100% found this document useful (1 vote)
807 views1 page

Inventory List of Scaffoldings PDF

This document is an inventory list of scaffolding materials for the Hallare Building construction project. It contains 7 items, including G.I pipes of various lengths, clamps, basejacks, catwalks, and stair ladders. The quantities rented, in use, and not in use are reported for each item. The inventory was prepared by Edrick John Abad, a security guard, and noted by the project architect Dorothy P. Castro.

Uploaded by

Doroty Castro
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
807 views1 page

Inventory List of Scaffoldings PDF

This document is an inventory list of scaffolding materials for the Hallare Building construction project. It contains 7 items, including G.I pipes of various lengths, clamps, basejacks, catwalks, and stair ladders. The quantities rented, in use, and not in use are reported for each item. The inventory was prepared by Edrick John Abad, a security guard, and noted by the project architect Dorothy P. Castro.

Uploaded by

Doroty Castro
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Date: July 21,2020

Project: Hallare Building ( 6-Storey with Roof Deck)


Owner: c/o Francis del Hallare III
Location: 10 East Capitol Drive Kapitolyo Pasig City
Subject: Inventory of Materials

INVENTORY LIST OF SCAFFOLDINGS


NO. RENTED QTY
NO. PARTICULARS
QTY UNIT NOT IN USE IN USE
1 G.I Pipe 1 1/2"x 6m 460 pcs 460 0
2 G.I Pipe 1 1/2"x 3m 80 pcs 80 0
3 G.I Pipe 1 1/2"x 2m 300 pcs 300 0
4 Swivel Clamp 1 1/2" x 1 1/2" 800 pcs 800 0
5 Fixed Clamp 1 1/2" x 1 1/2" 1250 pcs 1189 61
6 Adjustable Basejack 1 1/4" x 600 mm 44 pcs 44 0
7 Catwalk 50 x 180 cm 100 pcs 100 0
8 Stair Ladder 50 x 180 cm 13 pcs 13 0

Prepared by : Noted by:

Edrick John Abad Archt. Dorothy P. Castro,uap


Secuirty Guard Project Architect