A) A Distribution Panel With 2000A TP ACB Incomer With Ammeter and Selector Switch

This document outlines the electrical equipment requirements for a new power distribution system including: 1) A 2000A floor standing breaker panel with AC circuit breaker to connect to an existing powerhouse distributor. 2) A 2000A distribution panel with MCCB feeders for various equipment loads totaling over 1000kW and provision for a future 350kW panel. 3) Power cables ranging from 165m of 1300A cable to supply the panel to 100m of 60mm2 cable for distribution, along with lugs and accessories. 4) Three lighting switchboards with circuit breakers and sockets for lighting loads.

Uploaded by

Aayush Agrawal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
216 views5 pages

A) A Distribution Panel With 2000A TP ACB Incomer With Ammeter and Selector Switch

This document outlines the electrical equipment requirements for a new power distribution system including: 1) A 2000A floor standing breaker panel with AC circuit breaker to connect to an existing powerhouse distributor. 2) A 2000A distribution panel with MCCB feeders for various equipment loads totaling over 1000kW and provision for a future 350kW panel. 3) Power cables ranging from 165m of 1300A cable to supply the panel to 100m of 60mm2 cable for distribution, along with lugs and accessories. 4) Three lighting switchboards with circuit breakers and sockets for lighting loads.

Uploaded by

Aayush Agrawal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 5

1) Floor standing out going breaker panel with (400V) 2000 A TP ;ACB,(reputed make

like ABB, Siemens etc) 55 KA C/W Shunt trip, Under voltage trip and closing
mechanism ,EFR, CTs, & indicating lamps.
1 No.
The above has to be joined with our existing powerhouse distributor thro’ anodized
copper bus, Dimension shall be provided Schematic sketch attached

2)
a) A distribution panel with 2000A TP ACB incomer with ammeter and selector switch,
CTs, shorting terminal, Voltmeter and selector switch, indicating lamps, control
fuses, neutral link and all safeties.

b) 7 Nos outgoing feeders as under


 630/600 A MCCB ( this is for an air compressor of 220 kw with soft start arrangement. Starting ampere shall be in the region of 1000A) --- 1 no.
 600 A MCCB (this for an equipment with major load being heating lamps
with installed capacity of 280 KW but running load at 100 kw-----------------1 no
 300 A MCCB (this is for 140 kw chilled water refrigeration system --------1 no
 160 A MCCB ( Cooling and conveyor system) --------2 nos.
 120 A MCCB (HVAC) ------- 1 no
 63 A MCCB (lighting) ------- 1no.
The panel shall be modular and have “bus bars” designed to accommodate a future distribution panel of total power 350kw (sketch enclosed)

3) Power distribution XLPE 4 core copper cables as below.


 Suitable cables to carry 1300 A to be laid below ground ------165 meters
 Cable lugs for above both ends
 Cable sleeve and cable glands
 500 sq mm cable (4 core) --------50 mts
 300 sq mm cable (4 core) ------------ 60 mtrs
 150 sqmm/120 sq mm 4 core -------------60 mts
 60 sq,mm -------------100 mts
 25 sq mm ------------50 mts
All the above cables need to have copper lugs, glands and sleeves ; quote needed

4) Lighting switch board consisting of


 63 A TP incomer-1 no, 40A DP- 3 nos, 25A DP -6 nos., -------------1 set
 40A DP main MCB -1 no, 5 A sp MCB-11 nos., 15 A socket with MCB-1 no ----------- 1 set
 25D P main MCB-1no., 5 A SP mcb-3 nos., 15 A sp socket with MCB ------------1set.,
e x i s t i n g
p a n e l
2000 A