
31, page 256-270 July 11-13, 2007
31. Robel Assefa (2015), Schedule Delay Identification and Assessment On Addis Ababa’s
Light Rail Transit Construction, Addis Ababa institute of Technology Master of Science
Thesis
32. Sidney M.Levy (2002), Project management in construction, fourth edition, K K
Chitkara, (2003). Construction Project Management. Planning, Scheduling and Monitoring
33. Stephen O ogunlana, Krit Promkuntong and Vithool Jearkjirm: “Construction Delays
in a Fast-Growing Economy: Comparing Thailand with other economies.” International
Journal of Project Management, volume 14, issue 1, Feb. 1996, pages 37-45
34. Syed M.Ahmed, Salman Azhar and Mr. Mauricio Castillo & Ms.Pragnya
Kappagatula: Construction Delays in Florida: An Empirical Study, 2005
35. Toufic M.Mezher and Wissam Tawil: “Causes of Delays in the Construction Industry of
Lebanon.” Engineering Construction and Architectural Management Journal volume 5,
issue 3, 1998, pages 251-260
36. Trauner, T. J., W. A. Manginelli, J. S. Lowe, M. F. Nagata and B. J. Furniss (2009)
Construction Delays: Understanding Them Clearly, Analyzing Them Correctly, Elsevier
Inc USA.
APPENDIXES
Appendix A
Research Proposal
1. ABSTRACT
Delay in construction project completion is a global phenomenon that occurs in the construction
industry and considered as one of the most common problems causing a multitude of negative
effects on the project and its participating parties especially where the government projects are
concerned.
Construction projects are characterized by advanced technologies, multiparty participation, and
frequent owner-desired changes. Coupled with uncertainties and complexities in the physical,
financial, and economic environment in which most projects are performed. Such conditions have
made completing projects on schedule and on budget a difficult task to accomplish, often leading
to claims on cost compensations and time extensions.
The construction activities in Ethiopia are increasing, most of public projects are facing problems
related to delays in completion time, requiring higher budget than estimated, the final deliverables
become inferior in quality, detrimental variations and reworks and dissatisfaction by other party
lead to disputes.
Therefore, it is found important to assess the critical cause and effects of delay on projects’
successful completion and healthy relationship among the stakeholders.
The research work will address the following research questions
1. What are the real causes of project delays in the Higher Educational Building Construction
Projects?
2. How do construction project delay related to the project’s successful completion?
3. What is the stakeholders’ response for the effect of construction delays over successful
completion?
4. How does construction delays influence projects’ performance criteria and successful
completion?
So, this thesis will examine delay factors in an integrated manner and to determine how critical
delay causes are most influential in project performance. This will provide owners, Consultants and
construction organizations involved in construction projects with the foundation on which such
strategies – on how to avoid delays - can be developed in the future.
This thesis focuses on Higher Educational Building Construction Projects in Addis Ababa, which
were assessed for delay causes and examines the corresponding effects identified and provide
recommendation based on the findings to improve project performance within the higher education
building projects as well as the general public construction projects.
Key words: Educational building construction projects, Construction Delays, Causes of Delay,
Effects of delay, Addis Ababa University
2. BACKGROUND
Construction delay defined as the time over run either beyond completion date specified in a
contract or beyond the date that parties agree upon for delivery of a project [1]. Delay in
construction involves during different stages of the construction process (Pre-Construction and
Construction phases). It can be caused by different parties in a contract and also be internal or
external. N. Hamzah et al., (2011) under his study on Factors Contributing to delay Project
Construction in Higher Learning Education, identified 22 factors of delay and out of which seven
of them categorized as critical factors for delay in his study.
Critical causes of delays classified:
Insufficient capital
Late progress payment
Delay in work approval and Slow decision making
Contractor’s management failure
Scarce construction materials
Design change, New instruction and additional works
3. PROBLEM STATEMENT
Delays in a construction project is counted as a common problem and became a cause for projects
to be completed with huge cost overrun (requiring higher budget than estimated), extended
completion time, the final deliverables are inferior in quality and contract termination.
In the recent time it was an accepted to have delays in construction projects completion time. For
the client, construction delay is a loss of revenue, lack of productivity, dependency on existing
facilities, etc. For the contractor, construction delay is the higher costs, longer work duration,
increased labor cost, higher material and equipment costs etc. Completion of construction projects
on specified time or time agreed by the parties indicates their efficiency. The delays in construction
projects happen because of various factors or causes. These causes lead to the delay in construction
completion, and this delay leads to negative effects on the construction project.
In Ethiopian construction projects, it is very rare that construction projects are completed on the
time specified or agreed upon. There are many higher educational building construction projects in
Addis Ababa, which suffered delay or in some cases suffered suspension or abandonment.
4. RESEARCH QUESTION
On the basis of the above stated facts, the following would be the research questions.
1. What are the real causes of project delays in the Higher Educational Building Construction
Projects?
2. How do construction project delay related to the project’s successful completion?
3. What is the stakeholders’ response for the effect of construction delays over successful
completion?
4. How does construction delays influence projects’ performance criteria and successful
completion?
5. RESEARCH OBJECTIVE
5.1. General objectives
The general objective of this study is to assess the major causes of delays on building projects in
the Ethiopian Construction Industry and its influence on the successful completion of the project.
The primary objective is to identify the principal factors responsible for delays in the Addis Ababa
Higher Educational Building Projects, their effect on the progress as well as timely delivery.
6. LITERATURE REVIEW
6.1 Contract
Contract is a written agreement between or among two or more parties whereby each party promises
to do or not to do something and agrees to terms (conditions and Warranties) set out in the contract.
Conditions of Contract are terms in which parties in the contract are governed / administered with.
That is, it is an administrative law which is the legally binding part of the contract. These promises
and terms shall be enforceable by law and incorporates the rights, obligations and Remedial rights
of each contracting parties.
6.2 Project Planning and Scheduling
Project scheduling is a written or graphical representation of the Contractor’s plan for completing
a construction project that emphasizes the elements of time and sequence. However, construction
planning is a fundamental and challenging activity in the management and execution of construction
projects. Construction planning involves the choice of technology, the definition of work tasks, the
estimation of the required resources and durations for individual tasks, and the identification of any
inter-relationship among the different work tasks [1]
Construction project planning is a method of determining “What” is going to be done, “How” things
are going to be done, “Who” will be doing activities and “How Much” activities will cost. In this
sense planning does not cover scheduling, which addresses the “When” to do, but once planning is
completed scheduling can be done.
7. RESEARCH METHODOLOGY
7.1 Study design
The methodology considered and adopted for this research work focus on literature review
and, structured questionnaire survey was designed and employed to assess the knowledge
and practice on the cause and effects of delays in the construction projects. It also uses a
mixed research method (both quantitative and qualitative methods) in the data collection
process. The quantifiable responses will be analyzed through a quantitative method as the
name implies. The qualitative data gives more emphasis to the non-quantifiable responses
and it is chosen due to its flexible nature. In recent time, the responses gathered through
questionnaires are becoming less reliable as the respondents did not give due attention to
the outcomes, it is essential to strengthen through interviews and face to face discussions.
Therefore, the qualitative method used to support the quantitative data that was collected in
the research. Finally, based on the obtained data and results of the analysis, conclusions and
recommendations are provided.
The participant should have experience in contract management at any public building
construction project
Finally, this research will contribute in the field of construction management. It will add more
information on the most frequent and critical causes of delay and to tackle the problems as early as
possible.
9. Time Table
Activities Time in Days Day No.
Planning and Proposal writing 5 1-5
Getting approval 2 7
Literature Review Always 1-40
Preparation of questionnaires and distribution 5-15 20
Data collection 7-10 31
Data Analysis 5 36
Writing the first draft of the report 5 40
Writing the final draft of the research document and
submission 7 45
10. Budget
Items/Activities Amount in Birr
Advisor consultation 10,000
Secretarial Work 3,000
Stationeries, photocopy and duplication 1,500
Expense for Participants 2,000
Telephone Expense 1,500
Internet Expense 500
Transportation 1,500
Other expenses 500
Total 20,500
REFERENCE
Appendix B
Questionnaire Survey
Questionnaire
To the respondents,
This survey is part of academic research that aim to assess the major causes of delays on building
projects in the Ethiopian Construction Industry and its influence on the successful completion of
the project. The primary objective is to identify the principal factors responsible for delays in the
Addis Ababa Higher Educational Building Projects, their effect on the progress as well as timely
delivery.
With this survey, I would like to investigate the critical delay factors that currently exist in the
construction of higher educational building projects in order to improve the building construction
delivery process. In the long term, this research could help the contracting parties to complete
projects on time, within budget and highest quality. All the information you provide will kept in
strict confidentiality and it will be only used for academic research. Please answer each questions
carefully. There is no right or wrong answer. If you are unsure of an answer, please respond with
your best estimate. I value your participation and thank you for the commitment of time, energy
and effort. If you have any further questions, I can be reached at the address below.
Sincerely,
Shewaferahu Tilahun
Post Graduate Candidate, Construction Technology and Management
School of Civil and Environmental Engineering
Addis Ababa Institute of Technology (AAiT)
Addis Ababa University
Tel.: +251 911 219 129
Email: [email protected]
1) Name: (Optional)
2) Company Name
3) Email:
Consultant
Contractor
Others
8) Project Size
Delay Causes 1 2 3 4 5
Inadequate experience of Consultant
Poor Communication and coordination
Mistakes and discrepancies in design
documents
Consultant Related Poor contract management
Frequent chang and varaion orders
Inaccurate site investigation
Unclear and inadequate details in drawings
Slow response and inspection
Shortage of construction materials
Delay in material delivery
Change in material type during construction
Material Related Late procurement of materials
Rise in material prices
Quality of material
Inadequate material
Shortage of equipment
Equipment breakdown
Low level of operator's skill
Equipment Related
Low productivity and efficiency of
equipment
Shortage of equipment parts
Shortage of labors
Personal conflict among labors
Low labor productivity
Labor Related
Non attendance
Labor injuries
Labor strikes
Delay in obtaining permit
Rise in price of materials
Weather Condition
Natural Disasters
External Factors Regulatory changes
Unforeseen site conditions
Delay in providing services from utilities
(such as water, electricity, etc)
Government Policies
If you have comments regarding the causes of delay and/or their importance, please specify here:
Please rank effects of delay below in what you consider to be the most influential effect of delay.
The five point scale ranged from 1 to 5.
1= Strongly Disagree
2= Disagree
3= Slightly Disagree
4= Agree
5= Strongly Agree
Importance and Ranking of Delay
3.1) Effects
1 2 3 4 5
Sl. Str.
Effects S. Disagree Disagree Disagree Agree Agree
Time Overrun
Cost Overrun
Wastage and underutilization
of manpower and resources
Tying down of Client's capital
due to non-completion of the
project
Abandonment of building
project
Dispute between parties
involved
Reduced profit or total loss
Arbitration
Litigation and court case
3.2) If you have comments regarding delay effects, please specify here:
3.3) What is your general comment regarding causes of delays and their effect on the building
construction project: